OVERHEAD DESIGN MANUAL

Size: px
Start display at page:

Download "OVERHEAD DESIGN MANUAL"

Transcription

1 OVERHEAD DESIGN MANUAL Section 4 Poletop Constructions Approved by: F ZAINI ENERGEX 2018 MANUAL 00302

2

3 CONSTRUCTION SELECTION General Notes 1. Constructions should be selected according to: spanning and angular limitations (refer layout guides in this manual or mainsdes application). suitability for local environment consider visual impact, vegetation, wildlife, pollution, reliability ease of construction and maintenance phasing 33kV Construction Vertical Delta Vertical Offset Application Preferred construction for new feeders. Suitable replacement for existing wishbone constructions, subject to spanning constraints. Suitable for replacement of other older construction types subject to adequate clearances from subcircuits. Refer note 4 Preferred construction for new feeders in narrow easements. Suitable for double circuit applications, either side of the pole combined with special crossarms. 2. Constructions that do not include timber cross-arms, eg vertical delta or trident, are preferred on new feeders. These generally have superior reliability and life in the field. 3. Flat and trident constructions are suited where pole height is limited or where the line presents a hazard to birds or bats. 4. On pole replacements, if the existing constructions are flat, it is preferred to use another same flat construction or trident on the new pole. This avoids conductor rolling to and from a vertical delta construction. If a continuous run of poles were to be replaced from shackle to shackle, then the vertical delta or trident constructions are preferred. 5. Insulated lines have superior reliability to bare mains and are especially suited to areas where vegetation is in the vicinity of the line, where there is significant wildlife, where lines may be contacted by boat masts etc. 6. Equipment subject to ongoing operational requirements (e.g. drop outs or EDO ), should be no more than 11m above ground level. LV Construction Application LVABC Preferred construction for new feeders. Can be parallelled to increase current rating of circuit. Open Wire Used for replacement of existing constructions. Suitable for industrial areas with high load currents. Suitable for rural applications where long spans are required, subject to absence of vegetation in vicinity of line. Trident Preferred replacement for existing 33kV flat constructions (subject to application constraints) where overhead earth wire does not exist. Double Circuit For limited use only. Use where 2 single circuit feeders cannot be accommodated in easements or other restricted space situations. Use overhead earth wire for entire length of all new 33kV feeders. 11kV Construction Trident 11A, 11P, and 11FP Vertical Delta Vertical Offset Application Shall be the 1 st choice for all new and replacement constructions subject to application constraints. Unsuitable for subcircuits. 11A shall be 1 st choice as subcircuit construction below 33kV subject to application constraints. Suitable for narrow corridors and easements. Rural better suited to longer spans than 11A and other flat constructions. Refer note 4 Preferred construction for new lines in narrow easements. Rural (greater phase separation for long spans) and Urban (compact) styles. Double Circuit For limited use only where short sections of double circuit construction are required. Same as 33kV application. 11ABC For use as an alternative to CCT and open wire where clearances would otherwise be inadequate A APP D CKD DATE APP D DATE REC D F. ZAINI 20/10/2015 POLETOP CONSTRUCTIONS SELECTION GUIDELINES Constructions & CCT ATHR ORIGINAL ISSUE COPYRIGHT 2015 ENERGEX This drawing must not be reproduced in part or whole without written permission from ENERGEX CKD AUTHR P. RELF K. GOSDEN WORD A4 SEC 4 SUB 2 SHT 1 REV A

4 A APP D CKD 11 KV CCT GUIDELINES For planning and design purposes, 120 sq mm CCT maximum continuous current rating is approx. 400 Amps at 80 deg C compared to Moon 7/4.75 AAC rated at 400 amps at 75 deg C. CCT has an emergency operating temperature (2hrs) at 100 deg C. Maximum allowable stringing tension is Table 220. Design Considerations for New Feeders and Reconductoring Old Feeders CCT is generally used in areas with trees or heavy vegetation to minimise reliability problems associated with wind blown branches, debris, or wildlife. When reconductoring, CCT cannot be used with existing pin or disc types of insulators because of voltage stress grading issues. Therefore, if no supercircuit exists (eg 33 kv above), all intermediate constructions shall be replaced with the expanded trident construction. This construction uses post insulators, and the crossarm has provision for mounting surge arresters. When reconductoring and a supercircuit exists, the first choice is to replace the construction with vertical delta. However, since most of these situations will be constrained by available pole space, the second choice will be to replace all intermediate constructions with an 11A. Refer drawing 7100-A4 for layout guides. Mounting brackets are available to mount surge arresters on this construction. Reconductoring with CCT will increase the pole tip loads, and designers must check existing poles to ensure they are capable of withstanding the increased loadings. Where the CCT loads exceed the tip load strength of existing poles, those poles shall be replaced with new poles of sufficient tip load strength. Where the feeder has previously been constructed using the older narrow based trident at intermediate structures, this construction may be retained for use with CCT only at structures where surge arresters will not be required. CCT shall not be installed at railway crossings. Surge Arrester Requirements Surge arresters are required to be installed on CCT feeders to protect against high voltage surges from lightning strikes. When CCT is installed in areas with trees, buildings, or heavy vegetation (closed areas), to provide adequate protection surge arresters are to be installed at or near the beginning and end of the conductor route and also at approximately 200 metre intervals and no more than 250 metre intervals. Where the CCT route passes through open areas (where there are no surrounding trees, buildings, or vegetation), surge arresters will be required at 100 metre intervals due to the increased risk of lightning strikes. The following alternative guidelines are also acceptable and may be more practical in some instances: DATE ATHR ORIGINAL ISSUE APP D DATE REC D COPYRIGHT 2015 ENERGEX CKD This drawing must not be reproduced in part or whole without written AUTHR permission from ENERGEX F. ZAINI 20/10/2015 P. RELF K. GOSDEN WORD 1. In closed areas, one set of surge arresters installed will protect the CCT for a distance up to 125 metres on either side of the arresters. HV surge arresters fitted to other pole mounted plant eg UG Cable Terminations, Load Break Switches, and PT Stations nearby the CCT route or along the CCT route will offer the same level of protection. The nearby feeder needs to be electrically connected to the CCT feeder without any normally open points and HV surge arresters need to be no further than 125 metres away. In open areas the protected distance is halved, so twice as many arresters are required. 2. Surge arresters cannot be fitted to flat shackle constructions due to the complexity of the bridging required. For this reason, although arresters would be preferred, they cannot be fitted in practice. Where there is a continuous run of shackle to shackle spans totaling 200 metres or more, refer the proposed design to Network Standards Department to assess surge arrester requirements and fitment options. CCT TYPES There are 2 types of CCT used in ENERGEX for 11kV mains alloy. This is the current type of CCT being supplied and can be used for 11kV bridging as well as 11kv mains. Drum length is 600 metres. The method used to terminate the cable is by the use of wedge clamps fitted directly to the wire conductors. The Compatible Unit (CU) is 11CCT alloy. This was the original type supplied by OLEX until the end of Due to the hard XLPE covering, this type of CCT was terminated by the use of a helical wrapon dead end applied over the outside of the cable insulation. POLETOP CONSTRUCTIONS SELECTION GUIDELINES A4 SEC 4 SUB 2 SHT 2 REV A

