1 Transportation Services McArthur Avenue Cycling Lanes (between St. Laurent Boulevard and North River Road) Voies cyclables de l avenue McArthur (du boulevard St-Laurent au chemin North River) Open House - March 8, 2017 Wednesday Drop in between 6:30 and 8:30 p.m. Cafeteria, Ottawa Technical Secondary School 485 Donald Street, Ottawa Séance portes ouvertes - Le 8 mars 2017 Mercredi Accès libre de 18 h 30 à 20 h 30 Cafétéria, Ottawa Technical Secondary School 485, rue Donald, Ottawa 1
2 Background Speeding concerns along McArthur Avenue Residents have raised speeding concerns along McArthur Ave Speed data shows 62% of vehicles respecting speed limit Adawe Crossing Generating approximately cycling trips during summer months Desire to create East-West link to facilitate commutes Ottawa Cycle Plan Ottawa Cycling Plan 2013 had allocated $70, 000 for sharrows along Donald Street. An alternate east-west corridor using McArthur Avenue is proposed, since it would allow for the addition of bicycle lanes due to a wider right-of-way and less demand for on-street parking. The McArthur corridor also has greater connectivity potential to communities east of St. Laurent (Carson Grove/Carson Meadows, La Cité, CSEC Complex, etc.) and the Aviation Parkway multi-use pathway. This project can be accommodated within the existing budget envelope and has also been approved for matching by a Federal Funding Program. 2
3 Parking Demand and Supply Parking usage was recorded nine times on three different days at various times ( Saturday, Tuesday and Thursday). Parking was observed along McArthur Avenue, on side streets, and in certain parking lots (marked on Figure 1). Parking usage was recorded using dash cam mounted in a vehicle. The pie charts below illustrate the maximum parking used out of the 9 visits., For detailed parking usage, see Table 1 and 2 on the right Table 1: Parking usage along McArthur Avenue Parking spots occupied Date and time: Saturday 27 February Tue. 12 Apr. Thursday 14 April Parking Location Available 10 am 1 pm 5 pm 10 am 1 pm 10 am 1 pm 3 pm 6 pm S1 6 5* 0 0 ** ** N ** ** S N S N S N S N5 6*** S N S N S N S Total: *emergency vehicles**mcarthur Avenue closed beyond Olmstead Street***4 additional spots available after 5:30pm and on weekends Figure 1 : Study Area Table 2: Parking usage on side streets Parking spots occupied Date and time: Saturday 27 February Tue. 12 Apr. Thursday 14 April Parking 10am 1pm 5pm 10am 1pm 10am 1pm 3pm 6pm Location Available Cyr Avenue Olmstead Street Crete Place 8 1 ** Allen Boulevard 31 2 ** Lacasse Avenue Carmen Avenue 16 3 ** Lafontaine Avenue Eastwood Place Irwin Miller Street 35 4 ** Brant Street 30 0 ** Dieppe Street 30 3 ** Belisle Street Moorvale Street 32 7 ** rue de l'église May Street 22* * * * * Total: *May Street was closed on 14 April **Recording failure 3
4 Existing Parking Restrictions 4
5 Heavy Vehicles Heavy vehicle volume McArthur and Lafontaine, Wednesday, July 22, 2015, (11hrs) Eastbound :65 Westbound :71 Heavy vehicle volume McArthur and Olmstead, Wednesday, July , (11hrs) Eastbound :126 Westbound :105 Heavy vehicle volume McArthur and Olmstead, Friday, August , (11hrs) Eastbound :122 Westbound :127 Heavy vehicles include; Vehicles with one rear axles with 4 or more wheels (Figure 1) Or two of more axles OC Transpo Buses - Route 14 runs along McArthur - # of buses on Wednesday March 8 th, 2017 Eastbound 44 Westbound 44 School buses Figure 1: Truck with 4 wheels on rear axle 5
6 Project Objectives Reduce speeding behavior Create East-West cycling facility Visually narrow the road to discourage excessive speeding Enhance walking and cycling environment Road reconfiguration to be completed by line painting only (no physical modification) Draft Plan Cross Sections City staff, in conjunction with Councillors Mathieu Fleury and Tobi Nussbaum have developed a draft plan. The draft plan includes 2 vehicle travel lanes, 2 cycle lanes, turning lanes where applicable and parking when it can be accommodated. 3 typical cross sections are proposed along the corridor. 6
