OTAHUHU-MANGERE-ROSKILL- HEPBURN ROAD 110 KV CIRCUITS
|
|
- Gwendoline McDonald
- 5 years ago
- Views:
Transcription
1 NORTH AUCKLAND AND NORTHLAND GRID UPGRADE PROJECT ATTACHMENT J OTAHUHU-MANGERE-ROSKILL- HEPBURN ROAD 110 KV CIRCUITS UPGRADE WITH HIGH TEMPERATURE LOW SAG CONDUCTOR September 2007
2 Contents 1 INTRODUCTION 3 2 METHODOLOGY 4 3 CONDUCTOR BEHAVIOUR Existing Zebra ACSR Existing Wolf ACSR Current Flow Magnetic Field 7 4 VISUAL IMPACT 8 5 FEASIBILITY 8 6 COSTING 9 7 SUMMARY 10 8 CONCLUSIONS 10 September 2007 Transpower 2007 Page 2 of 10
3 1 Introduction The purpose of this document is to summarise the analysis undertaken at a very high level, with respect to re-conductoring the following circuits with High Temperature Low Sag (HTLS) conductors. MNG-OTA 1 & 2 (3.7km) (MNG-OTA A) MNG-ROS 1 & 2 (11.7km) (MNG-ROS A) OTA-ROS 1 & 2 (19.7km) (OTA-PEN B, PEN-ROS A) HEP-ROS 1 & 2 (7.5 & 7.1km) (HEN-ROS A, HEP-ROS A) HEP-HEN 1, 2,3,& 4 (6.7km) (HEN-ROS A, HEN-HEP A) The Northland and North Auckland loads are presently supplied by a two-circuit 220kV line between Otahuhu and Henderson (HEN-OTA A). The (N-1) capacity of these circuits is forecast to be exceeded around Transpower are looking at alternative options for providing a secure supply to these areas beyond The option of having a cross-harbour cable route between Penrose and Albany is presently being investigated. However, alternatives are required to be investigated as part of a complete assessment of the options. This document investigates at a very high level the re-conductoring of the existing 110kV lines between Otahuhu and Henderson as alternative to the cross harbour cables. It is a companion to the similar investigation for the HEN-OTA 220kV line undertaken in August 2007 (see Attachment I). The scope of this study is to investigate the feasibility of using HTLS conductors to achieve maximum possible line ratings without any modification to the existing structures, and whilst maintaining the visual appearance of the lines with respect to sag and conductor diameter, or without increasing conductor sags beyond those presently in place. The existing conductor types are as follows Line Conductor MNG-OTA 1 & 2 Duplex 75 C MNG-ROS 1 & 2 Simplex 75 C OTA-ROS 1 & 2 Simplex 75 C HEP-ROS 1 & 2 Simplex 75 C HEP-HEN 1, 2,3,& 4 Simplex 75 C Table 1-1. Existing 110kV Conductors Costs have been estimated, to an accuracy of +/-50%. This includes costs related to materials and construction and does not include for property costs or consenting costs. September 2007 Transpower 2007 Page 3 of 10
4 2 Methodology Identify one of each of the following High Temperature Low Sag (HTLS) conductor types for investigation. ACSS - Aluminium Conductor Steel Supported ZTACIR - Zirconium Alloy Thermally Resistant Invar Reinforced TACSR/ACS - Thermally Resistant ACSR ACCR - Aluminium Conductor Composite Reinforced ACCC/TW - Aluminium Conductor Composite Core Ensure the chosen conductors satisfy the following general requirements: Overall diameter similar to the existing conductor Conductor maximum horizontal tension not to exceed existing conductor tension (to reduce impact on structures and foundations) Conductor Sag at the maximum operating temperature to be limited to that of the existing conductor Investigate the conductors in PLS-CADD using a representative span. Establish the maximum operating temperature that gives the same or less sag than the existing conductors. Investigate the feasibility of using the chosen conductors on the 5 Lines with particular reference to the following aspects, compared to the existing ACSR conductor: EMF levels Conductor swing Maximum continuous operating temperature without loss of strength and the corresponding MVA rating Estimate the total cost for design, material supply (including conductor, insulators, hardware, connectors etc) and installation, for each conductor option. Note, while similar sized conductors to existing have been analysed, in order to exclude a need to strengthen towers or foundations, it must be considered that some structures may be overloaded in their as-built condition. Detailed analysis may identify a need to strengthen at the time of re-conductoring. No allowance has been made for this. The following conductors were selected for investigation: Type Name Stranding Diameter (mm) Mass (N/m) UTS (kn) Max operating Temperature ( C) ACSR/GZ Zebra 54/ ACSS (54/7) Condor 54/ ZTACIR Drake 26/ Zebra TACSR/ACS (Lumpi) 54/ ACCR 795-T16 26/ ACCC/TW Drake 22/1? September 2007 Transpower 2007 Page 4 of 10
5 ACSR/GZ Wolf 30/ ACSS (54/7) Oriole 30/ ZTACIR Invar160 30/ TACSR/ACS Wolf (Lumpi) 30/ ACCR 336-T16 26/ ACCC/TW Linnet 22/1? Table 2-1. Standard and High Temperature Conductors used in Investigation 3 Conductor Behaviour 3.1 Existing Zebra ACSR Based on the average MNG-OTA A span length of 256m the sag and blowout of the various conductors has been calculated for this line. The crept tension has been matched to the existing tension in the Zebra ACSR/GZ to ensure that the towers will not be overloaded. It can be seen that in all cases the sag and blowout of the chosen conductors is similar or less than that of the existing Zebra. Type Name Stringing Tension (%UTS) Operating Temperature ( C) Max Op. Temp (m) Difference to Existing (m) Blowout from centreline 35 C) Difference to Existing (m) ACSR/GZ Zebra 21% ACSS Condor 37% ZTACIR Drake 20% TACSR/ACS Zebra (Lumpi) 21% ACCR 795-T16 20% ACCC/TW Drake 15% Table 3-1. Physical Parameters for Selected High Temperature Conductors (Zebra Replacements) The initial tensions have been checked against table 6.3 "Overhead conductor safe design tension with respect to aeolian vibrations" Cigre Task Force B , June 2005 to ensure there will be no issues with Aeolian Vibration when the conductor is first installed. 3.2 Existing Wolf ACSR The remaining lines are presently strung with simplex Wolf ACSR ranging in tension from 12.3kN to 15.0kN at 10 C, and average span lengths ranging from 207m to 277m. September 2007 Transpower 2007 Page 5 of 10