5 HVABC GUIDELINES There are two 11kV Aerial Bundled Conductor types available. 35 mm 2 will give a continuous current rating of 145 Amps and will be suitable for radial spurs. 120 mm 2 will give a continuous current rating of 300 Amps and will be suitable for feeder backbone. 11ABC cannot be strung any tighter than T ABC does not have exposed live parts and does not require safe approach distance except on terminations and joints where the earthed screen is broken out from the conductors. These joints and termination require a 700mm safe approach distance to live conductors 11ABC is light duty screened. As a result its application is limited to areas where the phase to ground fault current does not exceed 2.1 ka. Use 11ABC only if any of the following situations prevent the use of open wire or CCT: Where there is sensitive vegetation in the vicinity of the new feeder, and the clearing profile must be minimized. Where feeder clearances to objects such as buildings and awnings cannot be maintained using bare or CCT constructions. Where blowout of conductor needs to be minimized. Because of its weight 11ABC will have less midspan blowout than other conductors at the same stringing table and span length. Where an existing 11ABC feeder or 11ABC section of a feeder requires replacement or upgrading. (Replace 11ABC with 11ABC.) Where differences in conductor sags need to be minimized under hot/cold conditions. Because 11ABC has a catenary wire to support the conductor, there is little change in sag between hot and cold operating temperatures. New features that allow 11ABC to be used in areas where open wire and CCT is unsuitable: 11ABC can be used on feeders that require tee-offs. 11ABC can be used on feeders that require pole mounted plant to be installed. (Eg, transformers, regulators, remote controlled load break switches, load transfer switches, sectionalisers,& reclosers) Where the pole mounted plant requires an LV supply, (usually for remote controlled load break switches and reclosers), the LV supply should be from LVABC mains attached to the plant pole. If LV mains do not exist, a small PT will need to be installed nearby and LVABC mains run to the plant pole. With 11ABC installations, this method of LV supply to the plant equipment is preferable to using an 11kV voltage transformer, commonly used with the open wire or CCT feeder situation. Joints and Earthing 11ABC requires the catenary wire to be earthed at regular intervals at least every 300 metres. 11ABC has a screen wire that is required to be earthed at one end only for each cable run from joint to joint. 11ABC should have joints at no more than 300 metres apart. Dual Circuit Construction Dual 11ABC circuits on the same pole is to be avoided wherever possible. Engineering Standards to be consulted before proceeding with any dual circuit designs. To avoid safe approach distance issues designs should stagger the 11ABC joint and terminations by only having 1 leg of HVABC terminate or join on any one pole. Each 11ABC circuit when installed in a double circuit construction is to be identified by reflective and coloured tag at each pole. A DATE APP D F. ZAINI APP D DATE 20/10/2015 CKD REC D ATHR COPYRIGHT 2015 ENERGEX CKD P. RELF ORIGINAL ISSUE This drawing must not be reproduced in part or whole without written AUTHR K. GOSDEN permission from ENERGEX WORD POLETOP CONSTRUCTIONS SELECTION GUIDELINES A4 SEC 4 SUB 2 SHT 3 REV A

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28 HV INSULATOR SELECTION UP TO 33 kv Designers need to nominate insulator types for use on poletop constructions. In general, long rod synthetic insulators are preferred to normal disc insulators on strain or suspension constructions since they are light, inexpensive, and non-puncturable. Normal disc insulators may be shorter than synthetic insulators. This may be of importance in determining clearances from a suspension construction to subcircuits below. Normal disc insulators have a smaller surface creepage length than long rod synthetic insulators. Fog disc insulators have a very high surface creepage length and shall be used in areas of heavy salt pollution or industrial pollution. Heavy salt pollution areas are typically within 3km of the marine coast with continual direct exposure to salt spray i.e. no vegetation, landscape, buildings, and prevailing winds to block the salt spray from contaminating the surface of the insulators. Industrial pollution areas are typically sites or localities where there is a continual problem with dirt, dust, and smoke that can contaminate the surface of the insulators. Eg, mining sites and quarries. Pin insulators are unsuitable for use with 11kV covered conductor thick (CCT). Post type insulators must be used for this application. Post insulators are preferred over Pin insulators (subject to application constraints) for HV conductors All insulation in contact with CCA-treated poles, concrete poles or steel cross-arms (all of which must be considered conductive to some degree, especially when wet) must be either: Two part, eg 2 or more disks, OR Non-puncturable, eg porcelain post or long rod synthetic insulators. For additional information, Refer AS/NZS 7000:2010 Appendix P. B APP D CKD ATHR DATE 15/07/16 F. ZAINI P. RELF P. RELF POST INSULATORS NOTE ADDED APP D DATE REC D COPYRIGHT 2015 ENERGEX CKD This drawing must not be reproduced in part or whole without written AUTHR permission from ENERGEX F. ZAINI 20/10/2015 P. RELF K. GOSDEN WORD POLETOP CONSTRUCTIONS H.V. INSULATOR SELECTION GUIDELINES A4 SEC 4 SUB 13 SHT 1 REV B

29

30

31

32

33

34

35

36 APPLICATION GUIDELINES Voltage LV Overhead Horizontal (Flat) Construction N-A-B-C from the property to the road. HV A-B-C from left to right ** with HV bushings closest to observer. Overhead Vertical Construction N-A-B-C from top to bottom. Conductors roll as required (refer Sheet 2). ** This does not indicate source/substation phasing. Notes: Table: Standard Configuration of Conductors It is recommended (not mandatory): 1. Pole transformers are located so the neutral of the transformer is on the same side as the LV mains neutral. This will reduce the requirement to cross the transformer LV bridging. 2. Where cost effective and practical, pole transformers should be located in low speed streets that carry low traffic volumes. 3. Pole transformers and stays not be located on the same side of the pole (except for a termination where the transformer may be located on the same side as the stay). 4. Transformer phase transpositions be done on the HV. Phasing, Phase Rotation and Phasing Out are specialised areas. They are dealt with in detail in the following references: 1. Phasing Out Manual Operating Practices Manual, Section 2.10 Phasing Out. 2. Phasing and Phase Rotation Standard Substation Design Standards, Part 1, Section 5 Energex Phasing Standard. In rural/bush situations (i.e. where a property/road reference is not available), select best possible phase configuration by: 1. attempting to conform with the above 2. agreement between designer and commissioning crew. Designers need only refer to the above Table to complete Works Plans. A APP D CKD DATE APP D DATE REC D F. ZAINI 20/10/2015 POLETOP CONSTRUCTIONS PHASING APPLICATION GUIDELINES ATHR ORIGINAL ISSUE COPYRIGHT 2015 ENERGEX This drawing must not be reproduced in part or whole without written permission from ENERGEX CKD AUTHR P. RELF K. GOSDEN WORD A4 SEC 4 SUB 17 SHT 1 REV A

