Ukujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances

Size: px
Start display at page:

Download "Ukujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances"

Transcription

1 Ukujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances 29 Juli 2014 Page 1

2 Characteristics of the Project Parameter Detail Generation Site Ukujima Island Source of Energy Photovoltaic Installed Power 430 MW Voltage at Generation Site 0.4 / 33 kv Point of Common Coupling Ainoura Substation Ainoura S/S 220 kv Network Operator at PCC Kyushu Power & El. Length to PCC Voltage at PCC 65.5 km 220 kv 400 MW 65.5 km Ukujima S/S 約 500m 漁業権境界29 Juli 2014 Page 2

3 Challenges: Project Internal Design General Considerations The installed capacity of 400MW is identically to kinds of conventional Power Plants The project s Character of a Power Plant and therefore the meaning for the existing Japanese Transmission System requires the consideration of appropriate technical solutions concerning The use of applications according to the State of the Art The fulfillement of the criteria for the reliability of power supply The knowledge of specifics for the Japanese Transmission system (e. g. JEAC) The application of international experiences for the grid connection of Renewables The electrical phenomena caused by the long submarine cable connection Two Issues are the main Challenge concerning the Planning Process: - A technical-economical Green-Field Structure for the Network at Ukujima - The Identification of the optimal HV power transmission technology! 29 Juli 2014 Page 3

4 Challenges: Project Internal Design Green-Field Network Planning Baseline Design PV Farm 400MW Internal PV-DC network 10Tkm Invertertstations 217 pcs. 434 Inverter 1000kVA each Network 33kV 150km - Radial MV network structure - max 18 Stations per MV-String - max 630 A per String - only Load-break switches Substation 220kV 2 x 250 MVA Submarine Cable 220kV 65km cross section mm² Al General Structure of the internal MV Network 33 kv A B C D 29 Juli 2014 Page 4

5 Challenges: Project Internal Design Power Transmission Technology to Ainoura HVDC vs. HVAC LCC- / CSC-Technology *1 - Use Since early 1950 Not applicable for Ukujiima! - Requires connection of two active power networks at both sides of the link Applicable for Ukujiima! - Use of AC technology for long distances on- and offshore is well approved and experienced VSC-Technology *2 - Use since 1999 Applicable for Ukujiima! - Contrary to LCC, can be applied for linking isolate networks, like remote islands For both technologies practical experiences are available *1 Line Commutated Current-Sorced Converter *2 Voltage Source Commutated 29 Juli 2014 Page 5

6 Challenges: Project Internal Design Int l HV Power Transmission Experiences VSC - HVDC HVAC Other worlwide applications besides Germany / Europe are available for both technologies as well! Conclusion for the UMSP project The power to be transmitted The length of connection 400 MW 65 km Both Technologies - HVAC and HVDC are applicable! 29 Juli 2014 Page 6

7 Challenges: Project Internal Design Optimal HV Power Transmission Technology Advantages HVDC Independent control of Active and Reactive Power Disadvantages More expansive than HVAC Cost Break-even >70km; lower losses will not compensate higher investment costs Space problems for the placement of the landside converter station Extreme long lead time HVAC Most economical solution considering CAPEX + OPEX Expected influences to the existing transmission system 220kV More References Separate System Studies are necessary 29 Juli 2014 Page 7

8 Challenges: Project Internal Design Need and Content of System Studies The Main System Study Issues due to the influence of the existing transmission system by a long distance HVAC cable are: I. Power Quality Analysis Impedance-Frequency-Curve and Harmonics 200 Impedance [Ohm] 150 Z=f(f) with UMSP Displacement of the Resonance due to the long HVAC cable Z=f(f) without UMSP II. Electromagn. Transient Analysis Voltage Drops, Surge Resonances and Harmonics during switching processes Zero-miss currents during normal and disturbed network conditions Frequency [Hz] Effects of the Cable Discharge to the existing equipment (e. g. breakers) Lower Harmonic Resonances during a Fault Current Juli 2014 Page 8

9 Challenges: Project Internal Design Powerful System Analysis Software PowerFactory DIgSILENT, Germany Load Flow analysis and Short-Circuit Analysis (IEC 60909, ANSI C37, IEC 61363, complete method, multiple faults, DC Short-Circuit calculation according to IEC and ANSI/IEEE 946) Optimal Power Flow (OPF): Reactive power optimization and economic dispatch Protection Functions: Time-Overcurrent Protection and Distance Protection; comprehensive relay library with relay models suitable for steady-state, RMS and EMT calculations Voltage stability analysis: PQ and QV curves; P-, Q-, I- and V-measurement models, consideration of load flow constraints, verification of system observability Cable Sizing: Automatic cable sizing and cable reinforcement optimization Basic MV/LV Network Analysis: Feeder Analysis Tool, Radial Feeder Tool, Backbone Calculation Power Quality and Harmonic Analysis Harmonic Load Flow and Filter Analysis: Various harmonic distortion indices, Multiple harmonic injections Flicker Analysis: Flicker Assessment (IEC ), Flicker Meter (IEC ) Impedance-Frequency-Curve: Balanced and unbalanced network model Stability Analysis Functions (RMS): balanced/unbalanced, multi-phase AC networks, DC networks, simulation of any kind of faults or events + Electromagnetic Transients (EMT): FACTS, HVDC interconnections, power electronic devices 29 Juli 2014 Page 9

