A Guide to Non Destructive Testing of Guy Wires
|
|
- Molly Joella Powers
- 5 years ago
- Views:
Transcription
1 ZENITH CONSULTANTS 38 Dryden road Loanhead Midlothian EH20 9LZ A Guide to Non Destructive Testing of Guy Wires
2 Introduction: Zenith Structural Access Solutions offers magnetic, non-destructive testing of guy wires as part of our comprehensive range of flare stack inspections. About the instrument: The instrument used to carry out this survey is an Intron Intros MH20-40 magnetic head. This can successfully determine faults within wires ranging from 20 and 40mm in diameter which would ordinarily go undetected by a visual inspection. The head is connected to a data logger, which records the data in real time. For manufacturers details, see Appendix iii. Rigging the Instrument: The instrument is simply clamped to the wire and pulled up and down the guy wire in a controlled manner via a pulley system mounted at the upper support. No proprietary work is required to the guy wire, and no adverse stresses or strains are imposed onto it. How it s done: The survey involves attaching the magnetic head onto the wire, and running it up and down the wire to magnetise it. Once the wire is magnetised, the magnetic head is run up and down a further time to gather the required data, which is stored onto the data logger. The stored information is then downloaded, and analysed using wintros software. By analysing the graphical output from the wintros software, localised faults (LF) and/or metallic loss of area (LMA) can be identified. For full instructions, see appendix ii.
3 What it tells us: These inspections aim to locate the LF s and LMA s, and to determine their severity / magnitude. LF (localised fault): Detects the presence of a broken/defective wire(s), or discontinuity in the rope. LMA (loss of metallic area): Detects loss of sectional area, highlighting possible loss of capacity. What is produced: A detailed report showing the likely locations and suggested severity of faults along the length of each wire. For sample report, see Appendix i.
4 Appendices: i Sample Report ii Instructions for Use iii Manufacturers Brochure
5 Appendix i- Sample Report
6 ZENITH CONSULTANTS Unit 7 Dryden Vale Bilston Glen Industrial Estate Loanhead Midlothian EH20 9HN XXXXXXX XXXXXXXX Inspection Report Revision C Survey Engineer David Kellyy Prepared By:...John Lambb August 2014 Document Revision Status Rev Details Dated Statuss C Add comparison Tables 13/10 C Author CC Checked SC
7 SECTION 1 - INTRODUCTION 1.0 INTRODUCTION 1.1 In August 2014 Zenith Consultants were engaged by XXXXXX to undertake a survey of the 36-S500B flare stack. The survey was carried out on 03 rd & 04 th August 2014 during the KG TAR shutdown.the report is best read in conjunction with Appendix A, B & C 1.2 The purpose of the survey was to identify and record any defects to the guy wires and termination connections to the flare and to make recommendations for future repair.
8 SECTION 2 DESCRIPTION OF STRUCTURE 2.0 DESCRIPTION 2.1 The flare is 90m high from ground level guyed structure, with 3No anchor blocks located at 120 degrees. Each anchor block has four guy wires supporting the flare. 2.2 The flare has a fixed ladder and staged gantries over the height.
9 SECTION 3 - PROCEDURES AND METHODS 3.0 PROCEDURES AND METHODS 3.1 Access to the head of the flare was achieved using the fixed ladder/gantry arrangement. 3.2 A visual examination of all external parts. 3.3 The Magnetic Inspection was carried out on each guy wire. 3.4 The inspection was carried out using an Intron Magnetic head with Wintros software for assessment of the results. The apparatus uses LMA (loss of metallic area) and LF (local fault) readings to assess the condition of the cable. 3.5 The first section of cable was first magnetised and then used to calibrate the equipment. 3,6 The inspection was carried out using a hoisting arrangement. 3.7 The cable was first magnetised before two inspections were carried out.
10 SECTION 4 - SURVEY RESULTS 4.0 SURVEY RESULTS 4.1 Ground Termination Bases: No evidence of distress to the concrete pile block or soil surrounds. 4.2 Ground Termination Anchors: No evidence of corrosion, distortion or separation from the concrete pile. 4.3 Ground Termination Eyelets and Pins: No evidence of excessive wear, 4.4 Ground Termination Rope Shackles: Shackles appear in good condition and showing no signs of corrosion. 4.5 Ground Termination Turnbuckle: Turnbuckle is in good condition, is fully operational and secure. 70% of adjustment in the turnbuckle is currently in use. 4.5 Stack Termination eyelet arrangement: Good condition, no chaffing or wear. 4.6 Stack Termination Shackle: Good condition. 4.7 Stack Termination Lug: Good condition, no evidence of weld fractures. 4.8 Guy Wire Inspection: Guy wires are in generally good condition, there are however a number of broken wires within some of the cables, but the small number of breaks will have no effect on the stability of the flare. Loss of the metallic coat on the wires over localized areas is evident from the survey data. Refer to Appendix A, B & C for survey results of the guy wires.
