Schematic Layout Development

Size: px
Start display at page:

Download "Schematic Layout Development"

Transcription

1 Schematic Layout Development Northeast Hangar Area Manassas Regional Airport Manassas, Virginia November 2015

2 Introduction In response to the continuing development demand at Manassas Regional Airport, the following report summarizes the methodology and findings associated with the development of schematic layouts for the northeast hangar area. The intent of this effort was to develop a concept that demonstrates the overall potential for the northeast hangar complex. The resulting layouts presented herein are not intended to establish final layouts or limits, only to document that development is possible, and to what overall magnitude. Once demand generates a need to expand into this area, a more detailed preliminary engineering effort should be completed. Additional data will also need to be gathered and taken into consideration, including but not limited to: Formal environmental clearance (Environemental Assessment) Field coordination with various agencies on RPA/Wetland limits (Information used in this report is based on aerial information only. Formal investigations were not undertaken.) Floodplain impacts/assessments Traffic impact on local roads including queueing for railroad crossings Utility capacity Development criteria/interface with portions of site located within Prince William County, including Coastal Zone coordination Stormwater quality and quantity management November 2015 Page 1 of 22

3 Site Information/Background Manassas Regional Airport is a public use airport, owned and operated by the City of Manassas, Virginia. Just thirty miles south of our nation s capital, the Airport s facilities and location make it a key regional asset (see Figure 1). The Federal Aviation Administration has recognized Manassas s importance by designating it as one of the 84 national General Aviation airports, providing communities access to national and international markets. The airport is served by an Air Traffic Control Tower, and is home to several businesses, basing several large turbine corporate aircraft. As presented in Figure 2, Runway 16L-34R (6,200 x 100 ) is the airport s primary runway and is supported by parallel Runway 16R-34L (3,702 x 100). Runway 16L s Instrument Landing System (ILS) approach allows the airport to function during most visibility conditions by providing 1/2 mile visibility and 200 foot ceiling minimums. The parallel runway system is served by several taxiways which lead from hangar, FBO, and apron areas located to either side of the parallel runway complex. The airport terminal building is the center of a variety of services for arriving and departing travelers, those in need of U.S. Customs assistance, and pilots. November 2015 Page 2 of 22

4 10 Schematic Layout Report: Northeast Hangar Area GAI Airport JYO Airport IAD Airport DCA Airport M i l e s Manassas Regional Airport (HEF) 20 Mi l es N GRAPHIC SCALE: 1" = 5 Mile Figure 1: Vicinity Map November 2015 Page 3 of 22

5 Figure 2: Airport Diagram November 2015 Page 4 of 22

6 Northeast Hangar Area Shown on Figure 3, the northeast hangar complex is home to some of the larger aircraft and business based users. The northeast area has been expanded to a point where any future expansion is very limited or a change in development patterns would be necessary. The purpose of this paper is to present the general constraints on expansion within the existing limited footprint and to explore expansion options to the east of the complex, across Wakeman Drive. Figure 3: Northeast Hangar Complex November 2015 Page 5 of 22

7 Site Features/Constraints The project area has several features that affect development including: Wakeman Drive - currently the eastern boundary of the site Observation Road to the north Commuter/heavy rail line to the north Cannon Branch and associated environmental buffers to the east (beyond Wakeman Drive) Airport boundary north near the rail line and along Cannon Branch to the east Harry Parrish Boulevard to the south Airport to the west Design Parameters The desire for any future development of the northeast area is to continue to service large aircraft using the airport and to support the businesses associated with the aircraft owners. Using this information, an Airplane Design Group III, as defined in the FAA s Advisory Circular AC 150/ A) was chosen as the critical aircraft group to use for evaluating development potential. This design group includes aircraft with wingspans up to but not including 118 feet. Some of the aircraft in this group are: The Boeing Business Jet (B 737) Gulfstream series aircraft (including the G VI) Challenger Series Aircraft Bombardier Q-400 Bombardier Global Series Aircraft November 2015 Page 6 of 22

8 Table 4-1 from FAA AC 150/ A Airport Design lists the design standards. November 2015 Page 7 of 22

9 Development Options Option 1 While indicated as not desirable by airport staff and inconsistent with the Airport Layout Plan (See Figure 4), an option was developed using the existing physical limits, specifically Wakeman Drive. As presented on Figure 5, the development potential within the immediate footprint of the site is limited. Figure 4: Plan for Northeast quadrant from Airport Layout Plan While other concepts are possible, the option shown provides the necessary perspective to identify issues including: A hangar smaller than the desired aircraft size Problematic site access thru an existing lease area Likely no direct access to Observation Road or Wakeman Drive Precludes future growth to the east without removal of facility Unlikely to meet City design standard requirement for setbacks, etc. Inconsistent with current Airport Layout Plan November 2015 Page 8 of 22

10 Figure 5: Option 1 - Development within existing limitations November 2015 Page 9 of 22

11 Option 2 Option 2 was developed to evaluate the potential of expanding to the east. As shown on Figure 6, for this Option, the road was relocated to the eastern most boundary, established by approximating a 100 foot environmental buffer along Cannon Branch (which is also close to the airport property line). Figure 6: Option 2 - Development with adjustments to Wakeman Drive and other features It s important to note that this environmental buffer is approximate; formal surveys and an environmental assessment would be required prior to any construction. These surveys and assessment would likely revise the boundary. However for the purpose/goal of this effort, the boundary location is adequate. With the eastern boundary defined, the next step for Option 2 was to determine where and how aircraft could move from the existing airfield pavements to the area opened for development. By working north to south, five general areas of development were defined as presented below. November 2015 Page 10 of 22

12 Option 2 - Area 1 It is likely that any relocation of Wakeman Drive will require a substantial commitment by a tenant to justify the local costs associated with the road relocation. Items that would have to be addressed include environmental impacts and a crossing of a small stream/ditch. Area 1, the northern most site, shown in Figure 7, is providing the most promise for large hangars as the space available is relatively deep compared to the rest of the overall site. Highlights of Option 2 - Area 1 include: T h e a b i l i t y t o p h a s e t h e r e l o c a t i o n o f W a k e m a n D r i v e. W h i l e not ideal for traffic flow, the phased relocation shown allows for incremental financial commitment. Apron space and taxilanes designed for Group III aircraft (wingspans up to 118 feet, taxilane object free width is 162 ). Potential for large hangars. Those shown are for visual references only. Actual hangar size(s) will depend on need of future tenant. To accommodate new apron, existing autoparking needs to be relocated. A parking lot east of existing Wakeman Drive has been shown to replace those spaces lost. It is important to note that the lot size is based on maximizing the general space available and not based on any space demand. Phase I relocation of Wakeman Drive. Figure 7: Option 2 - Area 1 November 2015 Page 11 of 22

