Robofish Charging Station (RCS) Test Plan

Size: px
Start display at page:

Download "Robofish Charging Station (RCS) Test Plan"

Transcription

1 Team P /26/2016 Rev A Robofish Charging Station (RCS) Test Plan 1

2 Table of Contents 1. Objectives 2. Test Criteria 3. Test Resources 4. Test Procedures 5. Results 6. Conclusions 1. Objectives 1.1. Definitions Robofish : An autonomous underwater robot that utilizes McKibben style muscles to translocate. The project is outlined by the customer requirements of P14029, P15029, P16029, and P Robofish Charging Station (RCS) : A station that harvests and stores solar energy that is capable of automatically docking the Robofish, charging the Robofish, and releasing the Robofish. The project is outlined by the customer requirements of P Docking Sequence : A sequence that begins with the Robofish physically and electrically disconnected from the RCS and ends with the Robofish physically and electrically connected to the RCS. Assuming the Robofish is in position and capable of controlling its buoyancy. Charging Sequence : A sequence during which electrical energy is supplied to and managed to charge the Robofish battery. Full Charge (of Robofish): A full charge is defined as charging the Robofish from 10% capacity to 100% capacity in 90% of the required time (12 hrs). Undocking Sequence : A sequence that begins with the Robofish physically and electrically connected to the RCS and ends with the Robofish physically and electrically disconnected from the RCS. Assuming the Robofish is capable of controlling its buoyancy Purpose This document details the test plan for the Robofish Charging Station. The purpose of this document is threefold. First, necessary test criteria are identified that demonstrate the final design meets the engineering requirements and ultimately the customer 2

3 requirements. Second, test resources and procedures are specified that provide a means of proving the criteria. Third, test results are recorded based on the execution of those procedures and adherence to the requirements is examined Scope This test plan applies to the finalized design for the Robofish Charging Station and any affixed hardware necessary for it to perform the functions outlined in the customer requirements (see 2.1). The Robofish is not encompassed, with the exception of the battery and the battery management system. The battery and battery management system includes all electronics necessary to provide power to the Robofish up to but not including the 24V Buck converter implemented by team P Test Criteria 2.1. Customer Requirements Table 1: Customer Requirements 2.2. Customer Requirement Completion Criteria CR1: Will be satisfied if ER6 is satisfied and if fish remains attached to the RCS during the Automated Process Test. CR2: Will be satisfied if ER4 is satisfied. 3

4 CR3: Will be satisfied if ER2 and ER3 and ER4 are satisfied. CR4: Will be satisfied if ER1 is satisfied. CR5: Will be satisfied if ER5 is satisfied. CR6: Will be satisfied if ER9 is satisfied. CR7: Will be satisfied if ER7 and ER8 are satisfied Engineering Requirements Table 2: Engineering Requirements 2.4. Engineering Requirement Completion Criteria ER1: Shall be satisfied through a Depth Test that demonstrates the RCS lies less than 1m below the water s surface and is fully capable of docking the Robofish, charging the Robofish, and releasing the Robofish while at that depth. ER2: Shall be satisfied through a Battery Capacity Test that demonstrates the RCS can store enough energy to charge the Robofish for 3 full charge cycles (see 1.1) in the event that insufficient solar energy is harvested on a given day. 4

5 ER3: Shall be satisfied through an Energy Delivery Test that demonstrates the charging station provides enough power to fully charge (see 1.1) the Robofish battery in the required time. ER4: Shall be satisfied through an Energy Harvesting Test that demonstrates the RCS is capable of harvesting the required energy by testing the power that is harvested on three different test dates, twice each day. ER5: Shall be satisfied through a Budget Review that demonstrates the cost of the project remained under the funds allotted. The Budget Review will occur outside of this document as it is not a technical requirement. ER6: Shall be satisfied through a Robofish Attachment Strength Test that demonstrates the Robofish remains attached to the RCS when a force is applied to it in the plus and minus directions of three coordinate axes. ER7: Shall be satisfied through a Buoyancy and Stability Test that demonstrates the lower frame of the RCS remains fully above the surface of the water when a load is applied at five selected locations. ER8: Shall be satisfied through a Waterproof Test that demonstrates the RCS electronics enclosure withstands splashes of water, following the waterproof ipx3 standard, and ideally sprays of water, following the waterproof ipx4 standard. ER9: Shall be satisfied through an Automated Process Test that demonstrates the RCS can dock the Robofish, charge the Robofish, and release the Robofish without human interaction. 3. Test Equipment 3.1. Depth Test Table 3: Depth Test Resources Equipment Description Measuring Tape Must have cm markings and be accurate to ±1 cm Body of water Non-salt, less than 1m deep 5

