Truck Priority Evaluation

Size: px
Start display at page:

Download "Truck Priority Evaluation"

Transcription

1 Truck Priority Evaluation Minnesota Department of Transportation MnDOT Contract No W02 SEH No. MNTMD January 26, 2012

2 Truck Priority Evaluation Minnesota Department of Transportation MnDOT Contract No W02 SEH No. MNTMD January 26, 2012 I hereby certify that this report was prepared by me or under my direct supervision, and that I am a duly Licensed Professional Engineer under the laws of the State of Minnesota. Roger A. Plum, PE Date: January 17, 2012 Lic. No.: Reviewed by: January 17, 2012 Date Short Elliott Hendrickson Inc Vadnais Center Drive St. Paul, MN

3 Table of Contents Letter of Transmittal Certification Page Table of Contents Page 1.0 Overview Site selection System Design and Installation Controller setting modifications Truck detection validation Data collection September Results from September Data Collection Additional Data Collection November Results from Additional Data Collection (November) Potential Benefit Annual Benefits Conclusions and Recommendations List of Tables Table 1 Measures of Effectiveness and Auxiliary Related Data (September 27-29, 2011)... 9 Table 2 Measures of Effectiveness and Auxiliary Related Data (November 16-17, 2011).. 13 Table 3 Evaluation of Quantities of Trucks Receiving Benefits from Priority List of Figures Figure 1 TH 24 & County Road 8, Sherburne County... 3 Figure 2 Vehicles Detected as Trucks... 5 Figure 3 Vehicles Not Detected as Trucks... 6 SEH is a registered trademark of Short Elliott Hendrickson Inc. Page i

4 January 2012 Truck Priority Evaluation Prepared for the Minnesota Department of Transportation 1.0 Overview The purpose of this project is to evaluate the potential benefits and the actual effectiveness of implementing a detection system which would provide priority for heavy commercial vehicles at signalized intersections where these vehicles represent a significant percentage of overall traffic. The truck detection system consists of a pair of conventional 6 x6 loops located upstream of the existing normal extension detectors on each approach. The two detectors in the truck detector pair are separated by 24 feet. Using the logic processor capabilities of the traffic signal controller (Econolite ASC/3), a pseudo-detector on each approach was created which is active only when both of the truck detector loops in the pair are occupied. Because of the spacing of the pair of loops, this should only occur when a long vehicle (longer than approximately 24 feet) is passing over the detectors. Under free-flow conditions, this pair of detectors could be concurrently occupied by two vehicles only if the second vehicle is following very closely to the point of being extremely unsafe. (At 55 miles per hour, the headway between these two vehicles would need to be less than ½ second.) The pseudo-detector was then assigned to the appropriate phase to allow for extension of the green indication on the approach, providing an extra extension of the green for trucks to reach the previously-existing extension detector. The theory behind providing this extra extension is to reduce the number of trucks which have to stop. Due to their relatively low acceleration characteristics, trucks which stop (and any vehicles which may be queued behind them) experience more delay than passenger vehicles. 2.0 Site selection At the project kick-off meeting on April 25, 2011, between Short Elliott Hendrickson Inc. (SEH )and the Minnesota Department of Transportation (MnDOT), the following desired characteristics were identified for potential sites: Signalized Single-lane approaches a truck priority detection project had been conducted several years earlier by MnDOT on USH 169 in Belle Plaine. At that intersection, the benefits of truck priority were not fully realized due to the fact that both mainline approaches contained two through lanes. Consequently, passenger vehicles queued behind a stopped truck generally were able to pass the truck and minimize their delay once the queues began to dissipate. Therefore, the primary benefactors of the system were the commercial vehicles. With single-lane approaches, it was expected that commercial vehicles would benefit and passenger vehicles would benefit due to not being caught behind slowly accelerating trucks as often. Page 1

5 Truck traffic should be percent of overall traffic Intersection should not be close to another signalized intersection (to avoid the impacts of traffic platoons on the results) No advance warning flasher (AWF) system though not identified as a fatal flaw, the AWF would mask the effects of truck priority due to its own green extension characteristics Consideration of seasonal harvest traffic (not necessarily required) Prior to that meeting MnDOT had already prepared a preliminary list of six candidate intersections. Based on the above desired attributes all of the MnDOT districts were contacted, and an additional three candidate intersections were identified. Following is the list of candidate intersections. TH 5 & County Road 14, Washington County USH 12 & TH 15, Meeker County USH 12 & County Road 139, Wright County USH 14 & USH 71, Redwood County TH 55 & County Road 19, Hennepin County USH 71 & TH 7, Kandiyohi County USH 2 & CSAH 13, St. Louis County USH 14 & County Road 11, Olmsted County TH 24 & County Road 8, Sherburne County The majority of the above locations were eliminated after a more in-depth review of their traffic characteristics. The intersections in Washington County, Meeker County, Wright County, Hennepin County, and Olmstead County were found to have heavy commercial vehicles comprising less than 10 percent of the total traffic. Of the four remaining intersections, TH 24 & County Road 8 in Sherburne County was determined to be a better candidate than the rest because of its high number of commercial vehicles (over 1800 per day) relative to the other three, none of which had daily truck traffic greater than 700 per day. The Wright County intersection, with 1240 commercial vehicles per day (but only 8.8 percent of overall traffic) was the only other intersection with more than 1000 commercial vehicles per day. Figure 1 is an aerial depiction of the selected intersection, with northbound TH 24 traffic traveling from the lower left to the upper right of the figure. Page 2

6 Figure 1 TH 24 & County Road 8, Sherburne County 3.0 System Design and Installation Following selection of the TH 24 & County Road 8 intersection as the test site on May 25, MnDOT developed a design and prepared construction plans and specifications based on the previously-developed MnDOT truck priority system design and guidelines developed. Following the state government shutdown, final plans and specs were released by MnDOT on August 9. Design Electric was selected and approved as the electrical contractor for the project on August 23. Notice to proceed occurred on August 30. Construction occurred and was essentially completed on September 9. A new controller (Econolite ASC/3) was installed by MnDOT, replacing the ASC/2 controller and allowing the use of logic processing to manage the truck detectors and gather other data automatically. MnDOT completed their detector connections in the cabinet and programming of the controller by September Controller setting modifications SEH made modifications to the controller settings entered by MnDOT for only two reasons: to activate or de-activate the truck priority operation, and to allow the controller to automatically collect additional data of interest for this project. No timings were altered by SEH. In the controller cabinet MnDOT wired the new loop detectors as detectors 17 and 18 for northbound traffic and detectors 19 and 20 for southbound traffic. Page 3

7 Using the logic processor capabilities of the ASC/3 controller, SEH created pseudo-detectors, the data from which can be obtained from the controller as volume and occupancy information in the same manner as conventional detector data. SEH created the following pseudo-detectors in the controller: Detector 25 was used as the northbound truck detector and was active only when detectors 17 and 18 were active simultaneously. Detector 27 was used as the southbound truck detector and was active only when detectors 19 and 20 were active simultaneously. Detector 26 was set up to be active when the northbound truck detector (#25) was active and that detector would have provided a green extension to phase 2, the phase serving the northbound through movement. In other words, this detector was active when a truck was detected and the truck would have received the benefit of the green extension. Detector 28 was set up in a similar fashion for the southbound direction, being active when a truck was detected and that truck would have received the benefit of the green extension. Detectors (northbound) and detectors (southbound) were set up to identify the frequency of conditions when the truck detector was activated but no benefit could be provided. The conditions under which no benefit would be provided to the truck are: The truck is detected when the through phase in that direction is not green, or The truck is detected during the first portion of the minimum green time, and the remaining minimum green time would have allowed the truck to reach the previously-existing extension loop, or The truck is detected after the minimum green time for the through phase has expired, but there is no call for a conflicting phase, in which case the signal indication would have remained green anyway. Detector 45 was set up to record activations of detector 10 (EB detector 475 upstream of the stop line) when the eastbound phase (4) is not green, i.e. arrivals during yellow or red. Detector 46 was set up to record activations of the detector 4 (EB stop line detection) when phase 4 is not green. The occupancy from this detector can be used as a measure of how long eastbound vehicles are waiting for service at the intersection. Detectors 47 and 48 were set up for the westbound direction to accomplish the same tasks as detectors 45 and 46 provided for the eastbound direction. Detectors 51, 52, 54, 55, 56 and 58 were set up to monitor when each of the signal phases (1, 2, 4, 5, 6, and 8, respectively) were active. 5.0 Truck detection validation Prior to starting data collection, the ability of the system to detect trucks needed to be confirmed. As expected, because the detection is based on a certain length of vehicle, not all vehicles detected as trucks were actually heavy commercial vehicles, and not all commercial vehicles were detected as trucks. Pickup (or larger) trucks towing trailers were frequently detected as trucks. This fact is not believed to be a negative consequence of the method used to detect trucks. In many of these cases, these vehicles towing trailers also exhibited low acceleration rates, perhaps not as low as tractor-trailer, but low enough to have a negative impact on following traffic to the point where extending the green for them could be beneficial to them and traffic following them. Page 4

8 Below are photographs of vehicles detected as trucks (Figure 2) and not detected as trucks (Figure 3). With the exception of the tractor-trailer in the upper left photograph, an attempt has been made to show the smallest vehicles detected as trucks and the largest vehicles not detected as trucks. It should be emphasized that during the validation process there were no cases in which a tractor-trailer failed to be detected as a truck. Figure 2 Vehicles Detected as Trucks Page 5

