1 Current State of the Renewable Energy in Kyushu Electric Power and Our Future Plan. Kyushu Electric Power Co. Inc. June 8, 2017
2 Now in Kyushu Balance of demand and supply on January 1, 2017 (MW) 10,000 8,000 Pumped storage generation Pumped storage energy Demand Renewable energy: 64% (Photovoltaic power: 57%) (MW) 8,000 Demand 6,940 MW 1 6,000 6,000 Thermal Nuclear Thermal 4,000 2,000 Photovoltaic 4,000 2,000 Photovoltaic 3,930MW Renewable energy 4,420MW 0 Hydraulic, geothermal, wind, and biomass Nuclear 0 (Time) Hydraulic, geothermal. etc. 490MW Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 1
3 Contents 2 1 Current Status of Renewable Energy in Kyushu 2 Current Issues and Responses 3 Verification Tests for the Future 4 Summary Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 2
4 3 1 Current Status of Renewable Energy in Kyushu Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 3
5 Location of Kyushu in Asia 4 Major Cities in Asia and Kyushu Vladivostok Nakhodka Beijing Qingdao Nanjing Hangzhou Dalian Incheon Busan Seoul Kyushu Shanghai Japan Nagoya Osaka Tokyo Guangzhou Taipei Hog Kong Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 4
6 Many Good Places for Renewable Energy in Kyushu 5 Good solar radiation : Photovoltaic Good wind conditions : Wind Many volcanos : Geothermal Many forests, Livestock industry is thriving :Biomass Mountainous : Hydraulic and pumped-storage Comparatively low land price Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 5
7 Explosive Increase of Photovoltaic Power after FIT 6 (MW) 10,000 1,000 FIT implemented (July 2012) + Contracted 11,000MW 8, , , ,160 6, , , ,110 2, FIT Tariff (10 kw min. Exc, tax) 40 yen 36 yen 32 yen 27 yen* 24 yen (Year) *: 29 yen from April to June yen since July 2015 Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 6
8 Wind Power Increasing Steadily 7 (MW) 800 FIT implemented (July 2012) + Contracted 620MW FIT Tariff (20 kw min. Exc. tax) 22 yen 22 yen 22 yen 22 yen 22 yen (Year) Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 7
9 Connected PV Power Twice as Large as Economic Scale 8 Percentage of national total 11% Kyushu Accounts for 10% of Japan's Economy Approximately twice 10% 9% 19% Area Population Sold Power PV Power Connected Source : Created based on "Preliminary Report of Total Electric Power Demand in 2015" of the Agency for Natural Resources and Energy, Feed-in Tariff information from the official website, and "Illustrated Kyushu Economy 2017" of Kyushu Economic Research Center Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 8
10 9 2 Current Issues and Responses Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 9
11 Issues about the Quantity and Quality of Electricity 10 Quantity Quality Main Issue Surplus power Thermal capacity Frequency System voltage Current Response Suppressing thermal power and using pumped storage power Using large-capacity storage batteries Controlling renewable energy output (Remote islands) Reinforcing transmission and transformation equipment Installing storage batteries for renewable energies (Remote islands) Installing additional voltage regulators Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 10
12 11 Balancing Power Consumption and Power Output [Balanced] [Balance lost] Pedaling force = Load (Supply) (Demand) Pedaling force << Load (Supply) (Demand) Pedaling force = Power output (Supply) Rotation speed down Fall = Outage Wheel rotation speed = Frequency Pedaling force >> Load (Supply) (Demand) Rotation speed Rotation speed up Load = Consumption (Demand) Fall = Outage Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 11
13 Balancing by Pumped Storage Instead of Thermal Output o Percentage of renewable energy (kw) on May 4, 2016:78% max (PV power:62%) o Percentage of renewable energy (kwh):38% (MW) [Demand-supply balance on May 4, 2016] 12,000 10,000 Result in 2015:17% Best mix in 2030:22 to 24% Surplus power absorbed by pumped storage energy 12 8,000 6,000 4,000 Demand Thermal Photovoltaic Pumped storage generation 2,000 0 Hydraulic, geothermal, wind, and biomass Nuclear (Time) Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 12
14 (Ref.) Pumped Storage Power Plant as Storage Battery 13 Discharge (70%) Electric energy Electric energy Potential energy of water Upper reservoir (Upper regulating reservoir) Water intake Pumping up (Charge) Charge (100%) Power generation (Discharge) Underground power plant Pump turbine Lower reservoir (Lower regulating reservoir) Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 13
15 (Ref.) Pumped Storage Power Plants in Kyushu 14 Tenzan : 600 MW (300 MW 2 units) Ohira : 500 MW (250 MW 2 units) Omarugawa : 1,200 MW (300 MW 4 units) Total : 2,300 MW Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 14
16 Order of Measures against Surplus Power Output 15 Output suppression order 1 Suppress thermal power output and use pumped storage power 2 Supply to areas outside Kyushu 3 Suppress biomass power 4 Control PV and wind power output 5 Wheel power outside Kyushu according to a broadarea organization 6 Suppress of hydraulic and geothermal output Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 15
17 (Ref.) Output Already Controlled on Remote islands Example of Tanegashima, Kagoshima Pref. (January 3, 2017) (kw) 20,000 15,000 10,000 Output control 980 kw Demand Renewable energy 8,120 kw Minimum combustion power output 16 5,000 0 Combustion power Photovoltaic power output Wind power output (Time) Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 16
