ALTERNATIVE PROJECT DELIVERY

Size: px
Start display at page:

Download "ALTERNATIVE PROJECT DELIVERY"

Transcription

1 ALTERNATIVE PROJECT DELIVERY Varuna Singh

2 SH 288 IN HARRIS COUNTY

3 SH 288 in Harris County SEGMENT 1: 8 New Tolled Direct Connectors at SH 288 and Beltway 8 Existing traffic uses frontage roads today to travel between these two facilities Both SH 288 general purpose lanes and managed toll lanes will be able to access new tolled DCs 4 New Managed Toll Lanes (2 in each direction)

4 SH 288 in Harris County SEGMENTS 2 & 3: 4 New Managed Toll Lanes (2 in each direction)

5 SH 288 in Harris County SEGMENT 4: Full Reconstruction of existing nontoll 8 Direct Connectors Both SH 288 general purpose and managed toll lanes can access nontoll DCs Full Reconstruction of Holly Hall St over SH New Managed Toll Lanes (2 in each direction)

6 SH 288 in Harris County SEGMENT 5: 2 New Tolled Direct Connectors in/out of Texas Medical Center 4 New Managed Toll Lanes (2 in each direction)

7 SH 288 in Harris County SEGMENT 6: 4 New Tolled Managed Lanes (2 in each direction) Full Reconstruction of Southmore Blvd over SH New Managed Toll Lanes (2 in each direction)

8 SH Project Team Structure Owner: Texas Department of Transportation (TxDOT) Developer: Blueridge Transportation Group, LLC (BTG) ACS Infrastructure Development, Inc. 21.6% InfraRed Capital Partners 21.6% Shikun & Binui Concessions USA, Inc. 21.6% Northleaf Capital Partners 18% Clal Insurance 12.1% Star America Infrastructure Partners 5% Lead Contractor: Almeda-Genoa Constructors (A-GC) Dragados USA 30% Pulice Construction, Inc. 20% Shikun & Binui America Inc. 50% Lead Design Engineering Firm: Stantec (formerly KBR) Operations &Maintenance: Roy Jorgensen Co.

9 SH Project Costs & Funding Capital Costs Funding Sources Design & Construction $802,340,050 CDA Developer 1 $798,411,339 Utilities $1,066,007 TxDOT via Concession Payment 2 $3,680,000 Right-of-Way $12,105,282 TxDOT via Category 12 $13,420,000 Sub-total $815,511,339 Sub-total $815,511,339 Change Orders $1,973,968 TxDOT via Category 3 (PROP12) $3,952,972 Hazardous Material Remediation $1,979,004 Sub-total $3,952,972 TOTAL $819,464,311 TOTAL $819,464,311 Note 1: Comprised of TIFIA Loan, Bonds and Equity Note 2: Total Developer Concession Payment to TxDOT was $25.48M

10 SH 288 in Harris County - Milestones March 4, 2016: Contract Executed May 9, 2016: Developer achieved Financial Close October 25, 2016: Notice to Proceed 2 Issued START of 1000 days/33 months completion deadline As of today, March 28, 2018: 519 of 1000 days elapsed (52% of project time) Design: over 95% complete Construction: over 27% complete July 22, 2019: Substantial Completion END of 1000 days/33 months completion deadline, project opens to traffic

11 SH 288 Managed Lanes Project (P3 Concession CDA)

12 SH 249 CORRIDOR

13 SH 249 Corridor Segment 1: 14 miles Owner: TxDOT Scope: 4 toll lanes from FM 1774 near Pinehurst to FM 1774 near Todd Mission (2 lanes in each direction)

14 SH 249 Corridor Segment 1: 14 miles Owner: TxDOT Scope: 4 toll lanes from FM 1774 near Pinehurst to FM 1774 near Todd Mission (2 lanes in each direction) Segment 2: 10 miles Owner: TxDOT Scope: 2 non-tolled lane configuration for entire limits (1 lane in each direction)

15 SH 249 Corridor Segment 3: 3 miles Owner: Montgomery County Toll Road Authority Adds 4 toll lanes within existing non-toll frontage roads from Harris/Montgomery County Line to FM 1774 in Pinehurst

16 SH 249 Corridor Segment 3: 3 miles Owner: Montgomery County Toll Road Authority Adds 4 toll lanes within existing non-toll frontage roads from Harris/Montgomery County Line to FM 1774 in Pinehurst Segment 4: 1.5 miles Owner: Harris County Toll Road Authority Adds 6 toll lanes within existing non-toll frontage roads from FM 2920 to Harris/Montgomery County Line

17 SH Milestones October 4, 2017: Contract Execution (NTP1) Base & Option 1 Segment 1 + Segment 2 Segment 1 October 25, 2017: Limited NTP2 for ROW Clearing January 10, 2018: Limited Design NTP2 March 15, 2018: Full NTP2 (Anticipated) July 10, 2020: Substantial Completion 1,010 days (33 months) after NTP1

18 SH Milestones Segment 2 June 15, 2018: Limited Design NTP2 (Anticipated) October 15, 2018: Limited Construction NTP2 (Anticipated) January 15, 2019: Full NTP2 (Anticipated) Dependent on USACE Nationwide Permit March 20, 2022: Substantial Completion 1,160 days (38 months) after NTP2

19 SH Current Status Segment 1 is at 60% overall design for earthwork, drainage, retaining walls, and bridges. Design for Segment 1 is anticipated to be completed by July Design has started on several utility re-locations. All utility relocations are anticipated to be completed by the end of 2018.