7 Expected Benefits and Impacts Benefits Reduce speeding behavior Create cycling friendly corridor Cycling link to Adawe crossing Parking will be inviting and properly identified Added buffer makes pedestrians more comfortable Planters enhance the streetscape Create parking West of Marguerite Avenue Impacts Increase travel time for vehicles and transit 25%. (Ex, if you current commute is 4 minutes along McArthur, your new commute will be 5 minutes) Increased maintenance for City operations Parking decreased: 40 parking spaces will be available along McArthur Avenue. Currently, there are 164 parking spaces. Period of adjustment for road users 7
8 Next Steps Additional feedback will be collected by or online A summary of the feedback will be provided to participants who signed up and posted on the project website Staff will use the suggestions to refine the draft plan For more information, please contact the project manager below: Eric Ouimet Coordinator, Area Traffic Management Transportation Services110 Laurier Avenue West Ottawa, Ontario K1P 1J , ext Fax: eric.ouimet@ottawa.ca 8
APPENDIX A. OC Transpo Maps & Route Information
APPENDIX A OC Transpo Maps & Route Information OC Transpo Route 99 APPENDIX B Traffic Count Information & Collision Data VEHICULAR TURNING MOVEMENTS (15 Min. Volumes) Limebank Road & Spratt Road
More informationCTfastrak Expansion. Stakeholder Meeting #4 Manchester Town Hall June 3, 2016
CTfastrak Expansion Stakeholder Meeting #4 Manchester Town Hall June 3, 2016 Today s Agenda Phase I Update 2016 Service Plan Implementation Schedule & Cost Update Phase II Services Timeline Market Analysis
More informationM E M O / N O T E D E S E R V I C E
M E M O / N O T E D E S E R V I C E To / Destinataire Mayor and Members of Council Chair and Members of the Transit Commission File/N de fichier: T12-01 SER From / Expéditeur General Manager Transportation
More information2.0 Development Driveways. Movin Out June 2017
Movin Out June 2017 1.0 Introduction The proposed Movin Out development is a mixed use development in the northeast quadrant of the intersection of West Broadway and Fayette Avenue in the City of Madison.
More informationM E M O / N O T E D E S E R V I C E
M E M O / N O T E D E S E R V I C E To / Destinataire From / Expéditeur Mayor and Members of Council Chair and Members of the Transit Commission General Manager Transportation Services Department File/N
More informationService and Operations Planning for Ottawa s New Light Rail Line Pat Scrimgeour
Service and Operations Planning for Ottawa s New Light Rail Line Pat Scrimgeour Manager, Transit Service Planning and Reporting OC Transpo Ottawa, Ontario Ottawa Light Rail Project 12.5 km, 13 stations
More informationProject Scoping Open House Welcome
Scoping Meeting Project Scoping Open House Welcome Alternatives Analysis (AA) and Draft Environmental Impact Statement/Draft Environmental Impact Report (DEIS/DEIR) Project Purpose Purpose of the Project
More informationMAR1011. West Birmingham Bus Network Review March 2010
MAR1011 West Birmingham Bus Network Review March 2010 West Birmingham Bus Network Review In December 2008, Centro published a strategy document entitled Transforming Bus Travel (TBT) which sets out a vision
More informationCONFEDERATION LINE EAST SEGMENT
The O-Train Confederation Line project is the first stage in Ottawa s future light rail network. The 12.5 kilometre electric rail system will replace existing diesel powered buses, providing rapid transit
More informationContinued coordination and facilitation with City of Austin staff on documentation of processes to permit construction activities at the site.
