CHAPER 5 POWER FLOW STUDY IN THE INTEGRATED GRID NETWORK
|
|
- Berenice Park
- 5 years ago
- Views:
Transcription
1 91 CHAPER 5 POWER FLOW STUDY IN THE INTEGRATED GRID NETWORK CHAPTER CONTENTS: 5.1 INTRODUCTION 5.2 CONDUCTION OF VARIOUS POWER FLOW STUDIES ON THE MODEL 5.3 EXPERIMENTS CONDUCTED FOR VARIOUS POWER FLOW STUDIES 5.4 CHAPTER CONCLUSION 5.1 INTRODUCTION Power flow studies are important in planning and designing of the power system. The future expansion of power system as well as determining the best operation of existing system is also dependant of power flow studies of the system. In our designed system, the major information attained from a power flow study is the magnitude of the voltage at each bus and the real and reactive power flowing in each line. The designed prototype of power grid with SCADA software provides clear insight into the power flow mechanism of an interconnected grid network. It has facilities for measuring active parameters: V, I. mva, mw, mvar and Power Factor at each Generator, Transmission Line and load. The current that flows in different parts of a power system immediately after the occurrence of a fault differ from those flowing a few cycles later just before the circuit breakers trip to open the line on both sides of the fault. And those currents differ widely from the current which would flow under steady state conditions if the fault were not isolated from the rest of the system by the operation of circuit breakers. Selection of the circuit breaker depends upon the current flowing immediately after the fault occurs and the minimum current on which the breaker must break off.
2 CONDUCTION OF VARIOUS POWER FLOW STUDIES ON THE MODEL The main experiments that are conducted to examine proper power flow in the grid prototype are as follows: 1. Monitoring and Control of Voltage, Speed and Frequency through SCADA Automation 2. Synchronization amongst all the three generators 3. While achieving synchronization amongst all the three generators, checking the functionality of synchroscope and more importantly the functionality of protection system i.e. Reverse Power Relay (RPR) 4. The voltage changes of the generator bus bar on load fluctuation 5. Changes that occur in other two generators during fault in one generator (Regulation) 6. Changes that occur in other loads during fault in one generator (Load Shedding) 7. Changes that occur in transmission lines during fault in one generator. 8. Fault simulation to test status of Miniature Circuit Board (MCB) & Over Current Relay (OCR) 9. Observation and control of Active Power, Reactive Power and Power Factor in all the bus bars of generators, loads and transmission lines without the FACT device UPFC 10. Observation and control of Active Power, Reactive Power and Power Factor in all the bus bars of generators, loads and transmission lines with the FACT device UPFC (by varying its series and shunt transformer output)
3 EXPERIMENTS CONDUCTED FOR VARIOUS POWER FLOW STUDIES EXPERIMENT 1: This experiment comprises one generator, one 300 km transmission line, one 200 km transmission line and one load (Refer figure 5.1). Here the power flow study is made to examine the functionality of power transmission from generator to load via the transmission lines. Figure no. 5.1: Power flow from generator to load
4 94 In this experiment, there is a Generator. Transmission line is divided into two sections one of 300 km and the other of 200 km, and one Load. This is a three phase (RYB) system which represents the power flow. The experiment is conducted by operating the model manually as well as through SCADA. The generator voltage is kept at 100V. The generator current, power and other data are seen on MFM. The functionality of the related components mounted on the model is verified through this experiment. EXPERIMENT 2: This experiment is conducted with two generators, three transmission lines and two loads. Power flow is studied in using generators G1 & G2, loads L1 & L2, and transmission lines TL1 & TL2. Transmission line TL 3, which is a Tie Line, interconnects the two areas. In this power flow study the importance of direction of power flow and synchronization of the two generators were studied. Refer figure 5.2. Figure no. 5.2: The circuit of power system where two generators, two loads and three transmission line are interconnected
5 95 In this experiment the synchronization between two generators is achieved and process is studied, here a synchroscope is used for monitoring synchronization (Refer figure 5.3). The main factors which have to be controlled to achieve synchronizing state are: Frequency, Voltage and Phase Angle. These factors can be controlled by speed and excitation of motor generator and voltage regulation through voltage regulating VARIAC. This is necessary because exactly at that time the circuit breaker is switched on to join the tie line connected between the two generators. Without synchronization the two generators should not be connected to the bus bar as it may swing the alternator. There is Reverse Power Relay placed for protection to prevent power flow in reverse direction. Figure no. 5.3: Generator with Reverse Power Relay for its protection