18 Great Discrepancy between Predicted and Actual PV Output 17 (MW) 4, , Down 1,700MW (MW) 4, , Up 2,200MW 3, , Prediction 予測 3, , , , Result 1, , Prediction 予測 1, Result 1, (Time) Forecast; Slightly cloudy Rain in some areas (Time) Forecast: Cloudy and rain Fair in some areas Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 17
19 Great Fluctuation of PV Output 18 (MW) 5, Up/down 1,500MW (MW) 5, Quickly down 1,900MW 4, , , , Result 2, , Result Prediction 2, , Prediction 1.5 hours (Time) (Time) Clear, occasionally cloudy Sudden unpredictable worsening of weather Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 18
20 Line Voltage Increase after Volume Renewable Energies 100/200V 100/200V 19 Substation 6,600V Voltage regulator Ordinary power PV power Deviation PV power 107V 95V Proper voltage range (101±6V) After PV power connection After measures Before PV connection Distance from substation Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 19
21 Thermal Capacity Shortage after Volume Renewable Energies 20 Renewable energy electricity flow Renewable energy Reinforcement necessary Power plant Substation Customer Ordinary electricity flow Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 20
22 Wide Power System Reinforcement Needed in Kyushu 21 Regions under System limitation Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 21
23 Unstable Frequency after Volume Renewable Energies Iki Island, Nagasaki Pref. (kw) 1,500 Wind power output 22 1, Wind power output up quickly 1Wind power output down quickly 0 (Hz) 0:19 0:20 Frequency 0:21 0: Frequency up Frequency up 2Frequency down (Internal combustion engine output up) :19 0:20 0:21 0:22 (Time) Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 22
24 23 3 Verification Tests for the Future Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 23
25 Verification Tests for the Future 24 Main Issue Effort Quantity Surplus power Improvement of PV power output prediction accuracy Verification test on large-capacity storage battery Verification test for PV power output control ( VPP verification test) Quality Thermal capacity Frequency Storage battery verification test on remote islands - ( EV reuse storage battery verification test) System voltage Verification test to maintain proper line voltage *( ) : Cooperation to other business operators for their verification tests Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 24
26 Verification Tests for the Future 25 Main Issue Effort Quantity Surplus power Improvement of PV power output prediction accuracy Verification test on large-capacity storage battery Verification test for PV power output control ( VPP verification test) Quality Thermal capacity Frequency Storage battery verification test on remote islands - ( EV reuse storage battery verification test) System voltage Verification test to maintain proper line voltage *( ) : Cooperation to other business operators for their verification tests Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 25
27 Improvement of PV Output Prediction Accuracy [Current] 1Meteorological data and images 2Solar radiation prediction (Each prefecture) 3Output prediction (Each prefecture) 26 Generated amount Past result [Accuracy improvement] 1Meteorological data and images 2Solar radiation prediction (Each point) Solar radiation 3Output prediction (Each point) + Past solar radiation (the same month) + Past (most recent) meteorological change Solar radiation Generated amount Past result Corrected Recent result Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 26
28 Verification Tests for the Future 27 Main Issue Effort Quantity Surplus power Improvement of PV power output prediction accuracy Verification test on large-capacity storage battery Verification test for PV power output control ( VPP verification test) Quality Thermal capacity Frequency Storage battery verification test on remote islands - ( EV reuse storage battery verification test) System voltage Verification test to maintain proper line voltage *( ) : Cooperation to other business operators for their verification tests Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 27
29 Effects of Storage Battery 28 Renewable Energy Output Large Storage Battery Charge Small Discharge 1 Absorbing surplus power 2 Suppressing frequency fluctuation Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 28
30 Demand-supply Balancing by Using Storage Batteries 29 [Storage batteries at Buzen Power Plant] Subsidized by the Ministry of Economy, Trade and Industry Bank No. 2 (started operation on March 3, 2016) PCS storage package Bank No. 1 (started operation on February 10, 2016) 140 m NAS battery subunit (800 kw 63 units) 6kV Reception and transformation equipment 66/6kV interconnection transformer (30,000kVA 2 units) 100 m NAS battery container: 252 total Output:200 kw/unit Total:50,400 kw Capacity:50,000 kw(300,000 kwh) World's largest class Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 29
31 Verification Tests for the Future 30 Main Issue Effort Quantity Surplus power Improvement of PV power output prediction accuracy Verification test on large-capacity storage battery Verification test for PV power output control ( VPP verification test) Quality Thermal capacity Frequency Storage battery verification test on remote islands - ( EV reuse storage battery verification test) System voltage Verification test to maintain proper line voltage *( ) : Cooperation to other business operators for their verification tests Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 30