20 SH 249 at FM 1488 From South Looking North

21 SH 249 Public Information For information about the project, please contact the Public Information Team: Hotline: TX-SH249 Public Information Office located at Landmark Building FM 1488, Magnolia, TX 77354

22 SH 99 GRAND PKWY SEGMENTS H&I

23 SH 99 Segments H&I Design-Build SCOPE: Segments H and I-1 (37.5 miles) I-69/US 59 to I-10E New 2 to 4 toll lane facility Segment I-2A (8.7 miles) I-10E to FM 1405 Existing 4-lane toll facility Upgrades to ITS and tolling equipment Segment I-2B (6.5 miles) FM 1405 to SH 146 New 4 toll lane facility TOTAL Length: 52.7 miles

24 SH 99 Segments H&I Current Status Design: 7% complete Right-of-Way: (in addition to existing ROW in early construction areas below) Total Parcel Count to be acquired: 220 Parcel Count currently available for construction: 6 Parcel County not yet available for construction: 214 Utility Relocations: Approximately 60 utility owners involved Approximately 320 adjustments needed Construction: early work areas Northern project limits: I-69/US 59 interchange to Loop 494(1.6 miles) Southern project limits: Cedar Bayou to SH 146 (3.3 miles) 24

25 SH 99 Segments H&I - Milestones June 30, 2017: Contract Executed October 27, 2018: NTP2 and H-West Option Issued August 2018: Start of Construction August 2019: Anticipated completion of design Late 2019: Anticipated access to all parcels for construction Mid 2020: Anticipated relocations of all utilities February 2022: Substantial Completion 1,674 days (56 months) after NTP1

26 SH 99 Segments H&I Public Information For information about the project, please contact the Public Information Team: Hotline: Public Information Office located at: Wachter Building 7560 FM 1960, Dayton, TX 77535

27 NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP)

28 NHHIP OVERVIEW Environmental Impact Statement (EIS) Project divided into 3 Segments: 45 Segment 1: Beltway 8 to I-610 (9 mi) Segment 2: I-610 to I-10 (3 mi) Segment 3: Downtown Loop System (12.3 mi) Goal: provide a safer facility with additional capacity for projected demand by incorporating transit opportunities, travel demand strategies, and flexible operations One Proposed Recommended Alternative per segment = single corridor end to end (24 mi total)

29 SEGMENT 3: PROPOSED RECOMMENDED ALTERNATIVE Segment 1 Segment 2 Segment 3 29

30 NHHIP - Milestones Summer 2017: Public Hearings Held Summer 2018: Issue Design-Build RFQ for Segment 3 Fall 2018: Shortlist Design-Build Proposers for Segment 3 Late 2018: Anticipated Record of Decision (all 3 segments) Early 2019: Issue Design-Build RFP for Segment 3 Mid 2019: Receive Design-Build Proposals for Segment 3 Late Summer 2019: Conditional Award Design-Build Segment 3 Fall 2019 to Late 2019: Design-Build Contract Execution for Segment 3 Spring 2020: Design and early construction

31 NHHIP Houston District Resources & Questions Quincy Allen, P.E. TxDOT Houston District Engineer (713) / quincy.allen@txdot.gov Raquelle Lewis TxDOT Houston District PIO (713) / raquelle.lewis@txdot.gov Pat Henry, P.E. TxDOT Houston District Director for Advance Project Development (713) / pat.henry@txdot.gov Varuna Singh, P.E. TxDOT Houston District Director for Alternative Project Delivery (713) / varuna.singh@txdot.gov

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018 NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3 April 19, 2018 NHHIP OVERVIEW NHHIP divided into 3 Segments: Segment 1: I-45: Beltway 8 to I-610 (9 mi) 45 Segment 2: I-45: I-610 to I-10 (3

More information

TXDOT PLANNING CONFERENCE. Quincy D. Allen, P.E. Houston District Engineer June 16, 2016

TXDOT PLANNING CONFERENCE. Quincy D. Allen, P.E. Houston District Engineer June 16, 2016 TXDOT PLANNING CONFERENCE Quincy D. Allen, P.E. Houston District Engineer June 16, 2016 Welcome to Houston Show video...http://youtu.be/knchpl8sdfu Population Growth in Texas Texas added 1.3 million people

More information

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP)

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP) NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP) Project Overview Briefing Packet March 2017 PROJECT OVERVIEW Environmental Impact Statement (EIS) Project divided into 3 Segments Segment 1: Beltway 8

More information

SH 249 IN GRIMES COUNTY. Open House April 3, 2014

SH 249 IN GRIMES COUNTY. Open House April 3, 2014 SH 249 IN GRIMES COUNTY Open House April 3, 2014 Meeting Agenda Purpose of Meeting Today: Review the purpose and need for the SH 249 Grimes County project Review the proposed project and alternatives Discuss

More information

SH 249 PUBLIC MEETING DESIGN CHANGES FROM FM 2920 TO HARDIN STORE ROAD

SH 249 PUBLIC MEETING DESIGN CHANGES FROM FM 2920 TO HARDIN STORE ROAD SH 249 PUBLIC MEETING DESIGN CHANGES FROM FM 2920 TO HARDIN STORE ROAD Lone Star College, Tomball Campus December 8, 2015 Open House 5:30-7:30 pm National Environmental Policy Act The environmental review,

