DFO STATEMENT OF NEED REPORT
|
|
- Dustin George
- 5 years ago
- Views:
Transcription
1 APPENDIX E DFO STATEMENT OF NEED REPORT
2
3 Table of Contents 1.0 Executive Summary Description of the Area Geographic Study Area System Configuration Area Loading & Risk Assessment Load Growth Development Load Forecast Current Configuration Risk Assessment Load at Risk Magnitude Area Supply Deficiency No. 39 Substation Transformer Overloading During Contingency (Table 4) Feeder Overloading During Contingency (Table 5) Transformer Overloading During Normal Operation (Table 2) Alternatives Considered to Address Deficiency Alternative 1: Do nothing Alternative 2: Load Transfer to Adjacent Substations Alternative 3 (Preferred): 2 nd Transformer Addition at No. 162 Substation Alternative 4: Transformer Upgrade at No. 39 Substation Alternative 5: New Distribution Point of Delivery Substation Capital Cost Estimates Alternative 1: Do nothing Alternative 2: Load Transfer to Adjacent Substations Alternative 3 (preferred): Transformer Addition at No. 162 Substation Alternative 4: 25kV Transformer Upgrade at No. 39 Substation Alternative 5: New kV Distribution Substation to the East Proposed System Development - Preferred Alternative Preferred Alternative Transmission Scope of Work 2017 (Figure 6): Preferred Alternative Distribution Scope of Work Preferred Alternative Future Distribution Considerations Load Forecast Preferred Alternative 3 Implemented In-Service Date Potential Future System Changes... 26
4 1.0 Executive Summary ENMAX Power Corporation (EPC) is seeking endorsement from the Alberta Electric System Operator (AESO) and approval from the Alberta Utilities Commission (AUC) for the addition of a second kV 30/40/50MVA transformer at No. 162 Substation. The requested transformation capacity upgrade and associated 25kV switchgear is necessary to supply two [2] new 25kV distribution feeders to accommodate 80MVA of load growth and to maintain restoration capability in the northeast area of Calgary over a ten year timeframe. No. 162 Substation, scheduled for completion in 2015, is comprised of one [1] kV 30/40/50MVA transformer to supply the residential developments of Redstone, Skyview Ranch, Saddleridge, Cornerstone and Cityscape and the industrial & commercial developments of Northeast Industrial, Calgary International Airport, Stoney Industrial, Northpoint Industrial and Nose Creek. Through system analysis it was determined that the loss of the single transformer at No. 162 Substation will result in 5 MVA of unsupplied load (Load at Risk) in the area during winter 2017/2018, increasing to 43MVA by winter 2023/2024. The addition of a second kV 30/40/50MVA transformer at No. 162 Substation and construction of two [2] new 25kV distribution feeders was determined as the most viable and cost effective long term engineering solution to address the identified deficiency and support the expected load growth. The estimated Transmission cost for the new kV 30/40/50MVA transformer and associated bus work is approximately $5,300,000 (+/-50%). The estimated Distribution cost for the two [2] new 25kV distribution feeders is approximately $2,500,000 (+/-50%), for an expected total project cost of $7,800,000 (+/-50%). The Transmission cost estimate includes the cost of four [4] new 25kV distribution breakers which is EPC s standard practice with a new transformer addition. Installing four [4] breakers minimizes compatibility issues in the future and provides capacity at No. 162 Substation to accommodate the 10 year forecasted growth. The requested in-service date for the second kV 30/40/50MVA transformer addition at No. 162 Substation and two [2] new 25kV distribution feeders is Q4 of This Statement of Need complies with the EPC Planning Guidelines and Criteria. Page 1 of 26
5 2.0 Description of the Area 2.1 Geographic Study Area The geographic study area discussed in this Statement of Need covers 25kV facilities supplying the following industrial, residential and commercial communities: Redstone Skyview Ranch/Cityscape Saddleridge Saddleridge Business Park Cornerstone Freeport Jacksonport Nose Creek Stoney Industrial Northeast Industrial Park Northpoint Industrial Park Calgary International Airport Reference Figure 1 25kV System Configuration (2016) System Configuration The 25kV residential, industrial and commercial load in the northeast corner of the ENMAX service area is currently proposed to be supplied by the following EPC Infrastructure (Figure 1): No. 162 Substation [1] (Figure 2) consisting of: One [1] kV 30/40/50MVA transformer (162.4TR) Four [4] 25kV feeders on 162.4TR supplying the following areas: o Redstone, Skyview Ranch/Cityscape o Stoney Industrial, Nose Creek, Northpoint Industrial o Calgary International Airport (New Terminal) o Northeast Industrial, Saddleridge, Cornerstone (In Service Date 2016) [1] No. 162 Substation is both a kV step down station and a kV POD source (by 2015). This Statement of Need addresses the kV substation component only. Page 2 of 26
6 Page 3 of 26
7 Figure 2: Existing No. 162 Substation kV Configuration (2016) PLANNING SCOPE ONLY. Not to be used for final design or switching purposes. Page 4 of 26