32 Meticulous PV Power Output Control [Remote operation] Control by percentage of rated output 31 [Kyushu Electric] [PV power plant] Leased line PCS Auto control Extra-high voltage High & low voltages Internet PCS Auto control Output control schedule Get schedule Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 31
33 Verification Tests for the Future 32 Main Issue Effort Quantity Surplus power Improvement of PV power output prediction accuracy Verification test on large-capacity storage battery Verification test for PV power output control ( VPP verification test) Quality Thermal capacity Frequency Storage battery verification test on remote islands - ( EV reuse storage battery verification test) System voltage Verification test to maintain proper line voltage *( ) : Cooperation to other business operators for their verification tests Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 32
34 (Ref.) Cooperation for VPP Verification Test [Kyushu Electric] Output control schedule 1Output control schedule Internet [Aggregator] 33 Get schedule Iki Island, Nagasaki Pref. Present 3Output reduction 2Charge control [Photovoltaic power plant] Subsidized by the Ministry of Economy, Trade and Industry Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 33
35 Verification Tests for the Future 34 Main Issue Effort Quantity Surplus power Improvement of PV power output prediction accuracy Verification test on large-capacity storage battery Verification test for PV power output control ( VPP verification test) Quality Thermal capacity Frequency Storage battery verification test on remote islands - ( EV reuse storage battery verification test) System voltage Verification test to maintain proper line voltage *( ) : Cooperation to other business operators for their verification tests Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 34
36 Stabilize Frequency by Using Storage Batteries on Islands [Verification facilities (Storage batteries)] Iki (4 MW) Tsushima (3.5 MW) Lithium-ion batteries Amamioshima (2 MW) [Result of test on the Iki Island, Nagasaki Pref.] Storage battery control Tanegashima (3 MW) * Subsidized by the Ministry of Economy, Trade and Industry and the Ministry of Environment (Hz) Hz :30 16:37 16:45 16: Hz (Time) Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 35
37 Verification Tests for the Future 36 Main Issue Effort Quantity Surplus power Improvement of PV power output prediction accuracy Verification test on large-capacity storage battery Verification test for PV power output control ( VPP verification test) Quality Thermal capacity Frequency Storage battery verification test on remote islands - ( EV reuse storage battery verification test) System voltage Verification test to maintain proper line voltage *( ) : Cooperation to other business operators for their verification tests Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 36
38 (Ref.) Cooperation for EV Reuse Storage Battery Test 37 Koshikijima, Kagoshima Pref. (Satsumasendai City) EV reuse storage battery(24 kwh 36 units) [Combustion power plant] 2 Easing the output fluctuation of renewable energy by using battery 1 Transmitting renewable energy output Output Output [PV power plant] [Wind power plant] * Subsidized by the Ministry of Economy, Trade and Industry Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 37
39 Verification Tests for the Future 38 Main Issue Effort Quantity Surplus power Improvement of PV power output prediction accuracy Verification test on large-capacity storage battery Verification test for PV power output control ( VPP verification test) Quality Thermal capacity Frequency Storage battery verification test on remote islands - ( EV reuse storage battery verification test) System voltage Verification test to maintain proper line voltage *( ) : Cooperation to other business operators for their verification tests Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 38
40 Maintenance of Proper Voltage in Local Grids [Substation] 6,600V PV1 PV2 PV3 PV4 39 (V) [Verification facilities] PV power Storage battery Simulation facilities, etc [Example of test result] 1 2 Proper voltage range (101±6V) Satsumasendai City Approximately 280kW 118kW (130kWh) Simulated power distribution line, etc. Voltage regulator Distance from substation Optimum arrangement Before measures After measures Voltage regulator Photovoltaic power Simulation facilities Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 39 3
41 40 4 Summary Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 40
42 Summary 41 o Because of regional characteristics, renewable energy is expected to be introduced and expanded more in Kyushu. o As the pioneer of high penetration of renewable energies, Kyushu Electric will proactively work on issues for stable power supply. Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 41
43 42 Thank you for your attention Kyushu Electric Power Co., Inc. Copyright(C) 2017 Kyushu Electric Power CO., Inc. All Rights Reserved. 42
Demonstration Project utilizing Hybrid Storage Battery System in the Oki-islands
Demonstration Project utilizing Hybrid Storage Battery System in the Oki-islands Subsidized project of Ministry of the Environment June 16, 2016 Power System Division The Chugoku Electric Power Co., Inc.
More informationTechnology from the New Product SANUPS K for a Smart Grid Society
Features: Technology Contributing to Effective Use of Power Technology from the New Product SANUPS K for a Smart Grid Society Yoshiaki Okui 1. Introduction After the Tohoku Earthquake, there is a movement