13 Option 2 - Area 2 Schematic Layout Report: Northeast Hangar Area As presented in Figure 8, Area 2 is to some extent interdependent on Area 1. Due to the lack of direct airfield access to Area 2, an office building is shown to the east of the parking lot developed as part of Area 1. This office can either be an office used for direct airport use or through coordination with the FAA, this area could be defined as nonaviation related use. Also shown as part of Area 2 is the potential relocation of the airport s fuel farm and its Figure 8: Option 2 - Area 2 replacement with a second office building. This idea is being presented primarily to reinforce conversations during the development of these layouts that the fuel farm location is not fixed and under the right circumstances, could be relocated. The other purpose for showing the relocation is the somewhat cumbersome access that is developed for the fuel farm with the relocation of Wakeman Drive. Highlights of Option 2 Area 2 include: Two new multi-story office buildings (height limit subject to FAR Part 77 surfaces). Common parking with office and adjacent development to allow for campus style development. Potential to shift/expand development to the south with the relocation of the fuel farm. Airside access from the fuel farm (prior to relocation or if it remains) and other users is maintained. November 2015 Page 12 of 22

14 Option 2 - Area 3 Area 3 (Figure 9) starts by constructing the second phase of the Wakeman Drive relocation. As before, the traffic pattern developed is somewhat awkward as it requires right turns versus a direct path. These right turns are necessary to accommodate the future and final phase of the relocation while not sacrificing or creating temporary roads. An example of this can be seen where the access to Area 2 is now shifted to the east of the second phase of Wakeman Drive relocation, yet the original leg is still maintained and now accesses the parking lots only. Highlights of Option 2 Area 3 include: A new 58,000 sf apron area Two new hangars The rotating beacon and the airfield electrical vault are between Area 2 and 3 and would likely be relocated to more appropriate locations. Airside access is maintained thru existing gates and roadway network. Phase II of Wakeman Drive It is important to note that with expansion into Area 3, the airport boundary now crosses into Prince William County. Development would likely require review and approval of both the City of Manassas and Prince William County. This also triggers the need to complete Coastal Zone coordination. Something that would have been completed as part of the environmental effort. Figure 9: Option 2 - Area 3 November 2015 Page 13 of 22

15 Option 2 - Areas 4 and 5 Areas 4 and 5 will likely be developed together. When Area 4 or 5 are opened, (see Figure 10) little would be gained by adding an additional phase to the relocation of Wakeman Drive. Area 4 opens up with the relocation/removal of two T-hangar buildings. While in fair to good condition today, by the time development demand moves to Area 4, it is likely that a costly rehabilitation of both the buildings and site would be necessary. This option re-designates the area for use by larger aircraft. Area 5 lacks the airside access so development would likely be for support facilities similar to the ARFF station currently shown on the Airport Layout plan. Highlights of Option 2 Area 4 and 5 include: A new apron area New large hangar with enough space to support a large parking lot or the space could be used for other needs if the parking needs are smaller than that shown. A local area to be used by the Airport for support. While designated as ARFF, any support facility could be accommodate. ARFF would likely require some airside access improvements. November 2015 Page 14 of 22

16 It is important to note that with expansion into Area 3, the airport boundary now crosses over into Prince William County. Development would likely require review and approval of both the City of Manassas and the County. Figure 10: Option 2 - Area 4 and 5 A complete layout of Option 2 is presented in Figure 11. November 2015 Page 15 of 22

17 Figure 11: Option 2 November 2015 Page 16 of 22

18 Option 3 East of the Airport, on the opposite side of Cannon Creek, is an industrial park. This park, located in Prince William County is currently managed by CBRE. The company s web page provides the layout shown in below which indicates that the proposed use is warehouse and distribution. As presented on Figure 12, an opportunity may exist to provide airport access across Cannon Creek. While direct airfield access would not be possible, this connection could facilitate use of both the airport and the industrial park by one entity that has both an aviation component and a non-aviation component. Accessing the industrial area to the east also introduces the possibility of using the industrial park s road in place of relocating Wakeman Drive. While this concept would require multiple crossings of Cannon Creek, this concept would provide for some additional depth for airport development and the connecting roads could provide for improved security for airport tenants. November 2015 Page 17 of 22

19 Figure 12: Option 3 November 2015 Page 18 of 22

20 Figure 13: Option 4 November 2015 Page 19 of 22

21 BUDGET ESTIMATES Budgets have been developed based on recent (CY 2015) prices for similar projects. Details of the budgets are presented in Appendix A. It is important to note that, due to the limited detailed information known at this level of effort, several contingencies have been added. Even with these contingencies, budgets should be revisited as any phase of the relocation of Wakeman Drive progresses. Budgets for each phase of work are presented below. November 2015 Page 20 of 22

22 Appendix A Preliminary Project Budget

23 PRELIMINARY PROJECT BUDGET RELOCATE WAKEMAN DRIVE MANASSAS REGIONAL AIRPORT, VIRGINIA Date: November 9, 2015 Administration IFE Estimate $ 5, $ 5, $ 5, $ 15, May be AIP Eligible Postage, other admin costs $ 10, $ 10, $ 10, $ 30, May be AIP Eligible Subtotal $ 15, $ 15, $ 15, $ 45, Preliminary expense ALP Update, planning study $ 150, $ - $ - $ 150, One time cost. Environmental Assessment $ 450, $ - $ - $ 450, Engineering basic fees Subtotal $ 600, $ - $ - $ 600, Design $ 350, $ 50, $ 50, $ 450, Bidding $ 10, $ 10, $ 10, $ 30, Subtotal $ 360, $ 60, $ 60, $ 480, Project inspection fees Construction Phase services $ 250, $ 225, $ 225, $ 700, May be AIP Eligible Subtotal $ 250, $ 225, $ 225, $ 700, Assumes high costs associated with Cannon Creek Phase 1 includes full design, other phases are bid package development Construction and project improvement cost Budget construction costs (rounded up to nearest $50,000) $ 1,800, $ 1,150, $ 1,150, $ 4,100, May be AIP Eligible Wetland mitigation and permitting (assume 3 acres) $ 250, $ - $ - $ 250, Cost is upfront for cumulative impacts Relocate Utilities Miscellaneous cost PHASE 1 PHASE 2 PHASE 3 TOTAL Contained in construction budgets Subtotal $ 2,050, $ 1,150, $ 1,150, $ 4,350, REMARKS Contingency 15% $ 490, $ 220, $ 220, $ 930, May be AIP Eligible Subtotal $ 490, $ 220, $ 220, $ 930, TOTALS $ 3,765, $ 1,670, $ 1,670, $ 7,105, All costs in CY 2015 dollars N:\15071\03 Project Data\Estimates\15071 CS01_Preliminary Page 1 of 1

