1 Direct Testimony and Schedules Grant Stevenson STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION IN THE MATTER OF THE APPLICATION FOR A ROUTE PERMIT FOR THE PLEASANT VALLEY TO BYRON KV TRANSMISSION LINE PROJECT PUC DOCKET NO. E00/TL-09- OAH DOCKET NO DIRECT TESTIMONY OF GRANT STEVENSON On Behalf of APPLICANT NORTHERN STATES POWER COMPANY, A MINNESOTA CORPORATION October, 00 Exhibit

2 TABLE OF CONTENTS PAGE I. INTRODUCTION AND QUALIFICATIONS... II. DOUBLE CIRCUIT STRUCTURES... III. PIPELINE STUDY... IV. CONCLUSION...

3 I. INTRODUCTION AND QUALIFICATIONS Q. PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. A. My name is Grant Stevenson and my business address is Nicollet Mall, Minneapolis, MN 0. Q. BY WHOM ARE YOU EMPLOYED AND WHAT IS YOUR POSITION? A. I am employed by Xcel Energy Services Inc. ( XES ) as a Senior Transmission Project Manager. XES is the service provider for Northern States Power Company, a Minnesota corporation ( Xcel Energy ). My resume is attached as Schedule. Q. PLEASE SUMMARIZE YOUR EDUCATION AND PROFESSIONAL EXPERIENCE. A. I graduated from the University of Minnesota in 98 with a Bachelor s degree in Mechanical Engineering. After graduation, I joined Northern States Power Company as a Mechanical Engineer at the Sherburne County generating plant in Becker, Minnesota. I was responsible for managing projects to improve productivity, efficiency, and safety at the company s largest generating plant. I also managed contractors, plant operations, maintenance, and technical personal. Since 98, I have held positions with Xcel Energy with increasing responsibility. I became a Transmission Project Manager in September 000 and today I hold the title of Senior Transmission Project Manager. In my role as Transmission Project Manager I was a project manager for Xcel Energy s 8 megawatt ( MW ) wind outlet transmission projects in southwestern Minnesota from 00 until 00. The project included more than 00 miles of transmission lines and PUC Docket No. E00/TL-09- OAH Docket No

4 affected 9 substations. In August 00 I was promoted to Senior Transmission Project Manager. I provide strategic leadership and am responsible for capital project scope, cost, schedule, and risk management for the Pleasant Valley to Byron kv Transmission Project ( Project ) in addition to several other Xcel Energy projects including the CapX00 Hampton Rochester La Crosse kv Project. My resume is attached as Schedule. Q. FOR WHOM ARE YOU TESTIFYING? A. I am providing testimony on behalf of Xcel Energy, the Applicant for a Route Permit in this proceeding. Q. WHAT IS THE PURPOSE OF YOUR TESTIMONY IN THIS PROCEEDING? A. The purpose of my testimony is to provide information about Xcel Energy s request to have the flexibility to use double-circuit structures for a portion of the Project. I am also providing testimony regarding the potential issues involved with the close proximity of a transmission line and a natural gas pipeline given that a short segment of the Preferred Route shares the same road corridor as a pipeline. Q. WERE YOU INVOLVED IN THE PREPARATION OF XCEL ENERGY S ROUTE PERMIT APPLICATION IN THIS PROCEEDING? A. Yes. I contributed to the engineering and Project management sections of the Route Permit Application ( Application ) and was involved in the routing analysis. Q. WHAT SCHEDULES ARE ATTACHED TO YOUR TESTIMONY? PUC Docket No. E00/TL-09- OAH Docket No

5 A. Schedule : CV of Grant Stevenson Schedule : Map of Pipeline and Potential Double Circuit Area Q. ARE YOU AVAILABLE TO PROVIDE TESTIMONY IN SUPPORT OF PARTICULAR SECTIONS OF THE ROUTE PERMIT APPLICATION? A. Yes. I am testifying in support of portions of Chapter of the Route Permit Application including Sections. (Project Schedule) and. (Project Cost), and portions of Chapter including Sections. (Transmission Structures and Right- of-way Design) and. (Transmission Line Construction, Restoration and Maintenance). II. DOUBLE CIRCUIT STRUCTURES Q. YOU MENTIONED THAT XCEL ENERGY IS REQUESTING THE FLEXIBILITY TO USE DOUBLE CIRCUIT STRUCTURES FOR A PORTION OF THE ROUTE, WHY IS THIS FLEXIBILITY NEEDED? A. After the filing of the Application, Xcel Energy became aware that Pleasant Valley Wind, LLC ( PVW ) is seeking local approval for a 8 kv transmission line that it plans to construct near the Pleasant Valley Substation in Mower County. This proposed 8 kv line shares the Preferred Route for this Project for. miles along 80 th Avenue. The map attached to my testimony as Schedule shows the portion of the Preferred Route that overlaps with PVW s proposed 8 kv line. At this time, Xcel Energy and PVW are exploring the possibility of double circuiting Xcel Energy s proposed kv transmission line with PVW s proposed 8 kv line to reduce impacts to landowners. As a result, Xcel Energy requests the flexibility to use double circuit structures for this PUC Docket No. E00/TL-09- OAH Docket No

