SUBJECT: EMERALD NECKLACE IMPLEMENTATION PLAN PHASE 1 TRAFFIC ASSESSMENT SUMMARY OF FINDINGS. May 9, 2016

Size: px
Start display at page:

Download "SUBJECT: EMERALD NECKLACE IMPLEMENTATION PLAN PHASE 1 TRAFFIC ASSESSMENT SUMMARY OF FINDINGS. May 9, 2016"

Transcription

1 May 9, 2016 Mr. Jesus "Freddie" Olmos ECORP CONSULTING, INC. 215 North 5 th Street Redlands, CA SUBJECT: EMERALD NECKLACE IMPLEMENTATION PLAN PHASE 1 TRAFFIC ASSESSMENT Dear Mr. Jesus "Freddie" Olmos: The firm of Urban Crossroads, Inc. is pleased to submit this Traffic Assessment for the Emerald Necklace Implementation Plan Phase 1 (referred to as Project ), which is located beside two waterways, the San Gabriel and the Rio Honda. The Project is proposed to include the development of a 17-mile loop of bicycle and multi-use trails which link parks and open spaces through multiple jurisdictions. SUMMARY OF FINDINGS As the proposed Project is not expected to result in a significant increase to vehicular traffic, the primary focus of this traffic assessment was to evaluate potential operational and safety impacts to the following intersection locations: Peck Road at Foothill Transit Driveway Durfee Avenue/San Gabriel Avenue at Rosemead Boulevard San Gabriel Avenue at Lincoln Avenue The Project proposes to provide a new at-grade trail crossing at each location. The crossings on Peck Road at Foothill Transit, San Gabriel Avenue/Durfee Avenue at Rosemead Boulevard and San Gabriel Avenue at Lincoln Avenue are proposed at existing signalized intersections with pedestrian crosswalks. Signal modifications may be required to add pedestrian, bicycle detection and to comply with Americans with Disabilities Act (ADA) requirements, and intersection warning signs may be used on a path in advance of the intersection to indicate the presence of the crossing and the possibility of turning or entering traffic. Based on the results of this analysis, the increased pedestrian, cyclist and/or equestrian activity is not anticipated to significantly impact current intersection operations. The study area intersections are anticipated to continue to operate at an acceptable LOS with the proposed Project Letter Report

2 Mr. Jesus "Freddie" Olmos ECORP CONSULTING, INC. May 9, 2016 Page 2 of 12 APPENDIX G The Project also proposes a mid-bock crossing along Rosemead Boulevard for the SCE easement trail. It is suggested that the crossing utilize the more visible piano key configuration of longitudinal stripes. This is consistent with guidance in the 2014 California Manual on Uniform Traffic Control Devices (2014 CA MUTCD), which states that this type of marking should be used at locations where a crosswalk might not be expected. The vehicular volumes on Rosemead Boulevard and the potential pedestrian and bicycle activity indicates that a pedestrian traffic signal would be warranted at the mid-block crossing. Finally, in addition to traffic operations, potential impacts to existing on-street parking were also reviewed. The Project proposes to eliminate on-street parking along Clark Street in the vicinity of Varus Street to Durfee Avenue. A parking survey conducted over weekend conditions indicates a maximum of 69 vehicles were parked on Clark Street in the vicinity of the Project. During the same interval, the maximum number of observed vehicles parked on Clark Street between Varus Street and Durfee Avenue was 14. Elimination of on-street parking in this area would potentially result in a significant impact as there is limited opportunity to provide for alternative parking locations in the vicinity. PROJECT DESCRIPTION The Project is proposed to include the development of a 17-mile loop of bicycle and multi-use trails which link parks and open spaces through multiple jurisdictions as shown on Exhibit 1. Phase I includes 16 projects which are designed to close gaps in the existing regional recreational trails network. However, for the purposes of this analysis, project number four of 16 will be analyzed separately from this Phase I program-level analysis. The 15 projects within Phase I development analyzed in this analysis are provided on Table Letter Report

3 Mr. Jesus "Freddie" Olmos ECORP CONSULTING, INC. May 9, 2016 Page 3 of 12 APPENDIX G EXHIBIT 1: LOCATION MAP TABLE 1: PHASE I PROJECT DESCRIPTIONS Chapter Title 1 Quarry Clasp Park Development 2 Quarry Clasp Multi-Use Trail 3 Quarry Clasp Peck Road Signalized Crossing 5 Rosemead Bike Path 6 Whittier North San Gabriel Bike Path 7 Whittier SCE Easement Bike Path 8 Whittier North Pellissier Multi-Use Trail 9 Whittier North Pellissier Bridge Letter Report

4 Mr. Jesus "Freddie" Olmos ECORP CONSULTING, INC. May 9, 2016 Page 4 of 12 APPENDIX G EXISTING CIRCULATION NETWORK 10 San Jose Creek Trails and Bridges 11 San Jose Eastside Trail 12 West Alhambra to Garvey 13 West Side Rosemead Access Ramp 14 West Site Rosemead Underpass 15 West Side Rosemead to Valley 16 West 10 Underpass The following three study area intersections adjacent to crossings of the bicycle and multi-use trails across public streets and one future mid-block crossing location shown on Exhibit 2 and listed in Table 2 were selected for this TIA. TABLE 2: INTERSECTION ANALYSIS LOCATIONS ID Intersection Location Jurisdiction 1 E. Lincoln Avenue / San Gabriel Boulevard County of Los Angeles, Montebello 2 Rosemead Boulevard / San Gabriel Boulevard County of Los Angeles, Caltrans 3 Rosemead Boulevard / SCE Easement Future Crossing County of Los Angeles, Caltrans 4 Peck Road / Foothill Transit Driveway City of Arcadia Exhibit 2 illustrates the study area and identifies the number of through traffic lanes for existing roadways and intersection traffic controls. EXISTING (2016) TRAFFIC VOLUMES Peak hour turning movement counts were conducted at the study area intersections in April Given the uses of trails, weekday PM peak hour (4-6PM) and Saturday morning peak (7-9AM) turning movement counts were collected. Existing (2016) AM and PM peak hour intersection volumes are shown on Exhibit 3. The raw manual peak hour turning movement traffic count data sheets are included in Attachment A. In addition, 24 hour directional volume counts were collected on Rosemead Boulevard near the proposed mid-block crossing near SCE easement. The 24 hour counts showed an average daily count (ADT) of 27, 071 on a weekday and 24,603 on a Saturday. The weekday peak hour volume on Rosemead Boulevard is 2,273 vehicles per hour (vph) and the Saturday peak hour volume is 1,782 vph. The 24 hour count data are also included in Attachment A Letter Report

5 Mr. Jesus "Freddie" Olmos ECORP CONSULTING, INC. May 9, 2016 Page 5 of 12 APPENDIX G PROJECT TRIP GENERATION Trip generation represents the amount of traffic which is both attracted to and produced by a development. The proposed Project site will consist of approximately acre Passive Park and Trails. Although only a 5 acre park is proposed in the Project, the total area of all the proposed multi-use trails have been added for the purposes of trip generation calculation to provide a conservative estimate. Traffic generation rates for the proposed Project have been derived from (Not So) Brief Guide of Vehicular Traffic General Rates for the San Diego Region (April 2002) published by San Diego association of Governments (SANDAG). The trip generation rates used for this analysis are shown in Table 3. The rates published by SANDAG are more conservative compared to rates in ITE Trip Generation manual. As such, trip generation rates published by SANDAG have been used to provide a conservative estimate for Project trips. A summary of the proposed Project s trip generation is also shown on Table 3. The Project is anticipated to generate a total of 487 trips per day with approximately 19 AM peak hour trips and 39 PM peak hour trips. The estimated peak hour vehicular Project trips on study area roadways and intersections are nominal. Therefore, the focus of this traffic analysis is to evaluate the existing operations. Addition of Project trips is not expected to have significant impacts on study area roadways and intersections. INTERSECTION CAPACITY ANALYSIS The definitions of LOS for interrupted traffic flow (flow restrained by the existence of traffic signals and other traffic control devices) differ slightly depending on the type of traffic control. The LOS is typically dependent on the quality of traffic flow at the intersections along a roadway. The 2010 Highway Capacity Manual (HCM) methodology was used for the study intersections. Intersection LOS operations are based on an intersection s average control delay. Control delay includes initial deceleration delay, queue move-up time, stopped delay, and final acceleration delay. For signalized intersections LOS is directly related to the average control delay per vehicle and is correlated to a LOS designation as described in Table 4. TABLE 4: SIGNALIZED INTERSECTION HCM 2010 LOS THRESHOLDS Description Average Control Delay (Seconds), V/C 1.0 Level of Service, V/C 1.0 Operations with very low delay occurring with favorable progression and/or short cycle length. Operations with low delay occurring with good progression and/or short cycle lengths. Operations with average delays resulting from fair progression and/or longer cycle lengths. Individual cycle failures begin to Level of Service, V/C > to A F to B F to C F Letter Report

6 Mr. Jesus "Freddie" Olmos ECORP CONSULTING, INC. May 9, 2016 Page 6 of 12 APPENDIX G appear. Operations with longer delays due to a combination of unfavorable progression, long cycle lengths, or high V/C ratios. Many vehicles stop and individual cycle failures are noticeable. Operations with high delay values indicating poor progression, long cycle lengths, and high V/C ratios. Individual cycle failures are frequent occurrences. This is considered to be the limit of acceptable delay. Operation with delays unacceptable to most drivers occurring due to over saturation, poor progression, or very long cycle lengths Source: HCM 2010, Chapter to D F to E F and up F F The definition of an intersection deficiency has been obtained from each of the applicable surrounding jurisdictions. The City of Arcadia, City of Montebello, County of Los Angeles and Caltrans have set the goal for acceptable LOS as LOS D or better, for study area intersections. Existing (2016) peak hour traffic operations have been evaluated for the study area intersections based on HCM 2010 methodology. The intersection operations analysis results are summarized in Table 5 which indicates that the existing study area intersections are currently operating at acceptable LOS (i.e., LOS D or better) during the peak hours. The intersection operations analysis worksheets are included in Attachment B. PROJECT IMPACTS As discussed previously, vehicular Project trips on study area roadways and intersections are nominal. The potential increase in number of pedestrian and bicycle crossings at the crosswalks at study area intersections is unknown. However, based on review of existing delay and LOS at the study area intersections, it appears the potential increase in pedestrian and bicycle crossings will not have a significant impact on delay and LOS with the completion of the Project. The study area intersections are anticipated to continue to operate at acceptable LOS with Project. TRAIL CROSSING EVALUATION The Project proposes at-grade pedestrian, bicycle and/or equestrian crossings at the following locations. Peck Road at Foothill Transit Driveway Durfee Avenue/San Gabriel Avenue at Rosemead Boulevard San Gabriel Avenue at Lincoln Avenue Rosemead Boulevard at SCE Easement trail Letter Report