8 3.0 Area Loading & Risk Assessment 3.1 Load Growth Development The northeast corner of the ENMAX service area is expecting a significant amount of load growth within the next 10 years. The major subdivisions and associated forecasted load growth for the area are listed in Table 1 below. This load growth includes all sectors such as Industrial, Residential and Commercial. The load growth listed in Table 1 below has been integrated into the overall area load forecast, indicated in Section 3.2 Load Forecast. Table 1 - Major Area Load Addition Expectations ( ) Description of New Load Addition Forecasted Load [MVA] Redstone 4 Skyview Ranch/Cityscape 5 Saddleridge 4 Cornerstone 10 Jacksonport 5 Saddleridge Business Park 2 Nose Creek 5 Northeast Industrial 28 Stoney Industrial 4 Freeport 2 Northpoint Industrial 2 Calgary International Airport 12* Total Area Load Growth (Non-Diversified) 83 Refer to Figure 3 Expected Area Load Growth for a geographic reference of the new load growth. *The Calgary International Airport (YYC) is undergoing a significant expansion including a new terminal, runway system (completed and operational as of June 28 th, 2014), and hotel. Distribution System Planning s current forecast includes 12MVA of load growth within the next 10 years. Page 5 of 26
9 Page 6 of 26
10 3.2 Load Forecast Current Configuration Table 2 outlines the 25kV transformer load forecast at No. 162 Substation. Table 2 Transformer 162.4TR Load Forecast - Existing System (MVA) Installed S/W Actual Load [MVA] Diversified Forecasted Load [MVA] Transformer Capacity [MVA] Peak S ² 59² 65² 162.4TR¹ 50 W ² 63² 71² 79² 50 S POD³ 50 W Note: 1. Transformer 162.4TR in service date Transformer at or exceeds nameplate rating and is at risk of overloading under normal operation 3. Non-diversified POD peak only includes 25kV sources. This Statement of Need addresses the 25kV system facilities only. Table 3 outlines the 25kV feeder load forecast at No. 162 Substation. Table 3 Feeder Load Forecast - Existing System (MVA) S/W Actual Load [MVA] Non-Diversified Forecasted Load [MVA] Feeder* Peak S W S W S W S W *Feeder cable ratings for 25kV feeders is 25.9MVA Note: 1. Feeder proposed in service date Feeder proposed in service date Feeder at or exceeds the thermal rated capacity of the cable (25.9MVA) under normal operation Page 7 of 26
11 4.0 Risk Assessment 4.1 Load at Risk Magnitude Load at Risk is defined as customer load that cannot be returned to service within an acceptable timeframe. The Load at Risk highlighted in Table 4 & 5 represents the maximum unsupplied customer load under peak loading conditions in the event of the loss of the single kV 30/40/50MVA transformer at No. 162 Substation. Table 4 Customer Load at Risk During Winter Peak (MVA) Loss of 162.4TR Peak TR¹ Transformer Loading W Total Tie Away Capacity² (Adjacent Feeders) W Load at Risk W Note: 1. Transformer 162.4TR in service date Tie Away Capacity: max load adjacent feeders can restore Table 5 Feeder Load at Risk - Peak Conditions (MVA) Feeder* Peak Loading Tie-Away Capacity W Load at Risk Loading Tie-Away Capacity W Load at Risk Loading Tie-Away Capacity W Load at Risk Loading Tie-Away Capacity W Load at Risk Loading Tie-Away Capacity W Load at Risk *Feeder cable ratings for 25kV feeders is 25.9MVA Note: 1. Feeder proposed in service date Feeder proposed in service date Load at Risk on feeder is due to insufficient feeder backup capacity from No. 162 Substation. Page 8 of 26
12 4.2 Expected Frequency of Load at Risk Occurring During Contingency An analysis was completed based on the data in Table 5, to determine the number of days over the winter peak season (October 1 to April 30) that EPC customers would be exposed to a potential loss of supply due to the limited restoration capability in the event of a transformer outage at No. 162 Substation (162.4TR). The analysis is based off of historical loading profiles applied to identify the frequency and magnitude of customer Load at Risk. Figures 4 & 5 represent a graphical display of the anticipated magnitude of the load at risk along with the identified possible days at risk over the winter peak season from years Table 6 summarizes the data from the graphs of Figure 4 & 5, which represent the number of days that customer loads would be at risk throughout the winter peak season, during a contingency. Table 6 Frequency of Risk (Days) Peak Days at Risk* Winter *Days at risk: Number of days throughout the winter season customers are exposed to risk of un-restored load. Page 9 of 26
13 Figure 4 Winter Load at Risk Duration Existing system Page 10 of 26
14 Figure 5 Winter Load at Risk Duration Existing system Page 11 of 26
15 5.0 Area Supply Deficiency With an expected load growth greater than 80MVA over the next ten years the existing Substation and Distribution infrastructure supplying the residential, commercial and industrial loads in the surrounding area of No. 162 Substation will be unable to maintain the EPC planning criteria requiring full mutual backup capacity over peak loading over the 2017/2018 winter peak season. By the 2019/2020 & 2020/2021 winter peak seasons feeder and transformer 162.4TR will be loaded above their rated capacity, respectively. The identified system deficiencies include: 5.1 No. 39 Substation Transformer Overloading During Contingency (Table 4) By the winter of 2017/2018, 39.4TR transformer will exceed nameplate rating and cannot provide restoration to No. 162 Substation feeders during a transformer contingency of 162.4TR. 5.2 Feeder Overloading During Contingency (Table 5) By the winter of 2017/2018, feeder can no longer be restored during a contingency due to transformer 39.4TR exceeding its nameplate rating (through feeder tie to ). Also, in the winter of 2018/2019 feeder can no longer be restored during a contingency due to an exceeded thermal capacity of the 25kV feeder cables (26MVA) on Transformer Overloading During Normal Operation (Table 2) By the winter of 2020/2021, 162.4TR transformer will be overloading under normal operation TR transformer has a maximum nameplate rating of 50MVA which will be exceeded by 5MVA during winter peak conditions in 2020/2021. Page 12 of 26