Project Manager Ed Collins LJA Engineering, Inc. Transportation Planning Manager 5316 Highway 290 West Austin Public Infrastructure Group Austin, TX 78735 (512) 762-6301 cell (512) 439-4757 office CARTS
More informationTrip Generation and Parking Study New Californian Apartments, Berkeley
Trip Generation and Parking Study New Californian Apartments, Berkeley Institute of Transportation Engineers University of California, Berkeley Student Chapter Spring 2012 Background The ITE Student Chapter
More informationStart Time. LOCATION: Scotts Valley Dr QC JOB #: SPECIFIC LOCATION: 0 ft from Tabor St. DIRECTION: EB/WB CITY/STATE: Scotts Valley, CA
Tube Counts Type of report: Tube Count - Volume Data LOCATION: Scotts Valley Dr QC JOB #: 245667 SPECIFIC LOCATION: ft from Tabor St DIRECTION: EB/WB CITY/STATE: Scotts Valley, CA DATE: Mar 2 24 - Mar
More informationHelp shape your community investment in Wake Transit. Fiscal Year 2019 Draft Work Plan Summary
Help shape your community investment in Wake Transit Fiscal Year 2019 Draft Work Plan Summary Wake County, growth and transit The Triangle is one of the fastest-growing regions in the nation. Wake County
More informationCentral Park Drives Traffic Management Overview
Central Park Drives Traffic Management Overview Spring 2015 New York City Department of Transportation Existing Traffic Management From Labor Day thru Last Day of NYC Public School: 8-10 AM weekdays (Southbound)
More informationConfederation Line West Queensway Terrace North. May 27, 2017
Confederation Line West Queensway Terrace North May 27, 2017 Agenda Background Lincoln Fields Station Concept LRT alignment, southwest of Lincoln Fields to Queensway, including: Pedestrian bridge replacement
More information886 March Road McDonald's Transportation Study
McDonald's Restaurants of Canada Limited March 2013 886 March Road McDonald's Transportation Study Submitted by: HDR Corporation 100 York Boulevard, Suite 300 Richmond Hill, ON L4B 1J8 (905) 882-4100 www.hdrinc.com
More informationBackground Information about the Metrobus 29 Lines Study
Background Information about the Metrobus 29 Lines Study Questions Overview of Existing Service Q. Why is the study being conducted? A. The 29 Lines provide an important connection between Annandale and
More information2405 Mer Bleue Orleans, (Ottawa), ON Community Transportation Study Mattamy Homes. Prepared By: Stantec Consulting Ltd. Version 2
2405 Mer Bleue Orleans, (Ottawa), ON Community Transportation Study Mattamy Homes Prepared By: Stantec Consulting Ltd. Version 2 April 2014 Stantec Consulting Ltd. 400-1331 Clyde Avenue, Ottawa ON K2C
More informationVan Ness Transit Corridor Improvement Project. Engineering, Maintenance and Safety Committee March 25, 2015
Van Ness Transit Corridor Improvement Project Engineering, Maintenance and Safety Committee March 25, 2015 Project Need 16,000 daily passenger boardings within the project corridor Average bus speed 8
More informationVanier Parkway and Presland Road Residential Development Transportation Impact Study
Vanier Parkway and Presland Road Residential Development Transportation Impact Study Final Report (Revised) March 2011 Submitted to: Groupe Lépine Ottawa Project No. 09-1613 Submitted by: Groupe Lépine
More informationDOWNTOWN PARKING STUDY AND STRATEGIC PLAN
INTRODUCTION This report includes a summary of several key components of the Rapid City Downtown Parking Study and Strategic Plan, including: Current Conditions Analysis (Inventory and Occupancy and Length
More informationTHE CORNERSTONE APARTMENTS TRAFFIC IMPACT STUDY R&M PROJECT NO
THE CORNERSTONE APARTMENTS SITUATED AT N/E/C OF STAUDERMAN AVENUE AND FOREST AVENUE VILLAGE OF LYNBROOK NASSAU COUNTY, NEW YORK TRAFFIC IMPACT STUDY R&M PROJECT NO. 2018-089 September 2018 50 Elm Street,
More informationCITY OF OAKLAND INTRODUCTION
CITY OF OAKLAND CITY HALL ONE FRANK OGAWA PLAZA 3RD FLOOR OAKLAND CA 94612 City Administrator s ADA Programs Division (510) 238-4754 TDD: (510) 238-2007 : January 4, To: Mayor s Commission on Persons with
More information1 Downtown LRT Connector: Draft Concept
Downtown LRT Connector: Draft Concept Plan November 2010 We re moving forward. Get involved. On June 21, 2010, City Council approved a street-level downtown LRT route, including a connector for the future
More informationDATE: March 21, 2017 REPORT NO. PW TYPE OF REPORT CONSENT ITEM [ ] ITEM FOR CONSIDERATION [ X ] 2.0 TOPIC
PUBLIC WORKS COMMISSION PUBLIC WORKS COMMISSION DATE: March 21, 2017 REPORT NO. PW2017-022 TO: FROM: Chair and Members Committee of the Whole Operations and Administration E. (Beth) Goodger, General Manager
More informationSouth Gloucestershire Challenge Fund and Cycle Ambition Fund
South Gloucestershire Challenge Fund and Cycle Ambition Fund The Challenge Fund A4174 scheme is coordinated and delivered by South Gloucestershire Council who were awarded 14 million pounds from the Department
More informationWIM #37 was operational for the entire month of September Volume was computed using all monthly data.