11 Verticality & Rope Tension 4.9 The results of the verticality and rope tension are appended (Appendix D) The tension figures in the lower ropes are generally in line with pretension design figures. The recorded information does not reflect the tension values obtained in the previous year s measurements, the recorded information for this year is consistently higher than the 2009 readings The variation in readings could be due a variation in site wind speed, wind direction, gusting, site temperature, operating temperature etc. If the site variables are low during one survey, a relatively modest increase of the variables in the next survey could result in a threefold increase in load In the absence of the original calculations Zenith have adopted a comparison against of the tension figures suggested by Guydes, (Guydes being one of the leading software packages for the design of guyed stacks) For the purpose of comparison, good practice suggests guy stacks are typically set at pretension of only 6% to 12% of the breaking strength due to the hot gases flowing into the stacks The ropes are within these guidelines but remain marginally over tensioned when compared to the pre-tension design data on record. It would be normal practice to only tension ropes rather than slacken ropes in a scenario where the towers have performed with out fault and show no sign of distress In conclusion the ropes would be re-examined within 12 months recording all tolerances at site level including temperature and wind speed The verticality of the structure is marginally out with tolerance in the lower two positions. No correction has been made at this time based on the upper levels of the flare stack being within tolerance. It was determined that any adjustment at this stage would compromise the overall results and therefore no action undertaken.
12 SECTION 5 - DISCUSSION AND RECOMMENDATIONS 5.0 DISCUSSION AND RECOMMENDATIONS 5.1 The flare guy wires and termination points should be inspected at regular intervals. 5.2 The flare remains serviceable under current operating conditions. 5.3 The flare guy wires are in serviceable condition and should be re-inspected during the next shutdown in Although there are localized areas where the metal coat to the wire has thinned or has been removed, there is no requirement for any repair work to be carried out at this time. 5.5 A magnetic inspection should be carried out at the next shut down in The result of which should be read alongside this survey to give a rate of deterioration of the wires. 5.6 Zenith remain satisfied that the guy ropes and the flare stacks are operating within tolerance as the thermal expansion due to hot gases in this instance is limited to the tip of the stack and not throughout the full length hence the tension in the wires can approach the 20% to % generally used for transmission towers restrained by guys. 5.8 The verticality of the tower should be checked at regular intervals (not exceeding 12 months) and where tension has relaxed every effort made to correct the verticality to within the BSEN standards without compromising the overall tolerances.
13 SECTION 6 APPENDICES APPENDICES A- Elevation A guy wires B- Elevation B guy wires C- Elevation C guy wires D- Verticality & Rope Tension E- Comparison Tables
14 APPENDIX A- ELEVATION 'A' GUY WIRES
15 LF trace, mv LF trace, mv LF trace, mv LF trace, mv
16 APPENDIX B - ELEVATION '8' GUY WIRES
17 LF trace, mv LF trace, mv LF trace, mv LF trace, mv
18 APPENDIX C ELEVATION C GUY WIRES
19 LF trace, mv LF trace, mv LF trace, mv LF trace, mv
20 APPENDIX D - VERTICALITY AND ROPE TENSION
21
22 APPENDIX 'E' - COMPARISON TABLES
23 Client Structure Ineos Manufactuing (Scotland) Ltd Flare B 36 S 500 B Height D1 D2 Max. Allowable Resultant Result mm mm mm mm Total MM2 MM 1 1 (Lower) FALSE FALSE OK 4 4 (Upper) OK FALSE FALSE * D1 = Direction 1, D2 = Direction 2 Readings are based on 'Latch & Batchelor' Steel Wire Ropes Booklet for General Purpose Ropes to BSEN with a Steel Core Grade 1770 N/MM2 and should only be used as a guide. Where a direct comparsion can not be made the reading (i.e dia/construction) the next lower performing wire should be used. Comparison with the original design / construction should be completed, wherever practical. Rope No Position Diameter Measured Load (Kn) Theoretical MBL (Kn) % of MBL 1 A B C A B C A B C A B C Cross Check Information Dia MBL MBL 6% Lower Theoretical 9% Average Theoretical 12% Upper Theoretical 20% Cold Structure 40% Upper Limit MM Rope Type Kn t Kn t Kn t Kn t Kn t Kn t 18 6X19, 6X36, 6X X19, 6X36, 6X X19, 6X36, 6X X19, 6X36, 6X X19, 6X36, 6X X19, 6X36, 6X X19, 6X36, 6X X19, 6X36, 6X X19, 6X36, 6X X19, 6X36, 6X X19, 6X36, 6X X19, 6X36, 6X X19, 6X36, 6X X19, 6X36, 6X X19, 6X36, 6X X19, 6X36, 6X X19, 6X36, 6X X19, 6X36, 6X
24 Appendix ii -Instructions for Use
25
26
27 Appendix iii- Manufacturers Brochure
28
29
30
31
32
33
34
35
Status: Issue 08 Date: 18/10/17 Reference: Lifting Operations and Lifting Equipment Regulations 1998 Regulation 9
GUIDANCE IN-SERVICE INSPECTION PROCEDURES Number: MLCC 03 Prepared by: MACHINERY LIFTS AND CRANE COMMITTEE Status: Issue 08 Date: 18/10/17 Reference: Lifting Operations and Lifting Equipment Regulations