24 ENGINEER'S OPINION OF PROBABLE COST RELOCATE WAKEMAN DRIVE MANASSAS REGIONAL AIRPORT MANASSAS, VIRGINIA DELTA PROJECT NO DATE November 9, 2015 (CY 2015 DOLLARS USED) PHASE 1 PHASE 2 PHASE 3 TOTAL DESCRIPTION UNIT QTY UNIT PRICE TOTAL QTY UNIT PRICE TOTAL QTY UNIT PRICE TOTAL QTY UNIT PRICE TOTAL MISCELLANEOUS ITEMS PAVEMENT DRAINAGE MOBILIZATION (10% OF ALL OTHER COSTS, ROUNDED) LS 1 $ 130, $ 130, $ 80, $ 80, $ 80, $ 80, $ 290, $ 290, MISCELLANEOUS DEMOLITION LS 1 $ 10, $ 10, $ 10, $ 10, $ 10, $ 10, $ 30, $ 30, CLEARING AND GRUBBING AC 10 $ 5, $ 50, $ 5, $ 35, $ 5, $ 35, $ 5, $ 120, UNCLASSIFIED EXCAVATION CY 25,000 $ 8.00 $ 200, ,000 $ 8.00 $ 120, ,000 $ 8.00 $ 120, ,000 $ 8.00 $ 440, EROSION AND SEDIMENT CONTROL LS 1 $ 50, $ 50, $ 50, $ 50, $ 50, $ 50, $ 150, $ 150, SEEDING AND MULCHING AC 10 $ 3, $ 30, $ 3, $ 21, $ 3, $ 21, $ 3, $ 72, AGGREGATE BASE, VDOT 21A TN 3,000 $ $ 90, ,500 $ $ 45, ,500 $ $ 45, ,000 $ $ 180, ASPHALT CONCRETE PAVEMENT, SM-9.5A TN 1,100 $ $ 110, $ $ 55, $ $ 55, ,200 $ $ 220, ASPHALT CONCRETE PAVEMENT, BM-25.0 TN 700 $ $ 63, $ $ 31, $ $ 31, ,400 $ $ 126, " RCP, CLASS III (ASSUMED) LF 130 $ $ 39, $ $ 39, $ $ 39, $ $ 117, " UNDERDRAIN PIPE LF 5,000 $ $ 50, ,500 $ $ 25, ,500 $ $ 25, ,000 $ $ 100, VDOT STD ES-1 EA 2 $ 5, $ 10, $ 5, $ 10, $ 5, $ 10, $ 5, $ 30, RIPRAP, CLASS I SY 25 $ $ 2, $ $ 2, $ $ 2, $ $ 6, MISC DRAINAGE (20% OF ALL OTHER DRAINAGE) LS 1 $ 20, $ 20, $ 15, $ 15, $ 15, $ 15, $ 50, $ 50, SECURITY UTILITIES TRAFFIC CONTROL 8' GALVANIZED CHAIN LINK FENCE LF 2,500 $ $ 62, ,200 $ $ 30, ,200 $ $ 30, ,900 $ $ 122, AUTOMATIC VEHICLE SLIDING GATE EA 2 $ 10, $ 20, $ 10, $ 20, $ 10, $ 20, $ 10, $ 60, PEDESTRIAN GATE EA 2 $ 1, $ 3, $ 1, $ 3, $ 1, $ 3, $ 1, $ 9, ACCESS CONTROL SYSTEM UPGRADES LS 1 $ 50, $ 50, $ 50, $ 50, $ 50, $ 50, $ 150, $ 150, " WATER MAIN LF 2,500 $ $ 200, ,200 $ $ 96, ,200 $ $ 96, ,900 $ $ 392, FIRE HYDRANT EA 2 $ 4, $ 9, $ 4, $ 9, $ 4, $ 9, $ 4, $ 27, WATER MAIN APPURTENANCES LS 1 $ 25, $ 25, $ 25, $ 25, $ 25, $ 25, $ 75, $ 75, SANITARY SEWER LF 2,500 $ $ 125, ,200 $ $ 60, ,200 $ $ 60, ,900 $ $ 245, SANITARY SEWER MANHOLE EA 2 $ 5, $ 10, $ 5, $ 10, $ 5, $ 10, $ 5, $ 30, POWER LS 1 $ 50, $ 50, $ 50, $ 50, $ 50, $ 50, $ 150, $ 150, TRAFFIC SIGNS LS 1 $ 5, $ 5, $ 5, $ 5, $ 5, $ 5, $ 5, $ 15, PAVEMENT MARKING 4" SF 1,700 $ 4.00 $ 6, $ 4.00 $ 3, $ 4.00 $ 3, ,300 $ 4.00 $ 13, SUBTOTAL CONTINGENCY 25% TOTAL CONSTRUCTION (rounded) $ 1,420,800 $ 899,825 $ 899,825 $ 3,220,075 $ 355,200 $ 224,956 $ 224,956 $ 805,019 $ 1,780,000 $ 1,120,000 $ 1,120,000 $ 4,030,000 N:\15071\03 Project Data\Estimates\15071 EST01 Page 1 of 1

Capital Improvement Program

Capital Improvement Program 7 INTRODUCTION The (CIP) involves the compilation of a schedule of recommended development projects, and their probable costs, that are based on the fi ndings of the demand forecasts and facility requirements

More information

Terminal Alternatives

Terminal Alternatives Chapter 5 Terminal Alternatives Missoula International Airport Master Plan Update Prepared for Missoula County Airport Authority OCTOBER 2008 Contents Section Page 5 Terminal Alternatives...5-1 5.1 Terminal

More information

Wentzville Parkway South Phase 2 & 2A

Wentzville Parkway South Phase 2 & 2A Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total

More information

CONCEPTUAL DESIGN SUBMITTAL MADISON AASF #2 ROTARY WING PARKING APRON Project No. 05H2W

CONCEPTUAL DESIGN SUBMITTAL MADISON AASF #2 ROTARY WING PARKING APRON Project No. 05H2W CONCEPTUAL DESIGN SUBMITTAL MADISON AASF #2 ROTARY WING PARKING APRON Project No. 05H2W Wisconsin Army National Guard Madison AASF #2 Dane County Regional Airport Madison, Wisconsin July 2009 TABLE OF

More information

Photo credit: Vanessa Bauman

Photo credit: Vanessa Bauman Ted Stevens Anchorage International Airport 2014 MASTER PLAN UPDATE APPENDIX G - AIRCRAFT RESCUE AND FIRE FIGHTING TRAINING FACILITY SITING STUDY FINAL DECEMBER 2014 IN ASSOCIATION WITH: HDR DOWL HKM RIM

More information

Transportation Analysis. Pedestrian Pathways. Sterling District. County Project Manager: Suheili Pérez-Jiménez. Prepared by: J2 Engineers, Inc.

Transportation Analysis. Pedestrian Pathways. Sterling District. County Project Manager: Suheili Pérez-Jiménez. Prepared by: J2 Engineers, Inc. Transportation Analysis Pedestrian Pathways Prepared for: Loudoun County Department of Transportation and Capital Infrastructure County Project Manager: Suheili Pérez-Jiménez Prepared by: J2 Engineers,

More information

4 COSTS AND OPERATIONS

4 COSTS AND OPERATIONS 4 COSTS AND OPERATIONS 4.1 INTRODUCTION This chapter summarizes the estimated capital and operations and maintenance (O&M) costs for the Modal and High-Speed Train (HST) Alternatives evaluated in this

More information

Steese Rd - Curb & Sidewalk Improvement

Steese Rd - Curb & Sidewalk Improvement REF. NO. ITEM NO. Steese Rd - Curb & Sidewalk Improvement DESCRIPTION QTY UNITS UNIT COST SUB-TOTAL 1 103.05 Requirement of Contract Bid 1 LS 24,048.00 24,048.00 2 201 Clearing and Grubbing 1 LS 11,077.00

More information

CITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS Engineering Division PROJECT NO INCA STREET MULTI-USE PATH 38 TH AVE. TO 43 RD AVE.

CITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS Engineering Division PROJECT NO INCA STREET MULTI-USE PATH 38 TH AVE. TO 43 RD AVE. 201-00000 Clearing and Grubbing 1 LS 202-00010 Removal of Tree 9 EA 202-00019 Removal of Inlet 8 EA 202-00034 Removal of Pipe (6 Inch) 196 LF 202-00035 Removal of Pipe (18 Inch) 10 LF 202-00036 Removal

More information

APPENDIX C: COSTS BACK-UP

APPENDIX C: COSTS BACK-UP APPENDIX C: COSTS BACK-UP SECTION 2010-2015 Executive Recap DESCRIPTION MAC LTCP PLAN RANGE LOW HIGH Humphrey Terminal Expansion - Phase I (Add 17 Gates) $224,077,000 - $263,620,000 OTHER PHASE SCOPE

More information

THORNTON ROAD WIDENING PROJECT NO. PW1428 B I D D I N G S C H E D U L E

THORNTON ROAD WIDENING PROJECT NO. PW1428 B I D D I N G S C H E D U L E THORNTON ROAD WIDENING PROJECT NO. PW1428 B I D D I N G S C H E D U L E Each bidder shall bid each item of the Base Bid Schedule and Alternate A Bid Schedule. Failure to bid an item shall be just cause

More information

Chapter 8.0 PROPOSED CAPITAL IMPROVEMENT PROGRAM

Chapter 8.0 PROPOSED CAPITAL IMPROVEMENT PROGRAM Chapter 8.0 PROPOSED CAPITAL IMPROVEMENT PROGRAM This chapter presents the proposed Capital Improvement Program (CIP) for the District based on the findings of this Master Plan. The Master Plan primarily

More information

HILLS MATERIALS COMPANY UNIT COST TOTAL COST UNIT COST TOTAL COST UNIT COST $294, $294, $74, $74, $35, $35,000.

HILLS MATERIALS COMPANY UNIT COST TOTAL COST UNIT COST TOTAL COST UNIT COST $294, $294, $74, $74, $35, $35,000. PROJECT NAME: Anamosa Street Reconstruction - Midway Street to Miiwuakee Street PROJECT NUMBER: PROJECT NO. 07-1473 / CIP NO. 50559 LET DATE: April 11, 2017 LOW BID AMOUNT: $3,941,397.20 ENGINEER'S ESTIMATE

More information

Oaks Commerce Center

Oaks Commerce Center Mansour Edlin Consulting 1515 Mockingbird Lane Charlotte, NC 28209 Oaks Commerce Center Water & Sanitary Sewer Improvements Phase I - Concept Utility Plan Gravity Sanitary Sewer A1 Connect to Existing

More information

Appendix D. Airside and Landside Pavement Inventories

Appendix D. Airside and Landside Pavement Inventories Appendix D Airside and Landside Pavement Inventories Runway 5-23 2010 2" Mill and 2" Bituminous Surface Course Overlay 2001 2" Bituminous Surface Overlay 1984 2" Bituminous Surface Course Partial Overlay

More information

COST ESTIMATES: Curb-Running

COST ESTIMATES: Curb-Running COST ESTIMATES: Curb-Running PROJECT FEASIBILITY COST ESTIMATE SUMMARY Geary Bus Rapid Transit Study Alternative: Side Lane (Curb Running) Date: 4/12/07 Percent Cost Total Project Capital Outlay I- Roadway

More information

DESCRIPTION QUANTITY PRICE TOTAL

DESCRIPTION QUANTITY PRICE TOTAL GENERAL 1 TRAFFIC CONTROL LS 1 $40,000 $40,000 $8,500.00 $8,500.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $15,000.00 $15,000.00 2 MOBILIZATION LS 1 $557,000 $557,000 $629,500.00 $629,500.00 $350,000.00

More information

McCRORY & WILLIAMS, INC. HILLCREST ROAD CONNECTOR MCR ROADWAY ITEMS

McCRORY & WILLIAMS, INC. HILLCREST ROAD CONNECTOR MCR ROADWAY ITEMS BID TABULATION Hillcrest Road Connector John G. Walton Construction M. C. Williams Contracting Hosea. Weaver & Sons, Inc. BID OPENING: March 25, 29 Company, Inc. Company, Inc. QTY DESCRIPTION DOLLARSjCTS

More information

Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary

Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Prepared

More information

ATTACHMENT #1. TO: Patricia delabruere DATE: May 5, 2015 JNU Airport Manager

ATTACHMENT #1. TO: Patricia delabruere DATE: May 5, 2015 JNU Airport Manager MEMO TO: Patricia delabruere DATE: May 5, 2015 JNU Airport Manager FROM: RE: Catherine Fritz, AIA JNU Airport Architect ARFF Project Formulation The Airport Board s funding authorization on February 11,

More information

ANDERSON PROPERTY SITE ANALYSIS

ANDERSON PROPERTY SITE ANALYSIS ANDERSON PROPERTY SITE ANALYSIS Introduction The Montgomery County Department of Transportation (MCDOT) initiated a feasibility study in the fall of 2012 to evaluate the need for transit service expansion

More information

City of Grand Forks Staff Report

City of Grand Forks Staff Report City of Grand Forks Staff Report Service/Safety Committee December 15, 2015 City Council December 21, 2015 Agenda Item: Amendment No. 1 to Engineering Services Agreement with CPS for City Project No. 7143,

More information

SPAS Concepts Preliminary Rough Order of Magnitude Cost Estimates

SPAS Concepts Preliminary Rough Order of Magnitude Cost Estimates Appendix G LAX SPECIFIC PLAN AMENDMENT STUDY REPORT SPAS Concepts Preliminary Rough Order of Magnitude Estimates 2011/2012 Prepared for: Los Angeles World Airports One World Way Los Angeles, California

More information

I-20 East Transit Initiative

I-20 East Transit Initiative I-20 East Transit Initiative PRELIMINARY ORDER OF MAGNITUDE CAPITAL COST ESTIMATING METHODOLOGY Technical Memorandum December 2011 Prepared for: Metropolitan Atlanta Rapid Transit Authority Atlanta, GA

More information

The Eastern Connector Study November, 2007 planning for the future

The Eastern Connector Study November, 2007 planning for the future The Eastern Connector Study November, 2007 planning for the future In late 2006, Albemarle County and the City of Charlottesville jointly initiated the Eastern Connector Corridor Study. The Project Team