10 Challenges: Project Internal Design Outcome of the System Studies The Main Outcome of the System Studies is: Definition of measures for a secure and stable operation under undisturbed conditions Fulfilment of the Grid Code requirements acc. to JEAC 9701 Definition of Countermeasures for the specific electrical phenomena due to longdistance submarine cables (e. g. harmonic filters, surge arresters) Definitions for the setting of the Protection Devices Challenges Chances Input System Study Output Constrution Contribution to a Stable Operation of the Transmission System 29 Juli 2014 Page 10

11 Chances: Stability of Transmission Systems Stability Criteria The Operator of the Transmission System (TSO) is responsible for the keep of it s Stability! Power System Stability Frequency Stability Voltage Stability Rotor Angle Stability * Stability of the Actice Power Balance Stability of the Reactice Power Balance Small Signal Stability Large Signal (Transient Stability) Generation U Balanced Reactive Power Area Unbalanced Reactive Power Area TSO System Frequency Demand U min Safe Operation Area CriticalOperation Area Impossible Operation Area ** P max P * Not in Scope ** Source: EirGrid 29 Juli 2014 Page 11

12 Chances: Stability of Transmission Systems Stability Requirements to Generating Units The Main International Requirements to Generating Units including Renewables are: Criterion Description of the Requirement Stability Type Frequency range Normal operation 47.5 Hz f r50hz 51.5 Hz or 57.0 Hz f r60hz 61.8 Hz (Europe 48.5 Hz f r50hz 50.5 Hz) Voltage range Normal operation between 80% U r 120 % (Europe 80% U r 120 %) Frequency Voltage JEAC 9701 Active Power Control Active Power Control within a given Frequency Range Frequency --- Reactive Power Control Possibility to meet a given P-Q-diagram independently to voltage changes (P-Q-diagram in a voltage band) Voltage Fault Ride- Through Stable connection during network faults within a give time-frame; (not in JEAC: injection of a reactive current) Voltage Information exchange Online transfer for the value of active power and possibility for its reduction by the grid operator Frequency Control system Voltage, reactive power or power factor control Voltage 29 Juli 2014 Page 12

13 Chances: Stability of Transmission Systems Stability Requirements to Generating Units Detailed Requirements to Renewables according to JEAC : Active Power Control No specific requirements regarding the control of the active power due to frequency deviations Reactive Power Control Power Factor between 0.9 lag and 0.95 lead (systems point of view) No specific requirements regarding the infeed of a reactive current during 0.9 lag 200 +Q P Max P [MW -P +P lead -Q Q [Mvar] Lagging 0.85 Fault-Ride-Through Not disconnection during a voltage drop down to 20% U r over 0.3 sec Reversion to 80% of U r within 0.1 s after clearence of the external network failure Voltage Level [p. u.] After March 2017 Before March 2017 Achievement of the origin voltage after 1.5 sec Time [s] 29 Juli 2014 Page 13

14 Chances: Stability of Transmission Systems Stability Requirements to Generating Units Ability for Stability Support by the INVERTERS of the UMSP in Comparison to JEAC 9701 Criterion According to JEAC Additional Ability Active Power (AP) Control Reactive Power Control Full Compliance to JEAC Normal Operation in the range 57.0 Hz f r60hz 61.8 Hz Full Compliance to JEAC P Max Reverse Power Flow 0.9 lag P [MW] lead Q [Mvar] 200 Non-Reverse Power Flow lag AP Reduction starting from a Setpoint (e. g. 50.2Hz); The Gradient of the Power Reduction in MW/Hz must be Defined by the TSO P P ref Active Power Setpoint f f n i Droop f f n Fault-Ride- Through -150 Full Compliance to JEAC Injection of a Reactive Current during the external network fault Additional support for the Voltage at the PCC 29 Juli 2014 Page 14

15 Chances: Stability of Transmission Systems Capabilities of the Renewables Assets Summarize: How UMSP is able to meet stability requirements of JEAC? Criterion Description Inverter - Cability according to JEAC 9701 Add. Ability Active Power Control Normal operation 57.0 Hz f r60hz 61.8 Hz AP Variation during Frequency deviations Reactive Power Control Fault-Ride-Through Normal operation between 80% U r 120 % 0.9 lag cosφ 0.9 lead Not Disconnection; Voltage Recovery Reactive Current injection during FRT UMSP is able to meet the Stability requirements by JEAC AND to provide additional services for the keep of the stability! 29 Juli 2014 Page 15

16 Please don t hesitate to ask any questions at any time Contact: Photovolt Development Partners GmbH Kurfuerstendamm 136, D Berlin Joerg Zillmer Peter Gerstmann Principal Consultant Managing Director Phone: Phone: zillmer@pvdp.eu gerstmann@pvpd.eu 29 Juli 2014 Page 16

17 Chances: Stability of Transmission Systems Capabilities of Renewables Assets P / kva f / Hz 29 Juli 2014 Page 17

Experience on Technical Solutions for Grid Integration of Offshore Windfarms

Experience on Technical Solutions for Grid Integration of Offshore Windfarms Experience on Technical Solutions for Grid Integration of Offshore Windfarms Liangzhong Yao Programme Manager AREVA T&D Technology Centre 18 June 2007, DTI Conference Centre, London Agenda The 90MW Barrow

More information

Grid code Compliance and Renewable Energy Projects. Mick Barlow, Business Development Director, S&C Electric, United Kingdom