6 96 Figure 5.2 shows the circuit that is tested using two generators, three transmission lines and two loads. At load bus 1 and load bus 2 are interconnected by a Tie Line to demonstrate the flow of power from bus 1 to bus 2. This is achieved by keeping the Voltage at load bus 1 higher than the load bus 2. The following information is obtained from the test. The power generated by the alternator 1 is 4 Ampere at 250 volts where as the load 1 was 3 Amperes, therefore the 1 Ampere power can be diverted through the Tie Line to the load bus 2 to supply the load 2 of 3 Ampere capacity, whereas the generator 2 contributed 2 Ampere. The process here is controlled manually as well as through computer command. Paralleling AC Generators in the Experiment: Most electrical power grids and distribution systems have more than one AC generator operating at one time. Normally, two or more generators are operated in parallel in order to supply the demand of power. Three conditions must be met prior to paralleling of (or synchronizing) AC generators: 1. Their terminal voltages must be equal. If the voltages of the two AC generators are not equal, one of the AC generators would act as a reactive load to the other AC generator. This causes high currents to be exchanged between the two machines, possibly causing generator or distribution system damage. 2. Their frequencies must be equal. A mismatch in frequencies of the two AC generators will cause the generator with the lower frequency to act as a load on the other generator a condition referred to as motoring. 3. Their output voltages must be in phase. A mismatch in the phases will develop opposing voltages. The worst case would be 180 out of phase, resulting in an opposing voltage between the two generators of twice the output voltage. This high voltage can cause damage to the generators and distribution system due to high currents. During paralleling operations, voltages of the two generators that are to be paralleled are indicated through the use of voltmeters. Frequency matching is accomplished through the use of output frequency meters.
7 97 Phase matching is accomplished through the use of a synchroscope. It is a device that senses the two frequencies and gives an indication of phase differences and a relative comparison of frequency differences. Along with various power flow studies, some fault studies are also done. Faults are simulated to test status of Miniature Circuit Board (MCB) & Over Current Relay (OCR). There is provision of applying and using Digital Numerical Distance Relay (DNDR). Experiments using DNDR can be performed by simulating different types of faults but are not performed in our work. DNDR will indicate the distance to fault. Different types of faults are studied that frequently occur in the transmission lines are: 1. Double Line Fault (Figure 5.4) 2. Triple line Fault (Figure 5.5) 3. Line to Ground Fault (Figure 5.6) 4. Double Line to Ground Fault (Figure 5.7) 5. Triple Line to Ground Fault (Figure 5.8) Figure 5.4: Double Fault Line Figure 5.5: Triple Line Fault
8 98 Figure no. 5.6: Line to Ground Fault Figure no. 5.7: Double Line to Ground Fault Figure no. 5.8: Triple Line to Ground Fault
9 CHAPTER CONCLUSION To study proper power flow and working of all the components installed on the model, a Power System Model is designed here which simulates 400 kv, 500 km High Voltage Transmission Line. The following experiments are performed using this model: 1. Simulating faults conditions in the two sections of the simulated transmission line. 2. Power flow in Interconnected Grid network. 3. Data Acquisition and Supervisory Control using the SCADA architecture provided on the model. Faults are simulated to test status of Miniature Circuit Board (MCB) & Over Current Relay (OCR). The experiments may be conducted on the Power System Model to study working of DNDR which will provide protection to the transmission line by tripping the circuit and indicating distances of different types of faults (L-G, L-L, LL-G, LLL, LLL-G) common in overhead transmission lines. In most of the cases, the lines are not provided with the arrangement of DNDR due to the cost factor. The SCADA automation is implemented on the model to understand the architecture and its performance on a grid network of power system. The software screen indicates the layout of facilities for data acquisition from the MFM and remote supervisory control command that is used to control operational function of the model. The SCADA architecture implemented on the power system model comprises Siemens PLC, relays, software and software program. The SCADA is tested on the model and is found to work smoothly and accurately. The precautions are taken for providing good earthing and using co-axial connecting leads.
Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood
Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents
More informationCHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM
61 CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 3.1 INTRODUCTION The modeling of the real time system with STATCOM using MiPower simulation software is presented in this
More informationREDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION
REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION Summary Abhay Kumar Mata Prasad R C Maheshwari Asea Brown Boveri Ltd. 4th Floor, 71 Nehru Place, New Delhi
More informationABB POWER SYSTEMS CONSULTING
ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February
More informationIslanding of 24-bus IEEE Reliability Test System
Islanding of 24-bus IEEE Reliability Test System Paul Trodden February 14, 211 List of Figures 1 24-bus IEEE RTS, with line (3,24) tripped and buses 3,24 and line (3,9) uncertain....................................
More informationFifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008
Performance Evaluation of Composite Islanding and Load Management System using Real Time Digital Simulator Sachin Srivastava, Meera K.S, R.S. Shivakumara Aradhya and Sunil Verma Abstract A Composite Islanding
More informationVoltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC
IJSTE - International Journal of Science Technology & Engineering Volume 2 Issue 01 July 2015 ISSN (online): 2349-784X Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC Ravindra Mohana
More informationIslanding of 24-bus IEEE Reliability Test System
Islanding of 24-bus IEEE Reliability Test System Paul Trodden February 17, 211 List of Figures 1 24-bus IEEE RTS, with line (3,24) tripped and buses 3,24 and line (3,9) uncertain....................................
More informationPID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation
PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date
More informationDG SYNCHRONIZING &AMF PANEL
A 80, Sector 80, Phase 2, Noida 201305, Utter Pradesh, India DG SYNCHRONIZING &AMF PANEL Clients Bharat Petroleum Corp.Ltd PROJECT- DG Synchronization panel with AMF function. Design BY:- Errection By
More informationSYSTEM INTEGRATION. Railway and urban transport electrification Energy-efficient and reliable solutions
SYSTEM INTEGRATION Railway and urban transport electrification Energy-efficient and reliable solutions 2 R A I LWAY & U R B A N T R A N S P O R T E L E C T R I F I C AT I O N S O L U T I O N S ABB s substation
More informationGE Energy. Variable Frequency Transformers Grid Inter-tie
GE Energy Variable Frequency Transformers Grid Inter-tie Variable Frequency Transformers GE Energy revolutionizes the world of transmission solutions with its new Variable Frequency Transformer (VFT).
More informationPSO project EaseWind Enhanced ancillary services from Wind Power Plants. Anca D. Hansen DTU Wind Energy
PSO project EaseWind Enhanced ancillary services from Wind Power Plants Anca D. Hansen DTU Wind Energy Background PSO project EaseWind (2011-2014) Enhanced Ancillary Services from Wind Power Plants Partners:
More informationPerformance Analysis of Transient Stability on a Power System Network
Performance Analysis of Transient Stability on a Power System Network Ramesh B Epili 1, Dr.K.Vadirajacharya 2 Department of Electrical Engineering Dr. Babasaheb Ambedkar Technological University, Lonere
More informationNETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources
NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources Marija Ilic milic@netssinc.com and Jeffrey Lang jeffrey.lang@netssinc.com Principal NETSS Consultants
More informationDEMONSTRATION OF ESSENTIAL RELIABILITY SERVICES BY A 300-MW SOLAR PV POWER PLANT
DEMONSTRATION OF ESSENTIAL RELIABILITY SERVICES BY A 300-MW SOLAR PV POWER PLANT CONTROL SYSTEM DESIGN FIRST SOLAR PLANT CONTROL SYSTEM ARCHITECTURE Monitor conditions at the POI and compare them with
More informationIntroduction. Systems Specifications
Project Name: MANiFEST Description: Real and Reactive Power Profiles Intended for Calibration of Energy Storage Systems Initial Author(s): SN/DTG The University of Sheffield; AMP/RT The University of Manchester
More informationAswan high dam - Distributed control system AUTOMATION
Aswan high dam - Distributed control system AUTOMATION Power System Overview Aswan High Dam (AHD) -Hydro Power Plant was erected and commissioned in 1972. At the time it was the world's greatest, as well
More informationSmall Electrical Systems (Microgrids)
ELG4126: Microgrids Small Electrical Systems (Microgrids) A microgrid is a localized, scalable, and sustainable power grid consisting of an aggregation of electrical and thermal loads and corresponding
More informationEH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map
EH2741 Communication and Control in Electric Power Systems Lecture 3 Lars Nordström larsn@ics.kth.se 1 Course map 2 1 Outline 1. Repeating Power System Control 2. Power System Topologies Transmission Grids
More informationEE 456 Design Project
F-2014 EE 456 Design Project PROJECT REPORT MALUWELMENG, CONNIE SHARP, MEGAN Table of Contents Introduction... 2 Assignment I... 2 Setup... 2 Simulation... 2 Assignment II... 3 Problems... 3 Solution...