9 Figure 3 Vehicles Not Detected as Trucks 6.0 Data collection September Stop and delay data collection initially was conducted Tuesday through Thursday, September Data collected on September 27 and 28 represent the before condition, with the truck detectors not assigned to any phases and, therefore, not extending green indications. Just prior to data collection on September 29, the truck detectors were assigned to the phases serving the northbound and southbound through traffic on TH 24. Stop and travel time data on each approach were collected manually using Jamar electronic data collection boards. Data was collected for the before (truck detectors deactivated) and after (truck detectors activated) conditions during the two hours identified as the morning and afternoon peak hours (7:15-8:15 and 16:00-17:00) and during two additional non-peak hours (11:30-12:30 and 13:30-14:30) identified through volume data as being non-peak hours with the highest level of truck traffic. Data collected on the Jamar boards was done in an unconventional fashion. The conventional method of using the Jamar boards is to press one of two buttons once for each vehicle to record that vehicle as either a stopped vehicle or a through (i.e., did not stop) vehicle, and also every 15 seconds enter a number into the board representing the number of vehicles queued on the approach upstream of the signal. However, the data needs for this project were to record separate values for trucks (or vehicles detected as trucks) and for non-trucks, and it was desired to record vehicles total time approaching and departing the traffic signal. Consequently, the conventional detectors and the pseudo-detectors described in the Controller setting modifications section were used to count the numbers of total vehicles and trucks on each approach the difference of which would yield the number of non-trucks and the Jamar boards were used to record, for each travel direction, the numbers of both Page 6

10 trucks and non-trucks which stopped, as well as the number of all vehicles within the data collection zone at the end of each 15-second interval. Trucks within the data collection zone were recorded simultaneously, on a portable computer. Also recorded on the portable computer were the locations of the trucks in the queue at the start of the green interval for the through movement. Of specific interest was the number of times the front vehicle in the queue is a truck, which means all of the traffic behind it will be slowed due to the slow acceleration of the truck leading the platoon. The data collection zone consisted of a segment of the roadway approximately 1600 feet long, extending from a point on TH feet south of the center of the intersection to a point 800 feet north of the center of the intersection. As stated earlier, the goal of collecting data both upstream and downstream of the signal was to capture the total impact of stopping trucks, both on themselves as well as on other traffic. Finally, to keep data collection as consistent as possible for the before and after conditions, the two sets of data were collected within two days of each other, and the same personnel were used to collect data in the same direction, to avoid differences between individuals as to what constituted a truck and what did not. The initial data collection, specifically the detailed data collection for determining stops, delays, and queue positioning, was conducted three different days providing only one data sample in each of four one-hour time periods under two conditions (truck priority not activated, and truck priority activated). This study is not considered statistically significant; however, it provides a synopsis of the truck priority system. Also, as mentioned above, signal timing entered by MnDOT was not altered, and some of the results may be reflective of signal timing idiosyncrasies, which will be discussed in the Conclusions and Recommendations section. 6.1 Results from September Data Collection Results from the initial manual and automatic data collection are shown in Table 1. Table 1 has been separated into four sections, labeled sections A through D. Before going into detail regarding the results, it should be noted, as shown in Section C, that the total volume entering the intersection in the after condition was greater during all time periods than in the before condition. That difference ranges from 3.0 percent greater during the 16:00-17:00 time period to 9.3 percent greater during the 11:30-12:30 time period. Since, in general, higher volumes lead to higher delays, travel times (a function of delay) in the after case would be expected to be somewhat higher than the before case, if all other factors were equal. Section A contains the primary measures of effectiveness identified in the evaluation plan. Zone travel time has been used rather than delay for two reasons. First, travel time within the data collection zone is the actual measure which was recorded. Second, with a 1600-foot data collection zone, at the speed limit of 55 mph the expected travel time of a vehicle under free-flow conditions over the length of the zone would be 19.8 seconds. As can be seen in a few instances (e.g., NB trucks in the after case), the average zone travel time is less than this value, an indication that the average speed through the zone was consistently higher than the speed limit. The results in Section A show that for the northbound direction, activation of truck priority appears to decrease travel times and, therefore, delay for trucks during all four time periods, and this effect seems to be magnified during the higher-volume periods (AM and PM peaks). Page 7

11 At the same time, travel times for non-trucks increase slightly in three of the four cases, a result which is not intuitive. The percentage of trucks which stopped increased slightly during the AM peak, but decreased (slightly during the afternoon off-peak, significantly during the midday off-peak and the PM peak) at other times. Stops for non-trucks followed these same trends. The other key measure of effectiveness is how frequently the first vehicle in the queue is a truck, causing delays to following vehicles. This is of particular interest because the detection of a truck slightly upstream of other vehicles would tend to provide a better opportunity for the front vehicle in the queue to not be a truck. For this study, trucks were slightly less likely to be the front vehicle in the queue under truck priority, with the exception of the AM peak period, during which trucks were more likely to be queued at the front. The differences between the before and after conditions for all time periods were significant. Page 8

12 Page 9 Section D Section C Section B Section A Table 1 Measures of Effectiveness and Auxiliary Related Data (September 27-29, 2011) Time Four Time Periods Combined Before After Before After Change Before After Change Before After Change Before After Change Before After Change NB zone travel time for non trucks (sec/veh) NB zone travel time for trucks (sec/veh) NB non trucks stopped (%) 21.5% 28.5% +6.9% 31.0% 23.3% 7.7% 27.4% 29.1% +1.8% 31.7% 23.9% 7.8% 28.3% 26.1% 2.2% NB trucks stopped (%) 21.1% 21.7% +0.6% 22.5% 10.8% 11.7% 16.4% 16.3% 0.1% 20.0% 10.6% 9.4% 20.1% 14.6% 5.4% NB truck is front vehicle in queue at start of green 17.5% 19.0% +1.5% 23.7% 10.7% 13.0% 18.3% 10.5% 7.8% 12.1% 6.9% 5.2% 17.8% 11.9% 5.9% SB zone travel time for non trucks (sec/veh) SB zone travel time for trucks (sec/veh) SB non trucks stopped (%) 39.8% 33.9% 5.9% 48.1% 41.8% 6.3% 59.3% 51.2% 8.1% 31.9% 22.9% 9.0% 43.8% 36.2% 7.6% SB trucks stopped (%) 33.3% 20.3% 13.0% 23.1% 18.1% 5.0% 30.2% 17.5% 12.7% 32.1% 25.6% 6.4% 29.9% 19.6% 10.3% SB truck is front vehicle in queue at start of green 18.0% 12.1% 6.0% 18.6% 16.1% 2.6% 20.0% 12.3% 7.7% 10.3% 10.3% 0.0% 16.8% 12.7% 4.1% Occurrences of phase 1 (SBLT) Occurrences of phase 2 (NBT) Occurrences of phase 4 (EB) Occurrences of phase 5 (NBLT) Occurrences of phase 6 (SBT) Occurrences of phase 8 (WB) % time phase 1 (SBLT) 1% 1% +1% 1% 1% 0% 0% 1% +1% 1% 0% 0% 0% 1% 0% % time phase 2 (NBT) 72% 71% 1% 74% 76% +1% 73% 75% +2% 70% 74% +4% 72% 74% 2% % time phase 4 (EB) 26% 27% +1% 24% 23% 1% 27% 24% 3% 28% 25% 4% 26% 25% 2% % time phase 5 (NBLT) 11% 11% 1% 11% 7% 4% 8% 10% +2% 16% 13% 3% 11% 10% 1% % time phase 6 (SBT) 61% 61% 0% 64% 69% +5% 65% 66% +1% 55% 61% +6% 61% 64% 3% % time phase 8 (WB) 26% 27% +1% 24% 23% 1% 27% 24% 3% 28% 25% 4% 26% 25% 2% NB volume (all vehicles) SB volume (all vehicles) EB volume WB volume Total volume NB Truck Percentage 14% 13% 1% 20% 20% 0% 16% 17% +1% 9% 10% +2% 13% 14% 1% SB Truck Percentage 17% 15% 1% 17% 19% +2% 18% 24% +5% 13% 10% 3% 16% 17% 0% EB stop line occupancy 4% 3% 1% 4% 1% 3% 4% 7% +3% 10% 7% 3% 6% 5% 1% WB stop line occupancy 31% 45% +14% 38% 50% +12% 24% 21% 4% 24% 20% 4% 29% 34% 5% NB trucks detected NB trucks detected with potential benefit % NB trucks with benefit from priority 20% 26% +6% 14% 12% 2% 10% 19% +8% 40% 40% 0% 27% 29% 2% NB truck detected but phase not green 34% 30% 3% 35% 30% 5% 22% 29% +7% 22% 25% +3% 27% 28% 0% NB truck detected during minimum green 15% 22% +6% 15% 23% +7% 30% 26% 4% 29% 28% 1% 24% 26% 2% NB truck detected during green, no conflicting call 14% 23% +9% 31% 38% +7% 33% 17% 15% 9% 8% 1% 17% 17% 0% SB trucks detected SB trucks detected with potential benefit % SB trucks with benefit from priority 12% 22% +10% 17% 11% 6% 8% 23% +15% 25% 26% +1% 17% 21% 4% SB truck detected but phase not green 39% 47% +7% 42% 40% 2% 52% 39% 14% 55% 49% 6% 48% 43% 4% SB truck detected during minimum green 12% 25% +13% 17% 25% +8% 19% 16% 3% 23% 26% +3% 18% 22% 4% SB truck detected during green, no conflicting call 36% 6% 30% 23% 24% +1% 21% 23% +2% 0% 0% 0% 17% 14% 4%