Grid code Compliance and Renewable Energy Projects. Mick Barlow, Business Development Director, S&C Electric, United Kingdom Grid code Compliance and Renewable Energy Projects Mick Barlow, Business Development Director, S&C Electric, United Kingdom Why Grid Codes? Permit the development of and operation of an efficient and economical

More information

CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM

CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM 106 CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM 5.1 INTRODUCTION Inherent characteristics of renewable energy resources cause technical issues not encountered with conventional thermal,

More information

Introduction CONTENT Future of offshore wind energy in Europe Offshore wind energy in Spain Alternatives to the transmission system to the grid Compar

Introduction CONTENT Future of offshore wind energy in Europe Offshore wind energy in Spain Alternatives to the transmission system to the grid Compar OFFSHORE WIND FARM CONNECTIONS TO THE GRID Energy to Quality S.L. Santiago Arnaltes Gómez Introduction CONTENT Future of offshore wind energy in Europe Offshore wind energy in Spain Alternatives to the

More information

MVDC PLUS Managing the future grid

MVDC PLUS Managing the future grid MVDC PLUS Managing the future grid Bridge the distance How should we connect Islands, platforms, and remote areas? Connecting weak or unstable grids How will we integrate and stabilize grids? Reduce footprint

More information

Renewables from a TSO Perspective. M.BENA, SmartGrids Director, RTE, French TSO Vienna, 18 May 2015

Renewables from a TSO Perspective. M.BENA, SmartGrids Director, RTE, French TSO Vienna, 18 May 2015 Renewables from a TSO Perspective M.BENA, SmartGrids Director, RTE, French TSO Vienna, 18 May 2015 RTE in Europe 8500 employees Owner and Operator of the Assets 100 000 km UHV and HV lines (400 kv -> 63

More information

PES Cook Islands KEMA Grid Study Final Report

PES Cook Islands KEMA Grid Study Final Report Integrating PV Solar and Wind generation with the TAU electric system Te Aponga Uira O Tumu-Te_Varovaro Contents 1. Executive summary... 2 2. Introduction... 5 2.1 Proposed wind turbine sites... 6 2.2

More information

EVENT, DATE. The Smart Grid. Challenges & Solutions. Fahd Hashiesh, Global Business Development Manager, Power Consulting

EVENT, DATE. The Smart Grid. Challenges & Solutions. Fahd Hashiesh, Global Business Development Manager, Power Consulting EVENT, DATE The Smart Grid Challenges & Solutions Fahd Hashiesh, Global Business Development Manager, Power Consulting The Grid The Current, the Past and the Future Let s define the Smart Grid Environment

More information

Designing and Maintaining a Pollution-Resilient Electric Power System. Managing Pollution Issues

Designing and Maintaining a Pollution-Resilient Electric Power System. Managing Pollution Issues Designing and Maintaining a Pollution-Resilient Electric Power System Tom McDermott IEEE/PES T&D Conference April 21-24, 2008 Chicago, IL Managing Pollution Issues Define the metrics, and measure them

More information

Experiences with Wind Power Plants with Low SCR

Experiences with Wind Power Plants with Low SCR 1 Experiences with Wind Power Plants with Low SCR Lessons learned from the analysis, design and connection of wind power plants to weak electrical grids IEEE PES General Meeting Denver CO, 26 March 2015

More information

Krzysztof Rudion. Otto-von-Guericke Universität Magdeburg , Bremerhaven

Krzysztof Rudion. Otto-von-Guericke Universität Magdeburg , Bremerhaven Institut für Elektrische Energiesysteme Optimal Operation of Offshore Grid Krzysztof Rudion Otto-von-Guericke Universität Magdeburg 09.05.2012, Bremerhaven Gefördert auf Grund eines Beschlusses des Deutschen

More information

Chapter 1. Overview of HVDC applications

Chapter 1. Overview of HVDC applications ELEC0445 - High Voltage Direct Current grids Part 1. Line Commutated Converters Chapter 1. Overview of HVDC applications Patricia Rousseaux t.vancutsem@ulg.ac.be Thierry Van Cutsem www.montefiore.ulg.ac.be/~vct

More information

Full-Scale Medium-Voltage Converters for Wind Power Generators up to 7 MVA

Full-Scale Medium-Voltage Converters for Wind Power Generators up to 7 MVA Full-Scale Medium-Voltage Converters for Wind Power Generators up to 7 MVA Philippe Maibach, Alexander Faulstich, Markus Eichler, Stephen Dewar ABB Switzerland Ltd CH-5300 Turgi, Switzerland Phone: +41

More information

Enabling the power of wind. Competence and expertise for wind power customers

Enabling the power of wind. Competence and expertise for wind power customers Enabling the power of wind Competence and expertise for wind power customers This is Rising demand for energy and its impact on the environment are the defining challenges of this century. is tackling

More information

ABB Group August 27, 2010 Slide 1

ABB Group August 27, 2010 Slide 1 Michael Bahrman P.E., ABB Grid Systems, August 31, 2010, Asia Pacific Clean Energy Summit 2010, Honolulu Integration of Variable Renewable Energy for Hawaii Transmission of Isolated Resources August 27,

More information

Integration of Large Wind Farms into Electric Grids

Integration of Large Wind Farms into Electric Grids Integration of Large Wind Farms into Electric Grids Dr Mohammad AlZoubi Introduction Development WHAT IS NEXT!! Over the next 12 years, Europe must build new power capacity equal to half the current total.