6 portion of the route if an agreement can be reached between the parties to double circuit these two transmission lines. Q. IN THE EVENT THAT AN AGREEMENT IS REACHED, WHAT TYPE OF DOUBLE CIRCUIT STRUCTURES DOES XCEL ENERGY PROPOSE TO USE? A. The proposed structures would be single pole, weathering steel double circuit davit arm structures. The height of the double circuit structures will range from 90 to 0 feet. The spans between structures will typically range from 00 to 0 feet with a right-of-way of 80 feet. Structure base diameters for tangent structures will be to inches and will be 8 to 8 inches for angle structures. The foundation diameter for these double circuit structures will be to 9 feet. III. PIPELINE STUDY Q. YOU MENTIONED THAT THERE IS A PORTION OF THE PREFERRED ROUTE THAT SHARES THE SAME ROAD CORRIDOR AS A NATURAL GAS PIPELINE. WHERE IS THIS PORTION OF THE ROUTE? A. The Preferred Route for this Project shares the same road corridor as an existing Northern Natural Gas ( NNG ) underground natural gas pipeline for a short segment of the route along 80 th Street. The area of corridor sharing begins at a valve station located on the east side of 80 th Avenue beginning one-quarter mile north of 0 th Street and continuing to the north approximately. miles. The map attached to my testimony as Schedule shows the location of this pipeline in relation to the Preferred Route. PUC Docket No. E00/TL-09- OAH Docket No

7 Q. CAN YOU DESCRIBE THE POTENTIAL ISSUES THAT ARISE WHEN A TRANSMISSION LINE AND A PIPELINE SHARE THE SAME CORRIDOR? A. Steel pipelines which are buried in the earth must be protected from corrosion. This is typically accomplished by applying a protective coating on the pipe and using a cathodic protection system. The NNG pipeline along 80 th Street utilizes an epoxy coating and a direct current ( DC ) impressed voltage cathodic protection system. The system typically operates at less than two volts. When an alternating current ( AC ) transmission line is installed near a steel pipeline, the transmission line can induce a small voltage on the pipeline that can interfere with the pipeline s cathodic protection system and cause corrosion. Q. WHAT METHODS CAN BE USED TO REDUCE OR ELIMINATE INDUCED VOLTAGE ON A PIPELINE LOCATED NEAR A TRANSMISSION LINE? A. Induced voltage can be reduced or eliminated by physically separating the transmission line and pipeline by some distance. In addition, minor modifications to the transmission line design or changes to the pipeline cathodic protection system can also be used to reduce or eliminate induced voltage. Q. WHAT STEPS DOES XCEL ENERGY PROPOSE TO TAKE TO REDUCE OR ELIMINATE INDUCED VOLTAGE ON THE NNG PIPELINE? A. Xcel Energy has commissioned an AC interference study which will determine the appropriate physical separation and design changes that may be necessary for this Project. The results of this study will be available at or before the October, 00 public hearing. PUC Docket No. E00/TL-09- OAH Docket No

8 IV. CONCLUSION Q. DOES THIS CONCLUDE YOUR DIRECT TESTIMONY? A. Yes. 7889v PUC Docket No. E00/TL-09- OAH Docket No

9 Docket No.E00/TL-09- OAH Docket No Schedule Page of Grant David Stevenson, PMP Xcel Energy Nicollet Mall- MP8A Minneapolis, MN grant.stevenson@xcelenergy.com Experience Project Manager, Senior Project Manager 000 to present Transmission Business Unit, Xcel Energy, Minneapolis,.MN Provide strategic leadership to multidisciplinary teams on various high-profile transmission and substation projects. Work with planning, engineering, siting, construction, consultants and contractors to define scope of work, produce project estimates, gain capital spending authorization, establish project schedules, track and reconcile expenditures, gain permits, design, bid and construct capital projects to that meet budgets and in-service dates. Work extensively with the public and state regulatory officials during project pennitting phases to locate new transmission lines in areas that balance issues of land use, cost, impact to people and impact to the natural environment. Participate and lead public meetings and provide testimony in pennit proceedings. Recent project portfolio has included: Since 00, project manager for CapX 00 Fargo and LaCrosse projects. Project manager of Southwest Minnesota 8 MW wind transmission project, This $0 million project involved construction of 00 miles of new transmission lines, the reconstruction of 00 miles of existing lines, and impacted 9 substations. The project also required project agreements with electric utilities. SE Metro project, a rebuild of an existing line to double circuit. Bloomington relocation project, including kv double circuit underground construction. Sales and Customer Service Manager 999 to 000 Electric Sales and Customer Service, Northern States Power Company, Minneapolis,.MN Successfully led team of 0 account representatives to meet goals in sales, customer service, demand side management and customer satisfaction. Managed projects to improve customer satisfaction and team effectiveness. Hired, trained and coached employees on energy management, conservation, distribution reliability. Energy Management Engineer, Account Executive Northern States Power Company, Minneapolis, MN 990 to 999 Provided effective technical support to key industrial customers and NSP sales representatives regarding energy conservation programs and initiatives. Assumed role of Account Executive in 99, managing NSP's relationship with several demanding strategic customers. Led multidisciplinary teams to solve customer-specific electric reliability, power quality, capacity, and distribution construction problems. Plant Project Engineer 98 to 990 Sherburne County Generating Plant, Northern States Power Company, Becker, MN Managed contractors, directed work of plant operations, maintenance and technical personnel Managed projects to improve productivity, efficiency and safety at NSP's largest generating plant. Identified electrical and mechanical problems and recommended corrective repairs Professional Certification Certified Project Management Professional (PMP) by Project Management Institute, 007