37

38 APPLICATION GUIDELINES Ideal application is a single circuit pole with no other plant / switches located on the pole. Other pole configurations may be used provided care is exercised. 1. SITE SELECTION Select the cleanest possible pole. Do not use on poles with concentrated sources of magnetic fields such as transformers, underground cables, magnetically operated switches etc. At `tees' mount the indicator a span away from the junction, on the load side. Do not use on Tee-off poles. LINE VOLTAGE SEPARATION LINE VOLTAGE SEPARATION 11kV 25m 66kV 100m 22kV 35m 132kV 200m 33kV 50m kV 500m For other voltages distances are proportional to voltage. 2. POLE LOCATION For combined HV/LV circuits mount as indicated below: on the sunniest side of pole with the solar panel pointing in the same direction as the HV conductors directly above. between 1.2 (preferred provided safe working limits are maintained) and 3.5 metres below the lowest HV conductor. Do Not use indicators in the following instances: 1 phase lines, 3 phase lines or 2 wire lines that are fused or protected by single pole reclosers. (as remaining live conductors will prevent triggering) 4 wire HV systems with MEN (Multiple Earthed Neutral). The indicator should be kept the following distances from nearby lines that may remain energised after a fault: A APP D DATE APP D DATE F. ZAINI 20/10/2015 POLETOP CONSTRUCTIONS LINE FAULT INDICATORS CKD REC D ATHR ORIGINAL ISSUE COPYRIGHT 2015 ENERGEX This drawing must not be reproduced in part or whole without written permission from ENERGEX CKD AUTHR P. RELF K. GOSDEN WORD A4 SEC 4 SUB 18 SHT 1 REV A

39 APPLICATION GUIDELINES These guidelines are for LV supply to all: Pole Mounted Reclosers (PMR) Load Transfer Switches (LTS) and Sectionalisers. LV supply is required at these sites to charge the DC batteries used to provide supply for the control circuitry in these devices. In general supply is to be made available from a 11kV / 28V voltage transformer. However, if necessary LV can be supplied directly from LV mains in CMEN locations, or from LV mains via a 240V / 240V 15kV isolation transformer in new non-cmen locations. DSA schemes involve the remote control of: Regulators Pole Mounted Reclosers (PMR) Load Transfer Switches (LTS) and Sectionalisers. In all cases contact: References: Design Group Secondary Systems Team. Overhead Construction Manual, 4920-A4, Section 2, p20 and Section 7. Distribution System Automation (DSA) Schemes A APP D CKD DATE APP D DATE REC D F. ZAINI 20/10/2015 POLETOP CONSTRUCTIONS PMR, LOAD TRANSFER SWITCH & SECTIONALISER - LV SUPPLY ATHR ORIGINAL ISSUE COPYRIGHT 2015 ENERGEX This drawing must not be reproduced in part or whole without written permission from ENERGEX CKD AUTHR P. RELF K. GOSDEN WORD A4 SEC 4 SUB 19 SHT 1 REV A

40 ENGINEERING BACKGROUND LAYOUT GUIDES The Layout Guides indicate practical maximum (sometimes minimum) values of span length, and line deviation angle allowable for each construction, conductor type and stringing table combination. These limits are based on several underlying factors: The effect of these factors on span/angle capability Uncontrolled of a poletop Document construction When is Printed illustrated in the graph below. Note that it may be possible to exceed the stated maximum span slightly provided that the deviation angle is very small. Likewise it may be possible to exceed the stated maximum deviation angle slightly provided that the span length is less than the stated maximum. 1. Conductor mid-span clashing. The probability of mid-span conductor clashing increases as conductor sag increases, which in turn increases with span length. Increasing separation between phase conductors at supports reduces the probability of clashing. In general, to avoid clashing between conductors, the following condition must be met: (X 2 + Y 2 ) U / (D + l i ) where: X is the horizontal distance between the conductors at mid-span (m) Y is the vertical distance between the conductors at mid-span (m) U is the rms difference in potential between the two conductors (kv) D is the greater of the two conductor sags (m) No Wind, 50C l i is the length of any freely swinging suspension insulator with either conductor (m) 2. Strength of insulator assemblies, conductor ties, kingbolt, crossarms and other fittings. The forces on these elements increase with span length and line deviation angle. 3. Clearances of conductors and insulator discs from pole and cross-arms. This problem is illustrated in the diagram below. With certain deviation angles there may be inadequate spacing between these elements to maintain effective insulation. For angle constructions where disk insulators are fitted to a pole, eg 33TA, a minimum deviation angle may be specified as well as a maximum. clearance problem when deviation angle is too great Refer AS/NZS 7000:2010 Appendix Q for further details. Notice that for constructions such as 11P and 11SU maximum span lengths are greater if the centre phase is staggered, ie attached to alternate sides of the pole on alternate poles. Designers wishing to take advantage of this extended spanning should indicate that staggered construction is to be use on the works plan. For spans with different construction types at either end, the span length should not exceed the lesser of the two spanning limitations. When changing from flat to vertical construction, the maximum span length should be reduced by a further 30%. Where mid-span spacers are installed (normally as a remedial measure on an existing span), these effectively act as a support structure in terms of preventing midspan clashing. A APP D CKD DATE APP D F. ZAINI 20/10/2015 POLETOP CONSTRUCTIONS ENGINEERING BACKGROUND LAYOUT GUIDES ATHR ORIGINAL ISSUE DATE REC D COPYRIGHT 2015 ENERGEX CKD This drawing must not be reproduced in part or whole without written AUTHR permission from ENERGEX P. RELF K. GOSDEN WORD A4 SEC 4 SUB 20 SHT 1 REV A

Underground Distribution Construction Manual

Underground Distribution Construction Manual Underground Distribution Construction Manual Section E7 Earthing Approved by: A Smith de Perez Energex Limited 2014 ABN 40 078 849 055 MANUAL 00305 1. INSTALLATION Detailed earthing information may be

More information

Item Code Description Unit Qty Total

Item Code Description Unit Qty Total UNDP ELECTRICITY SECTOR NORTHERN GOVERNORATES Phase XI Item Code Description Unit Qty Total 04-02-00001 Service Pole - 6m, 75mm dia GS Pipe 11250 04-02-00002 9m Tubular Steel Poles complete with all Accessories

More information

Engineering Considerations. Glenn Stapleton - Senior Electrical Design Engineer Lines

Engineering Considerations. Glenn Stapleton - Senior Electrical Design Engineer Lines Engineering Considerations Glenn Stapleton - Senior Electrical Design Engineer Lines Overview Transmission line terminology and concepts Types of clearances Electrical safety considerations in co-use Underground

More information

When power interruptions happen.

When power interruptions happen. When power interruptions happen. We know it s never a good time to have your power go out, so we work all year pruning trees and investing in our system to cut down on problems before they start. Outage

More information

Item L.1 Voltages 1. The consumer voltage must be between +10% and -10% of the nominal national voltage (nnv.)

Item L.1 Voltages 1. The consumer voltage must be between +10% and -10% of the nominal national voltage (nnv.) Village Hydro Specifications Line Distribution Description of Requirement Item L.1 Voltages 1. The consumer voltage must be between +10% and -10% of the nominal national voltage (nnv.) Recommendation 2.