SEPTEMBER 2016 WIM Site Location WIM #37 is located on I-94 near Otsego in Wright county. The WIM is located only on the westbound (WB) side of I-94, meaning that all data mentioned in this report pertains
More informationTable of Contents INTRODUCTION... 3 PROJECT STUDY AREA Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS...
Crosshaven Drive Corridor Study City of Vestavia Hills, Alabama Table of Contents INTRODUCTION... 3 PROJECT STUDY AREA... 3 Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS...
More informationRe: Sainte-Geneviève Elementary School (2198 Arch Street) Transportation Overview
2 March 2015 OUR REF: TO3205TOB00 Conseil des écoles catholiques du Centre-Est (CECCE) 4000 rue Labelle Ottawa, Ontario K1J 1A1 Attention: Maguy Eustache Dear Maguy: Re: Sainte-Geneviève Elementary School
More information2019 New Transit Service Plan
Agenda Item 7.2 2019 New Transit Service Plan Draft Proposal VTA Board of Directors January 2019 Background: Next Network Plan and Today s Plan Early 2016 Transit Choices report and the ridership-coverage
More informationAttachment D Environmental Justice and Outreach
Attachment D Environmental Justice and Outreach ATTACHMENT D Environmental Justice and Outreach Indicate whether the project will have disproportionately high and adverse impacts on minority or low income
More informationConfederation Line Stage 1 and 2. Our Lady of Fatima Church May 10 th, 2018
Confederation Line Stage 1 and 2 Our Lady of Fatima Church May 10 th, 2018 Agenda Confederation Line Stage 1 Overview project, consortium, vehicles Confederation Line Stage 2 Overview project, benefits
More informationPublic Meeting: Metropolitan Washington Airports Authority (MWAA) TNC (Transportation Network Company) Lot on S. Eads Street
Public Meeting: Metropolitan Washington Airports Authority (MWAA) TNC (Transportation Network Company) Lot on S. Eads Street Department of Environmental Services, Transportation Division Sept. 27, 2018
More informationMEMO VIA . Ms. Amy Roth DPS Director, City of Three Rivers. To:
MEMO To: Ms. Amy Roth DPS Director, City of Three Rivers VIA EMAIL From: Michael J. Labadie, PE Julie M. Kroll, PE, PTOE Brandon Hayes, PE, P.Eng. Fleis & VandenBrink Date: January 5, 2017 Re: Proposed
More informationPARKING OCCUPANCY IN WINDSOR CENTER
PARKING OCCUPANCY IN WINDSOR CENTER TOWN OF WINDSOR, CONNECTICUT REPORT JUNE 2017 CONTENTS Background... 3 Other Relevant Data... 3 Parking Survey Design... 6 Parking Supply Inventory... 6 Parking Demand
More informationBARRHAVEN FELLOWSHIP CRC 3058 JOCKVALE ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for:
BARRHAVEN FELLOWSHIP CRC 3058 JOCKVALE ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: Barrhaven Fellowship CRC 3058 Jockvale Road Ottawa, ON K2J 2W7 December 7, 2016 116-649 Report_1.doc D. J.
More informationMETRO Orange Line BRT American Boulevard Station Options
METRO Orange Line BRT American Boulevard Station Options Bloomington City Council Work Session November 18, 2013 Christina Morrison BRT/Small Starts Project Office Coordinating Planning and Design AMERICAN
More informationOttawa LRT Stage 2. McKellar Park Information Session
Ottawa LRT Stage 2 McKellar Park Information Session Stage 2 Background Approved unanimously by Ottawa City Council in July 2015 East to Place d Orléans, west to Bayshore and Baseline, and south to Bowesville
More informationU N I V E R S I T Y O F B R I T I S H C O L U M B I A. Fall 2008 Transportation Status Report
U N I V E R S I T Y O F B R I T I S H C O L U M B I A Fall 2008 Transportation Status Report 6 February 2009 U N I V E R S I T Y O F B R I T I S H C O L U M B I A Fall 2008 Transportation Status Report
More informationThis letter summarizes our observations, anticipated traffic changes, and conclusions.