10 Docket No.E00/TL-09- OAH Docket No Schedule Page of Education Project Management Institute Project Management Professional Training, 007 Minnesota Management Institute, University of Minnesota School of Management, 000 Intensive, condensed MBA-level business management curriculum. Minnesota Management Academy, University of Minnesota School of Management, 998 Management principles and skills for front-line managers. Post~graduate coursework at University of S. Thomas and University of Minnesota in economics, business law, marketing, manufacturing. Bachelor of Mechanical Engineering, University of Minnesota, 98

11 70th County Rd 9 90th Docket No.E00/TL-09-, OAH Docket No , - Schedule, Page of County Hwy 0th Pipeline Area th th Potential double-circuit area with RES (8 kv line) 80th 0th Project Area Pleasant Valley Substation D od g e O lm s te d M ow e r Map produced by: Northern States Power Company-Minnesota, an Xcel Energy Company Siting and Land Rights -- jwf/wkc DRAFT: October, 009 Routes Added: October, 009 Proposed Routes Preferred Alternate!!!!!! ") Route Width Existing 9 kv Existing kv Existing kv Substation Airport Feet 0 00,000,000,000 Map of Pipeline and Potential Double Circuit Area H

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION DIRECT TESTIMONY OF GRANT STEVENSON. On Behalf of APPLICANT

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION DIRECT TESTIMONY OF GRANT STEVENSON. On Behalf of APPLICANT EXHIBIT Direct Testimony and Schedules Grant Stevenson STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION IN THE MATTER OF THE APPLICATION FOR A ROUTE PERMIT FOR THE

More information

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO.

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO. STATE OF MINNESOTA Direct Testimony and Schedule OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION Amanda King IN THE MATTER OF THE ROUTE PERMIT APPLICATION FOR THE CAPX00 HAMPTON ROCHESTER

More information

Plan and Profile for the Black Dog Natural Gas Pipeline Project Docket No. G002/GP

Plan and Profile for the Black Dog Natural Gas Pipeline Project Docket No. G002/GP 414 Nicollet Mall Minneapolis, MN 55401 March 13, 2017 Daniel P. Wolf Executive Secretary Minnesota Public Utilities Commission 121 7 th Place East, Suite 350 St. Paul, MN 55101 Via Electronic Filing RE:

More information

BEFORE THE NEW JERSEY BOARD OF PUBLIC UTILITIES

BEFORE THE NEW JERSEY BOARD OF PUBLIC UTILITIES EXHIBIT JC-2 BEFORE THE NEW JERSEY BOARD OF PUBLIC UTILITIES IN THE MATTER OF THE PETITION OF JERSEY CENTRAL POWER & LIGHT COMPANY PURSUANT TO N.J.S.A. 40:55D-19 FOR A DETERMINATION THAT THE OCEANVIEW

More information

STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION DOCKET NO. ET6675/CN OAH DOCKET NO REBUTTAL TESTIMONY

STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION DOCKET NO. ET6675/CN OAH DOCKET NO REBUTTAL TESTIMONY STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION DOCKET NO. ET6675/CN-12-1053 OAH DOCKET NO. 60-2500-30782 REBUTTAL TESTIMONY OF RANDALL PORTER, PE SUBMITTED ON BEHALF OF: WIND ON THE

More information

The Narragansett Electric Company. d/b/a National Grid (Interstate Reliability Project) RIPUC Dkt. No Testimony of. David M. Campilii, P.E.

The Narragansett Electric Company. d/b/a National Grid (Interstate Reliability Project) RIPUC Dkt. No Testimony of. David M. Campilii, P.E. (Interstate Reliability Project) RIPUC Dkt. No. 0 Testimony of David M. Campilii, P.E. November, 0 -v RIPUC Dkt. No. 0 PREFILED TESTIMONY OF DAVID M. CAMPILII 0 0 INTRODUCTION Q. Please state your name

More information

April 6, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

April 6, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 414 Nicollet Mall Minneapolis, MN 55401 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 RE: Public Service Company of Colorado Docket

More information

Re: Application for Approval of Route Permit Amendment, Spans 89-93, 95-97, and

Re: Application for Approval of Route Permit Amendment, Spans 89-93, 95-97, and January 11, 2011 VIA ELECTRONIC FILING and U.S. MAIL Dr. Burl W. Haar Executive Secretary Minnesota Public Utilities Commission 350 Metro Square Building 121 Seventh Place East St. Paul, MN 55101 Dear

More information

Michigan Thumb Loop Transmission Line Project

Michigan Thumb Loop Transmission Line Project Michigan Thumb Loop Transmission Line Project ITC Holdings Corp. Simon Whitelocke VP., Regulatory and External Affairs October 30, 2013 What is Transmission? The electric transmission system is the network

More information

NEW ECTOR COUNTY NORTH TO MOSS 138 kv TRANSMISSION LINE PROJECT PUBLIC OPEN HOUSE MEETING

NEW ECTOR COUNTY NORTH TO MOSS 138 kv TRANSMISSION LINE PROJECT PUBLIC OPEN HOUSE MEETING NEW ECTOR COUNTY NORTH TO MOSS 138 kv TRANSMISSION LINE PROJECT PUBLIC OPEN HOUSE MEETING TUESDAY AUGUST 17, 2010 4:00 PM 8:00 PM CAVAZOS ELEMENTARY SCHOOL CAFETERIA 9301 WEST 16 TH STREET ODESSA, TEXAS