More information

Title High Voltage and 1500 System Earthing References and Definitions. Reference Number PDS 02 (RIC Standard: EP SP)

Title High Voltage and 1500 System Earthing References and Definitions. Reference Number PDS 02 (RIC Standard: EP SP) Discipline Engineering Standard NSW Category Electrical Title High Voltage and 1500 System Earthing References and Definitions Reference Number PDS 02 (RIC Standard: EP 12 00 00 01 SP) Document Control

More information

Railway Infrastructure. Competent Solutions for Electric Railways and Tramways. the power connection THE PFISTERER GROUP

Railway Infrastructure. Competent Solutions for Electric Railways and Tramways. the power connection THE PFISTERER GROUP Competent Solutions for Electric Railways and Tramways THE PFISTERER GROUP the power connection Solutions for Today s and Future Challenges Reliable and maintenance-free infrastructure provides the basis

More information

RSC-G-004-B Guidelines For The Design Of Section 3 3 ELECTRIC TRACTION SYSTEMS 2

RSC-G-004-B Guidelines For The Design Of Section 3 3 ELECTRIC TRACTION SYSTEMS 2 3 ELECTRIC TRACTION SYSTEMS 2 3.1. SAFE FOR PEOPLE 2 3.1.1. Electric Traction System 2 3.1.2. Protection against unwanted access 2 3.1.3. Fencing 2 3.1.4. On bridges and other structures 2 3.1.5. At level

More information

SYDNEY TRAMWAY MUSEUM TROLLEY WIRE INSPECTION PROCEDURE

SYDNEY TRAMWAY MUSEUM TROLLEY WIRE INSPECTION PROCEDURE TROLLEY WIRE INSPECTION PROCEDURE JUNE 2014 1. Document Details: Name: SYDNEY TRAMWAY MUSEUM Document Control Record Number STM 6029 Version Number: 15 TrolleyWire Inspection Procedure Document Status:

More information

On_Disc. 2 o/c1 BS 7671 applies to a lift installations b highway equipment c equipment on board ships d electrical equipment of machines.

On_Disc. 2 o/c1 BS 7671 applies to a lift installations b highway equipment c equipment on board ships d electrical equipment of machines. 1 PAPER 4 Sample Questions - C&G 2382 17th Edition full paper D 1 o/c 1 - A recommendation for the interval to the first periodic inspection shall be made by: a the installation electrician. b the main

More information

Max value Max life Range from. ($000) (Years) Pole Type

Max value Max life Range from. ($000) (Years) Pole Type Draft Handbook Vector Asset Description 1 Unit Maximum Maximum Life Max value Max life Max Asset Life Max Asset Life Range from Submitters Max Asset Life ($000) SUBTRANSMISSION Concrete Wood Concrete Wood

More information

Title Requirements for Electric Aerials Crossing ARTC Infrastructure. Reference Number PYS 02 - (RIC Standard: EP SP)

Title Requirements for Electric Aerials Crossing ARTC Infrastructure. Reference Number PYS 02 - (RIC Standard: EP SP) Discipline Engineering Standard - NSW Category Electrical Title Requirements for Electric Aerials Crossing ARTC Infrastructure Reference Number PYS 02 - (RIC Standard: EP 10 01 00 05 SP) Document Control

More information

9. Non-Residential Services (Commercial, Industrial, and Agricultural)

9. Non-Residential Services (Commercial, Industrial, and Agricultural) Section 9 2016 Electric Service Requirements, 3rd Edition Section 9 Non-Residential Services Directory Page 9.1 General Requirements 68 9.2 Direct-Connect Metering, Single Installations 69 9.3 Direct-Connect

More information

Underground Distribution Construction Manual

Underground Distribution Construction Manual Underground Distribution Construction Manual Section E5 LV Joints and Terminations Approved by: A Smith - de Perez Energex Limited 2014 ABN 40 078 849 055 MANUAL 00305 ELECTRICAL SECTION E5 - LV JOINTS

More information

Molded Vacuum Reclosers The recloser you want, all in one package. Single- and Three-Phase Molded Vacuum Reclosers, 15 38kV

Molded Vacuum Reclosers The recloser you want, all in one package. Single- and Three-Phase Molded Vacuum Reclosers, 15 38kV The recloser you want, all in one package. Single- and Three-Phase, 15 38kV The need for automated reclosers has never been greater, but many of today s reclosers come with penalties. They weigh too much,

More information

TEKNISK RIKTLINJE TR05-10E

TEKNISK RIKTLINJE TR05-10E Notes Change notes Date 1 (A) Revision of standards and new template 09 / 07 2010 2 Template changed.clause. 10.5.1.4 support clamp inserted. Clause 10.5.4.2 creepage text revised. Clause 10.6.7 Dry inserted

More information

Unified requirements for systems with voltages above 1 kv up to 15 kv

Unified requirements for systems with voltages above 1 kv up to 15 kv (1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) (Corr.1 June 2018) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements

More information

SYSTEM PROTECTION SYSTEM PROTECTION. Underground Electric Distribution Standards I. FUSE COORDINATION

SYSTEM PROTECTION SYSTEM PROTECTION. Underground Electric Distribution Standards I. FUSE COORDINATION I. FUSE COORDINATION I.1. GENERAL I.1.1. The purpose of protective coordination is to provide isolation of a fault as close to the fault as possible so that a minimum of customers will be affected. The

More information

S. K. Industrial Corporation

S. K. Industrial Corporation +91-8048763042 S. K. Industrial Corporation https://www.indiamart.com/skindlcorpn/ We are an ISO 9001 : 2008 certified company. We are manufacturing, exporting and supplying HT and LT transmission line,

More information

Final Written Examination.

Final Written Examination. Benha University Semester (3 th year Power &Control) Faculty of Engineering Electrical Power Systems (E1331) Electrical Engineering Department Semester 2015-2016 Final Written Examination. 10/1/2016 Time

More information

THE PROTEAN AND POC-MAST DESIGN

THE PROTEAN AND POC-MAST DESIGN THE PROTEAN AND POC-MAST DESIGN Contents 1. The changing landscape of generation for power transmission and distribution. 2. The Holford rules and recommendations for OHL routing and design. 3. The current

More information

SUSPENSION 04 CLAMPS

SUSPENSION 04 CLAMPS SUSPENSION CLAMPS 04 4 SUSPENSION CLAMPS 57 Contents General... 58 Suspension clamp trunnion type, forged,... 63 Suspension clamp trunnion type, forged, with bigger angle of deflection, for aluminium based

More information

Guidance for Low Voltage Electrical Installations

Guidance for Low Voltage Electrical Installations Guidance for Low Voltage Electrical Synopsis This document provides information in support of GI/RT7007 Low Voltage Electrical. Signatures removed from electronic version Submitted by Anne E Blakeney Standards

More information

Title Low Voltage Distribution and Installations Earthing References and Definitions. Reference Number PDS 03 (ARTC Standard: EP SP)

Title Low Voltage Distribution and Installations Earthing References and Definitions. Reference Number PDS 03 (ARTC Standard: EP SP) Discipline Engineering Standard NSW Category Electrical Title Low Voltage Distribution and Installations Earthing References and Definitions Reference Number PDS 03 (ARTC Standard: EP 12 00 00 02 SP) Document

More information

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND

More information

SECTION 27 - PAD-MOUNTED TRANSFORMERS TABLE OF CONTENTS

SECTION 27 - PAD-MOUNTED TRANSFORMERS TABLE OF CONTENTS CABLE AND CONDUIT ENTRANCE SINGLE-PHASE PAD-MOUNTED TRANSFORMER INSTALLATION 100 KVA AND LARGER (CONCRETE PADS ONLY) 27.05-01 CABLE AND CONDUIT ENTRANCE SINGLE-PHASE PAD-MOUNTED TRANSFORMER INSTALLATION

More information

Solid Dielectric, Three Phase Reclosers CATALOG VS11

Solid Dielectric, Three Phase Reclosers CATALOG VS11 Solid Dielectric, Three Phase Reclosers Providing electronic, three phase overcurrent protection for systems rated through 38kV, 800A continuous current, 12.5kA symmetrical interrupting Reliable performance