More information

ABB Wind Power Solution

ABB Wind Power Solution Feng Li, Wind ISI, CNABB, November, 2016 ABB Wind Power Solution November 13, 2016 Slide 1 ABB deliveries from A to Z into the wind industry Wind power generation, transmission and integration, control

More information

Power Quality innovative SolutionS for industrial and distribution grids.

Power Quality innovative SolutionS for industrial and distribution grids. Power Quality innovative SolutionS for industrial and distribution grids. POWER QUALITY Power Quality - Solutions for grid efficiency improvement, loss reduction and voltage stabilization. 2 Improving

More information

Power Conditioning of Microgrids and Co-Generation Systems

Power Conditioning of Microgrids and Co-Generation Systems Power Conditioning of Microgrids and Co-Generation Systems Nothing protects quite like Piller piller.com Content 1 Introduction 3 2 Basic requirements of a stable isolated network 3 3 Requirements for

More information

Offshore Wind Connections HVDC for Offshore Grids

Offshore Wind Connections HVDC for Offshore Grids Michael Bahrman P.E., Grid Systems, UWIG Technical Workshop, Maui, October 2011 Offshore Wind Connections HVDC for Offshore Grids October 18, 2011 Slide 1 HVDC for Offshore Grids Topics Offshore wind market

More information

POWER TRANSMISSION OF LOW FREQUENCY WIND FIRMS

POWER TRANSMISSION OF LOW FREQUENCY WIND FIRMS Available Online at www.ijcsmc.com International Journal of Computer Science and Mobile Computing A Monthly Journal of Computer Science and Information Technology IJCSMC, Vol. 3, Issue. 10, October 2014,

More information

Battery Energy Storage System addressing the Power Quality Issue in Grid Connected Wind Energy Conversion System 9/15/2017 1

Battery Energy Storage System addressing the Power Quality Issue in Grid Connected Wind Energy Conversion System 9/15/2017 1 Battery Energy Storage System addressing the Power Quality Issue in Grid Connected Wind Energy Conversion System 9/15/2017 1 CONTENTS Introduction Types of WECS PQ problems in grid connected WECS Battery

More information

HVDC. TMT&D provides the best and most economical HVDC system.

HVDC. TMT&D provides the best and most economical HVDC system. HVDC TMT&D HVDC TMT&D provides the best and most economical HVDC system. In 1955, TMT&D started the development of HVDC and is the leading HVDC supplier in Japan. TMT&D has continued to develop HVDC technology

More information

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 1 Reactive Power Compensation for Solar Power Plants Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 2 Objectives Refresh the basics of reactive power from a generator s perspective Regulatory

More information

RESEARCH PROJECT VERBUNDNETZSTABIL

RESEARCH PROJECT VERBUNDNETZSTABIL RESEARCH PROJECT VERBUNDNETZSTABIL Grid control for inverter dominated power systems Soenke Rogalla Fraunhofer Institute for Solar Energy Systems ISE IRED Side Event Workshop Vienna, 17.10.2018 www.ise.fraunhofer.de

More information

Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC

Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC IJSTE - International Journal of Science Technology & Engineering Volume 2 Issue 01 July 2015 ISSN (online): 2349-784X Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC Ravindra Mohana

More information

ABB FACTS Grid connection of Wind Farms

ABB FACTS Grid connection of Wind Farms Christian PAYERL ABB FACTS Grid connection of Wind Farms May 28, 2010 Slide 1 ABB Power of Wind May 28, 2010 Slide 2 ABB FACTS 300 engineers, highly skilled in the following disciplines: Development Marketing

More information

Solar Power Switchgear & Energy Storage Renewable Energy Systems

Solar Power Switchgear & Energy Storage Renewable Energy Systems 7 Solar Power Switchgear & Energy Storage Renewable Energy Systems - Solution Brochure www.apt-power.com 433 N. 36 th Street PROVIDING A COMPREHENSIVE Lafayette, IN 47905 www.apt-power.com 433 APPROACH

More information

GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS

GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS Prof. Suryanarayana Doolla Department of Energy Science and Engineering Indian Institute of Technology Bombay OUTLINE Intoduction Grid

More information

Optimal and Modular Configuration of Wind Integrated Hybrid Power Plants for Off-Grid Systems

Optimal and Modular Configuration of Wind Integrated Hybrid Power Plants for Off-Grid Systems Optimal and Modular Configuration of Wind Integrated Hybrid Power Plants for Off-Grid Systems Lennart Petersen, Industrial Ph.D. Fellow Hybrid Solutions Co-Authors: F. Iov (Aalborg University), G. C. Tarnowski,

More information

Essential Reliability Services From PV Plants

Essential Reliability Services From PV Plants Essential Reliability Services From PV Plants Mahesh Morjaria, Ph. D. VP, PV Systems Enabling a world powered by reliable, affordable solar electricity. Utility-Scale PV Plants Support Grid Stability &

More information

HVDC Technology. Phil Sheppard Head of Network Strategy

HVDC Technology. Phil Sheppard Head of Network Strategy HVDC Technology Phil Sheppard Head of Network Strategy Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight

More information

Targeted Application of STATCOM Technology in the Distribution Zone

Targeted Application of STATCOM Technology in the Distribution Zone Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric

More information

Certificate of Conformity self-generation unit

Certificate of Conformity self-generation unit Seite 1 von 7 Certificate of Conformity self-generation unit Manufacturer / applicant: Type of power generation unit: SMA Solar Technology AG Sonnenallee 1 34266 Niestetal Germany Grid-tied photovoltaic

More information

High Voltage Direct Current and Alternating Current Transmission Systems Conference. August Nari Hingorani

High Voltage Direct Current and Alternating Current Transmission Systems Conference. August Nari Hingorani High Voltage Direct Current and Alternating Current Transmission Systems Conference at EPRI Palo Alto CA August 30 31 2011 Scope of VSC Based Technology in HVDC and FACTS Nari Hingorani HVDC and FACTS:

More information

PV Grid Integration Research in the U.S.