More information

I-820 (East) Project Description. Fort Worth District. Reconstruct Southern I-820/SH 121 Interchange

I-820 (East) Project Description. Fort Worth District. Reconstruct Southern I-820/SH 121 Interchange I-820 (East) Project Description Fort Worth District Reconstruct Southern I-820/SH 121 Interchange I-820 from approximately 2,000 feet north of Pipeline Road/Glenview Drive to approximately 3,200 feet

More information

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015 SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment

More information

PUBLIC INFRASTRUCTURE PROJECTS

PUBLIC INFRASTRUCTURE PROJECTS PUBLIC INFRASTRUCTURE PROJECTS FM 664 / OVILLA ROAD WIDENING & IMPROVEMENTS FM 664 / OVILLA ROAD CONNECTS US 287 WITH I-45 (SOURCE: TEXAS DEPARTMENT OF TRANSPORTATION. 2016 FM 664 / OVILLA ROAD WIDENING

More information

US 67 WIDENING PROJECT

US 67 WIDENING PROJECT US 67 WIDENING PROJECT From Belt Line Rd. to I-20 History & Background The US 67 improvements from Belt Line Rd to I-20 were originally part of TxDOT s Southern Gateway project, studied as part of the

More information

STATE LOOP 195 PUBLIC MEETING. Footer Text

STATE LOOP 195 PUBLIC MEETING. Footer Text STATE LOOP 195 PUBLIC MEETING STATE LOOP 195 From FM 755 to 1 mile west of Loma Blanca Rd Public Meeting Agenda Welcome & Introductions Octavio Saenz TxDOT Public Information Officer Technical Overview

More information

Crenshaw/LAX Transit Corridor. Transit Coalition Meeting June 26, 2012

Crenshaw/LAX Transit Corridor. Transit Coalition Meeting June 26, 2012 Transit Coalition Meeting June 26, 2012 Measure R Projects 8 ½ mile light rail line from Exposition/Crenshaw Blvds. to Metro Green Line s Aviation/LAX station Six stations with two optional stations carried

More information

Proposed Project I 35 Improvements from SH 195 to I 10

Proposed Project I 35 Improvements from SH 195 to I 10 I 35 ROADWAY Proposed Project I 35 Improvements from SH 195 to I 10 The existing I 35 facility from State Highway 195 (SH 195) north of Georgetown to Interstate 10 (I 10) in San Antonio varies from four

More information

TURNPIKE SYSTEM. Summary information from: Texas Department of Transportation GENERAL INFORMATION & SYSTEM MAP JOA REALTY

TURNPIKE SYSTEM. Summary information from: Texas Department of Transportation   GENERAL INFORMATION & SYSTEM MAP JOA REALTY GENERAL INFORMATION & SYSTEM MAP TURNPIKE SYSTEM Summary information from: Texas Department of Transportation www.texastollways.com Joa Realty JoaRealty.com Email: help@joarealty.com Office: 512.480.8384

More information

MAP OR PHOTO. Public Meeting & Open House July 23, Project Roadway Limits From: FM 1957 To: FM 471. Counties Bexar & Medina

MAP OR PHOTO. Public Meeting & Open House July 23, Project Roadway Limits From: FM 1957 To: FM 471. Counties Bexar & Medina Public Meeting & Open House July 23, 2013 Project Roadway Limits From: FM 1957 To: FM 471 MAP OR PHOTO Counties Bexar & Medina 1 I. Project History II. III. IV. Project Overview Project Alternatives Response

More information

Corridor Management Committee. March 7, 2012

Corridor Management Committee. March 7, 2012 Corridor Management Committee March 7, 2012 2 Today s Topics SWLRT Project Office Update Engineering Services Procurement Update Legislative Leadership Tour Annual New Starts Report Update on Proposed

More information

SOUTH TEXAS COMMISSION MEETING

SOUTH TEXAS COMMISSION MEETING SOUTH TEXAS COMMISSION MEETING September 26, 2013 Pharr District Commission Meeting Pharr District: Overview The Pharr District plans, designs, builds, operates and maintains the state transportation system

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate

More information

S.M. Wright Project (I-45, US 175, SH 310) and Road to Work Opportunity Program. Transportation and Trinity River Project Committee May 23, 2016

S.M. Wright Project (I-45, US 175, SH 310) and Road to Work Opportunity Program. Transportation and Trinity River Project Committee May 23, 2016 635 S.M. Wright Project (I-45, US 175, SH 310) and Road to Work Opportunity Program Transportation and Trinity River Project Committee May 23, 2016 Project Scope Increase safety by removing the existing

More information

Janice Fortunato Senior Director Business Partnerships

Janice Fortunato Senior Director Business Partnerships Janice Fortunato Senior Director Business Partnerships What are Megaprojects? They are large-scale projects distinguished by cost, complexity and the potential impact on the community. Collectively, these

More information

W&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237)

W&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) W&OD TRAIL BRIDGE OVER LEE HIGHWAY A COMPONENT OF THE I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) October 11, 2018 Bill Cuttler, PE

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Laura Cornejo, DEO Regional Planner Regional Operator Metro is LA County s Regional Builder/Funder Rail Bus Service (Metro/Muni/Local)