More informationGuideline for Parallel Grid Exit Point Connection 28/10/2010
Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND
More informationGenerator Interconnection System Impact Study For
Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...
More informationEL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS
EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004
More informationELG4125: Flexible AC Transmission Systems (FACTS)
ELG4125: Flexible AC Transmission Systems (FACTS) The philosophy of FACTS is to use power electronics for controlling power flow in a transmission network, thus allowing the transmission line to be loaded
More informationUNC-Charlotte's Power Engineering Teaching lab
1 UNC-Charlotte's Power Engineering Teaching lab B. Chowdhury Panel Session Title: Existing and Proposed Power Systems Laboratories for the Undergraduate Curriculum PES GM 2015 2 Outline Background - Energy
More informationGeneration Interconnection Facilities Study For
Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015 TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications...
More informationMar H: SUPPLEMENTAL PARALLELING GEAR (16315-H)
2101 Commonwealth Blvd, Suite B Ann Arbor, MI 48105-5759 www.med.umich.edu/facilities/plan/ 263010-H: SUPPLEMENTAL PARALLELING GEAR (16315-H) Related Sections Basis Guideline: N/A For an explanation of
More informationVariable frequency transformer for asynchronous power transfer
Variable frequency transformer for asynchronous power transfer by Einar Larsen, Richard Piwko and Donald McLaren, GE Energy A new power transmission technology has been developed. The variable frequency
More informationNext-generation SCADA and Control Technologies for Large-scale Use of Photovoltaic Generation on Electric Power Grid
Hitachi Review Vol. 60 (2011), No. 3 143 Next-generation SCADA and Control Technologies for Large-scale Use of Photovoltaic Generation on Electric Power Grid Masahiro Watanabe Tsukasa Onishi Takahiro Omori
More informationLow Voltage Automatic Transfer Switch Systems
Suitable for Emergency, Peak and Prime Power System Applications Low Voltage Automatic Transfer Switch Systems THE POWER AUTHORITY THE POWER AUTHORITY ASCO s experience and commitment to excellence in
More informationInterconnection System Impact Study Report Request # GI
Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010
More informationCOMPARISON OF DIFFERENT SOFTWARE PACKAGES IN POWER FLOW AND SHORT-CIRCUIT SIMULATION STUDIES. A Project
COMPARISON OF DIFFERENT SOFTWARE PACKAGES IN POWER FLOW AND SHORT-CIRCUIT SIMULATION STUDIES A Project Presented to the faculty of the Department of Electrical and Electronic Engineering California State
More informationSIEMENS POWER SYSTEM SIMULATION FOR ENGINEERS (PSS/E) LAB1 INTRODUCTION TO SAVE CASE (*.sav) FILES
SIEMENS POWER SYSTEM SIMULATION FOR ENGINEERS (PSS/E) LAB1 INTRODUCTION TO SAVE CASE (*.sav) FILES Power Systems Simulations Colorado State University The purpose of ECE Power labs is to introduce students
More informationA system fault contribution of 750 mva shall be used when determining the required interrupting rating for unit substation equipment.