More informationGUIDANCE IN-SERVICE INSPECTION PROCEDURES
GUIDANCE IN-SERVICE INSPECTION PROCEDURES Number: MLCC 03 Prepared by: MACHINERY LIFTS AND CRANE COMMITTEE Status: Issue 07 Date: 23/06/15 Reference: Health, Safety and Welfare at Work (General Application)
More informationPIPE HANGERS & SUPPORTS PRIVATE LIMITED Plot No 29 Industrial Estate Perungudi Chennai, Tamilnadu India
PIPE HANGERS & SUPPORTS PRIVATE LIMITED Plot No 29 Industrial Estate Perungudi Chennai, Tamilnadu India-600096 Telephone +91 (0) 44-2496 1003, 2496 2668 Fax: +44 (0) 44-24961395 E mail: mengg@pipehangers.in
More informationPIPE HANGERS & SUPPORTS PRIVATE LIMITED Plot No 29 Industrial Estate Perungudi Chennai, Tamilnadu India
PIPE HANGERS & SUPPORTS PRIVATE LIMITED Plot No 29 Industrial Estate Perungudi Chennai, Tamilnadu India-600096 Telephone +91 (0) 44-24962668, 24961003 Fax: +44 (0) 44-24961395 E mail: mengg@pipehangers.in
More informationPIPE SUPPORTS INDIA PRIVATELIMITED Plot No 29 Industrial Estate Perungudi Chennai, Tamilnadu India
PIPE SUPPORTS INDIA PRIVATELIMITED Plot No 29 Industrial Estate Perungudi Chennai, Tamilnadu India-600096 Telephone +91 (0) 44-24952668, 24961003 Fax: +44 (0) 44-24961395 E mail: psindia@vsnl.com www.pipesupports.com
More informationSpring hangers, spring supports
Spring hangers, spring supports 2 spring Spring hangers, supports PRODUCT 2 GROUP Spring hangers, spring supports Contents Page Field of application...2.1 Overview of spring hangers and spring supports...2.3
More informationPolice Operations: Tachograph Equipment Inspection
Higher National Unit Specification General information for centres Unit code: F0N9 35 Unit purpose: This Unit is designed to enable candidates to analyse tachograph recording equipment and use the information
More informationIDENTIFYING DISC COUPLING FAILURES COUPLING FUNDAMENTALS
IDENTIFYING DISC COUPLING FAILURES While couplings are designed for infinite life, they must be operated within their intended design limits in order to achieve optimal performance. Due to installation
More informationSPRING HANGERS, SPRING SUPPORTS PRODUCT GROUP
SPRING HANGERS, SPRING SUPPORTS PRODUCT GROUP VARIABLE SPRING ELEMENTS CONTENTS PAGE 0 Spring hangers, spring supports, sway braces.1 Load table for spring hangers, spring supports and other spring elements.3
More informationDalchully, Laggan PH20 1BU, UK T: +44 (0) E: W:
Dalchully, Laggan PH20 1BU, UK T: +44 (0) 1528 544 201 E: angus@adac-structures.co.uk W: www.adac-structures.co.uk Location map for various sites Job name: Condition report into foundations of various
More informationReviewed: DD Month University Code of Practice for Electrical Safety. PART B - Design and Construction of Electrical Equipment within the University
Safety Office Reviewed: 17 July 2012 Reviewed: DD Month University Code of Practice for Electrical Safety PART B - Design and Construction of Electrical Equipment within the University The purpose of this
More informationDYNAMIC PILE TESTING 10/26/ General.
te: The MoDOT LRFD Bridge Design Manual indicates that the frequency of dynamic pile testing should be 1 to 10% of the number of piles. Additionally, the frequency of initial driving tests and restrike
More informationHigher National Unit Specification. General information for centres. Electrical Motor Drive Systems. Unit code: DN4K 35
Higher National Unit Specification General information for centres Unit code: DN4K 35 Unit purpose: This Unit has been designed to allow candidates to develop a knowledge and understanding of electrical
More informationHigher National Unit Specification. General information for centres. Electrical Motors and Motor Starting. Unit code: DV9M 34
Higher National Unit Specification General information for centres Unit title: Electrical Motors and Motor Starting Unit code: DV9M 34 Unit purpose: This Unit has been developed to provide candidates with
More informationCPCS renewal test factsheet
CPCS renewal test factsheet Introduction to the CPCS renewal test The industry-led CPCS Management Committee has determined that key safety-related knowledge must be checked on each category prior to the
More informationSpeeding. Standard Operating Procedure
Speeding Standard Operating Procedure Notice: This document has been made available through the Police Service of Scotland Freedom of Information Publication Scheme. It should not be utilised as guidance
More informationGuideline for Parallel Grid Exit Point Connection 28/10/2010
Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND
More informationGMD 13 New gravimetric measuring system with evaluation on location
Dr. Födisch Umweltmesstechnik AG Zwenkauer Strasse 159 04420 Markranstädt Germany Phone: +49 34205 755-0 Fax: +49 34205 755-40 E-mail: sales@foedisch.de Internet: www.foedisch.de GMD 13 New gravimetric
More informationPowerlock Termination Guide
Powerlock Termination Guide Contents Index 1. OVERVIEW... 2 2. TERMINATION METHODS... 2 2.1 CRIMP TERMINATION... 2 2.1.1 Crimp Connector Components... 2 2.1.3 Crimp Tool... 3 2.1.4 Crimp Assembly Tools...