More information

Alternatives Analysis Findings Report

Alternatives Analysis Findings Report 6.0 This chapter presents estimates of the potential capital, operations and maintenance costs associated with the alternatives carried forward for detailed evaluation. The methodology used to develop

More information

Wentzville Parkway South Phase 2 & 2A

Wentzville Parkway South Phase 2 & 2A Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total

More information

METRO CNG Program Phase I Update. Customer Service Committee April 2014

METRO CNG Program Phase I Update. Customer Service Committee April 2014 METRO CNG Program Phase I Update Customer Service Committee April 2014 METRO CNG Program Background Bus purchase Short term solutions Long term plans Bus purchase options 2 METRO CNG Program April 2011

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 9/8/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

WARES. October, 2018

WARES. October, 2018 WARES October, 2018 1 Project Overview A new 16 mile east-west light rail line between Bethesda in Montgomery County and New Carrollton in Prince George s County Operates mostly on the surface with 21

More information

system performance I-820 East Loop FM 156 TxDOT is working to expand its busiest metropolitan corridors.

system performance I-820 East Loop FM 156 TxDOT is working to expand its busiest metropolitan corridors. system performance TxDOT is working to expand its busiest metropolitan corridors. Nine of the state s 100 most congested highways are located in Tarrant County. Six of these highways will be expanded and

More information

CONVERSION OF TWO-WAY FRONTAGE ROADS TO ONE-WAY

CONVERSION OF TWO-WAY FRONTAGE ROADS TO ONE-WAY CONVERSION OF TWO-WAY FRONTAGE ROADS TO ONE-WAY IH 30 in Texarkana Introduction Video Texarkana Two cities Two states One MPO Texarkana IH 30 U.S. Post Office and Court House IH 30 Corridor IH 30 constructed

More information

US 59 (SOUTHWEST FWY) IH 610 (West Loop) to SH 288 (South Fwy)

US 59 (SOUTHWEST FWY) IH 610 (West Loop) to SH 288 (South Fwy) Mobility Investment Priorities Project Houston US 59 US 59 (SOUTHWEST FWY) IH 610 (West Loop) to SH 288 (South Fwy) Current Conditions From IH 610 West to SH 288, US 59 operates with four or five lanes

More information

IH 45 (GULF FWY) IH 10 (Katy Fwy) to IH 610 S (South Loop) 2010 Rank: Rank: 12

IH 45 (GULF FWY) IH 10 (Katy Fwy) to IH 610 S (South Loop) 2010 Rank: Rank: 12 Mobility Investment Priorities Project Houston IH 45 IH 45 (GULF FWY) IH 10 (Katy Fwy) to IH 610 S (South Loop) Current Conditions From IH 10 to IH 610 south, IH 45 is a 6- to 9-lane facility with three

More information

PORTS-TO-PLAINS. Corridor Planning. Ports-to-Plains Stakeholder Meeting

PORTS-TO-PLAINS. Corridor Planning. Ports-to-Plains Stakeholder Meeting PORTS-TO-PLAINS Corridor Planning Stakeholder Workshop - Agenda 1 Purpose of Stakeholder Workshops 3 2 Rural Transportation System Overview 4 3 Ports-to-Plains 8 4 5 6 7 I-27 Expansion Key Considerations

More information

PUBLIC MEETING. Bear Creek Park Community Center. January 24, :30 pm to 7:30 pm

PUBLIC MEETING. Bear Creek Park Community Center. January 24, :30 pm to 7:30 pm PUBLIC MEETING Bear Creek Park Community Center January 24, 2017 5:30 pm to 7:30 pm PURPOSE OF THE MEETING This is an open House No formal presentation Introduce the project to the public Present existing

More information

SEPULVEDA PASS CORRIDOR

SEPULVEDA PASS CORRIDOR SEPULVEDA PASS CORRIDOR PUBLIC PRIVATE PARTNERSHIP DELIVERY PRE-DEVELOPMENT AGREEMENT PDA Sepulveda Pass Mobility Issues Most congested highway segment in the U.S. 295,000 vehicles per day (2010) 430,000

More information

US 81 Bypass of Chickasha Environmental Assessment Public Meeting

US 81 Bypass of Chickasha Environmental Assessment Public Meeting US 81 Bypass of Chickasha Environmental Assessment Public Meeting March 14, 2013 Introductions ODOT FHWA SAIC Meeting Purpose Present need for bypass Provide responses to 10/04/11 public meeting comments

More information

District-Wide Prop 39, Interior LED Lighting Upgrades Pre-Conference Meeting Re-Bid No January 9 at 10:00 AM Las Positas College

District-Wide Prop 39, Interior LED Lighting Upgrades Pre-Conference Meeting Re-Bid No January 9 at 10:00 AM Las Positas College January 9 at 10:00 AM Las Positas College AGENDA I. Welcome & Introduction II. Project Overview III. Site, Constraints & Challenges IV. Bid Document Summary V. Bid Schedule II. Project Overview A. Project

More information

Board of Directors authorization is required for all goods and services contracts obligating TriMet to pay in excess of $500,000.