7 Mr. Jesus "Freddie" Olmos ECORP CONSULTING, INC. May 9, 2016 Page 7 of 12 APPENDIX G Based on information provided from the Federal Highway Administration (FHWA) Safety Program marked crosswalks serve two purposes: they tell the pedestrian the best place to cross; and they clarify that a legal crosswalk exists at a particular location. Marked crosswalks are one tool to get pedestrians safely across the street. When considering marked crosswalks at uncontrolled locations, the question should not simply be: Should I provide a marked crosswalk or not? Instead, the question should be: Is this an appropriate tool for getting pedestrians across the street? Regardless of whether marked crosswalks are used, there remains the fundamental objective of getting pedestrians safely across the street. Marked crosswalks should not be installed in close proximity to traffic signals or stop signs, since pedestrians should be encouraged to cross at the intersection in most situations. The objective of adding a marked crosswalk is to channel pedestrians and bicyclists to safer crossing points. It should be understood, however, that pedestrian crossing behavior may be difficult to control merely by the addition of marked crosswalks. On many roadways, particularly multilane and high-speed crossing location, more substantial improvements are often needed for safer pedestrian crossings. Marked crosswalk alone are not recommended at uncontrolled crossing locations on multilane roads. At uncontrolled pedestrian crossing locations, installing marked crosswalks should not be regarded as a magic cure for pedestrian safety problems. However, marked crosswalks also should not be considered as a negative measure that will necessarily increase pedestrian crashes. Crossings within 350 feet of an existing signalized intersection with pedestrian crosswalks are typically diverted to the signalized intersection for safety purposes. The crossings on Peck Road at Foothill Transit, San Gabriel Avenue/Durfee Avenue at Rosemead Boulevard and San Gabriel Avenue at Lincoln Avenue are proposed at existing signalized intersections with pedestrian crosswalks. Signal modifications may be required to add pedestrian, bicycle detection and to comply with Americans with Disabilities Act (ADA) requirements. Intersection Warning signs may be used on a path in advance of the intersection to indicate the presence of the crossing and the possibility of turning or entering traffic. ROSEMEAD BOULEVARD MID-BLOCK CROSSWALK The mid-block crosswalk on Rosemead Boulevard at SCE easement trail shall utilize the more visible piano key configuration of longitudinal stripes. This is consistent with guidance in the 2014 California Manual on Uniform Traffic Control Devices (2014 CA MUTCD), which states that this type of marking should be used at locations where a crosswalk might not be expected. The 2014 CA MUTCD states that safety must be considered when evaluating whether to install a mid-block pedestrian crossing. Recognizing the safety concerns associated with mid-block pedestrian crossings, the mid-block crosswalk design concept is supplemented with local and advance warning systems and signage such as the mid-block pedestrian / bicycle signal, pedestrian actuated pedestrian hybrid beacon or rectangular rapid flash beacon (RRFB), Letter Report

8 Mr. Jesus "Freddie" Olmos ECORP CONSULTING, INC. May 9, 2016 Page 8 of 12 APPENDIX G flashing beacons, and speed feedback sign consistent with the 2014 CA MUTCD criteria shown on Table 1. The 2014 CA MUTCD criteria are based on peak hour traffic volumes and also take the volume of pedestrians / cyclists using the crossing into consideration, as well as the length of the crossing. The warrants for pedestrian traffic signal was evaluated based on Figure 4C-8 from 2014 CA MUTCD and warrants for pedestrian hybrid beacon was evaluated based on Figure 4F- 2 from 2014 CA MUTCD. The vehicular volumes on Rosemead Boulevard (2,273 vph on weekday and 1,782 vph on Saturday) result in the warrants being satisfied based on the minimum threshold crossing volumes of 20 pedestrians / cyclists for a Pedestrian Hybrid Beacon or 93 pedestrians / cyclists for a mid-block pedestrian signal. The warrant sheets are provided in Attachment C of this report. No explicit projections of the number of pedestrians / cyclists that will use each crossing are available (and as the crossings do not exist, it is not possible to collect existing counts). However, existing pedestrian and bicycle counts at the intersection of Rosemead Boulevard and San Gabriel Avenue / Durfee Avenue shows approximately 26 pedestrians and 79 bicyclists crossing Rosemead Boulevard during Saturday AM peak period, which indicates mid-block pedestrian/bicycle signal warrant threshold would be satisfied Letter Report

9 Mr. Jesus "Freddie" Olmos ECORP CONSULTING, INC. May 9, 2016 Page 9 of 12 APPENDIX G TABLE 6 PEDESTRIAN CROSSING DEVICES EVALUATION PARAMETERS TYPE OF CROSSING Criteria Mid-Block Pedestrian / Bike Signal Pedestrian Hybrid Beacon Flashing Beacon In-Roadway Flashing Lights Roadway Vehicular Traffic Crossing Traffic Speed Safety Other 2014 CALIFORNIA MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES Per Figure 4C-6 (4 hours) or Figure 4C-8 (1 hour) of MUTCD 1 Per Figure 4C-6 (4 hours) or Figure 4C-8 (1 hour) of MUTCD 1 Determines which warrant to use Safety must be considered in engineering study At least 100 feet from adjacent driveways or streets; at least 300 feet from nearest signal (or STOP sign) control on the street being crossed. Parking should be prohibited 100' before and 20' beyond crosswalk. Per Figure 4F-1 1. May also determine if gaps in traffic are not adequate to allow pedestrian crossing without control N/A N/A Per Figure 4F-2 N/A N/A May be used to determine if a pedestrian Hybrid beacon is appropriate N/A Parking should be prohibited 100' before and 20' beyond crosswalk. Should be coordinated with nearby signals. 1 Figures referenced based on 85th percentile speed > 35 mph.(see Attachment C ) N/A Used to provide warning. Typical Applications include mid-block crosswalks N/A Used to provide warning. Not for use at crosswalks controlled by Yield, STOP, or Signals. Often have maintenance issues. QUARRY CLASP PARK AND CLARK STREET PARKING EVALUATION The Quarry Clasp Park project consists of the acquisition of land for the development of a 5 acre public park at the intersection of Durfee Avenue and Clark Street within the City of Arcadia. With the acquisition of land, a conceptual park design that features equestrian amenities such Letter Report

10 Mr. Jesus "Freddie" Olmos ECORP CONSULTING, INC. May 9, 2016 Page 10 of 12 APPENDIX G as trailer parking, picnic areas, restroom facilities, a potable water source, trail maps, native plantings and interpretive signage will be developed. A concept plan is shown on Exhibit 4. EXHIBIT 4: QUARRY CLASP CONCEPT PLAN The County of Los Angeles Code Chapter 22.52, General Regulations, Part 11, Vehicle Parking Space, requires one automobile parking space for each one-half acre of developed park area up to 15 acres. For a 5-acre park, 10 automobile parking spaces would be required per code. The park will include parking space for approximately five horse trailers and five cars Letter Report

11 Mr. Jesus "Freddie" Olmos ECORP CONSULTING, INC. May 9, 2016 Page 11 of 12 APPENDIX G The Quarry Clasp multi-use trail and bicycle path is intended to connect both a multi-use trail and a combination of Class I bicycle path and Class IV bikeway from the Foothill Transit parking lot on Peck Road to the existing Class I bicycle path on the San Gabriel River. These trails will connect to the extension of the Rio Hondo Class I bicycle path in the Peck Road Water Conservation Park at an existing traffic light on Peck Road at the Foothill Transit Driveway. As shown on Exhibit 5, trail alignment follows the southern edge of the Hanson Quarry, turning south behind the Transit Center and then east to parallel Clark Street. Approximately mid-way towards the San Gabriel River, industrial building development at the quarry edge forces the trails into Clark Street right-of-way. The trail alignments continue on Clark Street through the intersection of Clark Street and Durfee Avenue. EXHIBIT 5: QUARRY CLASP MULTI-USE TRAIL AND BICYCLE PATH On-street parking will be eliminated in the section of Clark Street that will accommodate the two trails. Parking survey was conducted on Clark Street from 7 AM to 7 PM on a weekday and Saturday to determine the impact of elimination of on-street parking on Clark Street. Summary of on-street parking utilization for weekday and Saturday are shown on Tables 7 and 8, respectively. The parking survey data is included in Attachment D Letter Report

12 Mr. Jesus "Freddie" Olmos ECORP CONSULTING, INC. May 9, 2016 Page 12 of 12 APPENDIX G The removal of on-street parking will have more impact on Saturday (weekend) where a maximum of 69 vehicles were parked on both sides of Clark Street. However majority of the vehicles are parked between Foothill Transit Driveway / Kardashian Avenue and Varus Street. The elimination of on-street parking would be needed approximately mid-way towards the San Gabriel River, industrial building development at the quarry edge forces the trails into Clark Street right-of-way, i.e., between Varus Street and Durfee Avenue. A maximum of 14 vehicles were parked on both sides of the Clark Street in the section between Varus Street and Durfee Avenue. Elimination of on-street parking would create a significant parking impact for the vehicles currently being parked in this section of Clark Street. TABLE 7: ON-STREET PARKING ON CLARK STREET, TUESDAY, APRIL 12, 2016 Clark Street Foothill Transit DW to Varus Clark Street Varus to Cogswell Clark Street Cogswell to Durfee TOTALS 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 North Side South Side North Side South Side North Side South Side North Side South Side TOTAL TABLE 8: ON-STREET PARKING ON CLARK STREET, SATURDAY, APRIL 12, 2016 Clark Street Foothill Transit DW to Varus Clark Street Varus to Cogswell Clark Street Cogswell to Durfee TOTALS 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 North Side South Side North Side South Side North Side South Side North Side South Side TOTAL If you have any questions, please contact me directly at (949) , extension 205. Respectfully submitted, URBAN CROSSROADS, INC. Pranesh Tarikere, PE Senior Engineer Letter Report

13

14

15 APPENDIX Table 3 G Project Trip Generation Summary ITE LU AM Peak Hour PM Peak Hour Weekday Land Use Code Units 1 In Out Total In Out Total Daily Project Trip Generation Rates Passive Park 2 AC AM Peak Hour PM Peak Hour Land Use Quantity Units 2 In Out Total In Out Total Daily Project Trip Generation Summary Park AC AC = Acres 2 Trip Generation Source: (Not So) Brief Guide of Vehicular Traffic Generation Rates, April 2002 for Regional Park (Developed).