13 In the southbound direction, travel times for trucks in the zone did not demonstrate a consistent trend to increase or decrease across the four time periods, actually increasing slightly with truck priority activated in three of the four time periods. For non-trucks, three of the four time periods showed the opposite trend, with a slight decrease in travel time. These comparisons of trucks and non-trucks are interesting because they are in the same traffic stream, and the changes would be expected to be consistent for the two groups. However, when the stop data is examined, the results are much more definitive, both across time periods and across vehicle types. In all cases, southbound vehicles experienced fewer stops when truck priority was activated, with trucks showing greater overall reductions than non-trucks. Finally, when examining the likelihood of a truck being at the front of the queue when the through signal changes to green, it can be seen that in three of the four cases, that likelihood is reduced when truck priority was activated. In the PM peak case, the percentage remained unchanged. Section B highlights the signal timing attributes under both the de-activated and activated conditions. The upper half of that section shows how many times each phase was served during the hour in which data was collected. The lower half shows the percentage of time each phase was active during that hour. With only a handful of exceptions, the number of occurrences of any given phase decreased slightly when truck priority was activated. This result is consistent with expectations. As trucks are detected farther upstream, each through movement green would be extended, increasing the average cycle length slightly and thereby reducing the total number of cycles within the hour. On the other hand, the percentages of times each phase was active remained relatively stable, which would also be expected and consistent with the fully-actuated control at this intersection. As other phases green times increase, on average more vehicles will arrive during any given phase s red time. As a result, that phase s green time needs to also increase slightly to accommodate the extra vehicles. As long as the conditions remain uncongested (as was observed) the percentages should remain relatively stable within the same time periods. Section C shows the volumes on each approach as well as the mainline truck percentages in each direction and the occupancies of the stop line detectors on the eastbound and westbound approaches. As mentioned above, the interesting aspect of the volumes is the consistently higher volume in the after condition than in the before condition, which would tend to skew the results in favor of the before condition in the absence of other factors. With respect to the number of trucks as a percentage of total traffic, notice that the percentages are higher during the off-peak periods than during the peak periods. This is actually a reflection of the non-truck traffic more than the truck traffic, since the number of trucks during an hour (which can be seen in Section D) actually remained fairly constant over the four time periods and all days. The significant point of interest in section C was the eastbound and westbound detector occupancies at the stop lines, which reflect the percentage of time vehicles would have been waiting on those approaches. It was expected that the slight increases in green time due to truck priority on the mainline would have increased the wait time on the cross street. This proved to be the case only for the AM peak and midday off-peak periods for the westbound approach, which was generally busier than the eastbound approach. During the other two time periods, the percentage of wait time actually decreased slightly. Finally, section D of the table is intended to demonstrate how frequently the existence of the truck detectors would actually provide priority treatment. This was determined by using the pseudo-detectors described in the Controller setting modifications section, to collect Page 10

14 information about certain conditions. A truck was defined as receiving potential benefit from the detectors under the following conditions: 1. The signal indication for that truck is already green, and 2. Extending the green for the truck will extend the green beyond the programmed minimum green time, and 3. There is a call for a conflicting phase either on the cross street or for the opposing leftturn phase. With respect to item 1 above, if the signal is not already green, the detection of a truck will have no benefit since the purpose of the truck detector is to extend an existing green for the truck. With respect to item 2 above, if the controller is still timing its minimum green time and sufficient time remains in that minimum to permit the truck to travel from the truck detector to the conventional extension detector, the truck detection will have no impact. Finally, with respect to item 3 above, until there is a call for a conflicting phase, the signal will remain green and, therefore, the truck detector provides no benefit. As shown in section D of Table 1, in all cases the trucks which benefit from the truck detection system represents less than half of all the trucks. However, as shown in the far right columns in Table 1, where the results from the four individual time periods have been weighted based on volumes, the priority system will benefit approximately 25 percent of all trucks. In the PM peak, 40 percent of the trucks would benefit. During the peak periods, the primary reasons trucks would not receive the benefit of priority is either because the signal is not green as the trucks approach or the minimum green will provide sufficient time for the truck to reach the stop line. As traffic levels shift from higher volumes during the peak hours to lower volumes in the off-peak hours, the primary reason for trucks not benefiting from the priority is that there is less conflicting traffic to terminate the green for the truck. From these results, there appears to be a definite trend showing benefits of the truck priority system. Aside from the travel time (delay) for NB non-trucks increasing by about 1 second per vehicle, the remainder of the measures show reductions in delays and stops to both trucks and non-trucks, as well as a reduction in the probability of the truck being stopped at the front of a queue. 7.0 Additional Data Collection November Upon review of the signal timing, MnDOT determined that an omission had been made in converting the ASC2 controller settings to ASC3 controller settings. Specifically, in the ASC2 controller the added initial function of the controller, which allows for a variable minimum green time based on detector actuations during red, is activated automatically by entering values in the actuations before added initial field, the seconds per actuation field, and the maximum initial field. For the ASC3 controller, activation of the added initial feature also requires that detectors be assigned to the function. Unfortunately, no detectors had been thus assigned prior to the September data collection effort. In early November, MnDOT personnel assigned detectors to the added initial function, and SEH conducted data collection for the non-priority and priority operations on Wednesday, November 16, and Thursday, November 17, respectively. Page 11

15 Data was collected at the same times of day as the September effort: 7:15-8:15, 11:30-12:30, 13:30-14:30 and 16:00-17:00. Eastbound and westbound vehicle stop and stopped delay time data on County Road 8, the minor street, was also collected during this effort. 7.1 Results from Additional Data Collection (November) The measures of effectiveness (MOEs) from this data collection effort are shown in Table 2. The new minor street stop and delay data appears in section C of the MOE table. For the majority of MOEs, the results obtained in November provide further support for the conclusions derived from the September data. Average travel times and, therefore, delays to both trucks and non-trucks on TH 24 tend to be slightly reduced, and the reduction to trucks appears to be slightly better than for non-trucks. Similarly, the percentages of trucks and non-trucks which stop for the signal appears to decrease due to the truck priority, and the reduction for trucks is markedly higher than for non-trucks. As shown in section B, in general the percentages of phase times for each phase did not change significantly between the non-priority and priority cases. For the minor street in the westbound direction, the average delay per vehicle did increase by a few seconds in each case, a result which would be expected with the lengthening of the mainline phases due to trucks being detected. Somewhat contrary to what was expected, the delays to minor street vehicles eastbound (approaching from the west) decreased slightly in the truck priority scenario. While not initially obvious, field observation of the intersection reveals that the majority of eastbound traffic is turning right onto TH 24. The lengthening of the mainline green for trucks (because it is lengthened for either northbound or southbound trucks) actually provided a greater opportunity for those eastbound right-turning vehicles to turn right on red. As was also observed in the September data, the data collected in November revealed a significantly higher overall traffic level on Thursday, over 12 percent higher than the traffic on Wednesday during the same four time periods. Page 12

16 Page 13 Section D Section C Section B Section A Table 2 Measures of Effectiveness and Auxiliary Related Data (November 16-17, 2011) Time AM peak Four Time Periods Combined Before After Before After Change Before After Change Before After Change Before After Change Before After Change NB zone travel time for non trucks (sec/veh) NB zone travel time for trucks (sec/veh) NB non trucks stopped (%) 36.2% 22.2% 14.0% 18.2% 13.4% 4.8% 14.8% 17.3% +2.6% 20.3% 21.9% +1.6% 22.2% 19.6% 2.5% NB trucks stopped (%) 25.9% 7.3% 18.6% 25.0% 1.9% 23.1% 7.4% 14.5% +7.1% 15.2% 13.0% 2.2% 18.1% 9.5% 8.6% NB truck is front vehicle in queue at start of green 20.0% 5.8% 14.2% 25.0% 3.9% 21.1% 6.5% 14.9% +8.4% 7.7% 5.5% 2.2% 14.9% 7.3% 7.6% SB zone travel time for non trucks (sec/veh) SB zone travel time for trucks (sec/veh) SB non trucks stopped (%) 30.7% 21.9% 9% 14.7% 21.1% +6% 22.8% 26.7% +4% 25.4% 31.0% +6% 24.2% 25.4% +1.3% SB trucks stopped (%) 29.0% 25.5% 4% 26.7% 12.3% 14% 23.9% 9.4% 15% 18.2% 37.0% +19% 25.2% 20.2% 5.1% SB truck is front vehicle in queue at start of green 18.3% 12.3% 6% 19.2% 17.2% 2% 19.2% 8.9% 10% 8.5% 17.5% +9% 16.1% 14.0% 2.1% Occurrences of phase 1 (SBLT) Occurrences of phase 2 (NBT) Occurrences of phase 4 (EB) Occurrences of phase 5 (NBLT) Occurrences of phase 6 (SBT) Occurrences of phase 8 (WB) % time phase 1 (SBLT) 0% 1% +1% 1% 1% 0% 0% 0% 0% 1% 0% 0% 0% 0% 0% % time phase 2 (NBT) 73% 73% 0% 78% 76% 2% 78% 78% 0% 75% 72% 3% 76% 75% 1% % time phase 4 (EB) 26% 26% 1% 21% 23% +2% 21% 21% 0% 23% 27% +3% 23% 24% +1% % time phase 5 (NBLT) 12% 12% 0% 6% 8% +1% 10% 9% 1% 12% 15% +2% 10% 11% +1% % time phase 6 (SBT) 61% 62% +1% 72% 69% 3% 68% 69% +1% 63% 58% 6% 66% 64% 2% % time phase 8 (WB) 26% 26% 1% 21% 23% +2% 21% 21% 0% 23% 27% +3% 23% 24% +1% NB volume (all vehicles) SB volume (all vehicles) EB volume WB volume Total volume NB Truck Percentage 17% 12% 5% 24% 17% 7% 19% 17% 2% 10% 8% 2% 16% 12% 3% SB Truck Percentage 19% 14% 5% 23% 22% 1% 22% 19% 3% 9% 14% +5% 17% 17% 1% EB stop line occupancy 3% 1% 1% 2% 2% +1% 2% 2% 0% 9% 7% 2% 4% 3% 1% WB stop line occupancy 34% 41% +7% 17% 20% +3% 22% 27% +5% 33% 46% +14% 27% 34% +7% NB trucks detected NB trucks detected with potential benefit % NB trucks with benefit from priority 17% 27% +10% 9% 17% +8% 6% 14% +9% 32% 26% 6% 22% 22% 0% NB truck detected but phase not green 38% 33% 5% 35% 25% 11% 26% 35% +8% 32% 33% +2% 33% 32% 2% NB truck detected during minimum green 28% 24% 4% 29% 32% +3% 24% 13% 10% 24% 30% +5% 26% 25% 1% NB truck detected during green, no conflicting call 19% 16% 3% 28% 26% 2% 37% 35% 2% 11% 11% +1% 18% 21% +3% SB trucks detected SB trucks detected with potential benefit % SB trucks with benefit from priority 2% 11% +9% 5% 6% +1% 7% 11% +3% 15% 15% 0% 9% 11% +2% SB truck detected but phase not green 52% 64% +12% 42% 40% 2% 42% 42% 0% 39% 57% +18% 42% 52% +10% SB truck detected during minimum green 44% 27% 16% 18% 28% +9% 30% 31% +1% 30% 28% 3% 29% 29% 0% SB truck detected during green, no conflicting call 3% 0% 3% 35% 26% 9% 21% 16% 5% 15% 0% 15% 21% 9% 12%