Board of Directors authorization is required for all goods and services contracts obligating TriMet to pay in excess of $500,000. Date: April 11, 2012 To: From: Board of Directors Neil McFarlane Subject: RESOLUTION 12-04-30 OF THE TRI-COUNTY METROPOLITAN TRANSPORTATION DISTRICT OF OREGON (TRIMET) AUTHORIZING A CONTRACT WITH SIEMENS

More information

Mobility 2045 Plan Workshop

Mobility 2045 Plan Workshop Mobility 2045 Plan Workshop Regional Transportation Council October 12, 2017 Agenda Mobility Planning Mobility 2045 Innovative Funding and Strategic Partnerships Public Outreach Efforts Next Steps 2 Mobility

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 2/19/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

Purple Line Light Rail P3 Project

Purple Line Light Rail P3 Project Purple Line Light Rail P3 Project TPB Meeting May 18, 2016 1 Topics General Project Overview The P3 Contract Details on The Successful Proposal 2 Recap of Purple Line P3 Events In November 2013 MTA initiated

More information

Metro Highway Program

Metro Highway Program Metro Highway Program ACEC November 2018 I-5 North HOV and Truck Lanes 14 miles of HOV lanes in both directions 2 miles of truck climbing lanes at the south end 7 bridge modifications at: Gavin Canyon

More information

Program. presented by: September 22, 2010

Program. presented by: September 22, 2010 Minnesota s s High Speed Passenger Rail Program presented by: Minnesota Department of Transportation September 22, 2010 Presentation Overview State Rail Plan National High Speed Rail Initiatives Passenger

More information

Transit Project Delivery Status Report. Significant Issues

Transit Project Delivery Status Report. Significant Issues Item 1 Transit Project Delivery Status Report Significant Issues Presented By K.N. Murthy Executive Director Construction Committee 1 I-405 Sepulveda Pass Closure Construction Committee I-405 Sepulveda

More information

I-10 West AA/EIS Pre-Screening and Tier 1 Analysis Results. Public Meeting. Wulf Grote, Director Project Development Rick Pilgrim, Project Manager

I-10 West AA/EIS Pre-Screening and Tier 1 Analysis Results. Public Meeting. Wulf Grote, Director Project Development Rick Pilgrim, Project Manager I-10 West AA/EIS Pre-Screening and Tier 1 Analysis Results Public Meeting Wulf Grote, Director Project Development Rick Pilgrim, Project Manager March 4 & 5, 2008 Today s Agenda Overview of Alternatives

More information

congestion management program

congestion management program congestion management program 2550 Rail Vehicle Program March 2012 11-0319tr 2010 lacmta Q U A R T E R LY P R O J E C T S TAT U S R E P O R T 255O RAIL VEHICLE PROGRAM QUARTERLY PROJECT STATUS REPORT THE

More information

Open House. Highway212. Meetings. Corridor Access Management, Safety & Phasing Plan. 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition

Open House. Highway212. Meetings. Corridor Access Management, Safety & Phasing Plan. 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition Welcome Meetings 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition 6:30 to 8:00 p.m. - Open House Why is Highway 212 Project Important? Important Arterial Route Local Support Highway 212

More information

Utility work, road construction substantially done on Fourth Street

Utility work, road construction substantially done on Fourth Street November 2010 Fourth Street in downtown is reopen to vehicle traffic between Minnesota and Broadway streets. Utility relocation and road construction are substantially complete there. Utility work, road

More information

DART Priorities Overview

DART Priorities Overview City of Dallas Transportation and Trinity River Project Committee DART Priorities Overview Gary C. Thomas President/Executive Director August 10, 2015 City of Dallas Transportation & Trinity River Committee

More information

Business Advisory Committee. July 7, 2015

Business Advisory Committee. July 7, 2015 Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS

More information

Maryland Gets to Work

Maryland Gets to Work I-695/Leeds Avenue Interchange Reconstruction Baltimore County Reconstruction of the I-695/Leeds Avenue interchange including replacing the I-695 Inner Loop bridges over Benson Avenue, Amtrak s Northeast

More information

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What

More information

South Dallas-Waxahachie Corridor Strategy Meeting. June 2, 2009

South Dallas-Waxahachie Corridor Strategy Meeting. June 2, 2009 South Dallas-Waxahachie Corridor Strategy Meeting June 2, 2009 Project Mission Provide additional transportation choices connecting major activity centers in Dallas County and Ellis County by efficiently

More information

I-4 Beyond the Ultimate. Florida Transportation Builders Association January 18, 2019

I-4 Beyond the Ultimate. Florida Transportation Builders Association January 18, 2019 I-4 Beyond the Ultimate Florida Transportation Builders Association January 18, 2019 FDOT District 5 Improving Mobility & Safety in Central Florida FDOT District 5 is: Designing and building a better Interstate

More information

2/1/2018. February 1, Item #1 CITIZENS PARTICIPATION

2/1/2018. February 1, Item #1 CITIZENS PARTICIPATION February 1, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments

More information

WOODVILLE HIGHWAY (SR 363) PD&E STUDY From Capital Circle Southeast To Paul Russell Road FPID NUMBER: Public Hearing

WOODVILLE HIGHWAY (SR 363) PD&E STUDY From Capital Circle Southeast To Paul Russell Road FPID NUMBER: Public Hearing WOODVILLE HIGHWAY (SR 363) PD&E STUDY From Capital Circle Southeast To Paul Russell Road FPID NUMBER: 424009-3 Public Hearing May 9, 2013 This Public Hearing is being held in accordance with the Federal-aid

More information

Public Information Workshop

Public Information Workshop Public Information Workshop Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 29, 2018 Welcome to the Public Information Workshop for Harborview Road Project Development and Environment (PD&E)

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.5 SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY DIVISION: Capital Programs & Construction BRIEF DESCRIPTION: Awarding San Francisco Municipal Transportation Agency

More information

Agenda. Utility Undergrounding Strategies & Laguna Canyon Road Master Plan

Agenda. Utility Undergrounding Strategies & Laguna Canyon Road Master Plan Utility Undergrounding Strategies & Laguna Canyon Road Master Plan January 17, 2017 City Council Meeting 2 Agenda Progress since March 2016 Status of undergrounding and road widening between El Toro Rd.