6 Based on the average MNG-ROS span length of 277m, and a conductor tension of 15kN (based on ALS survey data) the sag and blowout of the various conductors has been calculated. The crept stringing tension has been matched to the existing tension in the Wolf ACSR/GZ to ensure that the towers will not be overloaded. Type Name Stringing Tension (%UTS) Operating Temperature ( C) Max Op. Temp (m) Difference to Existing (m) Blowout from centreline 35 C) Difference to Existing (m) ACSR/GZ Wolf 22% ACSS Oriole 23% ZTACIR Invar160 24% TACSR/ACS Wolf (Lumpi) 22% ACCR 336-T16 24% ACCC/TW Linnet 21% Table 3-2. Physical Parameters for Selected High Temperature Conductors (Wolf Replacements) The Initial tensions have been checked against table 6.3 "Overhead conductor safe design tension with respect to aeolian vibrations" Cigre Task Force B , June 2005 to ensure there will be no issues with Aeolian Vibration when the conductor is first installed 3.3 Current Flow The possible current flow achievable with the use of high temperature conductors is given below. These are LATTA summer ratings (30 C ambient, 0.6m/s wind) Type Name Operating Temperature ( C) Latta Current Summer Rating (Amps) Latta Power Summer Rating (MVA) ACSR/GZ Zebra ACSS Condor ZTACIR Drake TACSR/ACS Zebra (Lumpi) ACCR 795-T ACCC/TW Drake Rank Type Name Operating Temperature ( C) Latta Current Summer Rating (Amps) Latta Power Summer Rating (MVA) ACSR/GZ Wolf ACSS Oriole ZTACIR Invar TACSR/ACS Wolf (Lumpi) ACCR 336-T ACCC/TW Linnet Rank Table 3-1. Current Ratings of Selected High Temperature Conductors September 2007 Transpower 2007 Page 6 of 10
7 3.4 Magnetic Field The increase in current made possible by the use of high temperature conductors will increase the magnetic field generated by the lines. As there is no change in voltage, there is no change in the electric fields. There are four main tower contract types used on the 5 lines C26, C5532, C460 and C252. The duplex Zebra Line (MNG-OTA A) has C460 towers. The other 3 contract types have been investigated with respect to the Wolf, and it has been found the contract type with the highest magnetic fields is C252 (HEP-ROS and HEP-HEN) due to greater phase spacing The plots below show magnetic field levels at various ratings for the Zebra and the worst case Wolf structures (C252). All are within the ICNIRP levels. These plots are highly conservative as they are based on the mid span sag point and an assumed 100% current in each circuit. In reality the system would be operated at maximum of approximately 50% of capacity and could rise up to 100% only when one circuit is out of service MNG-OTA A reconductoring - Both circuits in service Magnetic Field Profile under 6.5 m clearance Duplex Drake 569 MVA 80 Magnetic Field (µt) PRELIMINARY DRAFT! FOR DISCUSSION ONLY! Please discuss with Pre- Approval engineering before making any conclusions relating to this information. Duplex Condor 490 MVA Existing Duplex 358 MVA Distance from Centre (m) MF - Existing 75 deg C MF A MF A 100µT limit Figure 1 Magnetic Field Profile Comparison of High Temperature and Standard Conductors Zebra Tower Structures September 2007 Transpower 2007 Page 7 of 10
8 Auckland 110 kv HTLS reconductoring C252 - Both circuits in service Magnetic Field Profile under 6.5 m clearance Magnetic Field (µt) PRELIMINARY DRAFT! FOR DISCUSSION ONLY! Please discuss with Pre- Approval engineering before making any conclusions relating to this information Linnet 210 MVA Oriole 185 MVA Invar MVA Existing Simplex 92 MVA Distance from Centre (m) MF - Existing 75 deg C MF - 726A MF - 970A MF- 1103A 100µT limit Figure 2 Magnetic Field Profile Comparison of High Temperature and Standard Conductors Wolf Tower Structures 4 Visual Impact In order to ensure that there is very little change in the visual impact of the line, the conductors assessed have similar diameters to the existing ACSR and the lines have been sagged to match the sag and swing as closely as possible to the existing conductors. 5 Feasibility The stringing of conductors over heavily built up areas and a large number of roads will incur significant hurdling costs and other construction difficulties. In order to maintain safe stringing practices, it may be required that both circuits on the line being restrung are out of service during stringing. If however it is a requirement for one circuit to be continually in service, then a detailed study will be required, including input from the FSO and local maintenance contractors, to determine suitable stringing practices. This is expected to result in additional costs to the stringing works, in the form of special construction practices, as well as increased risk. Sign-off from higher management is likely to be required with respect to the increased risk profile associated with stringing within close proximity of live conductors. September 2007 Transpower 2007 Page 8 of 10