General Unit substations shall be 500 kva minimum, 1500 kva maximum unless approved otherwise by the University. For the required configuration of University substations see Standard Electrical Detail
More informationString Monitoring and Control System for Solar Photo Voltaic Power Plants
ISSN 2278 0211 (Online) String Monitoring and Control System for Solar Photo Voltaic Power Plants K. Ajay Senior Manager, Control & Instrumentation Lab, BHEL Corporate Research & Development, Vikasnagar,
More informationXXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS
XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS El Paso Electric Company System Operations Department System Planning
More informationCHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM
106 CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM 5.1 INTRODUCTION Inherent characteristics of renewable energy resources cause technical issues not encountered with conventional thermal,
More informationDesign considerations for generator set mounted paralleling breakers
Our energy working for you. Design considerations for generator set mounted paralleling breakers White Paper Hassan Obeid, Application Group Cummins Power Generation Cummins Power Systems has been delivering
More informationFabrication and Automation of Solvent less Packaging Machine
Fabrication and Automation of Solvent less Packaging Machine Masood Nazir*, Prof Rashmi Ranjan Das# * M.tech Student at School of Electrical Engineering, VIT University Vellore, Tamilnadu-632014 India
More informationExperience on Technical Solutions for Grid Integration of Offshore Windfarms
Experience on Technical Solutions for Grid Integration of Offshore Windfarms Liangzhong Yao Programme Manager AREVA T&D Technology Centre 18 June 2007, DTI Conference Centre, London Agenda The 90MW Barrow
More informationDesign and Hardware Implementation of a Supervisory Controller for a Wind Power Turbine
ECE 4600 Group Design Project Proposal Group 09 Design and Hardware Implementation of a Supervisory Controller for a Wind Power Turbine Supervisors Annakkage, Udaya D., P.Eng McNeill, Dean, P.Eng Bagen
More informationPJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008
PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral
More informationISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements
Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner
More informationPower Consump-on Management and Control for Peak Load Reduc-on in Smart Grids Using UPFC
1 Power Consump-on Management and Control for Peak Load Reduc-on in Smart Grids Using UPFC M. R. Aghaebrahimi, M. Tourani, M. Amiri Presented by: Mayssam Amiri University of Birjand Outline 1. Introduction
More informationOMAR - Power Generation AUTOMATION
OMAR - Power Generation AUTOMATION SYRIA Power System Overview POWER GENERATION & DISTRIBUTION SYSTEM - OMAR in Al Furat oil fields - Omar, Syria Location: Gas Plant Generators: 2 Devices: 18 Large consumers:
More informationWang Bin & Michael Ho, TIIAE Power management system
Wang Bin & Michael Ho, TIIAE 2011 Power management system Content Introduction System configuration Functionality Reference Summary Live demonstration Q & A ABB Group September 5, 2011 Slide 2 Content
More informationThe University of New South Wales. School of Electrical Engineering and Telecommunications. Industrial and Commercial Power Systems Topic 6
The University of New South Wales School of Electrical Engineering and Telecommunications Industrial and Commercial Power Systems Topic 6 PROTECTIONS 1 FUNCTION OF ELECTRICAL PROTECTION SYSTEMS Problems:
More informationFeasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation
Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT
More informationAppendix A. Power Management System Test Guidelines
Appendix A Power Management System Test Guidelines The MTS DP Committee wants to thank Don Wilkes of Minden Engineering Company for his authorship of this appendix to the Test Guidelines Table of Contents
More informationHIGH VOLTAGE MODULE TEST SYSTEM
HIGH VOLTAGE MODULE TEST SYSTEM 4.0/4 Module Test Systems n AC, DC, and impulse testing n Factory testing n R&D n Education / training MODULES FOR VOLTAGE GENERATION Test transformers for 100 and 200 kv
More informationBenefits of HVDC and FACTS Devices Applied in Power Systems
Benefits of HVDC and FACTS Devices Applied in Power Systems 1 P. SURESH KUMAR, 2 G. RAVI KUMAR 1 M.Tech Research Scholar, Priyadarshini Institute of Technology & Management 2 Associate Professor, Priyadarshini
More informationPower Conditioning of Microgrids and Co-Generation Systems
Power Conditioning of Microgrids and Co-Generation Systems Nothing protects quite like Piller piller.com Content 1 Introduction 3 2 Basic requirements of a stable isolated network 3 3 Requirements for
More informationProject #148. Generation Interconnection System Impact Study Report
Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection
More informationInterconnection Feasibility Study Report GIP-226-FEAS-R3
Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power
More informationNew 115 kv Disconnect Switches at Bloomsburg MTS
115 kv Line tap from C9 to Bloomsburg MTS & New Bus Tie Switch CAA ID Number: 2007-EX353 Final Draft ASSESSMENT SUMMARY 1. GENERAL DESCRIPTION Norfolk TS and Bloomsburg MTS are supplied by a single 115
More informationTIME REQUIREMENT GUIDE (TRG)
CAT SWITCHGEAR TIME REQUIREMENT GUIDE (TRG) This warranty repair time requirement guide is designed to: Provide detailed guidance on troubleshooting Determine possible solutions Guide the technician to
More informationControl System for a Diesel Generator and UPS
Control System for a Diesel Generator and UPS I. INTRODUCTION In recent years demand in the continuity of power supply in the local distributed areas is steadily increasing. Nowadays, more and more consumers
More informationGrid Stability Analysis for High Penetration Solar Photovoltaics
Grid Stability Analysis for High Penetration Solar Photovoltaics Ajit Kumar K Asst. Manager Solar Business Unit Larsen & Toubro Construction, Chennai Co Authors Dr. M. P. Selvan Asst. Professor Department
More informationDISTRIBUTED GENERATION FROM SMALL HYDRO PLANTS. A CASE STUDY OF THE IMPACTS ON THE POWER DISTRIBUTION NETWORK.