More information

Committee Report. Transportation Committee. Business Item No

Committee Report. Transportation Committee. Business Item No Committee Report Business Item No. 2015-280 Transportation Committee For the Metropolitan Council meeting of December 9, 2015 Subject: METRO Blue Line Extension (Bottineau Light Rail Transit) Revised Scope

More information

US 50/SOUTH SHORE COMMUNITY REVITALIZATION PROJECT

US 50/SOUTH SHORE COMMUNITY REVITALIZATION PROJECT US 50/SOUTH SHORE COMMUNITY REVITALIZATION PROJECT April 25, 2012 Tahoe Transportation District (TTD) Tahoe Transportation District (TTD) established 1980 as Bi-State Agency TTD Goals Implement Transportation

More information

Making Mobility Better, Together

Making Mobility Better, Together Making Mobility Better, Together Austin Transportation Department Gordon Derr, P.E., for Robert J. Spillar, P.E Director, Austin Transportation Department 1 AUSTIN TRANSPORTATION DEPARTMENT Our Mission

More information

CPG is pleased to report the following accomplishments this quarter:

CPG is pleased to report the following accomplishments this quarter: MEMORANDUM To: From: Metrolinx Board of Directors Matthew Clark Chief Capital Officer (A), Capital Projects Group Date: February 7, 2019 Re: Capital Projects Group Quarterly Report Recommendation That

More information

INDIANA DEPARTMENT OF TRANSPORTATION PAGE 1 NOTICE TO HIGHWAY CONTRACTORS

INDIANA DEPARTMENT OF TRANSPORTATION PAGE 1 NOTICE TO HIGHWAY CONTRACTORS INDIANA DEPARTMENT OF TRANSPORTATION PAGE 1 NOTICE TO HIGHWAY CONTRACTORS DATE OF LETTING: March 04, 2015 TIME OF LETTING: 10:00 AM EASTERN STD DESIGN BUILD CONTRACTS Sealed proposals for certain highway

More information

CONNECTED AND AUTOMATED TRANSPORTATION AND THE TEXAS AV PROVING GROUNDS PARTNERSHIP

CONNECTED AND AUTOMATED TRANSPORTATION AND THE TEXAS AV PROVING GROUNDS PARTNERSHIP CONNECTED AND AUTOMATED TRANSPORTATION AND THE TEXAS AV PROVING GROUNDS PARTNERSHIP Christopher Poe, Ph.D., P.E. Assistant Director, Connected and Automated Transportation Strategy Texas A&M Transportation

More information

EUROPEAN MANUFACTURER OPENS NEW HIGH-TECH FACILITY IN ARKANSAS TO SERVE PLAINS & EASTERN CLEAN LINE

EUROPEAN MANUFACTURER OPENS NEW HIGH-TECH FACILITY IN ARKANSAS TO SERVE PLAINS & EASTERN CLEAN LINE MEDIA CONTACT Sarah Bray Jason Brown Clean Line Energy The Communications Group 832.319.6340 office 501.376.8722 office 832.226.2116 cell 501.515.0849 cell sbray@cleanlineenergy.com jbrown@comgroup.com

More information

Broward County Intermodal Center And People Mover. AASHTO Value Engineering Conference Presentation. September 1, 2009 San Diego, CA

Broward County Intermodal Center And People Mover. AASHTO Value Engineering Conference Presentation. September 1, 2009 San Diego, CA Project Development & Environment Study Broward County Intermodal Center And People Mover AASHTO Value Engineering Conference Presentation September 1, 2009 San Diego, CA Background P D & E Study Regional

More information

Road User Cost Analysis

Road User Cost Analysis Road User Cost Analysis I-45 Gulf Freeway at Beltway 8 Interchange CSJ #500-03-382 1994 Texas Transportation Institute ROAD USER COST ANALYSIS CSJ #500-03-382 The Texas Department of Transportation (TxDOT)

More information

Request for Statements of Qualification Gardnerville Station (Eagle Gas Station Redevelopment Project) 1395 Highway 395 N Gardnerville, NV

Request for Statements of Qualification Gardnerville Station (Eagle Gas Station Redevelopment Project) 1395 Highway 395 N Gardnerville, NV Gardnerville Station (Eagle Gas Station Redevelopment Project) 1395 Highway 395 N Gardnerville, NV Issued: Monday, Site Tour: Friday, January 30, 2015 at 10:00 a.m. Submittal Deadline: 5:00 p.m. on Friday,

More information

Delivering the North West Rail Link. Colin Rudd, Deputy Project Director, NWRL David Polkinghorne, Design Team Leader, TJHD