17 Also consistent with what was found in the earlier data collection, the implementation of priority for trucks also slightly increases the percentage of trucks which may benefit from the priority. While the reason is not obvious, it is believed that increasing the green slightly for the phase serving the truck movements lengthens the green time available for additional trucks to be detected. The percentage of trucks which could benefit from truck priority is significantly different for the northbound and southbound directions. On average, 22 percent of northbound trucks would be expected to benefit during the four time periods, while only about 10 percent of southbound trucks would be expected to benefit. The reason for this can be found in the signal timing data (in section B) and the reasons priority is not provided (in section D). Northbound left-turning traffic is significant, as evidenced by the approximately 10 percent phase time for phase 5. Southbound left-turning traffic is very light, with average phase time for phase 1 being less than one percent. (On both Wednesday and Thursday, there was demand for phase 1 only six times in the four hours data was collected.) Because the northbound left turn opposes the southbound through traffic, the northbound left turns increase the red time experienced by southbound through traffic (relative to northbound through traffic). Consequently, southbound trucks are much more likely to approach the intersection when their phase (6) is not green than are northbound trucks; and priority can only be provided when the phase is green. There was one data sampling period (the 16:00-17:00 period after truck priority was implemented) which skewed the results to some extent in favor of the non-priority operation. In particular, the southbound MOEs showed a worse operation for the priority cases than for the non-priority case. However, it appears the major reason for these results is a 63 percent increase (from 33 to 54) in southbound truck traffic during that one-hour period on Thursday relative to the same period on Wednesday. Compounding that problem was a decrease of five percent in the amount of phase time provided for the southbound through movement (phase 6) from 63 percent to 58 percent due to increased times for the northbound left turn (phase 5) and the minor street (phase 4 and 8) traffic. Based on field observations at the time, it appeared that phase 6 was extending to maximum green time on several occasions, building up the northbound left turn and minor street queue lengths, which in turn increased the phase times for those movements. Because phase 6 was already reaching its maximum, those other movements which phases were not reaching maximum received a higher percentage of the overall time. 8.0 Potential Benefit In addition to attempting to identify how much benefit may be achieved by implementing a truck priority system, the other question is How many trucks may benefit from such a system? In an attempt to answer that questions, over 700 hours of detector data were collected and uploaded from the ASC3 controller at the intersections. Table 3 shows the day-by-day results of that data collection, with aggregated results shown by day of week and weekly. Page 14

18 Table 3 Evaluation of Quantities of Trucks Receiving Benefits from Priority Page 15

19 The data is not continuous because the controller is capable of storing only approximately five and a half days of detector data before it begins overwriting the data already stored. Nevertheless, information to answer the question as to how many vehicles may benefit can be estimated. The bottom portion of table 3 has taken all of the data collected from the 34 days shown and aggregated it on a day of week basis, with the weekly results shown on the bottom line. From that table, it can be seen that 13 percent of all traffic on TH 24 is truck traffic, not surprisingly higher on weekdays than and weekends. Of the estimated 12,150 trucks on TH 24 during the week, it is believed that 16 percent (1947) would benefit through the implementation of truck priority at this intersection. 9.0 Annual Benefits In an attempt to quantify the benefits which would be obtained by implementing truck priority at this intersection, the data collected in November and summarized in Table 2 was used and applied to truck rental rates for truck operations. According to the Minnesota Department of Transportation (April 4, 2011) the tractor-trailer rental rate, including the prevailing wage plus fringe benefits for tractor-trailer drivers, is $94.43 per hour. Based on the average travel time reduction of 3.7 seconds to northbound trucks and the average increase of 1.7 seconds to southbound trucks, the average weekday volume of trucks (1034 northbound, 938 southbound, from Table 3), and 255 weekdays per year, it is estimated that the truck priority system will result in an annual reduction of 158 truck-hours, corresponding to an annual operational cost savings of $14,924. The same calculations were performed on the September data, before MnDOT changed the signal timing parameters. From that data, the average travel time reductions were 5.3 seconds and 1.9 seconds for northbound and southbound trucks, respectively. In that situation truck priority would have provided an annual reduction of 514 hours and $48,577. With respect to non-trucks, the November data collection showed a 1.1 second/vehicle reduction for 6054 northbound vehicles each weekday and a 0.5 second/vehicle increase for 4630 southbound vehicles each weekday. Expanded to a full year, this corresponds to an overall reduction of 308 vehicle-hours for non-trucks Conclusions and Recommendations Based on the results of this project, including personal observations and data collected before and after implementation, the overall conclusion is that providing special detection to implement truck priority in the form of extending the green interval for that movement does provide benefit, both to the heavy commercial vehicles themselves and to other vehicles which may be following them. However, the benefits derived are not clear-cut. In some cases travel times (delays) actually increased slightly for both types of vehicles when truck priority was implemented. Rather than delays, it appears that greater benefits derived through implementation of truck priority are a reduction in stops (both to trucks and to non-trucks) and a reduction in the probability that at the start of the green indication, the front vehicle in the queue will be a truck. Although relatively small improvements in delays were attained through truck priority, and although the number of trucks triggering the priority request at this location (approximately 16 percent) was also relatively small, as demonstrated in the Annual Benefits section, when multiplied by the total number of trucks over the course of a year, the time and monetary savings provided by truck priority become significant. Therefore, it is recommended that Page 16

20 priority operation be expanded to other intersections with high truck activity, with total truck volumes being the primary criteria used in determining precedence of those intersections. With respect to this particular intersection, the conclusions in November above were qualitatively the same as those drawn from the original data collection effort in September. At that time, it was believed that a possible cause of these mixed results was the signal timing omission mentioned earlier with respect to the conversion from the ASC2 controller to the ASC3 controller. The controller programming was corrected prior to the November data collection, and the November data yielded trends similar to those in September. Based on the magnitude of the time and monetary savings between the September and November data, the change in the controller settings were found to have a significant impact on improving the operation, and the implementation of truck priority provides an additional benefit. At this intersection, one concern that remains in the controller programming is that the mainline phases (2 and 6) have been programmed with soft vehicle recalls rather than hard vehicle recalls. Soft vehicle recalls will place a call to that phase only if there is no activity on any conflicting phases. Consequently, phase 6 (for example) would only be called if a southbound vehicle passed over the detector 550 feet upstream of the stop line or if there were no calls on phases 4, 5 and 8. As a result, a slow-moving southbound vehicle approaching which arrives at the intersection just as the signal turns red may not receive a green indication until after the controller has cycled back and forth several times between phases 4/8 and phase 5. This was actually observed several times in the field under low-flow conditions. This potential problem was exacerbated by the added initial timing features not being implemented for the September data collection. While the corrected controller programming has reduced this problem, it was still observed a handful of times in the field during the November data collection. Even if added initial detection is implemented as suggested, it is recommended that hard vehicle recalls be used for phases 2 and 6. Considering the high percentage of trucks at this location and their low acceleration rates, there is a relatively high probability of trapping a truck between the extension loop and the stop line on several occasions during the day. Based on field observations and the latest results from the data collection, it is believed that further improvement in overall operations at this intersection can be achieved by increasing the maximum green time for phases 2 and 6 (especially phase 6). As described earlier, it appears that the maximum green time on several occasions during the afternoon peak hour is limiting the controller s ability to fully accommodate the southbound demand. Finally, it was difficult to find locations within the state which met the two primary criteria for consideration high percentages of trucks, and single-lane approaches. Finding locations with single-lane approaches was essential for this project to verify that non-trucks are not adversely affected by truck priority. That was confirmed by the overall reduction in vehiclehours to non-trucks. Going forward, however, single-lane approaches need not be a prerequisite for implementing truck priority. With multi-lane approaches, although drivers of non-trucks can minimize their delays by maneuvering around trucks slowly accelerating from a stop at the traffic signal, this project has demonstrated that the savings to trucks alone from priority treatment can justify the installation. Page 17

Interstate Operations Study: Fargo-Moorhead Metropolitan Area Simulation Results

Interstate Operations Study: Fargo-Moorhead Metropolitan Area Simulation Results NDSU Dept #2880 PO Box 6050 Fargo, ND 58108-6050 Tel 701-231-8058 Fax 701-231-6265 www.ugpti.org www.atacenter.org Interstate Operations Study: Fargo-Moorhead Metropolitan Area 2025 Simulation Results

More information

County State Aid Highway 32 (Cliff Road) and Dodd Road Intersection Study

County State Aid Highway 32 (Cliff Road) and Dodd Road Intersection Study County State Aid Highway 32 (Cliff Road) and Dodd Road Intersection Study City of Eagan, Dakota County, Minnesota Date: March 2012 Project No. 14957.000 444 Cedar Street, Suite 1500 Saint Paul, MN 55101

More information

Truck Priority at Signalized Intersections

Truck Priority at Signalized Intersections Truck Priority at Signalized Intersections SEH No. December 15, 2004 Truck Priority at Signalized Intersections SEH No. December 15, 2004 I hereby certify that this report was prepared by me or under my

More information

County State Aid Highway 30 (Diffley Road) and Dodd Road Intersection Study

County State Aid Highway 30 (Diffley Road) and Dodd Road Intersection Study County State Aid Highway 30 (Diffley Road) and Dodd Road Intersection Study City of Eagan, Dakota County, Minnesota Date: March 2012 Project No. 14957.000 444 Cedar Street, Suite 1500 Saint Paul, MN 55101

More information

Interstate Operations Study: Fargo-Moorhead Metropolitan Area Simulation Output

Interstate Operations Study: Fargo-Moorhead Metropolitan Area Simulation Output NDSU Dept #2880 PO Box 6050 Fargo, ND 58108-6050 Tel 701-231-8058 Fax 701-231-6265 www.ugpti.org www.atacenter.org Interstate Operations Study: Fargo-Moorhead Metropolitan Area 2015 Simulation Output Technical

More information

Evaluation of Renton Ramp Meters on I-405

Evaluation of Renton Ramp Meters on I-405 Evaluation of Renton Ramp Meters on I-405 From the SE 8 th St. Interchange in Bellevue to the SR 167 Interchange in Renton January 2000 By Hien Trinh Edited by Jason Gibbens Northwest Region Traffic Systems

More information

The purpose of this lab is to explore the timing and termination of a phase for the cross street approach of an isolated intersection.

