PREPARED FOR: City of Richmond 6911 No 3 Road Richmond, B.C. V6Y 2C1. AUTHORED BY: AES Engineering Ltd.

Size: px
Start display at page:

Download "PREPARED FOR: City of Richmond 6911 No 3 Road Richmond, B.C. V6Y 2C1. AUTHORED BY: AES Engineering Ltd."

Transcription

1 Report For Electric Vehicle Charging Infrastructure in New Multifamily Developments - Requirement Options and Costing Analysis Electrical Engineering Services PREPARED FOR: 6911 No 3 Road Richmond, B.C. V6Y 2C1 AUTHORED BY: AES Engineering Ltd. PEER REVIEWED BY: Kevin Cheong P.Eng., RCDD, LEED AP BD+C SUBMITTED BY: AES Engineering Ltd Granville Street Vancouver, BC Canada V6Z 1M7 P F PROECT NO April 4, 2017

2 Electric Vehicle Charging Requirements Analysis TABLE OF CONTENTS 1.0 SCOPE General DEFINING EV INFRASTRUCTURE REQUIREMENTS AND TECHNOLOGIES General Infrastructure Definitions Load Management and Load Sharing RECOMMENDATIONS ON POLICY FOR EV INFRASTRUCTURE General Minimum Performance Levels Accommodating Load Management and Load Sharing Billing Systems Mechanisms To Ensure Availability Of Charging ASSESSMENT OF DIFFERENT EV INFRASTRUCTURE REQUIREMENTS Life Cycle Costing Qualitative Commentary CONCLUSIONS Recommendations... 8 Appendix A Appendix B Appendix C Appendix D Appendix E Appendix F Appendix G Appendix H Appendix I Appendix Appendix K Appendix L Costing Analysis Costing Analysis Partial Infrastructure Parkade Layouts Single Line Diagrams Metering Data Proposed CEC Changes Performance Analysis Right-to-Charge Legislation Load Calculations Definitions Example Bylaw Acknowledgements AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

3 Electric Vehicle Charging Requirements Analysis Page SCOPE 1.1 GENERAL The s Official Community Plan (OCP) includes a target to reduce Richmond s community greenhouse gas emissions 80% below 2007 levels by Richmond s Community Energy and Emissions Plan (CEEP) identifies that to reach this target will require near universal adoption of zero carbon vehicles by the 2040s. The CEEP includes Strategy 7 to Promote Low Carbon Vehicles, and actions pursuant to this strategy. The following report addresses Action 18 of the CEEP, which states that the (The City) will set minimum requirements for EV charging infrastructure in new developments, as part of an objective to reduce energy use and greenhouse gas (GHG) emissions. Accordingly, the City is currently reevaluating policies to improve the provision of electric vehicle (EV) infrastructure in new developments, to better enable wide-spread adoption. Multi Unit Residential Building (MURB) construction represents 58% (24,360 units) of the projected increase in residential dwellings from 2011 to 2041, and is the focus of this report. MURB s inherently include the greatest barriers to EV adoption due to the challenges associated with common property. Community charging infrastructure deployment, which is also a fundamental element in the holistic approach to the provision of EV infrastructure is not addressed in the analysis. The report presents the results of an analysis of EV charging infrastructure requirements for Council s Consideration. The assessment included: Development of definitions for charging infrastructure requirements; Recommendation of mechanisms to better ensure effective implementation of in new strata developments; Assessment of costs and benefits of different EV infrastructure requirements. The intent of the assessment was to identify reasonable, cost effective measures, to achieve the greatest value for money, with consideration afforded to both developers and EV owners, whilst remaining cognizant of the fundamental objective to better enable wide-spread adoption. The following sections provide the results of the assessment for each of the major items indicated above. AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

4 Electric Vehicle Charging Requirements Analysis Page DEFINING EV INFRASTRUCTURE REQUIREMENTS AND TECHNOLOGIES 2.1 GENERAL Definitions for key EV infrastructure configurations are provided in the following sub-sections. Appendix includes definitions for other terminology used in this report. 2.2 INFRASTRUCTURE DEFINITIONS The following definitions for EV infrastructure requirements are recommended. (Electric Vehicle Supply Equipment) installed : All infrastructure required for charging of an electrical vehicle (EV), including all electrical equipment (including metering), cabling and associated raceways, and connections, and Level 2 equipment permanently installed. Energized : All infrastructure required for charging of an electric vehicle (EV), including all electrical equipment (including metering), cabling and associated raceways, and connections, with exception of the Level 2 equipment. Partial EV infrastructure (note: not recommended for inclusion in policy): All infrastructure required for charging of an electric vehicle (EV), including all electrical equipment (including metering), cabling and associated raceways, and connections, up to the provisional branch panelboard locations, minus the feeder cabling to the panelboards. Raceways for the feeder cabling to the provisional panelboard locations would be included as part of the Partial EV infrastructure. The branch panelboards and associated feeder cabling, branch cabling and associated raceways, and connections to s would be installed at a later-date. Although Partial EV infrastructure configurations were assessed, it is not recommended for inclusion in City regulation, as detailed in Section 3.1. Refer to single line diagrams (Appendix D) for further details of the components of the EV infrastructure. 2.3 LOAD MANAGEMENT AND LOAD SHARING Load management and load sharing are control technologies that reduce peak power demand and improve utilization of EV charging systems, thereby reducing electrical infrastructure costs. The technologies also provide the capability to control the time of use, which may be utilized in reducing the impact on the Utility s system. Terminology utilized in this report includes: Load management : Control of the current drawn by the, at the main switchboard of the building. AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

5 Electric Vehicle Charging Requirements Analysis Page 3 Load sharing : Control of the current drawn by multiple on a single circuit, to ensure the capacity of the circuit is not exceeded, and that maximum charging is achieved at each based on the available capacity. A number of EV charging service providers offer with load management and/or load sharing functionality. One business model that has been established is to provide equipment capable of load management and load sharing, as well as metering EV electricity consumption to allow for reconciliation of building electrical costs. Providers offering these smart charging services in the market today typically charge a service fee that is paid by the EV owner. This arrangement is assumed in the life cycle costing in Appendix A. However, some providers are emerging that offer capable of load management and/or sharing that are not based on such a subscription model, and could result in reduced costs for end users. 3.0 RECOMMENDATIONS ON POLICY FOR EV INFRASTRUCTURE 3.1 GENERAL If the City intends for all residents of new multifamily developments to have access to at home EV charging, it is recommended that City policy specify that all residential parking stalls be Energized. As part of the Terms of Reference for this study, the City requested commentary on the following question: For parking stalls that are not Energized, should the City specify that remaining stalls feature a Partial EV Infrastructure configuration? The proponent should propose a Partial EV Infrastructure definition that can be included in City regulation. The proponent should then describe the benefits and drawbacks of including this definition in City regulation, and recommend whether it be included. Although Partial EV infrastructure configuration specifications were developed, it is not recommended that the City make reference to this configuration in the requirements due to: Higher costs associated with completion of the installation at a later-date. Appendix B includes Partial Infrastructure costing analysis; Additional time associated with completion of the installation at a later-date; Delays in gaining strata approval; Extending the sales cycle (awaiting installation of charging infrastructure); Common property complications associated with apportioning of costs; Reasonable costs associated with Energized infrastructure; Complications with parking stall re-assignment; AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

6 Electric Vehicle Charging Requirements Analysis Page 4 Disincentive of additional costs for the EV owner, which is contrary to the initiative to encourage EV adoption (i.e. Demand elasticity is high (between 3.0 and 4.0), which means sales are significantly impacted by price); Inclusion of Partial EV infrastructure assumes EV adoption will follow a linear progression as opposed to exponential, which is contrary to the historical record for disruptive technologies. Analysis identifies that Partial EV infrastructure provision represents significantly higher final costs compared to complete (Energized) installations. Depending on building archetype and design, selected infrastructure configuration, and extent of partial provisions, the increase in final costs (with the exception of the townhouse archetype) ranges from 20% to well over 700%. Refer to Appendix B for a summary of results of the Partial EV infrastructure costing analysis. Given acceptance that EV adoption is required to meet GHG emission reduction targets, and widespread projections for exponential growth in uptake of EV s, the logical conclusion is that provision of Partial EV infrastructure incurs additional time and cost on future buildings owners and residents, and is contrary to the objective to better enable wide-spread adoption. On this basis, complete EV infrastructure installation (Energized) should not be viewed from the perspective of an additional cost compared to Partial EV infrastructure, but more appropriately, a cost savings compared to Partial EV infrastructure. 3.2 MINIMUM PERFORMANCE LEVELS As part of the Terms of Reference for this study, the City requested commentary on the following question: Should the City specify a minimum performance level for EV Infrastructure (e.g. a kw minimum; or average and maximum kwh overnight delivered to stalls)? This could preclude load managed designs that provide insufficient power to effectively charge vehicles. The proponent should recommend whether a minimum performance level is necessary, and recommend a performance level if so. The recommended minimum performance level is: A minimum performance level of 12 kwh per, over an eight (8) hour overnight period. Load management and/or load sharing may be implemented. Refer to Appendix G for details of the basis for the minimum performance levels. Analysis indicates that a 40A 208V connection to each parking stall, with circuit sharing of up to four stalls per branch circuit, or equivalent (additional chargers on a circuit of greater ampacity) is sufficient to provide the minimum charging requirement. This is based on provision of load sharing to maximize utilization of circuit ampacity, and to benefit from the capacity pooling effect of sharing, in lieu of restricting each charger to a maximum of 25% of the circuit ampacity. AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

7 Electric Vehicle Charging Requirements Analysis Page 5 The above statements should not be interpreted to preclude the use of alternate configurations to achieve the minimum performance level. It is highlighted that it is not the intent to limit the options of designers, only to establish a minimum performance level to be achieved. A minimum performance level is necessary to ensure an appropriate experience for the EV owner, thereby encouraging EV adoption. It is understood that the City may wish to entertain reduced performance requirements, including Level 1 charging, in some specific instances where average driving distances of residents of a specific building are considered atypical/limited. It is highlighted that the industry is generally coalescing around Level 2 charging due to the reasons of performance requirements (average driving distances) and consumer expectation. Level 2 charging is considerably more consistent with the objective to better enable widespread adoption, and represents a lower initial infrastructure (not including ) installation cost than Level 1 charging where load sharing is implemented. Should there be specific instances where the City considers reducing the requirement to Level 1 it is recommended that some level of performance augmentation, such as the installation of a number of dedicated Level 2 or DC fast chargers, be considered. Metering issues inherent with Level 1 charging would also need to be carefully considered in any such instances. 3.3 ACCOMMODATING LOAD MANAGEMENT AND LOAD SHARING As part of the Terms of Reference for this study, the City requested commentary on the following question: Should the City make any special requirements to ensure that EV infrastructure configurations designed for load management will be able to be used by building occupants? E.g. Should an EV charging infrastructure design be shown to be compatible with specific EV charging service providers offerings (or multiple different service providers)? Should a contractual relationship with an EV charging service provider be demonstrated? The proponent should recommend any requirements appropriate for the City to pursue during its development approvals process. The recommendation is to not preclude load management/load sharing configurations, as many are capable of achieving the minimum performance level, and are cost effective installations. The process of amendment to CSA C22.1 (refer to Appendix F for further details) to clarify the allowance of load management, is in progress. Requirements should allow designs to be based on any system capable of achieving the minimum performance level, and not favor a specific vendor. Contractual relationship with an EV charging service provider whilst to be encouraged for reasons of quality of service, is not necessarily recommended for inclusion in City regulation. Requirements proposed for inclusion during the development approvals process are the definitions and minimum performance levels. Load sharing solutions provide the opportunity to significantly reduce infrastructure costs by avoiding the inherent high costs of dedicated circuits. A Level 2 load sharing installation is less than one-third the cost AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

8 Electric Vehicle Charging Requirements Analysis Page 6 of a dedicated circuit installation; and even less than a Level 1 dedicated circuit installation. Historically, installations and Codes have been based on dedicated circuits. Analysis identifies there are significant opportunities for cost reductions through the implementation of load management and load sharing solutions. The trade-off for the cost benefit is reduced performance and restriction on selection. A minimum performance level requirement, as designated in Section 3.2 addresses the performance issue. In terms of selection, the equipment must be capable of load sharing, which means a networked, as opposed to standalone. At present equipment from various manufacturers is not open protocol and cannot work in a sharing arrangement with equipment from other manufacturers. This means a requirement (at present) to select one manufacturer, at least for each shared circuit, and more realistically/appropriately for each building. Additional benefits of networked systems include monitoring and maintenance features, thereby improving the experience for the EV owner, which better enables wide-spread adoption. It is anticipated that in the future all chargers will be smart chargers with increased features and range of available services and capabilities, eventually including open protocols to allow greater selection and interconnection of equipment. It is also anticipated that capabilities will further develop in relation to instantaneous monitoring of available building electrical capacity to maximize charging performance whilst minimizing infrastructure costs. 3.4 BILLING SYSTEMS To ensure electricity consumption costs are appropriately apportioned to EV owners it is recommended that revenue grade metering (one meter) be provided on electrical distribution equipment feeding equipment. Apportioning of costs as opposed to resale of electricity may then be performed via metering integral to the equipment. Alternatively, as is the case in 20 US states currently, resale of electricity by the strata organization may be performed based on metering integral to equipment, once issues with the BC Utilities Commission Act (and other regulations) are resolved. 3.5 MECHANISMS TO ENSURE AVAILABILITY OF CHARGING The recommendation to avoid Partial EV infrastructure minimizes potential restrictions to charging availability and avoids complexities inherent with parking stall re-assignment. However, it does not eliminate all possible impediments to an EV driver being able to charge. Provincial Right-to-Charge legislation similar to that enacted by the State of California (on September 21, 2014) would ensure availability of charging to MURB residents. Costs associated with the purchase and installation of equipment, electricity consumption costs, and ongoing maintenance of the equipment would be AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

9 Electric Vehicle Charging Requirements Analysis Page 7 borne by the EV owner. Costs associated with Energized provisions would be borne by the developer of the property. California s Right-to-Charge legislation is included in Appendix H. staff have noted their preference for effective provincial Right-to-Charge legislation to ensure access to EV charging in buildings subject to EV infrastructure requirements. In the potential absence of provincial action, City staff note that Right-to-Charge provisions may be included in strata bylaws and/or covenant, which could be secured through rezoning and development approval processes. Potential clauses for such mechanisms are included in Appendix H. 4.0 ASSESSMENT OF DIFFERENT EV INFRASTRUCTURE REQUIREMENTS 4.1 LIFE CYCLE COSTING Analysis identifies the opportunities for significant cost savings through the implementation of load managed and load shared solutions. While the life cycle cost for the 100% AC L1 energized (dedicated) configuration represents the lowest cost over a 20-year period (due to the absence of the Level 2 charger and EV service costs) it comes at the cost of performance. The 100% AC L2 energized (4-way load shared and load managed) configuration represents the least expensive option assessed as achieving the recommended minimum performance level. It also represents the least expensive initial cost of any option (including the 100% AC L1 energized (dedicated) configuration), at an average of $561/stall for the four archetypes. EV service costs include all provider service charges, including incorporation into the provider system, configuration of chargers, monitoring (operation, usage), control of access to chargers (users, time), 24/7 remote support, generation of reports, and software updates. Refer to Appendix A for a complete summary of results of the costing analysis. Cost estimates were primarily developed using RSMeans 2017, with additional review by Mott Electric GP. 4.2 QUALITATIVE COMMENTARY In accordance with Section 3.2 a minimum performance level of 12 kwh (over an eight-hour period), which corresponds to a 65km of charge range is considered a reasonable compromise between performance and price, for a MURB installation in the. The 100% AC L1 energized (dedicated) configuration provides the lowest charging rate at 1.4kW, and the 100% AC L2 energized (dedicated) configuration provides the highest charging rate at 6.3kW. Refer to Appendix G for details of charging rates for the various configurations. AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

10 Electric Vehicle Charging Requirements Analysis Page CONCLUSIONS 5.1 RECOMMENDATIONS The cost analysis identifies the 100% AC L2 energized (4-way load shared and load managed) configuration as a reasonable compromise between price and performance. It also avoids concerns inherent with Partial EV infrastructure installations. Whilst it has been identified as a reasonable solution, it should not preclude other configurations or favor a specific vendor. It is recommended that alternate configurations that can reasonably be verified to achieve the minimum recommended performance level for a specific installation, be deemed acceptable. Solutions that provide an improved performance level are particularly encouraged, to inspire range confidence and maximize the experience for the EV owner, thereby further encouraging EV adoption. For example, a minimal provision (1% - 2% of stalls) of DC Fast charging (in suitably accessible locations) for larger developments (>100 stalls), whilst not included in the recommendations, is encouraged for consideration during the development process, to increase EV adoption, sustainability, and marketability of the development. It is understood the City may have the ability to offset costs associated with EV infrastructure through reduction in the required/designated number of parking stalls. Through implementation of load managed and load shared solutions (as opposed to dedicated circuits) the reduction in parking stalls necessary to offset costs would be minimal (2% 3%). A reduction in parking stall numbers would also be consistent with the trend towards reduced vehicle ownership, increased sharing options and membership, and associated potential future impacts of autonomous vehicles. The larger disruptive technology of battery storage (which EV s are a component) can be expected to play a role in influencing charging infrastructure and equipment in the future. Autonomous and wireless technologies are also expected to impact requirements in the longer-term. We understand that the recommendations are likely to inspire considerable comment and debate from the many and varied stakeholders. For this reason, we recommend further consultation with the various stakeholders, to ensure appropriate opportunity for expression of opinions and due consideration, prior to implementation of any final requirements. With the increasingly rapid developments inherent with this disruptive technology, the perception of the recommendations is also likely to change within a short period of time, and the consultation period would provide such time. AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

11 Electric Vehicle Charging Requirements Analysis Appendix A Costing Analysis AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

12 Appendix A Page 1 ARCHETYPE SUMMARY Archetype Floor Area Suites/ Units Parking Stalls Floors (above grade) Construction Cost Capacity Max. Demand ft 2 No. No. No. $/ft 2 M$ kw kw % High Rise - City Centre 100, Mid Rise - City Centre 100, Mid Rise - Outside City Centre 80, Townhouse - Outside City Centre 20, Loading

13 Appendix A Page 2 COST SUMMARY Installation Cost $ % $/stall 100% AC L1 "energized" (dedicated) High Rise - City Centre 155, ,443 Mid Rise - City Centre 106, Mid Rise - Outside City Centre 119, Townhouse - Outside City Centre 4, % AC L2 "energized" (dedicated) High Rise - City Centre 326, ,023 Mid Rise - City Centre 308, ,448 Mid Rise - Outside City Centre 314, ,314 Townhouse - Outside City Centre 95, , % AC L2 "energized" (dedicated, load managed) High Rise - City Centre 264, ,446 Mid Rise - City Centre 243, ,929 Mid Rise - Outside City Centre 241, ,778 Townhouse - Outside City Centre 11, % AC L2 "energized" (2-way load shared) High Rise - City Centre 177, ,641 Mid Rise - City Centre 158, ,256 Mid Rise - Outside City Centre 145, ,067 Townhouse - Outside City Centre 26, % AC L2 "energized" (4-way load shared) High Rise - City Centre 108, ,005 Mid Rise - City Centre 79, Mid Rise - Outside City Centre 86, Townhouse - Outside City Centre 26, % AC L2 "energized" (4-way load shared & load managed) High Rise - City Centre 82, Mid Rise - City Centre 77, Mid Rise - Outside City Centre 76, Townhouse - Outside City Centre 11, % AC L2 "energized" (panel shared) High Rise - City Centre 174, ,617 Mid Rise - City Centre 149, ,186 Mid Rise - Outside City Centre 163, ,199 Townhouse - Outside City Centre 26, % AC L2 "energized" (12-way load shared, 150A) High Rise - City Centre 168, ,563 Mid Rise - City Centre 164, ,309 Mid Rise - Outside City Centre 158, ,167 Townhouse - Outside City Centre 26, % AC L2 "energized" (18-way load shared, 80A) High Rise - City Centre 83, Mid Rise - City Centre 72, Mid Rise - Outside City Centre 104, Townhouse - Outside City Centre 26,

14 Appendix A Page 3 Initial Cost ($/stall) 3,500 3, % AC L1 "energized" (dedicated) 100% AC L2 "energized" (dedicated) 2,500 2,000 1,500 1, % AC L2 "energized" (dedicated, load managed) 100% AC L2 "energized" (2-way load shared) 100% AC L2 "energized" (4-way load shared) 100% AC L2 "energized" (4-way load shared & load managed) 100% AC L2 "energized" (panel shared) 100% AC L2 "energized" (12-way load shared, 150A) 100% AC L2 "energized" (18-way load shared, 80A) 0 HIGH RISE - CITY CENTRE MID RISE - CITY CENTRE MID RISE - OUTSIDE CITY CENTRE TOWNHOUSE - OUTSIDE CITY CENTRE

15 Appendix A Page 4 Average Initial Cost ($/stall) 3,000 2,500 2,610 2,000 1,500 1,615 1,000 1,174 1,184 1, % AC L1 "ENERGIZED" (DEDICATED) 100% AC L2 "ENERGIZED" (DEDICATED) 100% AC L2 "ENERGIZED" (DEDICATED, LOAD MANAGED) 100% AC L2 "ENERGIZED" (2- WAY LOAD SHARED) 100% AC L2 "ENERGIZED" (4- WAY LOAD SHARED) 100% AC L2 "ENERGIZED" (4- WAY LOAD SHARED & LOAD MANAGED) 100% AC L2 "ENERGIZED" (PANEL SHARED) 100% AC L2 "ENERGIZED" (12- WAY LOAD SHARED, 150A) 100% AC L2 "ENERGIZED" (18- WAY LOAD SHARED, 80A)

16 Appendix A Page 5 COST SUMMARY - LIFE CYCLE Cost ($/stall) Installation EV Service Infrastructure Charger (20 years) Total 100% AC L1 "energized" (dedicated) High Rise - City Centre 1, ,443 Mid Rise - City Centre Mid Rise - Outside City Centre Townhouse - Outside City Centre % AC L2 "energized" (dedicated) High Rise - City Centre 3,023 2,000 6,000 11,023 Mid Rise - City Centre 2,448 2,000 6,000 10,448 Mid Rise - Outside City Centre 2,314 2,000 6,000 10,314 Townhouse - Outside City Centre 2,655 2,000 6,000 10, % AC L2 "energized" (dedicated, load managed) High Rise - City Centre 2,446 2,000 6,000 10,446 Mid Rise - City Centre 1,929 2,000 6,000 9,929 Mid Rise - Outside City Centre 1,778 2,000 6,000 9,778 Townhouse - Outside City Centre 307 2,000 6,000 8, % AC L2 "energized" (2-way load shared) High Rise - City Centre 1,641 2,000 6,000 9,641 Mid Rise - City Centre 1,256 2,000 6,000 9,256 Mid Rise - Outside City Centre 1,067 2,000 6,000 9,067 Townhouse - Outside City Centre 733 2,000 6,000 8, % AC L2 "energized" (4-way load shared) High Rise - City Centre 1,005 2,000 6,000 9,005 Mid Rise - City Centre 628 2,000 6,000 8,628 Mid Rise - Outside City Centre 638 2,000 6,000 8,638 Townhouse - Outside City Centre 733 2,000 6,000 8, % AC L2 "energized" (4-way load shared & load managed) High Rise - City Centre 760 2,000 6,000 8,760 Mid Rise - City Centre 612 2,000 6,000 8,612 Mid Rise - Outside City Centre 566 2,000 6,000 8,566 Townhouse - Outside City Centre 307 2,000 6,000 8, % AC L2 "energized" (panel shared) High Rise - City Centre 1,617 2,000 6,000 9,617 Mid Rise - City Centre 1,186 2,000 6,000 9,186 Mid Rise - Outside City Centre 1,199 2,000 6,000 9,199 Townhouse - Outside City Centre 733 2,000 6,000 8, % AC L2 "energized" (12-way load shared, 150A) High Rise - City Centre 1,563 2,000 6,000 9,563 Mid Rise - City Centre 1,309 2,000 6,000 9,309 Mid Rise - Outside City Centre 1,167 2,000 6,000 9,167 Townhouse - Outside City Centre 733 2,000 6,000 8, % AC L2 "energized" (18-way load shared, 80A) High Rise - City Centre 770 2,000 6,000 8,770 Mid Rise - City Centre 572 2,000 6,000 8,572 Mid Rise - Outside City Centre 768 2,000 6,000 8,768 Townhouse - Outside City Centre 733 2,000 6,000 8,733

17 Electric Vehicle Charging Infrastructure Requirements Appendix A Page 6 20-Year Life Cycle Cost ($/stall) 12, % AC L1 "energized" (dedicated) 10, % AC L2 "energized" (dedicated) 8,000 6,000 4,000 2, % AC L2 "energized" (dedicated, load managed) 100% AC L2 "energized" (2-way load shared) 100% AC L2 "energized" (4-way load shared) 100% AC L2 "energized" (4-way load shared & load managed) 100% AC L2 "energized" (panel shared) 100% AC L2 "energized" (12-way load shared, 150A) 100% AC L2 "energized" (18-way load shared, 80A) 0 HIGH RISE - CITY CENTRE MID RISE - CITY CENTRE MID RISE - OUTSIDE CITY CENTRE TOWNHOUSE - OUTSIDE CITY CENTRE