More informationAPPENDIX D. D.1 Macalloy Bars. Approximate safe working loads (kn) Appendix D - Proprietary Components (1/9) Stainless steel architectural ties
Appendix D - Proprietary Components (1/9) APPENDIX D D.1 Macalloy Bars Bar dia. mm Stressing ties Stainless steel stressing ties Stainless steel architectural ties High strength Tie rods grades precision
More informationPAGE 1 OF 5 HEALTH, SAFETY & ENVIRONMENTAL MANUAL PROCEDURE: S360 Overhead Cranes & Lifts Procedure REV 4.0 8/14/2012
PAGE 1 OF 5 PURPOSE: OVERHEAD CRANES AND LIFTS PROCEDURE The purpose of this procedure is to define the safety and training requirements for use of overhead cranes and lifts. Procedure: Definitions Designated
More informationDirectivity of the CoRTN road traffic noise model
Proceedings of th International Congress on Acoustics, ICA 10 23-27 August 10, Sydney, Australia Directivity of the CoRTN road traffic noise model Simon Moore, Matthew Stead and Jonathan Cooper AECOM,
More informationCARES Technical Approval Report TA1C
CARES Technical Approval Report TA1C - 5057 Issue 1 LENTON Standard, Position, Parallel Bolt Couplers and Mechanical Anchor Assessment of the LENTON Standard, Standard Transition, Position, Parallel Bolt
More informationN Daily Weekly Monthly Every 3 months. Every 6 months 1 Remove any materials not related
MV / LV cabins maintenance The operation and maintenance of the cabins are meant to ensure high reliability (i.e. the early detection of anomalies, the failure prevention and monitoring functional) and
More informationTRANSDUCERS. Conversion of Measured Strain or Output Voltage into Physical Quantity. Sensitivity Decrease due to Cable Extension
2-2 Strain gage transducers are designed to transduce physical variables such as load, force, pressure, acceleration, vibration, displacement and torque into electric signals by using strain gages as sensing
More informationVehicle Details. Inspection Summary. Tyre Tread (mm) Front Suspension / Steering. Road Test & Final Checks
Mr Aaron Rodgers Your check was conducted on 07 Mar 2016 R A C House RAC Engineer Peter Cullingworth Walsall Place of inspection DA3 8PU West Midlands Weather during inspection Dry WS5 4AW Light Conditions
More informationTEST REPORT. Ceram Reference: (QT21489/2/SL)/Ref: 1.0A. Tensile and Frictional Tests on the Fast Fit BeamClamp Systems.
TEST REPORT Ceram Reference: 121557 (QT21489/2/SL)/Ref: 1.0A Project Title: Tensile and Frictional Tests on the Fast Fit BeamClamp Systems Client: Kee Safety Limited For The Attention of: Mr Phil Higgs
More informationAppendix 3. DRAFT Policy on Vehicle Activated Signs
Appendix 3 DRAFT Policy on Vehicle Activated Signs Ealing Council has been installing vehicle activated signs for around three years and there are now 45 across the borough. These signs help to reduce
More informationConveyor Condition Monitoring. Increase uptime, decrease damage, plan repairs, avoid disaster
Conveyor Condition Monitoring Increase uptime, decrease damage, plan repairs, avoid disaster Reliability through Condition Based Monitoring Benefits: Early identification of potential failures Reduce correction
More informationCPCS renewal test factsheet
CPCS renewal test factsheet Introduction to the CPCS renewal test The industry-led CPCS Management Committee has determined that key safety-related knowledge must be checked on each category prior to the
More informationPVP Field Calibration and Accuracy of Torque Wrenches. Proceedings of ASME PVP ASME Pressure Vessel and Piping Conference PVP2011-
Proceedings of ASME PVP2011 2011 ASME Pressure Vessel and Piping Conference Proceedings of the ASME 2011 Pressure Vessels July 17-21, & Piping 2011, Division Baltimore, Conference Maryland PVP2011 July
More informationINME 4011 Term Project Guideline
INME 4011 Term Project Guideline Each team consists of four students (maximum). The projects are described in the attached document. First part of the project includes the calculation of the shaft diameter
More informationFUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER C: DESIGN BASIS AND GENERAL LAYOUT 4. CONTROL-ROD DRIVE MECHANISM
PAGE : 1 / 12 4. CONTROL-ROD DRIVE MECHANISM 4.0. SAFETY REQUIREMENTS 4.0.1. Safety functions The control rod drive mechanisms [CRDMs] carry out the following safety functions: Reactivity control during
More informationOntario ENGINEERING STANDARD SPECIFICATION 1.0 PURPOSE 2.0 OVERHEAD CRANES
1/5 1.0 PURPOSE This specification describes the minimum requirements for all activities involving hoisting, moving or transporting cargo using equipment such as mobile cranes, hoisting equipment in underground
More informationCONTENTS. Model & Parameter List 3. Installation Specification of Guyed Tower 5. Installation Specification of Tapered Tower 13
USER S MANUAL 1 CONTENTS Model & Parameter List 3 Installation Specification of Guyed Tower 5 Installation Specification of Tapered Tower 13 Configuration Specification of Batteries 15 Electric Wiring