Mr. David Jorschumb Project Manager Boulder Valley School District Re: Review of proposed school access improvements at the Foothills Elementary School in Boulder Dear Mr. Jorschumb, At your request, the
More informationClick to edit Master title style
Nelson/Nygaard Consulting Associates SERVICE IMPROVEMENT STRATEGIES September 22, 2015 1 PROJECT OVERVIEW & WORK TO DATE 1. Extensive stakeholder involvement Throughout 2. System and market assessment
More informationNew McNicoll Bus Garage Public Open House
New McNicoll Bus Garage Public Open House Kennedy Public School 1 The Need for a New Bus Garage Riders Increased ridership means Buses Need for new buses Garage And a new buses facility Problems Garages
More informationD. J. Halpenny & Associates Ltd. Consulting Transportation Engineers
D. J. Halpenny & Associates Ltd. Consulting Transportation Engineers August 24, 2015 File: 115-622 Mr. R. Baumann, President The RGB Group 277 Kirchoffer Avenue Ottawa, ON K2A 1Y1 RE: RESIDENTIAL DEVELOPMENT
More informationHarlem Avenue between 63 rd and 65 th
Harlem Avenue between 63 rd and 65 th Public Meeting #2 March 13, 2018 Summit Park District Welcome to the second Public Meeting for the preliminary engineering and environmental studies of Illinois 43
More informationDockless Micromobility Regulatory Framework
Dockless Micromobility Regulatory Framework Transportation and Municipal Infrastructure Committee March 19, 2019 Dockless Micromobility was last discussed at the February 5 th committee meeting TMI committee
More informationClearlake Road (State Road 501) Project Development & Environment (PD&E) Study
Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study FROM MICHIGAN AVENUE TO INDUSTRY ROAD BREVARD COUNTY, FLORIDA Financial Project ID No: 433605-1-22-01 Federal Aid Project
More informationPace Bus Depot Location Analysis
Pace Bus Depot Location Analysis Key Notes 1. Options refer to conceptual sketches prepared by Kimley Horn. 2. The depot is assumed to accommodate Pace routes as they currently exist: 17 routes on the
More informationWe Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network:
We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network: Richmond North of Oxford Street Richmond Row Dundas Street
More informationCOMMISSION WORKSHOP Tuesday, May 12, :00 a.m. 12:00 p.m.
COMMISSION WORKSHOP Tuesday, 9:00 a.m. 12:00 p.m. AGENDA 1. Approval of the April 30, 2009 Workshop Minutes 2. Community Redevelopment Agency a. CRA Master Plan Update b. Downtown Parking Study 3. Economic
More informationStudy Area and Location District PSA Ward ANC Phase Description B Existing 600 Block New York Avenue Northeast Westbound
Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia 6 Block New York Avenue NE Study Area and Location District PSA Ward ANC Phase Description 5 55 5 5B
More informationCITY OF MANHATTAN BEACH DEPARTMENT OF COMMUNITY DEVELOPMENT
CITY OF MANHATTAN BEACH DEPARTMENT OF COMMUNITY DEVELOPMENT TO: FROM: Parking and Public Improvements Commission Marisa Lundstedt, Director of Community Development Erik Zandvliet T.E., City Traffic Engineer
More informationTransportation Improvement Program (TIP) Candidate Project List for Public Review
2011-2014 Transportation Improvement Program (TIP) Candidate List for Public Review Table 1 Annual Listing Of Federal Aid Obligation For Federal Fiscal Year 2010 North Dakota s Number Transit 410083 Transit
More informationDRAFT TRANSPORTATION IMPACT STUDY CASTILIAN REDEVELOPMENT PROJECT
DRAFT TRANSPORTATION IMPACT STUDY CASTILIAN REDEVELOPMENT PROJECT Prepared for: Submitted by: 299 Lava Ridge Ct. Suite 2 Roseville, CA. 95661 June 212 TABLE OF CONTENTS 1. Introduction... 1 Project Location
More informationBROWARD BOULEVARD CORRIDOR TRANSIT STUDY
BROWARD BOULEVARD CORRIDOR TRANSIT STUDY FM # 42802411201 EXECUTIVE SUMMARY July 2012 GOBROWARD Broward Boulevard Corridor Transit Study FM # 42802411201 Executive Summary Prepared For: Ms. Khalilah Ffrench,
More informationClean Harbors Canada, Inc.