PV Grid Integration Research in the U.S. PV Grid Integration Research in the U.S. Barry Mather Ph.D. NREL- Power Systems Engineering Center HEPIA IEA PVPS Task 14 Utility Workshop Geneva, Switzerland March 31 st, 2014 NREL is a national laboratory

More information

Certificate of Conformity self-generation unit

Certificate of Conformity self-generation unit Seite 1 von 7 Certificate of Conformity self-generation unit Manufacturer / applicant: Type of power generation unit: SMA Solar Technology AG Sonnenallee 1 34266 Niestetal Germany Grid-tied photovoltaic

More information

Certificate of Conformity self-generation unit

Certificate of Conformity self-generation unit Seite 1 von 7 Certificate of Conformity self-generation unit Manufacturer / applicant: Type of power generation unit: SMA Solar Technology AG Sonnenallee 1 34266 Niestetal Germany Grid-tied photovoltaic

More information

An Integrated Grid Path for Solar. Thomas Key, EPRI Senior Technical Executive. ISES Webinar. April 22, 2016

An Integrated Grid Path for Solar. Thomas Key, EPRI Senior Technical Executive. ISES Webinar. April 22, 2016 An Integrated Grid Path for Solar Thomas Key, EPRI Senior Technical Executive ISES Webinar April 22, 2016 Changing Landscape: An Integrated Grid is a Better Grid Combined Heat & Power Demand Response Energy

More information

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management Southern Company Interconnection Process Dexter Lewis Research Engineer Research and Technology Management Southern Company Outline Southern Company GPC Solar Interconnection Process Application requirements

More information

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 61 CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM 3.1 INTRODUCTION The modeling of the real time system with STATCOM using MiPower simulation software is presented in this

More information

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION Presentation by Engr. O. C. Akamnnonu Chief Executive Officer, Ikeja Electricity Distribution Company AGENDA WORK THROUGH

More information

Challenges and opportunities in the integration of PV in the electricity distribution networks

Challenges and opportunities in the integration of PV in the electricity distribution networks REPOWERING EUROPE Photovoltaics: centre-stage in the power system Challenges and opportunities in the integration of PV in the electricity distribution networks Nikos Hatziargyriou, HEDNO, BoD Chairman

More information

ABB November 16, 2016 Slide 1

ABB November 16, 2016 Slide 1 Xuemei Wang, Power Quality Center, Xi an ABB Capacitor Company Ltd, November, 2016 ABB Power World 2016 Power Quality Solution in Distribution Net Work ABB November 16, 2016 Slide 1 Power Quality Basic

More information

Renewable Energy Grid Integration and Distributed Generation Specialization Syllabus

Renewable Energy Grid Integration and Distributed Generation Specialization Syllabus Renewable Energy Grid Integration and Distributed Generation Specialization Syllabus Contents: 1. DISTRIBUTED GENERATION 2. GENERATION AND STORING TECHNOLOGIES 3. CONTROL TECHNIQUES AND RENEWABLE ENERGY

More information

S C ELECTRIC EUROPE LTD. Excellence Through Innovation. Harnessing the Wind. November 2011 Descriptive Bulletin E

S C ELECTRIC EUROPE LTD. Excellence Through Innovation. Harnessing the Wind. November 2011 Descriptive Bulletin E S C ELECTRIC EUROPE LTD. Excellence Through Innovation Harnessing the Wind November 2011 Descriptive Bulletin 2000-42E Introduction Founded in 1911, S&C Electric Company is a global provider of equipment

More information

Guidelines for connection of generators:

Guidelines for connection of generators: Guidelines for connection of generators: Greater than 30 kva, and not greater than 10 MW, to the Western Power distribution network January, 2017. EDM 32419002 / DM 13529244 Page 1 of 14 Contents 1 INTRODUCTION...

More information

ANCILLARY SERVICES WITH VRE (VARIABLE RENEWABLE ENERGY): FOCUS PV

ANCILLARY SERVICES WITH VRE (VARIABLE RENEWABLE ENERGY): FOCUS PV ANCILLARY SERVICES WITH VRE (VARIABLE RENEWABLE ENERGY): FOCUS PV September 2017 1st International Conference on Large-Scale Grid Integration of Renewable Energy in India Andreas Falk, Ancillary services

More information

Regulating life s ups and downs

Regulating life s ups and downs Regulating life s ups and downs Increasing grid capacity to connect renewable energies MARTIN CARLEN, ADAM SLUPINSKI, FRANK CORNELIUS José González sang, I see problems down the line, I know that I m right,

More information

Dr.-Ing. Ervin Spahi, Wadden Sea Forum, Bremerhaven Electric grid on and off-shore: current status, obstacles and new developments

Dr.-Ing. Ervin Spahi, Wadden Sea Forum, Bremerhaven Electric grid on and off-shore: current status, obstacles and new developments Dr.-Ing. Ervin Spahi, Wadden Sea Forum, Bremerhaven 26.11.09 Electric grid on and off-shore: current status, obstacles and new developments November 26, 2009 Slide 1 Transmission grid The challenges Optimal

More information

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba

More information

Medium Voltage. Power Factor Correction Reactive Compensation Harmonic Filters. Electrical Power Quality Management at its best.