18 Appendix A Page 7 Average 20-Year Life Cycle Cost ($/stall) 12,000 10,000 10,610 8,000 9,615 9,174 8,751 8,561 9,184 9,193 8,711 6,000 4,000 2, % AC L1 "ENERGIZED" (DEDICATED) 100% AC L2 "ENERGIZED" (DEDICATED) 100% AC L2 "ENERGIZED" (DEDICATED, LOAD MANAGED) 100% AC L2 "ENERGIZED" (2- WAY LOAD SHARED) 100% AC L2 "ENERGIZED" (4- WAY LOAD SHARED) 100% AC L2 "ENERGIZED" (4- WAY LOAD SHARED & LOAD MANAGED) 100% AC L2 "ENERGIZED" (PANEL SHARED) 100% AC L2 100% AC L2 "ENERGIZED" (12-"ENERGIZED" (18- WAY LOAD WAY LOAD SHARED, 150A) SHARED, 80A)

19 Appendix A Page 8 100% AC L1 "energized" (dedicated, no load management) Archetype 1 - High Rise - City Centre Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, ,032 No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 600Y/347V main transformer from 1,000 kva to 1,500 kva 1 21,319 2 Increase rating of main switchboard (and main breaker) from 800 A to 1,200 A 1 7, A, 600Y/347V switchboard circuit breaker 1 2, kva, 600V - 208Y/120V transformer 1 12, A, 208Y/120V switchboard (No Main) 1 9, A, 208Y/120V switchboard circuit breaker 4 10, ft of 2" conduit 4 2, ft of 4#3/0 4 5, A main lugs, 208Y/120V, 42 cct panelboard (with 20 A circuit breakers) 4 19, ft of 2" conduit 18 18, sets of (100 ft of 2#8 + 1#10B) 18 34, Additional electrical room area (ft 2 ) 50 12,500 Cost ( $) 155,895 Cost ( %) 0.62 Cost ($ per stall) 1,443

20 Appendix A Page 9 100% AC L1 "energized" (dedicated, no load management) Archetype 2 - Mid Rise - City Centre Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, ,077 No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 208Y/120V main transformer from 1,000 kva to 1,500 kva 1 3, ,000 A main switchboard (no change) A switchboard circuit breaker 4 10, ft of 2" conduit 4 2, ft of 4#3/0 4 5, A main lugs, 208Y/120V, 42 cct panelboard (with 20 A circuit breakers) 4 19, ft of 2" conduit 21 21, sets of (100 ft of 2#8 + 1#10B) 21 40,195 9 Additional electrical room area (ft 2 ) 20 4,400 Cost ( $) 106,727 Cost ( %) 0.49 Cost ($ per stall) 847

21 Appendix A Page % AC L1 "energized" (dedicated, no load management) Archetype 3 - Mid Rise - Outside City Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 208Y/120V main transformer from 500 kva to 750 kva 1 7,571 2 Increase rating of main switchboard (and main breaker) from 1,600 A to 2,000 A 1 2, A switchboard circuit breaker 4 10, ft of 2" conduit 4 2, ft of 4#3/0 4 5, A main lugs, 208Y/120V, 42 cct panelboard (with 20 A circuit breakers) 4 19, ft of 2" conduit 24 24, sets of (100ft of 2#8 + 1#10B) 24 45,937 9 Additional electrical room area (ft 2 ) 20 3,000 Cost ( $) 119,796 Cost ( %) 1.00 Cost ($ per stall) 881

22 Appendix A Page % AC L1 "energized" (dedicated, no load management) Archetype 4 - Townhouse - Outside City Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): 36 2,500, No. DESCRIPTION QTY COST ($) 1 Increase rating of 25kV - 208Y/120V main transformer from 225 kva to 300 kva 1 3, ft of ¾" conduit sets of (10 ft of 2#12 + 1#12B) Cost ( $) 4,522 Cost ( %) 0.18 Cost ($ per stall) 126

23 Appendix A Page % AC L2 "energized" (dedicated, no load management) Archetype 1 - High Rise - City Centre Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, ,543 No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 600Y/347V main transformer from 1,000 kva to 2,000 kva 1 35,876 2 Increase rating of main switchboard (and main breaker) from 800 A to 1,600 A 1 28, A, 600Y/347V switchboard circuit breaker 1 9, kva, 600V - 208Y/120V transformer 1 36, ,000 A, 208Y/120V switchboard 1 12, A, 208Y/120V switchboard circuit breaker 8 40, ft of two 2" conduit 8 8, ft of two parallel 4#3/0 8 20, A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 8 36, ft of 1" conduit 54 27, sets of (100ft of 2#8 + 1#10B) 54 34, Additional electrical room area (ft 2 ) ,500 Cost ( $) 326,467 Cost ( %) 1.31 Cost ($ per stall) 3,023

24 Appendix A Page % AC L2 "energized" (dedicated, no load management) Archetype 2 - Mid Rise - City Centre Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, ,673 No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 208Y/120V main transformer from 1,000 kva to 2,000 kva 1 18,203 2 Additional 3,000 A main switchboard section (and main breaker) 1 65, A switchboard circuit breaker 10 50, ft of two 2" conduit 10 10, ft of two parallel 4#3/ , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 10 45, ft of 1" conduit 63 31, sets of (100ft of 2#8 + 1#10B) 63 40,195 9 Additional electrical room area (ft 2 ) ,000 Cost ( $) 308,439 Cost ( %) 1.40 Cost ($ per stall) 2,448

25 Appendix A Page % AC L2 "energized" (dedicated, no load management) Archetype 3 - Mid Rise - Outside City Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, ,365 No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 208Y/120V main transformer from 500 kva to 1,500 kva 1 25,810 2 Additional 3,000 A main switchboard section (and main breaker) 1 65, A switchboard circuit breaker 10 50, ft of two 2" conduit 10 10, ft of two parallel 4#3/ , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 10 45, ft of 1" conduit 68 34, sets of (100ft of 2#8 + 1#10B) 68 43,385 7 Additional electrical room area (ft 2 ) ,000 Cost ( $) 314,756 Cost ( %) 2.62 Cost ($ per stall) 2,314

26 Appendix A Page % AC L2 "energized" (dedicated, no load management) Archetype 4 - Townhouse - Outside City Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): 36 2,500, No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 208Y/120V main transformer from 225 kva to 500 kva 1 23,636 2 Increase rating of main switchboard (and main breaker) from 600 A to 1,200 A 1 10,515 3 Increase rating of switchboard circuit breakers from 100 A to 200 A 18 24,042 4 Increase size of 100 ft feeders from 3#3 to 3#3/ ,339 5 Increase rating of panelboards from 100 A to 200 A 18 15, ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1,148 Cost ( $) 95,588 Cost ( %) 3.82 Cost ($ per stall) 2,655

27 Appendix A Page % AC L2 "energized" (dedicated, load managed) Archetype 1 - High Rise - City Centre Stalls: Base cost ($): Base load (kw): (kw): Final load (kw): ,000, available 825 No. DESCRIPTION QTY COST ( $) A, 600Y/347V switchboard circuit breaker 1 9, kva, 600V - 208Y/120V transformer 1 36, ,000 A, 208Y/120V switchboard 1 12, A, 208Y/120V switchboard circuit breaker 8 40, ft of two 2" conduit 8 8, ft of two parallel 4#3/0 8 20, A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 8 36, ft of 1" conduit 54 27, sets of (100 ft of 2#8 + 1#10B) 54 34, Additional electrical room area (ft 2 ) , Load management 1 2,000 Cost ( $) 264,165 Cost ( %) 1.06 Cost ($ per stall) 2,446

28 Appendix A Page % AC L2 "energized" (dedicated, load managed) Archetype 2 - Mid Rise - City Centre Stalls: Base cost ($): Base load (kw): (kw): Final load (kw): ,000, available 835 No. DESCRIPTION QTY COST ( $) 1 Additional 3,000 A main switchboard section 1 15, A switchboard circuit breaker 10 50, ft of two 2" conduit 10 10, ft of two parallel 4#3/ , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 10 45, ft of 1" conduit 63 31, sets of (100 ft of 2#8 + 1#10B) 63 40,195 8 Additional electrical room area (ft 2 ) ,000 9 Load management 1 2,000 Cost ( $) 243,037 Cost ( %) 1.10 Cost ($ per stall) 1,929

29 Appendix A Page % AC L2 "energized" (dedicated, load managed) Archetype 3 - Mid Rise - Outside City Stalls: Base cost ($): Base load (kw): (kw): Final load (kw): ,000, available 461 No. DESCRIPTION QTY COST ( $) 1 Additional 3,000 A main switchboard section 1 15, A switchboard circuit breaker 10 50, ft of two 2" conduit 10 10, ft of two parallel 4#3/ , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 10 45, ft of 1" conduit 68 34, sets of (100 ft of 2#8 + 1#10B) 68 43,385 8 Additional electrical room area (ft 2 ) ,000 9 Load management 1 2,000 Cost ( $) 241,747 Cost ( %) 2.01 Cost ($ per stall) 1,778

30 Appendix A Page % AC L2 "energized" (dedicated, load managed) Archetype 4 - Townhouse - Outside City Stalls: Base cost ($): Base load (kw): (kw): Final load (kw): 36 2,500, available 170 No. DESCRIPTION QTY COST ( $) 1 10 ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1,148 3 Load management 18 9,000 Cost ( $) 11,056 Cost ( %) 0.44 Cost ($ per stall) 307

31 Appendix A Page % AC L2 "energized" (2-way load shared) Archetype 1 - High Rise - City Centre Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, ,184 No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 600Y/347V main transformer from 1,000 kva to 1,500 kva 1 21,319 2 Increase rating of main switchboard (and main breaker) from 800 A to 1,200 A 1 7, A, 600Y/347V switchboard circuit breaker 1 5, kva, 600V - 208Y/120V transformer 1 22, ,200 A, 208Y/120V switchboard 1 11, A, 208Y/120V switchboard circuit breaker 4 20, ft of two 2" conduit 4 4, ft of two parallel 4#3/0 4 10, A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 4 18, ft of 1" conduit 28 14, sets of (100ft of 2#8 + 1#10B) 28 17, Additional electrical room area (ft 2 ) ,000 Cost ( $) 177,229 Cost ( %) 0.71 Cost ($ per stall) 1,641

32 Appendix A Page % AC L2 "energized" (2-way load shared) Archetype 2 - Mid Rise - City Centre Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, ,254 No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 208Y/120V main transformer from 1,000 kva to 1,500 kva 1 3,951 2 Additional 1,200 A main switchboard section (and main breaker) 1 27, A switchboard circuit breaker 6 30, ft of two 2" conduit 6 6, ft of two parallel 4#3/0 6 15, A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 6 27, ft of 1" conduit 32 16, sets of (100ft of 2#8 + 1#10B) 32 20,417 9 Additional electrical room area (ft 2 ) 50 11,000 Cost ( $) 158,205 Cost ( %) 0.72 Cost ($ per stall) 1,256

33 Appendix A Page % AC L2 "energized" (2-way load shared) Archetype 3 - Mid Rise - Outside City Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 208Y/120V main transformer from 500 kva to 1,000 kva 1 21,859 2 Increase rating of main switchboard (and main breaker) from 1,600 A to 3,000 A 1 15, A switchboard circuit breaker 5 25, ft of two 2" conduit 5 5, ft of two parallel 4#3/0 5 12, A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 5 22, ft of 1" conduit 34 17, sets of (100ft of 2#8 + 1#10B) 34 21,693 9 Additional electrical room area (ft 2 ) 20 3,000 Cost ( $) 145,126 Cost ( %) 1.21 Cost ($ per stall) 1,067

34 Appendix A Page % AC L2 "energized" (2-way load shared) Archetype 4 - Townhouse - Outside City Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): 36 2,500, No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 208Y/120V main transformer from 225 kva to 300 kva 1 3,083 2 Increase rating of main switchboard (and main breaker) from 600 A to 800 A 1 3,355 3 Increase rating of switchboard circuit breakers from 100 A to 125 A 18 8,474 4 Increase size of 100 ft feeders from 3#3 to 3#1 18 5,811 5 Increase rating of panelboards from 100 A to 125 A 18 3, ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1,148 Cost ( $) 26,379 Cost ( %) 1.06 Cost ($ per stall) 733

35 Appendix A Page % AC L2 "energized" (4-way load shared) Archetype 1 - High Rise - City Centre Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, ,005 No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 600Y/347V main transformer from 1,000 kva to 1,500 kva 1 21,319 2 Increase rating of main switchboard (and main breaker) from 800 A to 1,200 A 1 7, A, 600Y/347V switchboard circuit breaker 1 2, kva, 600V - 208Y/120V transformer 1 12, A, 208Y/120V switchboard 1 9, A, 208Y/120V switchboard circuit breaker 2 10, ft of two 2" conduit 2 2, ft of two parallel 4#3/0 2 5, A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 2 9, ft of 1" conduit 14 7, sets of (100ft of 2#8 + 1#10B) 14 8, Additional electrical room area (ft 2 ) 50 12,500 Cost ( $) 108,528 Cost ( %) 0.43 Cost ($ per stall) 1,005

36 Appendix A Page % AC L2 "energized" (4-way load shared) Archetype 2 - Mid Rise - City Centre Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, ,044 No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 208Y/120V main transformer from 1,000 kva to 1,500 kva 1 3, ,000 A main switchboard (no change) A switchboard circuit breaker 4 20, ft of two 2" conduit 4 4, ft of two parallel 4#3/0 4 10, A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 4 18, ft of 1" conduit 16 8, sets of (100ft of 2#8 + 1#10B) 16 10,208 9 Additional electrical room area (ft 2 ) 20 4,400 Cost ( $) 79,126 Cost ( %) 0.36 Cost ($ per stall) 628

37 Appendix A Page % AC L2 "energized" (4-way load shared) Archetype 3 - Mid Rise - Outside City Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 208Y/120V main transformer from 500 kva to 750 kva 1 7,571 2 Increase rating of main switchboard (and main breaker) from 1,600 A to 2,000 A 1 4, A switchboard circuit breaker 4 20, ft of two 2" conduit 4 4, ft of two parallel 4#3/0 4 10, A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 4 18, ft of 1" conduit 17 8, sets of (100ft of 2#8 + 1#10B) 17 10,846 9 Additional electrical room area (ft 2 ) 20 3,000 Cost ( $) 86,709 Cost ( %) 0.72 Cost ($ per stall) 638

38 Appendix A Page % AC L2 "energized" (4-way load shared) Archetype 4 - Townhouse - Outside City Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): 36 2,500, No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 208Y/120V main transformer from 225 kva to 300 kva 1 3,083 2 Increase rating of main switchboard (and main breaker) from 600 A to 800 A 1 3,355 3 Increase rating of switchboard circuit breakers from 100 A to 125 A 18 8,474 4 Increase size of 100 ft feeders from 3#3 to 3#1 18 5,811 5 Increase rating of panelboards from 100 A to 125 A 18 3, ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1,148 Cost ( $) 26,379 Cost ( %) 1.06 Cost ($ per stall) 733

39 Appendix A Page % AC L2 "energized" (dedicated, panel shared /4) Archetype 1 - High Rise - City Centre Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, ,005 No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 600Y/347V main transformer from 1,000 kva to 1,500 kva 1 21,319 2 Increase rating of main switchboard (and main breaker) from 800 A to 1,200 A 1 7, A, 600Y/347V switchboard circuit breaker 1 2, kva, 600V - 208Y/120V transformer 1 12, A, 208Y/120V switchboard 1 9, A, 208Y/120V switchboard circuit breaker 4 11, ft of 2" conduit 4 2, ft of 4#3/0 4 5, A main lugs, 208Y/120V, 60 cct panelboard (with 40 A circuit breakers) 4 27, ft of 1" conduit 54 27, sets of (100ft of 2#8 + 1#10B) 54 34, Additional electrical room area (ft 2 ) 50 12,500 Cost ( $) 174,603 Cost ( %) 0.70 Cost ($ per stall) 1,617

40 Appendix A Page % AC L2 "energized" (dedicated, panel shared /4) Archetype 2 - Mid Rise - City Centre Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, ,044 No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 208Y/120V main transformer from 1,000 kva to 1,500 kva 1 3, ,000 A main switchboard (no change) A switchboard circuit breaker 5 25, ft of 2" conduit 5 2, ft of 4#3/0 5 6, A main lugs, 208Y/120V, 60 cct panelboard (with 40 A circuit breakers) 5 34, ft of 1" conduit 63 31, sets of (100ft of 2#8 + 1#10B) 63 40,195 9 Additional electrical room area (ft 2 ) 20 4,400 Cost ( $) 149,462 Cost ( %) 0.68 Cost ($ per stall) 1,186

41 Appendix A Page % AC L2 "energized" (dedicated, panel shared /4) Archetype 3 - Mid Rise - Outside City Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 208Y/120V main transformer from 500 kva to 750 kva 1 7,571 2 Increase rating of main switchboard (and main breaker) from 1,600 A to 2,000 A 1 4, A switchboard circuit breaker 5 25, ft of 2" conduit 5 2, ft of 4#3/0 5 6, A main lugs, 208Y/120V, 60 cct panelboard (with 40 A circuit breakers) 5 34, ft of 1" conduit 68 34, sets of (100ft of 2#8 + 1#10B) 68 43,385 9 Additional electrical room area (ft 2 ) 20 4,400 Cost ( $) 163,014 Cost ( %) 1.36 Cost ($ per stall) 1,199

42 Appendix A Page % AC L2 "energized" (dedicated, panel shared /4) Archetype 4 - Townhouse - Outside City Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): 36 2,500, No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 208Y/120V main transformer from 225 kva to 300 kva 1 3,083 2 Increase rating of main switchboard (and main breaker) from 600 A to 800 A 1 3,355 3 Increase rating of switchboard circuit breakers from 100 A to 125 A 18 8,474 4 Increase size of 100 ft feeders from 3#3 to 3#1 18 5,811 5 Increase rating of panelboards from 100 A to 125 A 18 3, ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1,148 Cost ( $) 26,379 Cost ( %) 1.06 Cost ($ per stall) 733

43 Appendix A Page % AC L2 "energized" (4-way load shared, load managed) Archetype 1 - High Rise - City Centre Stalls: Base cost ($): Base load (kw): (kw): Final load (kw): ,000, available 825 No. DESCRIPTION QTY COST ( $) A, 600Y/347V switchboard circuit breaker 1 2, kva, 600V - 208Y/120V transformer 1 12, A, 208Y/120V switchboard 1 9, A, 208Y/120V switchboard circuit breaker 2 10, ft of two 2" conduit 2 2, ft of two parallel 4#3/0 2 5, A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 2 9, ft of 1" conduit 14 7, sets of (100ft of 2#8 + 1#10B) 14 8, Additional electrical room area (ft 2 ) 50 12, Load management 1 2,000 Cost ( $) 82,049 Cost ( %) 0.33 Cost ($ per stall) 760

44 Appendix A Page % AC L2 "energized" (4-way load shared, load managed) Archetype 2 - Mid Rise - City Centre Stalls: Base cost ($): Base load (kw): (kw): Final load (kw): ,000, available 835 No. DESCRIPTION QTY COST ( $) A switchboard circuit breaker 4 20, ft of two 2" conduit 4 4, ft of two parallel 4#3/0 4 10, A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 4 18, ft of 1" conduit 16 8, sets of (100ft of 2#8 + 1#10B) in 1" conduit 16 10,208 7 Additional electrical room area (ft 2 ) 20 4,400 8 Load management 1 2,000 Cost ( $) 77,175 Cost ( %) 0.35 Cost ($ per stall) 612

45 Appendix A Page % AC L2 "energized" (4-way load shared, load managed) Archetype 3 - Mid Rise - Outside City Stalls: Base cost ($): Base load (kw): (kw): Final load (kw): ,000, available 461 No. DESCRIPTION QTY COST ( $) A switchboard circuit breaker 4 20, ft of two 2" conduit 4 4, ft of two parallel 4#3/0 4 10, A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 4 18, ft of 1" conduit 17 8, sets of (100ft of 2#8 + 1#10B) 17 10,846 7 Additional electrical room area (ft 2 ) 20 3,000 8 Load management 1 2,000 Cost ( $) 76,917 Cost ( %) 0.64 Cost ($ per stall) 566

46 Appendix A Page % AC L2 "energized" (4-way load shared, load managed) Archetype 4 - Townhouse - Outside City Stalls: Base cost ($): Base load (kw): (kw): Final load (kw): 36 2,500, available 170 No. DESCRIPTION QTY COST ( $) 1 10 ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1,148 3 Load management 18 9,000 Cost ( $) 11,056 Cost ( %) 0.44 Cost ($ per stall) 307

47 Appendix A Page % AC L2 "energized" (12-way load shared, on 150A trunk) Archetype 1 - High Rise - City Centre Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, ,214 No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 600Y/347V main transformer from 1,000 kva to 1,500 kva 1 21,319 2 Increase rating of main switchboard (and main breaker) from 800 A to 1,200 A 1 7, A, 600Y/347V switchboard circuit breaker 1 5, kva, 600V - 208Y/120V transformer 1 22, ,200 A, 208Y/120V switchboard 1 11, A, 208Y/120V switchboard circuit breaker 9 19, ft of 1-1/2" conduit 9 14, ft of (3#2/0 + 1#6B) 9 27, A, 2-pole, circuit breaker in enclosure , ft of ¾" conduit 108 4, ft of (2#8 + 1#10B) 108 3, Additional electrical room area (ft 2 ) 50 12,500 Cost ( $) 168,836 Cost ( %) 0.68 Cost ($ per stall) 1,563

48 Appendix A Page % AC L2 "energized" (12-way load shared, on 150A trunk) Archetype 2 - Mid Rise - City Centre Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, ,310 No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 208Y/120V main transformer from 1,000 kva to 1,500 kva 1 3,951 2 Additional 1,600 A switchboard (with main breaker) 1 49, A, 208Y/120V switchboard circuit breaker 11 23, ft of 1-1/2" conduit 11 18, ft of (3#2/0 + 1#6B) 11 33, A, 2-pole, circuit breaker in enclosure , ft of ¾" conduit 126 4, ft of (2#8 + 1#10B) 126 4,020 9 Additional electrical room area (ft 2 ) 20 5,000 Cost ( $) 164,933 Cost ( %) 0.75 Cost ($ per stall) 1,309

49 Appendix A Page % AC L2 "energized" (12-way load shared, on 150A trunk) Archetype 3 - Mid Rise - Outside City Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 208Y/120V main transformer from 500 kva to 1,000 kva 1 21,859 2 Increase rating of main switchboard (and main breaker) from 1,600 A to 3,000 A 1 15, A, 208Y/120V switchboard circuit breaker 12 25, ft of 1-1/2" conduit 12 19, ft of (3#2/0 + 1#6B) 12 36, A, 2-pole, circuit breaker in enclosure , ft of ¾" conduit 136 5, ft of (2#8 + 1#10B) 136 4,339 9 Additional electrical room area (ft 2 ) 20 5,000 Cost ( $) 158,768 Cost ( %) 1.32 Cost ($ per stall) 1,167

50 Appendix A Page % AC L2 "energized" (12-way load shared, on 150A trunk) Archetype 4 - Townhouse - Outside City Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): 36 2,500, No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 208Y/120V main transformer from 225 kva to 300 kva 1 3,083 2 Increase rating of main switchboard (and main breaker) from 600 A to 800 A 1 3,355 3 Increase rating of switchboard circuit breakers from 100 A to 125 A 18 8,474 4 Increase size of 100 ft feeders from 3#3 to 3#1 18 5,811 5 Increase rating of panelboards from 100 A to 125 A 18 3, ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1,148 Cost ( $) 26,379 Cost ( %) 1.06 Cost ($ per stall) 733

51 Appendix A Page % AC L2 "energized" (18-way load shared) Archetype 1 - High Rise - City Centre Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, No. DESCRIPTION QTY COST ( $) 1 1,000 kva, 25kV - 600Y/347V main transformer (no change) 1-2 Increase rating of main switchboard (and main breaker) from 800 A to 1,200 A 1 7, A, 600Y/347V switchboard circuit breaker 1 1, kva, 600V - 208Y/120V transformer 1 7, ft of two 2" conduit 1 1, ft of two parallel 4#3/0 1 2, A main lugs, 208Y/120V, 42 cct panelboard (lugs only) 1 2, A, 2p circuit breakers 6 1, ft of 1-1/4" conduit 6 8, ft of (2#1 + 1#6B) 6 10, A, 2-pole, circuit breaker in enclosure , ft of ¾" conduit 108 4, ft of (2#8 + 1#10B) 108 3, Additional electrical room area (ft 2 ) 50 12,500 Cost ( $) 83,184 Cost ( %) 0.33 Cost ($ per stall) 770

52 Appendix A Page % AC L2 "energized" (18-way load shared) Archetype 2 - Mid Rise - City Centre Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, No. DESCRIPTION QTY COST ( $) 1 1,000 kva, 25kV - 600Y/347V main transformer (no change) 1-2 3,000 A main switchboard (no change) A switchboard circuit breaker 1 5, ft of two 2" conduit 1 1, ft of two parallel 4#3/0 1 2, A main lugs, 208Y/120V, 42 cct panelboard (lugs only) 1 2, A, 2p circuit breakers 7 2, ft of 1-1/4" conduit 7 9, ft of (2#1 + 1#6B) 7 12, A, 2-pole, circuit breaker in enclosure , ft of ¾" conduit 126 4, ft of (2#8 + 1#10B) 126 4, Additional electrical room area (ft 2 ) 20 5,000 Cost ( $) 72,078 Cost ( %) 0.33 Cost ($ per stall) 572