Delivering the North West Rail Link. Colin Rudd, Deputy Project Director, NWRL David Polkinghorne, Design Team Leader, TJHD Delivering the North West Rail Link Colin Rudd, Deputy Project Director, NWRL David Polkinghorne, Design Team Leader, TJHD November 26, 2013 The starting point Project overview $8.3 billion budget Open

More information

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension

BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension Date of Meeting: July 20, 2017 # 6 BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM SUBJECT: ELECTION DISTRICT: CRITICAL ACTION DATE: STAFF CONTACTS: Design Endorsement for Sterling Boulevard Extension

More information

Waco Rapid Transit Corridor (RTC) Feasibility Study

Waco Rapid Transit Corridor (RTC) Feasibility Study Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM

More information

KANSAS CITY STREETCAR

KANSAS CITY STREETCAR KANSAS CITY STREETCAR KAREN CLAWSON MID-AMERICA REGIONAL COUNCIL KANSAS CITY STREETCAR Regional Context Alternatives Analysis Kansas City Streetcar Project KANSAS CITY REGION KANSAS CITY REGION KANSAS

More information

Metropolitan Domestic Water Improvement District Board of Directors Meeting. August 8, July 2011 Report

Metropolitan Domestic Water Improvement District Board of Directors Meeting. August 8, July 2011 Report Metropolitan Domestic Water Improvement District Synopsis The purpose of this agenda item is to provide the Board with an update of the District s activities for the past month. This is not an action item,

More information

Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study

Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study FROM MICHIGAN AVENUE TO INDUSTRY ROAD BREVARD COUNTY, FLORIDA Financial Project ID No: 433605-1-22-01 Federal Aid Project

More information

MDOT Metro Region. Jim Schultz, P.E. Manager of Planning

MDOT Metro Region. Jim Schultz, P.E. Manager of Planning MDOT Metro Region Jim Schultz, P.E. Manager of Planning Presentation Overview Part 1: I-75 Reconstruction Monroe County Part 2: Gordie Howe International Bridge Part 3: M1 Rail Streetcar Project I-75 Reconstruction

More information

Project Scoping Report Appendix B Project Web Site. APPENDIX B Project Web Site

Project Scoping Report Appendix B Project Web Site. APPENDIX B Project Web Site Project Scoping Report Appendix B Project Web Site APPENDIX B Project Web Site WESTSIDE EXTENSION TRANSIT CORRIDOR STUDY February 4, 2008 News and Info of 1 http://metro.net/projects_programs/westside/news_info.htm#topofpage

More information

Basic Project Information

Basic Project Information FY 2015-16 PROJECT DESCRIPTION FORM (7B) Submitting Agency: Fairfax County Basic Project Information Project Title: South Van Dorn Street and Franconia Road Interchange 7B Project Type (check one): Roadway

More information

2018 American Zero Emission Bus Conference INNOVATIVE CLEAN TRANSIT PROPOSED REGULATION

2018 American Zero Emission Bus Conference INNOVATIVE CLEAN TRANSIT PROPOSED REGULATION 2018 American Zero Emission Bus Conference INNOVATIVE CLEAN TRANSIT PROPOSED REGULATION L o s A n g e l e s S e p t e m b e r 1 0 th & 11 th 1 General Considerations of Staff Proposal Achieve zero emission

More information

Clifton Corridor Transit Initiative. Briefing to Medlock Area Neighborhood Association (MANA) February 15, 2016

Clifton Corridor Transit Initiative. Briefing to Medlock Area Neighborhood Association (MANA) February 15, 2016 Clifton Corridor Transit Initiative Briefing to Medlock Area Neighborhood Association (MANA) February 15, 2016 Neighborhood Concerns and Requests Provide a general overview and background of the project

More information

UPGRADING THE AMTRAK KEYSTONE CORRIDOR

UPGRADING THE AMTRAK KEYSTONE CORRIDOR UPGRADING THE AMTRAK KEYSTONE CORRIDOR Mark A. Wurpel Director Project Initiation & Development Amtrak 2005 AREMA Conference & Exposition Chicago, Illinois ABSTRACT: Upgrading the Amtrak Keystone Corridor

More information

Welcome. Highway 23 Gap New London to Paynesville. Open House. - Please Sign In -

Welcome. Highway 23 Gap New London to Paynesville. Open House. - Please Sign In - Highway Gap New London to Paynesville Welcome Highway Gap New London to Paynesville Open House - Please Sign In - There is no formal presentation, but representatives are available to answer your questions.

More information

South Gloucestershire Challenge Fund and Cycle Ambition Fund

South Gloucestershire Challenge Fund and Cycle Ambition Fund South Gloucestershire Challenge Fund and Cycle Ambition Fund The Challenge Fund A4174 scheme is coordinated and delivered by South Gloucestershire Council who were awarded 14 million pounds from the Department

More information

ORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement to Purchase Compressed Natural Gas Articulated Buses. Staff Report

ORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement to Purchase Compressed Natural Gas Articulated Buses. Staff Report ORANGE COUNTY TRANSPORTATION AUTHORITY Agreement to Purchase Compressed Natural Gas Articulated Staff Report November 8, 2012 To: From: Subject: Transit Committee Will Kempton, Chief Executive Officer