More informationModelling Analysis for Optimal Integration of Solar PV in National Power Grid of Japan
USAEE/IAEE 36th North American Conference, Concurrent Session 28, Hilton Crystal City, Washington DC USA, September 25, 2018 Modelling Analysis for imal Integration of Solar PV in National Power Grid of
More informationStrategy and Roadmap for PV Systems in Japan
APEC EGNRET44, Laoag, Philippines Strategy and Roadmap for PV Systems in Japan April 13-14th, 2015 Takao Ikeda The Institute of Energy Economics, Japan (IEEJ) Road Map for PV 2014 2020 2030 2050 Conversion
More informationOpportunities and Challenges for Smart Grid in Japan. March 8, Shuichi Ashidate
Opportunities and Challenges for Smart Grid in Japan March 8, 2016 Shuichi Ashidate Vice President of TEPCO Research Institute Tokyo Electric Power Co., Inc. TEPCO All Rights Reserved, March 8, 2016 Capacity
More informationRenewable Energy Policy in Japan
Renewable Energy Policy in Japan Kenji Kimura February 6, 2018 Researcher, New and Renewable Energy Group The Institute of Energy Economics, Japan IEEJ Feb. 2018 Table of Contents 1 Ⅰ. Status of Japan
More informationOptimum Operation Control of Distributed Energy Resources Using ENERGYMATE-Factory
FEATURED TOPIC Optimum Operation Control of Distributed Energy Resources Using ENERGYMATE-Factory Yusaku IJIRI*, Motonobu FUJIWARA, Terumi TAKEHARA, Hiroki SUMIDA and Akifumi SADATOSHI ----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
More informationToshiba s Smart Grid technologies and solutions for MV/LV grid
Toshiba s Smart Grid technologies and solutions for MV/LV grid Copyright 2012, Toshiba Corporation Dr. Katsutoshi Toda, Technology Executive Social Infrastructure Systems Company, Toshiba Corporation Threat
More informationJapanese Power Market Regulation Large Scale Battery Storage as a Solution for Challenges in Ancillary Services
Electricity 2017 Session WPM5.5 Eilat ISRAEL Nov. 8 th, 2017 Japanese Power Market Regulation Large Scale Battery Storage as a Solution for Challenges in Ancillary Services Koji Yamashita Central Research
More informationNEDO Case Studies of Project in New Mexico, US
NEDO Case Studies of Project in New Mexico, US March 8 th, 2016 Kazuyuki Takada Smart Community Department NEDO, Japan 1. Project in New Mexico Whole picture of Project in New Mexico Efforts in Los Alamos
More informationNAS batteries for Technical Challenges with Renewable Energy
NAS batteries for Technical Challenges with Renewable Energy November, 2018 NGK INSULATORS, LTD. NAS is the trademark of NGK INSULATORS,LTD., registered in the U.S. 2018 NGK Insulators, Ltd. All rights
More informationKazuyuki Takada Representative NEDO Representative office in Washington DC
Smart Grid Related Activity in NEDO Smart Grid Advisory Meeting October 2009 Kazuyuki Takada Representative NEDO Representative office in Washington DC What is NEDO As Japan's public management organization
More informationMicro-Grid and Battery Energy Storage Technologies for Large Scale Renewable Energy Integration
Micro-Grid and Battery Energy Storage Technologies for Large Scale Renewable Energy Integration Int l Seminar on Energy Storage Options for Renewable Energy Integration at India Habitat Centre, New Delhi,
More informationEnergy Storage at PG&E
Energy Storage at PG&E Hal LaFlash Director Emerging Clean Technologies April 5, 2011 Pacific Gas and Electric Company 2009 2010 Energy services to 15 MM people: 5.1 MM Electric customer accounts 4.3 MM
More information2016 Load & Capacity Data Report
Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness
More informationMicrogrid System for Isolated Islands
Microgrid System for Isolated Islands Takehiko Kojima Yoshifumi Fukuya ABSTRACT There are many inhabited isolated islands throughout the world and most of these operate with independent power s. Because
More information(1) Current State and Issues of the Electricity Sector in Indonesia
Japanese ODA Loan Ex-ante Evaluation 1. Name of the Project Country: The Republic of Indonesia Project: Java-Sumatra Interconnection Transmission Line Project (I) Loan Agreement: April 30, 2010 Loan Amount:
More informationConstruction and Practices of Strong & Smart Grid. State Grid Corporation of China 5-6 April 2011, Hongyu LIN, France
Construction and Practices of Strong & Smart Grid State Grid Corporation of China 5-6 April 2011, Hongyu LIN, France 1 CONTENTS PROFILE OF SGCC CONCEPTS PLANNING PRACTICES 2 1. PROFILE OF SGCC Service
More informationPolicy Strategy and Priority of New and Renewable Development in Japan
APEC EGNRET45, Xiamen, China Policy Strategy and Priority of New and Renewable Development in Japan November 16th, 2015 Takao Ikeda The Institute of Energy Economics, Japan (IEEJ) 1. Long term energy outlook
More informationADB Knowledge Partnership Week. Hirokazu Yamaguchi May, 2015
ADB Knowledge Partnership Week Hirokazu Yamaguchi May, 2015 TEPCO AT A GLANCE 1 THE 10 ELECTRIC POWER COMPANIES BY SERVICE AREA In Japan, 10 regional privately owned and managed General Electricity Utilities
More informationNEDO s Smart Grid Demonstration Projects in the U. S. JUMPSmartmaui Project in Hawaii
NEDO s Smart Grid Demonstration Projects in the U. S. JUMPSmartmaui Project in Hawaii 1 2 Maui of Hawaii Today High cost of energy is driven by variable oil prices. Hawaii ranks #1 in electric energy costs:
More information- Renewable Applications & NAS Battery
Sodium-Sulfur (NAS ) Battery - Renewable Applications & NAS Battery Central Asia Regional Economic Cooperation (CAREC) July 27, 2015 NAS, the NAS logo are trademarks of NGK INSULATORS,LTD., registered