More informationReport of Inspection
P. O. Box 8238 Searcy, AR 72145 866.811.5237 / 501.279.1166 Fax: 501.279.1225 As required by NFPA 1911 19.3: CFS Inspections is accredited to the requirements of ISO/IEC 17020. Report of Inspection SAFET
More informationRescue Hoist Ground Support Equipment
Rescue Hoist Ground Support Equipment Zephyr International LLC 120 Royal Manor Rd. Easton, PA 18042 USA zephyrintl@rcn.com Page 1 of 6 Introduction: Helicopter rescue hoists use tension rollers to keep
More informationThe FRACOF Composite Slab Test
The FRACOF Composite Slab Test Experiment, Predictions & Results Anthony Abu & Ian Burgess Fire Resistance Assessment of partially protected COmposite Floors - FRACOF Introduction To increase the use of
More information8.3kV, 9.9kV, 15.5kV, 17.2kV and 23kV Cooper ELSP Backup Fuses Testing per C
CP No.: CP1101 Rev. 00 Page: 1 of 9 CERTIFIED TEST REPORT 8.3, 9.9, 15.5, 17.2 and 23 Cooper ELSP Backup Fuses Testing per C37.41-2008 Rev. 00 DATE: May 3, 2011 ORIGINAL REPORT DATE: May 3, 2011 Cooper
More informationY-fl'. MINISTRY OF TRANSPORT AND COMMUNICATIONS DEPARTMENT OF MARINE ADMINISTRATION
MINISTRY OF TRANSPORT AND COMMUNICATIONS DEPARTMENT OF MARINE ADMINISTRATION No-363/421, Corner of Merchant & Theinbyu Road, Botataung Township, Yangon, Myanmar E-mail : d gdma.mm@ gmail.com; dma.myan@smail.com
More informationA Recommended Approach to Pipe Stress Analysis to Avoid Compressor Piping Integrity Risk
A Recommended Approach to Pipe Stress Analysis to Avoid Compressor Piping Integrity Risk by: Kelly Eberle, P.Eng. Beta Machinery Analysis Calgary, AB Canada keberle@betamachinery.com keywords: reciprocating
More informationInstallation and Maintenance Manual CORRUGATED RIVETED GALVANIZED STEEL WATER STORAGE TANKS
BH TANK A Division Of American Tank Co., Inc. Installation and Maintenance Manual CORRUGATED RIVETED GALVANIZED STEEL WATER STORAGE TANKS American Tank Co., Inc. P.O. Box 340 Windsor CA 95492 www.bhtank.com
More informationGuideline No.: E-03(201806) E-03 MOTORS. Issued date: June 7, China Classification Society
Guideline No.: E-03(201806) E-03 MOTORS Issued date: June 7, 2018 China Classification Society Foreword: This Guideline is a part of CCS Rules, which contains technical requirements, inspection and testing
More informationDowntown Lee s Summit Parking Study
Downtown Lee s Summit Parking Study As part of the Downtown Lee s Summit Master Plan, a downtown parking and traffic study was completed by TranSystems Corporation in November 2003. The parking analysis
More informationInstallation, Care and maintenance
Installation, Care and maintenance DOCK-LOCK TM, Lifting system 892434/04 CONTENTS Safety 2 Guarantee 3 Data plate interpretation 3 Product description 4 Materials 4 Dimensions 4 Operation 8 Safety precautions
More informationدبي لحلول االستشعار. Active Load Brochure Load Cells
Active Load Brochure Load Cells www.dusense.ae +97148135972 info@dusense.ae Load Measuring Shackles DuSense is Middle-East Agent by Active Load to provide complete transducer solution designing and manufacturing
More informationEarth-Rite MGV Mobile Grounding Verification. White Paper. Author Details: Page 1 of 5
White Paper Author Details: Mike O Brien, Head of Marketing and Sales for Newson Gale If you have any questions relating to the topics discussed in this article, you can contact Mike directly at: mike.obrien@hoerbiger.com
More informationINSTRUCTIONS FOR USE CAUTIONS AND WARNINGS
SECTION 3 General INSTRUCTIONS FOR USE CAUTIONS AND WARNINGS Commercial shackles are not to be used for lifting purposes. Should extreme circumstances or shock loadings be applicable, this must be taken
More informationENGINEERING REPORT RE11049
Subject Client Client Address Analysis of Proposed Load Restraint Configurations for Round Cotton Modules B-Safe Winches Australia (a Division of Dangerous Goods Equipment Pty Ltd) PO Box 4029 Eight Mile
More informationPASSING ABILITY OF SCC IMPROVED METHOD BASED ON THE P-RING
PASSING ABILITY OF SCC IMPROVED METHOD BASED ON THE P-RING K D Chan*, Leppo Concrete Sdn Bhd, Malaysia K C G Ong, National University of Singapore, Singapore C T Tam, National University of Singapore,
More informationImproving predictive maintenance with oil condition monitoring.
Improving predictive maintenance with oil condition monitoring. Contents 1. Introduction 2. The Big Five 3. Pros and cons 4. The perfect match? 5. Two is better than one 6. Gearboxes, for example 7. What
More informationELMS1 Overload protection
Force measurement ELMS1 Overload protection Certified safety PL d acc. DIN EN ISO 13849 Certified system solution for overload protection Reliable overload prevention for protecting people and materials:
More informationLow and medium voltage service. Power Care Customer Support Agreements
Low and medium voltage service Power Care Customer Support Agreements Power Care Power Care is the best, most convenient and guaranteed way of ensuring electrification system availability and reliability.