16 6.0 Alternatives Considered to Address Deficiency 6.1 Alternative 1: Do nothing Alternative 1 was dismissed as it does not address the identified system deficiencies and results in a violation of EPC loading and reliability criteria policy statements as detailed in the Distribution System Planning Guideline. Alternative 1 is not a viable solution. 6.2 Alternative 2: Load Transfer to Adjacent Substations Adjacent substations do not have the capacity to offload No. 162 Substation. The areas with major growth and future load at risk are in proximity to No. 162 Substation. Supplying these areas from adjacent substations would result in longer feeders which is an ineffective use of distribution infrastructure. Advantages: None Disadvantages: Would result in longer feeders to supply the areas of growth. Would shift the system deficiencies in the area to adjacent substations Alternative 2 was dismissed as it does not address the identified system deficiencies and was not considered to be the best engineering solution. Alternative 2 is not a viable solution. 6.3 Alternative 3 (Preferred): 2 nd Transformer Addition at No. 162 Substation Installation of a second kV 30/40/50MVA transformer and construction of two [2] new 25kV distribution feeders to service the loads to the south of No. 162 Substation. Advantages: System upgrade meets EPC Planning Criteria through addressing the risk of transformer and feeder overloads during normal operation and under contingency. Meets long term reliability and capacity needs for forecasted growth ( ). No. 162 Substation can accommodate the installation of a second transformer and is central to the area of major load growth. Disadvantages: No material disadvantages noted Alternative 3 is considered to be the preferred option as it is the best long term, cost effective solution to address the identified system deficiencies. Page 13 of 26
17 6.4 Alternative 4: Transformer Upgrade at No. 39 Substation Upgrade the two [2] existing kV transformers at No. 39 Substation from 30/40/50MVA to 50/67/83MVA providing additional capacity to this substation. Construction of two [2] new 25kV distribution feeders to service the loads to the north of No. 39 Substation. Advantages: System upgrade meets EPC Planning Criteria through addressing the risk of transformer and feeder overloads during normal operation and under contingency. Provides an efficient solution to supply load growth to the east of Stoney Trail due to existing infrastructure from No. 39 Substation. Disadvantages: An additional cost of $6,700,000 compared to Alternative 3 associated with upgrading two [2] kV transformers. New load growth is geographically close to No. 162 Substation. Due to the geographic location supplying this new load growth from No. 39 Substation would result in long distribution feeders. This alternative was dismissed due to the limited advantages it provides given the associated higher cost. 6.5 Alternative 5: New Distribution Point of Delivery Substation Construction of a new kV 30/40/50MVA substation to the east of Stoney Trail and construction of two [2] new 25kV distribution feeders to serve the loads to the West of the new substation. Advantages: System upgrade meets EPC Planning Criteria through addressing the risk of transformer and feeder overloads during normal operation and under contingency. Provides flexibility to serve the load growth in the area and improves reliability due to the addition of a new Point-of-Delivery substation. Provides an established source for potential future development east of Stoney Trail. Disadvantages: An additional cost of $15,700,000 compared to Alternative 3 Constructing a new substation without utilizing the established infrastructure at No. 162 Substation (i.e. provision for a second transformer) is not a prudent use of system infrastructure. New transmission lines would be required to supply the new substation. This alternative was dismissed due to the limited advantages it provides given the associated higher cost. Page 14 of 26
18 7.0 Capital Cost Estimates Cost estimates were prepared for viable alternatives 3, 4, and 5. Alternatives 1 & 2 were deemed not viable and dismissed. 7.1 Alternative 1: Do nothing No capital cost estimates were prepared for Alternative 1 as it does not address system deficiencies and was dismissed. 7.2 Alternative 2: Load Transfer to Adjacent Substations No capital cost estimates were prepared for Alternative 1 as it does not address system deficiencies and was dismissed. 7.3 Alternative 3 (preferred): Transformer Addition at No. 162 Substation Table 7 Cost Estimate (+/- 50%) Alternative 3 (Preferred): kV 30/40/50MVA Second Transformer Addition at No. 162 Substation Transmission: Installation of one [1] new kV 30/40/50MVA transformer, associated bus work and installation of four [4] new 25kV distribution breakers. Distribution: Construction of two [2] new 25kV feeders from No. 162 Substation. Capital Cost Estimate $ $ 5,300,000 2,500,000 Total: $ 7,800, Alternative 4: 25kV Transformer Upgrade at No. 39 Substation Table 8 - Cost Estimate (+/- 50%) Alternative 4: 25kV Transformer Upgrade at No. 39 Substation Transmission: Upgrading both existing kV 30/40/50MVA transformers to kV 50/67/83MVA transformers and any associated bus work. Installation of four [4] new 25kV distribution breakers. Distribution: Construction of two [2] new 25kV feeders from No. 39 Substation Capital Cost Estimate $ 11,000,000 $ 3,500,000 Total: $ 14,500,000 Page 15 of 26