More information

Medium Voltage Outdoor Apparatus Portfolio 2009

Medium Voltage Outdoor Apparatus Portfolio 2009 PPMV, April/May 2009 Medium Voltage Outdoor Apparatus Portfolio 2009 May 5, 2009 Slide 1 Summary Reclosers Outdoor dead tank vacuum circuit breakers Outdoor live tank circuit breakers Pole mounted circuit

More information

environment briefing02

environment briefing02 The Voice of the Networks environment briefing02 transporting electricity Overhead Lines or Underground Cables Introduction The Electricity Act 1989 requires electricity companies both to maintain an efficient

More information

Technical Specification for Pole Mounted Capacitor Rack

Technical Specification for Pole Mounted Capacitor Rack Technical Specification for Pole Mounted Rack Page 1 1. Scope and Function a) Pole mounted capacitor racks shall be installed on a distribution feed as an economical means of applying capacitor units to

More information

Pretest Module 29 High Voltage Unit 1

Pretest Module 29 High Voltage Unit 1 Pretest Module 29 High Voltage Unit 1 1. Is a person qualified to work on high-voltage installations when this module is completed? 2. What is the code definition of high-voltage? 3. What is the IEEE definition

More information

3.1 Overview of ATCO Electric s URD System Design

3.1 Overview of ATCO Electric s URD System Design Page: 3-1 3.0 URD DESIGN GUIDELINES 3.1 Overview of ATCO Electric s URD System Design The power supply to all single lot underground residential services is through front lot service. Single phase transformers

More information

AFTER GAZETTING (WORKING DOCUMENT FOR A 3 YEAR PERIOD) DATE PAGE PARAGRAPH DESCRIPTION ORIGINATOR APPROVED

AFTER GAZETTING (WORKING DOCUMENT FOR A 3 YEAR PERIOD) DATE PAGE PARAGRAPH DESCRIPTION ORIGINATOR APPROVED PART B-07 TITLE: SERVICE CONNECTIONS SPECIFICTION NO: B-07 INCEPTION DATE: AFTER GAZETTING (WORKING DOCUMENT FOR A 3 YEAR PERIOD) AMENDMENTS / REVISIONS DATE PAGE PARAGRAPH DESCRIPTION ORIGINATOR APPROVED

More information

Technical Specification 43-8 Issue Amendment

Technical Specification 43-8 Issue Amendment PRODUCED BY THE OPERATIONS DIRECTORATE OF ENERGY NETWORKS ASSOCIATION Technical Specification 43-8 Issue 4 2015 + Amendment 1 2016 Overhead line clearances www.energynetworks.org PUBLISHING AND COPYRIGHT

More information

EE 741 Over-voltage and Overcurrent. Spring 2014

EE 741 Over-voltage and Overcurrent. Spring 2014 EE 741 Over-voltage and Overcurrent Protection Spring 2014 Causes of Over-voltages Lightning Capacitor switching Faults (where interruption occurs prior to zero current crossing) Accidental contact with

More information

TGK Prefabricated Substation Technical Data

TGK Prefabricated Substation Technical Data TGK Prefabricated Substation Technical Data Ref Item Data 1 General Technical 1.1 Frequency (Hz) 50 1.2 Transformer Rating (kva) 315/750 1.3 Transformer Primary Voltage (kv) 11 1.4 Transformer Secondary

More information

AMENDMENT ELECTRIC SERVICE MANUAL 2014

AMENDMENT ELECTRIC SERVICE MANUAL 2014 AMENDMENT (Pages 20,43,50,72,74,,76,78,83,86,99) ELECTRIC SERVICE MANUAL 2014 Effective April 1, 2015 18-7 6.0 SERVICE AND SERVICE ENTRANCES (General), Continued Conductor Sizing It is recommended that

More information

Comparison of Indian Electricity Rules, 1956 Vs CEA (Measures relating to Safety and Electric Supply) Regulations, 2010

Comparison of Indian Electricity Rules, 1956 Vs CEA (Measures relating to Safety and Electric Supply) Regulations, 2010 1 of 5. Comparison of Indian Electricity Rules, 1956 Vs CEA (Measures relating to Safety and Electric Supply) Regulations, 2010 2 Definitions 2 Not seen the definition for Inspector. But with, - Qualifications,

More information

CAT-1 Series 3. Installation Guide. The Valley Group, Inc. 871 Ethan Allen Hwy. Suite 104 Ridgefield, CT 06877

CAT-1 Series 3. Installation Guide. The Valley Group, Inc. 871 Ethan Allen Hwy. Suite 104 Ridgefield, CT 06877 CAT-1 Series 3 Installation Guide The Valley Group, Inc. 871 Ethan Allen Hwy. Suite 104 Ridgefield, CT 06877 (203) 431-0262 (203) 431-0296 FAX tvg@cat-1.com Installation of Load Cells for CAT-1 Systems

More information

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS 1. PURPOSE AND SCOPE OF THIS DOCUMENT... 3 2. DEFINITIONS...

More information

Volume-III : Section-I 370 Technical Specifications

Volume-III : Section-I 370 Technical Specifications Volume-III : Section-I 370 TECHNICAL SPECIFICATION-PIERCING INSULATOR 5.1 Insulation Piercing Connectors (IPC) 5.1.1 Insulation Piercing Connectors (IPC) are used for making Tee/Tap-off/Service connectors

More information

16kA Solid Dielectric, Triple Option Reclosers Catalog VLT12

16kA Solid Dielectric, Triple Option Reclosers Catalog VLT12 16kA Solid Dielectric, Triple Option Reclosers Providing electronic overcurrent protection for single or three phase operation on systems rated through 27kV, 630A continuous current, 16kA symmetrical interrupting

More information

CLP POWER HONG KONG LIMITED. SUPPLY RULES March 2001

CLP POWER HONG KONG LIMITED. SUPPLY RULES March 2001 CLP POWER HONG KONG LIMITED SUPPLY March 2001 ADVISORY SERVICE Advice concerning matters relating to the supply of electricity may be obtained free of charge from the Company. OTHER COMPANY PUBLICATIONS

More information

SERVICE ATTACHMENT ON A BUILDING WITH BUS DUCT SERVICE ENTRANCE AND INDOOR METERING

SERVICE ATTACHMENT ON A BUILDING WITH BUS DUCT SERVICE ENTRANCE AND INDOOR METERING SERVICE ATTACHMENT ON A BUILDING WITH BUS DUCT SERVICE ENTRANCE AND INDOOR METERING Obtain acceptance and specific details from the local Company office. 1. Service entrance duct (see Note 1). Company

More information

Power System Analysis I TRANSMISSION LINE PARAMETERS

Power System Analysis I TRANSMISSION LINE PARAMETERS Power System Analysis I TRANSMISSION LINE PARAMETERS Components of Overhead Lines Transmission Line Parameters An overhead transmission line consists of conductors, insulators, support structures, and,

More information

34-SDMS-01 SPECIFICATIONS FOR

34-SDMS-01 SPECIFICATIONS FOR SPECIFICATIONS FOR M V DROPOUT FUSE CUT OUTS This specification is property of SEC and subject to change or modification without any notice CONTENTS C l a u s e s: Page No. 1- SCOPE 3 2- CROSS REFERENCES