DISTRIBUTED GENERATION FROM SMALL HYDRO PLANTS. A CASE STUDY OF THE IMPACTS ON THE POWER DISTRIBUTION NETWORK. N. Lettas*, A. Dagoumas*, G. Papagiannis*, P. Dokopoulos*, A. Zafirakis**, S. Fachouridis**,
More informationUnit Protection System for Pumped-Storage Power Stations
Unit Protection System for Pumped-Storage Power Stations 1. Introduction In many power systems, pumped-storage power stations are used in addition to run-of-river power stations. These power stations serve
More informationExperience on Realizing Smart Grids. IEEE PES conference, Gothenburg
Experience on Realizing Smart Grids Bazmi Husain 2010-10-12 IEEE PES conference, Gothenburg IEEE PES Conference, Gothenburg, 2010-10-12. Slide 1 On the way to the smarter grid A quietly astounding evolution
More informationInterconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado
Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission
More informationModular Standardized Electrical and Control Solutions for Fast Track Projects
Modular Standardized Electrical and Control Solutions for Supporting fast track projects ABB is the leading supplier of electrical and control equipment for power plants. The company offers a comprehensive
More informationImplementation of Steady-State Power System Visualizations Using PowerWorld Simulator. Dr. Jung-Uk Lim, Department of Electrical Engineering
A. Title Page Implementation of Steady-State Power System Visualizations Using PowerWorld Simulator Dr. Jung-Uk Lim, Department of Electrical Engineering B. Statement of problem researched or creative
More informationNEPAL ELECTRICITY AUTHORITY (A Government of Nepal Undertaking)
NEPAL ELECTRICITY AUTHORITY (A Government of Nepal Undertaking) Generation Directorate Medium Generation Operation and Maintenance Department SUNDARIJAL HYDROPOWER PLANT REHABILITATION PROJECT Electricity
More informationElectrical Theory. Generator Theory. PJM State & Member Training Dept. PJM /22/2018
Electrical Theory Generator Theory PJM State & Member Training Dept. PJM 2018 Objectives The student will be able to: Describe the process of electromagnetic induction Identify the major components of
More informationEPE97 OPTIMIZED DESIGN OF VARIABLE-SPEED DRIVES BASED ON NUMERICAL SIMULATION
EPE97 OPTIMIZED DESIGN OF VARIABLE-SPEED DRIVES BASED ON NUMERICAL SIMULATION J.-J.Simond*, A.Sapin**, B.Kawkabani*, D.Schafer***, M.Tu Xuan*, B.Willy*** *Swiss Federal Institute of Technology, Electrical
More informationPower Solutions Manager Generac Power Systems, Inc.