9 The analysis outlined in this document takes into consideration the HTLS technology currently available in use throughout the world. It is in no way to be taken as an endorsement of this technology by PAE (lines), nor a recommendation for its use. Indeed, significant research, testing and study of related aspects (such as constructability techniques, reliability, maintenance, availability of parts etc.) would need to be carried out prior to addition of an HTLS conductor to the Transpower suite of conductors. This in itself may make the use of HTLS conductors in this situation unfeasible, depending on the timeframes involved. 6 Costing For the purposes of this investigation only those conductors of similar size to the existing conductors have been assessed. They have been strung at similar tensions to the existing conductors. As such, the transverse and longitudinal loading is expected to be similar, and it has been assumed no tower or foundation strengthening or replacement would be required. Type Name Total Cost ($M) Rank ACSS Condor ZTACIR Drake TACSR/ACS Zebra (Lumpi) ACCR 795-T ACCC/TW Drake Table 6-1 Costs of High Temperature Conductors for MNG-OTA 1 & 2 Circuits Type Name Total Cost ($M) Rank ACSS Oriole 24 2 ZTACIR Invar TACSR/ACS Wolf (Lumpi) 24 1 ACCR 3m336-T ACCC/TW Linnet 32 4 Table 6-2 Costs of High Temperature Conductors for MNG-ROS 1 & 2,OTA-ROS 1 & 2, HEP-ROS 1 & 2 and HEP-HEN 1,2,3 & 4 Circuits Costs have been estimated, to an accuracy of +/-50%. It must be noted there is significant uncertainty about the cost of stringing, and about the cost of some of the more experimental conductors (ACCR & ACCC). The tabulated values above include costs related to materials and construction. Note that these estimates do not allow for non engineering impacts such as E & P, outages, interest etc, nor are those associated with progressing this technology to a stage where it is accepted as a standard conductor in the Transpower suite. September 2007 Transpower 2007 Page 9 of 10
10 7 Summary Within the constraints of keeping the clearances and tensions similar to the existing line, the advantage of thermally resistant ACSR cannot be utilised. Therefore using TACSR/ACS type conductors offers no advantages over the existing conductor. The ACCC and ACCR composite type of conductors are new on the market, and while they may offer advantages with respect to line rating there have only been a few short line trials worldwide, and the costs are well in excess of the alternatives. ZTACIR type conductors are used in Japan and Korea, and ACSS conductors are becoming more common in the USA. The costs of these types of conductors is less than that of the composite types, and they are considered potentially feasible options. However, significant work would still be required before they could be accepted as standard Transpower conductors. 8 Conclusions This is a very high level investigation and further works will be required before progressing further down this path. The use of HTLS conductor on the Auckland 110kV lines is yet to be determined as feasible from an engineering perspective. All the chosen conductors can be strung with the same or lower sag and blowout, but with higher current flow. The similar diameters ensure the visual impact is minimal. The major difference to the existing line is that the much higher currents result in an increase in the magnetic fields, although a preliminary assessment indicates that all options remain below the ICNIRP limit. The ACCC and the ACCR type conductors are not sufficiently proven at this stage to be considered a reliable option for a core grid lines, and are also the 2 most expensive options. The TACSR does not offer any benefits in this case. It is thought that only ZTACIR and ACSS are suitable for use on the lines investigated. The ZTACIR conductor is approximately 3 times more expensive than the ACSS, although total engineering costs are expected to be within 50%. Of the two, the ACSS conductor has the highest current rating. The overall construction cost is significantly different between the options, ranging in price from approximately $28M for the ACSS to $45M for the ACCR (+/- 50%), excluding E & P, outages, interest etc. The lines are all double circuit lines and could be strung one circuit at a time, with double circuit outages likely to be required. The outage times are difficult to estimate, and would be dependent on the length of the line, which varies from 3.7km to 19.7km, and specific terrain characteristics such as road crossings etc. September 2007 Transpower 2007 Page 10 of 10
National Seminar on New Generation High Performance Conductors. 4 th Dec 14
National Seminar on New Generation High Performance Conductors 4 th Dec 14 Compulsion for alternative why? Limitation of power flow New line ROW Constraint Increasing urbanization left no inlet for critical
More informationLine using HTLS Conductors to increase
Upgradation of 132kV Transmission Line using HTLS Conductors to increase the load transfer capacity. By Srikrushna S. Navlakhe Executive Engineer, EHV Construction cum Operation and Maintenance Zone, MSETCL,
More informationEnhancement of Power Transfer Capability of Existing 400kV Transmission Lines
558 NATIONAL POWER SYSTEMS CONFERENCE, NPSC 22 Enhancement of Power Transfer Capability of Existing 4kV Transmission Lines Rajiv Gandhi, Anish Anand, Y. K. Sehgal, M. Krishnakumar and Anand Mohan Abstract--The
More informationHow the choice of transmission conductor can reduce greenhouse gas emissions.