19 7.5 Alternative 5: New kV Distribution Substation to the East Table 9 Cost Estimate (+/- 50%) Alternative 5: New kV 50MVA Point of Delivery Substation to the East of Stoney Trail Transmission: Construction of one [1] new kV substation with one [1] kV 30/40/50MVA transformer, associated transmission line and bus work and the installation of four [4] new 25kV distribution breakers. Distribution: Construction of two [2] new 25kV feeders from new substation and associated load transfers. Capital Cost Estimate $ 20,000,000 $ 3,500,000 Total: $ 23,500,000 Page 16 of 26
20 8.0 Proposed System Development - Preferred Alternative 3 The preferred solution (Alternative 3) addressing the identified deficiencies includes the installation of a second kV 30/40/50MVA transformer at No. 162 Substation and associated 25kV switchgear to support additional 25kV future feeders. Alternative 3 has been selected as the preferred solution for the following reasons: Provides a long term solution that addresses identified deficiencies. Provides improved reliability and operational flexibility at No.162 Point of Delivery Substation. Effectively makes use of provision for expansion at No. 162 Point of Delivery Substation. Provides sufficient capacity to accommodate forecasted load growth in the area over the next 8 years. Least cost viable solution Facilitates transformer maintenance at No. 162 Substation. 8.1 Preferred Alternative Transmission Scope of Work 2017 (Figure 6): Install second kV 30/40/50MVA transformer at No. 162 Substation complete with associated 25kV bus work. Install four [4] new 25kV distribution feeder breakers Add and modify protection and control equipment as required. The estimated cost of the required substation work is 5,300,000$ (+/- 50%). Page 17 of 26
21 Figure 6 Proposed No. 162 Substation 25kV Configuration Alternative 3 implemented PLANNING SCOPE ONLY. Not to be used for final design or switching purposes. Page 18 of 26
22 8.2 Preferred Alternative Distribution Scope of Work 2017 (Figure 7): Construction of new 25kV distribution feeder to offload industrial load (Freeport) from Construction of new 25kV distribution feeder to sectionalize and offload The estimated cost of the required distribution work is $2,500,000 (+/- 50%). 8.3 Preferred Alternative Future Distribution Considerations Distribution System Planning has identified a future need for additional distribution infrastructure by A conceptual solution is presented in this document to outline a forecasted long term plan. Future system assessments will be performed along with the development of relevant business cases to address the need and timing. Distribution System Planning is not requesting approval at this time for the distribution infrastructure to be built by 2021 (Figure 8) outlined below (Figure 8): Construction of new 25kV distribution feeder to support growth in Northeast Industrial Park. Construction of new 25kV distribution feeder to support growth in residential developments. Cost estimates of the distribution infrastructure subject to the development of the appropriate business cases. [1] The in-service date of 2021 for the potential addition of two [2] new 25kV feeders from No. 162 Substation is a reflection of Distribution System Planning s current load forecast and long term plan. These feeders and their in-service dates are subject to further system assessments prior to commitment. Page 19 of 26
23 Page 20 of 26
24 Page 21 of 26
25 9.0 Load Forecast Preferred Alternative 3 Implemented Table 10 outlines the 25kV transformer load forecast at No. 162 Substation with Alternative 3 implemented. Table 10 Transformer Load Forecast - Preferred Alternative Implemented (MVA) Installed S/W Diversified Forecasted Load [MVA] Transformer Capacity [MVA] Peak S TR 2 50 W S TR 1 50 W S POD W Note: 1. Transformer 162.4TR in service date Transformer 162.3TR proposed in service date Non-diversified POD peak only includes 25kV sources. This Statement of Need addresses the 25kV system facilities only. Page 22 of 26
26 Table 11 outlines the 25kV feeder load forecast at No. 162 Substation. Table 11 indicates that the implementation of the preferred alternative eliminates feeder overloading under normal operation. Table 11 Feeder Load Forecast - Preferred Alternative Implemented (MVA) Feeder* S/W Non-Diversified Forecasted Load [MVA] Peak S W S W S W S W S W S W S W S W *Feeder cable ratings for 25kV feeders is 25.9MVA Note: 1. Feeder proposed in service date Feeder proposed in service date Feeder proposed in service date Future conceptual feeders anticipated to be required in Subject to future system assessment and approval. Page 23 of 26
27 Table 12 indicates that during a specified transformer outage the implemented preferred alternative eliminates the load at risk. Table 12 Customer Load at Risk - Preferred Alternative Implemented (MVA) Loss of 162.4TR 162.4TR 1 Transformer Loading Total Tie Away Capacity 2 (Adjacent Feeders & Remaining Transformer) Load at Risk 4 Loss of 162.3TR 162.3TR 3 Transformer Loading Total Tie Away Capacity 2 (Adjacent Feeders & Remaining Transformer) Load at Risk 4 Peak W W W Peak W W W Note: 1. Transformer 162.4TR in service date Tie Away Capacity: max load adjacent feeders and/or remaining transformer can restore within thermal capacity of 25kV cable and transformer nameplate rating 3. Transformer 162.3TR proposed in service date Load at Risk is defined as the customer load that cannot be returned to service within an acceptable timeframe Page 24 of 26