53 Appendix A Page % AC L2 "energized" (18-way load shared) Archetype 3 - Mid Rise - Outside City Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 208Y/120V main transformer from 500 kva to 750 kva 1 7,571 2 Increase rating of main switchboard (and main breaker) from 1,600 A to 2,000 A 1 4, A switchboard circuit breaker 2 10, ft of two 2" conduit 2 2, ft of two parallel 4#3/0 2 5, A main lugs, 208Y/120V, 42 cct panelboard (lugs only) 2 5, A, 2p circuit breakers 9 2, ft of 1-1/4" conduit 9 12, ft of (2#1 + 1#6B) 9 15, A, 2-pole, circuit breaker in enclosure , ft of ¾" conduit 136 5, ft of (2#8 + 1#10B) 136 4, Additional electrical room area (ft 2 ) 20 5,000 Cost ( $) 104,434 Cost ( %) 0.87 Cost ($ per stall) 768

54 Appendix A Page % AC L2 "energized" (18-way load shared) Archetype 4 - Townhouse - Outside City Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): 36 2,500, No. DESCRIPTION QTY COST ( $) 1 Increase rating of 25kV - 208Y/120V main transformer from 225 kva to 300 kva 1 3,083 2 Increase rating of main switchboard (and main breaker) from 600 A to 800 A 1 3,355 3 Increase rating of switchboard circuit breakers from 100 A to 125 A 18 8,474 4 Increase size of 100 ft feeders from 3#3 to 3#1 18 5,811 5 Increase rating of panelboards from 100 A to 125 A 18 3, ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1,148 Cost ( $) 26,379 Cost ( %) 1.06 Cost ($ per stall) 733

55 Electric Vehicle Charging Requirements Analysis Appendix B Costing Analysis Partial Infrastructure AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

56 Appendix B Page 1 AC L2 Energized vs Partial, dedicated, with conduits Energized Partial Later Costs Archetype 1 - High Rise - City Centre Stalls: 108 Stalls (20%): 22 Base cost ($): 25,000,000 Base load (kw): 825 Increase (kw): 718 Final load (kw): 1,543 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 600Y/347V main transformer from 1,000 kva to 2,000 kva 1 35, , Increase rating of main switchboard (and main breaker) from 800 A to 1,600 A 1 28, , A, 600Y/347V switchboard circuit breaker 1 9, , kva, 600V - 208Y/120V transformer 1 36, , ,000 A, 208Y/120V switchboard 1 12, , A, 208Y/120V switchboard circuit breaker 8 40, , ft of two 2" conduit 8 8, , ft of two parallel 4#3/0 8 20, , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 8 36, , ft of 1" conduit 54 27, , sets of (100ft of 2#8 + 1#10B) 54 34, , , Additional electrical room area (ft2) , , Cost ( $) 326, ,033 82,305 Cost ( %) Cost ($ per energized stall) 3,023 13,

57 Appendix B Page 2 AC L2 Energized vs Partial, dedicated, with conduits Energized Partial Later Costs Archetype 2 - Mid Rise - City Centre Stalls: 126 Stalls (20%): 26 Base cost ($): 22,000,000 Base load (kw): 835 Increase (kw): 838 Final load (kw): 1,673 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 1,000 kva to 2,000 kva 1 18, , Additional 3,000 A main switchboard section (and main breaker) 1 65, , A switchboard circuit breaker 10 50, , ft of two 2" conduit 10 10, , ft of two parallel 4#3/ , , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 10 45, , ft of 1" conduit 63 31, , sets of (100ft of 2#8 + 1#10B) 63 40, , ,703 9 Additional electrical room area (ft2) , , Cost ( $) 308, ,538 95,703 Cost ( %) Cost ($ per energized stall) 2,448 10,

58 Appendix B Page 3 AC L2 Energized vs Partial, dedicated, with conduits Energized Partial Later Costs Archetype 3 - Mid Rise - Outside City Stalls: 136 Stalls (20%): 28 Base cost ($): 12,000,000 Base load (kw): 461 Increase (kw): 904 Final load (kw): 1,365 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 500 kva to 1,500 kva 1 25, , Additional 3,000 A main switchboard section (and main breaker) 1 65, , A switchboard circuit breaker 10 50, , ft of two 2" conduit 10 10, , ft of two parallel 4#3/ , , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 10 45, , ft of 1" conduit 68 34, , sets of (100ft of 2#8 + 1#10B) 68 43, , ,359 7 Additional electrical room area (ft2) , , Cost ( $) 314, , ,359 Cost ( %) Cost ($ per energized stall) 2,314 10,

59 Appendix B Page 4 AC L2 Energized vs Partial, dedicated, with conduits Energized Partial Later Costs Archetype 4 - Townhouse - Outside City Stalls: Stalls (50%): Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,500, No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 225 kva to 500 kva 1 23, , Increase rating of main switchboard (and main breaker) from 600 A to 1,200 A 1 10, , Increase rating of switchboard circuit breakers from 100 A to 200 A 18 24, , Increase size of 100 ft feeders from 3#3 to 3#3/ , , Increase rating of panelboards from 100 A to 200 A 18 15, , ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1, ,723 Cost ( $) 95,588 95,014 1,723 Cost ( %) Cost ($ per energized stall) 2,655 5,279 96

60 Appendix B Page 5 AC L2 Energized vs Partial, dedicated, without conduits Energized Partial Later Costs Archetype 1 - High Rise - City Centre Stalls: 108 Stalls (20%): 22 Base cost ($): 25,000,000 Base load (kw): 825 Increase (kw): 718 Final load (kw): 1,543 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 600Y/347V main transformer from 1,000 kva to 2,000 kva 1 35, , Increase rating of main switchboard (and main breaker) from 800 A to 1,600 A 1 28, , A, 600Y/347V switchboard circuit breaker 1 9, , kva, 600V - 208Y/120V transformer 1 36, , ,000 A, 208Y/120V switchboard 1 12, , A, 208Y/120V switchboard circuit breaker 8 40, , , ft of two 2" conduit 8 8, , , ft of two parallel 4#3/0 8 20, , , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 8 36, , , ft of 1" conduit 54 27, , , sets of (100ft of 2#8 + 1#10B) 54 34, , , Additional electrical room area (ft2) , , Cost ( $) 326, , ,557 Cost ( %) Cost ($ per energized stall) 3,023 9,028 4,611

61 Appendix B Page 6 AC L2 Energized vs Partial, dedicated, without conduits Energized Partial Later Costs Archetype 2 - Mid Rise - City Centre Stalls: 126 Stalls (20%): 26 Base cost ($): 22,000,000 Base load (kw): 835 Increase (kw): 838 Final load (kw): 1,673 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 1,000 kva to 2,000 kva 1 18, , Additional 3,000 A main switchboard section (and main breaker) 1 65, , A switchboard circuit breaker 10 50, , , ft of two 2" conduit 10 10, , , ft of two parallel 4#3/ , , , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 10 45, , , ft of 1" conduit 63 31, , , sets of (100ft of 2#8 + 1#10B) 63 40, , ,802 9 Additional electrical room area (ft2) , , Cost ( $) 308, , ,905 Cost ( %) Cost ($ per energized stall) 2,448 5,628 5,009

62 Appendix B Page 7 AC L2 Energized vs Partial, dedicated, without conduits Energized Partial Later Costs Archetype 3 - Mid Rise - Outside City Stalls: Stalls (20%): Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, ,365 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 500 kva to 1,500 kva 1 25, , Additional 3,000 A main switchboard section (and main breaker) 1 65, , A switchboard circuit breaker 10 50, , , ft of two 2" conduit 10 10, , , ft of two parallel 4#3/ , , , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 10 45, , , ft of 1" conduit 68 34, , , sets of (100ft of 2#8 + 1#10B) 68 43, , ,906 7 Additional electrical room area (ft2) , , Cost ( $) 314, , ,089 Cost ( %) Cost ($ per energized stall) 2,314 5,289 4,779

63 Appendix B Page 8 AC L2 Energized vs Partial, dedicated, without conduits Energized Partial Later Costs Archetype 4 - Townhouse - Outside City Stalls: 36 Stalls (50%): 18 Base cost ($): 2,500,000 Base load (kw): 170 Increase (kw): 239 Final load (kw): 409 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 225 kva to 500 kva 1 23, , Increase rating of main switchboard (and main breaker) from 600 A to 1,200 A 1 10, , Increase rating of switchboard circuit breakers from 100 A to 200 A 18 24, , Increase size of 100 ft feeders from 3#3 to 3#3/ , , Increase rating of panelboards from 100 A to 200 A 18 15, , ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1, ,723 Cost ( $) 95,588 95,014 1,723 Cost ( %) Cost ($ per energized stall) 2,655 5,279 96

64 Appendix B Page L2 Dedicated Energized vs Partial (Total Cost k$) % Future/Retrofit 20% Partial Infrastructure 100% Energized

65 Appendix B Page 10 AC L2 Energized vs Partial, dedicated and load managed, with conduits Energized Partial Later Costs Archetype 1 - High Rise - City Centre Stalls: 108 Stalls (20%): 22 Base cost ($): 25,000,000 Base load (kw): 825 (kw): 718 available Final load (kw): 825 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST A, 600Y/347V switchboard circuit breaker 1 9, , kva, 600V - 208Y/120V transformer 1 36, , ,000 A, 208Y/120V switchboard 1 12, , A, 208Y/120V switchboard circuit breaker 8 40, , ft of two 2" conduit 8 8, , ft of two parallel 4#3/0 8 20, , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 8 36, , ft of 1" conduit 54 27, , sets of (100 ft of 2#8 + 1#10B) 54 34, , , Additional electrical room area (ft2) , , Load management 1 2, , Cost ( $) 264, ,730 82,305 Cost ( %) Cost ($ per energized stall) 2,446 10,

66 Appendix B Page 11 AC L2 Energized vs Partial, dedicated and load managed, with conduits Energized Partial Later Costs Archetype 2 - Mid Rise - City Centre Stalls: 126 Stalls (20%): 26 Base cost ($): 22,000,000 Base load (kw): 835 (kw): 838 available Final load (kw): 835 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Additional 3,000 A main switchboard section 1 15, , A switchboard circuit breaker 10 50, , ft of two 2" conduit 10 10, , ft of two parallel 4#3/ , , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 10 45, , ft of 1" conduit 63 31, , sets of (100 ft of 2#8 + 1#10B) 63 40, , ,703 8 Additional electrical room area (ft2) , , Load management 1 2, , Cost ( $) 243, ,136 95,703 Cost ( %) Cost ($ per energized stall) 1,929 8,

67 Appendix B Page 12 AC L2 Energized vs Partial, dedicated and load managed, with conduits Energized Partial Later Costs Archetype 3 - Mid Rise - Outside City Stalls: Stalls (20%): Base cost ($): Base load (kw): (kw): Final load (kw): ,000, available 461 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Additional 3,000 A main switchboard section 1 15, , A switchboard circuit breaker 10 50, , ft of two 2" conduit 10 10, , ft of two parallel 4#3/ , , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 10 45, , ft of 1" conduit 68 34, , sets of (100 ft of 2#8 + 1#10B) 68 43, , ,359 8 Additional electrical room area (ft2) , , Load management 1 2, , Cost ( $) 241, , ,359 Cost ( %) Cost ($ per energized stall) 1,778 7,

68 Appendix B Page 13 AC L2 Energized vs Partial, dedicated and load managed, with conduits Energized Partial Later Costs Archetype 4 - Townhouse - Outside City Stalls: 36 Stalls (50%): 18 Base cost ($): 2,500,000 Base load (kw): 170 (kw): 239 available Final load (kw): 170 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 10 ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1, ,723 3 Load management 18 9, , Cost ( $) 11,056 10,481 1,723 Cost ( %) Cost ($ per energized stall)

69 Appendix B Page 14 AC L2 Energized vs Partial, dedicated and load managed, without conduits Energized Partial Later Costs Archetype 1 - High Rise - City Centre Stalls: 108 Stalls (20%): 22 Base cost ($): 25,000,000 Base load (kw): 825 (kw): 718 available Final load (kw): 825 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST A, 600Y/347V switchboard circuit breaker 1 9, , kva, 600V - 208Y/120V transformer 1 36, , ,000 A, 208Y/120V switchboard 1 12, , A, 208Y/120V switchboard circuit breaker 8 40, , , ft of two 2" conduit 8 8, , , ft of two parallel 4#3/0 8 20, , , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 8 36, , , ft of 1" conduit 54 27, , , sets of (100 ft of 2#8 + 1#10B) 54 34, , , Additional electrical room area (ft2) , , Load management 1 2, , Cost ( $) 264, , ,557 Cost ( %) Cost ($ per energized stall) 2,446 6,196 4,611

70 Appendix B Page 15 AC L2 Energized vs Partial, dedicated and load managed, without conduits Energized Partial Later Costs Archetype 2 - Mid Rise - City Centre Stalls: 126 Stalls (20%): 26 Base cost ($): 22,000,000 Base load (kw): 835 (kw): 838 available Final load (kw): 835 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Additional 3,000 A main switchboard section 1 15, , A switchboard circuit breaker 10 50, , , ft of two 2" conduit 10 10, , , ft of two parallel 4#3/ , , , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 10 45, , , ft of 1" conduit 63 31, , , sets of (100 ft of 2#8 + 1#10B) 63 40, , ,802 8 Additional electrical room area (ft2) , , Load management 1 2, , Cost ( $) 243,037 80, ,905 Cost ( %) Cost ($ per energized stall) 1,929 3,113 5,009

71 Appendix B Page 16 AC L2 Energized vs Partial, dedicated and load managed, without conduits Energized Partial Later Costs Archetype 3 - Mid Rise - Outside City Stalls: Stalls (20%): Base cost ($): Base load (kw): (kw): Final load (kw): ,000, available 461 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Additional 3,000 A main switchboard section 1 15, , A switchboard circuit breaker 10 50, , , ft of two 2" conduit 10 10, , , ft of two parallel 4#3/ , , , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 10 45, , , ft of 1" conduit 68 34, , , sets of (100 ft of 2#8 + 1#10B) 68 43, , ,906 8 Additional electrical room area (ft2) , , Load management 1 2, , Cost ( $) 241,747 75, ,089 Cost ( %) Cost ($ per energized stall) 1,778 2,681 4,779

72 Appendix B Page 17 AC L2 Energized vs Partial, dedicated and load managed, without conduits Energized Partial Later Costs Archetype 4 - Townhouse - Outside City Stalls: 36 Stalls (50%): 18 Base cost ($): 2,500,000 Base load (kw): 170 (kw): 239 available Final load (kw): 170 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 10 ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1, ,723 3 Load management 18 9, , Cost ( $) 11,056 10,481 1,723 Cost ( %) Cost ($ per energized stall)

73 Appendix B Page L2 Dedicated and Load Managed Energized vs Partial (Total Cost k$) 80% Future/Retrofit % Partial Infrastructure 100% Energized

74 Appendix B Page 19 AC L2 Energized vs Partial, 2-way shared, with conduits Energized Partial Later Costs Archetype 1 - High Rise - City Centre Stalls: 108 Stalls (20%): 22 Base cost ($): 25,000,000 Base load (kw): 825 Increase (kw): 359 Final load (kw): 1,184 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 600Y/347V main transformer from 1,000 kva to 1,500 kva 1 21, , Increase rating of main switchboard (and main breaker) from 800 A to 1,200 A 1 7, , A, 600Y/347V switchboard circuit breaker 1 5, , kva, 600V - 208Y/120V transformer 1 22, , ,200 A, 208Y/120V switchboard 1 11, , A, 208Y/120V switchboard circuit breaker 4 20, , ft of two 2" conduit 4 4, , ft of two parallel 4#3/0 4 10, , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 4 18, , ft of 1" conduit 28 14, , sets of (100ft of 2#8 + 1#10B) 28 17, , , Additional electrical room area (ft2) , , Cost ( $) 177, ,193 42,109 Cost ( %) Cost ($ per energized stall) 1,641 7,

75 Appendix B Page 20 AC L2 Energized vs Partial, 2-way shared, with conduits Energized Partial Later Costs Archetype 2 - Mid Rise - City Centre Stalls: 126 Stalls (20%): 26 Base cost ($): 22,000,000 Base load (kw): 835 Increase (kw): 419 Final load (kw): 1,254 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 1,000 kva to 1,500 kva 1 3, , Additional 1,200 A main switchboard section (and main breaker) 1 27, , A switchboard circuit breaker 6 30, , ft of two 2" conduit 6 6, , ft of two parallel 4#3/0 6 15, , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 6 27, , ft of 1" conduit 32 16, , sets of (100ft of 2#8 + 1#10B) 32 20, , ,852 9 Additional electrical room area (ft2) 50 11, , Cost ( $) 158, ,254 47,852 Cost ( %) Cost ($ per energized stall) 1,256 5,

76 Appendix B Page 21 AC L2 Energized vs Partial, 2-way shared, with conduits Energized Partial Later Costs Archetype 3 - Mid Rise - Outside City Stalls: Stalls (20%): Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 500 kva to 1,000 kva 1 21, , Increase rating of main switchboard (and main breaker) from 1,600 A to 3,000 A 1 15, , A switchboard circuit breaker 5 25, , ft of two 2" conduit 5 5, , ft of two parallel 4#3/0 5 12, , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 5 22, , ft of 1" conduit 34 17, , sets of (100ft of 2#8 + 1#10B) 34 21, , ,680 9 Additional electrical room area (ft2) 20 3, , Cost ( $) 145, ,900 51,680 Cost ( %) Cost ($ per energized stall) 1,067 4,

77 Appendix B Page 22 AC L2 Energized vs Partial, 2-way shared, with conduits Energized Partial Later Costs Archetype 4 - Townhouse - Outside City Stalls: 36 Stalls (50%): 18 Base cost ($): 2,500,000 Base load (kw): 170 Increase (kw): 120 Final load (kw): 290 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 225 kva to 300 kva 1 3, , Increase rating of main switchboard (and main breaker) from 600 A to 800 A 1 3, , Increase rating of switchboard circuit breakers from 100 A to 125 A 18 8, , Increase size of 100 ft feeders from 3#3 to 3#1 18 5, , Increase rating of panelboards from 100 A to 125 A 18 3, , ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1, ,723 Cost ( $) 26,379 25,805 1,723 Cost ( %) Cost ($ per energized stall) 733 1,434 96

78 Appendix B Page 23 AC L2 Energized vs Partial, 2-way shared, without conduits Energized Partial Later Costs Archetype 1 - High Rise - City Centre Stalls: 108 Stalls (20%): 22 Base cost ($): 25,000,000 Base load (kw): 825 Increase (kw): 359 Final load (kw): 1,184 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 600Y/347V main transformer from 1,000 kva to 1,500 kva 1 21, , Increase rating of main switchboard (and main breaker) from 800 A to 1,200 A 1 7, , A, 600Y/347V switchboard circuit breaker 1 5, , kva, 600V - 208Y/120V transformer 1 22, , ,200 A, 208Y/120V switchboard 1 11, , A, 208Y/120V switchboard circuit breaker 4 20, , , ft of two 2" conduit 4 4, , , ft of two parallel 4#3/0 4 10, , , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 4 18, , , ft of 1" conduit 28 14, , , sets of (100ft of 2#8 + 1#10B) 28 17, , , Additional electrical room area (ft2) , , Cost ( $) 177, , ,176 Cost ( %) Cost ($ per energized stall) 1,641 5,124 2,328

79 Appendix B Page 24 AC L2 Energized vs Partial, 2-way shared, without conduits Energized Partial Later Costs Archetype 2 - Mid Rise - City Centre Stalls: 126 Stalls (20%): 26 Base cost ($): 22,000,000 Base load (kw): 835 Increase (kw): 419 Final load (kw): 1,254 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 1,000 kva to 1,500 kva 1 3, , Additional 1,200 A main switchboard section (and main breaker) 1 27, , A switchboard circuit breaker 6 30, , , ft of two 2" conduit 6 6, , , ft of two parallel 4#3/0 6 15, , , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 6 27, , , ft of 1" conduit 32 16, , , sets of (100ft of 2#8 + 1#10B) 32 20, , ,901 9 Additional electrical room area (ft2) 50 11, , Cost ( $) 158,205 64, ,340 Cost ( %) Cost ($ per energized stall) 1,256 2,463 2,893

80 Appendix B Page 25 AC L2 Energized vs Partial, 2-way shared, without conduits Energized Partial Later Costs Archetype 3 - Mid Rise - Outside City Stalls (20%): Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 500 kva to 1,000 kva 1 21, , Increase rating of main switchboard (and main breaker) from 1,600 A to 3,000 A 1 15, , A switchboard circuit breaker 5 25, , , ft of two 2" conduit 5 5, , , ft of two parallel 4#3/0 5 12, , , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 5 22, , , ft of 1" conduit 34 17, , , sets of (100ft of 2#8 + 1#10B) 34 21, , ,453 9 Additional electrical room area (ft2) 20 3, , Cost ( $) 145,126 61, ,044 Cost ( %) Cost ($ per energized stall) 1,067 2,207 2,389

81 Appendix B Page 26 AC L2 Energized vs Partial, 2-way shared, without conduits Energized Partial Later Costs Archetype 4 - Townhouse - Outside City Stalls (50%): Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,500, No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 225 kva to 300 kva 1 3, , Increase rating of main switchboard (and main breaker) from 600 A to 800 A 1 3, , Increase rating of switchboard circuit breakers from 100 A to 125 A 18 8, , Increase size of 100 ft feeders from 3#3 to 3#1 18 5, , Increase rating of panelboards from 100 A to 125 A 18 3, , ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1, ,723 Cost ( $) 26,379 25,805 1,723 Cost ( %) Cost ($ per energized stall) 733 1,434 96

82 Appendix B Page Two-Way Load Shared Energized vs Partial (Total Cost k$) % Future/Retrofit 20% Partial Infrastructure 100% Energized

83 Appendix B Page 28 AC L2 Energized vs Partial, 4-way shared, with conduits Energized Partial Later Costs Archetype 1 - High Rise - City Centre Stalls: 108 Stalls (20%): 22 Base cost ($): 25,000,000 Base load (kw): 825 Increase (kw): 180 Final load (kw): 1,005 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 600Y/347V main transformer from 1,000 kva to 1,500 kva 1 21, , Increase rating of main switchboard (and main breaker) from 800 A to 1,200 A 1 7, , A, 600Y/347V switchboard circuit breaker 1 2, , kva, 600V - 208Y/120V transformer 1 12, , A, 208Y/120V switchboard 1 9, , A, 208Y/120V switchboard circuit breaker 2 10, , ft of two 2" conduit 2 2, , ft of two parallel 4#3/0 2 5, , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 2 9, , ft of 1" conduit 14 7, , sets of (100ft of 2#8 + 1#10B) 14 8, , , Additional electrical room area (ft2) 50 12, , Cost ( $) 108, ,509 21,055 Cost ( %) Cost ($ per energized stall) 1,005 4,

84 Appendix B Page 29 AC L2 Energized vs Partial, 4-way shared, with conduits Energized Partial Later Costs Archetype 2 - Mid Rise - City Centre Stalls: 126 Stalls (20%): 26 Base cost ($): 22,000,000 Base load (kw): 835 Increase (kw): 209 Final load (kw): 1,044 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 1,000 kva to 1,500 kva 1 3, , ,000 A main switchboard (no change) A switchboard circuit breaker 4 20, , ft of two 2" conduit 4 4, , ft of two parallel 4#3/0 4 10, , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 4 18, , ft of 1" conduit 16 8, , sets of (100ft of 2#8 + 1#10B) 16 10, , ,969 9 Additional electrical room area (ft2) 20 4, , Cost ( $) 79,126 71,470 22,969 Cost ( %) Cost ($ per energized stall) 628 2,

85 Appendix B Page 30 AC L2 Energized vs Partial, 4-way shared, with conduits Energized Partial Later Costs Archetype 3 - Mid Rise - Outside City Stalls: 136 Stalls (20%): 28 Base cost ($): 12,000,000 Base load (kw): 461 Increase (kw): 226 Final load (kw): 687 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 500 kva to 750 kva 1 7, , Increase rating of main switchboard (and main breaker) from 1,600 A to 2,000 A 1 4, , A switchboard circuit breaker 4 20, , ft of two 2" conduit 4 4, , ft of two parallel 4#3/0 4 10, , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 4 18, , ft of 1" conduit 17 8, , sets of (100ft of 2#8 + 1#10B) 17 10, , ,883 9 Additional electrical room area (ft2) 20 3, , Cost ( $) 86,709 78,415 24,883 Cost ( %) Cost ($ per energized stall) 638 2,

86 Appendix B Page 31 AC L2 Energized vs Partial, 4-way shared, with conduits Energized Partial Later Costs Archetype 4 - Townhouse - Outside City Stalls (50%): Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,500, No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 225 kva to 300 kva 1 3, , Increase rating of main switchboard (and main breaker) from 600 A to 800 A 1 3, , Increase rating of switchboard circuit breakers from 100 A to 125 A 18 8, , Increase size of 100 ft feeders from 3#3 to 3#1 18 5, , Increase rating of panelboards from 100 A to 125 A 18 3, , ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1, ,723 Cost ( $) 26,379 25,805 1,723 Cost ( %) Cost ($ per energized stall) 733 1,434 96

87 Appendix B Page 32 AC L2 Energized vs Partial, 4-way shared, without conduits Energized Partial Later Costs Archetype 1 - High Rise - City Centre Stalls: 108 Stalls (20%): 22 Base cost ($): 25,000,000 Base load (kw): 825 Increase (kw): 180 Final load (kw): 1,005 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 600Y/347V main transformer from 1,000 kva to 1,500 kva 1 21, , Increase rating of main switchboard (and main breaker) from 800 A to 1,200 A 1 7, , A, 600Y/347V switchboard circuit breaker 1 2, , kva, 600V - 208Y/120V transformer 1 12, , A, 208Y/120V switchboard 1 9, , A, 208Y/120V switchboard circuit breaker 2 10, , , ft of two 2" conduit 2 2, , , ft of two parallel 4#3/0 2 5, , , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 2 9, , , ft of 1" conduit 14 7, , , sets of (100ft of 2#8 + 1#10B) 14 8, , , Additional electrical room area (ft2) 50 12, , Cost ( $) 108,528 82,840 80,644 Cost ( %) Cost ($ per energized stall) 1,005 3,