Engine Generator Paralleling Concepts Gen. #1 Gen. #2 Gen. #3 Gen. #4 Gen. #5 Presenter: Daniel Barbersek Power Solutions Manager Generac Power Systems, Inc. RUNNING HEADLINE What Topics Will Be Covered
More informationJ.-J.Simond*, A.Sapin**, B.Kawkabani*, D.Schafer***, M.Tu Xuan*, B.Willy***
EPE97 OPTIMIZED DESIGN OF VARIABLE-SPEED DRIVES BASED ON NUMERICAL SIMULATION J.-J.Simond*, A.Sapin**, B.Kawkabani*, D.Schafer***, M.Tu Xuan*, B.Willy*** *Swiss Federal Institute of Technology, Electrical
More informationS C ELECTRIC EUROPE LTD. Excellence Through Innovation. Harnessing the Wind. November 2011 Descriptive Bulletin E
S C ELECTRIC EUROPE LTD. Excellence Through Innovation Harnessing the Wind November 2011 Descriptive Bulletin 2000-42E Introduction Founded in 1911, S&C Electric Company is a global provider of equipment
More informationTexas A&M Microgrid and Electrical System Study. Cushing Memorial Library & Archives
Texas A&M Microgrid and Electrical System Study Cushing Memorial Library & Archives Introduction of Texas A&M Microgrid Study Purpose Why are we studying the TAMU electrical system? Process How do we want
More informationRenewable Energy Systems 14
Renewable Energy Systems 14 Buchla, Kissell, Floyd Chapter Outline The Electric Power Grid 14 Buchla, Kissell, Floyd 14-1 THREE-PHASE AC 14-2 THREE-PHASE TRANSFORMERS 14-3 GRID OVERVIEW 14-4 SMART GRID
More informationAccidental Islanding of Distribution Systems with Multiple Distributed Generation Units of Various Technologies
CIGRÉ-EPRI Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS Boston, MA, October 20-22, 2013 http : //www.cigre.org Accidental Islanding of Distribution Systems with Multiple Distributed Generation
More informationPES Cook Islands KEMA Grid Study Final Report
Integrating PV Solar and Wind generation with the TAU electric system Te Aponga Uira O Tumu-Te_Varovaro Contents 1. Executive summary... 2 2. Introduction... 5 2.1 Proposed wind turbine sites... 6 2.2
More informationPerformance Analysis of Transmission Line system under Unsymmetrical Faults with UPFC
Int. J. of P. & Life Sci. (Special Issue Engg. Tech.) Performance Analysis of Transmission Line system under Unsymmetrical Faults with UPFC Durgesh Kumar and Sonora ME Scholar Department of Electrical
More informationEE069: Electrical Engineering for Non-Electrical Engineers
EE069: Electrical Engineering for Non-Electrical Engineers EE069 Rev.002 CMCT COURSE OUTLINE Page 1 of 5 Training Description: This course introduces the Basic Principles of Electricity in a simple, easy
More informationFuzzy based STATCOM Controller for Grid connected wind Farms with Fixed Speed Induction Generators
Fuzzy based STATCOM Controller for Grid connected wind Farms with Fixed Speed Induction Generators Abstract: G. Thrisandhya M.Tech Student, (Electrical Power systems), Electrical and Electronics Department,
More informationResearch on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC
Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC Rong Cai, Mats Andersson, Hailian Xie Corporate Research, Power and Control ABB (China) Ltd. Beijing, China rong.cai@cn.abb.com,
More informationINTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY
INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES 10-100 KILOWATTS IN THE STATE OF NEW JERSEY January 1, 2005 Rockland Electric Company 390 West Route 59 Spring Valley,
More informationGrid-Friendly Utility-Scale PV Plants
White Paper Grid-Friendly Utility-Scale PV Plants Mahesh Morjaria & Dmitriy Anichkov, First Solar, Tempe, Arizona, USA 13 August 2013 Table of Contents Introduction.... 3 Power Plant Controller Architecture...
More informationImplementing a Microgrid Using Standard Utility Control Equipment
Implementing a Microgrid Using Standard Utility Control Equipment Tom Fenimore Duke Energy Andy Gould and Larry Wright Schweitzer Engineering Laboratories, Inc. Copyright Duke Energy and SEL 2016 Overview
More informationIEEE T&D FACTS Panel Session Part II (08TD0140) Wednesday, April 23, 2008
IEEE T&D FACTS Panel Session Part II (08TD0140) Wednesday, April 23, 2008 Improving Power System Dynamic Performance in Laredo, TX Prepared by Paul Hassink (AEP) Paul Marken (GE) Rob O Keefe (AEP) Gerardo
More informationSession 10 NERC Interconnection Requirements
GE Energy Session 10 NERC Interconnection Requirements UVIG Short Course 2014 Portland, Oregon Jason MacDowell NERC Standards Recently Adopted NERC GVSDT* standards MOD (Model Validation): MOD-025: Verification
More information15 Nelson-Marlborough Regional Plan
15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant
More informationNew Power Flow Controller for Congestion Management and Reliability Improvement in Transmission and Distribution Systems
New Power Flow Controller for Congestion Management and Reliability Improvement in Transmission and Distribution Systems Alberto Del Rosso EPRI CIGRE US National Committee 204 Grid of the Future Symposium
More informationDate Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS
Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS 1. PURPOSE AND SCOPE OF THIS DOCUMENT... 3 2. DEFINITIONS...