More information

MINIMUM DISTRIBUTION SYSTEM CONCEPTS AND APPLICATIONS. Larry Vogt. Manager, Rates

MINIMUM DISTRIBUTION SYSTEM CONCEPTS AND APPLICATIONS. Larry Vogt. Manager, Rates MINIMUM DISTRIBUTION SYSTEM CONCEPTS AND APPLICATIONS Larry Vogt Manager, Rates Minimum Distribution System What is MDS? MDS is an analysis module of the cost-of-service study in which distribution investment

More information

Aurora Energy Limited. Network Connection Requirements (NS5.1)

Aurora Energy Limited. Network Connection Requirements (NS5.1) Limited Version 1.1 Issued: 1June 2011 Status and Application of these Requirements All connections on the Aurora electrical distribution network (the Network) are subject to the contractual terms of a

More information

KYN28A-12 (GZS1) A.C METALCLAD REMOVABLE SWITCHGEAR FOR INDOOR USE CHINATCS

KYN28A-12 (GZS1) A.C METALCLAD REMOVABLE SWITCHGEAR FOR INDOOR USE CHINATCS KYN28A-12 (GZS1) A.C METALCLAD REMOVABLE SWITCHGEAR FOR INDOOR USE CHINATCS 2001.09 KYN28A-12 (GZS1) A.C Metalclad Removable Switchgear for Indoor Use --------The Leader in Switchgear Up to 12kV 1. The

More information

Port Hacking cable crossing project Community engagement and feedback summary August 2016

Port Hacking cable crossing project Community engagement and feedback summary August 2016 Port Hacking cable crossing project Community engagement and feedback summary August 2016 For period from April 2016 to 12 August 2016 1 Contents Contents... 2 1 Project background... 3 1.1 Project options...

More information

Electrical Awareness and Considerations

Electrical Awareness and Considerations Electrical Awareness and Considerations By David Taylor FIHE MIET IEng Objectives Awareness of specifications. Awareness of Distribution Network Operators (DNO) earthing arrangements. Awareness of basic

More information

Assembly instructions

Assembly instructions Please carefully read the assembly instructions before beginning the installation, operation and maintenance of the solar facility. Noncompliance could cause injury to persons or damage to the equipment.

More information

MATERIAL FOR FIBRE OPTIC LINES. General C-bracket HSU trunnion type, forged, for aluminium based OPGW conductors...

MATERIAL FOR FIBRE OPTIC LINES. General C-bracket HSU trunnion type, forged, for aluminium based OPGW conductors... 153 Contents General.................................................................................................. 154 C-bracket.................................................................................................

More information

SECTION 3 - PRIMARY CONSTRUCTION OVERHEAD TABLE OF CONTENTS

SECTION 3 - PRIMARY CONSTRUCTION OVERHEAD TABLE OF CONTENTS 03.00 GENERAL CONSTRUCTION NOTES PRIMARY CONSTRUCTION PRIMARY CONSTRUCTION PIN INSULATOR INSTALLATION 03.00-02 03.00-04 03.00-20 03.02 CONNECTORS AUTOMATIC SPLICE INSTALLATION 03.02-01 INSTALLATION GUIDE

More information

Innovators in Protection Technology Moulded Case Circuit Breaker Instruction Manual

Innovators in Protection Technology Moulded Case Circuit Breaker Instruction Manual Innovators in Protection Technology Moulded Case Circuit Breaker Instruction Manual 11-M61E TABLE OF CONTENTS HANDLING & MAINTENANCE Storage 1 Transport 1 STANDARD ENVIRONMENT 1 INSTALLATION AND CONNECTION

More information

THE DAYTON POWER AND LIGHT COMPANY Original Sheet No. 15 DPL Building Courthouse Plaza Southwest Dayton, Ohio P.U.C.O. NO. 1

THE DAYTON POWER AND LIGHT COMPANY Original Sheet No. 15 DPL Building Courthouse Plaza Southwest Dayton, Ohio P.U.C.O. NO. 1 THE DAYTON POWER AND LIGHT COMPANY Original Sheet No. 15 SCHEDULE 1 Schedule of fees and charges used for determining sacrifice value, excess height and/or strength and sale costs of poles. Year % Set

More information

Dead Tank Circuit Breaker 145PM40-C Compact design with enhanced reliability

Dead Tank Circuit Breaker 145PM40-C Compact design with enhanced reliability Dead Tank Circuit Breaker 145PM40-C Compact design with enhanced reliability ABB innovations for changing demands ABB (www.abb.com) is a leader in power and automation technologies that enables utility

More information

SIMOBREAKER The New Substation with Rotary Disconnector Fully Assembled, Compact and with High Availability

SIMOBREAKER The New Substation with Rotary Disconnector Fully Assembled, Compact and with High Availability SIMOBREAKER The New Substation with Rotary Disconnector Fully Assembled, Compact and with High Availability Convincing arguments for the outdoor modular switchgear bay Complete delivery from a single source

More information

SAFE WORK METHOD STATEMENT OVERHEAD AND UNDERGROUND ELECTRICAL CABLES

SAFE WORK METHOD STATEMENT OVERHEAD AND UNDERGROUND ELECTRICAL CABLES SAFE WORK METHOD STATEMENT OVERHEAD AND UNDERGROUND ELECTRICAL CABLES NOTE: = Risk Rating befe controls implemented - = Risk Rating after controls are implemented Task - Contact will not be made with underground

More information

Specification for 11kV and 33kV Overhead Lines of Unearthed Construction on Single and H Type Wood Poles

Specification for 11kV and 33kV Overhead Lines of Unearthed Construction on Single and H Type Wood Poles 1. SCOPE Specification for 11kV and 33kV overhead power lines of unearthed construction employing AAAC conductors, supported on single and H type wood pole supports. 2. ISSUE RECORD This is a Reference

More information

Mains Powered Energizer

Mains Powered Energizer Mains Powered Energizer Instruction Manual For more information: 1300 559 732 info@whitesgroup.com.au whitesgroup.com.au/obriens DISCLAIMER: Whilst every effort has been made to ensure accuracy, neither

More information

Figure 1. Non-removable buttonhead Edison Links. TABLE 1 Edison Link Fuse Designs. System Fuse Ampere Rating Type Rating

Figure 1. Non-removable buttonhead Edison Links. TABLE 1 Edison Link Fuse Designs. System Fuse Ampere Rating Type Rating Fusing Equipment Edison Links Electrical Apparatus K-SEC 100 GENERAL Cooper Power Systems Kearney line of fuse links, Edison Links, can be applied to a variety of applications requiring overcurrent protection

More information

THP145 HYBRID GAS INSULATED SWITCHGEAR (HGIS) Energy, Fast! tgood.com

THP145 HYBRID GAS INSULATED SWITCHGEAR (HGIS) Energy, Fast! tgood.com THP145 HYBRID GAS INSULATED SWITCHGEAR (HGIS) Energy, Fast! tgood.com TGOOD produces over 5000 switchgear units annually for projects around the globe SOLUTION OVERVIEW For use in affordable air insulated

More information

Small wonder. Station service voltage transformers for small power requirements

Small wonder. Station service voltage transformers for small power requirements Small wonder Station service voltage transformers for small power requirements MATHEW PAUL An estimated 1.3 billion people worldwide have no access to electricity. In small communities, this is often due