88 Appendix B Page 33 AC L2 Energized vs Partial, 4-way shared, without conduits Energized Partial Later Costs Archetype 2 - Mid Rise - City Centre Stalls: 126 Stalls (20%): 26 Base cost ($): 22,000,000 Base load (kw): 835 Increase (kw): 209 Final load (kw): 1,044 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 1,000 kva to 1,500 kva 1 3, , ,000 A main switchboard (no change) A switchboard circuit breaker 4 20, , , ft of two 2" conduit 4 4, , , ft of two parallel 4#3/0 4 10, , , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 4 18, , , ft of 1" conduit 16 8, , , sets of (100ft of 2#8 + 1#10B) 16 10, , ,312 9 Additional electrical room area (ft2) 20 4, , Cost ( $) 79,126 26, ,216 Cost ( %) Cost ($ per energized stall) 628 1,002 1,622

89 Appendix B Page 34 AC L2 Energized vs Partial, 4-way shared, without conduits Energized Partial Later Costs Archetype 3 - Mid Rise - Outside City Stalls: 136 Stalls (20%): 28 Base cost ($): 12,000,000 Base load (kw): 461 Increase (kw): 226 Final load (kw): 687 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 500 kva to 750 kva 1 7, , Increase rating of main switchboard (and main breaker) from 1,600 A to 2,000 A 1 4, , A switchboard circuit breaker 4 20, , , ft of two 2" conduit 4 4, , , ft of two parallel 4#3/0 4 10, , , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 4 18, , , ft of 1" conduit 17 8, , , sets of (100ft of 2#8 + 1#10B) 17 10, , ,589 9 Additional electrical room area (ft2) 20 3, , Cost ( $) 86,709 32, ,012 Cost ( %) Cost ($ per energized stall) 638 1,160 1,537

90 Appendix B Page 35 AC L2 Energized vs Partial, 4-way shared, without conduits Energized Partial Later Costs Archetype 4 - Townhouse - Outside City Stalls (50%): Stalls: Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,500, No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 225 kva to 300 kva 1 3, , Increase rating of main switchboard (and main breaker) from 600 A to 800 A 1 3, , Increase rating of switchboard circuit breakers from 100 A to 125 A 18 8, , Increase size of 100 ft feeders from 3#3 to 3#1 18 5, , Increase rating of panelboards from 100 A to 125 A 18 3, , ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1, ,723 Cost ( $) 26,379 25,805 1,723 Cost ( %) Cost ($ per energized stall) 733 1,434 96

91 Appendix B Page Four-Way Load Shared Energized vs Partial (Total Cost k$) 80% Future/Retrofit 20% Partial Infrastructure % Energized

92 Appendix B Page 37 AC L2 Energized vs Partial, 4-fold panel shared, with conduits Energized Partial Later Costs Archetype 1 - High Rise - City Centre Stalls Stalls (20%): Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, ,214 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 600Y/347V main transformer from 1,000 kva to 1,500 kva 1 21, , Increase rating of main switchboard (and main breaker) from 800 A to 1,200 A 1 7, , A, 600Y/347V switchboard circuit breaker 1 2, , kva, 600V - 208Y/120V transformer 1 12, , A, 208Y/120V switchboard 1 9, , A, 208Y/120V switchboard circuit breaker 4 11, , ft of 2" conduit 4 2, , ft of 4#3/0 4 5, , A main lugs, 208Y/120V, 60 cct panelboard (with 40 A circuit breakers) 4 27, , ft of 1" conduit 54 27, , sets of (100ft of 2#8 + 1#10B) 54 34, , , Additional electrical room area (ft 2 ) 50 12, , Cost ( $) 174, ,168 82,305 Cost ( %) Cost ($ per energized stall) 1,617 6,

93 Appendix B Page 38 AC L2 Energized vs Partial, 4-fold panel shared, with conduits Energized Partial Later Costs Archetype 2 - Mid Rise - City Centre Stalls: Stalls (20%): Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 1,000 kva to 1,500 kva 1 3, , ,000 A main switchboard (no change) A switchboard circuit breaker 5 25, , ft of 2" conduit 5 2, , ft of 4#3/0 5 6, , A main lugs, 208Y/120V, 60 cct panelboard (with 40 A circuit breakers) 5 34, , ft of 1" conduit 63 31, , sets of (100ft of 2#8 + 1#10B) 63 40, , ,820 9 Additional electrical room area (ft 2 ) 20 4, , Cost ( $) 149, ,856 70,820 Cost ( %) Cost ($ per energized stall) 1,186 4,

94 Appendix B Page 39 AC L2 Energized vs Partial, 4-fold panel shared, with conduits Energized Partial Later Costs Archetype 3 - Mid Rise - Outside City Stalls: Stalls (20%): Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 500 kva to 750 kva 1 7, , Increase rating of main switchboard (and main breaker) from 1,600 A to 2,000 A 1 4, , A switchboard circuit breaker 5 25, , ft of 2" conduit 5 2, , ft of 4#3/0 5 6, , A main lugs, 208Y/120V, 60 cct panelboard (with 40 A circuit breakers) 5 34, , ft of 1" conduit 68 34, , sets of (100ft of 2#8 + 1#10B) 68 43, , ,562 9 Additional electrical room area (ft 2 ) 20 4, , Cost ( $) 163, ,493 76,562 Cost ( %) Cost ($ per energized stall) 1,199 4,

95 Appendix B Page 40 AC L2 Energized vs Partial, 4-fold panel shared, with conduits Energized Partial Later Costs Archetype 4 - Townhouse - Outside City Stalls: 36 Stalls (50%): 18 Base cost ($): 2,500,000 Base load (kw): 170 Increase (kw): 120 Final load (kw): 290 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 225 kva to 300 kva 1 3, , Increase rating of main switchboard (and main breaker) from 600 A to 800 A 1 3, , Increase rating of switchboard circuit breakers from 100 A to 125 A 18 8, , Increase size of 100 ft feeders from 3#3 to 3#1 18 5, , Increase rating of panelboards from 100 A to 125 A 18 3, , ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1, ,723 Cost ( $) 26,379 25,805 1,723 Cost ( %) Cost ($ per energized stall) 733 1,434 96

96 Appendix B Page 41 AC L2 Energized vs Partial, 4-fold panel shared, without conduits Energized Partial Later Costs Archetype 1 - High Rise - City Centre Stalls Stalls (20%): Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, ,214 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 600Y/347V main transformer from 1,000 kva to 1,500 kva 1 21, , Increase rating of main switchboard (and main breaker) from 800 A to 1,200 A 1 7, , A, 600Y/347V switchboard circuit breaker 1 2, , kva, 600V - 208Y/120V transformer 1 12, , A, 208Y/120V switchboard 1 9, , A, 208Y/120V switchboard circuit breaker 4 11, , , ft of 2" conduit 4 2, , ft of 4#3/0 4 5, , , A main lugs, 208Y/120V, 60 cct panelboard (with 40 A circuit breakers) 4 27, , , ft of 1" conduit 54 27, , , sets of (100ft of 2#8 + 1#10B) 54 34, , , Additional electrical room area (ft 2 ) 50 12, , Cost ( $) 174,603 90, ,449 Cost ( %) Cost ($ per energized stall) 1,617 4,114 3,110

97 Appendix B Page 42 AC L2 Energized vs Partial, 4-fold panel shared, without conduits Energized Partial Later Costs Archetype 2 - Mid Rise - City Centre Stalls: Stalls (20%): Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 1,000 kva to 1,500 kva 1 3, , ,000 A main switchboard (no change) A switchboard circuit breaker 5 25, , , ft of 2" conduit 5 2, , ft of 4#3/0 5 6, , , A main lugs, 208Y/120V, 60 cct panelboard (with 40 A circuit breakers) 5 34, , , ft of 1" conduit 63 31, , , sets of (100ft of 2#8 + 1#10B) 63 40, , ,213 9 Additional electrical room area (ft 2 ) 20 4, , Cost ( $) 149,462 51, ,470 Cost ( %) Cost ($ per energized stall) 1,186 1,995 3,055

98 Appendix B Page 43 AC L2 Energized vs Partial, 4-fold panel shared, without conduits Energized Partial Later Costs Archetype 3 - Mid Rise - Outside City Stalls: Stalls (20%): Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 500 kva to 750 kva 1 7, , Increase rating of main switchboard (and main breaker) from 1,600 A to 2,000 A 1 4, , A switchboard circuit breaker 5 25, , , ft of 2" conduit 5 2, , ft of 4#3/0 5 6, , , A main lugs, 208Y/120V, 60 cct panelboard (with 40 A circuit breakers) 5 34, , , ft of 1" conduit 68 34, , , sets of (100ft of 2#8 + 1#10B) 68 43, , ,042 9 Additional electrical room area (ft 2 ) 20 4, , Cost ( $) 163,014 62, ,858 Cost ( %) Cost ($ per energized stall) 1,199 2,214 2,934

99 Appendix B Page 44 AC L2 Energized vs Partial, 4-fold panel shared, without conduits Energized Partial Later Costs Archetype 4 - Townhouse - Outside City Stalls: Stalls (50%): Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,500, No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 225 kva to 300 kva 1 3, , Increase rating of main switchboard (and main breaker) from 600 A to 800 A 1 3, , Increase rating of switchboard circuit breakers from 100 A to 125 A 18 8, , Increase size of 100 ft feeders from 3#3 to 3#1 18 5, , Increase rating of panelboards from 100 A to 125 A 18 3, , ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1, ,723 Cost ( $) 26,379 25,805 1,723 Cost ( %) Cost ($ per energized stall) 733 1,434 96

100 Appendix B Page Panel Shared Energized vs Partial (Total Cost k$) % Future/Retrofit 20% Partial Infrastructure 100% Energized

101 Appendix B Page 46 AC L2 Energized vs Partial, 4-way shared and managed, with conduits Energized Partial Later Costs Archetype 1 - High Rise - City Centre Stalls: 108 Stalls (20%): 22 Base cost ($): 25,000,000 Base load (kw): 825 (kw): 180 available Final load (kw): 825 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST A, 600Y/347V switchboard circuit breaker 1 2, , kva, 600V - 208Y/120V transformer 1 12, , A, 208Y/120V switchboard 1 9, , A, 208Y/120V switchboard circuit breaker 2 10, , ft of two 2" conduit 2 2, , ft of two parallel 4#3/0 2 5, , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 2 9, , ft of 1" conduit 14 7, , sets of (100ft of 2#8 + 1#10B) 14 8, , , Additional electrical room area (ft2) 50 12, , Load management 1 2, , Cost ( $) 82,049 75,031 21,055 Cost ( %) Cost ($ per energized stall) 760 3,

102 Appendix B Page 47 AC L2 Energized vs Partial, 4-way shared and managed, with conduits Energized Partial Later Costs Archetype 2 - Mid Rise - City Centre Stalls: 126 Stalls (20%): 26 Base cost ($): 22,000,000 Base load (kw): 835 (kw): 209 available Final load (kw): 835 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST A switchboard circuit breaker 4 20, , ft of two 2" conduit 4 4, , ft of two parallel 4#3/0 4 10, , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 4 18, , ft of 1" conduit 16 8, , sets of (100ft of 2#8 + 1#10B) in 1" conduit 16 10, , ,969 7 Additional electrical room area (ft2) 20 4, , Load management 1 2, , Cost ( $) 77,175 69,519 22,969 Cost ( %) Cost ($ per energized stall) 612 2,

103 Appendix B Page 48 AC L2 Energized vs Partial, 4-way shared and managed, with conduits Energized Partial Later Costs Archetype 3 - Mid Rise - Outside City Stalls: 136 Stalls (20%): 28 Base cost ($): 12,000,000 Base load (kw): 461 (kw): 226 available Final load (kw): 461 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST A switchboard circuit breaker 4 20, , ft of two 2" conduit 4 4, , ft of two parallel 4#3/0 4 10, , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 4 18, , ft of 1" conduit 17 8, , sets of (100ft of 2#8 + 1#10B) 17 10, , ,883 7 Additional electrical room area (ft2) 20 3, , Load management 1 2, , Cost ( $) 76,917 68,623 24,883 Cost ( %) Cost ($ per energized stall) 566 2,

104 Appendix B Page 49 AC L2 Energized vs Partial, 4-way shared and managed, with conduits Energized Partial Later Costs Archetype 4 - Townhouse - Outside City Stalls: 36 Stalls (50%): 18 Base cost ($): 2,500,000 Base load (kw): 170 (kw): 120 available Final load (kw): 170 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 10 ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1, ,723 3 Load management 18 9, , Cost ( $) 11,056 10,481 1,723 Cost ( %) Cost ($ per energized stall)

105 Appendix B Page 50 AC L2 Energized vs Partial, 4-way shared and managed, without conduits Energized Partial Later Costs Archetype 1 - High Rise - City Centre Stalls: 108 Stalls (20%): 22 Base cost ($): 25,000,000 Base load (kw): 825 (kw): 180 available Final load (kw): 825 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST A, 600Y/347V switchboard circuit breaker 1 2, , kva, 600V - 208Y/120V transformer 1 12, , A, 208Y/120V switchboard 1 9, , A, 208Y/120V switchboard circuit breaker 2 10, , , ft of two 2" conduit 2 2, , , ft of two parallel 4#3/0 2 5, , , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 2 9, , , ft of 1" conduit 14 7, , , sets of (100ft of 2#8 + 1#10B) 14 8, , , Additional electrical room area (ft2) 50 12, , Load management 1 2, , Cost ( $) 82,049 56,361 80,644 Cost ( %) Cost ($ per energized stall) 760 2,

106 Appendix B Page 51 AC L2 Energized vs Partial, 4-way shared and managed, without conduits Energized Partial Later Costs Archetype 2 - Mid Rise - City Centre Stalls: 126 Stalls (20%): 26 Base cost ($): 22,000,000 Base load (kw): 835 (kw): 209 available Final load (kw): 835 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST A switchboard circuit breaker 4 20, , , ft of two 2" conduit 4 4, , , ft of two parallel 4#3/0 4 10, , , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 4 18, , , ft of 1" conduit 16 8, , , sets of (100ft of 2#8 + 1#10B) in 1" conduit 16 10, , ,312 7 Additional electrical room area (ft2) 20 4, , Load management 1 2, , Cost ( $) 77,175 24, ,216 Cost ( %) Cost ($ per energized stall) ,622

107 Appendix B Page 52 AC L2 Energized vs Partial, 4-way shared and managed, without conduits Energized Partial Later Costs Archetype 3 - Mid Rise - Outside City Stalls: 136 Stalls (20%): 28 Base cost ($): 12,000,000 Base load (kw): 461 (kw): 226 available Final load (kw): 461 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST A switchboard circuit breaker 4 20, , , ft of two 2" conduit 4 4, , , ft of two parallel 4#3/0 4 10, , , A main lugs, 208Y/120V, 42 cct panelboard (with 40 A circuit breakers) 4 18, , , ft of 1" conduit 17 8, , , sets of (100ft of 2#8 + 1#10B) 17 10, , ,589 7 Additional electrical room area (ft2) 20 3, , Load management 1 2, , Cost ( $) 76,917 22, ,012 Cost ( %) Cost ($ per energized stall) ,537

108 Appendix B Page 53 AC L2 Energized vs Partial, 4-way shared and managed, without conduits Energized Partial Later Costs Archetype 4 - Townhouse - Outside City Stalls: 36 Stalls (50%): 18 Base cost ($): 2,500,000 Base load (kw): 170 (kw): 120 available Final load (kw): 170 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 10 ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1, ,723 3 Load management 18 9, , Cost ( $) 11,056 10,481 1,723 Cost ( %) Cost ($ per energized stall)

109 Appendix B Page Four-Way Load Shared and Load Managed Energized vs Partial (Total Cost k$) % Future/Retrofit 20% Partial Infrastructure % Energized

110 Appendix B Page 55 AC L2 Energized vs Partial, 12-way shared on 150A trunk, with conduits Energized Partial Later Costs Archetype 1 - High Rise - City Centre Stalls Stalls (20%): Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, ,214 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 600Y/347V main transformer from 1,000 kva to 1,500 kva 1 21, , Increase rating of main switchboard (and main breaker) from 800 A to 1,200 A 1 7, , A, 600Y/347V switchboard circuit breaker 1 5, , kva, 600V - 208Y/120V transformer 1 22, , ,200 A, 208Y/120V switchboard 1 11, , A, 208Y/120V switchboard circuit breaker 9 19, , ft of 1-1/2" conduit 9 14, , ft of (3#2/0 + 1#6B) 9 27, , A, 2-pole, circuit breaker in enclosure , , ft of ¾" conduit 108 4, , ft of (2#8 + 1#10B) 108 3, , Additional electrical room area (ft2) 50 12, , Cost ( $) 168, ,093 8,230 Cost ( %) Cost ($ per energized stall) 1,563 7,550 96

111 Appendix B Page 56 AC L2 Energized vs Partial, 12-way shared on 150A trunk, with conduits Energized Partial Later Costs Archetype 2 - Mid Rise - City Centre Stalls: Stalls (20%): Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 1,000 kva to 1,500 kva 1 3, , Additional 1,600 A switchboard (with main breaker) 1 49, , A, 208Y/120V switchboard circuit breaker 11 23, , ft of 1-1/2" conduit 11 18, , ft of (3#2/0 + 1#6B) 11 33, , A, 2-pole, circuit breaker in enclosure , , ft of ¾" conduit 126 4, , ft of (2#8 + 1#10B) 126 4, ,570 9 Additional electrical room area (ft 2 ) 20 5, , Cost ( $) 164, ,743 9,570 Cost ( %) Cost ($ per energized stall) 1,309 6,221 96

112 Appendix B Page 57 AC L2 Energized vs Partial, 12-way shared on 150A trunk, with conduits Energized Partial Later Costs Archetype 3 - Mid Rise - Outside City Stalls: Stalls (20%): Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 500 kva to 1,000 kva 1 21, , Increase rating of main switchboard (and main breaker) from 1,600 A to 3,000 A 1 15, , A, 208Y/120V switchboard circuit breaker 12 25, , ft of 1-1/2" conduit 12 19, , ft of (3#2/0 + 1#6B) 12 36, , A, 2-pole, circuit breaker in enclosure , , ft of ¾" conduit 136 5, , ft of (2#8 + 1#10B) 136 4, ,336 9 Additional electrical room area (ft 2 ) 20 5, , Cost ( $) 158, ,323 10,336 Cost ( %) Cost ($ per energized stall) 1,167 5,547 96

113 Appendix B Page 58 AC L2 Energized vs Partial, 12-way shared on 150A trunk, with conduits Energized Partial Later Costs Archetype 4 - Townhouse - Outside City Stalls: Stalls (50%): Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,500, No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 225 kva to 300 kva 1 3, , Increase rating of main switchboard (and main breaker) from 600 A to 800 A 1 3, , Increase rating of switchboard circuit breakers from 100 A to 125 A 18 8, , Increase size of 100 ft feeders from 3#3 to 3#1 18 5, , Increase rating of panelboards from 100 A to 125 A 18 3, , ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1, ,723 Cost ( $) 26,379 25,805 1,723 Cost ( %) Cost ($ per energized stall) 733 1,434 96

114 Appendix B Page 59 AC L2 Energized vs Partial, 12-way shared on 150A trunk, without conduits Energized Partial Later Costs Archetype 1 - High Rise - City Centre Stalls Stalls (20%): Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, ,214 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 600Y/347V main transformer from 1,000 kva to 1,500 kva 1 21, , Increase rating of main switchboard (and main breaker) from 800 A to 1,200 A 1 7, , A, 600Y/347V switchboard circuit breaker 1 5, , kva, 600V - 208Y/120V transformer 1 22, , ,200 A, 208Y/120V switchboard 1 11, , A, 208Y/120V switchboard circuit breaker 9 19, , , ft of 1-1/2" conduit 9 14, , , ft of (3#2/0 + 1#6B) 9 27, , , A, 2-pole, circuit breaker in enclosure , , , ft of ¾" conduit 108 4, , ft of (2#8 + 1#10B) 108 3, , Additional electrical room area (ft2) 50 12, , Cost ( $) 168,836 99, ,037 Cost ( %) Cost ($ per energized stall) 1,563 4,520 2,489

115 Appendix B Page 60 AC L2 Energized vs Partial, 12-way shared on 150A trunk, without conduits Energized Partial Later Costs Archetype 2 - Mid Rise - City Centre Stalls: Stalls (20%): Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 1,000 kva to 1,500 kva 1 3, , Additional 1,600 A switchboard (with main breaker) 1 49, , A, 208Y/120V switchboard circuit breaker 11 23, , , ft of 1-1/2" conduit 11 18, , , ft of (3#2/0 + 1#6B) 11 33, , , A, 2-pole, circuit breaker in enclosure , , , ft of ¾" conduit 126 4, , ft of (2#8 + 1#10B) 126 4, ,380 9 Additional electrical room area (ft 2 ) 20 5, , Cost ( $) 164,933 78, ,752 Cost ( %) Cost ($ per energized stall) 1,309 3,014 2,668

116 Appendix B Page 61 AC L2 Energized vs Partial, 12-way shared on 150A trunk, without conduits Energized Partial Later Costs Archetype 3 - Mid Rise - Outside City Stalls: Stalls (20%): Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 500 kva to 1,000 kva 1 21, , Increase rating of main switchboard (and main breaker) from 1,600 A to 3,000 A 1 15, , A, 208Y/120V switchboard circuit breaker 12 25, , , ft of 1-1/2" conduit 12 19, , , ft of (3#2/0 + 1#6B) 12 36, , , A, 2-pole, circuit breaker in enclosure , , , ft of ¾" conduit 136 5, , , ft of (2#8 + 1#10B) 136 4, ,891 9 Additional electrical room area (ft 2 ) 20 5, , Cost ( $) 158,768 70, ,138 Cost ( %) Cost ($ per energized stall) 1,167 2,507 2,529

117 Appendix B Page 62 AC L2 Energized vs Partial, 12-way shared on 150A trunk, without conduits Energized Partial Later Costs Archetype 4 - Townhouse - Outside City Stalls: 36 Stalls (50%): 18 Base cost ($): 2,500,000 Base load (kw): 170 Increase (kw): 120 Final load (kw): 290 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 Increase rating of 25kV - 208Y/120V main transformer from 225 kva to 300 kva 1 3, , Increase rating of main switchboard (and main breaker) from 600 A to 800 A 1 3, , Increase rating of switchboard circuit breakers from 100 A to 125 A 18 8, , Increase size of 100 ft feeders from 3#3 to 3#1 18 5, , Increase rating of panelboards from 100 A to 125 A 18 3, , ft of 1" conduit sets of (10 ft of 2#8 + 1#10B) 18 1, ,723 Cost ( $) 26,379 25,805 1,723 Cost ( %) Cost ($ per energized stall) 733 1,434 96

118 Appendix B Page Twelve-Way Load Shared on 150A Trunk Energized vs Partial (Total Cost $) 80% Future/Retrofit % Partial Infrastructure 100% Energized

119 Appendix B Page 64 AC L2 Energized vs Partial, 18-way shared, with conduits Energized Partial Later Costs Archetype 1 - High Rise - City Centre Stalls: 108 Stalls (20%): 22 Base cost ($): 25,000,000 Base load (kw): 825 Increase (kw): 80 Final load (kw): 905 No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 1,000 kva, 25kV - 600Y/347V main transformer (no change) Increase rating of main switchboard (and main breaker) from 800 A to 1,200 A 1 7, , A, 600Y/347V switchboard circuit breaker 1 1, , kva, 600V - 208Y/120V transformer 1 7, , ft of two 2" conduit 1 1, , ft of two parallel 4#3/0 1 2, , A main lugs, 208Y/120V, 42 cct panelboard (lugs only) 1 2, , A, 2p circuit breakers 6 1, , ft of 1-1/4" conduit 6 8, , ft of (2#1 + 1#6B) 6 10, , A, 2-pole, circuit breaker in enclosure , , ft of ¾" conduit 108 4, , ft of (2#8 + 1#10B) 108 3, , Additional electrical room area (ft2) 50 12, , Cost ( $) 83,184 80,441 8,230 Cost ( %) Cost ($ per energized stall) 770 3,656 96

120 Appendix B Page 65 AC L2 Energized vs Partial, 18-way shared, with conduits Energized Partial Later Costs Archetype 2 - Mid Rise - City Centre Stalls: Stalls (20%): Base cost ($): Base load (kw): Increase (kw): Final load (kw): ,000, No. DESCRIPTION QTY COST ( $) QTY COST ( $) QTY MULT COST 1 1,000 kva, 25kV - 600Y/347V main transformer (no change) ,000 A main switchboard (no change) A switchboard circuit breaker 1 5, , ft of two 2" conduit 1 1, , ft of two parallel 4#3/0 1 2, , A main lugs, 208Y/120V, 42 cct panelboard (lugs only) 1 2, , A, 2p circuit breakers 7 2, , ft of 1-1/4" conduit 7 9, , ft of (2#1 + 1#6B) 7 12, , A, 2-pole, circuit breaker in enclosure , , ft of ¾" conduit 126 4, , ft of (2#8 + 1#10B) 126 4, , Additional electrical room area (ft2) 20 5, , Cost ( $) 72,078 68,888 9,570 Cost ( %) Cost ($ per energized stall) 572 2,650 96

121 Electric Vehicle Charging Requirements Analysis Appendix C Parkade Layouts AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