How the choice of transmission conductor can reduce greenhouse gas emissions. What is the scope of the impact? Complete conversion of the US grid to efficient conductor would eliminate 44 million metric
More informationTHE PROTEAN AND POC-MAST DESIGN
THE PROTEAN AND POC-MAST DESIGN Contents 1. The changing landscape of generation for power transmission and distribution. 2. The Holford rules and recommendations for OHL routing and design. 3. The current
More informationHigh-Temperature Low Sag (HTLS) conductors. for easy Upgrading of Overhead Transmission Lines
Gap-type conductor High-Temperature Low Sag (HTLS) conductors for easy Upgrading of Overhead Transmission Lines J-Power Systems (JPS) is a joint-venture of HITACHI CABLE and SUMITOMO ELECTRIC INDUSTRIES
More informationNEW TREND ON TRANSMISSION POWER LINES AND RELATED STRINGING EQUIPMENT DEVELOPMENT
NEW TREND ON TRANSMISSION POWER LINES AND RELATED STRINGING EQUIPMENT DEVELOPMENT Background Several regions of the world are facing severe pressure on transmission line infrastructure, while the trends
More informationHow Aerospace Technology is Improving the Efficiency, Capacity and Reliability of the Smart Grid
CIGRE US National Committee 2013 Grid of the Future Symposium Boston, Massachusetts October 2013 How Aerospace Technology is Improving the Efficiency, Capacity and Reliability of the Smart Grid Dave Bryant,
More informationTransmission Corporation of Telangana, Jawaharlal Nehru Technological University Hyderabad
ENHANCEMENT OF POWER TRANSFER CAPABILITY OF TRANSMISSION LINES USING HTLS CONDUCTOR 1 M.SHESHAGIRI, 2 B.V.SANKER RAM Transmission Corporation of Telangana, Jawaharlal Nehru Technological University Hyderabad
More informationProtecting. Grid. Integrity. More amps, more confidence. 3M Aluminum Conductor Composite Reinforced (ACCR) High-capacity transmission conductor
3M Aluminum Conductor Composite Reinforced (ACCR) High-capacity transmission conductor Metric Units Protecting Grid Integrity More amps, more confidence 3 3M Aluminum Conductor Composite Reinforced In
More informationHow Aerospace Technology is Improving the Efficiency, Capacity and Reliability of the Smart Grid. D.C. BRYANT 1 CTC Global Corporation United States
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2013 Grid of the Future Symposium How Aerospace Technology is Improving the Efficiency, Capacity and Reliability of the
More informationACCC. Aluminum Conductor Composite Core. High Tension Low Sag Conductors
RELATIVE TO CONVENTIONAL CONDUCTORS Up to Twice the Current Carrying Capacity Greater & Reduced Sag Reduced Line Losses by 25% to 40% or more Increased Spans on Fewer & Shorter Structures High Resistance
More informationLive-line transmission lines upgrade projects. First-in-Africa project
Live-line transmission lines upgrade projects First-in-Africa project Author & presenter: Patrick O Halloran BTECH Manager Technology Services at City Power Johannesburg Abstract This paper covers live-line
More informationMETRO NORTH TRANSMISSION STUDY ELECTRIC AND MAGNETIC FIELD PROFILES (VILLAGE OF ANMORE)
METRO NORTH TRANSMISSION STUDY ELECTRIC AND MAGNETIC FIELD PROFILES (VILLAGE OF ANMORE) File: T2016-6004 METRO NORTH TRANSMISSION STUDY ELECTRIC AND MAGNETIC FIELD PROFILES METRO NORTH TRANSMISSION STUDY
More informationStudy on Economic Partnership Projects. in Developing Countries in FY kV Lines in West Java, in Indonesia SUMMARY.