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

Minnesota Public Utilities Commission Staff Briefing Papers

Minnesota Public Utilities Commission Staff Briefing Papers Minnesota Public Utilities Commission Staff Briefing Papers Meeting Date: September 9, 2004................................ Agenda Item # Company: Docket No. Issue(s): Mankato Energy Center IP-6345/CN-03-1884

More information

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA Submission of Indicated New York Transmission Owners For Authority to Construct and Operate Electric Transmission Facilities in Multiple Counties in New York Case 13-M-0457 Edic to New Scotland 345 kv

More information

Portland General Electric Company Second Revision of Sheet No. 122-1 P.U.C. Oregon No. E-18 Canceling First Revision of Sheet No. 122-1 PURPOSE SCHEDULE 122 RENEWABLE RESOURCES AUTOMATIC ADJUSTMENT CLAUSE

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION IN THE MATTER OF THE APPLICATION FOR A CUSTOMER RELEASE FROM WOODRUFF ELECTRIC COOPERATIVE CORPORATION TO OF PIVOT WELLS BELONGING TO WAYNE WILKISON PREPARED

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY DAVID A. LOW. on behalf of

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY DAVID A. LOW. on behalf of BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN PUBLIC SERVICE COMPANY S APPLICATION FOR REVISION OF ITS RETAIL RATES UNDER ADVICE NOTICE NO., SOUTHWESTERN PUBLIC SERVICE

More information

Included in this Stakeholder Information Package:

Included in this Stakeholder Information Package: Who can you contact for more information? Yellowhead Area Transmission Reinforcement: TERA Environmental Consultants Dave Sare Phone: 403-538-5734 Email: dsare@teraenv.com Drayton Valley Area AltaLink

More information

PREPARED DIRECT TESTIMONY

PREPARED DIRECT TESTIMONY Application No.: A.0-04- Exhibit No.: SDG&E-4 Witness: William V. Torre In the Matter of San Diego Gas & Electric Company s Application for Authorization to (1) to Participate in the Steam Generator Replacement

More information

COMPANY AND WORKFORCE

COMPANY AND WORKFORCE COMPANY AND WORKFORCE Workforce Totals by Job Classification and State (as of year-end 2017) The following table includes all full-time, part-time and temporary employees of Xcel Energy, but excludes contractors

More information

SunZia Southwest Transmission Project

SunZia Southwest Transmission Project SunZia Southwest Transmission Project SunZia Project Update for the Southern Arizona Economic Development Group September 12, 2017 SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 0 SouthWestern

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal TransWest Express Transmission AC and DC Project 2018 2019 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN PUBLIC SERVICE COMPANY S APPLICATION REQUESTING APPROVAL TO RETIRE AND ABANDON ITS CARLSBAD GENERATING STATION, SOUTHWESTERN

More information

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD In re : : Docket No. SB-00-0 () : Testimony of David M. Campilii, P.E. June, 00 PROV-- 0 0 TESTIMONY OF DAVID M. CAMPILII,

More information

SunZia Southwest Transmission Project

SunZia Southwest Transmission Project SunZia Southwest Transmission Project SunZia Project Update for the 9 th Annual Transmission Summit West October 13, 2017 SUNZIA SOUTHWEST TRANSMISSION PROJECT OCTOBER 13, 2017 0 SouthWestern Power Group

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY RICHARD M. LUTH. on behalf of

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY RICHARD M. LUTH. on behalf of BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN PUBLIC SERVICE COMPANY S APPLICATION FOR REVISION OF ITS RETAIL RATES UNDER ADVICE NOTICE NO., SOUTHWESTERN PUBLIC SERVICE

More information

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE LIBERTY UTILITIES (GRANITE STATE ELECTRIC) CORP. d/b/a LIBERTY UTILITIES

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE LIBERTY UTILITIES (GRANITE STATE ELECTRIC) CORP. d/b/a LIBERTY UTILITIES STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE 17-058 LIBERTY UTILITIES (GRANITE STATE ELECTRIC) CORP. d/b/a LIBERTY UTILITIES Request for Approval of Energy Supply Solicitation and Resulting Rates

More information

VERMONT ELECTRIC POWER COMPANY (VELCO)

VERMONT ELECTRIC POWER COMPANY (VELCO) TRANSMISSION PROJECTS: AT A GLANCE Vermont Electric Power Company (VELCO) VERMONT ELECTRIC POWER COMPANY (VELCO) VELCO was formed in 1956 when local utilities joined together to create the nation s first

More information

7.7 Southeast Zone. Transmission Projects Report Section 7: Needs

7.7 Southeast Zone. Transmission Projects Report Section 7: Needs 7.7 Southeast Zone The following table provides a list of transmission needs identified in the Southeast Zone and the map on the following page shows the location of each item in the table. Southeast Zone

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016 Decision 21481-D01-2016 October 18, 2016 Alberta Utilities Commission Decision 21481-D01-2016 Proceeding 21481 Application 21481-A001 October 18, 2016 Published by the: Alberta Utilities Commission Fifth

More information

BEMIDJI GRAND RAPIDS 230-KV TRANSMISSION LINE

BEMIDJI GRAND RAPIDS 230-KV TRANSMISSION LINE BEMIDJI GRAND RAPIDS 230-KV TRANSMISSION LINE Project Overview and Need The Bemidji-Grand Rapids 230-kV transmission line was fully energized in September of 2012 to improve reliability for the Red River