122 STRATA LOT (62.2 m 2 ) STRATA LOT (45.6 m 2 ) STRATA LOT (45.8 m 2 ) STRATA LOT (45.8 m 2 ) STRATA LOT (103.7 m 2 ) STRATA LOT (56.4 m 2 ) STRATA LOT (64.2 m 2 ) MECHANICAL ROOM S 12 S 11 S 10 S 9 S 8 S 7 S 6 S 5 S 4 S 3 S 2 S 1 STAIRS STAIRS DRIVEWAY LOBBY LOBBY ELEV ELEC ENTRANCE STAIRS CORR GARBAGE/ RECYCLE ROOM CABLE RISER ELECTRICAL AND COMMUNICATIONS ROOM WATER ROOM GENE- RATOR ROOM S 13 S 14 S 15 S 16 S 17 S 46 S 47 S 48 S 49 S 50 S 51 S 52 S 53 S 54 S 45 S 44 S 43 S 42 S 41 S 40 S 39 S 38 S 37 ENTRANCE RAMP S 36 S 35 GENERAL NOTES 2 LEVELS OF PARKADE 54 PARKING STALLS PER FLOOR 108 PARKING STALLS TOTAL S 18 S 34 DRIVEWAY S 33 S 19 S 32 FAN ROOM S 20 S 21 S 22 S 23 S 24 S 25 S 26 S 27 S 28 S 29 S 30 S 31 STORAGE seal consultant 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project drawing title ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS TYPICAL HIGH RISE PARKING FLOOR PLAN designed scale date CF 1: AN 16 drawn project no. CF checked drawing no. rev. RB approved E100 1

123 STRATA LOT (62.2 m 2 ) STRATA LOT (45.6 m 2 ) STRATA LOT (45.8 m 2 ) STRATA LOT (45.8 m 2 ) LOBBY STRATA LOT (103.7 m 2 ) LOBBY STRATA LOT (56.4 m 2 ) ELEV ELEC ENTRANCE STAIRS CORR GARBAGE/ RECYCLE ROOM STRATA LOT (64.2 m 2 ) CABLE RISER ELECTRICAL AND COMMUNICATIONS ROOM WATER ROOM GENE- RATOR ROOM MECHANICAL ROOM STAIRS S 13 S 14 S 15 S 16 S 17 S 18 S 19 S 12 S 11 S 10 S 9 S 8 S 7 S 6 S 5 S 4 S 3 S 2 4 SETS OF 2#8 + 1#10 BOND IN 1-1/2"C 208Y/120V, 225A, 42 CCT PANEL 3 SETS OF 2#8 + 1#10 BOND IN 1-1/4"C 6 SETS OF 2#8 + 1#10 BOND IN 2"C 6 SETS OF 2#8 + 1#10 BOND IN 2"C DRIVEWAY S 46 S 47 S 48 S 49 S 50 S 51 S 52 S 53 S 45 S 44 S 43 S 42 S 41 S 40 S 39 S 38 DRIVEWAY S 54 S SETS OF 2#10 + 1#12 BOND IN 2"C 8 SETS OF 2#10 + 1#12 BOND IN 1-1/2"C 6 SETS OF 2#8 + 1#10 BOND IN 2"C 6 SETS OF 2#8 + 1#10 BOND IN 2"C S 1 STAIRS ENTRANCE RAMP 208Y/120V, 225A, 42 CCT PANEL S 36 S 35 S 34 S 33 S 32 GENERAL NOTES 2 LEVELS OF PARKADE 54 PARKING STALLS PER FLOOR 108 PARKING STALLS TOTAL LEVEL 1 CHARGING - DEDICATED 120V, 16A (1920W) PER STALL 208Y/120V, 225A, 42 CCT PANELS TOTAL OF 2 PANELS REQUIRED PER FLOOR 6 SETS OF 2#8 + 1#10 BOND IN 2"C FAN ROOM S 20 S 21 S 22 S 23 S 24 S 25 S 26 S 27 S 28 S 29 S 30 S 31 STORAGE seal consultant 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project drawing title ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS TYPICAL HIGH RISE L1 CHARGING (DEDICATED) designed scale date CF 1: AN 16 drawn project no. CF checked drawing no. rev. RB approved E101 1

124 STRATA LOT (62.2 m 2 ) STRATA LOT (45.6 m 2 ) STRATA LOT (45.8 m 2 ) STRATA LOT (45.8 m 2 ) STRATA LOT (103.7 m 2 ) STRATA LOT (56.4 m 2 ) STRATA LOT (64.2 m 2 ) MECHANICAL ROOM S 12 S 11 S 10 S 9 S 8 S 7 S 6 S 5 S 4 S 3 S 2 S 1 STAIRS STAIRS 2 SETS OF 2#8 + 1#10 BOND IN 1"C 2 SETS OF 2#8 + 1#10 BOND IN 1"C DRIVEWAY LOBBY LOBBY ELEV ELEC ENTRANCE STAIRS CORR GARBAGE/ RECYCLE ROOM CABLE RISER ELECTRICAL AND COMMUNICATIONS ROOM WATER ROOM GENE- RATOR ROOM S 13 2 SETS OF 2#8 + 1#10 BOND IN 1"C S 14 S 15 S 16 S Y/120V, 400A, 42 CCT PANEL 208Y/120V, 400A, 42 CCT PANEL S 46 S 47 S 48 S 49 S 50 S 51 S 52 S 53 S 45 S 44 S 43 S 42 S 41 S 40 S 39 S 38 S 54 S 37 ENTRANCE RAMP 208Y/120V, 400A, 42 CCT PANEL S 36 S 35 GENERAL NOTES 2 LEVELS OF PARKADE 54 PARKING STALLS PER FLOOR 108 PARKING STALLS TOTAL LEVEL 2 CHARGING - DEDICATED 208V, 32A (6656W) PER STALL 208Y/120V, 400A, 42 CCT PANELS TOTAL OF 4 PANELS REQUIRED PER FLOOR S 18 3 SETS OF 2#8 + 1#10 BOND IN 1-1/4"C S 19 2 SETS OF 2#8 + 1#10 BOND IN 1"C DRIVEWAY 2 SETS OF 2#8 + 1#10 BOND IN 1"C 3 SETS OF 2#8 + 1#10 BOND IN 1-1/4"C S 34 S 33 2 SETS OF 2#8 + 1#10 BOND IN 1"C 2 SETS OF 2#8 + 1#10 BOND IN 1"C S 32 2 SETS OF 2#8 + 1#10 BOND IN 1"C FAN ROOM S 20 S 21 S 22 S 23 S 24 S 25 S 26 S 27 S 28 S 29 S 30 S Y/120V, 400A, 42 CCT PANEL STORAGE seal consultant 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project drawing title ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS TYPICAL HIGH RISE L2 CHARGING (DEDICATED) designed scale date CF 1: AN 16 drawn project no. CF checked drawing no. rev. RB approved E102 1

125 STRATA LOT (62.2 m 2 ) STRATA LOT (45.6 m 2 ) STRATA LOT (45.8 m 2 ) STRATA LOT (45.8 m 2 ) STRATA LOT (103.7 m 2 ) STRATA LOT (56.4 m 2 ) STRATA LOT (64.2 m 2 ) MECHANICAL ROOM S 12 S 11 S 10 S 9 S 8 S 7 S 6 S 5 S 4 S 3 S 2 S 1 STAIRS STAIRS 2 SETS OF 2#8 + 1#10B in 27mmC 1 SET OF 2#8 + 1#10B DRIVEWAY LOBBY LOBBY ELEV ELEC ENTRANCE STAIRS CORR GARBAGE/ RECYCLE ROOM CABLE RISER ELECTRICAL AND COMMUNICATIONS ROOM WATER ROOM GENE- RATOR ROOM S 13 S 14 S 15 S 16 S 17 1 SET OF 2#8 + 1#10B 208Y/120V, 400A, 42 CCT PANEL 2 SETS OF 2#8 + 1#10B S 46 S 47 S 48 S 49 S 50 S 51 S 52 S 53 S 54 S 45 S 44 S 43 S 42 S 41 S 40 S 39 S 38 S 37 ENTRANCE RAMP 208Y/120V, 400A, 42 CCT PANEL S 36 S 35 GENERAL NOTES 2 LEVELS OF PARKADE 54 PARKING STALLS PER FLOOR 108 PARKING STALLS TOTAL LEVEL 2 CHARGING - 4/SHARED 32A * 208V (6,656W) PER 4 STALLS 208Y / 120V, 400 A, 42cct PANELS 1 PANEL PER FLOOR S 18 1 SET OF 2#8 + 1#10B 2 SETS OF 2#8 + 1#10B 2 SETS OF 2#8 + 1#10B S 34 S 19 2 SETS OF 2#8 + 1#10B DRIVEWAY S 33 S 32 1 SET OF 2#8 + 1#10B FAN ROOM S 20 S 21 S 22 S 23 S 24 S 25 S 26 S 27 S 28 S 29 S 30 S 31 STORAGE seal consultant 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project drawing title ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS TYPICAL HIGH RISE L2 CHARGING (LOAD SHARING) designed scale date CF 1: AN 16 drawn project no. CF checked drawing no. rev. RB approved E103 1

126 STRATA LOT (62.2 m 2 ) STRATA LOT (45.6 m 2 ) STRATA LOT (45.8 m 2 ) STRATA LOT (45.8 m 2 ) STRATA LOT (103.7 m 2 ) STRATA LOT (56.4 m 2 ) STRATA LOT (64.2 m 2 ) MECHANICAL ROOM STAIRS STAIRS S 12 S 11 S 10 S 9 S 8 S 7 S 6 S 5 S 4 S 3 S 2 S 1 DRIVEWAY LOBBY LOBBY ELEV ELEC ENTRANCE STAIRS CORR GARBAGE/ RECYCLE ROOM CABLE RISER ELECTRICAL AND COMMUNICATIONS ROOM WATER ROOM GENE- RATOR ROOM S 13 S 14 S 15 S 16 S Y/120V, 400A, 42 CCT PANEL S 46 S 47 S 48 S 49 S 50 S 51 S 52 S 53 S 45 S 44 S 43 S 42 S 41 S 40 S 39 S 38 S 54 S 37 ENTRANCE RAMP S 36 S 35 GENERAL NOTES 2 LEVELS OF PARKADE 54 PARKING STALLS PER FLOOR 108 PARKING STALLS TOTAL LEVEL 2 CHARGING - TRUNK STYLE 208V, 64A (13,312W) PER CIRCUIT 208Y/120V, 400A, 42 CCT PANELS TOTAL OF 1 PANEL REQUIRED TOTAL OF 3 CIRCUITS REQUIRED PER FLOOR S 18 S 34 ALL BRANCH WIRING FROM UNCTION BOXES TO UNITS IS TO BE 2#8 + 1#10 BOND IN 3/4"C S 19 DRIVEWAY S 33 ALL WIRING FROM PANELS TO UNCTION BOXES IS TO BE 2#1 + 1#6 BOND IN 1-1/4"C S 32 S 20 S 21 S 22 S 23 S 24 S 25 S 26 S 27 S 28 S 29 S 30 S 31 FAN ROOM STORAGE seal consultant 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project drawing title ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS TYPICAL HIGH RISE L2 CHARGING (TRUNK STYLE) designed scale date CF 1: AN 16 drawn project no. CF checked drawing no. rev. RB approved E104 1

127 BIKE STORAGE S 1 STAIRS LOBBY S 38 S 37 S 36 S 35 S 34 S 33 S 32 S 31 S 30 S 29 S 2 ELECTRICAL S 3 DRIVEWAY S 4 MECHANICAL S 5 S 6 S 7 DRIVEWAY S 39 S 40 S 41 S 42 S 52 S 51 S 50 S 49 S 53 S 54 S 55 S 56 STORAGE STAIRS ENTRANCE RAMP GENERAL NOTES 2 LEVELS OF PARKADE 63 PARKING STALLS PER FLOOR 126 PARKING STALLS TOTAL S 8 STORAGE S 9 S 43 S 48 S 57 S 10 S 11 S 44 S 47 S 58 S 45 S 46 S 59 S 60 S 61 S 62 S 63 STORAGE S 12 S 13 DRIVEWAY S 14 S 15 S 16 S 17 S 18 S 19 S 20 S 21 S 22 S 23 S 24 S 25 S 26 S 27 S 28 seal consultant 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project drawing title ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS TYPICAL MID RISE - WITHIN CITY CENTRE PARKING FLOOR PLAN designed scale date CF 1: AN 16 drawn project no. CF checked drawing no. rev. RB approved E110 1

128 BIKE STORAGE S 1 STAIRS LOBBY S 38 S 37 S 36 S 35 S 34 S 33 S 32 S 31 S 30 S 29 S 2 1 SET OF 2#8 + 1#10 BOND IN 3/4"C 4 SETS OF 2#8 + 1#10 BOND IN 1-1/2"C 6 SETS OF 2#8 + 1#10 BOND IN 2"C ELECTRICAL MECHANICAL STORAGE STORAGE S 3 S 4 S 5 S 6 S 7 S 8 S 9 S 10 S 11 S 12 S 13 6 SETS OF 2#8 + 1#10 BOND IN 2"C DRIVEWAY 4 SETS OF 2#8 + 1#10 BOND IN 1-1/2"C 208Y/120V, 225A, 42 CCT PANEL S 39 S 40 S 41 S 42 S 52 S 51 S 50 S 49 S 43 S 48 S 44 S 47 DRIVEWAY 14 SETS OF 2#10 + 1#10 BOND IN 2"C S 53 S 54 S 55 S 58 S 45 S 46 S 59 DRIVEWAY 6 SETS OF 2#8 + 1#10 BOND IN 2"C STORAGE STAIRS ENTRANCE RAMP S 56 4 SETS OF 2#10 + 1#12 BOND IN 1"C 208Y/120V, 225A, 42 CCT S 57 PANEL 3 SETS OF 2#10 + 1#12 BOND IN 3/4"C 4 SETS OF 2#10 + 1#12 BOND IN 1"C 6 SETS OF 2#8 + 1#10 BOND IN 2"C S 60 S 61 S 62 S 63 5 SETS OF 2#8 + 1#10 BOND IN 1-1/2"C GENERAL NOTES 2 LEVELS OF PARKADE 63 PARKING STALLS PER FLOOR 126 PARKING STALLS TOTAL LEVEL 1 CHARGING - DEDICATED 120V, 16A (1920W) PER STALL 208Y/120V, 225A, 42 CCT PANELS TOTAL OF 2 PANELS REQUIRED PER FLOOR S 14 S 15 S 16 S 17 S 18 S 19 S 20 S 21 S 22 S 23 S 24 S 25 S 26 S 27 S 28 seal consultant 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project drawing title ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS TYPICAL MID RISE - WITHIN CITY CENTRE L1 CHARGING (DEDICATED) designed scale date CF 1: AN 16 drawn project no. CF checked drawing no. rev. RB approved E111 1

129 BIKE STORAGE S 1 STAIRS LOBBY S 38 S 37 S 36 S 35 S 34 S 33 S 32 S 31 S 30 S 29 S 2 1 SET OF 2#8 + 1#10 BOND IN 3/4"C 2 SETS OF 2#8 + 1#10 BOND IN 1"C 2 SETS OF 2#8 + 1#10 BOND IN 1"C ELECTRICAL MECHANICAL STORAGE STORAGE S 3 S 4 S 5 2 SETS OF 2#8 + 1#10 BOND IN 1"C S 6 S 7 S 8 S 9 S 10 S 11 S 12 S 13 DRIVEWAY 208Y/120V, 400A, 42 CCT PANEL 1 SET OF 2#8 + 1#10 BOND IN 3/4"C S 39 S 40 S 41 S 42 2 SETS OF 2#8 + 1#10 BOND IN 1"C S 52 S 51 S 50 S 49 S 43 S 48 S 44 S Y/120V, 400A, 42 CCT PANEL DRIVEWAY S 53 S 54 S 55 S 56 2 SETS OF 2#8 + 1#10 BOND IN 1"C S 57 3 SETS OF 2#8 + 1#10 BOND IN 1-1/4"C S 58 S 45 S 46 S 59 DRIVEWAY 2 SETS OF 2#8 + 1#10 BOND IN 1"C 208Y/120V, 400A, 42 CCT PANEL STORAGE STAIRS 208Y/120V, 400A, 42 CCT PANEL ENTRANCE RAMP 2 SETS OF 2#8 + 1#10 BOND IN 1"C S 60 S 61 S 62 S Y/120V, 400A, 42 CCT PANEL 1 SET OF 2#8 + 1#10 BOND IN 3/4"C 2 SETS OF 2#8 + 1#10 BOND IN 1"C GENERAL NOTES 2 LEVELS OF PARKADE 63 PARKING STALLS PER FLOOR 126 PARKING STALLS TOTAL LEVEL 2 CHARGING - DEDICATED 208V, 32A (6656W) PER STALL 208Y/120V, 400A, 42 CCT PANELS TOTAL OF 5 PANELS REQUIRED PER FLOOR S 14 S 15 S 16 S 17 S 18 S 19 S 20 S 21 S 22 S 23 S 24 S 25 S 26 S 27 S 28 seal consultant 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project drawing title ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS TYPICAL MID RISE - WITHIN CITY CENTRE L2 CHARGING (DEDICATED) designed scale date CF 1: AN 16 drawn project no. CF checked drawing no. rev. RB approved E112 1

130 BIKE STORAGE S 1 STAIRS LOBBY S 38 S 37 S 36 S 35 S 34 S 33 S 32 S 31 S 30 S 29 S 2 1 SET OF 2#8 + 1#10 BOND IN 3/4"C 1 SET OF 2#8 + 1#10 BOND IN 3/4"C 2 SETS OF 2#8 + 1#10 BOND IN 1"C 2 SETS OF 2#8 + 1#10 BOND IN 1"C ELECTRICAL MECHANICAL STORAGE STORAGE S 3 S 4 S 5 S 6 S 7 S 8 S 9 S 10 S 11 S 12 S 13 1 SET OF 2#8 + 1#10 BOND IN 3/4"C DRIVEWAY 1 SET OF 2#8 + 1#10 BOND IN 3/4"C 208Y/120V, 400A, 42 CCT PANEL S 39 S 40 S 41 S 42 S 52 S 51 S 50 S 49 S 43 S 48 S 44 S 47 2 SETS OF 2#8 + 1#10 BOND IN 1"C 2 SETS OF 2#8 + 1#10 BOND IN 1"C DRIVEWAY S 53 S 54 S 55 S 58 S 45 S 46 S 59 DRIVEWAY STORAGE STAIRS ENTRANCE RAMP S 56 1 SET OF 2#8 + 1#10 BOND IN 3/4"C 208Y/120V, 400A, 42 CCT S 57 PANEL 1 SET OF 2#8 + 1#10 BOND IN 3/4"C 1 SET OF 2#8 + 1#10 BOND IN 3/4"C 1 SET OF 2#8 + 1#10 BOND IN 3/4"C S 60 S 61 S 62 S 63 2 SETS OF 2#8 + 1#10 BOND IN 1"C GENERAL NOTES 2 LEVELS OF PARKADE 63 PARKING STALLS PER FLOOR 126 PARKING STALLS TOTAL LEVEL 2 CHARGING - LOAD SHARING 208V, 32A (6656W) PER 4 STALLS (APPROXIMATE) 208Y/120V, 400A, 42 CCT PANELS TOTAL OF 2 PANELS REQUIRED PER FLOOR S 14 S 15 S 16 S 17 S 18 S 19 S 20 S 21 S 22 S 23 S 24 S 25 S 26 S 27 S 28 seal consultant 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project drawing title ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS TYPICAL MID RISE - WITHIN CITY CENTRE L2 CHARGING (LOAD SHARING) designed scale date CF 1: AN 16 drawn project no. CF checked drawing no. rev. RB approved E113 1

131 BIKE STORAGE STAIRS LOBBY S 1 S 38 S 37 S 36 S 35 S 34 S 33 S 32 S 31 S 30 S 29 S 2 ELECTRICAL S 3 DRIVEWAY S 4 MECHANICAL S 5 S 6 S 7 DRIVEWAY S 39 S 40 S 41 S 42 S 52 S 51 S 50 S 49 S 53 S 54 S 55 S 56 STORAGE STAIRS ENTRANCE RAMP GENERAL NOTES 2 LEVELS OF PARKADE 63 PARKING STALLS PER FLOOR 126 PARKING STALLS TOTAL STORAGE S 8 S 9 S 10 S 43 S 48 S 44 S 47 S 57 S 58 LEVEL 2 CHARGING - TRUNK STYLE 208V, 64A (13,312W) PER CIRCUIT 208Y/120V, 400A, 42 CCT PANELS TOTAL OF 1 PANEL REQUIRED TOTAL OF 7 CIRCUITS REQUIRED STORAGE S 11 S 12 S 13 S 45 S 46 S 59 DRIVEWAY S 60 S 61 S 62 S Y/120V, 400A, 42 CCT PANEL TO 2ND FLOOR OF PARKADE TO 2ND FLOOR OF PARKADE ALL BRANCH WIRING FROM UNCTION BOXES TO UNITS IS TO BE 2#8 + 1#10 BOND IN 3/4"C ALL WIRING FROM PANELS TO UNCTION BOXES IS TO BE 2#1 + 1#6 BOND IN 1-1/4"C S 14 S 15 S 16 S 17 S 18 S 19 S 20 S 21 S 22 S 23 S 24 S 25 S 26 S 27 S 28 seal consultant 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project drawing title ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS TYPICAL MID RISE - WITHIN CITY CENTRE L2 CHARGING (TRUNK STYLE) designed scale date CF 1: AN 16 drawn project no. CF checked drawing no. rev. RB approved E114 1

132 MECHANICAL ROOM STORAGE S 68 S 67 S 66 S 65 S 64 S 63 S 62 S 61 S 60 S 59 S 58 S 57 S 56 S 55 S 54 S 53 S 52 S 51 S 50 ELECTRICAL ROOM DRIVEWAY DRIVEWAY STAIRS ENTRANCE RAMP S 1 S 2 S 69 S 70 S 92 S 91 S 93 S 94 S 112 S 111 S 113 S 114 S 136 S 135 S 49 S 3 S 4 S 5 S 6 DRIVEWAY S 71 S 72 S 73 S 74 S 90 S 89 S 88 S 87 DRIVEWAY S 95 S 96 S 97 STORAGE S 110 S 109 S 108 STAIRS DRIVEWAY S 115 S 116 S 117 S 118 S 134 S 133 S 132 S 131 DRIVEWAY S 48 S 47 S 46 S 45 GENERAL NOTES 1 LEVEL OF PARKADE 136 PARKING STALLS TOTAL S 7 S 8 S 75 S 86 S 119 S 130 CORRIDOR S 44 S 9 S 10 S 76 S 77 S 85 S 84 S 98 S 99 S 107 S 106 S 120 S 121 S 129 S 128 S 43 S 42 S 11 S 12 S 13 S 14 S 78 S 79 S 83 S 82 S 100 S 101 S 105 S 104 S 122 S 123 S 127 S 126 S 80 S 81 S 102 S 103 S 124 S 125 S 41 S 40 S 39 S 15 DRIVEWAY DRIVEWAY S 38 S 16 STORAGE STAIRS S 17 S 18 S 19 S 20 S 21 S 22 S 23 S 24 S 25 S 26 S 27 S 28 S 29 S 30 S 31 S 32 S 33 S 34 S 35 S 36 S 37 STAIRS seal consultant 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project drawing title ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS TYPICAL MID RISE - OUTSIDE CITY CENTRE PARKING FLOOR PLAN designed scale date CF 1: AN 16 drawn project no. CF checked drawing no. rev. RB approved E120 1

133 MECHANICAL ROOM STORAGE S 68 S 67 S 66 S 65 S 64 S 63 S 62 S 61 S 60 S 59 S 58 S 57 S 56 S 55 S 54 S 53 S 52 S 51 S 50 ELECTRICAL ROOM 5 SETS OF 2#8 + 1#10 BOND IN 1-1/2"C 8 SETS OF 2#8 + 1#10 BOND IN 2"C DRIVEWAY DRIVEWAY STAIRS S 1 S 2 8 SETS OF 2#8 + 1#10 BOND IN 2"C S 69 S Y/120V, 225A, 42 CCT PANEL 6 SETS OF 2#8 + 1#10 BOND IN 2"C 12 SETS OF 2#10 + 1#12 BOND IN 2"C S 92 S 91 S 93 S SETS OF 2#8 + 1#10 BOND IN 2-1/4"C S 112 S SETS OF 2#10 + 1#12 BOND IN 2"C S 113 S Y/120V, 225A, 42 CCT PANEL S 136 S 135 S 49 ENTRANCE RAMP S 3 S 4 S 5 S 6 S 7 S 8 DRIVEWAY S 71 S 72 S 73 S 74 S 90 S 89 S 88 S 87 DRIVEWAY S 95 S 96 S 97 S 75 S 86 S 119 S 130 CORRIDOR STORAGE S 110 S 109 S 108 STAIRS DRIVEWAY S 115 S 116 S 117 S 118 S 134 S 133 S 132 S SETS OF 2#8 + 1#10 BOND IN 2"C DRIVEWAY S 48 S 47 S 46 S 45 S 44 GENERAL NOTES 1 LEVEL OF PARKADE 136 PARKING STALLS TOTAL LEVEL 1 CHARGING - DEDICATED 120V, 16A (1920W) PER STALL 208Y/120V, 225A, 42 CCT PANELS TOTAL OF 4 PANELS REQUIRED S 9 S 10 S 76 S 77 S 85 S 84 S 98 S 99 S 107 S 106 S 120 S 121 S 129 S 128 S 43 S 42 S 11 S 12 S 13 S 14 S 15 S 78 S 79 S 83 S 82 S 80 S 81 S 102 S 103 S 124 S SETS OF 2#10 + 1#12 BOND IN 2"C 12 SETS OF 2#10 + 1#12 BOND IN 2"C 8 SETS OF 2#8 + 1#10 BOND IN 2"C 10 SETS OF 2#8 + 1#10 BOND IN 2-1/4"C 208Y/120V, 225A, 42 CCT PANEL DRIVEWAY S 100 S 101 S 105 S 104 DRIVEWAY S 122 S SETS OF 2#8 + 1#10 BOND IN 1-1/2"C S 127 S Y/120V, 225A, 42 CCT PANEL 6 SETS OF 2#8 + 1#10 BOND IN 2"C S 41 S 40 S 39 S 38 S 16 6 SETS OF 2#8 + 1#10 BOND IN 2"C 6 SETS OF 2#8 + 1#10 BOND IN 2"C 5 SETS OF 2#8 + 1#10 BOND IN 1-1/2"C STORAGE STAIRS S 17 S 18 S 19 S 20 S 21 S 22 S 23 S 24 S 25 S 26 S 27 S 28 S 29 S 30 S 31 S 32 S 33 S 34 S 35 S 36 S 37 STAIRS seal consultant 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project drawing title ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS TYPICAL MID RISE - OUTSIDE CITY CENTRE L1 CHARGING (DEDICATED) designed scale date CF 1: AN 16 drawn project no. CF checked drawing no. rev. RB approved E121 1