More informationTime-Dependent Behavior of Structural Bolt Assemblies with TurnaSure Direct Tension Indicators and Assemblies with Only Washers
Time-Dependent Behavior of Structural Bolt Assemblies with TurnaSure Direct Tension Indicators and Assemblies with Only Washers A Report Prepared for TurnaSure, LLC Douglas B. Cleary, Ph.D., P.E. William
More informationSAFETY ARTIC TIPPER GUIDANCE - PREVENTING OVERTURNS LAFARGETARMAC.COM
SAFETY ARTIC TIPPER GUIDANCE - PREVENTING OVERTURNS LAFARGETARMAC.COM DRIVING SAFETY SAFETY Lafarge Tarmac loads approximately 8500 deliveries each week on articulated vehicles. The safe delivery of product
More informationIndex. The Benefits of Experience 2. Design and Manufacture 3. Quality 3. Slides and Hooks 4-7. Gambrels & S Hooks 8. Beef Rollers 9.
Index The Benefits of Experience 2 Design and Manufacture 3 Quality 3 Slides and s 4-7 Gambrels & S s 8 Beef Rollers 9 Bleeders 10 Other Components 11-12 Notes on 13 Page 1 The Benefits of Experience.
More informationEligibility Criteria to Undertake an Advanced Technical Test
Eligibility Criteria to Undertake an Advanced Technical Test 1. The Scheme is supported by a cache of trained, experienced and qualified testers. It is essential that testers working within the Scheme
More informationFINAL REPORT CATHODIC PROTECTION EVALUATION. 42-Inch Water Transmission Pipeline Contract 1 Station 0+00 to South Texas Water Authority
FINAL REPORT CATHODIC PROTECTION EVALUATION 42-Inch Water Transmission Pipeline Contract 1 Station 0+00 to 50+00 South Texas Water Authority Prepared for: South Texas Water Authority P.O. Box 1701 Kingsville,
More informationOVERALL INSPECTION AND INTEGRITY ASSESSMENT OF OIL AND OIL PRODUCTS STORAGE TANKS R.S.
OVERALL INSPECTION AND INTEGRITY ASSESSMENT OF OIL AND OIL PRODUCTS STORAGE TANKS R.S. Gaspariants., G.A. Giller (JSC VNIIST, RUSSIA) L.Y. Mogilner., Y.Y. Semin (CJSC VNIIST-Diagnostika, RUSSIA) Steel
More informationEGR MASS FLOW SYSTEM CONVERSION KIT (FROM TWO-PIECE TUBE WITH BELLOWS-TYPE CONNECTIONS TO ONE-PIECE TUBE WITH HOSE CONNECTIONS) ASET AC ENGINES
SERVICE BULLETIN REV (Not applicable to Mack Trucks Australia) (Supersedes SB-214-026 dated 2/2/04) NUMBER: SB-214-026 DATE: 7/30/04 MODEL: ASET AC EGR MASS FLOW SYSTEM CONVERSION KIT (FROM TWO-PIECE TUBE
More informationGuideline No.: E-03(201610) E-03 MOTORS. Issued date: October 28,2016. China Classification Society
Guideline No.: E-03(201610) E-03 MOTORS Issued date: October 28,2016 China Classification Society Foreword: This Guideline is a part of CCS Rules, which contains technical requirements, inspection and
More informationReport No.: Name of Ship: Plans referred during Initial Survey:
Report on the Surveys Concerning International Oil Pollution Prevention Certificate Part 7 Survey of installation for discharges from cargo spaces Initial/ Annual/ Intermediate/ Renewal/ Change of Flag
More informationCONTROLLER DIAGNOSTIC GUIDE
Proprietary tice: This document contains proprietary information which not to be reproduced, transferred, to other documents, disclosed to others, used for manufacturing or any other purpose without the
More informationSYDNEY TRAMWAY MUSEUM TROLLEY WIRE INSPECTION PROCEDURE
TROLLEY WIRE INSPECTION PROCEDURE JUNE 2014 1. Document Details: Name: SYDNEY TRAMWAY MUSEUM Document Control Record Number STM 6029 Version Number: 15 TrolleyWire Inspection Procedure Document Status:
More information3.2. Current Limiting Fuses. Contents
.2 Contents Description Current Limiting Applications................. Voltage Rating.......................... Interrupting Rating....................... Continuous Current Rating................ Fuse
More informationGB NDT AXLE TESTING & DEFECT TYPES FOUND
Applied Inspection Ltd GB NDT AXLE TESTING & DEFECT TYPES FOUND ESIS TC24 Workshop at RSSB 03/04 March 2011 Presented by Roy Archer (Technical Manager Rail - Level 3) Manual ultrasonic testing used for
More informationModel H30 Operation Manual