16 Table 4 Intersection Analysis for Existing (2016) Conditions Intersection Approach Lanes 1 Delay 2 Level of Acceptable Traffic Northbound Southbound Eastbound Westbound (secs.) Service # Intersection Control 3 LOS L T R L T R L T R L T R PM Sat PM Sat 1 E. Lincoln Av. / San Gabriel Bl. TS B A D 2 Rosemead Bl. / San Gabriel Bl./Durfee Av. TS d 1 2 1> D D D 4 Peck Rd. / Foothill Transit Dwy. TS 1 2 d 1 2 d A A D When a right turn is designated, the lane can either be striped or unstriped. To function as a right turn lane there must be sufficient width for right turning vehicles to travel outside the through lanes. Per the 2010 Highway Capacity Manual, overall average intersection delay and level of service are shown for intersections with a traffic signal or all way stop control. For intersections with cross street stop control, the delay and level of service for the worst individual movement (or movements sharing a single lane) are shown. TS = Traffic Signal L = Left; T = Through; R = Right; > = Right Turn Overlap Phasing; d= Defacto Right Turn Lane

17 ATTACHMENT A TRAFFIC COUNTS (2016) Letter Report

18 Counts Unlimited, Inc. PO Box 1178 Corona, CA Location: El Monte Date: 4/12/2016 N/S: Lincoln Avenue Day: TUESDAY E/W: San Gabriel Blvd Project # TURNING MOVEMENT COUNT 4:00 PM 4:15 PM 4:30 PM 4:45 PM 5:00 PM 5:15 PM 5:30 PM 5:45 PM TOTAL VOLUMES: Lincoln Avenue Lincoln Avenue San Gabriel Blvd San Gabriel Blvd Northbound Southbound Eastbound Westbound NL NT NR RTOR SL ST SR RTOR EL ET ER RTOR WL WT WR RTOR TOTAL PM Peak Hr Begins at: 445 PM PEAK VOLUMES: NL NT NR RTOR SL ST SR RTOR EL ET ER RTOR WL WT WR RTOR TOTAL PEAK HR FACTOR:

19 Location: El Monte Date: 4/12/2016 N/S: Lincoln Avenue Day: TUESDAY E/W: San Gabriel Blvd Job # Lincoln Avenue IN OUT N 0 0. San Gabriel Blvd PM San Gabriel Blvd PM PM IN PM IN 1344 Peak Hour Data 530 OUT OUT PM TURNING MOVEMENT COUNT Lincoln Avenue IN OUT Lincoln Avenue / San Gabriel Blvd (Intersection Name) TUESDAY Day 4/12/2016 Date COUNT PERIOD pm 4:00 PM - 6:00 PM PM PEAK HOUR 445 PM

20 Location: El Monte Date: 4/12/2016 N/S: Lincoln Avenue Day: TUESDAY E/W: San Gabriel Blvd Project # PEDESTRIANS 4:00 PM 4:15 PM 4:30 PM 4:45 PM 5:00 PM 5:15 PM 5:30 PM 5:45 PM TOTAL VOLUMES: East Leg West Leg South Leg North Leg Lincoln Avenue San Gabriel Blvd Lincoln Avenue San Gabriel Blvd TOTAL Peak Hr 445

21 Location: El Monte Date: 4/12/2016 N/S: Lincoln Avenue Day: TUESDAY E/W: San Gabriel Blvd Project # BICYCLES 4:00 PM 4:15 PM 4:30 PM 4:45 PM 5:00 PM 5:15 PM 5:30 PM 5:45 PM TOTAL VOLUMES: East Leg West Leg South Leg North Leg Lincoln Avenue San Gabriel Blvd Lincoln Avenue San Gabriel Blvd TOTAL Peak Hr

22 Counts Unlimited, Inc. PO Box 1178 Corona, CA Location: El Monte Date: 4/12/2016 N/S: Rosemead Boulevard Day: TUESDAY E/W: San Gabriel Blvd / Durfee Project # TURNING MOVEMENT COUNT 4:00 PM 4:15 PM 4:30 PM 4:45 PM 5:00 PM 5:15 PM 5:30 PM 5:45 PM TOTAL VOLUMES: Rosemead Boulevard Rosemead Boulevard San Gabriel Blvd / Durfee Ave San Gabriel Blvd / Durfee Ave Northbound Southbound Eastbound Westbound NL NT NR RTOR SL ST SR RTOR EL ET ER RTOR WL WT WR RTOR TOTAL PM Peak Hr Begins at: 500 PM PEAK VOLUMES: NL NT NR RTOR SL ST SR RTOR EL ET ER RTOR WL WT WR RTOR TOTAL PEAK HR FACTOR:

23 Location: El Monte Date: 4/12/2016 N/S: Rosemead Boulevard Day: TUESDAY E/W: San Gabriel Blvd / Durfee Av Job # IN OUT N Rosemead Boulevard San Gabriel Blvd / Durfee Ave PM San Gabriel Blvd / Durfee Ave PM PM IN PM IN 709 Peak Hour Data 151 OUT OUT PM TURNING MOVEMENT COUNT Rosemead Boulevard IN OUT Rosemead Boulevard / San Gabriel Blvd / Durfee Ave (Intersection Name) TUESDAY Day COUNT PERIOD 4/12/2016 Date pm 4:00 PM - 6:00 PM PM PEAK HOUR 500 PM

24 Location: El Monte Date: 4/12/2016 N/S: Rosemead Boulevard Day: TUESDAY E/W: San Gabriel Blvd / Durfee Ave Project # PEDESTRIANS 4:00 PM 4:15 PM 4:30 PM 4:45 PM 5:00 PM 5:15 PM 5:30 PM 5:45 PM TOTAL VOLUMES: East Leg West Leg South Leg North Leg Rosemead Boulevard San Gabriel Blvd / Durfee Ave Rosemead Boulevard San Gabriel Blvd / Durfee Ave TOTAL Peak Hr

25 Location: El Monte Date: 4/12/2016 N/S: Rosemead Boulevard Day: TUESDAY E/W: San Gabriel Blvd / Durfee Ave Project # BICYCLES 4:00 PM 4:15 PM 4:30 PM 4:45 PM 5:00 PM 5:15 PM 5:30 PM 5:45 PM TOTAL VOLUMES: East Leg West Leg South Leg North Leg Rosemead Boulevard San Gabriel Blvd / Durfee Ave Rosemead Boulevard San Gabriel Blvd / Durfee Ave TOTAL Peak Hr

26 City of El Monte Peck Road N/ Foothill Transit Driveway 24 Hour Directional Volume Count APPENDIX G Counts Unlimited, Inc PO Box 1178 Corona, CA Phone: counts@countsunlimited.com Page 1 ELMPENFO Site Code: Start 4/12/2016 Northbound Hour Totals Southbound Hour Totals Combined Totals Time Tue Morning Afternoon Morning Afternoon Morning Afternoon Morning Afternoon Morning Afternoon 12: : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : Total Combined Total AM Peak - 07: : Vol P.H.F PM Peak : : Vol P.H.F Percentag 38.9% 61.1% 38.4% 61.6% e ADT/AADT ADT 23,386 AADT 23,386

27 Counts Unlimited, Inc. PO Box 1178 Corona, CA Location: El Monte Date: 4/16/2016 N/S: Lincoln Avenue Day: SATURDAY E/W: San Gabriel Blvd Project # TURNING MOVEMENT COUNT 7:00 AM 7:15 AM 7:30 AM 7:45 AM 8:00 AM 8:15 AM 8:30 AM 8:45 AM TOTAL VOLUMES: Lincoln Avenue Lincoln Avenue San Gabriel Blvd San Gabriel Blvd Northbound Southbound Eastbound Westbound NL NT NR RTOR SL ST SR RTOR EL ET ER RTOR WL WT WR RTOR TOTAL AM Peak Hr Begins at: 800 AM PEAK VOLUMES: NL NT NR RTOR SL ST SR RTOR EL ET ER RTOR WL WT WR RTOR TOTAL PEAK HR FACTOR:

28 Location: El Monte Date: 4/16/2016 N/S: Lincoln Avenue Day: SATURDAY E/W: San Gabriel Blvd Job # Lincoln Avenue IN OUT N 0 0. San Gabriel Blvd AM San Gabriel Blvd AM AM IN AM IN 287 Peak Hour Data 253 OUT OUT AM TURNING MOVEMENT COUNT Lincoln Avenue IN OUT Lincoln Avenue / San Gabriel Blvd (Intersection Name) SATURDAY Day 4/16/2016 Date COUNT PERIOD am 7:00 AM - 9:00 AM AM PEAK HOUR 800 AM

29 Location: El Monte Date: 4/16/2016 N/S: Lincoln Avenue Day: SATURDAY E/W: San Gabriel Blvd Project # PEDESTRIANS 7:00 AM 7:15 AM 7:30 AM 7:45 AM 8:00 AM 8:15 AM 8:30 AM 8:45 AM TOTAL VOLUMES: East Leg West Leg South Leg North Leg Lincoln Avenue San Gabriel Blvd Lincoln Avenue San Gabriel Blvd TOTAL Peak Hr 80 0

30 Location: El Monte Date: 4/16/2016 N/S: Lincoln Avenue Day: SATURDAY E/W: San Gabriel Blvd Project # BICYCLES 7:00 AM 7:15 AM 7:30 AM 7:45 AM 8:00 AM 8:15 AM 8:30 AM 8:45 AM TOTAL VOLUMES: East Leg West Leg South Leg North Leg Lincoln Avenue San Gabriel Blvd Lincoln Avenue San Gabriel Blvd TOTAL Peak Hr

31 Counts Unlimited, Inc. PO Box 1178 Corona, CA Location: El Monte Date: 4/16/2016 N/S: Rosemead Boulevard Day: SATURDAY E/W: San Gabriel Blvd / Durfee Project # TURNING MOVEMENT COUNT 7:00 AM 7:15 AM 7:30 AM 7:45 AM 8:00 AM 8:15 AM 8:30 AM 8:45 AM TOTAL VOLUMES: Rosemead Boulevard Rosemead Boulevard San Gabriel Blvd / Durfee Ave San Gabriel Blvd / Durfee Ave Northbound Southbound Eastbound Westbound NL NT NR RTOR SL ST SR RTOR EL ET ER RTOR WL WT WR RTOR TOTAL AM Peak Hr Begins at: 800 AM PEAK VOLUMES: NL NT NR RTOR SL ST SR RTOR EL ET ER RTOR WL WT WR RTOR TOTAL PEAK HR FACTOR:

32 Location: El Monte Date: 4/16/2016 N/S: Rosemead Boulevard Day: SATURDAY E/W: San Gabriel Blvd / Durfee Av Job # IN OUT N Rosemead Boulevard San Gabriel Blvd / Durfee Ave AM San Gabriel Blvd / Durfee Ave AM AM IN AM IN 86 Peak Hour Data 77 OUT OUT AM TURNING MOVEMENT COUNT Rosemead Boulevard IN OUT Rosemead Boulevard / San Gabriel Blvd / Durfee Ave (Intersection Name) SATURDAY Day COUNT PERIOD 4/16/2016 Date am 7:00 AM - 9:00 AM AM PEAK HOUR 800 AM