134 1 SET OF 2#8 + 1#10 BOND IN 3/4"C MECHANICAL ROOM STORAGE 208Y/120V, 400A, 42 CCT PANEL S 68 S 67 S 66 S 65 S 64 2 SETS OF 2#8 + 1#10 BOND IN 1"C S 63 S 62 S 61 S 60 S 59 S 58 S 57 S 56 S 55 S 54 S 53 S 52 DRIVEWAY DRIVEWAY S 51 S 50 2 SETS OF 2#8 + 1#10 BOND IN 1"C 2 SETS OF 2#8 + 1#10 BOND IN 1"C ELECTRICAL ROOM 208Y/120V, 400A, 42 CCT PANEL STAIRS 208Y/120V, 400A, 42 CCT PANEL 208Y/120V, 400A, 42 CCT PANEL 208Y/120V, 400A, 42 CCT PANEL ENTRANCE RAMP S 1 2 SETS OF 2#8 + 1#10 BOND IN 1"C S 2 S 69 S 70 S 92 2 SETS OF 2#8 + 1#10 BOND IN 1"C S 91 S 93 S 94 S SETS OF 2#8 + 1#10 BOND IN 1"C S 111 S 113 S 114 S 136 S 135 S 49 S 3 S 4 S 5 S 6 DRIVEWAY S 71 S 72 S 73 S 74 S 90 S 89 S 88 S 87 1 SET OF 2#8 + 1#10 BOND IN 3/4"C DRIVEWAY S 95 S 96 S 97 STORAGE S 110 S 109 S 108 STAIRS DRIVEWAY S 115 S 116 S 117 S 118 S 134 S 133 S 132 S 131 DRIVEWAY S 48 S 47 S 46 S 45 GENERAL NOTES 1 LEVEL OF PARKADE 136 PARKING STALLS TOTAL S 7 S 8 S 75 S 86 S 119 S 130 CORRIDOR S 44 LEVEL 2 CHARGING - DEDICATED 208V, 32A (6656W) PER STALL 208Y/120V, 400A, 42 CCT PANELS TOTAL OF 9 PANELS REQUIRED S 9 S 10 S 76 S 77 S 85 S 84 S 98 S 99 S 107 S 106 S 120 S 121 S 129 S 128 S 43 S 42 S 11 S 12 S 13 S 14 S 15 2 SETS OF 2#8 + 1#10 BOND IN 1"C S 78 S 79 S 83 S 82 S 100 S 101 S 80 S 81 S 102 S 103 S 124 S SETS OF 2#8 + 1#10 BOND IN 1"C 208Y/120V, 400A, 42 CCT PANEL 2 SETS OF 2#8 + 1#10 BOND IN 1"C S 105 S Y/120V, 400A, 42 CCT PANEL 2 SETS OF 2#8 + 1#10 BOND IN 1"C S 122 S 123 S 127 S Y/120V, 400A, 42 CCT PANEL S 41 S 40 S 39 S 38 S 16 2 SETS OF 2#8 + 1#10 BOND IN 1"C 2 SETS OF 2#8 + 1#10 BOND IN 1"C DRIVEWAY 1 SET OF 2#8 + 1#10 BOND IN 3/4"C 2 SETS OF 2#8 + 1#10 BOND IN 1"C 208Y/120V, 400A, 42 CCT PANEL STORAGE STAIRS S 17 S 18 S 19 S 20 S 21 S 22 S 23 S 24 S 25 S 26 S 27 S 28 S 29 S 30 S 31 S 32 S 33 S 34 S 35 S 36 S 37 STAIRS seal consultant 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project drawing title ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS TYPICAL MID RISE - OUTSIDE CITY CENTRE L2 CHARGING (DEDICATED) designed scale date CF 1: AN 16 drawn project no. CF checked drawing no. rev. RB approved E122 1

135 MECHANICAL ROOM STORAGE S 68 S 67 S 66 S 65 S 64 S 63 S 62 S 61 S 60 S 59 S 58 S 57 S 56 S 55 S 54 S 53 S 52 S 51 S 50 ELECTRICAL ROOM 2 SETS OF 2#8 + 1#10 BOND IN 1"C 1 SET OF 2#8 + 1#10 BOND IN 3/4"C 2 SETS OF 2#8 + 1#10 BOND IN 1"C DRIVEWAY DRIVEWAY STAIRS S 1 S 2 208Y/120V, 400A, 42 CCT PANEL 2 SETS OF 2#8 + 1#10 BOND IN 1"C S 69 S 70 3 SETS OF 2#8 + 1#10 BOND IN 1-1/4"C S 92 S 91 S 93 S 94 3 SETS OF 2#8 + 1#10 BOND IN 1-1/4"C S 112 S SETS OF 2#8 + 1#10 BOND IN 1-1/4"C S 113 S Y/120V, 400A, 42 CCT PANEL S 136 S 135 S 49 ENTRANCE RAMP S 3 S 4 S 5 S 6 DRIVEWAY S 71 S 72 S 73 S 74 S 90 S 89 S 88 S 87 DRIVEWAY S 95 S 96 S 97 STORAGE S 110 S 109 S 108 STAIRS DRIVEWAY S 115 S 116 S 117 S 118 S 134 S 133 S 132 S SETS OF 2#8 + 1#10 BOND IN 1"C DRIVEWAY S 48 S 47 S 46 S 45 GENERAL NOTES 1 LEVEL OF PARKADE 136 PARKING STALLS TOTAL S 7 S 8 S 75 S 86 S 119 S 130 CORRIDOR S 44 LEVEL 2 CHARGING - LOAD SHARING 208V, 32A (6656W) PER 4 STALLS (APPROXIMATE) 208Y/120V, 400A, 42 CCT PANELS TOTAL OF 4 PANELS REQUIRED S 9 S 10 S 76 S 77 S 85 S 84 S 98 S 99 S 107 S 106 S 120 S 121 S 129 S 128 S 43 S 42 S 11 S 12 S 13 S 14 S 15 S 78 S 79 S 83 S 82 S 80 S 81 S 102 S 103 S 124 S SETS OF 2#8 + 1#10 BOND IN 1-1/4"C 3 SETS OF 2#8 + 1#10 BOND IN 1-1/4"C 2 SETS OF 2#8 + 1#10 BOND IN 1"C 3 SETS OF 2#8 + 1#10 BOND IN 1-1/4"C 208Y/120V, 400A, 42 CCT PANEL DRIVEWAY S 100 S 101 S 105 S 104 DRIVEWAY S 122 S 123 S 127 S Y/120V, 400A, 42 CCT PANEL 1 SET OF 2#8 + 1#10 BOND IN 3/4"C S 41 S 40 S 39 S 38 S 16 2 SETS OF 2#8 + 1#10 BOND IN 1"C 1 SET OF 2#8 + 1#10 BOND IN 3/4"C 1 SET OF 2#8 + 1#10 BOND IN 3/4"C 2 SETS OF 2#8 + 1#10 BOND IN 1"C STORAGE STAIRS S 17 S 18 S 19 S 20 S 21 S 22 S 23 S 24 S 25 S 26 S 27 S 28 S 29 S 30 S 31 S 32 S 33 S 34 S 35 S 36 S 37 STAIRS seal consultant 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project drawing title ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS TYPICAL MID RISE - OUTSIDE CITY CENTRE L2 CHARGING (LOAD SHARING) designed scale date CF 1: AN 16 drawn project no. CF checked drawing no. rev. RB approved E123 1

136 MECHANICAL ROOM STORAGE S 68 S 67 S 66 S 65 S 64 S 63 S 62 S 61 S 60 S 59 S 58 S 57 S 56 S 55 S 54 S 53 S 52 S 51 S 50 ELECTRICAL ROOM DRIVEWAY DRIVEWAY STAIRS 208Y/120V, 400A, 42 CCT PANEL ENTRANCE RAMP S 1 S 69 S 92 S 93 S 112 S 113 S 136 S 2 S 3 S 4 S 5 S 6 S 7 S 8 DRIVEWAY S 70 S 91 S 71 S 90 S 72 S 89 S 73 S 88 S 74 S 87 DRIVEWAY S 94 S 111 S 95 S 110 S 96 S 97 S 109 S 108 STORAGE STAIRS S 75 S 86 CORRIDOR S 119 S 130 DRIVEWAY S 114 S 135 S 115 S 134 S 116 S 133 S 117 S 132 S 118 S 131 DRIVEWAY S 49 S 48 S 47 S 46 S 45 S 44 GENERAL NOTES 1 LEVEL OF PARKADE 136 PARKING STALLS TOTAL LEVEL 2 CHARGING - TRUNK STYLE 208V, 64A (13,312W) PER CIRCUIT 208Y/120V, 400A, 42 CCT PANELS TOTAL OF 2 PANELS REQUIRED TOTAL OF 9 CIRCUITS REQUIRED S 9 S 10 S 76 S 77 S 85 S 84 S 98 S 99 S 107 S 106 S 120 S 121 S 129 S 128 S 43 S 42 ALL BRANCH WIRING FROM UNCTION BOXES TO UNITS IS TO BE 2#8 + 1#10 BOND IN 3/4"C ALL WIRING FROM PANELS TO UNCTION BOXES IS TO BE 2#1 + 1#6 BOND IN 1-1/4"C S 11 S 12 S 13 S 14 S 15 S 78 S 79 S 83 S 82 DRIVEWAY S 100 S 101 S 80 S 81 S 102 S 103 S 124 S Y/120V, 400A, 42 CCT PANEL S 105 S 104 DRIVEWAY S 122 S 123 S 127 S 126 S 41 S 40 S 39 S 38 S 16 S 17 S 18 S 19 S 20 S 21 S 22 S 23 S 24 S 25 S 26 S 27 S 28 S 29 S 30 S 31 S 32 S 33 S 34 S 35 S 36 S 37 STORAGE STAIRS STAIRS seal consultant 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project drawing title ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS TYPICAL MID RISE - OUTSIDE CITY CENTRE L2 CHARGING (TRUNK STYLE) designed scale date CF 1: AN 16 drawn project no. CF checked drawing no. rev. RB approved E124 1

137 SUITE A SUITE B SUITE C SUITE D SUITE E SUITE F SUITE G SUITE H CLOSET BEDROOM STALL #1 STALL #2 ENTRANCE STAIRS WASHROOM STAIRS WASHROOM BEDROOM ENTRANCE STALL #1 STALL #2 CLOSET CLOSET BEDROOM STALL #1 STALL #2 ENTRANCE STAIRS WASHROOM STAIRS WASHROOM BEDROOM ENTRANCE STALL #1 STALL #2 CLOSET CLOSET BEDROOM STALL #1 STALL #2 ENTRANCE STAIRS WASHROOM STAIRS WASHROOM BEDROOM ENTRANCE STALL #1 STALL #2 CLOSET CLOSET BEDROOM STALL #1 STALL #2 ENTRANCE STAIRS WASHROOM STAIRS WASHROOM BEDROOM ENTRANCE STALL #1 STALL #2 CLOSET LANEWAY LANEWAY LANEWAY LANEWAY STALL #1 STALL #2 ENTRANCE STAIRS STAIRS ENTRANCE STALL #1 STALL #2 STALL #1 STALL #2 ENTRANCE STAIRS STAIRS ENTRANCE STALL #1 STALL #2 STALL #1 STALL #2 ENTRANCE STAIRS STAIRS ENTRANCE STALL #1 STALL #2 STALL #1 STALL #2 ENTRANCE STAIRS STAIRS ENTRANCE STALL #1 STALL #2 CLOSET BEDROOM WASHROOM WASHROOM BEDROOM CLOSET CLOSET BEDROOM WASHROOM WASHROOM BEDROOM CLOSET CLOSET BEDROOM WASHROOM WASHROOM BEDROOM CLOSET CLOSET BEDROOM WASHROOM WASHROOM BEDROOM CLOSET SUITE I SUITE SUITE K SUITE L SUITE M SUITE N SUITE O SUITE P GENERAL NOTES 16 SUITES 2 PARKING SPOTS PER SUITE 32 PARKING STALLS TOTAL FED FROM TENANT PANELBOARDS seal consultant 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project drawing title ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS TYPICAL TOWNHOUSES GROUND FLOOR PLAN designed scale date CF 1: AN 03 drawn project no. CF checked drawing no. rev. RB approved E130 1

138 Electric Vehicle Charging Requirements Analysis Appendix D APPENDIX Single Line D Diagrams AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

139 BC HYDRO KV SERVICE MAIN ELECTRICAL ROOM L.B.S. 25 kv MAIN CIRCUIT BREAKER 1000 kva 25 kv - 600Y/347V 800 A, SECONDARY CIRCUIT BREAKER 800A, 600Y/347V x A x A BCH COMMON AREA LOADS RESIDENTIAL UNIT LOADS (METER CENTRES) consultant drawing title designed scale date 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project HIGH RISE - CITY CENTRE BASE DESIGN ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS drawn checked approved CF CF RB RB project no. drawing no. N/A 2017 AN E000 rev. 1

140 BC HYDRO KV SERVICE MAIN ELECTRICAL ROOM L.B.S. 25 kv MAIN CIRCUIT BREAKER 1500 kva 25 kv - 600Y/347V 1200 A, SECONDARY CIRCUIT BREAKER 1200A, 600Y/347V x A x A 225 A BCH BCH COMMON AREA LOADS RESIDENTIAL UNIT LOADS (METER CENTRES) 225 kva 600V - 208Y/120V 800A, 208Y/120V 200A 200A 200A 200A 225A, 208Y/120V 42 CCT PANELBOARD 20A, 120V BRANCH CIRCUITS (108 TOTAL) consultant drawing title designed scale date 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project HIGH RISE - CITY CENTRE 100% L1 ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS drawn checked approved CF CF RB RB project no. drawing no. N/A 2017 AN E001 rev. 1

141 BC HYDRO KV SERVICE MAIN ELECTRICAL ROOM L.B.S. 25 kv MAIN CIRCUIT BREAKER 2000 kva 25 kv - 600Y/347V 1600 A, SECONDARY CIRCUIT BREAKER 1600A, 600Y/347V x A x A 800 AF / 690 AT BCH BCH COMMON AREA LOADS RESIDENTIAL UNIT LOADS (METER CENTRES) 750 kva 600V - 208Y/120V 2000A, 208Y/120V 400A 400A 400A 400A 400A 400A 400A 400A 400A, 208Y/120V 42 CCT PANELBOARD 40A, 208V BRANCH CIRCUITS (108 TOTAL) consultant drawing title designed scale date 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project HIGH RISE - CITY CENTRE 100% L2 ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS drawn checked approved CF CF RB RB project no. drawing no. N/A 2017 AN E002 rev. 1

142 BC HYDRO KV SERVICE MAIN ELECTRICAL ROOM L.B.S. 25 kv MAIN CIRCUIT BREAKER 1500 kva 25 kv - 600Y/347V 1200 A, SECONDARY CIRCUIT BREAKER 1200A, 600Y/347V x A x A 225 A BCH BCH COMMON AREA LOADS RESIDENTIAL UNIT LOADS (METER CENTRES) 225 kva 600V - 208Y/120V 800A, 208Y/120V 400A 400A 400A, 208Y/120V 42 CCT PANELBOARD 4 STALLS PER 40A, 208V BRANCH CIRCUIT (108 STALLS TOTAL) consultant drawing title designed scale date 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project HIGH RISE - CITY CENTRE 100% L2, 4-SHARED ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS drawn checked approved CF CF RB RB project no. drawing no. N/A 2017 AN E003 rev. 1

143 BC HYDRO KV SERVICE MAIN ELECTRICAL ROOM L.B.S. 25 kv MAIN CIRCUIT BREAKER 1000 kva 25 kv - 600Y/347V 125 A, SECONDARY CIRCUIT BREAKER 1200A, 600Y/347V x A x A 125 A BCH BCH COMMON AREA LOADS RESIDENTIAL UNIT LOADS (METER CENTRES) kva 600V - 208Y/120V 400A, 208Y/120V, PANELBOARD 80 A 2p 80 A 2p 80 A 2p 80 A 2p 80 A 2p 80 A 2p 80 A, 2p, TRUNK CIRCUIT 40A, 208V OUTLET 18 STALLS PER TRUNK (108 STALLS TOTAL) 40 A 2p... (18 TOTAL) 40 A 2p consultant drawing title designed scale date 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project HIGH RISE - CITY CENTRE 100% L2, TRUNK STYLE ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS drawn checked approved CF CF RB RB project no. drawing no. N/A 2017 AN E004 rev. 1

144 BC HYDRO KV SERVICE MAIN ELECTRICAL ROOM L.B.S. 25 kv MAIN CIRCUIT BREAKER 1000 kva 25 kv - 208Y/120V 3000 A, SECONDARY CIRCUIT BREAKER 3000A, 208Y/120V x A x A BCH COMMON AREA LOADS RESIDENTIAL UNIT LOADS (METER CENTRES) consultant drawing title designed scale date 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project MID RISE - CITY CENTRE BASE DESIGN ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS drawn checked approved CF CF RB RB project no. drawing no. N/A 2017 AN E010 rev. 1

145 BC HYDRO KV SERVICE MAIN ELECTRICAL ROOM L.B.S. 25 kv MAIN CIRCUIT BREAKER 1500 kva 25 kv - 208Y/120V 3000 A, SECONDARY CIRCUIT BREAKER BCH 3000A, 208Y/120V x A x A 200 A 200 A 200 A 200 A BCH COMMON AREA LOADS RESIDENTIAL UNIT LOADS (METER CENTRES) 225A, 208Y/120V 42 POLE PANELBOARDS 20A, 120V BRANCH CIRCUITS (126 TOTAL) consultant drawing title designed scale date 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project MID RISE - CITY CENTRE 100% L1 ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS drawn checked approved CF CF RB RB project no. drawing no. N/A 2017 AN E011 rev. 1

146 BC HYDRO KV SERVICE MAIN ELECTRICAL ROOM L.B.S. 25 kv MAIN CIRCUIT BREAKER 2000 kva 25 kv - 208Y/120V 3000 A, SECONDARY CIRCUIT BREAKER 3000 A, SECONDARY CIRCUIT BREAKER 3000A, 208Y/120V BCH x A x A 3000A, 208Y/120V BCH 400 A... (10 TOTAL) 400 A COMMON AREA LOADS RESIDENTIAL UNIT LOADS (METER CENTRES) 400A, 208Y/120V 42 CCT PANELBOARD 40A, 208V BRANCH CIRCUITS (126 TOTAL) consultant drawing title designed scale date 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project MID RISE - CITY CENTRE 100% L2 ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS drawn checked approved CF CF RB RB project no. drawing no. N/A 2017 AN E012 rev. 1

147 BC HYDRO KV SERVICE MAIN ELECTRICAL ROOM L.B.S. 25 kv MAIN CIRCUIT BREAKER 1500 kva 25 kv - 208Y/120V 3000 A, SECONDARY CIRCUIT BREAKER BCH 3000A, 208Y/120V x A x A 400 A 400 A 400 A 400 A BCH COMMON AREA LOADS RESIDENTIAL UNIT LOADS (METER CENTRES) 400A, 208Y/120V 42 CCT PANELBOARD 4 STALLS PER 40A, 208V BRANCH CIRCUIT (126 STALLS TOTAL) consultant drawing title designed scale date 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project MID RISE - CITY CENTRE 100% L2, 4-SHARED ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS drawn checked approved CF CF RB RB project no. drawing no. N/A 2017 AN E013 rev. 1

148 BC HYDRO KV SERVICE MAIN ELECTRICAL ROOM L.B.S. 25 kv MAIN CIRCUIT BREAKER 1000 kva 25 kv - 208Y/120V 3000 A, SECONDARY CIRCUIT BREAKER 3000A, 208Y/120V x A x A 400 A BCH BCH COMMON AREA LOADS RESIDENTIAL UNIT LOADS (METER CENTRES) 400A, 208Y/120V, PANELBOARD 80 A 2p 80 A 2p 80 A 2p 80 A 2p 80 A 2p 80 A 2p 80 A 2p 80 A, 2p, TRUNK CIRCUIT 40A, 208V OUTLET 18 STALLS PER TRUNK (126 STALLS TOTAL) 40 A 2p... (18 TOTAL) 40 A 2p consultant drawing title designed scale date 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project MID RISE - CITY CENTRE 100% L2, TRUNK STYLE ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS drawn checked approved CF CF RB RB project no. drawing no. N/A 2017 AN E014 rev. 1

149 BC HYDRO KV SERVICE MAIN ELECTRICAL ROOM L.B.S. 25 kv MAIN CIRCUIT BREAKER 500 kva 25 kv - 208Y/120V 1600 A, SECONDARY CIRCUIT BREAKER 1600A, 208Y/120V x A x A BCH COMMON AREA LOADS RESIDENTIAL UNIT LOADS (METER CENTRES) consultant drawing title designed scale date 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project MID RISE - OUTSIDE CITY CENTRE BASE DESIGN ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS drawn checked approved CF CF RB RB project no. drawing no. N/A 2017 AN E020 rev. 1

150 BC HYDRO KV SERVICE MAIN ELECTRICAL ROOM L.B.S. 25 kv MAIN CIRCUIT BREAKER 750 kva 25 kv - 208Y/120V 2000 A, SECONDARY CIRCUIT BREAKER BCH 2000A, 208Y/120V x A x A 200 A 200 A 200 A 200 A BCH COMMON AREA LOADS RESIDENTIAL UNIT LOADS (METER CENTRES) 225A, 208Y/120V 42 CCT PANELBOARD 20A, 120V BRANCH CIRCUITS (136 TOTAL) consultant drawing title designed scale date 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project MID RISE - OUTSIDE CITY CENTRE 100% L1 ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS drawn checked approved CF CF RB RB project no. drawing no. N/A 2017 AN E021 rev. 1

151 BC HYDRO KV SERVICE MAIN ELECTRICAL ROOM L.B.S. 25 kv MAIN CIRCUIT BREAKER 1500 kva 25 kv - 208Y/120V 1600 A, SECONDARY CIRCUIT BREAKER 3000 A, SECONDARY CIRCUIT BREAKER 1600A, 208Y/120V BCH x A x A 3000A, 208Y/120V BCH 400 A... (10 TOTAL) 400 A COMMON AREA LOADS RESIDENTIAL UNIT LOADS (METER CENTRES) 400A, 208Y/120V 42 CCT PANELBOARD 40A, 208V BRANCH CIRCUITS (136 TOTAL) consultant drawing title designed scale date 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project MID RISE - OUTSIDE CITY CENTRE 100% L2 ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS drawn checked approved CF CF RB RB project no. drawing no. N/A 2017 AN E022 rev. 1

152 BC HYDRO KV SERVICE MAIN ELECTRICAL ROOM L.B.S. 25 kv MAIN CIRCUIT BREAKER 750 kva 25 kv - 208Y/120V 2000 A, SECONDARY CIRCUIT BREAKER BCH 2000A, 208Y/120V x A x A 400 A 400 A 400 A 400 A BCH COMMON AREA LOADS RESIDENTIAL UNIT LOADS (METER CENTRES) 400A, 208Y/120V 42 CCT PANELBOARD 4 STALLS PER 40A, 208V BRANCH CIRCUIT (136 STALLS TOTAL) consultant drawing title designed scale date 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project MID RISE - OUTSIDE CITY CENTRE 100% L2, 4-SHARED ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS drawn checked approved CF CF RB RB project no. drawing no. N/A 2017 AN E023 rev. 1

153 BC HYDRO KV SERVICE MAIN ELECTRICAL ROOM L.B.S. 25 kv MAIN CIRCUIT BREAKER 750 kva 25 kv - 208Y/120V 2000 A, SECONDARY CIRCUIT BREAKER BCH 2000A, 208Y/120V x A x A 400 A 400 A BCH COMMON AREA LOADS RESIDENTIAL UNIT LOADS (METER CENTRES) 400A, 208Y/120V 42 CCT PANELBOARD WITH 80 A, 2p, CIRCUIT BREAKERS 400A, 208Y/120V, PANELBOARD 80 A 2p 80 A 2p 80 A 2p 80 A 2p 80 A 2p 80 A 2p 80 A, 2p, TRUNK CIRCUIT 40A, 208V OUTLET 18 STALLS PER TRUNK (136 STALLS TOTAL) 40 A 2p... (18 TOTAL) 40 A 2p consultant drawing title designed scale date 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project MID RISE - OUTSIDE CITY CENTRE 100% L2, TRUNK STYLE ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS drawn checked approved CF CF RB RB project no. drawing no. N/A 2017 AN E024 rev. 1