Clean Harbors Canada, Inc. Proposed Lambton Landfill Expansion Environmental Assessment Terms of Reference Transportation Assessment St. Clair Township, Ontario September 2009 itrans Consulting Inc. 260
More informationand Members of Municipal Council City of Niagara Falls, Ontario Mewburn Road Speed Control Review
TS-2018-10 May 8, 2018 REPORT TO: SUBMITTED BY: SUBJECT: Mayor James M. Diodati and Members of Municipal Council City of Niagara Falls, Ontario Transportation Services Department TS-2018-10 Mewburn Road
More informationBOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM. Design Endorsement for Sterling Boulevard Extension
Date of Meeting: July 20, 2017 # 6 BOARD OF SUPERVISORS BUSINESS MEETING ACTION ITEM SUBJECT: ELECTION DISTRICT: CRITICAL ACTION DATE: STAFF CONTACTS: Design Endorsement for Sterling Boulevard Extension
More informationStudy Area and Location District PSA Ward ANC Phase Description C Existing 100 Block Michigan Avenue Northeast Westbound
Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia 1 Block Michigan Avenue NE W/B Study Area and Location District PSA Ward ANC Phase Description 5 45
More informationMETRO Light Rail Update
American Society of Highway Engineers METRO Light Rail Update Brian Buchanan Director, Design and Construction October 13, 2009 1 High Capacity Transit System 2 20-Mile Light Rail Line 3 Operations Operations
More informationExhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup
Exhibit A Sound Transit Board Resolution R2016-07 Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Access Improvement Project. RESOLUTION NO. R2016-07 Selecting
More informationDraft Report: West Berkeley Bowl Project
Draft Report: West Berkeley Bowl Project July 2004 Prepared for: The City of Berkeley 1031-1925 F EHR & PEERS TRANSPORTATION CONSULTANTS 3685 Mt. Diablo Blvd. #301 Lafayette, CA 94549 925-284-3200 Fax:
More informationFixing the Line s Canarsie Tunnel. Manhattan CB6 11/5/2018
Fixing the Line s Canarsie Tunnel Manhattan CB6 11/5/2018 Interborough Bus Service 80+ buses in the peak hour in the peak direction over the Williamsburg Bridge Projected to carry 17% of riders 1 Bus Priority
More information5. OPPORTUNITIES AND NEXT STEPS
5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours
More informationTrip Generation & Parking Occupancy Data Collection: Grocery Stores Student Chapter of Institute of Transportation Engineers at UCLA Spring 2014
Trip Generation & Parking Occupancy Data Collection: Grocery Stores Student Chapter of Institute of Transportation Engineers at UCLA Spring 2014 Page 1 Introduction The UCLA Institute of Transportation
More information1012 & 1024 McGarry Terrace
December 217 112 & 124 McGarry Terrace Transportation Impact Study 112 & 124 McGarry Terrace Transportation Impact Study prepared for: Lépine Corporation 32 March Road Kanata, ON K2K 2E3 prepared by: 1223
More informationGASOLINE SERVICE STATION 1618, 1622 ROGER STEVENS DRIVE OTTAWA, ONTARIO TRANSPORTATION IMPACT ASSESSMENT. Prepared for:
GASOLINE SERVICE STATION 1618, 1622 ROGER STEVENS DRIVE OTTAWA, ONTARIO TRANSPORTATION IMPACT ASSESSMENT Prepared for: Invecta Development (Ottawa) Corporation 758 Shanks Height Milton, ON L9T 7P7 May
More informationPROPOSED TRAFFIC RESOLUTION
Reference Number: TR 50-18 Location:, Brooklyn Bus Hub - Brooklyn Proposal: Information: To provide new bus stops to create a Bus hub location on Cleveland Street, Brooklyn, as part of Wellington s new
More informationFigure 1 Map of intersection of SR 44 (Ravenna Rd) and Butternut Rd
Abbreviated Study District: 12 County: Geauga Route: SR 44 Section: 1.58 GEA 44 1.58 213 HSP # 47 (Rural Intersection) Prepared April 23, 215 By Bryan Emery Existing Conditions This study contains the
More informationUNIVERSITY OF BRITISH COLUMBIA. Transit Service Plan. Discussion Paper #8
OF BRITISH CONTENTS Summary... 1 1. Introduction... 2 1.1 U-TREK Program...2 1.2 Ridership Forecasts...3 2. s To UBC... 6 2.1 Existing s...6 2.1.1 Ridership...6 2.1.2 Target Markets...10 2.2 Future s...13
More informationWIM #31 US 2, MP 8.0 EAST GRAND FORKS, MN JANUARY 2015 MONTHLY REPORT