More information

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis Terry Blackwell Page 1 of 5 Education 1977 North Carolina State University BS, Electrical Engineering Power Systems emphasis Professional Qualifications 1977 PE-Professional Engineer Business Experience

More information

Arizona Energy Consortium Conference

Arizona Energy Consortium Conference SunZia Southwest Transmission Project SunZia and Potential Impacts of Regionalization Arizona Energy Consortium Conference SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 2018 0 SunZia: 500kV Project delivering

More information

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE 07-097 PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE Petition for Adjustment of Stranded Cost Recovery Charge Order Following Hearing O R D E R N O. 24,872

More information

DOCKET NO. DIRECT TESTIMONY of JOHN S. FULTON. on behalf of SOUTHWESTERN PUBLIC SERVICE COMPANY. April 29, (Filename: FultonDirect.

DOCKET NO. DIRECT TESTIMONY of JOHN S. FULTON. on behalf of SOUTHWESTERN PUBLIC SERVICE COMPANY. April 29, (Filename: FultonDirect. Page 1 of 23 DOCKET NO. JOINT REPORT AND APPLICATION OF SHARYLAND UTILITIES, L.P., SHARYLAND DISTRIBUTION & TRANSMISSION SERVICES, L.L.C., AND SOUTHWESTERN PUBLIC SERVICE COMPANY FOR APPROVAL OF PURCHASE

More information

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS. 25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context indicates otherwise, this section and 25.212 of this title (relating to Technical Requirements

More information

Renewable Energy Choices

Renewable Energy Choices More customers joined our renewable choice programs in 2017, with participation reaching more than 150,000 as program choices increased. CUSTOMER SOLUTIONS Renewable Energy Choices Our Approach We recognize

More information

Sales and Use Transportation Tax Implementation Plan

Sales and Use Transportation Tax Implementation Plan Sales and Use Transportation Tax Implementation Plan Transportation is more than just a way of getting from here to there. Reliable, safe transportation is necessary for commerce, economic development,

More information

The Capital Grid Project:

The Capital Grid Project: The Capital Grid Project: Building Tomorrow s Energy Grid Today Lamond- Riggs Citizens Association October 2, 2017 Agenda Welcome How Safe, Clean, and Affordable Energy is Delivered Our Current System

More information

FILED. IN THE MATfER OF THE APPLICATION OF 1 AND CONSTRUCT A 161 KV TRANSMISSION LINE )

FILED. IN THE MATfER OF THE APPLICATION OF 1 AND CONSTRUCT A 161 KV TRANSMISSION LINE ) BEFORE THE ARKANSAS PUBLlC SERVCE COMMSSON N THE MATfER OF THE APPLCATON OF 1 OKLAHOMA GAS AND ELECTRC COMPANY 1 FOR A CERTFCATE OF PUBLC CONVENENCE ) DOCKET NO. AND NECESSTY TO UPGRADE, OPERATE 1 AND

More information

Xcel Energy s Energy Efficiency Programs. Derek Shockley Trade Relations Manager Commercial and Industrial

Xcel Energy s Energy Efficiency Programs. Derek Shockley Trade Relations Manager Commercial and Industrial Xcel Energy s Energy Efficiency Programs Derek Shockley Trade Relations Manager Commercial and Industrial Driver: Colorado s Energy Needs In the last decade: Up 39% Up 15% Up 19% Number of Customers Electric

More information

STATE OF NEW HAMPSHIRE BEFORE THE NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION RE: PENNICHUCK WATERWORKS, INC. DW 13-

STATE OF NEW HAMPSHIRE BEFORE THE NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION RE: PENNICHUCK WATERWORKS, INC. DW 13- STATE OF NEW HAMPSHIRE BEFORE THE NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION RE: PENNICHUCK WATERWORKS, INC. 2013 WATER INFRASTRUCTURE AND CONSERVATION ADJUSTMENT FILING DIRECT TESTIMONY OF DONALD L. WARE

More information

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 TODAY WE LL TALK ABOUT Our challenges and how we re meeting them Why we re building this project Our planning process and considerations

More information

Minnesota Biennial Transmission. Zone Meeting 8

Minnesota Biennial Transmission. Zone Meeting 8 Minnesota Biennial Transmission Plan Zone Meeting 8 Today s Agenda Purpose of meeting Transmission What is it? How it works? Why improve it? System and Zone Overview Deficiencies Improvement Alternatives

More information

Community Shared Solar for Local Governments

Community Shared Solar for Local Governments Community Shared Solar for Local Governments Holly Lahd, Minnesota Department of Commerce, Division of Energy Resources Lissa Pawlisch, Clean Energy Resource Teams (CERTs) 2013 Solar Energy Legislation

More information

Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary

Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Prepared

More information

STATE OF NEW HAMPSHIRE Inter-Department Communication

STATE OF NEW HAMPSHIRE Inter-Department Communication STATE OF NEW HAMPSHIRE Inter-Department Communication DATE: February 11, 2010 AT (OFFICE): NHPUC FROM: Torn Frantz Director, Electric Division SUBJECT: DE 09-277: Petition by Public Service Company of

More information

Project Title: Lowertown Ballpark (CHS Field) Solar Arrays Contract Number: EP4-34 Milestone Number: 1 Report Date: June 21, 2016