Study on Economic Partnership Projects in Developing Countries in FY2007 Study on Upgrading Transmission Capacity of Existing 500kV Lines in West Java, in Indonesia SUMMARY March 2008 Tokyo Electric Power
More informationEfficiency, Capacity, Reliability AND Cost-Effective Carbon Reductions: The Multiple Benefits of High Performance Transmission Conductors (HPTC)
Efficiency, Capacity, Reliability AND Cost-Effective Carbon Reductions: The Multiple Benefits of High Performance Transmission Conductors (HPTC) WHY ARE WE HERE? The Transmission System: The Backbone of
More informationInterconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS
Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia
More informationTECHNICAL BRIEF OKLAHOMA GAS & ELECTRIC (OG&E) FIVE TRIBES PECAN CREEK 161 KV LINE
Company: Oklahoma Gas & Electric (OG&E) is a regulated electric utility serving more than 800,000 retail customers in Oklahoma and western Arkansas, and a number of wholesale customers throughout the region.
More informationGridlines. Composite Reinforced. Aluminum Conductor. In This Issue: AECC Uses 3M ACCR to Complete Challenging Upgrades...1
Aluminum Conductor Composite Reinforced Gridlines Summer 2014 In This Issue: AECC Uses 3M ACCR to Complete Challenging Upgrades...1 Arkansas Electric Cooperative Corp. is the latest rural electric co-op
More information15 Nelson-Marlborough Regional Plan
15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant
More informationDRIVER SPEED COMPLIANCE WITHIN SCHOOL ZONES AND EFFECTS OF 40 PAINTED SPEED LIMIT ON DRIVER SPEED BEHAVIOURS Tony Radalj Main Roads Western Australia
DRIVER SPEED COMPLIANCE WITHIN SCHOOL ZONES AND EFFECTS OF 4 PAINTED SPEED LIMIT ON DRIVER SPEED BEHAVIOURS Tony Radalj Main Roads Western Australia ABSTRACT Two speed surveys were conducted on nineteen
More informationUNIVERSITY OF NAIROBI
UNIVERSITY OF NAIROBI COLLEGE OF ARCHITECTURE AND ENGINEERING DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING PROJECT TITLE: UPRATING OF TRANSMISSION LINES-A CASE STUDY OF 132KV DANDORA JUJA RD LINES
More informationInterconnection System Impact Study Report Request # GI
Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010
More informationSPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN
SPN High Value Project PO Route RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN Document History Version Date Details Originator V0.1 20/06/2013 Initial version Chris Winch V0.2
More informationTENSION CLAMPS AND JOINTS. General Wedge tension clamp without jumper guide, for aluminium based conductors... 79
73 Contents General.................................................................................................. 74 Wedge tension clamp without jumper guide, for aluminium based conductors...........................
More informationGeneration Interconnection Facilities Study For
Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015 TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications...
More informationItem L.1 Voltages 1. The consumer voltage must be between +10% and -10% of the nominal national voltage (nnv.)
Village Hydro Specifications Line Distribution Description of Requirement Item L.1 Voltages 1. The consumer voltage must be between +10% and -10% of the nominal national voltage (nnv.) Recommendation 2.
More information3 Existing National Grid
3 Existing National Grid 3.1 Introduction 3.2 Load and generation 3.1 Introduction This chapter provides an overview of New Zealand s existing National Grid as at 28 February 2012 with respect to load
More informationAnnex to the Accreditation Certificate D-PL according to DIN EN ISO/IEC 17025:2005
Deutsche Akkreditierungsstelle GmbH Annex to the Accreditation Certificate D-PL-17453-01-00 according to DIN EN ISO/IEC 17025:2005 Period of validity: 03.07.2017 to 02.07.2022 Holder of certificate: SPIE
More informationDynamic Line Rating as a Means to Enhance Transmission Grid Resilience
Dynamic Line Rating as a Means to Enhance Transmission Grid Resilience McCall, J. Goodwin, T. Lindsey Manufacturing Tip Goodwin Consulting LLC USA Canada CIGRE US National Committee 2015 Grid of the Future
More informationNew 115 kv Disconnect Switches at Bloomsburg MTS
115 kv Line tap from C9 to Bloomsburg MTS & New Bus Tie Switch CAA ID Number: 2007-EX353 Final Draft ASSESSMENT SUMMARY 1. GENERAL DESCRIPTION Norfolk TS and Bloomsburg MTS are supplied by a single 115
More informationStandard Battery Energy Storage System (BESS) Connection Arrangements
Standard Battery Energy Storage System (BESS) Connection Arrangements Introduction A battery energy storage system (BESS) can be operated in a number of different ways to provide benefit to a customer.