More informationPV in Japan and Utility s activities
PV in Japan and Utility s activities PV &Utility Workshop, ASEAN POWER WEEK 2015 IEA PVPS Expert, Japan RTS Corporation, Tokyo kaizuka@rts-pv.com Contents Energy and PV status in Japan Utility companies
More informationsuccessful integration of distributed generation in rural areas
successful integration of distributed generation in rural areas Dr. Oliver Franz / Dr.-Ing. Torsten Hammerschmidt, RWE Deutschland AG, Regulatory Management / Grid Strategy RWE Deutschland 11.11.2013 SEITE
More informationDevelopment of Pumped Storage Power Station in China
Development of Pumped Storage Power Station in China QIAN Gangliang China Renewable Energy Engineering Institute Pumped storage power stations have become an important component for guaranteeing the secure,
More informationThe 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)
The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) February 2013 Contents I. Introduction 1 II. Status of Electricity Supply and Demand 2 1. Electricity Demand 2 2. Electricity
More informationBattery Energy Storage Systems for Maximizing Renewable Energy Introduction: Approaches and Cases in Japan
U.S.-Japan Renewable Energy Policy Business Roundtable December 11, 2013 Battery Energy Storage Systems for Maximizing Renewable Energy Introduction: Approaches and Cases in Japan Kikuo TAKAGI Technology
More informationEffects of Smart Grid Technology on the Bulk Power System
Effects of Smart Grid Technology on the Bulk Power System Rana Mukerji Senior Vice President Market Structures New York Independent System Operator Union College 2013 Environmental Science, Policy & Engineering
More informationConsumers Energy Net Metering
Consumers Energy Net Metering ELODY SAMUELSON September 20, 2016 Consumers Energy About Us Territory Overview 2 FOURTH-LARGEST COMBINATION UTILITY IN THE UNITED STATES Electric Utility 1.8 million electric
More informationConstruction of power supply system using electric vehicle for stable power delivery from PV generation
International Journal of Smart Grid and Clean Energy Construction of power supply system using electric vehicle for stable power delivery from PV generation Takahisa Kawagoe *, Kiyotaka Fuji, Atsushi Shiota,
More informationEnergy Storage Systems
Energy Storage Systems Global Energy Storage Market Overview & Regional Summary Report 2015 Toby Barber Dec 2015 Report Contributors: Australian Energy Storage Council, Energy Storage Association (US),
More informationIndia Smart Grid Week, 2017
India Smart Grid Week, 2017 N. Venu President and Head, Power Grids Division, South Asia, Middle East and Africa ABB 1 Big Shift in Power: Shaping the System of the Future Several global challenges Population
More informationSCHEDULE NO. ACG33 NET METERING SERVICE
Approved by Decision No.: 75408 Effective: January 19, 2016 Applicability Applicable to "Net Metering Facility" as defined below, or applicable Arizona Corporation Commission ("Cmnn1ission") Decision,
More informationESS for Thailand Future Power Grid Energy Absolute PCL.
ESS for Thailand Future Power Grid Energy Absolute PCL. Supa Waisayarat Energy Storage System (ESS) 2 Type of Energy Storage System (ESS) Source: PwC 2015 3 Application of ESS LAES or CES Li-ion Battery
More informationSmart Community Demonstration PJ in Maui
2011 Asia Pacific Clean Energy Summit Smart Community Demonstration PJ in Maui Sep. 13 th, 2011 1:30 p.m. 3:00 p.m. Hitachi, Ltd. Smart City Business Management Division Fumitoshi Emura Hitachi, Ltd. 2011.
More informationAsia Clean Energy Forum 2018
Asia Clean Energy Forum 2018 The current of ESS technology came from Rechargeable battery Lead-acid 40Wh/kg Ni-Cd 60Wh/kg Ni-Mh 80Wh/kg Lithium ion Battery High voltage, high energy density within light
More informationKICK STARTING THE PHILIPPINE RESIDENTIAL ROOFTOP MARKET. by: Mike de Guzman CEO, SolaricCorp.
KICK STARTING THE PHILIPPINE RESIDENTIAL ROOFTOP MARKET by: Mike de Guzman CEO, SolaricCorp. www.solaric.com.ph The Philippine Market High power rates at P12/kWh (~US $0.26/kWh) Fragmented-7,107 islands,
More informationFunctional PCS power supply system with EV battery storage for stable PV power delivery
International Journal of Smart Grid and Clean Energy Functional PCS power supply system with EV battery storage for stable power delivery Kiyotaka Fuji a,b, Yoshihito Shirai a, Takahisa Kawagoe b, Atsushi
More informationThe future role of storage in a smart and flexible energy system
The future role of storage in a smart and flexible energy system Prof Olav B. Fosso Dept. of Electric Power Engineering Norwegian University of Science and Technology (NTNU) Content Changing environment
More informationUS Japan Energy Opportunities. May 15, 2013 NEDO Silicon Valley Office Osamu Onodera
US Japan Energy Opportunities May 15, 2013 NEDO Silicon Valley Office Osamu Onodera Strategic Energy Plan of Japan (before Tohoku) Renewable and Nuclear were to be increased to reduce Co2 emissions but
More informationWhite River Electric Association, Inc. Net Metering Information & Service Requirements
White River Electric Association, Inc. Net Metering Information & Service Requirements What is Net Metering? Net Metering is an electric policy and service for consumers who own and utilize renewable energy
More informationMILESTONE SUMMARY REPORT Project funding provided by customers of Xcel Energy through a grant from the Renewable Development Fund