The purpose of this lab is to explore the timing and termination of a phase for the cross street approach of an isolated intersection. 1 The purpose of this lab is to explore the timing and termination of a phase for the cross street approach of an isolated intersection. Two learning objectives for this lab. We will proceed over the remainder

More information

Bennett Pit. Traffic Impact Study. J&T Consulting, Inc. Weld County, Colorado. March 3, 2017

Bennett Pit. Traffic Impact Study. J&T Consulting, Inc. Weld County, Colorado. March 3, 2017 Bennett Pit Traffic Impact Study J&T Consulting, Inc. Weld County, Colorado March 3, 217 Prepared By: Sustainable Traffic Solutions, Inc. http://www.sustainabletrafficsolutions.com/ Joseph L. Henderson,

More information

V. DEVELOPMENT OF CONCEPTS

V. DEVELOPMENT OF CONCEPTS Martin Luther King, Jr. Drive Extension FINAL Feasibility Study Page 9 V. DEVELOPMENT OF CONCEPTS Throughout the study process several alternative alignments were developed and eliminated. Initial discussion

More information

INTERSECTION CONTROL EVALUATION

INTERSECTION CONTROL EVALUATION INTERSECTION CONTROL EVALUATION Trunk Highway 22 and CSAH 21 (E Hill Street/Shanaska Creek Road) Kasota, Le Sueur County, Minnesota November 2018 Trunk Highway 22 and Le Sueur CSAH 21 (E Hill Street/Shanaska

More information

Transit City Etobicoke - Finch West LRT

Transit City Etobicoke - Finch West LRT Delcan Corporation Transit City Etobicoke - Finch West LRT APPENDIX D Microsimulation Traffic Modeling Report March 2010 March 2010 Appendix D CONTENTS 1.0 STUDY CONTEXT... 2 Figure 1 Study Limits... 2

More information

Downtown Lee s Summit Parking Study

Downtown Lee s Summit Parking Study Downtown Lee s Summit Parking Study As part of the Downtown Lee s Summit Master Plan, a downtown parking and traffic study was completed by TranSystems Corporation in November 2003. The parking analysis

More information

Project Title: Using Truck GPS Data for Freight Performance Analysis in the Twin Cities Metro Area Prepared by: Chen-Fu Liao (PI) Task Due: 9/30/2013

Project Title: Using Truck GPS Data for Freight Performance Analysis in the Twin Cities Metro Area Prepared by: Chen-Fu Liao (PI) Task Due: 9/30/2013 MnDOT Contract No. 998 Work Order No.47 213 Project Title: Using Truck GPS Data for Freight Performance Analysis in the Twin Cities Metro Area Prepared by: Chen-Fu Liao (PI) Task Due: 9/3/213 TASK #4:

More information

Traffic and Toll Revenue Estimates

Traffic and Toll Revenue Estimates The results of WSA s assessment of traffic and toll revenue characteristics of the proposed LBJ (MLs) are presented in this chapter. As discussed in Chapter 1, Alternatives 2 and 6 were selected as the

More information

Technical Memorandum. Purpose of Report and Study Objectives. Summary of Results

Technical Memorandum. Purpose of Report and Study Objectives. Summary of Results Technical Memorandum To: Derek Leuer, MnDOT Traffic Safety Engineer From: Max Moreland, P.E. and Bryant Ficek, P.E., P.T.O.E. Date: February 17, 217 Re: Median Acceleration Lane Usage Purpose of Report

More information

WIM #39 MN 43, MP 45.2 WINONA, MN APRIL 2010 MONTHLY REPORT

WIM #39 MN 43, MP 45.2 WINONA, MN APRIL 2010 MONTHLY REPORT WIM #39 MN 43, MP 45.2 WINONA, MN APRIL 2010 MONTHLY REPORT In order to understand the vehicle classes and groupings the Mn/DOT Vehicle Classification Scheme and the Vehicle Class Groupings for Forecasting

More information

Introduction and Background Study Purpose

Introduction and Background Study Purpose Introduction and Background The Brent Spence Bridge on I-71/75 across the Ohio River is arguably the single most important piece of transportation infrastructure the Ohio-Kentucky-Indiana (OKI) region.

More information

Table 1 - Land Use Comparisons - Proposed King s Wharf Development. Retail (SF) Office (SF) 354 6,000 10, Land Uses 1

Table 1 - Land Use Comparisons - Proposed King s Wharf Development. Retail (SF) Office (SF) 354 6,000 10, Land Uses 1 Ref. No. 171-6694 Phase 2 November 23, 217 Mr. David Quilichini, Vice President Fares & Co. Developments Inc. 31 Place Keelson Sales Centre DARTMOUTH NS B2Y C1 Sent Via Email to David@faresinc.com RE:

More information

To: File From: Adrian Soo, P. Eng. Markham, ON File: Date: August 18, 2015

To: File From: Adrian Soo, P. Eng. Markham, ON File: Date: August 18, 2015 Memo To: From: Adrian Soo, P. Eng. Markham, ON : 165620021 Date: Reference: E.C. Row Expressway, Dominion Boulevard Interchange, Dougall Avenue Interchange, and Howard 1. Review of Interchange Geometry

More information

Traffic Engineering Study

Traffic Engineering Study Traffic Engineering Study Bellaire Boulevard Prepared For: International Management District Technical Services, Inc. Texas Registered Engineering Firm F-3580 November 2009 Executive Summary has been requested

More information

Metropolitan Freeway System 2007 Congestion Report

Metropolitan Freeway System 2007 Congestion Report Metropolitan Freeway System 2007 Congestion Report Minnesota Department of Transportation Office of Traffic, Safety and Operations Freeway Operations Section Regional Transportation Management Center March

More information

Simulating Trucks in CORSIM

Simulating Trucks in CORSIM Simulating Trucks in CORSIM Minnesota Department of Transportation September 13, 2004 Simulating Trucks in CORSIM. Table of Contents 1.0 Overview... 3 2.0 Acquiring Truck Count Information... 5 3.0 Data

More information

Investigation of the Impact the I-94 ATM System has on the Safety of the I-94 Commons High Crash Area

Investigation of the Impact the I-94 ATM System has on the Safety of the I-94 Commons High Crash Area Investigation of the Impact the I-94 ATM System has on the Safety of the I-94 Commons High Crash Area John Hourdos and Stephen Zitzow Minnesota Traffic Observatory Overview Project Objectives I- 94 High

More information

MEMO VIA . Ms. Amy Roth DPS Director, City of Three Rivers. To:

MEMO VIA  . Ms. Amy Roth DPS Director, City of Three Rivers. To: MEMO To: Ms. Amy Roth DPS Director, City of Three Rivers VIA EMAIL From: Michael J. Labadie, PE Julie M. Kroll, PE, PTOE Brandon Hayes, PE, P.Eng. Fleis & VandenBrink Date: January 5, 2017 Re: Proposed

More information

Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. HNTB Project File: Subject

Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. HNTB Project File: Subject TECHNICAL MEMORANDUM To Kumar Neppalli Traffic Engineering Manager Town of Chapel Hill From Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. Cc HNTB Project File: 38435 Subject Obey Creek TIS 2022

More information

EXECUTIVE SUMMARY. The following is an outline of the traffic analysis performed by Hales Engineering for the traffic conditions of this project.

EXECUTIVE SUMMARY. The following is an outline of the traffic analysis performed by Hales Engineering for the traffic conditions of this project. EXECUTIVE SUMMARY This study addresses the traffic impacts associated with the proposed Shopko redevelopment located in Sugarhouse, Utah. The Shopko redevelopment project is located between 1300 East and

More information

Appendix B CTA Transit Data Supporting Documentation

Appendix B CTA Transit Data Supporting Documentation RED ED-PURPLE BYPASS PROJECT ENVIRONMENTAL ASSESSMENT AND SECTION 4(F) EVALUATION Appendix B CTA Transit Data Supporting Documentation 4( Memorandum Date: May 14, 2015 Subject: Chicago Transit Authority

More information

MEMORANDUM. Figure 1. Roundabout Interchange under Alternative D

MEMORANDUM. Figure 1. Roundabout Interchange under Alternative D MEMORANDUM Date: To: Liz Diamond, Dokken Engineering From: Subject: Dave Stanek, Fehr & Peers Western Placerville Interchanges 2045 Analysis RS08-2639 Fehr & Peers has completed a transportation analysis

More information

WIM #40 US 52, MP S. ST. PAUL, MN APRIL 2010 MONTHLY REPORT

WIM #40 US 52, MP S. ST. PAUL, MN APRIL 2010 MONTHLY REPORT WIM #40 US 52, MP 126.8 S. ST. PAUL, MN APRIL 2010 MONTHLY REPORT In order to understand the vehicle classes and groupings the Mn/DOT Vehicle Classification Scheme and the Vehicle Class Groupings for Forecasting

More information

TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA

TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA PREPARED FOR: UNIVERSITY OF PENNSYLVANIA HEALTH SYSTEM 34 CIVIC CENTER BOULEVARD PHILADELPHIA, PA 1987 (61)

More information

Table of Contents INTRODUCTION... 3 PROJECT STUDY AREA Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS...