WIM #31 US 2, MP 8.0 EAST GRAND FORKS, MN JANUARY 2015 MONTHLY REPORT WIM #31 EAST GRAND FORKS MONTHLY REPORT - JANUARY 2015 WIM Site Location WIM #31 is located on US 2 at mile post 8.0, southeast of
More informationMERIVALE PRIORITY SQUARE 2852 MERIVALE ROAD CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for: ONT Inc. 25 Winding Way Nepean, Ontario K2C 3H1
MERIVALE PRIORITY SQUARE 2852 MERIVALE ROAD CITY OF OTTAWA TRANSPORTATION BRIEF Prepared for: 2190986ONT Inc. 25 Winding Way Nepean, Ontario K2C 3H1 October 6, 2010 110-502 Report_1.doc D. J. Halpenny
More informationESTABLISH PERPENDICULAR PARKING Alabama Street, east side, from 75 feet to 96 feet south of Mullen Avenue (extends existing zone by 21 feet)
ESTABLISH STOP SIGNS Irving Street, eastbound and westbound, at 45 th Avenue, making this intersection an all-way STOP ESTABLISH BUS ZONE Market Street, north side, from Steuart Street to 110 feet westerly
More informationRTD Commuter Rail System APTA Rail Conference June 23, 2015
RTD Commuter Rail System APTA Rail Conference June 23, 2015 RTD Eagle & North Metro Commuter Rail System Today s Presentation Eagle Design, Construction, Systems Commuter Rail Vehicles and CRMF/OCC EC
More information370 Queen Elizabeth Drive Transportation Overview
December 8, 2014 OUR REF: TO3193TOA BY EMAIL: Ashley@rocahomes.ca 2253644 Ontario Inc. c/o BassCon 24 George Street West Ottawa, ON K1S 3J2 Attention: Ashley Lepine Dear Ashley: Re: 370 Queen Elizabeth
More informationPedestrians Road Safety
Pedestrians Road Safety Overview Over the period 1996-2009, 5,323 people have been killed on Irish road. Out of this 22% (1162) were pedestrians. Additional 3863 pedestrians were seriously injured in the
More informationAPPENDIX TR-1 PARKING AND QUEUING ASSESSMENT
APPENDIX TR-1 PARKING AND QUEUING ASSESSMENT Overland Overland Traffic Consultants, Traffic Consultants, Inc. Inc. Overland Traffic Consultants 952 Manhattan Beach Boulevard, Suite #100 Manhattan Beach,
More informationAPPENDIX C-2. Traffic Study Supplemental Analysis Memo
APPENDIX C-2 Traffic Study Supplemental Analysis Memo The Mobility Group Transportation Strategies & Solutions Memorandum To: From: Subject: Tomas Carranza, LADOT Matthew Simons Traffic Review - Revised
More informationMOTION NO. M Preferred Alternative for the Puyallup Station Access Improvement Project
MOTION NO. M2014 64 Preferred Alternative for the Puyallup Station Access Improvement Project MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 8/14/14 8/28/14 Recommendation
More informationConstruction Staging Area 4 Avenue Road
REPORT FOR ACTION Construction Staging Area 4 Avenue Road Date: September 27, 2017 To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto and East York District
More informationConstruction Realty Co.
MEMORANDUM TO: FROM : Jeff Pickus Construction Realty Co. Luay R. Aboona, PE Principal 9575 West Higgins Road, Suite 400 Rosemont, Illinois 60018 p: 847-518-9990 f: 847-518-9987 DATE: May 22, 2014 SUBJECT:
More information4 Circulation & Transportation
4.1 Mobility Network The mobility network at the new St. Paul s hospital and health campus is comprised of an interconnected system of sidewalks, cycle paths, transit routes and roadways. Figure 4-1: Indicative
More informationLacey Gateway Residential Phase 1
Lacey Gateway Residential Phase Transportation Impact Study April 23, 203 Prepared for: Gateway 850 LLC 5 Lake Bellevue Drive Suite 02 Bellevue, WA 98005 Prepared by: TENW Transportation Engineering West
More informationCentral Loop Bus Rapid Transit
Central Loop Bus Rapid Transit Transportation Goals of the Chicago Central Area ACTION Plan, page 2-6 Central Area Plan Improve Transit in Central Area Improve Pedestrian Environment Manage Traffic Circulation
More informationStrategies to keep people and goods moving in and through Seattle
Strategies to keep people and goods moving in and through Seattle SR 99 Closure and the Seattle Squeeze 2018-2024 DON Information Session Department of Transportation Delridge Community Center November
More informationLOADING AND UNLOADING SURVEY NATIONAL SCHOOL BUS. Kansas leads the world in the success of each student.