Project Title: Sodium Sulfur Battery Energy Storage Contract Number: RD3-1 Milestone Number: 1 Report Date: May 0, 009 Reporting Period: September 007 April 008 Milestone Description: Milestone 1 - Specifications
More informationJapan's Effort to Promote More PV
The Future of ASEAN s Energy Journey E-mobility-Smart Grid-Smart City Japan's Effort to Promote More PV June 6th, 2018 Takao Ikeda The Institute of Energy Economics, Japan (IEEJ) Table of Contents Ⅰ. Current
More informationHitachi s Smart Energy Activities - worldwide case studies -
Hitachi s Smart Energy Activities - worldwide case studies - June 17, 2015 Frank Emura Smart Energy Solution Division Information & Telecommunication Systems Group Hitachi, Ltd. 1-1. Business fields of
More informationPedro Nunes. July 2016
Integration of PV and electric vehicles in future energy systems Pedro Nunes July 2016 1. background 2 context Sectors of energy and transport are the biggest GHG emitters in the EU (30% and 20%, respectively)
More informationThe role of Transmission System Operator in Belgium and in Europe. Vlerick Alumni Event 26 January 2016
The role of Transmission System Operator in Belgium and in Europe Vlerick Alumni Event 26 January 2016 Agenda Introduction Infrastructure management Controlling the system Developing the EU Market 1/25/2016
More informationGrid Operations and the Increasing Challenges of Balancing Renewable Energy ALBUQUERQUE QUALITY NETWORK
Grid Operations and the Increasing Challenges of Balancing Renewable Energy JANUARY 18 ALBUQUERQUE QUALITY NETWORK JANUARY 18, 2018 AGENDA Overview and History of PNM Grid Operation Challenges Generation
More informationA New Era for Solar Sarah Kurtz IEEE SCV-PV Series Oct 10, 2018 Palo Alto, CA
A New Era for Solar Sarah Kurtz IEEE SCV-PV Series Oct 10, 2018 Palo Alto, CA SCHOOL OF ENGINEERING Overview Solar has grown Growth has been faster than expected Positive feedback encourages future growth
More informationApril 25, 2013 FOR IMMEDIATE RELEASE
FOR IMMEDIATE RELEASE April 25, 2013 Contact Information: ORIX Corporation NEC Corporation EPCO Corporation Corporate Planning Department Seiichiro Toda Yoshihara or Harasawa Tel: +81-3-5419-5042 +81-3-3798-6511
More informationRenewables induce a paradigm shift in power systems, is energy storage the holy grail?
THE VALUE OF STORAGE FOR THE ENERGY TRANSITION, EURELECTRIC CONFERENCE, DECEMBER 2017 storage for future power systems Adrian Timbus, Head of Technology and Solutions for Smart Grids and Renewables, ABB
More informationCore Components for Large-scale PV Generation Systems
Hitachi Review Vol. 63 (214), No. 4 172 Core Components for Large-scale PV Generation Systems Kosho Aikawa Riichiro Sakamoto Kyoichi Ohkubo Akira Susuki OVERVIEW: Recent years have seen the development
More informationEnergy Recourse Aggregation - Next Paradigm in Electric Energy System
ICEF 2016 : Smart Grids Energy Recourse Aggregation - Next Paradigm in Electric Energy System October 5, 2016 Hideo Ishii, Ph.D. Professor Advanced Collaborative Research Organization for Smart Society
More informationHousehold Renewable Energy
Household Renewable Energy Commissioner Richard Campbell May 23, 2012 Renewable Energy Promotion Methods for Households Net Metering Interconnection Rules Subsidies Tax Credits 2 Net Metering Net metering
More informationNext Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden
Conference-1 Latest Technologies in T & D, Renewable Energy Integration, Smart Grid, Energy Efficiency, Communication Next Generation of UHVDC System R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC
More informationThe Electric Power System
The Electric Power System INDIA Indian Power System 1 2 Basic facts Area:3.288 million km² Population:1.25 Billion Electricity consumers: 216 Million- (31.3.2013) Number of TSOs: 14- (31.3.2013) Numbe
More informationRenewable Energy Integration: Wind, Solar and Energy Storage
Renewable Energy Integration: Wind, Solar and Energy Storage ReGen Powertech Archit Khemka Technology Overview: Wind Solar Hybrid with Energy Storage Concepts Co-located System Two largely independent
More informationPV plus electricity storage, a Japanese case
PV plus electricity storage, a Japanese case Izumi KAIZUKA, kaizuka@rts-pv.com IEA PVPS Task1 Expert, Japan RTS Corporation Contents PV Market in Japan Residential PV plus Storage Storage for PV power
More informationEnergy Storage Options for the Electricity Network
Energy Storage Options for the Electricity Network Dr. Platon Baltas EUDITI 27 June 2018 Why Now? Energy Storage has always been a desired option. Pumped hydro plants represent over 95% of existing energy
More informationThe Role of DSO as Facilitator of the Electricity Markets in Macedonia. Key aspects and considerations
The Role of DSO as Facilitator of the Electricity Markets in Macedonia Key aspects and considerations 30 th of May, 2017 Renewable Energy Production in Macedonia (1/5) Supportive Measures Installed capacity
More informationMicrogrids Outback Power Technologies
Microgrids Outback Power Technologies Microgrids - Definition EPRI defines microgrids as a power system with distributed resources serving one or more customers that can operate as an independent electrical
More informationNJ Solar Market Update
NJ Solar Market Update April 16, 20 Renewable Energy Committee Meeting Trenton, NJ Prepared by Charlie Garrison Solar Installed Capacity Data The preliminary installed solar capacity as of 3/31/ is approximately
More informationNational Forum Next steps in Renewable Energy regulation Case Study on Net- Metering