Table of Contents INTRODUCTION... 3 PROJECT STUDY AREA Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS... Crosshaven Drive Corridor Study City of Vestavia Hills, Alabama Table of Contents INTRODUCTION... 3 PROJECT STUDY AREA... 3 Figure 1 Vicinity Map Study Area... 4 EXISTING CONDITIONS... 5 TRAFFIC OPERATIONS...

More information

Traffic Analysis for Bon Air Bridge Mitigation Magnolia Storm Water Quality Project

Traffic Analysis for Bon Air Bridge Mitigation Magnolia Storm Water Quality Project Memo To: Paul DiDonato, ATI Architects and Engineers From: David Parisi, PE and Ashley Tam, EIT Date: February 23, 216 Subject: Traffic Analysis for Bon Air Bridge Mitigation Magnolia Storm Water Quality

More information

Pembina Emerson Border Crossing Interim Measures Microsimulation

Pembina Emerson Border Crossing Interim Measures Microsimulation Pembina Emerson Border Crossing Interim Measures Microsimulation Final Report December 2013 Prepared for: North Dakota Department of Transportation Prepared by: Advanced Traffic Analysis Center Upper Great

More information

LAWRENCE TRANSIT CENTER LOCATION ANALYSIS 9 TH STREET & ROCKLEDGE ROAD / 21 ST STREET & IOWA STREET LAWRENCE, KANSAS

LAWRENCE TRANSIT CENTER LOCATION ANALYSIS 9 TH STREET & ROCKLEDGE ROAD / 21 ST STREET & IOWA STREET LAWRENCE, KANSAS LAWRENCE TRANSIT CENTER LOCATION ANALYSIS 9 TH STREET & ROCKLEDGE ROAD / 21 ST STREET & IOWA STREET LAWRENCE, KANSAS TRAFFIC IMPACT STUDY FEBRUARY 214 OA Project No. 213-542 TABLE OF CONTENTS 1. INTRODUCTION...

More information

Proposed location of Camp Parkway Commerce Center. Vicinity map of Camp Parkway Commerce Center Southampton County, VA

Proposed location of Camp Parkway Commerce Center. Vicinity map of Camp Parkway Commerce Center Southampton County, VA Proposed location of Camp Parkway Commerce Center Vicinity map of Camp Parkway Commerce Center Southampton County, VA Camp Parkway Commerce Center is a proposed distribution and industrial center to be

More information

TRAFFIC IMPACT ANALYSIS

TRAFFIC IMPACT ANALYSIS TRAFFIC IMPACT ANALYSIS Emerald Isle Commercial Development Prepared by SEPI Engineering & Construction Prepared for Ark Consulting Group, PLLC March 2016 I. Executive Summary A. Site Location The Emerald

More information

Metropolitan Freeway System 2013 Congestion Report

Metropolitan Freeway System 2013 Congestion Report Metropolitan Freeway System 2013 Congestion Report Metro District Office of Operations and Maintenance Regional Transportation Management Center May 2014 Table of Contents PURPOSE AND NEED... 1 INTRODUCTION...

More information

Memorandum. To: Sue Polka, City Engineer, City of Arden Hills. From: Sean Delmore, PE, PTOE. Date: June 21, 2017

Memorandum. To: Sue Polka, City Engineer, City of Arden Hills. From: Sean Delmore, PE, PTOE. Date: June 21, 2017 Memorandum engineering planning environmental construction 701 Xenia Avenue South Suite 300 Minneapolis, MN 55416 Tel: 763-541-4800 Fax: 763-541-1700 To: Sue Polka, City Engineer, City of Arden Hills From:

More information

PROJECT: Wilkinson Road Corridor Improvement Traffic Management Planning Project SUBJECT: Traffic Analysis

PROJECT: Wilkinson Road Corridor Improvement Traffic Management Planning Project SUBJECT: Traffic Analysis TECHNICAL MEMORANDUM DATE: September 10, 2014 PROJECT 5861.03 NO: PROJECT: Wilkinson Road Corridor Improvement Traffic Management Planning Project SUBJECT: Traffic Analysis TO: Steve Holroyd - District

More information

PAPER NO EVALUATION OF SPEED DISPLAYS AND RUMBLE STRIPS AT RURAL MAINTENANCE WORK ZONES

PAPER NO EVALUATION OF SPEED DISPLAYS AND RUMBLE STRIPS AT RURAL MAINTENANCE WORK ZONES PAPER NO. 01-2261 EVALUATION OF SPEED DISPLAYS AND RUMBLE STRIPS AT RURAL MAINTENANCE WORK ZONES Duplication for publication or sale is strictly prohibited without prior written permission of the Transportation

More information

RTE. 1 at RTE. 637 & RTE. 639

RTE. 1 at RTE. 637 & RTE. 639 INTERSECTION SAFETY STUDY Prepared for: Virginia Department of Transportation Central Region Operations Traffic Engineering (UPC #81378, TO 12-092) DAVENPORT Project Number: 13-368 / /2014 RTE. 1 at RTE.

More information

WIM #41 CSAH 14, MP 14.9 CROOKSTON, MINNESOTA APRIL 2014 MONTHLY REPORT

WIM #41 CSAH 14, MP 14.9 CROOKSTON, MINNESOTA APRIL 2014 MONTHLY REPORT WIM #41 CSAH 14, MP 14.9 CROOKSTON, MINNESOTA APRIL 2014 MONTHLY REPORT In order to understand the vehicle classes and groupings, the MnDOT Vehicle Classification Scheme and the Vehicle Classification

More information

Downtown One Way Street Conversion Technical Feasibility Report

Downtown One Way Street Conversion Technical Feasibility Report Downtown One Way Street Conversion Technical Feasibility Report As part of the City s Transportation Master Plan, this report reviews the technical feasibility of the proposed conversion of the current

More information

MILLERSVILLE PARK TRAFFIC IMPACT ANALYSIS ANNE ARUNDEL COUNTY, MARYLAND

MILLERSVILLE PARK TRAFFIC IMPACT ANALYSIS ANNE ARUNDEL COUNTY, MARYLAND MILLERSVILLE PARK TRAFFIC IMPACT ANALYSIS ANNE ARUNDEL COUNTY, MARYLAND Prepared for: Department of Public Works Anne Arundel County Prepared by: URS Corporation 4 North Park Drive, Suite 3 Hunt Valley,

More information

Appendix SAN San Diego, California 2003 Annual Report on Freeway Mobility and Reliability

Appendix SAN San Diego, California 2003 Annual Report on Freeway Mobility and Reliability (http://mobility.tamu.edu/mmp) Office of Operations, Federal Highway Administration Appendix SAN San Diego, California 2003 Annual Report on Freeway Mobility and Reliability This report is a supplement

More information

APPENDIX B. Origin Destination Study Data

APPENDIX B. Origin Destination Study Data APPENDIX B Origin Destination Study Data - TABLE OF CONTENTS - Page No. EXECUTIVE SUMMARY... 1 Map of the Study area with Site Locations... 2 Summary Table of Results for the TH 14 Corridor Study... 3

More information

2016 Congestion Report

2016 Congestion Report 2016 Congestion Report Metropolitan Freeway System May 2017 2016 Congestion Report 1 Table of Contents Purpose and Need...3 Introduction...3 Methodology...4 2016 Results...5 Explanation of Percentage Miles

More information

RE: A Traffic Impact Statement for a proposed development on Quinpool Road

RE: A Traffic Impact Statement for a proposed development on Quinpool Road James J. Copeland, P.Eng. GRIFFIN transportation group inc. 30 Bonny View Drive Fall River, NS B2T 1R2 May 31, 2018 Ellen O Hara, P.Eng. Project Engineer DesignPoint Engineering & Surveying Ltd. 200 Waterfront

More information

TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION

TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION DECEMBER 24 UPDATED

More information

APPENDIX C1 TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS

APPENDIX C1 TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS APPENDIX C1 TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS February 2018 Highway & Bridge Project PIN 6754.12 Route 13 Connector Road Chemung County February 2018 Appendix

More information

Shirk Road at State Route 198 Interchange Analysis Tulare County, California

Shirk Road at State Route 198 Interchange Analysis Tulare County, California Shirk Road at State Route 198 Interchange Analysis Tulare County, California DRAFT REPORT Prepared By Tulare County Association of Governments (TCAG) April 2013 Table of Contents Introduction:... 3 Project

More information

EVALUATION RESULT OF THE ALERT-2 RURAL INTERSECTION CONFLICT WARNING SYSTEM

EVALUATION RESULT OF THE ALERT-2 RURAL INTERSECTION CONFLICT WARNING SYSTEM EVALUATION RESULT OF THE ALERT-2 RURAL INTERSECTION CONFLICT WARNING SYSTEM Taek M. Kwon, Ph.D University of Minnesota Duluth Victor Lund (St. Louis County), Robert Ege, Alan Rindels (MnDOT) Outline Introduction

More information

WHITE PAPER. Preventing Collisions and Reducing Fleet Costs While Using the Zendrive Dashboard

WHITE PAPER. Preventing Collisions and Reducing Fleet Costs While Using the Zendrive Dashboard WHITE PAPER Preventing Collisions and Reducing Fleet Costs While Using the Zendrive Dashboard August 2017 Introduction The term accident, even in a collision sense, often has the connotation of being an

More information

APPENDIX C ROADWAY BEFORE-AND-AFTER STUDY

APPENDIX C ROADWAY BEFORE-AND-AFTER STUDY APPENDIX C ROADWAY BEFORE-AND-AFTER STUDY The benefits to pedestrians and bus patrons are numerous when a bus bay is replaced with a bus bulb. Buses should operate more efficiently at the stop when not

More information

Alberta Speeding Convictions and Collisions Involving Unsafe Speed

Alberta Speeding Convictions and Collisions Involving Unsafe Speed Alberta Speeding Convictions and Collisions Involving Unsafe Speed 2004-2008 Overview This document was prepared under the Alberta Traffic Safety Plan, Strategic Research Plan for 2008-2010, with the objective

More information

Poul Greibe 1 CHEVRON MARKINGS ON FREEWAYS: EFFECT ON SPEED, GAP AND SAFETY

Poul Greibe 1 CHEVRON MARKINGS ON FREEWAYS: EFFECT ON SPEED, GAP AND SAFETY Poul Greibe 1 CHEVRON MARKINGS ON FREEWAYS: EFFECT ON SPEED, GAP AND SAFETY Submission: 13 October 2009 Revised: 2 Marts 2010 Word count: 3130 + 8 tables/figures = 5130 words. Author: Mr. Poul Greibe M.Sc.,

More information

Clean Harbors Canada, Inc.