Medium Voltage. Power Factor Correction Reactive Compensation Harmonic Filters. Electrical Power Quality Management at its best. Medium Voltage Power Factor Correction Reactive Compensation Harmonic Filters POWER QUALITY Electrical Power Quality Management at its best. From electricity generation, transmission, thru its distribution

More information

POWER QUALITY SOLUTIONS FOR INDUSTRIAL AND DISTRIBUTION GRIDS. W WW.R EINHAU S EN.COM

POWER QUALITY SOLUTIONS FOR INDUSTRIAL AND DISTRIBUTION GRIDS. W WW.R EINHAU S EN.COM POWER QUALITY SOLUTIONS FOR INDUSTRIAL AND DISTRIBUTION GRIDS. W WW.R EINHAU S EN.COM POWER QUALITY POWER QUALITY - SOLUTIONS FOR GRID EFFICIENCY IMPROVEMENT, LOSS REDUCTION AND VOLTAGE STABILIZATION.

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM 1 1 The Latest in the MIT Future of Studies Recognizing the growing importance of energy issues and MIT s role as an honest broker, MIT faculty have undertaken a series of in-depth multidisciplinary studies.

More information

Getting Smart Evolution to the Smart Grid April 2008

Getting Smart Evolution to the Smart Grid April 2008 Getting Smart Evolution to the Smart Grid April 2008 Thomas F Garrity Vice President, Sales and Business Development Siemens Power T&D, Inc. Electrical energy is the backbone of our society Page 2 Mar-07

More information

Development and Operational Advantages of a Solid State Circuit Breaker with Current Limiting

Development and Operational Advantages of a Solid State Circuit Breaker with Current Limiting Development and Operational Advantages of a Solid State Circuit Breaker with Current Limiting Breaker Technology Operational Advantages Development Schedule Dave Richardson, Ph.D.,P.E. Powell Power Electronic

More information

Impact of Islanding and Resynchroniza?on on Distribu?on Systems

Impact of Islanding and Resynchroniza?on on Distribu?on Systems 1 Impact of Islanding and Resynchroniza?on on Distribu?on Systems Authors: Dr. Vijay Sood Damanjot Singh Kush Duggal 2 Contents Introduction System Description Rural Radial Distribution System Urban Meshed

More information

Regenerative Utility Simulator for Grid-Tied Inverters

Regenerative Utility Simulator for Grid-Tied Inverters Regenerative Utility Simulator for Grid-Tied Inverters AMETEK s RS & MX Series with the SNK Option provides the solution Testing of grid-tied inverters used in solar energy systems is emerging as a major

More information

(by authors Jouko Niiranen, Slavomir Seman, Jari-Pekka Matsinen, Reijo Virtanen, and Antti Vilhunen)

(by authors Jouko Niiranen, Slavomir Seman, Jari-Pekka Matsinen, Reijo Virtanen, and Antti Vilhunen) Technical Paper: Low voltage ride-through testing of wind turbine converters at ABB helps wind turbines meet the requirements of IEC 61400-21 more quickly (by authors Jouko Niiranen, Slavomir Seman, Jari-Pekka

More information

Dynamic Reactive Power Control for Wind Power Plants

Dynamic Reactive Power Control for Wind Power Plants Dynamic Reactive Power Control for Wind Power Plants Ernst Camm, Charles Edwards, Ken Mattern, Stephen Williams S&C Electric Company, 6601 N. Ridge Blvd, Chicago IL 60626 USA ecamm@sandc.com, cedwards@sandc.om,

More information

Cabo Verde s new Renewable-Energy-Friendly Grid Code

Cabo Verde s new Renewable-Energy-Friendly Grid Code Cabo Verde s new Renewable-Energy-Friendly Grid Code Bernd Weise DIgSILENT GmbH International Workshop on Renewable Energy Development in Macaronesia and West Africa Praia, Cabo Verde, May 30-31, 2016

More information

INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT

INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT Prof. Chandrashekhar Sakode 1, Vicky R. Khode 2, Harshal R. Malokar 3, Sanket S. Hate 4, Vinay H. Nasre 5, Ashish

More information

The Circuit and Control Technology in the Power Conditioner and Converter for Wind Turbine Systems

The Circuit and Control Technology in the Power Conditioner and Converter for Wind Turbine Systems The Circuit and Control Technology in the Power Conditioner and Converter for Wind Turbine Systems UMEZAWA Kazuyoshi UEHARA Fukashi YAMADA Toshiya ABSTRACT Because the generating power of wind turbines

More information

ECE 421 Project 1, Group 3 HVDC. Brian Beilstein, Robert Germick, James Haney, Alexander Joss, Matt Murphy, Shutang You

ECE 421 Project 1, Group 3 HVDC. Brian Beilstein, Robert Germick, James Haney, Alexander Joss, Matt Murphy, Shutang You ECE 421 Project 1, Group 3 HVDC Brian Beilstein, Robert Germick, James Haney, Alexander Joss, Matt Murphy, Shutang You History and Basic Theory First HVDC link in Sweden Mercury Arc Rectifiers Silicon