Project Title: Lowertown Ballpark (CHS Field) Solar Arrays Contract Number: EP4-34 Milestone Number: 1 Report Date: June 21, 2016 DEPARTMENT OF PARKS AND RECREATION DESIGN AND CONSTRUCTION CITY OF SAINT PAUL Mayor Christopher B. Coleman 400 City Hall Annex 25 West 4 th Street Saint Paul, Minnesota 55102 www.stpaul.gov/parks Telephone:

More information

DEPARTMENT OF TRANSPORTATION. Statutory Amendments Affecting Transportation of Agricultural Commodities and Farm Supplies

DEPARTMENT OF TRANSPORTATION. Statutory Amendments Affecting Transportation of Agricultural Commodities and Farm Supplies DEPARTMENT OF TRANSPORTATION [4910-EX-P] Federal Motor Carrier Safety Administration 49 CFR Chapter III Statutory Amendments Affecting Transportation of Agricultural Commodities and Farm Supplies AGENCY:

More information

STH 60 Northern Reliever Route Feasibility Study Report

STH 60 Northern Reliever Route Feasibility Study Report #233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development

More information

Appendix D Black Hills Project Summary

Appendix D Black Hills Project Summary Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain

More information

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment For NPCC Governmental / Regulatory Affairs Advisory Group May 21 st, 2009 ON IT Executive Summary Engineers from Con

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

Energy Technical Memorandum

Energy Technical Memorandum Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter

More information

Agenda. Utility Undergrounding Strategies & Laguna Canyon Road Master Plan

Agenda. Utility Undergrounding Strategies & Laguna Canyon Road Master Plan Utility Undergrounding Strategies & Laguna Canyon Road Master Plan January 17, 2017 City Council Meeting 2 Agenda Progress since March 2016 Status of undergrounding and road widening between El Toro Rd.

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82 Decision 21447-D01-2016 August 23, 2016 Decision 21447-D01-2016 Proceeding 21447 Application 21447-A001 August 23, 2016 Published by the: Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary,

More information

2200 IDS Center 80 South 8th Street Minneapolis MN tel fax

2200 IDS Center 80 South 8th Street Minneapolis MN tel fax BRIGGS B R I G G S labo M O R G A N 2200 IDS Center 80 South 8th Street Minneapolis 55402-2157 tel 612.977.8400 fax 612.977.8650 EXHIBIT 40 3,2014 kchurch@briggs.com ELECTRONIC FILING Hon. Steve M. Mihalchick

More information

CHAPTER 9: VEHICULAR ACCESS CONTROL Introduction and Goals Administration Standards

CHAPTER 9: VEHICULAR ACCESS CONTROL Introduction and Goals Administration Standards 9.00 Introduction and Goals 9.01 Administration 9.02 Standards 9.1 9.00 INTRODUCTION AND GOALS City streets serve two purposes that are often in conflict moving traffic and accessing property. The higher

More information

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat Galapagos San Cristobal Wind Project VOLT/VAR Optimization Report Prepared by the General Secretariat May 2015 Foreword The GSEP 2.4 MW Wind Park and its Hybrid control system was commissioned in October

More information

Application for Commission Approval to Construct a Generating Station Pursuant to Public Utilities Article Section and

Application for Commission Approval to Construct a Generating Station Pursuant to Public Utilities Article Section and Application for Commission Approval to Construct a Generating Station Pursuant to Public Utilities Article Section 7-207.1 and 7-207.2 APPLICABILITY The Public Service Commission of Maryland ( Commission

More information

Coalspur Mines (Operations) Ltd.

Coalspur Mines (Operations) Ltd. Decision 22744-D01-2017 Application for an Exemption Under Section 24 of the Hydro and Electric Energy Act October 5, 2017 Alberta Utilities Commission Decision 22744-D01-2017 Application for an Exemption

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

Ronnie van Eeden. Senior Mining Engineer. Overview

Ronnie van Eeden. Senior Mining Engineer. Overview Senior Mining Engineer Overview is a qualified Mining Engineer with other commercial qualifications. He has 46 years of experience in the coal industry working for mining houses, the smaller coal industry,

More information

West Station-West Cañon 115 kv Transmission Project

West Station-West Cañon 115 kv Transmission Project West Station-West Cañon 115 kv Transmission Project Project Sponsor: Additional Project Participants: Project Description: Black Hills Colorado Electric New 115 kv line from West Station to West Cañon

More information

Guide to Wisconsin Community Solar Welcome to Solar*Connect Community SM

Guide to Wisconsin Community Solar Welcome to Solar*Connect Community SM Guide to Wisconsin Community Solar Welcome to Solar*Connect Community SM Table of Contents Solar*Connect Community... 3 Make Solar*Connect Community Your Choice... 4 Benefits of Solar*Connect Community...

More information

Currant Lake Transmission Project

Currant Lake Transmission Project Currant Lake Transmission Project September 2010 Why are you receiving this project information package? New transmission facilities are needed in the Monitor area of southeastern Alberta. ATCO Electric

More information

This page is intentionally left blank.

This page is intentionally left blank. This page is intentionally left blank. Bipole III Southern Ground Electrode Line Route Selection Introduction Manitoba Hydro has recently selected a route for the southern ground electrode line (Map 1).