Clean Harbors Canada, Inc. Clean Harbors Canada, Inc. Proposed Lambton Landfill Expansion Environmental Assessment Terms of Reference Transportation Assessment St. Clair Township, Ontario September 2009 itrans Consulting Inc. 260

More information

King Soopers #116 Thornton, Colorado

King Soopers #116 Thornton, Colorado Traffic Impact Study King Soopers #116 Thornton, Colorado Prepared for: Galloway & Company, Inc. T R A F F I C I M P A C T S T U D Y King Soopers #116 Thornton, Colorado Prepared for Galloway & Company

More information

Traffic Impact Analysis. Alliance Cole Avenue Residential Site Dallas, Texas. Kimley-Horn and Associates, Inc. Dallas, Texas.

Traffic Impact Analysis. Alliance Cole Avenue Residential Site Dallas, Texas. Kimley-Horn and Associates, Inc. Dallas, Texas. Traffic Impact Analysis Alliance Cole Avenue Residential Site Dallas, Texas February 15, 2018 Kimley-Horn and Associates, Inc. Dallas, Texas Project #064524900 Registered Firm F-928 Traffic Impact Analysis

More information

Traffic Impact Statement (TIS)

Traffic Impact Statement (TIS) Traffic Impact Statement (TIS) Vincentian PUDA Collier County, FL 10/18/2013 Prepared for: Global Properties of Naples Prepared by: Trebilcock Consulting Solutions, PA 2614 Tamiami Trail N, Suite 615 1205

More information

WIM #41 CSAH 14, MP 14.9 CROOKSTON, MINNESOTA MAY 2013 MONTHLY REPORT

WIM #41 CSAH 14, MP 14.9 CROOKSTON, MINNESOTA MAY 2013 MONTHLY REPORT WIM #41 CSAH 14, MP 14.9 CROOKSTON, MINNESOTA MAY 2013 MONTHLY REPORT In order to understand the vehicle classes and groupings the Mn/DOT Vehicle Classification Scheme and the Vehicle Classification Groupings

More information

King County Metro. Columbia Street Transit Priority Improvements Alternative Analysis. Downtown Southend Transit Study. May 2014.

King County Metro. Columbia Street Transit Priority Improvements Alternative Analysis. Downtown Southend Transit Study. May 2014. King County Metro Columbia Street Transit Priority Improvements Alternative Analysis Downtown Southend Transit Study May 2014 Parametrix Table of Contents Introduction... 1 Methodology... 1 Study Area...

More information

Road User Cost Analysis

Road User Cost Analysis Road User Cost Analysis I-45 Gulf Freeway at Beltway 8 Interchange CSJ #500-03-382 1994 Texas Transportation Institute ROAD USER COST ANALYSIS CSJ #500-03-382 The Texas Department of Transportation (TxDOT)

More information

AVERAGE DELAY PER VEHICLE EXISTING CONDITIONS AND NO BUILD ALTERNATIVE

AVERAGE DELAY PER VEHICLE EXISTING CONDITIONS AND NO BUILD ALTERNATIVE AVERAGE DELAY PER VEHICLE EXISTING CONDITIONS AND NO BUILD ALTERNATIVE EXISTING CONDITIONS (1) NO BUILD ALTERNATIVE () Compared to existing conditions Peak Hour/Train Scenario No Train 1 With Train No

More information

Southern Windsor County 2016 Traffic Count Program Summary April 2017

Southern Windsor County 2016 Traffic Count Program Summary April 2017 Southern Windsor County 2016 Traffic Count Program Summary April 2017 The Southern Windsor County Regional Planning Commission (the RPC ) has been monitoring traffic at 19 locations throughout the southern

More information

Ryan Coyne, PE City Engineer City of Rye 1051 Boston Post Road Rye, NY Boston Post Road Realignment and Roundabout Design Report

Ryan Coyne, PE City Engineer City of Rye 1051 Boston Post Road Rye, NY Boston Post Road Realignment and Roundabout Design Report March 6, 2015 Ryan Coyne, PE City Engineer City of Rye 1051 Boston Post Road Rye, NY 10580 RE: JMC Project 14108 Boston Post Road Roundabout Boston Post Road and Parsons Street City of Rye, NY Dear Ryan:

More information

INTERSECTION ANALYSIS PARK AVENUE AND BRADDOCK ROAD (FROSTBURG, MD) FOR LENHART TRAFFIC CONSULTING, INC.

INTERSECTION ANALYSIS PARK AVENUE AND BRADDOCK ROAD (FROSTBURG, MD) FOR LENHART TRAFFIC CONSULTING, INC. INTERSECTION ANALYSIS FOR PARK AVENUE AND BRADDOCK ROAD (FROSTBURG, MD) Prepared for: City of Frostburg, Maryland & Allegany County Commissioners Prepared by: LENHART TRAFFIC CONSULTING, INC. TRAFFIC ENGINEERING

More information

Heavy Truck Conflicts at Expressway On-Ramps Part 1

Heavy Truck Conflicts at Expressway On-Ramps Part 1 Heavy Truck Conflicts at Expressway On-Ramps Part 1 Posting Date: 7-Dec-2016; Revised 14-Dec-2016 Figure 1: Every day vast numbers of large and long trucks must enter smoothly into high speed truck traffic

More information

APPENDIX E. Traffic Analysis Report

APPENDIX E. Traffic Analysis Report APPENDIX E Traffic Analysis Report THIS PAGE INTENTIONALLY BLANK EAGLE RIVER TRAFFIC MITIGATION PHASE I OLD GLENN HIGHWAY/EAGLE RIVER ROAD INTERSECTION IMPROVEMENTS TRAFFIC ANALYSIS Eagle River, Alaska

More information

Figure 1 Map of intersection of SR 44 (Ravenna Rd) and Butternut Rd

Figure 1 Map of intersection of SR 44 (Ravenna Rd) and Butternut Rd Abbreviated Study District: 12 County: Geauga Route: SR 44 Section: 1.58 GEA 44 1.58 213 HSP # 47 (Rural Intersection) Prepared April 23, 215 By Bryan Emery Existing Conditions This study contains the

More information

ZINFANDEL LANE / SILVERADO TRAIL INTERSECTION TRAFFIC ANALYSIS

ZINFANDEL LANE / SILVERADO TRAIL INTERSECTION TRAFFIC ANALYSIS ZINFANDEL LANE / SILVERADO TRAIL INTERSECTION TRAFFIC ANALYSIS UPDATED TRAFFIC STUDY FOR THE PROPOSED RAYMOND VINEYARDS WINERY USE PERMIT MODIFICATION #P11-00156 AUGUST 5, 2014 PREPARED BY: OMNI-MEANS,

More information

TRAFFIC IMPACT STUDY. USD #497 Warehouse and Bus Site

TRAFFIC IMPACT STUDY. USD #497 Warehouse and Bus Site TRAFFIC IMPACT STUDY for USD #497 Warehouse and Bus Site Prepared by: Jason Hoskinson, PE, PTOE BG Project No. 16-12L July 8, 216 145 Wakarusa Drive Lawrence, Kansas 6649 T: 785.749.4474 F: 785.749.734

More information

Speed measurements were taken at the following three locations on October 13 and 14, 2016 (See Location Map in Exhibit 1):

Speed measurements were taken at the following three locations on October 13 and 14, 2016 (See Location Map in Exhibit 1): 2709 McGraw Drive Bloomington, Illinois 61704 p 309.663.8435 f 309.663.1571 www.f-w.com www.greennavigation.com November 4, 2016 Mr. Kevin Kothe, PE City Engineer City of Bloomington Public Works Department

More information

IRSCH REEN Hirsch/Green Transportation Consulting, Inc.

IRSCH REEN Hirsch/Green Transportation Consulting, Inc. IRSCH REEN Hirsch/Green Transportation Consulting, Inc. February 6, 2013 Mr. David Weil Director of Finance St. Matthew s Parish School 1031 Bienveneda Avenue Pacific Palisades, California 90272 RE: Trip

More information

TIMBERVINE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO JANUARY Prepared for:

TIMBERVINE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO JANUARY Prepared for: TIMBERVINE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO JANUARY 2014 Prepared for: Hartford Companies 1218 W. Ash Street Suite A Windsor, Co 80550 Prepared by: DELICH ASSOCIATES 2272 Glen Haven Drive

More information

Oregon DOT Slow-Speed Weigh-in-Motion (SWIM) Project: Analysis of Initial Weight Data

Oregon DOT Slow-Speed Weigh-in-Motion (SWIM) Project: Analysis of Initial Weight Data Portland State University PDXScholar Center for Urban Studies Publications and Reports Center for Urban Studies 7-1997 Oregon DOT Slow-Speed Weigh-in-Motion (SWIM) Project: Analysis of Initial Weight Data

More information

Evaluation of Major Street Speeds for Minnesota Intersection Collision Warning Systems

Evaluation of Major Street Speeds for Minnesota Intersection Collision Warning Systems Evaluation of Major Street Speeds for Minnesota Intersection Collision Warning Systems Shauna Hallmark, Principal Investigator Center for Transportation Research and Education Iowa State University June

More information

Trip Generation Study: Provo Assisted Living Facility Land Use Code: 254

Trip Generation Study: Provo Assisted Living Facility Land Use Code: 254 Trip Generation Study: Provo Assisted Living Facility Land Use Code: 254 Introduction The Brigham Young University Institute of Transportation Engineers (BYU ITE) student chapter completed a trip generation

More information

DEVELOPMENT PROPERTY 1627 MAXIME STREET CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for: Subhas Bhargava. July 9, Overview_1.