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Life Needs Power, Hannover Messe 2017 Inertia in Future Electrical Power Systems Challenges and Solutions Dr. Ervin Spahic

Life Needs Power, Hannover Messe 2017 Inertia in Future Electrical Power Systems Challenges and Solutions Dr. Ervin Spahic Life Needs Power, Hannover Messe 2017 Inertia in Future Electrical Power Systems Challenges and Solutions Dr. Ervin Spahic siemens.com/energy-management Motivation Challenge of reduced synchronous generators

More information

PSO project EaseWind Enhanced ancillary services from Wind Power Plants. Anca D. Hansen DTU Wind Energy

PSO project EaseWind Enhanced ancillary services from Wind Power Plants. Anca D. Hansen DTU Wind Energy PSO project EaseWind Enhanced ancillary services from Wind Power Plants Anca D. Hansen DTU Wind Energy Background PSO project EaseWind (2011-2014) Enhanced Ancillary Services from Wind Power Plants Partners:

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Agility in energy Ahead of the challenge, ahead of the change

Agility in energy Ahead of the challenge, ahead of the change European Utility Week Vienna, November 3-5, 2015 Agility in energy Ahead of the challenge, ahead of the change Go-ahead application for existing distribution grids combines availability and efficiency

More information

Grid Stability Analysis for High Penetration Solar Photovoltaics

Grid Stability Analysis for High Penetration Solar Photovoltaics Grid Stability Analysis for High Penetration Solar Photovoltaics Ajit Kumar K Asst. Manager Solar Business Unit Larsen & Toubro Construction, Chennai Co Authors Dr. M. P. Selvan Asst. Professor Department

More information

ABB in Wind &Integration of renewables

ABB in Wind &Integration of renewables TEIJO KÄRNÄ, RM/ DEC 20 2017 ABB in Wind &Integration of renewables Making renewable energy real Wind Landscape Generation-Transmission-Distribution-Control January 12, 2018 Slide 2 Challenges of renewable

More information

Session 10 NERC Interconnection Requirements

Session 10 NERC Interconnection Requirements GE Energy Session 10 NERC Interconnection Requirements UVIG Short Course 2014 Portland, Oregon Jason MacDowell NERC Standards Recently Adopted NERC GVSDT* standards MOD (Model Validation): MOD-025: Verification

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Surabaya Seminar Ferdinand Sibarani, Surabaya, 30 th October Power Quality

Surabaya Seminar Ferdinand Sibarani, Surabaya, 30 th October Power Quality Surabaya Seminar 2014 Ferdinand Sibarani, Surabaya, 30 th October 2014 Power Quality Content 1. Power quality problems 2. ABB s low voltage (LV) solution PCS100 AVC (Active Voltage Conditioner) PCS100

More information

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT

More information

We are IntechOpen, the world s leading publisher of Open Access books Built by scientists, for scientists. International authors and editors

We are IntechOpen, the world s leading publisher of Open Access books Built by scientists, for scientists. International authors and editors We are IntechOpen, the world s leading publisher of Open Access books Built by scientists, for scientists 3,900 116,000 120M Open access books available International authors and editors Downloads Our

More information

Synchronous condenser solutions siemens.com/energy/facts

Synchronous condenser solutions siemens.com/energy/facts The stable way Synchronous condenser solutions siemens.com/energy/facts Bringing grids in line with new requirements bitte PSD-Datei von der Retusche liefern, da hier Tonwertabrisse 2 Global climate change

More information

4-Day Power System Analysis, Coordination, System Studies

4-Day Power System Analysis, Coordination, System Studies 4-Day Power System Analysis, Coordination, System Studies Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq Our

More information

HVDC Back-to-Back Interconnections Enabling reliable integration of power system

HVDC Back-to-Back Interconnections Enabling reliable integration of power system HVDC Back-to-Back Interconnections Enabling reliable integration of power system Dr Liliana Oprea FICHTNER GmbH&Co KG Swiss Chapter of IEEE PES Baden-Dättwil, 4 September 2013 Table of Contents Need for

More information

Grid Code Testing of Wind Turbines by VSC-based Test Equipment

Grid Code Testing of Wind Turbines by VSC-based Test Equipment Grid Code Testing of Wind Turbines by VSC-based Test Equipment Nicolás Espinoza, PhD Student nicolas.espinoza@chalmers.se CHALMERS VÄRLDENS UNIVERSITY SKILLNAD OF TECHNOLOGY Gothenburg, Sweden. 1 of 32

More information

ROBERTO BERNACCHI, GLOBAL PRODUCT MANAGER, 16 JUNE 2018 New power infrastructure concept for greener container terminals Creating Stronger, Smarter

ROBERTO BERNACCHI, GLOBAL PRODUCT MANAGER, 16 JUNE 2018 New power infrastructure concept for greener container terminals Creating Stronger, Smarter ROBERTO BERNACCHI, GLOBAL PRODUCT MANAGER, 16 JUNE 2018 New power infrastructure concept for greener container terminals Creating Stronger, Smarter and Greener port grids 1 greener Stronger, smarter and

More information

List of exemptions from compliance with the Technical Rules granted by Western Power after 1 July 2007