National Forum Next steps in Renewable Energy regulation Case Study on Net- Metering 19th March-20th March 2013 Speaker CONREPP Peter Weissferdt Which support can RE generate? Energy consumer Invest in
More informationDemand and applications for battery energy storage systems in new energy markets with high share of renewables
Batteriealterung Batteriemodelle Batteriediagnostik Batteriepackdesign Elektromobilität Stationäre Energiespeicher Energiesystemanalyse Demand and applications for battery energy storage systems in new
More informationField Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems
Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems Farid Katiraei *, Barry Mather **, Ahmadreza Momeni *, Li Yu *, and Gerardo Sanchez * * Quanta Technology, Raleigh,
More informationTechnical and Economic Assessment of Solar Photovoltaic and Energy Storage Options for Zero Energy Residential Buildings
Technical and Economic Assessment of Solar Photovoltaic and Energy Storage Options Pedro Moura, Diogo Monteiro, André Assunção, Filomeno Vieira, Aníbal de Almeida Presented by Pedro Moura pmoura@isr.uc.pt
More informationDevelopment of New Megasolar PCS Models and Functions Conforming to Feed-in-Tariff System in Japan
Distributed Power Supply Development of New Megasolar Models and Functions Conforming to Feed-in-Tariff System in Japan Kazuho Hasegawa, Naoto Kameda Keywords Photovoltaic generation,, Megasolar, FIT,
More informationPatrick Lee and Chuck Wells
Real-time microgrid and DERMS control using the PI System and PXiSE Advanced Control Technology Patrick Lee and Chuck Wells 1 PXiSE Energy Solutions A Modern Grid Control Solutions Company Located in San
More informationGreen Island Project Creating Value through Systems Thinking. Carlos A. Santos Silva MIT-Portugal Program Instituto Superior Técnico
Green Island Project Creating Value through Systems Thinking Carlos A. Santos Silva MIT-Portugal Program Instituto Superior Técnico The islands of Azores Azores satellite image (NASA) Azores Energy Outlook
More informationSolar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011
Solar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011 Jim Calore Public Service Electric & Gas Co. Overview This
More informationHawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER
1 Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER Lisa Dangelmaier Hawaii Electric Light lisa.dangelmaier@hawaiielectriclight.com Hawai'i Electric Light System Overview
More informationOperational Opportunities to Minimize Renewables Curtailments
Operational Opportunities to Minimize Renewables Curtailments Clyde Loutan Principal, Renewable Energy Integration July 24, 2017 2017 CAISO - Public Page 1 Agenda Background Real-time control performance
More informationPhotovoltaic Distributed Generation
Photovoltaic Distributed Generation Hawaii Case Study Marc M. Matsuura Sr. Smart Grid Program Manager, GridSTART Hawaii Natural Energy Institute School of Ocean & Earth Science & Technology University
More informationCity Power Johannesburg: Response to Potential Load Shedding. Presented by : Stuart Webb General Manager : PCM October 2014
City Power Johannesburg: Response to Potential Load Shedding Presented by : Stuart Webb General Manager : PCM October 2014 Topics to be discussed Background Challenges Options Available Summary 2 Background
More informationILLINOIS SUPPLEMENTAL PV PROCUREMENT PROGRAM (ROUND 3) JANUARY 13, 2016
ILLINOIS SUPPLEMENTAL PV PROCUREMENT PROGRAM (ROUND 3) JANUARY 13, 2016 SPEAKERS Tom MacKenty Associate, Environmental Markets Steven Eisenberg CEO 2 AGENDA Company Overview Program Overview SRECTrade
More informationFuture of the Power System? Presented by : Yazhou (Joel) Liu, Ph.D., PE Schneider Electric Engineering Services electric.
Microgrids Future of the Power System? Presented by : Yazhou (Joel) Liu, Ph.D., PE Schneider Electric Engineering Services Yazhou.liu@us.schneider electric.com Outline What is Microgrids? Why Microgrids?
More informationApplication of Battery Energy Storage for Frequency Regulation. Alexandre Oudalov
Application of Battery Energy Storage for Frequency Regulation Alexandre Oudalov IEEE PES Swiss Chapter Workshop, Daettwil, 9.11.2006 Agenda Energy storage technologies and applications Primary frequency
More informationSCE Smart Grid. Creating a Cleaner, Smarter Energy Future. Metering, Billing / MDM America Conference. San Diego. March 9, 2010
SCE Smart Grid Creating a Cleaner, Smarter Energy Future Metering, Billing / MDM America Conference San Diego March 9, 2010 SOUTHERN CALIFORNIA EDISON Southern California Edison An Edison International
More informationVPP: New Stage in Energy Management Smart Utilization of Self-Generation Facilities with Automated DR System
VPP: New Stage in Energy Management Smart Utilization of Self-Generation Facilities with Automated DR System 1 TOSHIAKI TANABE *1 SATOSHI KOKAJI *2 OSAMU NAKAKITA *3 MANABU INOUE *4 Along with the expansion
More informationLarge-Scale Hybrid Battery System Demonstration Project to Launch in Germany Aiming to Build a System and Establish a New Business Model
FOR IMMEDIATE RELEASE New Energy and Industrial Technology Development Organization Ministry for Economics, Labour and Transport of Niedersachsen, Federal Republic of Germany EWE-Verband EEW Holding Hitachi
More informationENERGY STRATEGY FOR YUKON. Independent Power Production Policy
ENERGY STRATEGY FOR YUKON Independent Power Production Policy May 20, 2014 Page 2 of 11 BACKGROUND The Government of Yukon released the Energy Strategy for Yukon in January 2009. The strategy sets out