More information

Information Meeting Transfer Station Options. September 30, 2014

Information Meeting Transfer Station Options. September 30, 2014 Information Meeting Transfer Station Options September 30, 2014 Outline of Presentation Why we are looking at changes Background on current Transfer Station Options that were considered need, function

More information

Update on Community or Heritage Rail Project (Project Manager Services) The Engineering Department recommends that Council:

Update on Community or Heritage Rail Project (Project Manager Services) The Engineering Department recommends that Council: Corporate NO: R279 Report COUNCIL DATE: DECEMBER 18, 2006 REGULAR COUNCIL TO: Mayor & Council DATE: December 15, 2006 FROM: General Manager, Engineering FILE: 8710-20 (Heritage) SUBJECT: Update on Community

More information

3.14 Parks and Community Facilities

3.14 Parks and Community Facilities 3.14 Parks and Community Facilities 3.14.1 Introduction This section identifies the park and community facility resources in the study area and examines the potential impacts that the proposed Expo Phase

More information

Link LRT: Maintenance Bases, Vehicles and Operations for ST2 Expansion

Link LRT: Maintenance Bases, Vehicles and Operations for ST2 Expansion Project Number SYS-LRT Subareas All Primary Mode Impacted Link Facility Type Link Service Version Number 4.0 Date Last Modified 7/24/2008 Project Locator Map Short Project Description Construct new light

More information

4.0 TIER 2 ALTERNATIVES

4.0 TIER 2 ALTERNATIVES 4.0 TIER 2 ALTERNATIVES The Tier 2 Alternatives represent the highest performing Tier 1 Alternatives. The purpose of the Tier 2 Screening was to identify the LPA utilizing a more robust list of evaluation

More information

Appendix C Capital Improvement Program Project Descriptions and Details

Appendix C Capital Improvement Program Project Descriptions and Details Appendix C Capital Improvement Program Project Descriptions and Details GIG HARBOR WW COMP PLAN DRAFT CAPITAL IMPROVEMENT PROGRAM LIFT STATION COST ESTIMATE Lift Station 1 Item Qty Units Unit Cost Extended

More information

Public Information Workshop

Public Information Workshop Public Information Workshop Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 29, 2018 Welcome to the Public Information Workshop for Harborview Road Project Development and Environment (PD&E)

More information

Project Book Worksheet for Cost Estimation

Project Book Worksheet for Cost Estimation 001.01 MOBILIZATION LS $34,716.18 007 3/17/2039 001.02 INCIDENTAL LS $23,929.43 019 3/17/2039 001.03 CONSTRUCTION STAKING LS $10,504.39 201 5/9/2013 001.04 REESTABLISH PROPERTY CORNERS EA $496.08 201 5/9/2013

More information

US 81 Bypass of Chickasha Environmental Assessment Public Meeting

US 81 Bypass of Chickasha Environmental Assessment Public Meeting US 81 Bypass of Chickasha Environmental Assessment Public Meeting March 14, 2013 Introductions ODOT FHWA SAIC Meeting Purpose Present need for bypass Provide responses to 10/04/11 public meeting comments

More information

CAPITAL FUND 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS

CAPITAL FUND 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS 2019-2023 9510 STREET & SIDEWALK IMPROVEMENTS - 01 STREET AND SIDEWALK MAINTENANCE PROGRAM $1,250,000 $0 $1,250,000

More information

CT Consultants, Inc.

CT Consultants, Inc. Cost 1 202 AHRESTY DRIVE REMOVAL 1 LS 2 202 EXISTING SILO DEMOLISHED AND REMOVED, AS PER PLAN 1 LS 3 203 EXCAVATION (NOT INCLUDING UNDERCUT) 2,372 CY 4 203 EMBANKMENT 3,306 CY 5 204 PROOF ROLLING 10 HRS

More information

BID TABULATION REPORT McKINNEY STREET DRAINAGE IMPROVEMENTS PROJECT No. PWDR10012 BID OPENED : TUESDAY, AUGUST 13, :00 P.M.

BID TABULATION REPORT McKINNEY STREET DRAINAGE IMPROVEMENTS PROJECT No. PWDR10012 BID OPENED : TUESDAY, AUGUST 13, :00 P.M. PAVING IMPROVEMENTS McKINNEY 101 Rightofway Preparation LS 1 75,000.00 75,000.00 200,000.00 200,000.00 67,000.00 67,000.00 110,000.00 110,000.00 102 12inch HMAC Street Pulvermix SY 11,650 3.00 34,950.00

More information

IH 35 FEASIBILITY STUDY

IH 35 FEASIBILITY STUDY IH 35 FEASIBILITY STUDY COOKE COUNTY, TEXAS February 1, 2007 Prepared by: Carter & Burgess, Inc. For: The Wichita Falls District of the Texas Department of Transportation INDEX I. INTRODUCTION. 3 II. PURPOSE

More information

Town of Medley Office of Capital Projects & Development Services 7777 NW 72 Avenue, Medley, Florida 33166

Town of Medley Office of Capital Projects & Development Services 7777 NW 72 Avenue, Medley, Florida 33166 Town of Medley Office of Capital Projects & Development Services 7777 NW 72 Avenue, Medley, Florida 33166 Date: August 10, 2016 Subject: Bid for Construction of NW 89 th Avenue, NW 93 rd Street and NW

More information

Madison BRT Transit Corridor Study Proposed BRT Operations Plans

Madison BRT Transit Corridor Study Proposed BRT Operations Plans Madison BRT Transit Corridor Study Proposed BRT Operations Plans This paper presents a description of the proposed BRT operations plan for use in the Madison BRT Transit Corridor Study. The objective is

More information

FEASIBILITY REPORT. 65 th STREET TRUNK WATER MAIN IMPROVEMENTS INVER GROVE HEIGHTS MINNESOTA DAKOTA COUNTY. October 2, 2017

FEASIBILITY REPORT. 65 th STREET TRUNK WATER MAIN IMPROVEMENTS INVER GROVE HEIGHTS MINNESOTA DAKOTA COUNTY. October 2, 2017 FEASIBILITY REPORT 65 th STREET TRUNK WATER MAIN IMPROVEMENTS INVER GROVE HEIGHTS MINNESOTA DAKOTA COUNTY October 2, 2017 Prepared for: City of Inver Grove Heights 8150 Barbara Avenue Inver Grove Heights,

More information

Energy Technical Memorandum

Energy Technical Memorandum Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter

More information

II. PROJECT DESCRIPTION

II. PROJECT DESCRIPTION II. PROJECT DESCRIPTION A. PROJECT APPLICANT The project applicants for the proposed Sepulveda/Rosecrans Site Rezoning are: Mar Ventures, Inc., 2050 West 190 th Street, Suite 108, Torrance, California,

More information

March 18, Samira Monshi Seungwon Noh Wilfredo Rodezno Brian Skelly

March 18, Samira Monshi Seungwon Noh Wilfredo Rodezno Brian Skelly March 18, 2013 Samira Monshi Seungwon Noh Wilfredo Rodezno Brian Skelly Overview Project Objective Stakeholder Feedback Review of Alternative Jet Fuel Supply Chain Options Under Consideration 2 Project