More informationCity of Palo Alto (ID # 6416) City Council Staff Report
City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building
More informationHigh Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007
High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services
More informationMILLIGAN SOLAR PROJECT
February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission
More informationInterconnection Feasibility Study Report GIP-226-FEAS-R3
Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power
More informationDevelopment of Motor-Assisted Hybrid Traction System
Development of -Assisted Hybrid Traction System 1 H. IHARA, H. KAKINUMA, I. SATO, T. INABA, K. ANADA, 2 M. MORIMOTO, Tetsuya ODA, S. KOBAYASHI, T. ONO, R. KARASAWA Hokkaido Railway Company, Sapporo, Japan
More informationGateway South Transmission Project
Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive
More informationThe Grid Link Project. Summary of the Report for the Independent Expert Panel
The Grid Link Project Summary of the Report for the Independent Expert Panel Who are EirGrid - and what do we do? EirGrid is responsible for a safe, secure and reliable supply of electricity: now and in
More informationUpdated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers
Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,
More informationWessel Bakker Business Line Director ETD BMEA DNV KEMA The Netherlands
Transmission grid extension for Lake Turkana Wind Farm Wessel Bakker Business Line Director ETD BMEA DNV KEMA The Netherlands wessel.bakker@dnvkema.com Contents Drivers for grid expansion Suswa and Loyangalani
More informationABB POWER SYSTEMS CONSULTING
ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February
More informationHIGH PERFORMANCE OVERHEAD LINE CONDUCTORS TO UPGRADE YOUR SYSTEM
HIGH PERFORMANCE OVERHEAD LINE CONDUCTORS TO UPGRADE YOUR SYSTEM ACPR LO-SAG CONDUCTOR UPGRADE YOUR INTERNAL BACKBONE AND CROSS-BORDER CAPACITY The innovative ACPR LO-SAG is much lighter & stronger, dispatching
More information100 MW Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility
More informationDevelopment of a High Efficiency Induction Motor and the Estimation of Energy Conservation Effect
PAPER Development of a High Efficiency Induction Motor and the Estimation of Energy Conservation Effect Minoru KONDO Drive Systems Laboratory, Minoru MIYABE Formerly Drive Systems Laboratory, Vehicle Control
More informationInterconnection Feasibility Study Report GIP-222-FEAS-R3
Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.
More informationEngineering Considerations. Glenn Stapleton - Senior Electrical Design Engineer Lines
Engineering Considerations Glenn Stapleton - Senior Electrical Design Engineer Lines Overview Transmission line terminology and concepts Types of clearances Electrical safety considerations in co-use Underground
More informationModernising the Great Western railway
Report by the Comptroller and Auditor General Department for Transport and Network Rail Modernising the Great Western railway HC 781 SESSION 2016-17 9 NOVEMBER 2016 4 Key facts Modernising the Great Western
More informationElbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI
Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility
More informationPID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation
PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date
More informationGeneration Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation
Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY
More informationWLTP DHC subgroup. Draft methodology to develop WLTP drive cycle
WLTP DHC subgroup Date 30/10/09 Title Working paper number Draft methodology to develop WLTP drive cycle WLTP-DHC-02-05 1.0. Introduction This paper sets out the methodology that will be used to generate
More informationAPPENDIX F: Project Need and Description
APPENDIX F: Project Need and Description California ISO/MID F-1 Intentionally left blank California ISO/MID F-2 Name Brief Description Type Lugo Victorville 500 kv Upgrade (SCE portion) The project was
More informationIncreased Transmission Capacity
Increased Transmission Capacity Program Description Program Overview For 2010, EPRI is offering three strategic collections of research projects or programs in virtual programs. These virtual programs
More informationACCC. CTC Global s High Performance Conductors for a Low Carbon World
ACCC CTC Global s High Performance Conductors for a Low Carbon World The Challenge The need to deliver reliable and affordable electric energy on a global scale has never been more important. While tens
More informationOverhead transmission lines Spacers
= SVENSKA KRAFTNÄT SWEDISH NATIONAL GRID UNIT, BUSINESS AREA AEL, Asset Management Lines OUR REFERENCE TR05-08E DATE 2016-06-09 CONSU12TATIONS TECHNICAL GUIDELINE REVISION 3 APPROVED Overhead transmission
More informationEXPERIMENTAL STUDY OF DYNAMIC THERMAL BEHAVIOUR OF AN 11 KV DISTRIBUTION TRANSFORMER
Paper 110 EXPERIMENTAL STUDY OF DYNAMIC THERMAL BEHAVIOUR OF AN 11 KV DISTRIBUTION TRANSFORMER Rafael VILLARROEL Qiang LIU Zhongdong WANG The University of Manchester - UK The University of Manchester
More informationSmart initiatives in Transmission System. Dr Shekhar Kelapure PRDC, Bangalore
Smart initiatives in Transmission System Dr Shekhar Kelapure PRDC, Bangalore Overview Introduction Objectives Challenges Technologies Conclusions Page #2 Why Smart Transmission Grids (STG)? Improve grid
More informationINTERCONNECTION BETWEEN IRELAND AND ENGLAND / WALES TECHNICAL INVESTIGATION INTO CONNECTION OF EAST WEST INTERCONNECTOR TO IRISH TRANSMISSION SYSTEM
INTERCONNECTION BETWEEN IRELAND AND ENGLAND / WALES TECHNICAL INVESTIGATION INTO CONNECTION OF EAST WEST INTERCONNECTOR TO IRISH TRANSMISSION SYSTEM EIRGRID AUGUST 2007 EXPLANATORY NOTE FOR PUBLISHED DOCUMENT
More informationAlberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation
Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta
More informationWOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017
WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 TODAY WE LL TALK ABOUT Our challenges and how we re meeting them Why we re building this project Our planning process and considerations
More informationDevelopment of a Multibody Systems Model for Investigation of the Effects of Hybrid Electric Vehicle Powertrains on Vehicle Dynamics.