33 Location: El Monte Date: 4/16/2016 N/S: Rosemead Boulevard Day: SATURDAY E/W: San Gabriel Blvd / Durfee Ave Project # PEDESTRIANS 7:00 AM 7:15 AM 7:30 AM 7:45 AM 8:00 AM 8:15 AM 8:30 AM 8:45 AM TOTAL VOLUMES: East Leg West Leg South Leg North Leg Rosemead Boulevard San Gabriel Blvd / Durfee Ave Rosemead Boulevard San Gabriel Blvd / Durfee Ave TOTAL Peak Hr

34 Location: El Monte Date: 4/16/2016 N/S: Rosemead Boulevard Day: SATURDAY E/W: San Gabriel Blvd / Durfee Ave Project # BICYCLES 7:00 AM 7:15 AM 7:30 AM 7:45 AM 8:00 AM 8:15 AM 8:30 AM 8:45 AM TOTAL VOLUMES: East Leg West Leg South Leg North Leg Rosemead Boulevard San Gabriel Blvd / Durfee Ave Rosemead Boulevard San Gabriel Blvd / Durfee Ave TOTAL Peak Hr

35 City of El Monte Peck Road N/ Foothill Transit Driveway 24 Hour Directional Volume Count APPENDIX G Counts Unlimited, Inc PO Box 1178 Corona, CA Phone: counts@countsunlimited.com Page 1 ELMPENFOSAT Site Code: Start 4/16/2016 Northbound Hour Totals Southbound Hour Totals Combined Totals Time Sat Morning Afternoon Morning Afternoon Morning Afternoon Morning Afternoon Morning Afternoon 12: : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : Total Combined Total AM Peak - 10: : Vol P.H.F PM Peak : : Vol P.H.F Percentag 37.6% 62.4% 32.2% 67.8% e ADT/AADT ADT 19,956 AADT 19,956

36 City of El Monte Rosemead Boulevard At SCE Pathway 24 Hour Directional Volume Count APPENDIX G Counts Unlimited, Inc PO Box 1178 Corona, CA Phone: counts@countsunlimited.com Page 1 ELMROSCE Site Code: Start 4/12/2016 Northbound Hour Totals Southbound Hour Totals Combined Totals Time Tue Morning Afternoon Morning Afternoon Morning Afternoon Morning Afternoon Morning Afternoon 12: : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : Total Combined Total AM Peak - 06: : Vol P.H.F PM Peak : : Vol P.H.F Percentag 42.5% 57.5% 35.3% 64.7% e ADT/AADT ADT 27,071 AADT 27,071

37 City of El Monte Rosemead Boulevard At SCE Pathway 24 Hour Directional Volume Count APPENDIX G Counts Unlimited, Inc PO Box 1178 Corona, CA Phone: counts@countsunlimited.com Page 1 ELMROSCESAT Site Code: Start 4/16/2016 Northbound Hour Totals Southbound Hour Totals Combined Totals Time Sat Morning Afternoon Morning Afternoon Morning Afternoon Morning Afternoon Morning Afternoon 12: : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : : Total Combined Total AM Peak - 10: : Vol P.H.F PM Peak : : Vol P.H.F Percentag 33.7% 66.3% 33.0% 67.0% e ADT/AADT ADT 24,603 AADT 24,603

38 Counts Unlimited, Inc. PO Box 1178 Corona, CA Location: El Monte Date: 4/12/2016 N/S: Peck Road Day: TUESDAY E/W: Foothill Transit Driveway Project # TURNING MOVEMENT COUNT 4:00 PM 4:15 PM 4:30 PM 4:45 PM 5:00 PM 5:15 PM 5:30 PM 5:45 PM TOTAL VOLUMES: Peck Road Peck Road Foothill Transit Driveway Foothill Transit Driveway Northbound Southbound Eastbound Westbound NL NT NR RTOR SL ST SR RTOR EL ET ER RTOR WL WT WR RTOR TOTAL PM Peak Hr Begins at: 430 PM PEAK VOLUMES: NL NT NR RTOR SL ST SR RTOR EL ET ER RTOR WL WT WR RTOR TOTAL PEAK HR FACTOR:

39 Location: El Monte Date: 4/12/2016 N/S: Peck Road Day: TUESDAY E/W: Foothill Transit Driveway Job # IN OUT N Peck Road Foothill Transit Driveway PM Foothill Transit Driveway PM PM IN PM IN 0 Peak Hour Data 0 OUT OUT PM TURNING MOVEMENT COUNT Peck Road IN OUT Peck Road / Foothill Transit Driveway (Intersection Name) TUESDAY Day 4/12/2016 Date COUNT PERIOD pm 4:00 PM - 6:00 PM PM PEAK HOUR 430 PM

40 Location: El Monte Date: 4/12/2016 N/S: Peck Road Day: TUESDAY E/W: Foothill Transit Driveway Project # PEDESTRIANS 4:00 PM 4:15 PM 4:30 PM 4:45 PM 5:00 PM 5:15 PM 5:30 PM 5:45 PM TOTAL VOLUMES: East Leg West Leg South Leg North Leg Peck Road Foothill Transit Driveway Peck Road Foothill Transit Driveway TOTAL Peak Hr

41 Location: El Monte Date: 4/12/2016 N/S: Peck Road Day: TUESDAY E/W: Foothill Transit Driveway Project # BICYCLES 4:00 PM 4:15 PM 4:30 PM 4:45 PM 5:00 PM 5:15 PM 5:30 PM 5:45 PM TOTAL VOLUMES: East Leg West Leg South Leg North Leg Peck Road Foothill Transit Driveway Peck Road Foothill Transit Driveway TOTAL Peak Hr

42 Counts Unlimited, Inc. PO Box 1178 Corona, CA Location: El Monte Date: 4/16/2016 N/S: Peck Road Day: SATURDAY E/W: Foothill Transit Driveway Project # TURNING MOVEMENT COUNT 7:00 AM 7:15 AM 7:30 AM 7:45 AM 8:00 AM 8:15 AM 8:30 AM 8:45 AM TOTAL VOLUMES: Peck Road Peck Road Foothill Transit Driveway Foothill Transit Driveway Northbound Southbound Eastbound Westbound NL NT NR RTOR SL ST SR RTOR EL ET ER RTOR WL WT WR RTOR TOTAL AM Peak Hr Begins at: 800 AM PEAK VOLUMES: NL NT NR RTOR SL ST SR RTOR EL ET ER RTOR WL WT WR RTOR TOTAL PEAK HR FACTOR:

43 Location: El Monte Date: 4/16/2016 N/S: Peck Road Day: SATURDAY E/W: Foothill Transit Driveway Job # IN OUT N Peck Road Foothill Transit Driveway AM Foothill Transit Driveway AM AM IN 2 0 AM 8 14 IN 0 Peak Hour Data 0 OUT OUT AM TURNING MOVEMENT COUNT Peck Road IN OUT Peck Road / Foothill Transit Driveway (Intersection Name) SATURDAY Day 4/16/2016 Date COUNT PERIOD am 7:00 AM - 9:00 AM AM PEAK HOUR 800 AM

44 Location: El Monte Date: 4/16/2016 N/S: Peck Road Day: SATURDAY E/W: Foothill Transit Driveway Project # PEDESTRIANS 7:00 AM 7:15 AM 7:30 AM 7:45 AM 8:00 AM 8:15 AM 8:30 AM 8:45 AM TOTAL VOLUMES: East Leg West Leg South Leg North Leg Peck Road Foothill Transit Driveway Peck Road Foothill Transit Driveway TOTAL Peak Hr

45 Location: El Monte Date: 4/16/2016 N/S: Peck Road Day: SATURDAY E/W: Foothill Transit Driveway Project # BICYCLES 7:00 AM 7:15 AM 7:30 AM 7:45 AM 8:00 AM 8:15 AM 8:30 AM 8:45 AM TOTAL VOLUMES: East Leg West Leg South Leg North Leg Peck Road Foothill Transit Driveway Peck Road Foothill Transit Driveway TOTAL Peak Hr

46 ATTACHMENT B EXISTING (2016) INTERSECTION ANALYSIS WORKSHEETS Letter Report

47 Timings Emerald Necklace (JN 07442) 1: E. Lincoln Av. & San Gabriel Bl. 5/5/2016 Lane Group EBT EBR WBL WBT NBL NBR Lane Configurations Traffic Volume (vph) Future Volume (vph) Turn Type NA Perm Perm NA Prot Perm Protected Phases Permitted Phases Detector Phase Switch Phase Minimum Initial (s) Minimum Split (s) Total Split (s) Total Split (%) 76.0% 76.0% 76.0% 76.0% 24.0% 24.0% Yellow Time (s) All-Red Time (s) Lost Time Adjust (s) Total Lost Time (s) Lead/Lag Lead-Lag Optimize? Recall Mode C-Max C-Max C-Max C-Max None None Act Effct Green (s) Actuated g/c Ratio v/c Ratio Control Delay Queue Delay Total Delay LOS A A E A D E Approach Delay Approach LOS A C E Intersection Summary Cycle Length: 90 Actuated Cycle Length: 90 Offset: 0 (0%), Referenced to phase 2:EBT and 6:WBTL, Start of Yellow Natural Cycle: 90 Control Type: Actuated-Coordinated Maximum v/c Ratio: 0.99 Intersection Signal Delay: 20.4 Intersection LOS: C Intersection Capacity Utilization 70.6% ICU Level of Service C Analysis Period (min) 15 Splits and Phases: 1: E. Lincoln Av. & San Gabriel Bl. Existing (2016) Conditions - Weekday PM Peak Hour Synchro 9 Report Urban Crossroads, Inc. Page 1

48 HCM 2010 Signalized Intersection Summary Emerald Necklace (JN 07442) 1: E. Lincoln Av. & San Gabriel Bl. 5/5/2016 Movement EBT EBR WBL WBT NBL NBR Lane Configurations Traffic Volume (veh/h) Future Volume (veh/h) Number Initial Q (Qb), veh 0 Ped-Bike Adj(A_pbT) Parking Bus, Adj Adj Sat Flow, veh/h/ln Adj Flow Rate, veh/h Adj No. of Lanes Peak Hour Factor Percent Heavy Veh, % Cap, veh/h Arrive On Green Sat Flow, veh/h Grp Volume(v), veh/h Grp Sat Flow(s),veh/h/ln Q Serve(g_s), s Cycle Q Clear(g_c), s Prop In Lane Lane Grp Cap(c), veh/h V/C Ratio(X) Avail Cap(c_a), veh/h HCM Platoon Ratio Upstream Filter(I) Uniform Delay (d), s/veh Incr Delay (d2), s/veh Initial Q Delay(d3),s/veh %ile BackOfQ(50%),veh/ln LnGrp Delay(d),s/veh LnGrp LOS A A C A D E Approach Vol, veh/h Approach Delay, s/veh Approach LOS A B D Timer Assigned Phs Phs Duration (G+Y+Rc), s Change Period (Y+Rc), s Max Green Setting (Gmax), s Max Q Clear Time (g_c+i1), s Green Ext Time (p_c), s Intersection Summary HCM 2010 Ctrl Delay 12.4 HCM 2010 LOS B Existing (2016) Conditions - Weekday PM Peak Hour Synchro 9 Report Urban Crossroads, Inc. Page 2