More information

Franklin County Engineer's Office - Highway Design ALKIRE RD & DEMOREST RD ROUNDABOUT CR NO. 11 & CR NO. 25 Bid Tabulation

Franklin County Engineer's Office - Highway Design ALKIRE RD & DEMOREST RD ROUNDABOUT CR NO. 11 & CR NO. 25 Bid Tabulation 7/07/2015 Page 1 of 20 Strawser Paving Co., Inc. Shelly & Sands, Inc. Double Z Construction Co Columbus Asphalt Paving, Inc. 1595 Frank Road P.O.Box 2469 2550 Harrison Road 1196 Technology Dr Columbus,

More information

City of Pacific Grove

City of Pacific Grove Regional Study Utilizing Caltrans Intersection Evaluation Section 7: City of Pacific Grove s: FIRST STREET AT CENTRAL AVENUE Transportation Agency for Monterey County Prepared by Transportation Agency

More information

STH 60 Northern Reliever Route Feasibility Study Report

STH 60 Northern Reliever Route Feasibility Study Report #233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development

More information

TABLE OF CONTENTS EXECUTIVE SUMMARY...1 INTRODUCTION...3 PROJECTED FUTURE GROWTH...3 ROADWAY IMPROVEMENT PROJECTS...4 POTENTIAL FUNDING SOURCES...

TABLE OF CONTENTS EXECUTIVE SUMMARY...1 INTRODUCTION...3 PROJECTED FUTURE GROWTH...3 ROADWAY IMPROVEMENT PROJECTS...4 POTENTIAL FUNDING SOURCES... Transportation Impact Fee Study September 2014 TABLE OF CONTENTS EXECUTIVE SUMMARY...1 INTRODUCTION...3 PROJECTED FUTURE GROWTH...3 ROADWAY IMPROVEMENT PROJECTS......4 POTENTIAL FUNDING SOURCES...7 PROPOSED

More information

BID FORM PART A. Total Quantity 1 LS $ - 2a Surveying, Layout, and Field Staking 1 LS $ - 2b Maintenance of Traffic 1 LS $ -

BID FORM PART A. Total Quantity 1 LS $ - 2a Surveying, Layout, and Field Staking 1 LS $ - 2b Maintenance of Traffic 1 LS $ - BID FORM PART A Name & Category Unit Unit Cost (B) Cost (AxB) GENERAL REQUIREMENTS 1 Mobilization (Maximum 3.0% of the total Contract Price) 1 LS $ - 2a Surveying, Layout, and Field Staking 1 LS $ - 2b

More information

Austin Constructors, LLC S FM N. Richey 9810 FM 969. Pasadena, TX Austin, TX 78724

Austin Constructors, LLC S FM N. Richey 9810 FM 969. Pasadena, TX Austin, TX 78724 National Power Rodding Corp. 9810 FM 969 Austin, TX 78724 Austin Constructors, LLC. 7907 S FM 973 Item No. Estimate Qty Unit of Issue Description Unit Price Total Unit Price Total Unit Price 103.1 125.00

More information

City of Houston Fondren Road Paving and Drainage

City of Houston Fondren Road Paving and Drainage City of Houston Fondren Road Paving and Drainage From Braeswood Boulevard to Creekbend Drive TRC Meeting March 2016 Location and Vicinity Maps City Council District K Key Map 530 Z, 530 Y Land Use Commercial

More information

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars.

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars. Sound Transit Phase 2 South Corridor LRT Design Report: SR 99 and I-5 Alignment Scenarios (S 200 th Street to Tacoma Dome Station) Tacoma Link Extension to West Tacoma Prepared for: Sound Transit Prepared

More information

RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE

RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE DULLES RAIL RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE ANALYSIS OF ALTERNATIVE AIRPORT ALIGNMENTS FOR METRORAIL AT WASHINGTON DULLES INTERNATIONAL AIRPORT MARCH 2011 PURPOSE This paper presents

More information

Ohio Department of Transportation Official Bid Tabulation James G. Beasley, P.E., P.S., Director

Ohio Department of Transportation Official Bid Tabulation James G. Beasley, P.E., P.S., Director Ohio Department of Transportation Official Bid Tabulation James G. Beasley, P.E., P.S., Director Project No. 080598 PID 21272 CUY-SR-237-4.93 - PART I (FRONT STREET); CUY-237-4.55 - P Federal Type: RAILROAD

More information

800 Access Control, R/W Use Permits and Drive Design

800 Access Control, R/W Use Permits and Drive Design Table of Contents 801 Access Control... 8-1 801.1 Access Control Directives... 8-1 801.2 Access Control Policies... 8-1 801.2.1 Interstate Limited Access... 8-1 801.2.2 Limited Access... 8-1 801.2.3 Controlled

More information

Maine Turnpike Authority

Maine Turnpike Authority Company Name Total Bid Amount Shaw Brothers Construction, Inc. - Gorham, ME $659,771.50 R J Grondin & Sons - Gorham, ME $690,828.50 Gendron & Gendron - Lewiston, ME $753,187.00 Gordon Contracting - Sangerville,

More information

BARRETT ROAD (C.R. 178) ROADWAY RESURFACING FROM LEWIS ROAD TO SPAFFORD ROAD IN OLMSTED TOWNSHIP, OHIO ITEMIZED UNIT PRICE BID ROADWAY

BARRETT ROAD (C.R. 178) ROADWAY RESURFACING FROM LEWIS ROAD TO SPAFFORD ROAD IN OLMSTED TOWNSHIP, OHIO ITEMIZED UNIT PRICE BID ROADWAY IZED PRICE BID DESCRIPTION PRICE BID ROADWAY 1 201 11000 CLEARING AND GRUBBING 1 - - LUMP 2 202 23000 PAVEMENT REMOVED NR SQ YD 20 3 202 35100 PIPE REMOVED, 24" AND UNDER NR FT 134 4 202 58000 MANHOLE

More information

NEW HAVEN HARTFORD SPRINGFIELD RAIL PROGRAM

NEW HAVEN HARTFORD SPRINGFIELD RAIL PROGRAM NEW HAVEN HARTFORD SPRINGFIELD RAIL PROGRAM Hartford Rail Alternatives Analysis www.nhhsrail.com What Is This Study About? The Connecticut Department of Transportation (CTDOT) conducted an Alternatives

More information

Traffic Management Plan and Queuing Analysis Lakehill Preparatory School Z Hillside Drive, Dallas, TX October 27, 2015

Traffic Management Plan and Queuing Analysis Lakehill Preparatory School Z Hillside Drive, Dallas, TX October 27, 2015 Traffic Management Plan and Queuing Analysis Lakehill Preparatory School Z145-235 2720 Hillside Drive, Dallas, TX October 27, 2015 Introduction: The Lakehill Preparatory School is located on the northeast