Development of a Multibody Systems Model for Investigation of the Effects of Hybrid Electric Vehicle Powertrains on Vehicle Dynamics. http://dx.doi.org/10.3991/ijoe.v11i6.5033 Matthew Bastin* and R Peter
More informationSUSPENSION 04 CLAMPS
SUSPENSION CLAMPS 04 4 SUSPENSION CLAMPS 57 Contents General... 58 Suspension clamp trunnion type, forged, for aluminium based conductors... 63 Suspension clamp trunnion type, forged, with bigger angle
More informationBritish Gas Comments and Questions on Kelton Engineering Draft SMER
British Gas Comments and Questions on Kelton Engineering Draft SMER 13 th September 2013 These comments and questions are associated with the draft SMER produced by Keith Vugler of Kelton Engineering,
More information15 Nelson-Marlborough Regional Plan
15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant
More informationEstimation of electrical losses in Network Rail Electrification Systems
Estimation of electrical losses in Network Rail Electrification Systems Page 1 of 16 Contents 1. BACKGROUND...3 2. PURPOSE...3 3. SCOPE...3 4. DEFINITIONS & ABBREVIATIONS...4 5. NETWORK RAIL INFRASTRUCTURE
More informationHTLS UPGRADES FOR POWER TRANSMISSION EXPANSION PLANNING AND OPERATION. Askhat Tokombayev
HTLS UPGRADES FOR POWER TRANSMISSION EXPANSION PLANNING AND OPERATION by Askhat Tokombayev A Thesis Presented in Partial Fulfillment of the Requirements for the Degree Master of Science Approved April
More informationHow Aerospace Technology is Improving the Efficiency, Capacity and Reliability of the Smart Grid
CIGRE US National Committee 2013 Grid of the Future Symposium Boston, Massachusetts October 2013 How Aerospace Technology is Improving the Efficiency, Capacity and Reliability of the Smart Grid Dave Bryant,
More informationSubstation Lightning Protection. Document Number: 1-11-FR-11
Substation Lightning Protection Document Number: 1-11-FR-11 VERSION 1.0 June 2018 This functional requirements document is in line with the organisation's 1-11-ACS-11 Substation Lightning Protection Asset
More informationReasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders
Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test: Salisbury Substation 11kV Feeders DISCLAIMER The purpose of this document is to inform customers, Interested Parties,
More informationDistribution lines Overload Control to Increase Reliability and Power Loss Reduction
Distribution lines Overload Control to Increase Reliability and Power Loss Reduction SHRIRANG KARANDIKAR Vice President (Business Development) Kalpataru Power Transmission Ltd. Santacruz (East), Mumbai-400055
More informationHeader. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8
Header Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations RT 007-11 Balhannah and Uraidla - Final Draft Page 1 of 8 DISCLAIMER The purpose of this document is to inform customers,
More information2015 Grid of the Future Symposium
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,
More informationVolume-III : Section-I 370 Technical Specifications
Volume-III : Section-I 370 TECHNICAL SPECIFICATION-PIERCING INSULATOR 5.1 Insulation Piercing Connectors (IPC) 5.1.1 Insulation Piercing Connectors (IPC) are used for making Tee/Tap-off/Service connectors
More informationTransmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015
No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the
More informationINCREASING electrical network interconnection is
Analysis and Quantification of the Benefits of Interconnected Distribution System Operation Steven M. Blair, Campbell D. Booth, Paul Turner, and Victoria Turnham Abstract In the UK, the Capacity to Customers
More informationCurrent collecting characteristics of catenary with non-tension contact wires
Current collecting characteristics of catenary with non-tension contact wires T. Hamada, A. Suzuki & T. Shimada Railway Technical Research Institute, Japan Abstract Feeder cables are additionally installed
More informationMemorandum. This memorandum requires Board action. EXECUTIVE SUMMARY
California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:
More information3M Brand Composite Conductor Connector Current Cycle Qualification Test for 795 kcmil Compression Connectors
3M Brand Composite Conductor Connector Current Cycle Qualification Test for 7 kcmil Compression Connectors 3M Company Purchase Orders 0000797063 and 0000866974 NEETRAC Project Number: 03-071 September,
More informationDevelopment of Large-capacity Indirect Hydrogen-cooled Turbine Generator and Latest Technologies Applied to After Sales Service
Development of Large-capacity Indirect Hydrogen-cooled Turbine Generator and Latest Technologies Applied to After Sales Service 39 KAZUHIKO TAKAHASHI *1 MITSURU ONODA *1 KIYOTERU TANAKA *2 SEIJIRO MURAMATSU,
More informationAppendix 3. DRAFT Policy on Vehicle Activated Signs
Appendix 3 DRAFT Policy on Vehicle Activated Signs Ealing Council has been installing vehicle activated signs for around three years and there are now 45 across the borough. These signs help to reduce
More informationInterconnection Feasibility Study Report GIP-084-FEAS-R2
Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power
More informationEnergy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director
Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th Alex Bettencourt Managing Director National Association Made Up of Entire Industry Utilities Industry Academia / R&D
More informationReluctance Motors Synchrel Design & Optimisation
Reluctance Motors Synchrel Design & Optimisation A Switched Reluctance Alternative Incorporating Novel Features The End Result 1 Existing Design Procedure Electromagnetic Design A Switched Reluctance solution
More informationThe Grid Toolbox. quickly increasing the capacity of existing power grids System reliability in renewables-driven power systems A Think Tank Workshop
The Grid Toolbox quickly increasing the capacity of existing power grids System reliability in renewables-driven power systems A Think Tank Workshop Dr. Stephanie Ropenus BERLIN 19TH APRIL 2018 Drivers
More informationSubmission for Tactical Transmission Upgrade Approval
Submission for Tactical Transmission Upgrade Approval April 2005 Electricity Commission Submission Tactical Transmission Projects April 05 1 Executive Summary Transpower seeks approval from the Electricity
More informationTRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID.