154 BC HYDRO KV SERVICE 225 kva 25 kv - 208Y/120V BC HYDRO PADMOUNT MAIN ELECTRICAL ROOM 800A MAIN CIRCUIT BREAKER 800A, 208Y/120V METER CENTERS 100 A A 200A BCH BCH BCH 100A, 120/208V, 2P, 3W PANELBOARDS (WITHIN RES UNIT) 18 RESIDENTIAL UNITS COMMON AREA LOADS consultant drawing title designed scale date 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project TOWNHOUSE BASE DESIGN ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS drawn checked approved CF CF RB RB project no. drawing no. N/A 2017 AN E030 rev. 1

155 BC HYDRO KV SERVICE 300 kva 25 kv - 208Y/120V BC HYDRO PADMOUNT MAIN ELECTRICAL ROOM 800A MAIN CIRCUIT BREAKER 800A, 208Y/120V METER CENTERS 100 A... (18 TOTAL) 100 A 200A BCH BCH BCH 100A, 120/208V, 2P, 3W PANELBOARDS (WITHIN RES UNIT) COMMON AREA LOADS 20A, 120V BRANCH CIRCUITS (2 PER UNIT, 36 TOTAL) consultant drawing title designed scale date 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project TOWNHOUSE 100% L1 ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS drawn checked approved CF CF RB RB project no. drawing no. N/A 2017 AN E031 rev. 1

156 BC HYDRO KV SERVICE 500 kva 25 kv - 208Y/120V BC HYDRO PADMOUNT MAIN ELECTRICAL ROOM 1200A MAIN CIRCUIT BREAKER 1200A, 208Y/120V METER CENTERS 200 A... (18 TOTAL) 200 A 200A BCH BCH BCH 225A, 120/208V, 2P, 3W PANELBOARDS (WITHIN RES UNIT) COMMON AREA LOADS 40A, 208V BRANCH CIRCUITS (2 PER UNIT, 36 TOTAL) consultant drawing title designed scale date 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project TOWNHOUSE 100% L2 ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS drawn checked approved CF CF RB RB project no. drawing no. N/A 2017 AN E032 rev. 1

157 BC HYDRO KV SERVICE 300 kva 25 kv - 208Y/120V BC HYDRO PADMOUNT MAIN ELECTRICAL ROOM 800A MAIN CIRCUIT BREAKER 800A, 208Y/120V METER CENTERS 125 A... (18 TOTAL) 125 A 200 A BCH BCH BCH 125A, 120/208V, 2P, 3W PANELBOARDS (WITHIN RES UNIT) COMMON AREA LOADS 2 STALLS PER 40A, 208V BRANCH CIRCUIT (2 PER UNIT, 36 TOTAL) consultant drawing title designed scale date 1330 Granville St. Vancouver, BC, V6Z 1M7 P : F : W : AESengr.com CALGARY VANCOUVER VICTORIA Designing A Better Tomorrow project TOWNHOUSE 100% L2, 2-SHARED ELECTRIC VEHICLE CHARGING INFRASTRUCTURE REQUIREMENTS drawn checked approved CF CF RB RB project no. drawing no. N/A 2017 AN E033 rev. 1

158 Electric Vehicle Charging Requirements Analysis Appendix APPENDIX E Metering D Data AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

159 Electric Vehicle Charging Requirements Analysis Appendix E Page 1 FIGURE 1 ARCHETYPE 1 (BLDG A) TENANTS CURRENT METERING AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

160 Electric Vehicle Charging Requirements Analysis Appendix E Page 2 FIGURE 2 ARCHETYPE 1 (BLDG A) TENANTS VOLTAGE METERING AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

161 Electric Vehicle Charging Requirements Analysis Appendix E Page 3 FIGURE 3 ARCHETYPE 1 (BLDG A) TENANTS POWER METERING AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

162 Electric Vehicle Charging Requirements Analysis Appendix E Page 4 FIGURE 4 ARCHETYPE 1 (BLDG A) HOUSE CURRENT METERING AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

163 Electric Vehicle Charging Requirements Analysis Appendix E Page 5 FIGURE 5 ARCHETYPE 1 (BLDG A) TENANTS POWER DEMAND FOR TYPICAL DAY AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

164 Electric Vehicle Charging Requirements Analysis Appendix E Page 6 FIGURE 6 ARCHETYPE 1 (BLDG A) HOUSE POWER DEMAND FOR TYPICAL DAY AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

165 Electric Vehicle Charging Requirements Analysis Appendix E Page 7 FIGURE 7 ARCHETYPE 1 (BLDG A) BUILDING POWER DEMAND FOR TYPICAL DAY AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

166 Electric Vehicle Charging Requirements Analysis Appendix E Page 8 FIGURE 8 ARCHETYPE 1 (BLDG B) TENANTS CURRENT METERING AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

167 Electric Vehicle Charging Requirements Analysis Appendix E Page 9 FIGURE 9 ARCHETYPE 1 (BLDG B) TENANTS POWER METERING AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

168 Electric Vehicle Charging Requirements Analysis Appendix E Page 10 FIGURE 10 ARCHETYPE 1 (BLDG B) HOUSE POWER DEMAND FOR TYPICAL DAY AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

169 Electric Vehicle Charging Requirements Analysis Appendix E Page 11 FIGURE 11 ARCHETYPE 1 (BLDG B) HOUSE POWER DEMAND FOR TYPICAL DAY AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

170 Electric Vehicle Charging Requirements Analysis Appendix F APPENDIX Proposed D CEC Changes AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

171

172

173

174 Electric Vehicle Charging Requirements Analysis Appendix E Page 1 Proposal to amend the Canadian Electrical Code, Part I Section 8 (Proposal for the 2 nd round of deliberations) Subject No Chair: A. Tsisserev Updated: anuary 10, 2017 Title: Demand loads for electric vehicle supply equipment where energy management systems are installed. Submitted on December 11, 2016 by: D. Chandler, Vancouver Electric Vehicle Association (DonChandler@shaw.ca / ) Primary Intent: 2,4 (1) Improve safety (2) Address new technology (3) Clarify existing wording (4) Correlate with product standard requirements (5) Correlate with the NEC, NBC or other relevant standard such as C22.2 No. 1, C282, or Z32, etc. Requests: (A) Add new definitions to Rule Rule Special terminology (see Appendix B) Control of electric vehicle supply equipment loads the predetermined process of connecting, disconnecting, increasing, or reducing electric power to electric vehicle supply equipment loads. Electric Vehicle Energy Management System a means of controlling electric vehicle supply equipment loads comprised of any of the following: a monitor(s), communications equipment, a controller(s), a timer(s) and other applicable device(s). (B) Add New Subrule 8-106(11) Use of demand factors (see Appendix B) (11) Where electric vehicle supply equipment loads are controlled by an Electric Vehicle Energy Management System, the demand load for the electric vehicle supply equipment shall be equal to the maximum load allowed by the Electric Vehicle Energy Management System. AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

175 Electric Vehicle Charging Requirements Analysis Appendix E Page 2 (12) For the purposes of Rules 8-200(1)(a)(vi), 8-202(3)(d), 8-204(1)(d), 8-206(1)(d), 8-208(1)(d) and 8-210(b), where an Electric Vehicle Energy Management System described in 8-106(11), monitors the consumer's service and/or feeders and controls the electric vehicle supply equipment loads in accordance with Rule 8-500, the demand load for the electric vehicle supply equipment is not required to be considered in determination of the calculated load. (C) Modify Item 8-200(1)(a)(vi) Single dwellings (see Appendices B and I) (1) The minimum ampacity of service or feeder conductors supplying a single dwelling shall be based on the greater of Item (a) or (b): (a) (vi) except as permitted by Rule 8-106(12) any electric vehicle supply equipment loads with a demand factor of 100%; plus (D) Modify Item 8-202(3)(d) Apartment and similar buildings (see Appendix B) (3) The minimum ampacity of service or feeder conductors from a main service supplying two or more dwelling units shall be based on the calculated load obtained from Subrule (1)(a) and the following: (d) except as permitted by Rule 8-106(12), any electric vehicle supply equipment loads not located in dwelling units shall be added with a demand factor as specified in Table XY; and (E) Modify Schools (1) The minimum ampacity of service or feeder conductors shall be based on the following: (a) (a) a basic load of 50 W/m 2 of classroom area; plus (b) (b) 10 W/m 2 of the remaining area of the building based on the outside dimensions; plus (c) (c) electric space-heating, air-conditioning, and total loads of other permanently connected equipment based on the rating of the equipment installed; plus (d) except as permitted by Rule 8-106(12), any electric vehicle supply equipment loads with a demand factor as specified in Table XY; plus (e) cord-connected equipment intended for connection to receptacles rated more than 125 V or 20 A based on (i) 80% of the rating of the receptacle; or (ii) the rating of the equipment intended for connection to the receptacle. AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

176 Electric Vehicle Charging Requirements Analysis Appendix E Page 3 (F) Modify Hospitals (1) The minimum ampacity of service or feeder conductors shall be based on the following: (a) a basic load of 20 W/m 2 of the area of the building based on the outside dimensions; plus (b) 100 W/m 2 for high-intensity areas such as operating rooms; plus (c) electric space-heating, air-conditioning, and total loads of other permanently connected equipment based on the rating of the equipment installed; plus (d) except as permitted by Rule 8-106(12), any electric vehicle supply equipment loads with a demand factor as specified in Table XY; plus (e) cord-connected equipment intended for connection to receptacles rated more than 125 V or 20 A based on (i) 80% of the rating of the receptacle; or (ii) the rating of the equipment intended for connection to the receptacle. (G) Modify Hotels, motels, dormitories, and buildings of similar occupancy (see Appendix B) (1) The minimum ampacity of service or feeder conductors shall be based on the following: (a) a basic load of 20 W/m 2 of the area of the building, based on the outside dimensions; plus (b) lighting loads for special areas such as ballrooms, based on the rating of the equipment installed; plus (c) electric space-heating, air-conditioning, and total loads of other permanently connected equipment based on the rating of the equipment installed; plus (d) except as permitted by Rule 8-106(12), any electric vehicle supply equipment loads with a demand factor as specified in Table XY; plus (e) cord-connected equipment intended for connection to receptacles rated more than 125 V or 20 A based on (i) 80% of the rating of the receptacle; or (ii) the rating of the equipment intended for connection to the receptacle. (H) Modify Item Other types of occupancy The minimum ampacity of service or feeder conductors for the types of occupancies listed in Table 14 shall be based on (a) a basic load in watts per square metre as required by Table 14 for the area of the occupancy served based on the outside dimensions of the occupancy, with application of demand factors as indicated in Table 14; plus (b) special loads such as electric space-heating, air-conditioning, motor loads, show window lighting, stage lighting, etc., based on the rating of the equipment installed with demand factors permitted by this Code. (c) except as permitted by Rule 8-106(12), any electric vehicle supply equipment loads with a demand factor as specified in Table XY. AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

177 Electric Vehicle Charging Requirements Analysis Appendix E Page 4 (I) Add new Subsection for energy management systems Electric vehicle energy management systems Electric Vehicle Energy Management Systems (1) Electric vehicle energy management systems shall be permitted to monitor electrical loads and/or to control electric vehicle supply equipment loads, (2) An electric vehicle energy management system shall not cause the load of a branch circuit, feeder, or service to exceed requirements of Rules 8-104(5) or 8-104(6). (3) Where an electric vehicle energy management system is employed to control electrical power through the use of a remote means, a directory identifying the controlled electrical equipment shall be posted on the enclosure of the controlled electrical equipment. () Add Appendix B Note for Subrule 8-106(11) Rule 8-106(11) It is intended by this Rule that the loads of the electric vehicle supply equipment which are controlled by an electric vehicle energy management system, should be considered to have a demand within the maximum limits allowed by the electric vehicle energy management system. The electric vehicle energy management system is provided with a maximum load rating which will determine the circuit, feeder and service loadings. (K) Add Appendix B Note for Rule 8-510(3) Rule 8-510(3) The use of the term remote is intended to convey that a controller can be operated via another means or location through communications without a direct operator interface with the controlled device. AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

178 Electric Vehicle Charging Requirements Analysis Appendix E Page 5 (L) Add new Table XY Number of automobile spaces or stalls 1 to 4 5 to 8 9 to to and over Table XY Electric vehicle supply equipment demand factors (See Rules and 8-210) Maximum load per stall (Watts) or more or more or more or more or more or more Demand factor (%) (M) Request that Section 86 subcommittee initiates the subject to revise Rule (2) as follows (revised wording is shown on the yellow background in the bold underlined text). (2) Notwithstanding Subrule (1), electric vehicle supply equipment shall be permitted to be supplied from a branch circuit supplying another load(s), provided that an Electric-Vehicle Energy Management System is installed in accordance with Subrule 8-106(11) or Subrule (12). control equipment prevents simultaneous operation of the electric vehicle supply equipment with other circuit loads such that the calculated demand of the circuit is not exceeded. AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

179 Electric Vehicle Charging Requirements Analysis Appendix G APPENDIX Performance D Analysis AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

180 Electric Vehicle Charging Requirements Analysis Appendix G Page PERFORMANCE ANALYSIS 1.1 GENERAL Performance analysis of the various charging system configurations is based on the ability of the charging system to transfer power from the building to the EV s. POWER IN POWER TRANSFER POWER OUT BUILDING CAPACITY CHARGING SYSTEM DRIVING DISTANCE FIGURE F1: POWER FLOW Power in: Power from the building electrical system. Power transfer: Power transferred by the charging system. Power out: Battery charge required by the EV s. 1.2 POWER IN The power available from the building for each of the archetypes is as follows. ARCHETYPE BUILDING CAPACITY (kw) PEAK DEMAND (kw) CAPACITY FOR CHARGING (kw) CAPACITY FOR CHARGING (kwh/day) High Rise City Centre ,680 Mid Rise City Centre ,960 Mid Rise Outside City Centre ,240 Townhouse Outside City Centre TABLE F1: POWER IN AES Engineering Ltd Granville Street, Vancouver, BC, Canada V6Z 1M7 P F

Bulletin Engineering Department 6911 No. 3 Road, Richmond, BC V6Y 2C1

Bulletin Engineering Department 6911 No. 3 Road, Richmond, BC V6Y 2C1 Bulletin Engineering Department 6911 No. 3 Road, Richmond, BC V6Y 2C1 www.richmond.ca Electric Vehicle Charging Infrastructure Requirements Zoning Bylaw 8500, Section 7.15 No.: ENGINEERING-05 Date: 2018-03-16

More information

Burnaby Electric Vehicle (EV) Charging Infrastructure Technical Bulletin Requirements and Guidelines for EV Charging Bylaw

Burnaby Electric Vehicle (EV) Charging Infrastructure Technical Bulletin Requirements and Guidelines for EV Charging Bylaw Burnaby Electric Vehicle (EV) Charging Infrastructure Technical Bulletin Requirements and Guidelines for EV Charging Bylaw Please refer to the website for latest version of this document: www.burnaby.ca/ev

More information

7:50 am The Municipal Perspective D. Miller, City of Victoria & M. Baynham, District of Saanich

7:50 am The Municipal Perspective D. Miller, City of Victoria & M. Baynham, District of Saanich Agenda Timeline Topic 7:30 am Welcome Kathy Hogan, UDI Capital Region 7:40 am EVs 101 N. Elliott, CRD Climate Action Program 7:50 am The Municipal Perspective D. Miller, City of Victoria & M. Baynham,

More information

Proposed Zoning Bylaw Text Amendments Pertaining to Electric Vehicle Charging Infrastructure Requirements (Bylaw No. 4905,2018)

Proposed Zoning Bylaw Text Amendments Pertaining to Electric Vehicle Charging Infrastructure Requirements (Bylaw No. 4905,2018) CoQuitlam For Council September 10, 2018, Our file: 08-3360-20/18 118298 RZ/l Doc#: 3032571.VI To: From; Subject: For: City Manager Director Development Services Proposed Zoning Bylaw Text Amendments Pertaining

More information

Date: December 12, 2016 From: John Irving, P.Eng. MPA File: /2016- Director, Engineering Vol 01

Date: December 12, 2016 From: John Irving, P.Eng. MPA File: /2016- Director, Engineering Vol 01 City of Richmond Report to Committee To: Planning Committee Date: December 12, 2016 From: John Irving, P.Eng. MPA File: 10-6125-07-02/2016- Director, Engineering Vol 01.. Re: Electric Vehicle Charging

More information

Public and Fleet Electric Vehicle Charging Infrastructure Strategy

Public and Fleet Electric Vehicle Charging Infrastructure Strategy CoQuitlam For Council Our File: 11-5210-01/000/2018-1 Doc#: 3187569.V3 To: From: Subject: For: City Manager General Manager, Engineering and Public Works Public and Fleet Electric Vehicle Charging Infrastructure

More information

Electric Vehicle Appendix Notes

Electric Vehicle Appendix Notes Electric Vehicle Appendix Notes Building Code Requirements Part 3 3.1.21. Electric Vehicle Charging 3.1.21.1. Electric Vehicle Charging Systems (1) Except as provided in Sentences (2.1) and (3), where

More information

RE: Regulatory Proposal under the Condominium Act, 1998 (17-MGCS021)

RE: Regulatory Proposal under the Condominium Act, 1998 (17-MGCS021) Ministry of Government & Consumer Services January 2 nd, 2018 56 Wellesley St. W, 6 th Floor Toronto, ON M7A 1C1 RE: Regulatory Proposal under the Condominium Act, 1998 (17-MGCS021) This letter is submitted

More information

On June 11, 2012, the Park Board approved the installation of three electric vehicle charging stations along Beach Avenue.

On June 11, 2012, the Park Board approved the installation of three electric vehicle charging stations along Beach Avenue. January 8, 2017 TO: Park Board Chair and Commissioners FROM: General Manager Vancouver Board of Parks and Recreation SUBJECT: Electric Vehicle Charging Stations New Park Board Locations RECOMMENDATION

More information

Electric Vehicle Charging Station Installation and Eco-Pass Updates. Report Prepared by: A. Rolston, Parking Operations Coordinator

Electric Vehicle Charging Station Installation and Eco-Pass Updates. Report Prepared by: A. Rolston, Parking Operations Coordinator Report to Council Date: File: 1862-01 To: From: Subject: City Manager D. Duncan, Manager, Parking Services Electric Vehicle Charging Station Installation and Eco-Pass Updates Report Prepared by: A. Rolston,

More information

3. That Richmond Official Community Plan Bylaw 9000, Amendment Bylaw No. 9520, having been considered in conjunction with:

3. That Richmond Official Community Plan Bylaw 9000, Amendment Bylaw No. 9520, having been considered in conjunction with: City of Richmond Report to Committee To: From: Re: Public Works and Transportation Committee Date: October 15, 2017 John Irving, P.Eng. MPA File: 10-6125-07-02/2017- Director, Engineering Vol 01 Electric

More information

District of Maple Ridge

District of Maple Ridge District of Maple Ridge TO: His Worship Mayor Ernie Daykin MEETING DATE: March 17, 2014 and Members of Council FILE NO: 2013-096-RZ FROM: Chief Administrative Officer MEETING: COW SUBJECT: Tandem Parking

More information

Draft Marrickville Car Share Policy 2014

Draft Marrickville Car Share Policy 2014 Draft Marrickville Car Share Policy 2014 1. Background 1.1. Marrickville Council has supported car sharing in the LGA since 2007 as part of a holistic approach to encouraging more sustainable modes of

More information

Technical Support for Electric Vehicle Charging Requirements in the Building Code that are in effect January 1, 2018

Technical Support for Electric Vehicle Charging Requirements in the Building Code that are in effect January 1, 2018 Technical Support for Electric Vehicle Charging Requirements in the Building Code that are in effect January 1, 2018 Houses Questions and Answers Provided on December 19, 2017 This document is intended

More information

Future Funding The sustainability of current transport revenue tools model and report November 2014

Future Funding The sustainability of current transport revenue tools model and report November 2014 Future Funding The sustainability of current transport revenue tools model and report November 214 Ensuring our transport system helps New Zealand thrive Future Funding: The sustainability of current transport

More information

Title 24: Building Codes for Plug-in Electric Vehicles September 22, 2015 Webinar Questions

Title 24: Building Codes for Plug-in Electric Vehicles September 22, 2015 Webinar Questions Title 24: Building Codes for Plug-in Electric Vehicles September 22, 2015 Webinar Questions 1. Enrique M. Rodriquez, what incentives and barriers are there to providing overhead structures supporting both

More information

Submission to the IESO re: RDGI Fund Virtual Net Metering Investigation Topic

Submission to the IESO re: RDGI Fund Virtual Net Metering Investigation Topic 1. Introduction The Canadian Solar Industries Association (CanSIA) is a national trade association that represents the solar energy industry throughout Canada. CanSIA s vision is for solar energy to be

More information

EVSE Load Balancing VS Load Shedding 1: Largest number of 30 Amps EVSEs that can be fed as per the code from the 600 volts feeder

EVSE Load Balancing VS Load Shedding 1: Largest number of 30 Amps EVSEs that can be fed as per the code from the 600 volts feeder EVSE Load Balancing VS Load Shedding 1: Largest number of 30 Amps EVSEs that can be fed as per the code from the 1600A @ 600 volts feeder The schematics shows that the 1600A feeder is split in 7 branches

More information

Joe Butler owns both full electric and hybrid electric vehicles since His fully electric EV became their primary vehicle in 2016.

Joe Butler owns both full electric and hybrid electric vehicles since His fully electric EV became their primary vehicle in 2016. Rate Mitigation Review Public Utilities Board P.O. Box 21040 St. John s NL A1A 5B2 Submission for Rate Mitigation Review Prepared by Drive Electric NL Thursday, January 17, 2019 Introduction Drive Electric

More information

Driving to Net Zero. Deploying EV Charging Infrastructure: What Site Hosts Need to Know. County of Santa Clara Office of Sustainability

Driving to Net Zero. Deploying EV Charging Infrastructure: What Site Hosts Need to Know. County of Santa Clara Office of Sustainability Deploying EV Charging Infrastructure: What Site Hosts Need to Know Driving to Net Zero Submitted to: Santa Clara County Submitted by: ICF FUNDED THROUGH A GRANT AWARDED BY THE CALIFORNIA STRATEGIC GROWTH

More information

Managing Electric Vehicle Supply Equipment (EVSE) Installations

Managing Electric Vehicle Supply Equipment (EVSE) Installations Managing Electric Vehicle Supply Equipment (EVSE) Installations Introduction to Electric Vehicle EVSE Electric vehicles create a need to build an infrastructure that will supply the added load of charging.

More information

1. Thank you for the opportunity to comment on the Low Emissions Economy Issues Paper ( Issues Paper ).

1. Thank you for the opportunity to comment on the Low Emissions Economy Issues Paper ( Issues Paper ). 20 September 2017 Low-emissions economy inquiry New Zealand Productivity Commission PO Box 8036 The Terrace Wellington 6143 info@productivity.govt.nz Dear Commission members, Re: Orion submission on Low

More information

Technical Support for Electric Vehicle Charging Requirements in the Building Code that are in effect January 1, 2018

Technical Support for Electric Vehicle Charging Requirements in the Building Code that are in effect January 1, 2018 Technical Support for Electric Vehicle Charging Requirements in the Building Code that are in effect January 1, 2018 Houses Questions and Answers Provided on December 19, 2017 This document is intended

More information

ACT Canada Sustainable Mobility Summit Planning Innovations in Practice Session 6B Tuesday November 23, 2010

ACT Canada Sustainable Mobility Summit Planning Innovations in Practice Session 6B Tuesday November 23, 2010 ACT Canada Sustainable Mobility Summit Planning Innovations in Practice Session 6B Tuesday November 23, 2010 Presentation Outline Context t of Mississauga i City Centre Implementing Paid Parking and TDM

More information

Letter Supporting Continuation of Clean Energy Vehicles Rebate

Letter Supporting Continuation of Clean Energy Vehicles Rebate City of Richmond Report to Committee To: From: Re: Public Works and Transportation Committee John Irving, P.Eng. MPA Director, Engineering Date: June 2, 2014 File: Letter Supporting Continuation of Clean

More information

PUBLIC Law, Chapter 539 LD 1535, item 1, 124th Maine State Legislature An Act To Create a Smart Grid Policy in the State

PUBLIC Law, Chapter 539 LD 1535, item 1, 124th Maine State Legislature An Act To Create a Smart Grid Policy in the State PLEASE NOTE: Legislative Information cannot perform research, provide legal advice, or interpret Maine law. For legal assistance, please contact a qualified attorney. Emergency preamble. Whereas, acts

More information

Residential Electric Vehicle Charging: A Guide for Local Governments

Residential Electric Vehicle Charging: A Guide for Local Governments Residential Electric Vehicle Charging: A Guide for Local Governments A publication of the City of Richmond with funding support from BC Hydro. This report was prepared with generous support of the BC Hydro

More information

S T A F F R E P O R T

S T A F F R E P O R T S T A F F R E P O R T DATE: December 11, 2012 TO: FROM: Honorable Mayor and City Council Superintendent, Brandon Graham SUBJECT: Net Metering Policy Section A 2. b. (Change the maximum installation capacity

More information

KANSAS CITY POWER AND LIGHT COMPANY P.S.C. MO. No. 7 Fourth Revised Sheet No. 39 Canceling P.S.C. MO. No. 7 Third Revised Sheet No.