More information

The Airport s busiest months are October through May. There are NO sprinkled structures on the property - This includes the hangars

The Airport s busiest months are October through May. There are NO sprinkled structures on the property - This includes the hangars Frogmore International is a regional airport for public and limited commercial air traffic The airport is open daily 0700 to 1900 (7am-7pm) *Note: Airplanes can however takeoff/land 24hrs a day The airport

More information

TRAFFIC AND TRANSPORTATION TECHNICAL MEMORANDUM

TRAFFIC AND TRANSPORTATION TECHNICAL MEMORANDUM TRAFFIC AND TRANSPORTATION TECHNICAL MEMORANDUM for ENVIRONMENTAL ASSESSMENT US 460 Bypass Interchange and Southgate Drive Relocation State Project No.: 0460-150-204, P101, R201, C501, B601; UPC 99425

More information

Appendix C Preferred Solution

Appendix C Preferred Solution Appendix C Preferred Solution C.1 Conceptual Design Drawings C.2 Preferred Option Ideas and Inspiration C.3 Concept Renderings C.4 Cost Estimate Appendix C.1 Conceptual Design Drawings Plan View Brock

More information

Downtown Lee s Summit Parking Study

Downtown Lee s Summit Parking Study Downtown Lee s Summit Parking Study As part of the Downtown Lee s Summit Master Plan, a downtown parking and traffic study was completed by TranSystems Corporation in November 2003. The parking analysis

More information

Cost to extending KC Streetcar north approximately ½ mile

Cost to extending KC Streetcar north approximately ½ mile Technical Memorandum September 22, 2015 Attention: Jason Waldron, PE From: Lucas L. Olson, PE; Cory Imhoff, PE RE: Cost to extending KC Streetcar north approximately ½ mile HDR was asked for their opinion

More information

STREET IMPROVEMENTS PROPOSAL BID ITEMS

STREET IMPROVEMENTS PROPOSAL BID ITEMS STREET IMPROVEMENTS 1 Excavation 3,525 CY $ $ 2 A.C. Planing (2" to 4" Depth) 20,586 SY $ $ 3 Furnish & Install Asphalt Concrete 4,270 TON $ $ 4 Furnish & Install Aggregate Base 2,955 TON $ $ 5 Remove

More information

Durham-Orange County Corridor Alternatives Analysis JULY Prepared by: U R S Team

Durham-Orange County Corridor Alternatives Analysis JULY Prepared by: U R S Team Durham-Orange County Corridor Alternatives Analysis Volume 3: Capital Cost Estimates Operations and Maintenance Cost Estimates Travel Time and Distance Calculations Ridership Summaries and Station to Station

More information

VDOT Unused Facilities

VDOT Unused Facilities VDOT Unused Facilities Appropriation Act Item 457 K.1 (2010) Report to the Chairmen of House Appropriations and Senate Finance Committees Virginia Department of Transportation 1401 East Broad Street Richmond,

More information

Business Advisory Committee. July 7, 2015

Business Advisory Committee. July 7, 2015 Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

Interstate Drive Extension

Interstate Drive Extension Interstate Drive Extension Sponsor County Highway Project No. RB19-000004 Project Type New Road TOTAL FUNDING Total County Sponsor Federal $2,700,000.00 $2,150,000.00 Project Description This project continues

More information

Appendix G Aquilla Lake Pool Rise Recreational Resources

Appendix G Aquilla Lake Pool Rise Recreational Resources Appendix G Aquilla Lake Pool Rise Recreational Resources 1. INTRODUCTION The purpose of this appendix is to document the impacts of a 2.5 ft (Alternative A), 4.5 ft (Alternative B), and 6.5 ft. (Alternative

More information

KEEPING HOUSTON AIRPORTS OPENING DAY FRESH

KEEPING HOUSTON AIRPORTS OPENING DAY FRESH KEEPING HOUSTON AIRPORTS OPENING DAY FRESH Devon Tiner, P.E., PMP Assistant Director Asset Engineering June 9, 2016 VISION AND MISSION STATEMENT MISSION: WE EXIST TO CONNECT PEOPLE, BUSINESSES, CULTURES

More information

City of Peachtree City

City of Peachtree City City of Peachtree City Lake Peachtree Spillway Replacement City Council Update September 15, 2016 Project Team Integrated Science & Engineering 1 Spillway Alternatives Analysis Spillway Alternatives Evaluated

More information

Scope of Services January 26, Project Development and Conceptual Engineering for City of Lake Forest Amtrak Station

Scope of Services January 26, Project Development and Conceptual Engineering for City of Lake Forest Amtrak Station 203 North LaSalle Street, Suite 2100 Chicago, IL 60601 (312) 558-1345 Fax: (312) 346-9603 E-Mail: cquandel@quandelconsultants.com www.quandel.com Scope of Services January 26, 2010 Project Development

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

ADDITIONAL UTILITY RELOCATION COSTS ARE MISSING FROM THE ESTIMATE.

ADDITIONAL UTILITY RELOCATION COSTS ARE MISSING FROM THE ESTIMATE. Comment to CHSRA Missing Utility Costs Page!1 May 7, 2018 COMMENT FOR CHSRA BUSINESS PLAN: ADDITIONAL UTILITY RELOCATION COSTS ARE MISSING FROM THE ESTIMATE. HIGH VOLTAGE TOWERS THAT CARRY ELECTRICITY

More information

Traffic Engineering Study

Traffic Engineering Study Traffic Engineering Study Bellaire Boulevard Prepared For: International Management District Technical Services, Inc. Texas Registered Engineering Firm F-3580 November 2009 Executive Summary has been requested

More information

DIXIE TIP CONCEPT REPORT APPLICATION FY 2015 (Due November 6, 2013) PROJECT INFORMATION

DIXIE TIP CONCEPT REPORT APPLICATION FY 2015 (Due November 6, 2013) PROJECT INFORMATION DIXIE TIP CONCEPT REPORT APPLICATION FY 2015 (Due November 6, 2013) PROJECT INFORMATION 1) TITLE: Old Hwy 91 (Swiss Village, Santa Clara to 200 East, Ivins) 2) DESCRIPTION: This joint Ivins/Santa Clara

More information

SUBTOTAL SITE WORK & DEMOLITION (UTILITIES) $180, $348, $319,943.71

SUBTOTAL SITE WORK & DEMOLITION (UTILITIES) $180, $348, $319,943.71 BASE BID 1.00 GENERAL CONDITIONS 1.01 Mobilization (Maximum 5% of Base Bid) LS 1 84,000.00 $ 84,000.00 100,000.00 $ 100,000.00 85,000.00 $ 85,000.00 1.02 Bonding, Insurance, Permits (including Plumbing,

More information

Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan

Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan Valley Line West LRT Concept Plan Recommended Amendments Lewis Farms LRT Terminus Site Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan Lewis Farms LRT terminus site, 87 Avenue/West

More information

Executive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009.