More information

Disconnect & ByPass Switches

Disconnect & ByPass Switches Disconnect & ByPass Switches Disconnect & Oil Circuit Recloser Bypass Switches; Regulator & Current Transformer Bypass Switches Electrical Apparatus K-SEC 060 & 090 Contents Type D-73 Distribution Class

More information

TEMPORARY ELECTRIC WIRING FOR CARNIVALS, CONVENTIONS, EXHIBITIONS, FAIRS AND SIMILAR USES

TEMPORARY ELECTRIC WIRING FOR CARNIVALS, CONVENTIONS, EXHIBITIONS, FAIRS AND SIMILAR USES INFORMATION BULLETIN / PUBLIC - ELECTRICAL CODE REFERENCE NO.: LAMC 93.0230 Effective: 3-24-69 DOCUMENT NO. P/EC 2002-006 Revised: 11-17-00 Previously Issued As: RGA #7-69 TEMPORARY ELECTRIC WIRING FOR

More information

III. Substation Bus Configurations & Substation Design Recommendations

III. Substation Bus Configurations & Substation Design Recommendations III. Substation Bus Configurations & Substation Design Recommendations 1.0 Introduction Pre-existing conditions, electrical arrangements or the criticality of the existing facility may limit this flexibility,

More information

INTRODUCTION. The plug-in connection on the cables and lightning arrestors, allows for easy installation and replacement.

INTRODUCTION. The plug-in connection on the cables and lightning arrestors, allows for easy installation and replacement. INTRODUCTION The Power Systems 44 kv MiniSub TM is the most compact system at this voltage available. Utilizing a deadfront termination and lightning arrestor setup, it eliminates the line top or side

More information

Wisconsin Public Utility Institute. June 28, Minimum Distribution Charges. Larry Vogt. Director, Rates Mississippi Power

Wisconsin Public Utility Institute. June 28, Minimum Distribution Charges. Larry Vogt. Director, Rates Mississippi Power Wisconsin Public Utility Institute June 28, 2017 Minimum Distribution Charges Larry Vogt Director, Rates Mississippi Power 1 Costs of Service vs. Cost Recovery Residential Service Example Assuming that

More information

URD Mini Pillar Installation Guide. UDS Universal Pillar Installation Guide. Cable to LV Isolators, Crossarm and Cable Detail

URD Mini Pillar Installation Guide. UDS Universal Pillar Installation Guide. Cable to LV Isolators, Crossarm and Cable Detail Part 5 LV Underground Drawing Register Number U8 U9 Description URD Mini Pillar Installation Guide UDS Universal Pillar Installation Guide U10-1 UDS Universal Pillar Double Link Unit Drilling Detail U10-2

More information

8DJ. Maintenance-free for lifetime

8DJ. Maintenance-free for lifetime 8DJ Maintenance-free for lifetime Energy Distribution Welcome! Page 2 October 1 st 2008 8DJ Main Applications for Medium-Voltage Switchgear Power generation Power stations G Power transmission High and

More information

OPERATING MANUAL C-1350 CABLE PUSHER. Copyright 2003 by CBS Products (KT), Ltd

OPERATING MANUAL C-1350 CABLE PUSHER. Copyright 2003 by CBS Products (KT), Ltd CBS Products (KT), Ltd, Pillings Road, Oakham, Rutland, LE15 6QF. UK Telephone: +44(0)1572723665 Fax: +44(0)1572 756006 E-Mail: sales@cbsproducts.com Website:www.cbsproducts.com OPERATING MANUAL C-1350

More information

TRELLEBORG ENGINEERED PRODUCTS. Electrical Safety Products

TRELLEBORG ENGINEERED PRODUCTS. Electrical Safety Products Electrical Safety Products Highest standard of protection. A safe working environment is important in all industries, but in the electrical generation and supply industry, it is paramount. Trelleborg specifically

More information

045 : 2000 CEB STANDARD

045 : 2000 CEB STANDARD 045 : 2000 CEB STANDARD LOW VOLTAGE FUSE SWITCH DISCONNECTOR CEYLON ELECTRICITY BOARD SRI LANKA Specification for LOW VOLTAGE FUSE SWITCH DISCONNECTOR CEB Standard 045 : 2000 CEYLON ELECTRICITY BOARD No.

More information

ZF SERIES HV GAS INSULATED SWITCHGEAR (GIS) tgood.com. Energy. Fast.

ZF SERIES HV GAS INSULATED SWITCHGEAR (GIS) tgood.com. Energy. Fast. ZF SERIES HV GAS INSULATED SWITCHGEAR (GIS) tgood.com Energy. Fast. TGOOD produces over 5000 switchgear units annually for projects around the globe PRODUCT OVERVIEW High performance alternative to air

More information

PRIVATELYOWNED POWER POLES AND POWERLINES

PRIVATELYOWNED POWER POLES AND POWERLINES PRIVATELYOWNED POWER POLES AND POWERLINES Privately-owned power poles and powerlines Privately-owned power poles and overhead powerlines must be properly maintained to ensure that they do not pose a serious

More information

7. Residential Single-Family and Duplex Buildings (Dwellings)

7. Residential Single-Family and Duplex Buildings (Dwellings) Sin g le -F a mily a n d Du p le x Bu ild in g s 2016 Electric Service Requirements, 2 nd Edition Section 7 Section 7 Residential Single-Family and Duplex Buildings (Dwellings) Directory Page 7.1 General

More information

produces and delivers products worldwide can provide the optimal solution for your requirements. are dedicated to supplying you with

produces and delivers products worldwide can provide the optimal solution for your requirements. are dedicated to supplying you with www.ppcinsulators.com The very Best. The very Best. That s what we deliver. Only a company that develops, produces and delivers products worldwide can provide the optimal solution for your requirements.

More information

ICOMIA Global Conformity Guideline for ISO/ABYC Standards and Canadian TP 1332 requirements. Guideline Number 3 Electrical

ICOMIA Global Conformity Guideline for ISO/ABYC Standards and Canadian TP 1332 requirements. Guideline Number 3 Electrical ICOMIA Global Conformity Guideline for ISO/ABYC Standards and Canadian TP 1332 requirements 1. PURPOSE sponsored by ABYC, BMF, ICOMIA, IMCI, and NMMA Author: Wieger de Wit Guideline Number 3 Electrical

More information

Live-line transmission lines upgrade projects. First-in-Africa project

Live-line transmission lines upgrade projects. First-in-Africa project Live-line transmission lines upgrade projects First-in-Africa project Author & presenter: Patrick O Halloran BTECH Manager Technology Services at City Power Johannesburg Abstract This paper covers live-line

More information

Diane Lindsey CenterPoint Energy SWEDE 2010

Diane Lindsey CenterPoint Energy SWEDE 2010 Diane Lindsey CenterPoint Energy SWEDE 2010 Agenda Background Pre Hurricane Ike Dredge Evaluation Aftermath of Hurricane Ike in 2008 Temporary West Galveston Mobile Substation Post Hurricane Ike Dredge

More information

EARTH WIRE FITTINGS 08

EARTH WIRE FITTINGS 08 EARTH WIRE FITTINGS 08 8 EARTH WIRE FITTINGS 119 Contents General... 120 C-bracket... 123 Suspension clamp with bolt, with straps, for steel and copper conductors... 123 Suspension clamp with bolt, with

More information

CABLE SYSTEMS. Accessories and Systems for Medium and High-Voltage Cables up to 300 kv.