More information

Transit on the New NY Bridge

Transit on the New NY Bridge Transit on the New NY Bridge TZB Cross Section North bridge incorporating 12ft shared use path and space for future bus lane South bridge with space for a future bus lane Gap between the two decks for

More information

Update of the Midwest Regional Rail Initiative. Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI

Update of the Midwest Regional Rail Initiative. Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI Update of the Midwest Regional Rail Initiative Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI Key Presentation Take-Aways Status of Midwest Regional Rail Initiative

More information

Delaware County Engineer s Office

Delaware County Engineer s Office Delaware County Engineer s Office JANUARY 2017 County Engineer Responsibility Serve as engineer to the Board of County Commissioners and 18 Boards of Township Trustees for roads, bridges and land surveying

More information

Background Information about the Metrobus 29 Lines Study

Background Information about the Metrobus 29 Lines Study Background Information about the Metrobus 29 Lines Study Questions Overview of Existing Service Q. Why is the study being conducted? A. The 29 Lines provide an important connection between Annandale and

More information

Highway 23 New London Access & Safety Assessment. Public Open House #2 October 3, :00 to 7:00 PM

Highway 23 New London Access & Safety Assessment. Public Open House #2 October 3, :00 to 7:00 PM Public Open House #2 October 3, 2017 5:00 to 7:00 PM Highway 9 OVERVIEW OF ASSESSMENT Assessment Limits Highway 23 from County Road 40 to North Shore Dr Purpose: Identify opportunities to reduce serious

More information

Continued coordination and facilitation with City of Austin staff on documentation of processes to permit construction activities at the site.

Continued coordination and facilitation with City of Austin staff on documentation of processes to permit construction activities at the site. Project Manager Ed Collins LJA Engineering, Inc. Transportation Planning Manager 5316 Highway 290 West Austin Public Infrastructure Group Austin, TX 78735 (512) 762-6301 cell (512) 439-4757 office CARTS

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item 44 Program Management Project Budget and Schedule Status Project Schedules* Project 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Expo Phase I Orange Line Extension I-405 Sepulveda

More information

IH 35 FEASIBILITY STUDY

IH 35 FEASIBILITY STUDY IH 35 FEASIBILITY STUDY COOKE COUNTY, TEXAS February 1, 2007 Prepared by: Carter & Burgess, Inc. For: The Wichita Falls District of the Texas Department of Transportation INDEX I. INTRODUCTION. 3 II. PURPOSE

More information

5. OPPORTUNITIES AND NEXT STEPS

5. OPPORTUNITIES AND NEXT STEPS 5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours

More information

Federal Way Link Extension

Federal Way Link Extension Federal Way Link Extension Draft EIS Summary Route & station alternatives and impacts Link Light Rail System Map Lynnwood Mountlake Terrace Lynnwood Link Extension Shoreline 14th Northgate 40 Northgate

More information

Balancing the Transportation Needs of a Growing City

Balancing the Transportation Needs of a Growing City Balancing the Transportation Needs of a Growing City FY 2019 and FY 2020 Capital Budget SFMTA Board Meeting Ed Reiskin, Director of Transportation April 3, 2018 1 FY 2019-23 Capital Improvement Program

More information

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1 Executive Summary Introduction The Eastside Transit Corridor Phase 2 Project is a vital public transit infrastructure investment that would provide a transit connection to the existing Metro Gold Line

More information

Proposed Program of Interrelated Projects

Proposed Program of Interrelated Projects DALLAS AREA RAPID TRANSIT Proposed Program of Interrelated Projects Federal Transit Administration Capital Investment Program Summer 204 INTRODUCTION The current federal transportation bill, Moving Ahead

More information

TEXAS RURAL TRANSPORTATION PLAN 2035 (TRTP 2035)

TEXAS RURAL TRANSPORTATION PLAN 2035 (TRTP 2035) TEXAS RURAL TRANSPORTATION PLAN 2035 (TRTP 2035) Helping shape the future of rural Texas Texas Rural Transportation Plan 2035 Texas Rural Transportation Plan 2035 What is it? Component of the Statewide

More information

congestion management program

congestion management program congestion management program 2550 Rail Vehicle Program June 2013 11-0319tr 2010 lacmta Q U A R T E R LY P R O J E C T S TAT U S R E P O R T 255O RAIL VEHICLE PROGRAM QUARTERLY PROJECT STATUS REPORT THE

More information

Request for Qualifications. for

Request for Qualifications. for ST. VINCENT ELECTRICITY SERVICES LIMITED and THE ROCKY MOUNTAIN INSTITUTE CARBON WAR ROOM Request for Qualifications for Mayreau Microgrid Project Engineering, Procurement and Construction Contract for

More information

Caltrain Modernization EMU Procurement

Caltrain Modernization EMU Procurement Caltrain Modernization EMU Procurement Boarding Height CAC Meeting May 20, 2015 Context 2 1 Riders (Boardings) Average Weekday Ridership Since 2004 143% increase 60,000 55,000 50,000 45,000 40,000 35,000

More information

Elected Officials Briefing. North Metro Rail Line Update. February 9, 2017

Elected Officials Briefing. North Metro Rail Line Update. February 9, 2017 Elected Officials Briefing North Metro Rail Line Update February 9, 2017 Dave Genova, RTD General Manager and CEO Openings 2016-2017 Flatiron Flyer, Jan. 3, 2016 University of Colorado A Line, April 22,

More information