Executive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009 Background As the Treasure Valley continues to grow, high-quality transportation connections

More information

City of Marina. Regional Roundabout Study Utilizing Caltrans Intersection Control Evaluation Section 4: Transportation Agency for Monterey County

City of Marina. Regional Roundabout Study Utilizing Caltrans Intersection Control Evaluation Section 4: Transportation Agency for Monterey County Regional Roundabout Study Utilizing Caltrans Intersection Control Evaluation Section 4: City of Marina Study Intersections: RESERVATION ROAD AT BEACH ROAD RESERVATION ROAD AT DEFOREST ROAD CARDOZA AVENUE

More information

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension Date of Meeting: July 20, 2017 # 6 BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM SUBJECT: ELECTION DISTRICT: CRITICAL ACTION DATE: STAFF CONTACTS: Design Endorsement for Sterling Boulevard Extension

More information

City of Grand Island Tuesday, February 13, 2018 Council Session

City of Grand Island Tuesday, February 13, 2018 Council Session City of Grand Island Tuesday, February 13, 2018 Council Session Item G-7 #2018-34 - Approving Certificate of Final Completion for the Construction of North Interceptor Phase I; Project No. 2012-S-6 Staff

More information

TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION

TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION DECEMBER 24 UPDATED

More information

Mercer Island Center for the Arts Parking Management Plan

Mercer Island Center for the Arts Parking Management Plan Parking Stalls Mercer Island Center for the Arts Parking Management Plan June 15, 2016 This Parking Management Plan (P) covers all tenants at the Mercer Island Center for the Arts (MICA) campus, including

More information

Cleary Rd and Belvedere Rd West Palm Beach, FL Great Centralized PB County location. Easy access to I-95 and Fl. Turnpike

Cleary Rd and Belvedere Rd West Palm Beach, FL Great Centralized PB County location. Easy access to I-95 and Fl. Turnpike and Belvedere Rd For more information contact: John Hoecker, CCIM, CPM, CSM President 5613668424 John@JupiterRealtyCompany.com Great Centralized PB County location. Easy access to I-95 and Fl. Turnpike

More information

ARTICLE 8 OFF-STREET PARKING AND PRIVATE DRIVEWAY STANDARDS

ARTICLE 8 OFF-STREET PARKING AND PRIVATE DRIVEWAY STANDARDS ARTICLE 8 OFF-STREET PARKING AND PRIVATE DRIVEWAY STANDARDS TABLE OF CONTENTS SECTION PAGE 8.1 GENERAL STANDARDS...8-2 8.2 PRIVATE DRIVEWAY PROVISIONS...8-4 8.3 OFF-STREET PARKING STANDARDS...8-5 8.4 OFF-STREET

More information

Fertilizer Type B 2 CWT $ $ $60.00 $ $60.00 $ Sod Water 60 MGAL $60.60 $3, $30.00 $1, $30.00 $1,

Fertilizer Type B 2 CWT $ $ $60.00 $ $60.00 $ Sod Water 60 MGAL $60.60 $3, $30.00 $1, $30.00 $1, BID TABS PROJECT 18-1029 22 nd AVENUE RECONSTRUCTION BID DATE: MAY 9, 2018 Stark Pavement Corp. Lalonde Contractors Cornerstone Pavers LLC Brookfield, WI Waukesha, WI Racine, WI Item Number Roadway Quantity

More information

FY 2013 Candidate Projects ($ Thousands) Street & Traffic Control Program - Thoroughfares

FY 2013 Candidate Projects ($ Thousands) Street & Traffic Control Program - Thoroughfares Need Area: NT032 Alternative No.: 1 Name: Drive Council District: G Limits: Dallas to Dickson Key Map No.: 492M Type: Major Thoroughfare and Collector Super Neighborhood: WBS No.: (To be assigned by the

More information

Offering Memorandum. 4333, 4375 and 4415 Bandini Boulevard Vernon, CA June Prepared by: Cresa

Offering Memorandum. 4333, 4375 and 4415 Bandini Boulevard Vernon, CA June Prepared by: Cresa Offering Memorandum 4333, 4375 and 4415 Bandini Boulevard Vernon, CA 90058 June 2015 Prepared by: Cresa Confidentiality Statement The information contained in the following Marketing Brochure is proprietary

More information

Subarea Study. Manning Avenue (CSAH 15) Corridor Management and Safety Improvement Project. Final Version 1. Washington County.

Subarea Study. Manning Avenue (CSAH 15) Corridor Management and Safety Improvement Project. Final Version 1. Washington County. Subarea Study Manning Avenue (CSAH 15) Corridor Management and Safety Improvement Project Final Version 1 Washington County June 12, 214 SRF No. 138141 Table of Contents Introduction... 1 Forecast Methodology

More information

Appendix C. Cost Estimates

Appendix C. Cost Estimates O Fallon Parks and Recreation Master Plan The cost estimates prepared for the ten year cost projections were estimated in 2010 US Dollars. The previous Implementation Strategies section of this Master

More information

Transit Vehicle (Trolley) Technology Review

Transit Vehicle (Trolley) Technology Review Transit Vehicle (Trolley) Technology Review Recommendation: 1. That the trolley system be phased out in 2009 and 2010. 2. That the purchase of 47 new hybrid buses to be received in 2010 be approved with

More information

RioVista. City of. Airfield STUDY

RioVista. City of. Airfield STUDY City of RioVista Airfield Electrical System Review STUDY Prepared for: City of Rio Vista March 2011 AIRFIELD ELECTRICAL SYSTEM REVIEW STUDY RIO VISTA MUNICIPAL AIRPORT RIO VISTA, CALIFORNIA Prepared for:

More information

Dulles Corridor Air Rights Study Investigation

Dulles Corridor Air Rights Study Investigation Dulles Corridor Air Rights Study Investigation Fairfax County Board of Supervisors Transportation Committee September 17, 2013 1 On March 19, 2013 the Fairfax County Board of Supervisors asked FCDOT staff

More information

APPENDIX C AIR QUALITY

APPENDIX C AIR QUALITY C.1 CONSTRUCTION APPENDIX C AIR QUALITY Construction activities associated with the Proposed Action are set to begin July 2020 and be completed by May 2023. Potential sources of construction emissions

More information

TRAFFIC PARKING ANALYSIS

TRAFFIC PARKING ANALYSIS TRAFFIC PARKING ANALYSIS NAPA FLEA MARKET COUNTY OF NAPA Prepared for: Tom Harding Napa-Vallejo Flea Market 33 Kelly Road American Canyon, CA 9453 Prepared by: 166 Olympic Boulevard, Suite 21 Walnut Creek,

More information

Rosedale Sanitary Sewer Feasibility Review Report

Rosedale Sanitary Sewer Feasibility Review Report Rosedale Sanitary Sewer Feasibility Review Report Submitted by: WEDLER ENGINEERING LLP 201 9300 Nowell Street Chilliwack BC V2P 4V7 Phone: 604 792 0651 Wedler File No: C13 5032/A December 6, 2013 STATEMENT

More information

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design Presented at the 2018 Transmission and Substation Design and Operation Symposium Revision presented at the

More information