More information

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES: TransWest Express Transmission Project TABLE OF CONTENTS 7.0 DESIGN OPTIONS... 7-1 7.1 OVERVIEW OF DESIGN OPTIONS... 7-1 7.2 DESIGN OPTIONS PURPOSE AND NEED AND DESIGN CHARACTERISTICS... 7-4 7.2.1 Design

More information

Committee Report. Transportation Committee. Business Item No

Committee Report. Transportation Committee. Business Item No Committee Report Business Item No. 2015-280 Transportation Committee For the Metropolitan Council meeting of December 9, 2015 Subject: METRO Blue Line Extension (Bottineau Light Rail Transit) Revised Scope

More information

ADDITIONAL UTILITY RELOCATION COSTS ARE MISSING FROM THE ESTIMATE.

ADDITIONAL UTILITY RELOCATION COSTS ARE MISSING FROM THE ESTIMATE. Comment to CHSRA Missing Utility Costs Page!1 May 7, 2018 COMMENT FOR CHSRA BUSINESS PLAN: ADDITIONAL UTILITY RELOCATION COSTS ARE MISSING FROM THE ESTIMATE. HIGH VOLTAGE TOWERS THAT CARRY ELECTRICITY

More information

Business Item No

Business Item No Business Item No. 2014-162 Metropolitan Council Meeting date: July 9, 2014 Subject: Southwest Light Rail Transit (Green Line Extension): Kenilworth Corridor Public Ownership Memorandum of Understanding

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Regional Reliability Standards ) VAR-002-WECC-2 and VAR-501-WECC-2 ) Docket No. RD15-1-000 COMMENTS OF DOMINION RESOURCES SERVICES,

More information

July 24, Docket No EI FPL s Petition for Approval of a New Depreciation Class and Rate for Energy Storage Equipment

July 24, Docket No EI FPL s Petition for Approval of a New Depreciation Class and Rate for Energy Storage Equipment John T. Butler Assistant General Counsel-Regulatory Florida Power & Light Company 700 Universe Boulevard Juno Beach, FL 33408-0420 (561) 304-5639 (561) 691-7135 (Facsimile) John.Butler@fpl.com July 24,

More information

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION ) ) ) ) ) ) ) ) DIRECT TESTIMONY JON PAUL DE LA HOUSSAYE PROJECT MANAGER CAPITAL PROJECTS - TRANSMISSION

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION ) ) ) ) ) ) ) ) DIRECT TESTIMONY JON PAUL DE LA HOUSSAYE PROJECT MANAGER CAPITAL PROJECTS - TRANSMISSION APSC FILED Time: //0 :: PM: Recvd //0 :0: PM: Docket -Doc. BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION IN THE MATTER OF THE APPLICATION OF ENTERGY ARKANSAS, INC. FOR A CERTIFICATE OF PUBLIC CONVENIENCE

More information

IC Definitions Sec. 1. The definitions in this chapter apply throughout this article. As added by P.L , SEC.78.

IC Definitions Sec. 1. The definitions in this chapter apply throughout this article. As added by P.L , SEC.78. IC 9-32-2 Chapter 2. Definitions IC 9-32-2-1 Definitions Sec. 1. The definitions in this chapter apply throughout this article. IC 9-32-2-2 ( by P.L.151-2015, SEC.30.) IC 9-32-2-3 "Advisory board" Sec.

More information

Background Information for MPRB Community Advisory Committee for 2010 Southwest Light Rail Transit Project DEIS Comment Letter Section 2

Background Information for MPRB Community Advisory Committee for 2010 Southwest Light Rail Transit Project DEIS Comment Letter Section 2 Background Information for MPRB Community Advisory Committee for 2010 Southwest Light Rail Transit Project DEIS Comment Letter Section 2 1 2. SW LRT Corridor Overview Source: http://www.southwesttransitway.org/home.html

More information

STATE OF MINNESOTA ENVIRONMENTAL QUALITY BOARD MEQB DOCKET NO. MP-HVTL-EA-1-99

STATE OF MINNESOTA ENVIRONMENTAL QUALITY BOARD MEQB DOCKET NO. MP-HVTL-EA-1-99 STATE OF MINNESOTA ENVIRONMENTAL QUALITY BOARD In the Matter of the Exemption Application by Minnesota Power for a 345/230 kv High Voltage Transmission Line Known as the Arrowhead Project. MINNESOTA ENVIRONMENTAL

More information

Large Scale Solar Integration

Large Scale Solar Integration Large Scale Solar Integration Experiences and Coming Changes in Distributed Energy Resource Interconnections October 26 th, 2017 Overview Background on Xcel Energy Expansion of Solar in Minnesota Changes

More information

DART Priorities Overview

DART Priorities Overview City of Dallas Transportation and Trinity River Project Committee DART Priorities Overview Gary C. Thomas President/Executive Director August 10, 2015 City of Dallas Transportation & Trinity River Committee

More information

Susan MacAdams Transit Consultant 269 S. Beverly Drive, Unit 1187 Beverly Hills, CA 90212

Susan MacAdams Transit Consultant 269 S. Beverly Drive, Unit 1187 Beverly Hills, CA 90212 Susan MacAdams Transit Consultant 269 S. Beverly Drive, Unit 1187 Beverly Hills, CA 90212 March 19, 2014 The Honorable Jeff Denham 1730 Longworth Building House Office Building United States House of Representatives

More information

Please Refer to Attached Sample Form

Please Refer to Attached Sample Form Pacific Gas and Electric Company San Francisco, California U 39 Revised Cal. P.U.C. Sheet No. 32105-E Cancelling Revised Cal. P.U.C. Sheet No. 28313-E Electric Sample Form No. 62-0686 Application for Service

More information

Bohn to Kettle River Transmission Project

Bohn to Kettle River Transmission Project April 2012 Why are you receiving this project information package? New transmission facilities are needed in the Fort McMurray area. ATCO Electric has been directed by the Alberta Electric System Operator

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) APPLICATION

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) APPLICATION BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Great Oaks Water Company (U-162-W for an Order establishing its authorized cost of capital for the period from July 1, 2019

More information

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION June 7, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments

More information

LIST OF OPEN TRAINING TRAINING PLANNER 2016/2017 Course location: Lagos, Abuja, Port Harcourt.