Model H30 Operation Manual Model H30 Version 1.0 August 1, 2007 2 135 West Davenport Street Rhinelander WI 54501 Phone: 866.441.7997 Fax: 866.278.0036 info@houstonst.com www.houstonst.com 3 Table of Contents
More informationREPEATABILITY OF CPX TYRE/ROAD NOISE MEASUREMENTS. Gillian Adams, Frits Kamst and Stephen Pugh ASK Consulting Engineers, Brisbane, Australia
ICSV14 Cairns Australia 9-12 July, 2007 REPEATABILITY OF CPX TYRE/ROAD NOISE MEASUREMENTS Gillian Adams, Frits Kamst and Stephen Pugh ASK Consulting Engineers, Brisbane, Australia frits@askce.com ABSTRACT
More information+91-8048764079 Crane Engineering Works http://www.craneengg.net/ We are one of the most renowned manufacturer and supplier of a wide array of Material Handling Equipment. The products offered by us are
More informationFletcher Moorland Ltd. Electric Motor Repair Specification
Fletcher Moorland Ltd Electric Motor Repair Specification Fletcher Moorland promotes best practice and reliability throughout its business. As an SKF certified rebuilder for electric motors we ensure each
More informationBUREAU OF STANDARDS. Effective Date: 8/19/2016 Section No. 4. Version: 1.2 Procedure No. 3
BUREAU OF STANDARDS Effective Date: 8/19/2016 Section No. 4 Version: 1.2 Procedure No. 3 TITLE: LP Gas Bulk Plant Final Inspection PURPOSE: This document details the procedures used to conduct a Final
More informationTOW & LOAD ASSESSMENT $75 WHAT S YOUR TOWING AND LOAD CARRYING SCENARIO? pedders.com.au. Pedders / 1
$75 K N O W Y O U R W E I G H T WHAT S YOUR TOWING AND LOAD CARRYING SCENARIO pedders.com.au Pedders / 1 Preface Since 1950, Pedders has been Australia s trusted undercar parts specialist. With over 130
More informationArc Weldable Vibrating Wire Strain Gauge. User Manual. Man /08/14 Lucie Williams Phil Day Chris Rasmussen
Arc Weldable Vibrating Wire Strain Gauge Man 175 6.1.0 06/08/14 Lucie Williams Phil Day Chris Rasmussen Manual No. Revision Date Originator Checked Authorised for Issue 1 Contents Section 1 : Foreword...
More informationDEVELOPMENTAL HALT Report R XSS S Power Supplies. Michael Farragher Engineering Test Technician Test Performed By
DEVELOPMENTAL HALT Report Product Tested: Service Proposal #: XSS00-24S Power Supplies S00000354 Job #: J09135-5198 Date Received: th March 2014 Test Dates: th to 14 th March 2014 Report Date: 4 th March
More informationSTANDARDS PRESENTATION Attachment No. 1 TO Page 1 of 6 CALIFORNIA OCCUPATIONAL SAFETY AND HEALTH STANDARDS BOARD
TO Page 1 of 6 TITLE 8: Division 1, Chapter 4, Subchapter 4. Construction Safety Orders Article 12. Pile Driving and Pile Extraction [Notes in italics are editorial notes and generally refer to A10.19
More informationTitle: Lifting Operations Involving Crane or Gantry Offshore
PTW CHECKLIST - NO. 30 Title: Lifting Operations Involving Crane or Gantry Offshore Owner: Capability Coordinator Approver: Capability Coordinator Permit No.: Max Validity Period: 5 yrs Date: Latest Rev
More informationPROCEDURE. Operative Date: 22/12/2016 Department: HSEC. Revision: Author: D Steel CONTENTS
Title: Cranes - Inspection and Maintenance PROCEDURE Procedure No: P314.422 Issue: 1 Revision: 0 Operative Date: 22/12/2016 Department: HSEC Sect./Classification: Safety / Gear & Equipment Author: D Steel
More informationSubstation Lightning Protection. Document Number: 1-11-FR-11
Substation Lightning Protection Document Number: 1-11-FR-11 VERSION 1.0 June 2018 This functional requirements document is in line with the organisation's 1-11-ACS-11 Substation Lightning Protection Asset
More informationSBS Range Rain Gauge User Manual
SBS Range Rain Gauge User Manual PUBLISHED BY Environmental Measurements Limited (EML) 7 Jupiter Court Orion Business Park North Shields NE29 7SE United Kingdom Visit our internet pages at http://www.emltd.net
More informationCrane & Hoist Safety Guidelines
Purpose Crane & Hoist Safety Guidelines Many types of cranes, hoists, and rigging devices are used at [COMPANY] for lifting and moving materials. [COMPANY]'s policy is to maintain a safe workplace for
More informationPIPINGSOLUTIONS, INC.