NATIONAL SCHOOL BUS LOADING AND UNLOADING SURVEY Kansas leads the world in the success of each student. January 2018 The Kansas State Department of Education School Bus Safety Unit wishes to thank the
More informationNational Household Travel Survey Add-On Use in the Des Moines, Iowa, Metropolitan Area
National Household Travel Survey Add-On Use in the Des Moines, Iowa, Metropolitan Area Presentation to the Transportation Research Board s National Household Travel Survey Conference: Data for Understanding
More informationMobility Corridor Updates. Transit & Active Transportation Projects
Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate
More informationKendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study
Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What
More informationTRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA
TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA PREPARED FOR: UNIVERSITY OF PENNSYLVANIA HEALTH SYSTEM 34 CIVIC CENTER BOULEVARD PHILADELPHIA, PA 1987 (61)
More informationAttachment F Transportation Technical Memorandum
Attachment F Transportation Technical Memorandum Sounder Yard and Shops Facility Project Transportation Technical Memorandum March 25, 216 Prepared for: Sound Transit Prepared by: Parsons Brinckerhoff
More informationTrip Generation Study: Provo Assisted Living Facility Land Use Code: 254
Trip Generation Study: Provo Assisted Living Facility Land Use Code: 254 Introduction The Brigham Young University Institute of Transportation Engineers (BYU ITE) student chapter completed a trip generation
More informationTHE CALIFORNIA STATE UNIVERSITY Commercial Paper Equipment Financing (CPEF) Fiscal Year Financing Schedules *
Updated 4-10-09 Fiscal Year 2009-10 Financing Schedules * Round of CPEF Call Response CP Issuance Funding Thirteenth March 10, 2009 June 3, 2009 June 4, 2009 Fourteenth June 9, 2009 September 1, 2009 September
More informationProject Status Update January 2017
Project Status Update January 2017 1 What is the Purple Line? A new 16 mile east-west light rail line Operates mostly on the surface with 21 stations Connects New Carrollton in Prince George s County and
More informationI-4 Beyond the Ultimate. Florida Transportation Builders Association January 18, 2019
I-4 Beyond the Ultimate Florida Transportation Builders Association January 18, 2019 FDOT District 5 Improving Mobility & Safety in Central Florida FDOT District 5 is: Designing and building a better Interstate
More informationCommittee Report. Transportation Committee. Business Item No
Committee Report Business Item No. 2015-280 Transportation Committee For the Metropolitan Council meeting of December 9, 2015 Subject: METRO Blue Line Extension (Bottineau Light Rail Transit) Revised Scope
More informationVAN NESS AVENUE BUS RAPID TRANSIT
VAN NESS AVENUE BUS RAPID TRANSIT Commission of the Environment Policy Committee May 22, 2014 Peter Gabancho Project Manager III Capital Programs & Construction SFMTA 1 Conceptual Visual Simulation Center-Running
More informationStudy Area and Location District PSA Ward ANC Phase Description C Planned Suitland Parkway Westbound at Stanton Road Southeast
Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia Suitland Parkway at Stanton Road SE Study Area and Location District PSA Ward ANC Phase Description
More informationWest Broadway Reconstruction/LRT Design. March 19, 2015
West Broadway Reconstruction/LRT Design March 19, 2015 1 Meeting Agenda 6:05 6:30 PM Brief presentation What we heard Project overview 6:30 8:00 PM Visit Six Topic Areas Road and LRT design elements Pedestrian
More informationINTERSECTION ANALYSIS PARK AVENUE AND BRADDOCK ROAD (FROSTBURG, MD) FOR LENHART TRAFFIC CONSULTING, INC.
INTERSECTION ANALYSIS FOR PARK AVENUE AND BRADDOCK ROAD (FROSTBURG, MD) Prepared for: City of Frostburg, Maryland & Allegany County Commissioners Prepared by: LENHART TRAFFIC CONSULTING, INC. TRAFFIC ENGINEERING
More informationBus Stop Optimization Study
Bus Stop Optimization Study Executive Summary February 2015 Prepared by: Passero Associates 242 West Main Street, Suite 100 Rochester, NY 14614 Office: 585 325 1000 Fax: 585 325 1691 In association with:
More information