More informationBattery Energy Storage
MARCH 2018 Battery Energy The power to control the energy Marcus Sousa, Territory Market Manager, Europe Challenges of the future power grid Long-term drivers for energy storage Electricity consumption
More informationCommercialized storage solutions for enhanced grid operation
Commercialized storage solutions for enhanced grid operation Dr. Andreas Luxa Principal Expert, Low and Medium Voltage Division, Amsterdam The power grid is in transformation: Increasingly complex source/generation
More informationDER101: Distributed Energy Resources basics. May 4, 2017
DER101: Distributed Energy Resources basics May 4, 2017 Agenda Introduction Definitions Abbreviations Types Why it is important Common Misconceptions DER System Basics References, Codes and Standards Interconnection
More informationHybrid Grid and Energy Storage: A Step towards Adaptation, Application and Development
Hybrid Grid and Energy Storage: A Step towards Adaptation, Application and Development BY J.S. CHANDOK AGM(NETRA) NETRA, NTPC LTD. About NTPC and NETRA India s MAHARATNA & Leading Power Generating Company
More informationWest Virginia Energy Plan and Becoming an Electric Generator
West Virginia Energy Plan and Becoming an Electric Generator June 25 th, 2013 Electricity Exports, 2010 2010 EIA Data 1 1 Costs are expressed in terms of net AC power available to the grid for the installed
More informationDevelopment and Demonstration of Redox Flow Battery System
FEATURED TOPIC Development and Demonstration of Redox Flow Battery System Keiji YANO*, Shuji HAYASHI, Takahiro KUMAMOTO, Toshikazu SHIBATA, Katsuya YAMANISHI and Kazuhiro FUJIKAWA ----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
More informationELECTRIC ENERGY STORAGE
ELECTRIC ENERGY STORAGE January 12-13, 13, 2011 Phoenix,, AZ Vincent Pusateri GS Battery (USA) Inc. Sr. Director, Business Development The Simpsons Season 21 Episode 19 The Squirt and the Whale The Simpsons
More informationPLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION
PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION Presentation by Engr. O. C. Akamnnonu Chief Executive Officer, Ikeja Electricity Distribution Company AGENDA WORK THROUGH
More information2018 Load & Capacity Data Report
Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness
More informationDecentralized Electrification of Suyuek in Xinjiang
Decentralized Electrification of Suyuek in Xinjiang EDF Solution for Decentralized Rural Electrification Asia Pacific Branch, EDF R&D, EDF Group CONTENT Brief introduction of EDF Activities EDF s solution
More informationIn Bulgaria by. Continental Wind Bulgaria EOOD
In Bulgaria by Continental Wind Bulgaria EOOD CONTINENTAL WIND PARTNERS OVERVIEW Leading global wind developer with over 3,000 MW under development Continental Wind Partners LLC (CWP) is one of the leading
More informationAncillary Services & Essential Reliability Services
Ancillary Services & Essential Reliability Services EGR 325 April 19, 2018 1 Basic Products & Ancillary Services Energy consumed by load Capacity to ensure reliability Power quality Other services? o (To
More informationPower Purchase Agreement for Commercial PV Systems
Power Purchase Agreement for Commercial PV Systems Dr. Özlem Döğerlioğlu IŞIKSUNGUR Managing Partner ozlem@dogerlihukuk.com WHO WE ARE? Döğerlioğlu Law Firm. CONTENT OF THE PRESENTATION Solar Energy Generation
More informationTechnical Information Average Efficiency of the SMA Flexible Storage System
Technical Information Average Efficiency of the SMA Flexible Storage System The average efficiency of a system for intermediate storage of energy, e.g. of the SMA Flexible Storage System, indicates how
More informationRESERVOIR SOLUTIONS. GE Power. Flexible, modular Energy Storage Solutions unlocking value across the electricity network
GE Power RESERVOIR SOLUTIONS Flexible, modular Energy Storage Solutions unlocking value across the electricity network TRENDS DISRUPTING THE POWER SECTOR FROM GENERATION TO T&D DECARBONIZATION DIGITIZATION
More informationBuilding Smart Grid with µems CEZ Spring Conference, 16 th -17 th April 2014 Igor Dremelj, VP Smart Grid Solutions EMEA
Building Smart Grid with µems CEZ Spring Conference, 16 th -17 th April 2014 Igor Dremelj, VP Smart Grid Solutions EMEA 1 TOSHIBA Group and its Business segments Company name: TOSHIBA CORPORATION Headquarters
More informationElectric Energy Storage in Batteries Platon Baltas Athens 16 October, rd Energy Tech Forum storage
Electric Energy Storage in Batteries Platon Baltas Athens 16 October, 2018 1 Why Now? Energy Storage has always been a desired option. Pumped hydro plants represent over 95% of existing energy worldwide,
More informationSimulation and Visualization of Power Grid Operations with High Renewable Penetration
Simulation and Visualization of Power Grid Operations with High Renewable Penetration Thomas J Overbye Fox Family Professor of Elect. & Comp. Eng. University of Illinois at Urbana-Champaign overbye@illinois.edu
More informationPV Aggregation Results from Germany
PV Netzstation MS-Netz 20 kv 0,4 kv Leitung HAS 1 HAS 2 Trafo P P Q 3~ P Q = P Last 1 Last 2 PV PV Aggregation Results from Germany Dr.-Ing. Bernhard Ernst Director Grid Integration, SMA Solar Technology
More informationManagement Plan for FY2013
for April 26, 2013 Fuji Electric Co., Ltd. 1 Looking back from FY2010 to Establish profitable structure by business restructuring ED&C, Magnetic Disks, Vending Machines, Drives, Power Semiconductors and