A GUIDE TO TRANSPOWER 2009 TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID. Contents 01 Introduction 02 System Operator 24/7
More informationSERTP rd Quarter Meeting
2015 SERTP SERTP 2015 3 rd Quarter Meeting 2nd RPSG Meeting September 24 th, 2015 APC Headquarters Birmingham, AL 2015 SERTP Process Information The SERTP process is a transmission planning process. Please
More informationNew Landscape & Design Approachs in Europe
New Landscape & Design Approachs in Europe Agenda 1. Introduction Europoles Group 2. Design vs. Feasibility Actual Developments in Extra High Voltage Grids 3. The Magic Triangle 4. Actual Developments
More informationEPRI HVDC Research. Gary Sibilant, EPRI. August 30, 2011
EPRI HVDC Research John Chan, Ram Adapa, Bernie Clairmont & Gary Sibilant, EPRI EPRI HVDC & FACTS Conference August 30, 2011 Presentation Contents 1. Team Members 2. Research Program Objective & Scope
More informationProposed Dounreay - Mybster 275 kv / 132 kv
Background Scottish Hydro-Electric Transmission Ltd (SHETL) is proposing a new 275 kilovolt (kv) (1 kilovolt = 1000volts) double circuit overhead line (OHL) between the Dounreay sub station and the new
More informationTransmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona
Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff
More informationELECTROMONTAJ S.A. 68 years in Power Transmission
ELECTROMONTAJ S.A. 68 years in Power Transmission 1, Candiano Popescu street, district 4, Bucharest, 040581 elmbuc@electromontaj.ro www.electromontaj.ro ELECTROMONTAJ S.A. Bucharest ELECTROMONTAJ S.A.
More informationCONTENTS. iii. Foreword Preface Chapter 1- Design Parameters for Transmission Lines
CONTENTS Foreword Preface Chapter 1- Design Parameters for Transmission Lines 1.1 Introduction 1.2 Mechanical Design 1.2.1 Wind Speed 1.2.2 Maximum Temperature of Current Carrying Conductor 1.2.3 Span
More informationPowerco CPP Portfolio Overview Document
Putaruru-Tirau Cable Powerco CPP Portfolio Overview Document Portfolio Name Expenditure Class Expenditure Category Putaruru-Tirau Cable Capex Growth & Security As at Date 12 June 2017 Expenditure Forecast
More informationFinal Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description
Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing
More informationHealth Monitoring of Overhead Power Transmission Line:
Vienna 26-27 January, 2004 Health Monitoring of Overhead Power Transmission Line: User Needs Dmitri SNEGOVSKI (Mech. Eng., PhD student) Transmission and Distribution of Electrical Energy University of
More informationCost Benefit Analysis of Faster Transmission System Protection Systems
Cost Benefit Analysis of Faster Transmission System Protection Systems Presented at the 71st Annual Conference for Protective Engineers Brian Ehsani, Black & Veatch Jason Hulme, Black & Veatch Abstract
More informationProposed Short circuit test: The attenuation coefficient to max allowed increased 0.05 db/km from the point of strike.
Proposed Short circuit test: The attenuation coefficient to max allowed increased 0.05 db/km from the point of strike. Test 1 2 3 Short-circuit current 6kA 9kA 20kA Duration 1.0Sec 0.5Sec 0.1Sec 46 Proposed
More informationImpact, Torsion, and Crush Tests for 477 kcmil and 795 kcmil 3M Brand Composite Conductor. 3M Company Purchase Order
Impact, Torsion, and Crush Tests for 477 kcmil and 795 kcmil 3M Brand Composite Conductor 3M Company Purchase Order 0000620410 NEETRAC Project Number: 02-229 October, 2002 A Center of The Georgia Institute
More information