KANSAS CITY POWER AND LIGHT COMPANY P.S.C. MO. No. 7 Fourth Revised Sheet No. 39 Canceling P.S.C. MO. No. 7 Third Revised Sheet No. P.S.C. MO. No. 7 Fourth Revised Sheet No. 39 Canceling P.S.C. MO. No. 7 Third Revised Sheet No. 39 PURPOSE: The purpose of the Solar Subscription Pilot Rider (Program) is to provide a limited number of

More information

Rate Schedules. Effective 1/1/2019

Rate Schedules. Effective 1/1/2019 Rate Schedules 2019 Effective 1/1/2019 SUMMARY OF RATE SCHEDULES REVISIONS FOR RATES EFFECTIVE JANUARY 1, 2019 (1) Rate component changes for Residential and Heating Service rate schedules. (2) General

More information

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1 Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide Version 1.1 October 21, 2016 1 Table of Contents: A. Application Processing Pages 3-4 B. Operational Modes Associated

More information

BC Hydro writes in compliance with Exhibit A-4 to provide its Final Submission in respect of the Application (Exhibit B-1).

BC Hydro writes in compliance with Exhibit A-4 to provide its Final Submission in respect of the Application (Exhibit B-1). Ken Duke Solicitor & Counsel Phone: 604-623-3623 Fax: 604-623-3606 bchydroregulatorygroup@bchydro.com April 30, 2014 Sixth Floor 900 Howe Street Vancouver, BC V6Z 2N3 Dear Ms. Hamilton: RE: (BCUC) British

More information

REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT COMPRESSED NATURAL GAS TRANSIT FLEET UPDATE

REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT COMPRESSED NATURAL GAS TRANSIT FLEET UPDATE September 7, 2016 REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT ON COMPRESSED NATURAL GAS TRANSIT FLEET UPDATE PURPOSE To update Council on Kamloops

More information

A Guide to the medium General Service. BC Hydro Last Updated: February 24, 2012

A Guide to the medium General Service. BC Hydro Last Updated: February 24, 2012 A Guide to the medium General Service Conservation Rate BC Hydro Last Updated: February 24, 2012 Executive summary The way Medium General Service (MGS) accounts pay for electricity is changing. MGS is

More information

SDG&E Electric Vehicle activities

SDG&E Electric Vehicle activities SDG&E Electric Vehicle activities Managing load and storage while maximizing customer value CAISO V2G Workshop Tuesday, February 5, 2013 Matt Zerega mzerega@semprautilities.com 2011San Diego Gas & Electric

More information

TECHNICAL WHITE PAPER

TECHNICAL WHITE PAPER TECHNICAL WHITE PAPER Chargers Integral to PHEV Success 1. ABSTRACT... 2 2. PLUG-IN HYBRIDS DEFINED... 2 3. PLUG-IN HYBRIDS GAIN MOMENTUM... 2 4. EARLY DELTA-Q SUPPORT FOR PHEV DEVELOPMENT... 2 5. PLUG-IN

More information

Appendix C. Parking Strategies

Appendix C. Parking Strategies Appendix C. Parking Strategies Bremerton Parking Study Introduction & Project Scope Community concerns regarding parking impacts in Downtown Bremerton and the surrounding residential areas have existed

More information

Comhairle Cathrach Chorcaí Cork City Council

Comhairle Cathrach Chorcaí Cork City Council Transportation Division City Hall Cork Response to the Consultation Paper on the ESBN Electric Vehicle Pilot & Associated Assets Reference CER/16/286 Introduction welcomes the opportunity to respond to

More information

Net Metering Policy Framework. July 2015

Net Metering Policy Framework. July 2015 Net Metering Policy Framework July 2015 Table of Contents 1.0 BACKGROUND... 2 2.0 POLICY OBJECTIVE... 2 3.1 Eligibility... 3 3.1.1 Renewable Generation... 3 3.1.2 Customer Class... 3 3.1.3 Size of Generation...

More information

Technical Support for Electric Vehicle Charging Requirements in the Building Code that are in effect January 1, 2018

Technical Support for Electric Vehicle Charging Requirements in the Building Code that are in effect January 1, 2018 Technical Support for Electric Vehicle Charging Requirements in the Building Code that are in effect January 1, 2018 Non-residential Buildings Questions and Answers Provided on December 19, 2017 This document

More information

Electric Vehicle Charge Ready Program

Electric Vehicle Charge Ready Program Electric Vehicle Charge Ready Program September 20, 2015 1 Agenda About SCE The Charge Ready Initiative Depreciation Proposals of The Charge Ready Initiative Challenges Outcomes September 20, 2015 2 About

More information

Innovations in Electric Vehicle Charging

Innovations in Electric Vehicle Charging 1 Innovations in Electric Vehicle Charging BCIT EV Infrastructure Project Knowledge Dissemination Workshop February 22, 2018 We acknowledge and thank the Coast Salish Nations of Squamish, Musqueam, and

More information

LIIKENNEVIRTA LTD GENERAL TERMS AND CONDITIONS FOR THE CHARGING SERVICE

LIIKENNEVIRTA LTD GENERAL TERMS AND CONDITIONS FOR THE CHARGING SERVICE 1 (7) LIIKENNEVIRTA LTD GENERAL TERMS AND CONDITIONS FOR THE CHARGING SERVICE 1 Scope of application and definitions 1.1 These General Terms and Conditions pertaining to the delivery of the Charging Service

More information

CITY OF MINNEAPOLIS GREEN FLEET POLICY

CITY OF MINNEAPOLIS GREEN FLEET POLICY CITY OF MINNEAPOLIS GREEN FLEET POLICY TABLE OF CONTENTS I. Introduction Purpose & Objectives Oversight: The Green Fleet Team II. Establishing a Baseline for Inventory III. Implementation Strategies Optimize

More information

WHEREAS, LADWP seeks to enable the continued growth of customer generation, including solar-powered generation; and

WHEREAS, LADWP seeks to enable the continued growth of customer generation, including solar-powered generation; and RESOLUTION NO. WHEREAS, the City of Los Angeles (City) Department of Water and Power (LADWP) will be further accelerating its efforts to replace its aging Power System infrastructure, much of which was

More information

CPUC Transportation Electrification Activities

CPUC Transportation Electrification Activities CPUC Transportation Electrification Activities 1 Committee on the Assessment of Technologies for Improving Fuel Economy of Light-Duty Vehicles January 24, 2019 The CPUC regulates the role IOUs serve in

More information

Submission to Select Committee on Electric Vehicles - inquiry into the use and manufacture of electric vehicles in Australia

Submission to Select Committee on Electric Vehicles - inquiry into the use and manufacture of electric vehicles in Australia 31 July 2018 Senator Tim Storer Department of the Senate PO Box 6100 Parliament House Canberra ACT 2600 Dear Senator Storer, RE: Submission to Select Committee on Electric Vehicles - inquiry into the use

More information

PROMOTING THE UPTAKE OF ELECTRIC AND OTHER LOW EMISSION VEHICLES

PROMOTING THE UPTAKE OF ELECTRIC AND OTHER LOW EMISSION VEHICLES Chair Cabinet Economic Growth and Infrastructure Committee Office of the Minister of Transport Office of the Minister of Energy and Resources PROMOTING THE UPTAKE OF ELECTRIC AND OTHER LOW EMISSION VEHICLES

More information

TOWN COUNCIL ACTION REPORT. May 2, 2013

TOWN COUNCIL ACTION REPORT. May 2, 2013 TOWN COUNCIL ACTION REPORT May 2, 2013 Resolution Authorizing the Execution of a Letter of Intent with Tesla Motors, Inc. for the Installation of Electric Vehicle Charging Stations in Uptown Station PREPARED

More information

Driving to Net Zero. County of Santa Clara Office of Sustainability. Submitted to: Santa Clara County Submitted by: ICF

Driving to Net Zero. County of Santa Clara Office of Sustainability. Submitted to: Santa Clara County Submitted by: ICF Driving to Net Zero Submitted to: Santa Clara County Submitted by: ICF County of Santa Clara Office of Sustainability Funded through a grant awarded by the California Strategic Growth Council MARCH 9,

More information

EVSE Permitting and Inspection Best Practices

EVSE Permitting and Inspection Best Practices EVSE Permitting and Inspection Best Practices The Permitting and Inspection Process for Plug-in Electric Vehicle Charging EVITP EV Community Readiness Seminar [Photo Courtesy: General Electric] This report

More information

Funding Scenario Descriptions & Performance

Funding Scenario Descriptions & Performance Funding Scenario Descriptions & Performance These scenarios were developed based on direction set by the Task Force at previous meetings. They represent approaches for funding to further Task Force discussion

More information

Section 2. Definitions

Section 2. Definitions Section 2 Definitions Words used in this By-law shall have the meaning assigned to them by sections 2, 9 and 10.5 of the Zoning and Development By-law unless otherwise stated and except as provided below.

More information

ENERGY STRATEGY FOR YUKON. Net Metering Policy DRAFT FOR CONSULTATION

ENERGY STRATEGY FOR YUKON. Net Metering Policy DRAFT FOR CONSULTATION ENERGY STRATEGY FOR YUKON Net Metering Policy DRAFT FOR CONSULTATION February 2011 Page 1 of 4 BACKGROUND The Yukon government released the Energy Strategy for Yukon in January 2009. The Energy Strategy

More information

TERMS AND CONDITIONS

TERMS AND CONDITIONS XXV. NET METERING A. Applicability and Availability 1. The terms Net Metering Service, Demand Charge-based Time-of- Use Tariff, Net Metering Customer, Customer, Time-of-Use Customer, Time-of-Use Tier,

More information

Climate Change. November 29, 2018 Growth Management Policy Board

Climate Change. November 29, 2018 Growth Management Policy Board Climate Change November 29, 2018 Growth Management Policy Board VISION 2050 and Climate Change 1. Climate Background Paper: Background information Regional inventory Emission reduction efforts Potential

More information

charging station installation in multi-family building

charging station installation in multi-family building charging station installation in multi-family building Summary of charging solutions to be implemented in apartments and condos to ensure that all co-owners have the availability of an electric vehicle

More information

Report Date: January 24, 2018 Contact: Ian Neville Contact No.: RTS No.: VanRIMS No.: Meeting Date: March 14, 2018

Report Date: January 24, 2018 Contact: Ian Neville Contact No.: RTS No.: VanRIMS No.: Meeting Date: March 14, 2018 POLICY REPORT Report Date: January 24, 2018 Contact: Ian Neville Contact No.: 604.673.8246 RTS No.: 12345 VanRIMS No.: 08-2000-20 Meeting Date: March 14, 2018 TO: FROM: SUBJECT: Standing Committee on City

More information

THE PUBLIC SERVICE COMMISSION OF MARYLAND

THE PUBLIC SERVICE COMMISSION OF MARYLAND THE PUBLIC SERVICE COMMISSION OF MARYLAND Report on the Status of Net Energy Metering In the State of Maryland Prepared for the General Assembly of Maryland Pursuant to 7-306(i) of the Public Utilities

More information

Mississauga Moves: A City in Transformation icity Symposium Hamish Campbell

Mississauga Moves: A City in Transformation icity Symposium Hamish Campbell Mississauga Moves: A City in Transformation 2018 icity Symposium Hamish Campbell Outline Mississauga: A City in Transformation Planning for a Transformative Future Transportation Master Plan Parking Master

More information

The Council of the City of Palo Alto does ORDAIN as follows:

The Council of the City of Palo Alto does ORDAIN as follows: Palo Ordinance No. 5263 Ordinance ofthe Council ofthe Ci~y of Palo Alto Adopting Section 16.14.380 of the Alto Municipal Code to Adopt Local Amendments to the California Green Building Standards Code and

More information

PG&E s Commercial Electricity Vehicle Rate

PG&E s Commercial Electricity Vehicle Rate PG&E s Commercial Electricity Vehicle Rate Webinar November 20, 2018 Michael Pimentel California Transit Association Cal Silcox Pacific Gas & Electric How to Ask Questions Submit your questions anytime

More information

MAY 2015 ELECTRIC VEHICLES: REDUCING ONTARIO S GREENHOUSE GAS EMISSIONS A CLIMATE CHANGE ACTION REPORT PREPARED BY:

MAY 2015 ELECTRIC VEHICLES: REDUCING ONTARIO S GREENHOUSE GAS EMISSIONS A CLIMATE CHANGE ACTION REPORT PREPARED BY: MAY 2015 ELECTRIC VEHICLES: REDUCING ONTARIO S GREENHOUSE GAS EMISSIONS A CLIMATE CHANGE ACTION REPORT PREPARED BY: PLUG N DRIVE - WHO WE ARE Plug n Drive is a non-profit organization committed to accelerating

More information

Attention: Mr. Patrick Wruck, Commission Secretary and Manager, Regulatory Support

Attention: Mr. Patrick Wruck, Commission Secretary and Manager, Regulatory Support Diane Roy Vice President, Regulatory Affairs Gas Regulatory Affairs Correspondence Email: gas.regulatory.affairs@fortisbc.com Electric Regulatory Affairs Correspondence Email: electricity.regulatory.affairs@fortisbc.com

More information

Electric Vehicle Charging Infrastructure in Shared Parking Areas: Resources to Support Implementation & Charging Infrastructure Requirements

Electric Vehicle Charging Infrastructure in Shared Parking Areas: Resources to Support Implementation & Charging Infrastructure Requirements Electric Vehicle Charging Infrastructure in Shared Parking Areas: Resources to Support Implementation & Charging Infrastructure Requirements A publication of the City of Richmond with funding support from

More information

Executive Summary. DC Fast Charging. Opportunities for Vehicle Electrification in the Denver Metro area and Across Colorado

Executive Summary. DC Fast Charging. Opportunities for Vehicle Electrification in the Denver Metro area and Across Colorado Opportunities for Vehicle Electrification in the Denver Metro area and Across Colorado Overcoming Charging Challenges to Maximize Air Quality Benefits The City and County of Denver has set aggressive goals

More information

SMALL BATTERY CHARGING SYSTEMS

SMALL BATTERY CHARGING SYSTEMS SMALL BATTERY CHARGING SYSTEMS REGULATORY PROPOSAL PREPARED BY: ENERGY EFFICIENCY BRANCH, BC MINISTRY OF ENERGY AND MINES HTTP://WWW.EMPR.GOV.BC.CA/EEC/STRATEGY/EEA/PAGES/DEFAULT.ASPX JANUARY 2014 PLEASE

More information

Renewables in Transport (RETRANS)

Renewables in Transport (RETRANS) Renewables in Transport (RETRANS) Synergies in the development of renewable energy and electric transport Project Presentation at BMU, Berlin 2 September 2010 2 RETRANS project - Introduction and scope

More information

Consumer Guidelines for Electric Power Generator Installation and Interconnection

Consumer Guidelines for Electric Power Generator Installation and Interconnection Consumer Guidelines for Electric Power Generator Installation and Interconnection Habersham EMC seeks to provide its members and patrons with the best electric service possible, and at the lowest cost

More information

Consumers, Vehicles and Energy Integration (CVEI) project

Consumers, Vehicles and Energy Integration (CVEI) project Consumers, Vehicles and Energy Integration (CVEI) project Dr Stephen Skippon, Chief Technologist September 2016 Project aims To address the challenges involved in transitioning to a secure and sustainable

More information

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY

More information

BC Hydro OATT - Balancing Area Transmission Service Workshop. January 20, 2014

BC Hydro OATT - Balancing Area Transmission Service Workshop. January 20, 2014 T BC Hydro OATT - Balancing Area Transmission Service Workshop January 20, 2014 1 AGENDA Topic Time Speaker Welcome and Introduction 09:00 09:15 Gord Doyle Background 09:15 10:00 Martin Huang Enforcement

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 27, 2012 SUBJECT: NOTICE OF AWARD PROCUREMENT AUTHORIZATION - ARTICULATED BUSES INFORMATION ITEM RECOMMENDATION

More information

Public Works and Infrastructure Committee. p:/2015/clusterb/tra/northyork/pw15086

Public Works and Infrastructure Committee. p:/2015/clusterb/tra/northyork/pw15086 PW9.10 STAFF REPORT ACTION REQUIRED Car-Share Parking in Permit Parking Areas Date: October 22, 2015 To: From: Wards: Reference Number: Public Works and Infrastructure Committee General Manager, Transportation

More information

Transportation Electrification: Reducing Emissions, Driving Innovation. August 2017

Transportation Electrification: Reducing Emissions, Driving Innovation. August 2017 Transportation Electrification: Reducing Emissions, Driving Innovation August 2017 CA raising the bar in environmental policy and action Senate Bill 350 (DeLeon, 2015) established broad and ambitious clean

More information

Transport An affordable transition to sustainable and secure energy for light vehicles in the UK

Transport An affordable transition to sustainable and secure energy for light vehicles in the UK An insights report by the Energy Technologies Institute Transport An affordable transition to sustainable and secure energy for light vehicles in the UK 02 03 Energy Technologies Institute www.eti.co.uk

More information

EU CO 2 emission policy : State of Play. European Commission, DG CLIMA. Climate Action

EU CO 2 emission policy : State of Play. European Commission, DG CLIMA. Climate Action EU CO 2 emission policy : State of Play European Commission, DG CLIMA Clean Mobility Package: an integrated approach 2016 Clean Energy Package RED II: lowemission fuels 2016 European Low-Emission Mobility

More information

San Joaquin Valley Plug-in Electric Vehicle Coordinating Council

San Joaquin Valley Plug-in Electric Vehicle Coordinating Council San Joaquin Valley Plug-in Electric Vehicle Coordinating Council Meeting #4 May 2, 2013 1 San Joaquin Valley Plug-in Electric Vehicle Coordinating Council Meeting #4 May 2, 2013 10:00 a.m. 12:00 p.m. Announcements

More information

ENGINEERING SPECIFICATION

ENGINEERING SPECIFICATION December 206 ENGINEERING SPECIFICATION No. of 6 DATE: 2-9-6 CATEGORY SUBJECT TABLE OF CONTENTS. Overview... 2 2. General Requirements for Service... 3 3. Definitions... 3 4. Abbreviations... 5 5. References

More information

Zero Emission Bus Impact on Infrastructure

Zero Emission Bus Impact on Infrastructure Zero Emission Bus Impact on Infrastructure California Transit Association (CTA) Fall Conference Nov 17, 2016 Russ Garwacki Director, Pricing Design & Research 626.302.6673 Russell.Garwacki@sce.com Barbara

More information

Electric Vehicle Basics for Your Business

Electric Vehicle Basics for Your Business Welcome to Electric Vehicle Basics for Your Business Electric Vehicle Basics for Your Business What You Need to Know About EVs and Charging September 25, 2013 1 Agenda 7788 Copyright 2012, -800-990- SCE

More information

Interconnection Process for Generation Systems

Interconnection Process for Generation Systems Interconnection Process for Generation Systems I. INTRODUCTION...1 II. GENERAL INFORMATION...2 A. Definitions...2 B. Nodak Electric Cooperative, Inc. Generation Interconnection Contacts...3 C. Engineering

More information

SUBSIDIARY BODY FOR SCIENTIFIC AND TECHNOLOGICAL ADVICE Fourteenth session Bonn, July 2001 Item 3 (b) of the provisional agenda

SUBSIDIARY BODY FOR SCIENTIFIC AND TECHNOLOGICAL ADVICE Fourteenth session Bonn, July 2001 Item 3 (b) of the provisional agenda UNITED NATIONS Distr. GENERAL 11 July 2001 ENGLISH ONLY SUBSIDIARY BODY FOR SCIENTIFIC AND TECHNOLOGICAL ADVICE Fourteenth session Bonn, 16-27 July 2001 Item 3 (b) of the provisional agenda REPORTS ON

More information

Filed with the Iowa Utilities Board on September 17, 2018, RMU STATE OF IOWA DEPARTMENT OF COMMERCE IOWA UTILITIES BOARD

Filed with the Iowa Utilities Board on September 17, 2018, RMU STATE OF IOWA DEPARTMENT OF COMMERCE IOWA UTILITIES BOARD STATE OF IOWA DEPARTMENT OF COMMERCE IOWA UTILITIES BOARD IN RE: DOCKET NO. RMU-2018-0100 ELECTRIC VEHICLE INFRASTRUCTURE JOINT UTILITY STAKEHOLDER COMMENTS MidAmerican Energy Company ( MidAmerican ),

More information

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS. 25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context indicates otherwise, this section and 25.212 of this title (relating to Technical Requirements

More information

Consumers, Vehicles and Energy Integration (CVEI) project

Consumers, Vehicles and Energy Integration (CVEI) project Consumers, Vehicles and Energy Integration (CVEI) project Auto Council Technology Group meeting Wednesday 22 nd February 2017 2017 Energy Technologies Institute LLP The information in this document is

More information

Residential Rate Design and Electric Vehicles

Residential Rate Design and Electric Vehicles December 17, 2018 Residential Rate Design and Electric Vehicles Presentation for US EPA The Regulatory Assistance Project (RAP) Nancy Seidman, Jessica Shipley www.raponline.org 1 Introduction What does

More information

Electric Plug-In Vehicle/Electric Vehicle Status Report

Electric Plug-In Vehicle/Electric Vehicle Status Report Electric Plug-In Vehicle/Electric Vehicle Status Report Prepared by: Sanjay Mehta, Electrical Engineering Assistant August 2010 ABSTRACT The purpose of this report is to identify the various Electric Plug-in-

More information

To: Honorable Public Utilities Board Submitted by: /s/ Rebecca Irwin AGM-Customer Resources. From: Kelly Birdwell Brezovec Approved by: /s/

To: Honorable Public Utilities Board Submitted by: /s/ Rebecca Irwin AGM-Customer Resources. From: Kelly Birdwell Brezovec Approved by: /s/ AGENDA ITEM NO.: 5.A.1 MEETING DATE: 10/16/2017 ADMINISTRATIVE REPORT NO.: 2018-15 To: Honorable Public Utilities Board Submitted by: /s/ Rebecca Irwin AGM-Customer Resources From: Kelly Birdwell Brezovec

More information

Southern California Edison Original Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Cal. PUC Sheet No.

Southern California Edison Original Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Cal. PUC Sheet No. Southern California Edison Original Cal. PUC Sheet No. 58584-E Schedule CRPP Sheet 1 APPLICABILITY This Schedule is applicable to Customer Participants, as defined below, who elect to participate in the

More information

Energy Management Through Peak Shaving and Demand Response: New Opportunities for Energy Savings at Manufacturing and Distribution Facilities

Energy Management Through Peak Shaving and Demand Response: New Opportunities for Energy Savings at Manufacturing and Distribution Facilities Energy Management Through Peak Shaving and Demand Response: New Opportunities for Energy Savings at Manufacturing and Distribution Facilities By: Nasser Kutkut, PhD, DBA Advanced Charging Technologies

More information

Generator Efficiency Optimization at Remote Sites

Generator Efficiency Optimization at Remote Sites Generator Efficiency Optimization at Remote Sites Alex Creviston Chief Engineer, April 10, 2015 Generator Efficiency Optimization at Remote Sites Summary Remote generation is used extensively to power

More information

Economics and Barriers to Solar Photovoltaic Applications in Barbados

Economics and Barriers to Solar Photovoltaic Applications in Barbados Economics and Barriers to Solar Photovoltaic Applications in Barbados Roland R Clarke PhD Clarke Energy Associates www.clarkeenergy@aol.com clarkeenergy@aol.com Presented to Alternative Energy: Pathways

More information

Recharge the Future Interim Findings

Recharge the Future Interim Findings Recharge the Future Interim Findings Jack Lewis Wilkinson, Smart Grid Development Engineer, UK Power Networks Celine Cluzel, Director, Element Energy Tristan Dodson, Senior Consultant, Element Energy 1

More information

Federal Gas Tax Program. Transportation Committee May 7, 2014

Federal Gas Tax Program. Transportation Committee May 7, 2014 5.2 Federal Gas Tax Program Transportation Committee May 7, 2014 Federal Gas Tax Transfer Program Original head agreement signed in 2005 (Canada-BC-UBCM) Purpose: provide local governments with stable,

More information

Estimation of electrical losses in Network Rail Electrification Systems

Estimation of electrical losses in Network Rail Electrification Systems Estimation of electrical losses in Network Rail Electrification Systems Page 1 of 16 Contents 1. BACKGROUND...3 2. PURPOSE...3 3. SCOPE...3 4. DEFINITIONS & ABBREVIATIONS...4 5. NETWORK RAIL INFRASTRUCTURE

More information

Large General Service Time-of-Use Storage Program

Large General Service Time-of-Use Storage Program Large General Service Time-of-Use Storage Program AVAILABILITY Available throughout the Company s entire electric service area where the facilities of the Company are of adequate capacity and are adjacent

More information

ELECTRIC VEHICLE CHARGING FOR BUILDINGS

ELECTRIC VEHICLE CHARGING FOR BUILDINGS PLANNING & DEVELOPMENT SERVICES Office of the Chief Building Official BULLETIN 2015-004-BU/EL June 25, 2015 ELECTRIC VEHICLE CHARGING FOR BUILDINGS This bulletin provides clarification of requirements

More information

3/16/2016. How Our Cities Can Plan for Driverless Cars April 2016

3/16/2016. How Our Cities Can Plan for Driverless Cars April 2016 How Our Cities Can Plan for Driverless Cars April 2016 1 They re coming The state of autonomous vehicle technology seems likely to advance with or without legislative and agency actions at the federal

More information

Battery Electric Bus Technology Review. Victoria Regional Transit Commission September 19, 2017 Aaron Lamb

Battery Electric Bus Technology Review. Victoria Regional Transit Commission September 19, 2017 Aaron Lamb Battery Electric Bus Technology Review Victoria Regional Transit Commission September 19, 2017 Aaron Lamb 0 Outline Battery Electric Bus Technology Why Electric? Potential Benefits Industry Assessment

More information