DEVELOPMENT PROPERTY 1627 MAXIME STREET CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for: Subhas Bhargava. July 9, Overview_1. DEVELOPMENT PROPERTY 1627 MAXIME STREET CITY OF OTTAWA TRANSPORTATION OVERVIEW Prepared for: Subhas Bhargava July 9, 2015 115-620 Overview_1.doc D. J. Halpenny & Associates Ltd. Consulting Transportation

More information

1 On Time Performance

1 On Time Performance MEMORANDUM: US 29 Travel Time & OTP To: From: Joana Conklin, Montgomery County DOT James A. Bunch, SWAI Subject: US 29 Travel Time and On Time Performance Analysis Date: This memorandum documents the US

More information

WIM #37 was operational for the entire month of September Volume was computed using all monthly data.

WIM #37 was operational for the entire month of September Volume was computed using all monthly data. SEPTEMBER 2016 WIM Site Location WIM #37 is located on I-94 near Otsego in Wright county. The WIM is located only on the westbound (WB) side of I-94, meaning that all data mentioned in this report pertains

More information

Collision Types of Motorcycle Accident and Countermeasures

Collision Types of Motorcycle Accident and Countermeasures Proceedings of the 2 nd World Congress on Civil, Structural, and Environmental Engineering (CSEE 17) Barcelona, Spain April 2 4, 2017 Paper No. ICTE 115 ISSN: 2371-5294 DOI: 10.11159/icte17.115 Collision

More information

Safety Evaluation of Converting On-Street Parking from Parallel to Angle

Safety Evaluation of Converting On-Street Parking from Parallel to Angle 36 TRANSPORTATION RESEARCH RECORD 1327 Safety Evaluation of Converting On-Street Parking from Parallel to Angle TIMOTHY A. McCOY, PATRICK T. McCoY, RICHARD J. HADEN, AND VIRENDRA A. SINGH To increase the

More information

DRIVER SPEED COMPLIANCE WITHIN SCHOOL ZONES AND EFFECTS OF 40 PAINTED SPEED LIMIT ON DRIVER SPEED BEHAVIOURS Tony Radalj Main Roads Western Australia

DRIVER SPEED COMPLIANCE WITHIN SCHOOL ZONES AND EFFECTS OF 40 PAINTED SPEED LIMIT ON DRIVER SPEED BEHAVIOURS Tony Radalj Main Roads Western Australia DRIVER SPEED COMPLIANCE WITHIN SCHOOL ZONES AND EFFECTS OF 4 PAINTED SPEED LIMIT ON DRIVER SPEED BEHAVIOURS Tony Radalj Main Roads Western Australia ABSTRACT Two speed surveys were conducted on nineteen

More information

VARIABLE SPEED LIMITS SIGNS: EFFECTS ON SPEED AND SPEED VARIATION IN WORK ZONES

VARIABLE SPEED LIMITS SIGNS: EFFECTS ON SPEED AND SPEED VARIATION IN WORK ZONES VARIABLE SPEED LIMITS SIGNS: EFFECTS ON SPEED AND SPEED VARIATION IN WORK ZONES by Thomas McMurtry Planner/GIS Technician InterPlan Co. Inc. 7719 South Main Street Midvale, UT 84607 Phone: 1-801-307-3400,

More information

Open House. Highway212. Meetings. Corridor Access Management, Safety & Phasing Plan. 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition

Open House. Highway212. Meetings. Corridor Access Management, Safety & Phasing Plan. 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition Welcome Meetings 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition 6:30 to 8:00 p.m. - Open House Why is Highway 212 Project Important? Important Arterial Route Local Support Highway 212

More information

Section 5.0 Traffic Information

Section 5.0 Traffic Information Section 5.0 Traffic Information 10.0 TRANSPORTATION MDM Transportation Consultants, Inc. (MDM) has prepared an evaluation of transportation impacts for the proposed evaluation for the expansion of the

More information

CONTENTS I. INTRODUCTION... 2 II. SPEED HUMP INSTALLATION POLICY... 3 III. SPEED HUMP INSTALLATION PROCEDURE... 7 APPENDIX A... 9 APPENDIX B...

CONTENTS I. INTRODUCTION... 2 II. SPEED HUMP INSTALLATION POLICY... 3 III. SPEED HUMP INSTALLATION PROCEDURE... 7 APPENDIX A... 9 APPENDIX B... Speed Hump Program CONTENTS I. INTRODUCTION... 2 II. SPEED HUMP INSTALLATION POLICY... 3 1. GENERAL... 3 2. ELIGIBILITY REQUIREMENTS... 3 A. PETITION... 3 B. OPERATIONAL AND GEOMETRIC CHARACTERISTICS OF

More information

Ref. No Task 3. April 28, Mr. Cesar Saleh, P. Eng. VP Planning and Design W.M. Fares Group th

Ref. No Task 3. April 28, Mr. Cesar Saleh, P. Eng. VP Planning and Design W.M. Fares Group th Ref. No. 151-00564 Task 3 April 28, 2015 Mr. Cesar Saleh, P. Eng. VP Planning and Design W.M. Fares Group th 3480 Joseph Howe Drive, 5 Floor HALIFAX NS B3L 4H7 Sent via Email to ceasr.saleh@wmfares.com

More information

WIM #31 US 2, MP 8.0 EAST GRAND FORKS, MN JANUARY 2015 MONTHLY REPORT

WIM #31 US 2, MP 8.0 EAST GRAND FORKS, MN JANUARY 2015 MONTHLY REPORT WIM #31 US 2, MP 8.0 EAST GRAND FORKS, MN JANUARY 2015 MONTHLY REPORT WIM #31 EAST GRAND FORKS MONTHLY REPORT - JANUARY 2015 WIM Site Location WIM #31 is located on US 2 at mile post 8.0, southeast of

More information

Traffic Analysis For Approved Uses within the St. Lucie West DRI Aldi Port St. Lucie, FL Prepared for: Bohler Engineering, LLC 1000 Corporate Drive Suite 250 Fort Lauderdale, FL 33334 Prepared by: 10795

More information

Key Findings. February 2009 Caltrain Annual Passenger Counts

Key Findings. February 2009 Caltrain Annual Passenger Counts Key Findings February 2009 Caltrain Annual Passenger Counts The 2009 annual Caltrain passenger counts, which were conducted starting in late-january and were complete by mid-february, followed the same

More information

ESTIMATING THE LIVES SAVED BY SAFETY BELTS AND AIR BAGS

ESTIMATING THE LIVES SAVED BY SAFETY BELTS AND AIR BAGS ESTIMATING THE LIVES SAVED BY SAFETY BELTS AND AIR BAGS Donna Glassbrenner National Center for Statistics and Analysis National Highway Traffic Safety Administration Washington DC 20590 Paper No. 500 ABSTRACT

More information

INDUSTRIAL DEVELOPMENT

INDUSTRIAL DEVELOPMENT INDUSTRIAL DEVELOPMENT Traffic Impact Study Plainfield, Illinois August 2018 Prepared for: Seefried Industrial Properties, Inc. TABLE OF CONTENTS Executive Summary 2 Introduction 3 Existing Conditions

More information

STH 60 Northern Reliever Route Feasibility Study Report

STH 60 Northern Reliever Route Feasibility Study Report #233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development

More information

National Household Travel Survey Add-On Use in the Des Moines, Iowa, Metropolitan Area

National Household Travel Survey Add-On Use in the Des Moines, Iowa, Metropolitan Area National Household Travel Survey Add-On Use in the Des Moines, Iowa, Metropolitan Area Presentation to the Transportation Research Board s National Household Travel Survey Conference: Data for Understanding

More information

Public Meeting: Metropolitan Washington Airports Authority (MWAA) TNC (Transportation Network Company) Lot on S. Eads Street

Public Meeting: Metropolitan Washington Airports Authority (MWAA) TNC (Transportation Network Company) Lot on S. Eads Street Public Meeting: Metropolitan Washington Airports Authority (MWAA) TNC (Transportation Network Company) Lot on S. Eads Street Department of Environmental Services, Transportation Division Sept. 27, 2018

More information

Bus Priority at Traffic Signals in Portland: The Powell Boulevard Pilot Project

Bus Priority at Traffic Signals in Portland: The Powell Boulevard Pilot Project TRANSPORTATION RESEARCH RECORD 1503 29 Bus Priority at Traffic Signals in Portland: The Powell Boulevard Pilot Project KATHARINE M. HUNTER-ZAWORSKI, WILLIAM C. KLOOS, AND ALAN R. DANAHER The city of Portland,

More information

Date: February 7, 2017 John Doyle, Z-Best Products Robert Del Rio. T.E. Z-Best Traffic Operations and Site Access Analysis

Date: February 7, 2017 John Doyle, Z-Best Products Robert Del Rio. T.E. Z-Best Traffic Operations and Site Access Analysis Memorandum Date: February 7, 07 To: From: Subject: John Doyle, Z-Best Products Robert Del Rio. T.E. Z-Best Traffic Operations and Site Access Analysis Introduction Hexagon Transportation Consultants, Inc.

More information

Act 229 Evaluation Report

Act 229 Evaluation Report R22-1 W21-19 W21-20 Act 229 Evaluation Report Prepared for Prepared by Table of Contents 1. Documentation Page 3 2. Executive Summary 4 2.1. Purpose 4 2.2. Evaluation Results 4 3. Background 4 4. Approach

More information