Winnetka Avenue Bike Lanes Traffic Impact Analysis

Winnetka Avenue Bike Lanes Traffic Impact Analysis Winnetka Avenue Bike Lanes Traffic Impact Analysis January 4, 2019 Prepared by City of Los Angeles Department of Transportation Active Transportation Division Winnetka Ave Bike Lanes Traffic Impact Analysis

More information

BUCKLEY ANNEX REDEVELOPMENT PLAN TRANSPORTATION ANALYSIS ADDENDUM

BUCKLEY ANNEX REDEVELOPMENT PLAN TRANSPORTATION ANALYSIS ADDENDUM BUCKLEY ANNEX REDEVELOPMENT PLAN TRANSPORTATION ANALYSIS ADDENDUM Prepared for: City and County of Denver Prepared by: Contact: Brian Bern, P.E., PTOE 303.572.0200 On Behalf of: Lowry Redevelopment Authority

More information

SR 104/Paradise Bay-Shine Road Intersection Safety Improvements Intersection Control Evaluation

SR 104/Paradise Bay-Shine Road Intersection Safety Improvements Intersection Control Evaluation SR 104/Paradise Bay-Shine Road Intersection Safety Improvements Intersection Control Evaluation Background and Project Needs SR 104 is functionally classified as a rural-principal arterial. It is a limited

More information

MEMORANDUM. Saint Edward Ballfields Traffic and Parking Analysis (Updated)

MEMORANDUM. Saint Edward Ballfields Traffic and Parking Analysis (Updated) MEMORANDUM Date: May 26, 2016 To: From: Subject: Debbie Bent and Kris Overleese, City of Kenmore Kendra Breiland and Sarah Keenan, Fehr & Peers Saint Edward Ballfields Traffic and Parking Analysis (Updated)

More information

1 st Street Intersection Study

1 st Street Intersection Study TRAFFIC ENGINEERING ASSISTANCE PROGRAM 1 st Street Intersection Study Prepared for: City of Independence In Cooperation With: Iowa Department of Transportation & Iowa Department of Public Safety Governor

More information

APPENDIX A LEVEL OF SERVICE CONCEPTS, ANALYSIS METHODOLOGIES,STANDARDS OF SIGNIFICANCE

APPENDIX A LEVEL OF SERVICE CONCEPTS, ANALYSIS METHODOLOGIES,STANDARDS OF SIGNIFICANCE APPENDIX A LEVEL OF SERVICE CONCEPTS, ANALYSIS METHODOLOGIES,STANDARDS OF SIGNIFICANCE Roadway Segment Level of Service Definitions LOS V/C Congestion/Delay Traffic Description (Used for surface streets,

More information

Aldridge Transportation Consultants, LLC Advanced Transportation Planning and Traffic Engineering

Aldridge Transportation Consultants, LLC Advanced Transportation Planning and Traffic Engineering Aldridge Transportation Consultants, LLC Advanced Transportation Planning and Traffic Engineering John M.W. Aldridge, PE, PTOE, AICP 1082 Chimney Rock Road Colorado Registered Professional Engineer Highlands

More information

TECHNICAL MEMORANDUM

TECHNICAL MEMORANDUM TECHNICAL MEMORANDUM TO: Merrimack Valley Metropolitan Planning Organization FROM: James Terlizzi, P.E., Transportation Planning Engineer DATE: March 6, 2017 SUBJECT: Further analysis of the recommendations

More information

Traffic Analysis For Approved Uses within the St. Lucie West DRI Aldi Port St. Lucie, FL Prepared for: Bohler Engineering, LLC 1000 Corporate Drive Suite 250 Fort Lauderdale, FL 33334 Prepared by: 10795

More information

Aldridge Transportation Consultants, LLC Advanced Transportation Planning and Traffic Engineering

Aldridge Transportation Consultants, LLC Advanced Transportation Planning and Traffic Engineering Aldridge Transportation Consultants, LLC Advanced Transportation Planning and Traffic Engineering John M.W. Aldridge, PE, PTOE, AICP 1082 Chimney Rock Road Colorado Registered Professional Engineer Highlands

More information

Provide an overview of the development proposal including projected site traffic volumes;

Provide an overview of the development proposal including projected site traffic volumes; December 19, 2013 File: 163600935 Attention: Troy Elliott Carl Elliott Limited 15-1831 Robertson Road PO Box 11117 Nepean, Ontario K1H 7T8 Dear Mr. Elliott, Reference: 2235 and 2265 Robertson Road Transportation

More information

TRAFFIC IMPACT ANALYSIS FOR. RESIDENCE INN PROJECT Davis, CA. Prepared For: JACKSON PROPERTIES 155 Cadillac Drive, Suite 100 Sacramento, CA 95825

TRAFFIC IMPACT ANALYSIS FOR. RESIDENCE INN PROJECT Davis, CA. Prepared For: JACKSON PROPERTIES 155 Cadillac Drive, Suite 100 Sacramento, CA 95825 TRAFFIC IMPACT ANALYSIS FOR RESIDENCE INN PROJECT Davis, CA Prepared For: JACKSON PROPERTIES 155 Cadillac Drive, Suite 100 Sacramento, CA 95825 Prepared By: KD Anderson & Associates, Inc. 3853 Taylor Road,

More information

Bennett Pit. Traffic Impact Study. J&T Consulting, Inc. Weld County, Colorado. March 3, 2017

Bennett Pit. Traffic Impact Study. J&T Consulting, Inc. Weld County, Colorado. March 3, 2017 Bennett Pit Traffic Impact Study J&T Consulting, Inc. Weld County, Colorado March 3, 217 Prepared By: Sustainable Traffic Solutions, Inc. http://www.sustainabletrafficsolutions.com/ Joseph L. Henderson,

More information

Addendum to Traffic Impact Analysis for Port Marigny Site Mandeville, LA

Addendum to Traffic Impact Analysis for Port Marigny Site Mandeville, LA Addendum to Traffic Impact Analysis for Port Marigny Site Mandeville, LA (St. Tammany Parish Mandeville, LA) Prepared For The Pittman Companies Michael N Pittman, MD 328 East Boston St Covington, LA 70433

More information

Re: Residential Development - Ogilvie/Cummings Transportation Overview

Re: Residential Development - Ogilvie/Cummings Transportation Overview 1223 Michael Street, Suite 100, Ottawa, ON K1J 7T2 Tel: 613.738.4160 Fax: 613.739.7105 www.delcan.com March 28, 2012 OUR REF: TO3088TOY Barry J. Hobin & Architects 63 Pamilla Street Ottawa, ON K1S 3K7

More information

ZINFANDEL LANE / SILVERADO TRAIL INTERSECTION TRAFFIC ANALYSIS

ZINFANDEL LANE / SILVERADO TRAIL INTERSECTION TRAFFIC ANALYSIS ZINFANDEL LANE / SILVERADO TRAIL INTERSECTION TRAFFIC ANALYSIS UPDATED TRAFFIC STUDY FOR THE PROPOSED RAYMOND VINEYARDS WINERY USE PERMIT MODIFICATION #P11-00156 AUGUST 5, 2014 PREPARED BY: OMNI-MEANS,

More information

Appendix E: Emission Reduction Calculations

Appendix E: Emission Reduction Calculations Derr Road and Home Road Conversion Feasibility Study Springfield, OH Appendix E: Emission Reduction Calculations Derr Road and Home Road Conversion Feasibility Study Springfield, OH Emission Reduction

More information

Re: Cyrville Road Car Dealership

Re: Cyrville Road Car Dealership 1223 Michael Street, Suite 100, Ottawa, ON K1J 7T2 Tel: 613.738.4160 Fax: 613.739.7105 www.delcan.com February 25, 2013 OUR REF: TO3098TOE Mark Motors of Ottawa 611 Montreal Road Ottawa, ON K1K 0T8 Attention:

More information

JOHNSON RANCH RAPID CITY, SOUTH DAKOTA TRAFFIC IMPACT ANALYSIS

JOHNSON RANCH RAPID CITY, SOUTH DAKOTA TRAFFIC IMPACT ANALYSIS JOHNSON RANCH RAPID CITY, SOUTH DAKOTA TRAFFIC IMPACT ANALYSIS Prepared for: KTM Design Solutions 528 Kansas City Street, Suite 1 Rapid City, SD 57701 Prepared by: Felsburg Holt & Ullevig 6300 South Syracuse

More information

Prescott Plaza Traffic Impact Analysis APPENDIX 1.1: APPROVED TRAFFIC STUDY SCOPING AGREEMENT TIA Report.docx

Prescott Plaza Traffic Impact Analysis APPENDIX 1.1: APPROVED TRAFFIC STUDY SCOPING AGREEMENT TIA Report.docx Prescott Plaza Traffic Impact Analysis APPENDIX 1.1: APPROVED TRAFFIC STUDY SCOPING AGREEMENT 11897-05 TIA Report.docx Prescott Plaza Traffic Impact Analysis This page is intentionally left blank 11897-05

More information

Final Technical Report US 17 Corridor Study Update (Market Street Road Diet)

Final Technical Report US 17 Corridor Study Update (Market Street Road Diet) Market Street Road Diet Wilmington, NC 2016 Final Technical Report US 17 Corridor Study Update (Market Street Road Diet) Wilmington, NC Parsons Brinckerhoff January 2016 FINAL TECHNICAL REPORT US 17 Corridor

More information

MURRIETA APARTMENTS TRAFFIC IMPACT ANALYSIS CITY OF MURRIETA, CALIFORNIA

MURRIETA APARTMENTS TRAFFIC IMPACT ANALYSIS CITY OF MURRIETA, CALIFORNIA MURRIETA APARTMENTS TRAFFIC IMPACT ANALYSIS CITY OF MURRIETA, CALIFORNIA SEPTEMBER 20, 2012 Prepared for: Golden Eagle Multi-Family Properties, LLC 6201 Oak Canyon Rd., Suite 250 Irvine, CA 92618 Prepared

More information

886 March Road McDonald's Transportation Study

886 March Road McDonald's Transportation Study McDonald's Restaurants of Canada Limited March 2013 886 March Road McDonald's Transportation Study Submitted by: HDR Corporation 100 York Boulevard, Suite 300 Richmond Hill, ON L4B 1J8 (905) 882-4100 www.hdrinc.com

More information

Table 1 - Land Use Comparisons - Proposed King s Wharf Development. Retail (SF) Office (SF) 354 6,000 10, Land Uses 1

Table 1 - Land Use Comparisons - Proposed King s Wharf Development. Retail (SF) Office (SF) 354 6,000 10, Land Uses 1 Ref. No. 171-6694 Phase 2 November 23, 217 Mr. David Quilichini, Vice President Fares & Co. Developments Inc. 31 Place Keelson Sales Centre DARTMOUTH NS B2Y C1 Sent Via Email to David@faresinc.com RE:

More information

HONDA DEALERSHIP LAKE ELSINORE, CALIFORNIA. Prepared by:

HONDA DEALERSHIP LAKE ELSINORE, CALIFORNIA. Prepared by: LOS ANGELES 21 S. Figueroa St, Suite 24 Los Angeles, CA 912 213.337.368 Fax :213.337.3679 ONTARIO 4141 E. Inland Empire Blvd, Suite 25 Ontario, CA 91764 99.481.575 Fax :99.481.5757 SAN DIEGO 6 B St, Suite

More information

L1TILE BEARS DAY CARE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO MAY Prepared for:

L1TILE BEARS DAY CARE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO MAY Prepared for: L1TILE BEARS DAY CARE TRANSPORTATION IMPACT STUDY FORT COLLINS, COLORADO MAY 2012 Prepared for: Hillside Construction, Inc. 216 Hemlock Street, Suite B Fort Collins, CO 80534 Prepared by: DELICH ASSOCIATES

More information

Weaver Road Senior Housing Traffic Impact Analysis

Weaver Road Senior Housing Traffic Impact Analysis Gibson Traffic Consultants, Inc. 2813 Rockefeller Avenue Suite B Everett, WA 9821 425.339.8266 Weaver Road Senior Housing Traffic Impact Analysis Jurisdiction: City of Snohomish January 218 GTC #17-37

More information

LAWRENCE TRANSIT CENTER LOCATION ANALYSIS 9 TH STREET & ROCKLEDGE ROAD / 21 ST STREET & IOWA STREET LAWRENCE, KANSAS

LAWRENCE TRANSIT CENTER LOCATION ANALYSIS 9 TH STREET & ROCKLEDGE ROAD / 21 ST STREET & IOWA STREET LAWRENCE, KANSAS LAWRENCE TRANSIT CENTER LOCATION ANALYSIS 9 TH STREET & ROCKLEDGE ROAD / 21 ST STREET & IOWA STREET LAWRENCE, KANSAS TRAFFIC IMPACT STUDY FEBRUARY 214 OA Project No. 213-542 TABLE OF CONTENTS 1. INTRODUCTION...

More information

Traffic Impact Analysis Farmington Center Village

Traffic Impact Analysis Farmington Center Village Traffic Impact Analysis Farmington Center Village Route 4 (Farmington Avenue) Farmington, Connecticut Prepared for: The Town of Farmington, CT Prepared By: BL Companies Meriden, Connecticut December 2016

More information

LOST LAKE CORRIDOR REVIEW

LOST LAKE CORRIDOR REVIEW LOST LAKE CORRIDOR REVIEW Prepared for: Prepared by: Broadview Developments Inc. c/o Westbrook Consulting Watt Consulting Group Our File: 2064.B01 Date: October 31, 2016 TABLE OF CONTENTS 1.0 INTRODUCTION...

More information

MERIVALE PRIORITY SQUARE 2852 MERIVALE ROAD CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for: ONT Inc. 25 Winding Way Nepean, Ontario K2C 3H1

MERIVALE PRIORITY SQUARE 2852 MERIVALE ROAD CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for: ONT Inc. 25 Winding Way Nepean, Ontario K2C 3H1 MERIVALE PRIORITY SQUARE 2852 MERIVALE ROAD CITY OF OTTAWA TRANSPORTATION BRIEF Prepared for: 2190986ONT Inc. 25 Winding Way Nepean, Ontario K2C 3H1 October 6, 2010 110-502 Report_1.doc D. J. Halpenny

More information

Sugarland Crossing Gwinnett County, Georgia

Sugarland Crossing Gwinnett County, Georgia Sugarland Crossing Gwinnett County, Georgia S IGNAL W ARRANT A NALYSIS For the Intersection of: Sugarloaf Parkway / Richards Middle School Driveway / Sugarland Crossing Main Site Driveway Prepared for:

More information

EXECUTIVE SUMMARY. The following is an outline of the traffic analysis performed by Hales Engineering for the traffic conditions of this project.

EXECUTIVE SUMMARY. The following is an outline of the traffic analysis performed by Hales Engineering for the traffic conditions of this project. EXECUTIVE SUMMARY This study addresses the traffic impacts associated with the proposed Shopko redevelopment located in Sugarhouse, Utah. The Shopko redevelopment project is located between 1300 East and

More information

TRAFFIC DATA. Existing Derousse Ave./River Rd. AM LOS Analysis Existing Derousse Ave./River Rd. PM LOS Analysis

TRAFFIC DATA. Existing Derousse Ave./River Rd. AM LOS Analysis Existing Derousse Ave./River Rd. PM LOS Analysis Appendix E NJ TRANSIT Pennsauken Junction Transit Center and Park & Ride RiverLINE and Atlantic City Line Pennsauken Township, Camden County, New Jersey TRAFFIC DATA Background Traffic Information for

More information

LATSON INTERCHANGE DEVELOPMENT TRAFFIC STUDIES. Genoa Township, Livingston County, MI

LATSON INTERCHANGE DEVELOPMENT TRAFFIC STUDIES. Genoa Township, Livingston County, MI LATSON INTERCHANGE DEVELOPMENT TRAFFIC STUDIES Genoa Township, Livingston County, MI DRAFT TRAFFIC STUDY FOR I-96 AT LATSON RD INTERCHANGE Livingston County CS 47065 JN 101622C Submitted to: Michigan Department

More information

Proposed Office Building Traffic Impact Study Chicago Avenue Evanston, Illinois

Proposed Office Building Traffic Impact Study Chicago Avenue Evanston, Illinois Proposed Office Building Traffic Impact Study 1714-1720 Chicago Avenue Evanston, Illinois Prepared For: HOLABIRD & ROOT, LLC Prepared by: Eriksson Engineering Associates, Ltd. 145 Commerce Drive, Ste A,

More information

INTERCHANGE OPERTIONS STUDY Interstate 77 / Wallings Road Interchange

INTERCHANGE OPERTIONS STUDY Interstate 77 / Wallings Road Interchange INTERCHANGE OPERTIONS STUDY Interstate 77 / Wallings Road Interchange City of Broadview Heights, Cuyahoga County, Ohio Prepared For: City of Broadview Heights Department of Engineering 9543 Broadview Road

More information

MEMO. McCORMICK RANKIN CORPORATION. File FROM: Keyur Shah DATE: February 1, 2010 COPIES: OUR FILE: SUBJECT: TO:

MEMO. McCORMICK RANKIN CORPORATION. File FROM: Keyur Shah DATE: February 1, 2010 COPIES: OUR FILE: SUBJECT: TO: McCORMICK RANKIN CORPORATION 2655 North Sheridan Way Mississauga, Ontario, L5K 2P8 Tel: (905)823-8500 Fax: (905) 823-8503 E-mail: mrc@mrc.ca Website: www.mrc.ca MEMO TO: File FROM: Keyur Shah DATE: February

More information

Salvini Consulting Inc. 459 Deer Ridge Drive Kitchener, ON N2P 0A November 8, 2017 Revised December 20, 2017

Salvini Consulting Inc. 459 Deer Ridge Drive Kitchener, ON N2P 0A November 8, 2017 Revised December 20, 2017 Salvini Consulting Inc. 459 Deer Ridge Drive Kitchener, ON N2P 0A7 519-591-0426 November 8, 2017 Revised December 20, 2017 Laurie Wills, PEng Deputy Director of Public Works Town of Cobourg 740 Division

More information

4.14 TRANSPORTATION AND CIRCULATION

4.14 TRANSPORTATION AND CIRCULATION 4.14 TRANSPORTATION AND CIRCULATION 4.14.1 Summary Table 4.14-1 summarizes the identified environmental impacts, proposed mitigation measures, and residual impacts of the proposed project with regard to

More information

Alpine Highway to North County Boulevard Connector Study

Alpine Highway to North County Boulevard Connector Study Alpine Highway to North County Boulevard Connector Study prepared by Avenue Consultants March 16, 2017 North County Boulevard Connector Study March 16, 2017 Table of Contents 1 Summary of Findings... 1

More information

June 21, Mr. Jeff Mark The Landhuis Company 212 North Wahsatch Avenue, Suite 301. Colorado Springs, CO 80903

June 21, Mr. Jeff Mark The Landhuis Company 212 North Wahsatch Avenue, Suite 301. Colorado Springs, CO 80903 LSC TRANSPORTATION CONSULTANTS, INC. 545 East Pikes Peak Avenue, Suite 210 Colorado Springs, CO 80903 (719) 633-2868 FAX (719) 633-5430 E-mail: lsc@lsctrans.com Website: http://www.lsctrans.com June 21,

More information

Barrhaven Honda Dealership. Dealership Drive, Ottawa, ON. Transportation Brief

Barrhaven Honda Dealership. Dealership Drive, Ottawa, ON. Transportation Brief Barrhaven Honda Dealership Dealership Drive, Ottawa, ON Transportation Brief Prepared By: NOVATECH Suite 200, 240 Michael Cowpland Drive Ottawa, Ontario K2M 1P6 September, 2015 File: 115136 Ref: R-2015-152

More information

Traffic Impact Study Proposed Commercial Development Ballwin, Missouri. Technical Memorandum for Traffic Impact Study

Traffic Impact Study Proposed Commercial Development Ballwin, Missouri. Technical Memorandum for Traffic Impact Study Traffic Impact Study Proposed Commercial Development Ballwin, Missouri Technical Memorandum for Traffic Impact Study Crawford, Bunte, Brammeier May 1, 2009 MEMORANDUM Date: April 24, 2009 To: From: Subject:

More information

10 th Street Residences Development Traffic Impact Analysis

10 th Street Residences Development Traffic Impact Analysis Gibson Traffic Consultants, Inc. 2813 Rockefeller Avenue Suite B Everett, WA 98201 425.339.8266 10 th Street Residences Development Traffic Impact Analysis Jurisdiction: City of Snohomish September 2018

More information

Escondido Marriott Hotel and Mixed-Use Condominium Project TRAFFIC IMPACT ANALYSIS REPORT

Escondido Marriott Hotel and Mixed-Use Condominium Project TRAFFIC IMPACT ANALYSIS REPORT Escondido Marriott Hotel and Mixed-Use Condominium Project TRAFFIC IMPACT ANALYSIS REPORT Prepared for Phelps Program Management 420 Sixth Avenue, Greeley, CO 80632 Prepared by 5050 Avenida Encinas, Suite

More information

KUM & GO 6400 WESTOWN PARKWAY WEST DES MOINES, IOWA 50266

KUM & GO 6400 WESTOWN PARKWAY WEST DES MOINES, IOWA 50266 KUM & GO #300 PECOS STREET & 88 TH AVENUE THORNTON, COLORADO TRAFFIC IMPACT STUDY REVISION 1 PREPARED FOR KUM & GO 6400 WESTOWN PARKWAY WEST DES MOINES, IOWA 50266 JANUARY 23, 2014 OA PROJECT NO. 013-1721

More information

Traffic Impact Study Morgan Road Commerce Park Pasco County, Florida

Traffic Impact Study Morgan Road Commerce Park Pasco County, Florida Traffic Impact Study Morgan Road Commerce Park Pasco County, Florida Summary Report June 2008 Prepared by: 12909 N 56 th Street # 201 Tampa, FL 33617 Ph: (813) 988-3180 Fax: (813) 343-6854 Morgan Road

More information

April Salvation Army Barrhaven Church 102 Bill Leathem Drive Transportation Brief

April Salvation Army Barrhaven Church 102 Bill Leathem Drive Transportation Brief April 26 Salvation Army Barrhaven Church 2 Bill Leathem Drive Transportation Brief Salvation Army Barrhaven Church 2 Bill Leathem Drive Transportation Brief prepared for: The Salvation Army 2 Overlea Blvd.