28 Table 13 indicates that the implementation of the preferred alternative eliminates load at risk on the No. 162 feeders until Table 13 Feeder Load at Risk - Preferred Alternative Implemented Feeder* Peak Loading Tie-Away Capacity W Load at Risk Loading Tie-Away Capacity W Load at Risk Loading Tie-Away Capacity W Load at Risk Loading Tie-Away Capacity W Load at Risk Loading Tie-Away Capacity W Load at Risk Loading Tie-Away Capacity W Load at Risk Loading Tie-Away Capacity W Load at Risk Loading Tie-Away Capacity W Load at Risk Loading Tie-Away Capacity W Load at Risk *Feeder cable ratings for 25kV feeders is 25.9MVA Note: 1. Feeder proposed in service date Feeder proposed in service date Feeder proposed in service date Future conceptual feeders 5. Forecast Load-at-Risk will be addressed through additional area system infrastructure appropriate at that time. Page 25 of 26
29 10.0 In-Service Date The requested in-service date for the kV 30/40/50MVA transformer addition at No. 162 Substation and two [2] new 25kV distribution feeders is Q4 of Potential Future System Changes Distribution As identified in Table 13, there will be a requirement for additional distribution infrastructure by 2021 in the northeast corner of the EPC service area. Distribution System Planning s current plan for the area includes building two [2] 25kV feeders out of No. 162 Substation as outlined in this Statement of Need. Future system assessments will be performed along with the development of relevant business cases to address the need and timing. Transmission/Substation Additionally, future development may include the possible installation of a new kV Point of Delivery (between No. 47 Substation and No. 162 Substation). The need for a future substation is conceptual at this time and represents Distribution System Planning s load forecast and long term plan to supply the area. Further assessment will be needed as the area develops. A separate Statement of Need document and AESO System Access Service Request (SASR) application will be prepared for this new substation when required. Page 26 of 26
ATTACHMENT - DFO STATEMENT OF NEED
ATTACHMENT - DFO STATEMENT OF NEED Table of Contents Executive Summary... 3 1. Description of the Area... 5 1.1 Geographic Study Area... 5 1.2 Current System Configuration... 7 1.3 Distributed Generation...
More information100 MW Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility
More information15 Nelson-Marlborough Regional Plan
15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant
More informationReasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders
Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test: Salisbury Substation 11kV Feeders DISCLAIMER The purpose of this document is to inform customers, Interested Parties,
More informationAlberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation
Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta
More informationPID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation
PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date
More informationConnection Engineering Study Report for AUC Application: AESO Project # 1674
APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System
More informationThe Energy Queensland Group Notice of no non-network options
The Energy Queensland Group Notice of no non-network options 24 September 2018 MCE Mount Crosby East Establish new substation to replace Mount Crosby Substation (SSMTC) Page 1 of 1 DISCLAIMER While care
More informationService Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #
Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists
More informationEngineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents
APPENDIX A CONNECTION ASSESSMENT : FortisAlberta Inc. Plamondon 5S Capacity Increase Contents Executive Summary.... Introduction... 6. Project... 6.. Project Overview... 6.. Load Component... 6.. Generation
More informationFOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT
FOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT Proposed 138kV Transmission Line Photo courtesy of The City of Calgary Project Overview The demand for power is increasing as Calgary continues
More informationFOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT
FOOTHILLS AREA TRANSMISSION DEVELOPMENT SOUTH CALGARY PROJECT Proposed 138kV Transmission Line Photo courtesy of The City of Calgary Project Overview The demand for power is increasing as Calgary continues
More informationTRANSMISSION PLANNING CRITERIA
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing
More information15 Nelson-Marlborough Regional Plan
15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant
More informationAlberta Electric System Operator Saleski Transmission Project Needs Identification Document
Decision 2013-127 Alberta Electric System Operator Saleski Transmission Project Needs Identification Document ATCO Electric Ltd. Saleski 901S Substation and 144-kV Transmission Line 7L142 Facility Application
More informationDecision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016
Decision 21481-D01-2016 October 18, 2016 Alberta Utilities Commission Decision 21481-D01-2016 Proceeding 21481 Application 21481-A001 October 18, 2016 Published by the: Alberta Utilities Commission Fifth
More informationHeader. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8
Header Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations RT 007-11 Balhannah and Uraidla - Final Draft Page 1 of 8 DISCLAIMER The purpose of this document is to inform customers,
More informationDunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study
` Dunvegan Hydroelectric Project For Glacier Power Limited Preliminary Interconnection Study Prepared by Pung Toy, P. Eng. and Ata Rehman, P. Eng. September 24, 2004 Table of Contents Table of Contents...
More informationTransmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation
Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT
More informationCurrant Lake Transmission Project
Currant Lake Transmission Project September 2010 Why are you receiving this project information package? New transmission facilities are needed in the Monitor area of southeastern Alberta. ATCO Electric
More informationThe Long-Range Transmission Plan
The Long-Range Transmission Plan 2015 2025 Matt Koenig Presentation to ESPWG / TPAS October 29 th, 2015 Long-Range Transmission Plan Driver of the Plan is to maintain local reliability 10-year planning
More information2017 Interim Area Transmission Review of the New York State Bulk Power Transmission System
2017 Interim Area Transmission Review of the New York State Bulk Power Transmission System A Draft Report by the New York Independent System Operator October 24, 2017 - DRAFT DRAFT PURPOSES ONLY NYISO
More informationInterconnection System Impact Study Report Request # GI
Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010
More informationBohn to Kettle River Transmission Project
April 2012 Why are you receiving this project information package? New transmission facilities are needed in the Fort McMurray area. ATCO Electric has been directed by the Alberta Electric System Operator
More informationKettle River Transmission Project
April 2012 Why are you receiving this project information package? New transmission facilities are needed in the Fort McMurray area. ATCO Electric has been directed by the Alberta Electric System Operator
More informationWillingdon Substation Decommission
November 2012 Why are you receiving this project information package? New transmission facilities have been proposed in central east Alberta. As a result, some existing facilities are no longer needed.
More informationElbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI
Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility
More informationAppendix D Black Hills Project Summary
Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain
More informationLocal Transmission Plan. October 11, 2013 Revised August 25, 2014
Local Transmission Plan October 11, 2013 Revised August 25, 2014 2 Central Hudson s System Zone G: Majority of Central Hudson s load Zone E: One small distribution substation Interconnections with Consolidated
More informationMILLIGAN SOLAR PROJECT
February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission
More informationSPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN
SPN High Value Project PO Route RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN Document History Version Date Details Originator V0.1 20/06/2013 Initial version Chris Winch V0.2
More informationSupplemental Report on the NCTPC Collaborative Transmission Plan
Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for
More informationPJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G
PJM Sub Regional RTEP Committee Mid-Atlantic January 22, 2016 Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PSE&G System Characteristics New Jersey utility characterized by densely populated
More informationSub Regional RTEP Committee Western Region ATSI
Sub Regional RTEP Committee Western Region ATSI February 20, 2019 1 ATSI Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider these
More informationDesign Criteria Implementation for the Network Development Plan Hursthill Substation
Design Criteria Implementation for the Network Development Plan Hursthill Substation Presenter : Riaan Swanepoel PRTechEng 1 Introduction The City of Johannesburg is embarking on a new spatial vision for
More informationMerger of the generator interconnection processes of Valley Electric and the ISO;
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric
More informationFalcon-Midway 115 kv Line Uprate Project Report
Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50
More informationAlternatives for meeting the need for transmission improvement described
Alternatives for meeting the need for transmission improvement described 240 kv Alternative Looped System Southern Alberta Transmission Reinforcement For more information please contact the AESO at 1.888.866.2959,
More informationDecision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82
Decision 21447-D01-2016 August 23, 2016 Decision 21447-D01-2016 Proceeding 21447 Application 21447-A001 August 23, 2016 Published by the: Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary,
More informationJemena Electricity Networks (Vic) Ltd
Jemena Electricity Networks (Vic) Ltd 2016-20 Electricity Distribution Price Review Regulatory Proposal Revocation and substitution submission Attachment 7-14 Revised Flemington network development strategy
More informationCUSTOMER/ TWIN ARROWS PROJECT
A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset
More informationReliability Analysis Update
Reliability Analysis Update Transmission Expansion Advisory Committee October 11, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects
More informationTransmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014
Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder
More informationInterconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS
Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia
More informationWest Station-West Cañon 115 kv Transmission Project
West Station-West Cañon 115 kv Transmission Project Project Sponsor: Additional Project Participants: Project Description: Black Hills Colorado Electric New 115 kv line from West Station to West Cañon
More informationMemorandum. This memorandum requires Board action. EXECUTIVE SUMMARY
California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:
More informationENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE
ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE RATES IN EFFECT AS OF APRIL 1, 2018 EPC DISTRIBUTION TARIFF RATE SCHEDULE Rate Code Rate Description Page D100 Distribution Tariff Residential
More informationGuideline for Parallel Grid Exit Point Connection 28/10/2010
Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND
More informationBlack Hills Project Summary
2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission
More informationEnvironmental Assessment Derry Road and Argentia Road Intersection
Air and Noise Study Environmental Assessment Derry Road and Argentia Road Intersection Project 11-4295 City of Mississauga, Region of Peel October 17, 2014 1 Region of Peel Environmental Assessment for
More informationJune Substation Refurbishment and Modernization. Prepared by: Substatiort Refu14bislrment and Modernization NP 2012 CBA
2.1 2012 Substatiort Refu14bislrment and Modernization NP 2012 CBA 2012 Substation Refurbishment and Modernization June 2011 Prepared by: Peter Feehan, P.Eng. A FORTIS COMPANY 2.1 2012 Substation Refurbishment
More informationEmera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC
OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn,
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS
More informationConnection Engineering Study Report for AUC Application: EPCOR Clover Bar 25 kv Breaker Addition
Connection Engineering Study Report for AUC Application: EPCOR Clover Bar 25 kv Breaker Addition Executive Summary Project Overview EPCOR Distribution & Transmission Inc. (EDTI), in its capacity as the
More informationTEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY
TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF
More informationInterconnection Feasibility Study Report GIP-222-FEAS-R3
Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.
More informationNew 115 kv Disconnect Switches at Bloomsburg MTS
115 kv Line tap from C9 to Bloomsburg MTS & New Bus Tie Switch CAA ID Number: 2007-EX353 Final Draft ASSESSMENT SUMMARY 1. GENERAL DESCRIPTION Norfolk TS and Bloomsburg MTS are supplied by a single 115
More informationOuter Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)
Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving
More informationMaddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016
New Transmission Line November 15, 2016 The enclosed information is proprietary to PSE&G and is provided solely for your use. It should not be copied, reproduced, or shared with others without PSE&G s
More informationFinal Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description
Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing
More informationDETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT
DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT Report No.: RP-160388-02-141-0001 CAA ID No. 2010-380 Rev. 01 Prepared by: AMEC Americas Limited Energy and Mining Division Power
More informationSOUTHWEST CALGARY RING ROAD (SWCRR)
PROJECT OVERVIEW Alberta Transportation has started planning for the construction of the SW portion of the road that will complete the Calgary Ring Road. The completion of the SWCRR requires the relocation
More informationDowntown Lee s Summit Parking Study
Downtown Lee s Summit Parking Study As part of the Downtown Lee s Summit Master Plan, a downtown parking and traffic study was completed by TranSystems Corporation in November 2003. The parking analysis
More informationENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE
ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE Rates in effect as of January 1, 2018 EPC DISTRIBUTION TARIFF RATE SCHEDULE Rate Code Rate Description Page D100 Distribution Tariff Residential
More informationTHE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS
THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive
More informationInterconnection Feasibility Study Report GIP-084-FEAS-R2
Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power
More informationOCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC
OCTOBER 17, 2018 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC
More informationNorth Oregon Coast Area Study. Adam Lint
North Oregon Coast Area Study Adam Lint PAGE 2 North Oregon Coast System Overview - Clatsop Study Covers: Transmission Switching Stations (Clatsop District): Astoria Lewis and Clark 115 kv Distribution
More informationCity of Palo Alto (ID # 6416) City Council Staff Report
City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building
More informationSystem Impact Study Report
Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS
More informationINTERCONNECTION BETWEEN IRELAND AND ENGLAND / WALES TECHNICAL INVESTIGATION INTO CONNECTION OF EAST WEST INTERCONNECTOR TO IRISH TRANSMISSION SYSTEM
INTERCONNECTION BETWEEN IRELAND AND ENGLAND / WALES TECHNICAL INVESTIGATION INTO CONNECTION OF EAST WEST INTERCONNECTOR TO IRISH TRANSMISSION SYSTEM EIRGRID AUGUST 2007 EXPLANATORY NOTE FOR PUBLISHED DOCUMENT
More informationTerry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis
Terry Blackwell Page 1 of 5 Education 1977 North Carolina State University BS, Electrical Engineering Power Systems emphasis Professional Qualifications 1977 PE-Professional Engineer Business Experience
More informationENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE
ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE Rates in effect as of September 1, 2015 EPC DISTRIBUTION TARIFF RATE SCHEDULE Rate Code Rate Description Page D100 Distribution Tariff
More informationUmatilla Electric Cooperative Net Metering Rules
Umatilla Electric Cooperative Net Metering Rules Version: July 2017 Umatilla Electric Cooperative NET METERING RULES Rule 0005 Scope and Applicability of Net Metering Facility Rules (1) Rule 0010 through