More informationDFIG Wind Turbine Modeling
DFIG Wind Turbine Modeling Team Power Team Drew McKinnon Cody Swisher Tiras Newman Andy Miles Professors: Dr. Herbert Hess Dr. Brian Johnson Dr. Feng Li Sponsor: SEL Dr. Normann Fishcher Student Mentors:
More information100 MW Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility
More informationWESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM
1 1 The Latest in the MIT Future of Studies Recognizing the growing importance of energy issues and MIT s role as an honest broker, MIT faculty have undertaken a series of in-depth multidisciplinary studies.
More informationStandards, Procedures and Policies for Grid Connection
Standards, Procedures and Policies for Grid Connection CONTENTS 1 INTRODUCTION 1 2 EMBEDDED GENERATION 1 2.1.1 OUTLINE OF EMBEDDED GENERATION 1 2.1.2 CHANGES IN EMBEDDED GENERATION 1 2.1.3 ASPECTS OF EMBEDDED
More informationElectric Networks/Ina Lehto Updated Original 12/2011
1 TECHNICAL APPENDIX 2 TO THE GUIDELINES CONNECTING AN ELECTRICITY GENERATION INSTALLATION TO THE DISTRIBUTION NETWORK CONNECTING AN INSTALLATION WITH A NOMINAL RATED CAPACITY OF OVER 100 These instructions
More informationThe 1,400-MW Kii-Channel HVDC System
The 1,4-MW Kii-Channel HVDC System The 1,4-MW Kii-Channel HVDC System 114 Hiroyuki Nakao Masahiro Hirose Takehisa Sakai Naoki Kawamura Hiroaki Miyata Makoto Kadowaki Takahiro Oomori Akihiko Watanabe OVERVIEW:
More informationModeling and Simulation of Battery Energy Storage Systems for Grid Frequency Regulation. X. XU, M. BISHOP, D. OIKARINEN S&C Electric Company USA
, rue d Artois, F-8 PARIS CIGRE US National Committee http : //www.cigre.org Grid of the Future Symposium Modeling and Simulation of Battery Energy Storage Systems for Grid Frequency Regulation X. XU,
More informationWind Power Plants with VSC Based STATCOM in PSCAD/EMTDC Environment
2012 2nd International Conference on Power and Energy Systems (ICPES 2012) IPCSIT vol. 56 (2012) (2012) IACSIT Press, Singapore DOI: 10.7763/IPCSIT.2012.V56.2 Wind Power Plants with VSC Based STATCOM in
More informationPRAGATI ENGINEERING COLLEGE
Report on Industrial Visit to Power Grid 765/400 KV (GIS) Sub-Station No. of days of Visit : Two days Date(s) of Visit : 19 th September, 2017& 7 th October, 2017 Faculty In-charges : 4 Members 1. Mr.S.Ashokreddy,
More informationSECTION 9: ELECTRICAL POWER DISTRIBUTION. ESE 470 Energy Distribution Systems
SECTION 9: ELECTRICAL POWER DISTRIBUTION ESE 470 Energy Distribution Systems 2 Introduction The Electrical Grid 3 Three main components to the electrical grid Generation ESE 450 Transmission Transmission
More informationHVDC Back-to-Back Interconnections Enabling reliable integration of power system
HVDC Back-to-Back Interconnections Enabling reliable integration of power system Dr Liliana Oprea FICHTNER GmbH&Co KG Swiss Chapter of IEEE PES Baden-Dättwil, 4 September 2013 Table of Contents Need for
More informationUkujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances
Ukujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances 29 Juli 2014 Page 1 Characteristics of the Project Parameter Detail
More informationPlanning for a Power Engineering Institute
Session Number 2233 Planning for a Power Engineering Institute Frank W. Pietryga, Gregory M. Dick, Jerry W. Samples University of Pittsburgh at Johnstown Abstract Anecdotal evidence suggests that emphasis
More information