More information

Traffic Impact Study Speedway Gas Station Redevelopment

Traffic Impact Study Speedway Gas Station Redevelopment Traffic Impact Study Speedway Gas Station Redevelopment Warrenville, Illinois Prepared For: Prepared By: April 11, 2018 Table of Contents 1. Introduction... 1 2. Existing Conditions... 4 Site Location...

More information

Traffic Impact Analysis Update

Traffic Impact Analysis Update Willow Bend Traffic Impact Analysis Update TABLE OF CONTENTS Page I. INTRODUCTION -------------------------------------------------------------------------------------------- 1 II. EXISTING CONDITIONS

More information

TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA

TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA TRAFFIC SIGNAL DESIGN REPORT KING OF PRUSSIA ROAD & RAIDER ROAD RADNOR TOWNSHIP PENNSYLVANIA PREPARED FOR: UNIVERSITY OF PENNSYLVANIA HEALTH SYSTEM 34 CIVIC CENTER BOULEVARD PHILADELPHIA, PA 1987 (61)

More information

Traffic Impact Analysis for 2171 Rosecrans Avenue

Traffic Impact Analysis for 2171 Rosecrans Avenue Traffic Impact Analysis for 2171 Rosecrans Avenue Prepared for: Continental Development Corporation Revised May 2016 LA16-2831 Prepared by: Fehr & Peers 600 Wilshire Blvd, Suite 1050 Los Angeles, CA 90017

More information

Date: February 7, 2017 John Doyle, Z-Best Products Robert Del Rio. T.E. Z-Best Traffic Operations and Site Access Analysis

Date: February 7, 2017 John Doyle, Z-Best Products Robert Del Rio. T.E. Z-Best Traffic Operations and Site Access Analysis Memorandum Date: February 7, 07 To: From: Subject: John Doyle, Z-Best Products Robert Del Rio. T.E. Z-Best Traffic Operations and Site Access Analysis Introduction Hexagon Transportation Consultants, Inc.

More information

One Harbor Point Residential

One Harbor Point Residential Residential Gig Harbor, WA Transportation Impact Analysis January 23, 2017 Prepared for: Neil Walter Company PO Box 2181 Tacoma, WA 98401 Prepared by: TENW Transportation Engineering NorthWest 11400 SE

More information

DIVISION STREET PLAT TRAFFIC IMPACT ANALYSIS

DIVISION STREET PLAT TRAFFIC IMPACT ANALYSIS DIVISION STREET PLAT TRAFFIC IMPACT ANALYSIS TABLE OF CONTENTS 1. Introduction...3 2. Project Description...3 3. Existing Conditions...3 4. Forecast Traffic Demand and Analysis...12 5. Conclusions and

More information

TECHNICAL MEMORANDUM Upper Broadway Road Diet Summary of Findings

TECHNICAL MEMORANDUM Upper Broadway Road Diet Summary of Findings TECHNICAL MEMORANDUM Summary of Findings Date: June 17, 2014 Project #: 17121.15 To: Si Lau, P.E.; City of Oakland, CA From: Erin Ferguson, P.E.; Aaron Elias, P.E.; Daphne Dethier; and Mark Bowman, P.E.;

More information

1012 & 1024 McGarry Terrace

1012 & 1024 McGarry Terrace December 217 112 & 124 McGarry Terrace Transportation Impact Study 112 & 124 McGarry Terrace Transportation Impact Study prepared for: Lépine Corporation 32 March Road Kanata, ON K2K 2E3 prepared by: 1223

More information

APPENDICES. APPENDIX D Synchro Level of Service Output Sheets

APPENDICES. APPENDIX D Synchro Level of Service Output Sheets APPENDICES APPENDIX D Synchro Level of Service Output Sheets Lanes, Volumes, Timings NO BUILD 2016 PM 8: 10th St & Thain Rd 10/05/2016 Lane Group NBL NBT NBR SBL SBT SBR SEL SET SER NWL NWT NWR

More information

Zachary Bugg, PhD, Diego Arguea, PE, and Phill Worth University of Oregon North Campus Conditional Use Permit Application Transportation Assessment

Zachary Bugg, PhD, Diego Arguea, PE, and Phill Worth University of Oregon North Campus Conditional Use Permit Application Transportation Assessment MEMORANDUM Date: June 22, 2018 Project #: 21562 To: Colin McArthur, AICP From: Project: Subject: Zachary Bugg, PhD, Diego Arguea, PE, and Phill Worth University of Oregon North Campus Conditional Use Permit

More information

TRAFFIC IMPACT ANALYSIS FOR. McDONALD S RESTAURANT IN CARMICAEL Sacramento County, CA. Prepared For:

TRAFFIC IMPACT ANALYSIS FOR. McDONALD S RESTAURANT IN CARMICAEL Sacramento County, CA. Prepared For: TRAFFIC IMPACT ANALYSIS FOR McDONALD S RESTAURANT IN CARMICAEL Sacramento County, CA Prepared For: McDonald s USA, LLC Pacific Sierra Region 2999 Oak Road, Suite 900 Walnut Creek, CA 94597 Prepared By:

More information

INDUSTRIAL DEVELOPMENT

INDUSTRIAL DEVELOPMENT INDUSTRIAL DEVELOPMENT Traffic Impact Study Plainfield, Illinois August 2018 Prepared for: Seefried Industrial Properties, Inc. TABLE OF CONTENTS Executive Summary 2 Introduction 3 Existing Conditions

More information

King Soopers #116 Thornton, Colorado

King Soopers #116 Thornton, Colorado Traffic Impact Study King Soopers #116 Thornton, Colorado Prepared for: Galloway & Company, Inc. T R A F F I C I M P A C T S T U D Y King Soopers #116 Thornton, Colorado Prepared for Galloway & Company

More information

TRAFFIC AND TRANSPORTATION TECHNICAL MEMORANDUM

TRAFFIC AND TRANSPORTATION TECHNICAL MEMORANDUM TRAFFIC AND TRANSPORTATION TECHNICAL MEMORANDUM for ENVIRONMENTAL ASSESSMENT US 460 Bypass Interchange and Southgate Drive Relocation State Project No.: 0460-150-204, P101, R201, C501, B601; UPC 99425

More information

King County Metro. Columbia Street Transit Priority Improvements Alternative Analysis. Downtown Southend Transit Study. May 2014.

King County Metro. Columbia Street Transit Priority Improvements Alternative Analysis. Downtown Southend Transit Study. May 2014. King County Metro Columbia Street Transit Priority Improvements Alternative Analysis Downtown Southend Transit Study May 2014 Parametrix Table of Contents Introduction... 1 Methodology... 1 Study Area...

More information

Paisley & Whitelaw - Paisley Park OPA / ZBA for Mixed Density Residential Use

Paisley & Whitelaw - Paisley Park OPA / ZBA for Mixed Density Residential Use Paisley & Whitelaw - Paisley Park OPA / ZBA for Mixed Density Residential Use Transportation Impact Study City of Guelph Prepared for: Armel Corporation August 2018 Table of Contents 1 Introduction...

More information

Wellington Street West

Wellington Street West Transportation Brief prepared for: 185 Davenport Road Suite 300 Toronto, ON M5R 1J1 prepared by: 1223 Michael Street Suite 100 Ottawa, ON K1J 7T2 November 5, 2013 TO3131TOH Transportation Brief November

More information

Oakbrook Village Plaza City of Laguna Hills

Oakbrook Village Plaza City of Laguna Hills Oakbrook Village Plaza City of Laguna Hills Traffic Impact Analysis Prepared by: HDR Engineering 3230 El Camino Real, Suite 200 Irvine, CA 92602 October 2012 Revision 3 D-1 Oakbrook Village Plaza Laguna

More information

Traffic Impact Study. Eastern Springs. A Proposed Development in Manorville, NY. April Haas Group Inc Transportation Planners and Engineers

Traffic Impact Study. Eastern Springs. A Proposed Development in Manorville, NY. April Haas Group Inc Transportation Planners and Engineers Traffic Impact Study For Eastern Springs A Proposed Development in Manorville, NY April 2018 Haas Group Inc Transportation Planners and Engineers Table of Contents 1) Executive Summary... 2 2) Study Purpose...

More information

APPENDIX C1 TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS

APPENDIX C1 TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS APPENDIX C1 TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS DESIGN YEAR TRAFFIC ANALYSIS February 2018 Highway & Bridge Project PIN 6754.12 Route 13 Connector Road Chemung County February 2018 Appendix

More information

APPENDIX TR-1 PARKING AND QUEUING ASSESSMENT

APPENDIX TR-1 PARKING AND QUEUING ASSESSMENT APPENDIX TR-1 PARKING AND QUEUING ASSESSMENT Overland Overland Traffic Consultants, Traffic Consultants, Inc. Inc. Overland Traffic Consultants 952 Manhattan Beach Boulevard, Suite #100 Manhattan Beach,

More information

MEMO VIA . Ms. Amy Roth DPS Director, City of Three Rivers. To:

MEMO VIA  . Ms. Amy Roth DPS Director, City of Three Rivers. To: MEMO To: Ms. Amy Roth DPS Director, City of Three Rivers VIA EMAIL From: Michael J. Labadie, PE Julie M. Kroll, PE, PTOE Brandon Hayes, PE, P.Eng. Fleis & VandenBrink Date: January 5, 2017 Re: Proposed

More information

Tijuana River Valley Regional Park Campground and Education Center

Tijuana River Valley Regional Park Campground and Education Center Tijuana River Valley Regional Park Campground and Education Center Draft Report September 2018 Prepared for: County of San Diego 5500 Overland Avenue, Suite 410 San Diego, CA 92123 Prepared by: 3900 Fifth

More information

Ref. No Task 3. April 28, Mr. Cesar Saleh, P. Eng. VP Planning and Design W.M. Fares Group th