Piping Stress Analysis Where do I start? The following information will take you step-by-step through the logic of the data collection effort that should occur prior to beginning to model a piping system
More informationInspection and Assessment of Track Geometry
Purpose This document defines requirements for inspection and assessment of track geometry. This document applies to all infrastructure on the Victorian Regional Infrastructure Lease managed by V/Line
More informationCARES Technical Approval Report TA1B
CARES Technical Approval Report TA1B - 5029 Issue 4 LENTON Standard, Standard Transition, Position, Position Transition, Parallel Bolt Couplers and Mechanical Anchors Assessment of the LENTON Standard,
More informationLow-torque Deep-groove Ball Bearings for Transmissions
New Product Low-torque Deep-groove Ball Bearings for Transmissions Katsuaki SASAKI To achieve low fuel consumption in response to environmental concerns, we have focused on reducing the friction of tapered
More informationWelded Steel Conveyor Pulleys
ANSI / CEMA B105.1-2009 A REVISION OF ANSI/CEMA B105.1-2003 (Approved May 19, 2009) CEMA Standard B105.1 Specifications for Welded Steel Conveyor Pulleys With Compression Type Hubs Conveyor Equipment Manufacturers
More informationSurface- and Pressure-Dependent Characterization of SAE Baja Tire Rolling Resistance
Surface- and Pressure-Dependent Characterization of SAE Baja Tire Rolling Resistance Abstract Cole Cochran David Mikesell Department of Mechanical Engineering Ohio Northern University Ada, OH 45810 Email:
More informationINSPECTION AND MAINTENANCE CHECKLIST
INSPECTION AND MAINTENANCE CHECKLIST Lattice-Boom Crawler Cranes Models 111-21000 & MLC Series Does Not Apply to Small Crawler Models or Model 31000 This record applies to the following crane: Crane Model:
More informationClick. Campbell Fittings Table of Contents. on the section you want
Campbell Fittings Table of Contents Click on the section you want Contents Clips, Forged Wire Rope Eyebolts Eyes, Lifting Hooks, Grab/Slip Hooks, Hoist Hooks, Latch Kits For Links Links, Clevis Links,
More information7.9.8 Elctromagnetism
7.9.8 Elctromagnetism 71 minutes 86 marks Page 1 of 25 Q1. The diagram shows an electromagnet used in a door lock. (a) The push switch is closed and the door unlocks. Explain in detail how this happens.
More informationArtesis MCM Case Studies. March 2011
Artesis MCM Case Studies March 2011 Case 1 Automotive Company: Automobile Manufacturer A Equipment: Pump Stator Isolation Breakdown Decreasing current unbalance level Case 1 Automotive Company: Automobile
More informationREDUCING THE OCCURRENCES AND IMPACT OF FREIGHT TRAIN DERAILMENTS
REDUCING THE OCCURRENCES AND IMPACT OF FREIGHT TRAIN DERAILMENTS D-Rail Final Workshop 12 th November - Stockholm Monitoring and supervision concepts and techniques for derailments investigation Antonella
More informationUSER MANUAL RHF SERIES
Hukseflux Thermal Sensors USER MANUAL RHF SERIES Ring heat flux sensors Copyright by Hukseflux manual v1824 www.hukseflux.com info@hukseflux.com Warning statements Follow the installation instructions
More informationINSTITUTE FOR SCIENCE AND INTERNATIONAL SECURITY
INSTITUTE FOR SCIENCE AND INTERNATIONAL SECURITY IMAGERY BRIEF Correlating the Operation of the Coal Plant to Reprocessing Activities at Yongbyon By David Albright, Olli Heinonen,* and Serena Kelleher-Vergantini
More informationDesign Tests for the 38.0 kv ELSP Current-limiting Fuse per ANSI/IEEE C
Page:1 of 9 CERTIFIED TEST REPORT Design Tests for the 38.0 kv ELSP Current-limiting Fuse per ANSI/IEEE C37.41-2008 REV. 00 August 11, 2014 Original Report Date: August 11, 2014 Eaton s Cooper Power Systems
More informationKEEP FOR FUTURE REFERENCE LADDER LIFT READ ALL INSTRUCTIONS AND WARNINGS BEFORE OPERATING THIS PRODUCT
KEEP FOR FUTURE REFERENCE P.O. Box 368 908 West Main Laurel, MT USA 59044 phone 800-548-7341 phone 406-628-8231 fax 406-628-8354 INSTRUCTIONS International Version MODEL NUMBER: LW185 SERIAL NUMBER: (please
More informationFuelsManager and Radar Tank Gauging for Overfill Prevention
White Paper November 12, 2009 FuelsManager and Radar Tank Gauging for Overfill Prevention Considerations for replacing your existing mechanical float switches with radar technology for continuous overfill
More informationDRIVER SPEED COMPLIANCE WITHIN SCHOOL ZONES AND EFFECTS OF 40 PAINTED SPEED LIMIT ON DRIVER SPEED BEHAVIOURS Tony Radalj Main Roads Western Australia
DRIVER SPEED COMPLIANCE WITHIN SCHOOL ZONES AND EFFECTS OF 4 PAINTED SPEED LIMIT ON DRIVER SPEED BEHAVIOURS Tony Radalj Main Roads Western Australia ABSTRACT Two speed surveys were conducted on nineteen
More informationMonitoring of Shoring Pile Movement using the ShapeAccel Array Field
2359 Royal Windsor Drive, Unit 25 Mississauga, Ontario L5J 4S9 t: 905-822-0090 f: 905-822-7911 monir.ca Monitoring of Shoring Pile Movement using the ShapeAccel Array Field Abstract: A ShapeAccel Array
More informationRisk Management of Rail Vehicle Axle Bearings
Railway Group Standard Risk Management of Rail Vehicle Axle Bearings Synopsis This Railway Group Standard mandates that there shall be riskbased processes to minimise and detect failures of rail vehicle
More informationIn-Place-Inclinometer Installation Manual
Geotechnical Instrumentation In-Place-Inclinometer Installation Manual SDI-12/RS485 Digital Network Device Vertical I-P-I Chain Operations Only Last updated Nov 2013 Keynes Controls In-place-inclinometer
More information