LIST OF OPEN TRAINING TRAINING PLANNER 2016/2017 Course location: Lagos, Abuja, Port Harcourt. JANUARY 2016 Credit Management and Collection of 4-6 11-15 14-27 Abuja/Lagos/PH 150,000 220,000 320,000 Receivables Developing Executive Management 4-6 11-15 14-27 Abuja/Lagos/PH 150,000 220,000 320,000

More information

Minnesota Biennial Transmission. Zone Meeting 8

Minnesota Biennial Transmission. Zone Meeting 8 Minnesota Biennial Transmission Plan Zone Meeting 8 Today s Agenda Purpose of meeting Transmission What is it? How it works? Why improve it? System and Zone Overview Deficiencies Improvement Alternatives

More information

MILESTONE SUMMARY REPORT Project funding provided by customers of Xcel Energy through a grant from the Renewable Development Fund

MILESTONE SUMMARY REPORT Project funding provided by customers of Xcel Energy through a grant from the Renewable Development Fund Project Title: Sodium Sulfur Battery Energy Storage Contract Number: RD3-1 Milestone Number: 1 Report Date: May 0, 009 Reporting Period: September 007 April 008 Milestone Description: Milestone 1 - Specifications

More information

Summer Reliability Assessment Report Electric Distribution Companies Perspective

Summer Reliability Assessment Report Electric Distribution Companies Perspective Energy Association of Pennsylvania Summer Reliability Assessment Report Electric Distribution Companies Perspective to the Pennsylvania Public Utility Commission June 9, 2011 Harrisburg, PA Terrance J.

More information

Review of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST

Review of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION In re: Staff's Second Data Request on OUC' s Review of Electric Utility Hurricane Preparedness and Restoration Actions Docket No. 20170215-EU Filed: January

More information

Michigan Renewable Energy Case Study

Michigan Renewable Energy Case Study Michigan Renewable Energy Case Study NARUC ENERGY REGULATORY PARTNERSHIP WITH GEORGIAN NATIONAL ENERGY AND WATER SUPPLY REGULATORY COMMISSION TBILISI, GEORGIA JANUARY 27-31, 2014 GREG R. WHITE, COMMISSIONER

More information

EMERGING REQUIREMENTS

EMERGING REQUIREMENTS Page of 0 EMERGING REQUIREMENTS EXTERNALLY INITIATED PLANT RELOCATIONS THESL distributes electricity to residential, commercial, and industrial customers via overhead and underground infrastructure. This

More information

Regulatory Treatment Of Recoating Costs

Regulatory Treatment Of Recoating Costs Regulatory Treatment Of Recoating Costs Prepared for the INGAA Foundation, Inc., by: Brown, Williams, Scarbrough & Quinn, Inc. 815 Connecticut Ave., N.W. Suite 750 Washington, DC 20006 F-9302 Copyright

More information

Frequently Asked Questions Trico Proposed Net Metering Tariff Modifications

Frequently Asked Questions Trico Proposed Net Metering Tariff Modifications Frequently Asked Questions Trico Proposed Net Metering Tariff Modifications 1. Who is a self-generation or Net Metering Member? This is a Member who has installed grid-connected renewable generation, such

More information

welcome to the BC Hydro community open house

welcome to the BC Hydro community open house welcome to the BC Hydro community open house Dawson Creek/ Chetwynd Area Transmission ProjecT Open House welcome Dawson Creek/Chetwynd Area Transmission Project (DCAT) The purpose of this open house is

More information

The University of St. Thomas Renewable Energy Facility (USTREF)

The University of St. Thomas Renewable Energy Facility (USTREF) The University of St. Thomas Renewable Energy Facility (USTREF) HIGHER EDUCATION BLOCK GRANT CONTRACT WITH THE MINNESOTA STATE COLLEGES AND UNIVERSITIES RENEWABLE DEVELOPMENT FUND CYCLE 4 GRANT CONTRACT

More information

Re: California Independent System Operator Corporation

Re: California Independent System Operator Corporation California Independent System Operator October 21, 2014 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent

More information

Pacific Gas and Electric Company TM

Pacific Gas and Electric Company TM Pacific Gas and Electric Company TM Evelyn C. Lee Mailing Address P.O. Box 7442 San Francisco, CA 94120 Street/Courier Address Law Department 77 Beale Street San Francisco, CA 94105 (415) 973-2786 Fax:

More information

Senior Substation Project Lead Engineer

Senior Substation Project Lead Engineer Senior Substation Project Lead Engineer Are you ready to be a technology pioneer? Oil and gas factories 3000 meters underwater, heavy locomotive traction motors, electric vehicle chargers that deliver