Ref. No Task 3. April 28, Mr. Cesar Saleh, P. Eng. VP Planning and Design W.M. Fares Group th Ref. No. 151-00564 Task 3 April 28, 2015 Mr. Cesar Saleh, P. Eng. VP Planning and Design W.M. Fares Group th 3480 Joseph Howe Drive, 5 Floor HALIFAX NS B3L 4H7 Sent via Email to ceasr.saleh@wmfares.com

More information

TRAFFIC PARKING ANALYSIS

TRAFFIC PARKING ANALYSIS TRAFFIC PARKING ANALYSIS NAPA FLEA MARKET COUNTY OF NAPA Prepared for: Tom Harding Napa-Vallejo Flea Market 33 Kelly Road American Canyon, CA 9453 Prepared by: 166 Olympic Boulevard, Suite 21 Walnut Creek,

More information

FORT MYERS CITY COUNCIL OSCAR M. CORBIN, JR. CITY HALL, 2200 SECOND STREET FORT MYERS, FLORIDA

FORT MYERS CITY COUNCIL OSCAR M. CORBIN, JR. CITY HALL, 2200 SECOND STREET FORT MYERS, FLORIDA Agenda City Council Special Mee ng March 18, 2019 1:00 PM Historic Preserva on Commission Appeal - Virginia Avenue/ McGregor Boulevard Roundabout MAYOR Randall P. Henderson, Jr. Ward 1 Teresa Watkins Brown

More information

Traffic Impact Analysis West Street Garden Plots Improvements and DuPage River Park Garden Plots Development Naperville, Illinois

Traffic Impact Analysis West Street Garden Plots Improvements and DuPage River Park Garden Plots Development Naperville, Illinois Traffic Impact Analysis West Street Garden Plots Improvements and DuPage River Park Garden Plots Development Naperville, Illinois Submitted by April 9, 2009 Introduction Kenig, Lindgren, O Hara, Aboona,

More information

INTERSECTION ANALYSIS PARK AVENUE AND BRADDOCK ROAD (FROSTBURG, MD) FOR LENHART TRAFFIC CONSULTING, INC.

INTERSECTION ANALYSIS PARK AVENUE AND BRADDOCK ROAD (FROSTBURG, MD) FOR LENHART TRAFFIC CONSULTING, INC. INTERSECTION ANALYSIS FOR PARK AVENUE AND BRADDOCK ROAD (FROSTBURG, MD) Prepared for: City of Frostburg, Maryland & Allegany County Commissioners Prepared by: LENHART TRAFFIC CONSULTING, INC. TRAFFIC ENGINEERING

More information

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily 5.8 TRAFFIC, ACCESS, AND CIRCULATION This section describes existing traffic conditions in the project area; summarizes applicable regulations; and analyzes the potential traffic, access, and circulation

More information

Existing Traffic Conditions

Existing Traffic Conditions May 14, 2014 Ms. Lorraine Weiss City of San Mateo 330 West 20 th Avenue San Mateo, CA 94403 Subject: Traffic Operational Study for the Proposed Tilton Avenue Residential Development in San Mateo, California

More information

County State Aid Highway 30 (Diffley Road) and Dodd Road Intersection Study

County State Aid Highway 30 (Diffley Road) and Dodd Road Intersection Study County State Aid Highway 30 (Diffley Road) and Dodd Road Intersection Study City of Eagan, Dakota County, Minnesota Date: March 2012 Project No. 14957.000 444 Cedar Street, Suite 1500 Saint Paul, MN 55101

More information

TABLE OF CONTENTS SECTION PAGE. Executive Summary... xii

TABLE OF CONTENTS SECTION PAGE. Executive Summary... xii TABLE OF CONTENTS SECTION PAGE Executive Summary... xii 1.0 Introduction... 1 1.1 Study Area... 2 1.2 Traffic Impact Analysis Scenarios... 4 1.3 Study Area - City of Orange... 4 2.0 Project Description

More information

ARVADA TRIANGLE REDEVELOPMENT TRAFFIC IMPACT ANALYSIS

ARVADA TRIANGLE REDEVELOPMENT TRAFFIC IMPACT ANALYSIS ARVADA TRIANGLE REDEVELOPMENT TRAFFIC IMPACT ANALYSIS Prepared for: Arvada Urban Renewal Authority 5601 Olde Wadsworth Boulevard, Suite 210 Arvada, Colorado 80002 (720) 898-7062 Prepared by: Felsburg Holt

More information

STANDARD LIMITATIONS

STANDARD LIMITATIONS STANDARD LIMITATIONS This report was prepared by MMM Group (MMM) for the account of Spire Construction Inc. (the Client). The disclosure of any information contained in this report is the sole responsibility

More information

Ryan Coyne, PE City Engineer City of Rye 1051 Boston Post Road Rye, NY Boston Post Road Realignment and Roundabout Design Report

Ryan Coyne, PE City Engineer City of Rye 1051 Boston Post Road Rye, NY Boston Post Road Realignment and Roundabout Design Report March 6, 2015 Ryan Coyne, PE City Engineer City of Rye 1051 Boston Post Road Rye, NY 10580 RE: JMC Project 14108 Boston Post Road Roundabout Boston Post Road and Parsons Street City of Rye, NY Dear Ryan:

More information

TRAFFIC IMPACT ANALYSIS

TRAFFIC IMPACT ANALYSIS TRAFFIC IMPACT ANALYSIS Emerald Isle Commercial Development Prepared by SEPI Engineering & Construction Prepared for Ark Consulting Group, PLLC March 2016 I. Executive Summary A. Site Location The Emerald

More information

Village of Richmond Transportation Brief

Village of Richmond Transportation Brief Village of Richmond Transportation Brief GENIVAR Project Number 111-18482-00 June 21 st, 2011 www.genivar.com GENIVAR 15 Fitzgerald Road, Suite 100 Ottawa, Ontario, CANADA K2H 9G1 Telephone: 613-829-2800

More information

Traffic Impact Analysis. Alliance Cole Avenue Residential Site Dallas, Texas. Kimley-Horn and Associates, Inc. Dallas, Texas.

Traffic Impact Analysis. Alliance Cole Avenue Residential Site Dallas, Texas. Kimley-Horn and Associates, Inc. Dallas, Texas. Traffic Impact Analysis Alliance Cole Avenue Residential Site Dallas, Texas February 15, 2018 Kimley-Horn and Associates, Inc. Dallas, Texas Project #064524900 Registered Firm F-928 Traffic Impact Analysis

More information

Traffic Engineering Study

Traffic Engineering Study Traffic Engineering Study Bellaire Boulevard Prepared For: International Management District Technical Services, Inc. Texas Registered Engineering Firm F-3580 November 2009 Executive Summary has been requested

More information

APPENDIX G TRAFFIC STUDY TECHNICAL MEMORANDUM

APPENDIX G TRAFFIC STUDY TECHNICAL MEMORANDUM APPENDIX G TRAFFIC STUDY TECHNICAL MEMORANDUM TECHNICAL MEMORANDUM To: From: Date: Subject: Jerry Flores - AECOM Brian A. Marchetti, AICP September 9, 5 DRAFT Traffic Study LABOE Channel 5 Studio Relocation

More information

APPENDIX B Traffic Analysis

APPENDIX B Traffic Analysis APPENDIX B Traffic Analysis Rim of the World Unified School District Reconfiguration Prepared for: Rim of the World School District 27315 North Bay Road, Blue Jay, CA 92317 Prepared by: 400 Oceangate,

More information

Traffic Impact Statement (TIS)

Traffic Impact Statement (TIS) Traffic Impact Statement (TIS) Vincentian PUDA Collier County, FL 10/18/2013 Prepared for: Global Properties of Naples Prepared by: Trebilcock Consulting Solutions, PA 2614 Tamiami Trail N, Suite 615 1205

More information

December 5, Red Bank Planning Board Municipal Building 90 Monmouth Street Red Bank, NJ 07701

December 5, Red Bank Planning Board Municipal Building 90 Monmouth Street Red Bank, NJ 07701 Dynamic Traffic, LLC www.dynamic-traffic.com 1904 Main Street Lake Como, NJ 07719 T. 732.681.0760 December 5, 2016 Red Bank Planning Board Municipal Building 90 Monmouth Street Red Bank, NJ 07701 Re: Traffic

More information

Proposed location of Camp Parkway Commerce Center. Vicinity map of Camp Parkway Commerce Center Southampton County, VA

Proposed location of Camp Parkway Commerce Center. Vicinity map of Camp Parkway Commerce Center Southampton County, VA Proposed location of Camp Parkway Commerce Center Vicinity map of Camp Parkway Commerce Center Southampton County, VA Camp Parkway Commerce Center is a proposed distribution and industrial center to be

More information

Shirk Road at State Route 198 Interchange Analysis Tulare County, California

Shirk Road at State Route 198 Interchange Analysis Tulare County, California Shirk Road at State Route 198 Interchange Analysis Tulare County, California DRAFT REPORT Prepared By Tulare County Association of Governments (TCAG) April 2013 Table of Contents Introduction:... 3 Project

More information

Traffic Impact Study Hudson Street Parking Garage MC Project No.: A Table of Contents

Traffic Impact Study Hudson Street Parking Garage MC Project No.: A Table of Contents Traffic Impact Study Hudson Street Parking Garage MC Project No.: 15001714A Table of Contents Table of Contents I. INTRODUCTION... 1 II. EXISTING CONDITIONS... 4 III. 2015 EXISTING TRAFFIC CONDITIONS...

More information

IV. REVISIONS TO THE DRAFT IS/MND

IV. REVISIONS TO THE DRAFT IS/MND IV. REVISIONS TO THE DRAFT IS/MND 1. REVISIONS TO THE DRAFT IS/MND This section presents corrections and clarifications that have been made to the text of the Draft IS/MND. These changes include revisions

More information

Lakeside Terrace Development

Lakeside Terrace Development Lakeside Terrace Development City of Barrie, County of Simcoe Traffic Brief for: Type of Document: Final Report Project Number: JDE 1617 Date Submitted: April 29 th, 216 4/29/16 John Northcote, P.Eng.

More information

267 O Connor Street Residential Development

267 O Connor Street Residential Development M a y 2014 267 O Connor Street Residential Development Transportation Brief Google 2014 Bing 2014 Prepared for: MASTERCRAFT STARWOOD Prepared by: Study 267 O'Connor Type Street May 2014 Study Residential

More information

MILLERSVILLE PARK TRAFFIC IMPACT ANALYSIS ANNE ARUNDEL COUNTY, MARYLAND

MILLERSVILLE PARK TRAFFIC IMPACT ANALYSIS ANNE ARUNDEL COUNTY, MARYLAND MILLERSVILLE PARK TRAFFIC IMPACT ANALYSIS ANNE ARUNDEL COUNTY, MARYLAND Prepared for: Department of Public Works Anne Arundel County Prepared by: URS Corporation 4 North Park Drive, Suite 3 Hunt Valley,

More information