More informationThe Grid Link Project. Summary of the Report for the Independent Expert Panel
The Grid Link Project Summary of the Report for the Independent Expert Panel Who are EirGrid - and what do we do? EirGrid is responsible for a safe, secure and reliable supply of electricity: now and in
More informationHigh Voltage Pad-mount Transformer
High Voltage Pad-mount Transformer What is the High Voltage Padmount Transformer(HVPT) Substation? Traditional substation vs. HVPT HVPT History In order to reduce its outlay in distribution, Manitoba Hydro
More informationHigh Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007
High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services
More informationTOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY
TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY
More informationSPP Notification to Construct
SPP Notification to Construct SPP-NTC-20123 February 14, 2011 Mr. Sam McGarrah Empire District Electric Company PO Box 127 Joplin, MO 64802 RE: Notification to Construct Approved Reliability Network Upgrades
More informationInterconnection Feasibility Study Report GIP-226-FEAS-R3
Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power
More informationCONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation
CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent
More informationRogers Road to Clubhouse 230kV New Transmission Line April 1, 2016
New Transmission Line April 1, 2016 The enclosed information is proprietary to PSE&G and is provided solely for your use. It should not be copied, reproduced, or shared with others without PSE&G s prior
More informationExecutive Summary. Project Overview. Existing System. Study Summary
APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: Hornbeck 345S Substation Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta), in its capacity
More informationDecision (Errata) Access Pipeline Inc. Errata to Decision Temporary Generation at Smoky Lake Pump Station.
Decision 2011-424 (Errata) Access Pipeline Inc. Errata to Decision 2011-424 Temporary Generation at Smoky Lake Pump Station January 4, 2012 The Alberta Utilities Commission Decision 2011-424 (Errata):
More informationIncluded in this Stakeholder Information Package:
Who can you contact for more information? Yellowhead Area Transmission Reinforcement: TERA Environmental Consultants Dave Sare Phone: 403-538-5734 Email: dsare@teraenv.com Drayton Valley Area AltaLink
More informationDecision The City of Calgary. 30-kW Solar Power Plant. March 8, 2012
Decision 2012-065 30-kW Solar Power Plant March 8, 2012 The Alberta Utilities Commission Decision 2012-065: 30-kW Solar Power Plant Application No. 1607869 Proceeding ID No. 1563 March 8, 2012 Published
More informationWestern NY Public Policy Transmission Planning Report
Western NY Public Policy Transmission Planning Report Dawei Fan Supervisor, Public Policy and Interregional Planning Business Issues Committee September 12, 2017 Operating Committee September 15, 2017
More informationGeneration Interconnection Facilities Study For
Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015 TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications...
More informationFIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION
PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection
More informationEL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS
EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic November 04, 2013 2013 RTEP Baseline Analysis Update 11/04/2013 AE Transmission Zone Cost Change for B2354 Install second 230/69kV transformer and 230kV circuit
More informationBrion Energy Corporation
Decision 20907-D01-2015 MacKay River Commercial Project October 29, 2015 Alberta Utilities Commission Decision 20907-D01-2015 MacKay River Commercial Project Proceeding 20907 Application 20907-A001 October
More informationFacilities Study for Alberta to US Available Transfer Capability
Facilities Study for Alberta to US Available Transfer Capability Report No: NPP2002-05 June 3, 2002 System Planning & Grid Operations, Transmission Line of Business Engineering Services Executive Summary
More informationEmera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC
OCTOBER 22, 2015 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC
More information2016 Load & Capacity Data Report
Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness
More information2011 Substation Refurbishment and Modernization. June 2010
Z,1 Substatiort Refurbish~nent and Modernization NP 2011 CBA 2011 Substation Refurbishment and Modernization June 2010 Prepared by: Peter Feehan, P.Eng. 2.1 2011 Substation Refurbishment and Modernization
More informationInterconnection Feasibility Study Report GIP-046-FEAS-R2
Interconnection Feasibility Study Report GIP-046-FEAS-R2 Generator Interconnection Request #46 32 MW Wind Generating Facility Colchester (L-6513), NS August 17, 2007 Control Centre Operations Nova Scotia
More informationNetwork. ENMAX Power Corporation Network Planning & Design November 4, 2011
Network ENMAX Power Corporation Network Planning & Design November 4, 2011 ENMAX Fast Facts Service area of 1,044 square kilometers 1,738MVA Peak load (2009) Transmission System 266 km overhead 15km underground
More informationProject #148. Generation Interconnection System Impact Study Report
Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection
More informationEmerald Reactive Support Alternative Solution Expressions of interest
Emerald Reactive Support Alternative Solution Expressions of interest Publishing Date 21/02/2017 Closing Date 21/03/2017 1. Executive Summary Ergon Energy Corporation Limited (EECL) is seeking expressions
More information