CABLE SYSTEMS. Accessories and Systems for Medium and High-Voltage Cables up to 300 kv. MV-CONNEX, HV-CONNEX, IXOSIL Terminations, IXOSIL MSA Slip-on Joint Boxes CABLE SYSTEMS Accessories and Systems for Medium and High-Voltage Cables up to 300 kv. Welcome to the CABLE SYSTEMS Centre of Competence.

More information

Transmission & Distribution Glossary of Electrical Terms

Transmission & Distribution Glossary of Electrical Terms Transmission & Distribution Glossary of Electrical s Breaker Panel Bushing Circuit Circuit Breaker Conductor Conduit Consumption Current Distribution Electricity (Static vs. Current) Electron Feeder The

More information

FUSES. Safety through quality

FUSES. Safety through quality Safety through quality HH HIGH VOLTAGE Over many decades SIBA has developed a global product line of High Voltage Fuses that are comprehensive for any and all applications. Superior engineering, advanced

More information

WILDLIFE PROTECTION

WILDLIFE PROTECTION 05 00 00 01 TABLE OF CONTENTS GENERAL INFORMATION INSTALLATION OF CRITTER LINE GUARDS INSTALLATION OF TANK MOUNTED LIGHTNING ARRESTER BRACKET GUARDS 25KV & BELOW EXISTING STRUCTURE MODIFICATION 05 00 00

More information

MOBILE SUBSTATION DESIGN Brad Bozich & Vitor Vieira 2755 Northwoods Parkway Norcross, Georgia

MOBILE SUBSTATION DESIGN Brad Bozich & Vitor Vieira 2755 Northwoods Parkway Norcross, Georgia MOBILE SUBSTATION DESIGN Brad Bozich & Vitor Vieira 2755 Northwoods Parkway Norcross, Georgia 30071 678.982.8928 brad.bozich@efacec.com SCOPE This document is intended to help define the main parameters

More information

Solid Dielectric, Triple Option Reclosers Catalog O-vlt14

Solid Dielectric, Triple Option Reclosers Catalog O-vlt14 Solid Dielectric, Triple Option Reclosers Providing electronic overcurrent protection for single or three phase operation on systems rated through 27kV, 630A or 800A continuous current, 12.5 or 16kA symmetrical

More information

DIN HV Distribution. DIN HV fuses are partial-range high voltage currentlimiting fuses for use in distribution circuits from kV.

DIN HV Distribution. DIN HV fuses are partial-range high voltage currentlimiting fuses for use in distribution circuits from kV. DIN HV Distribution DIN HV fuses are partial-range high voltage currentlimiting fuses for use in distribution circuits from 2.3-38kV. Their compact dimensions and non-venting characteristics make them

More information

Proposed Dounreay - Mybster 275 kv / 132 kv

Proposed Dounreay - Mybster 275 kv / 132 kv Background Scottish Hydro-Electric Transmission Ltd (SHETL) is proposing a new 275 kilovolt (kv) (1 kilovolt = 1000volts) double circuit overhead line (OHL) between the Dounreay sub station and the new

More information

AGRICULTURAL UNDERGROUND SERVICE 500 HP OR LESS

AGRICULTURAL UNDERGROUND SERVICE 500 HP OR LESS Prepared by: ABB1 AGRICULTURAL UNDERGROUND SERVICE 500 HP OR LESS 05619 Asset Type: Electric Metering Function: Design and Construction Issued by: Lisseth Villareal (LDV2) Date: 07-31-15 Rev. #10: This

More information

Distribution networks : Low Voltage Aerial Cables

Distribution networks : Low Voltage Aerial Cables Distribution networks : Low Voltage Aerial Cables Energy Infrastructures Generation Transmission - Distribution 050804 Nexans LV ABC & Accessories PK 2 Distribution networks : Low Voltage Aerial Bundled

More information

Procedure PR D Definitions and Conventions for Electrical Safety. Engineering Procedure Electrical Distribution Unit. Version 1.

Procedure PR D Definitions and Conventions for Electrical Safety. Engineering Procedure Electrical Distribution Unit. Version 1. Engineering Procedure Electrical Distribution Unit PR D 78100 Definitions and Conventions for Electrical Safety Version 1.0 Date in Force: 26 February 2016 Procedure UNCONTROLLED COPY WHEN PRINTED Approved

More information

OVERHEAD CONSTRUCTION MANUAL

OVERHEAD CONSTRUCTION MANUAL OVERHEAD CONSTRUCTION MANUAL Section Materials Quick Reference Approved by: A Smith-de Pere Energex Limited 214 ABN 4 78 849 55 DOCUMENT NUMBER: 492-A4 LAST UPDATE: 27/2/214 APPLE 6/113. 8372 APPLE 6/113.

More information

TABLE OF CONTENTS Page:

TABLE OF CONTENTS Page: TABLE OF CONTENTS Page: 1. LINETROLL 111K OVERVIEW... 2 2. FUNCTIONAL DESCRIPTION... 3 2.1. Adaptive detector... 3 2.2. Operation criteria... 3 2.2.1 Inrush blocking time 2.2.2 Fault current passage 2.2.3

More information

ACCESSORIES FOR LPOF, HPPT AND XLPE HIGH VOLTAGE CABLE SYSTEMS PRODUCT CATALOGUE

ACCESSORIES FOR LPOF, HPPT AND XLPE HIGH VOLTAGE CABLE SYSTEMS PRODUCT CATALOGUE ACCESSORIES FOR LPOF, HPPT AND XLPE HIGH VOLTAGE CABLE SYSTEMS PRODUCT CATALOGUE hvgrid-tech designs and manufactures high voltage cable accessories for all types of cable systems, ranging from 69 kv to

More information

Outdoor live tank vacuum circuit breaker Type OVB-VBF for 24/36/40.5 kv applications

Outdoor live tank vacuum circuit breaker Type OVB-VBF for 24/36/40.5 kv applications Outdoor live tank vacuum circuit breaker Type OVB-VBF for 24/36/40.5 kv applications ABB a global leader ABB is a global leader in power and automation technologies that enable utility and industry customers

More information

COMMERCIAL QUICK REFERENCE

COMMERCIAL QUICK REFERENCE COMMERCIAL QUICK REFERENCE PROVO CITY POWER STANDARDS ELECTRICAL ENGINEERING UPDATED: 2016 SPECIFICATIONS SUBJECT TO CHANGE WITHOUT NOTIFICATION. 18" MIN. OF TAIL. (NEUTRAL CONDUCTOR MUST BE WHITE OR

More information

Low Voltage Power Supplies in Electrified Areas

Low Voltage Power Supplies in Electrified Areas Low Voltage Power Supplies in Electrified Areas Synopsis This document mandates requirements for control of return and stray currents and the management of earthing for low voltage power supplies in electrified

More information

Procedure PR D Electrical Permits. Engineering Procedure Electrical Distribution Unit. Version 1.0. Date in Force: 4 November 2015

Procedure PR D Electrical Permits. Engineering Procedure Electrical Distribution Unit. Version 1.0. Date in Force: 4 November 2015 Engineering Procedure Electrical Distribution Unit PR D 78500 Electrical s Version 1.0 Date in Force: 4 November 2015 Procedure UNCONTROLLED COPY WHEN PRINTED Approved by: Sean Budge Manager Electrical

More information