List of exemptions from compliance with the Technical Rules granted by Western Power after 1 July 2007 to: details Version: 2007 Technical Rules 1 16-Jan-08 2 16-Jan-08 3 29-Jan-08 Neerabup (two generating units - Units G11 and G12) Neerabup (two generating units - Units G11 and G12) Bluewaters Power Station

More information

Distributed Energy Resources

Distributed Energy Resources Distributed Energy Resources WECC Data Subcommittee Rich Hydzik, Avista (ERSWG/DER Subgroup Lead) June 29, 2018 Why Are We Concerned About DER? Concern about changing generation fleet Large coal fired

More information

POWER QUALITY SEMINAR OF IRAN, 2 ND MARCH 2017 Power Quality Seminar. Abel-Zhang,Power Quality Center Manager

POWER QUALITY SEMINAR OF IRAN, 2 ND MARCH 2017 Power Quality Seminar. Abel-Zhang,Power Quality Center Manager POWER QUALITY SEMINAR OF IRAN, 2 ND MARCH 2017 Power Quality Seminar Abel-Zhang,Power Quality Center Manager Contents Capacitor Unit Capacitor Shunt Bank Type Solution of Filter March 7, 2017 Slide 2 Contents

More information

High speed, closed loop frequency control using PMU measurements for power grids

High speed, closed loop frequency control using PMU measurements for power grids PXiSE Energy Solutions, LLC High speed, closed loop frequency control using PMU measurements for power grids By: Chuck Wells and Raymond de Callafon Date: September 27, 2017 PXiSE Energy Solutions, LLC

More information

SYSTEM INTEGRATION. Railway and urban transport electrification Energy-efficient and reliable solutions

SYSTEM INTEGRATION. Railway and urban transport electrification Energy-efficient and reliable solutions SYSTEM INTEGRATION Railway and urban transport electrification Energy-efficient and reliable solutions 2 R A I LWAY & U R B A N T R A N S P O R T E L E C T R I F I C AT I O N S O L U T I O N S ABB s substation

More information

Small Electrical Systems (Microgrids)

Small Electrical Systems (Microgrids) ELG4126: Microgrids Small Electrical Systems (Microgrids) A microgrid is a localized, scalable, and sustainable power grid consisting of an aggregation of electrical and thermal loads and corresponding

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Lösungen zur Spannungsregelung in Verteilernetzen

Lösungen zur Spannungsregelung in Verteilernetzen Lösungen zur Spannungsregelung in Verteilernetzen Dr.-Ing. Andreas Averberg 15th LEIBNIZ CONFERENCE OF ADVANCED SCIENCE 02 03 Mai 2013 Berlin, Germany Agenda Traditional and future structure of the distribution

More information

India Smart Grid Week, 2017

India Smart Grid Week, 2017 India Smart Grid Week, 2017 N. Venu President and Head, Power Grids Division, South Asia, Middle East and Africa ABB 1 Big Shift in Power: Shaping the System of the Future Several global challenges Population

More information

Certificate of Conformity self-generation unit

Certificate of Conformity self-generation unit Seite 1 von 7 Certificate of Conformity self-generation unit Manufacturer / applicant: SMA Solar Technology AG Sonnenallee1 34266 Niestetal Germany Type of power generation unit: Active power (nominal

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE Yunqi WANG, B.T. PHUNG, Jayashri RAVISHANKAR School of Electrical Engineering and Telecommunications The

More information

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC Rong Cai, Mats Andersson, Hailian Xie Corporate Research, Power and Control ABB (China) Ltd. Beijing, China rong.cai@cn.abb.com,

More information

Robust Control Technique for Grid-connected Power Conditioner

Robust Control Technique for Grid-connected Power Conditioner Hitachi Review Vol. 63 (2014), No. 8 483 Featured Articles Robust Control Technique for Grid-connected Power Conditioner Hikaru Meguro Kazuya Tsutsumi Masaya Ichinose Tomomichi Ito Akira Kikuchi OVERVIEW:

More information

Abstract. Benefits and challenges of a grid coupled wound rotor synchronous generator in a wind turbine application

Abstract. Benefits and challenges of a grid coupled wound rotor synchronous generator in a wind turbine application Issue #WP102: Technical Information from Cummins Generator Technologies Benefits and challenges of a grid coupled wound rotor synchronous generator in a wind turbine application White Paper Ram Pillai

More information

Testing procedure for the evaluation of grid compliance of power generating units according to the requirements of the Indian Grid Code

Testing procedure for the evaluation of grid compliance of power generating units according to the requirements of the Indian Grid Code Testing procedure for the evaluation of grid compliance of power generating units according to the requirements of the Indian Grid Code Nivedh BS Wind Products & Certification UL India Private Ltd Bangalore,

More information

C PER. Center for Advanced Power Engineering Research C PER

C PER. Center for Advanced Power Engineering Research C PER Center for Advanced Power Engineering Research C PER 2017 Summer Research Planning Workshop Energy Storage Technologies and Application Roadmap Presented By: Johan Enslin Zucker Family Graduate Education

More information

HVDC with Voltage Source Converters A Desirable Solution for Connecting Renewable Energies

HVDC with Voltage Source Converters A Desirable Solution for Connecting Renewable Energies HVDC with Voltage Source Converters A Desirable Solution for Connecting Renewable Energies Ying Jiang-Häfner Rolf Ottersten Abstract When connecting a wind park (WP) to the main grid (MG) by way of an

More information