6 Tape Or another means of marking the bottom of the body of water 3.2. Battery Capacity Test Table 4: Battery Capacity Test Resources Equipment RCS Lead Acid Batteries (4) Flood Lamp Multimeter Description To be tested Used as a cheap high power resistor Include voltmeter and ammeter 3.3. Energy Delivery Test Table 5: Energy Delivery Test Resources Equipment Multimeter Timer/Stopwatch Computer (Excel Document) Robofish (LiPo Battery, LiPo Controller, Connector, Arduino) and RCS (Connector and Lead Acid Battery) Description Include voltmeter and ammeter. Must measure minutes and hours. Record measurements and calculate predicted delivery time. LiPo Battery, LiPo Controller, Connectors, and Lead Acid Battery 3.4. Energy Harvesting Test Table 6: Energy Harvesting Test Resources Equipment Multimeter An outdoor area Description Must read current to 10A and DC voltage to 30V Should have an area the size of the solar panel that has a direct line of sight to the sun (when there are no clouds) 3.5. Robofish Attachment Strength Test Table 7: Robofish Attachment Strength Test Resources 6

7 Equipment Description Force Gauge/Weights Force Gauge/Weights (5 N, 10 N, 15 N) Robofish Connector RCS Connector Clamp Connector, 3-Pin, Male Connector, 3-Pin, Female Clamp to fix RCS Connector in place 3.6. Buoyancy Test Table 8: Buoyancy Test Resources Equipment Weights Floatation_ASSY Body of Water Description 50 lbs, bar bells recommended Floatation assembly that includes shipping pails and 8020 framework. Non-salt water, pool recommended 3.7. Waterproof Test Table 9: Waterproof Test Resources Equipment Description See IP4 Waterproof Standard Automated Process Test Table 10: Automated Process Test Resources Equipment Waterproof Camera Description Must record video Robofish - 4. Test Procedures 4.1. Depth Test Depth Test Preparation 7

8 1. Using the measuring tape, measure and record the depth of the body of water from the surface to the bottom in 5 places (see figure 4.1.1). Mark each location on the bottom of the body of the water using tape. If the depth at every point is 1 meter, or less, the test may be performed in this body of water 2. Ensure that the station is fully assembled as it would be for operation. If components are missing, dummy weights may be used at the missing components location that matches the weight of the missing component. Figure 4.1.1: Water depth measurement sites Depth Test Procedure 1. Position the station so that the lowest point of the station is centered over depth measurement point 5 2. Position the fish in docking position and perform one docking sequence, one charging sequence, and one undocking sequence. 3. If the station is capable of performing these sequences the test is passed. *See section 1.1 for sequence descriptions 8

9 4.2. Battery Capacity Test Figure 4.1.2: RCS test position Battery Capacity Test Preparation 1. Charge batteries using solar panels on RCS Battery Capacity Test Procedure 1. Measure Open Circuit Voltage of battery at full charge 2. Attach 12v 40w flood lamp and let battery discharge through it for 5 hours 3. Every hour, disconnect lamp, measure open circuit voltage, and reconnect lamp 4. After 5 hours or battery voltage reaches 11v, mark down time spent discharging. The battery capacity is 3.33*hours discharging in Amp hours Figure 4.2: Schematic of Battery Capacity Test Setup 4.3. Energy Delivery Test Energy Delivery Test Preparation 1. Measure and record the initial values of the batteries (see 4.2 Battery Capacity Test). 2. Make sure the lead acid batteries have sufficient charge to supply to the LiPo battery and it s load. 3. Record the values expected of the 90% charged LiPo battery. 9

10 4. Set up a table for measuring the charging progression for use in a graph. 5. Make sure the lead acid batteries are in parallel. 6. Make sure the lead acid batteries are connected to the female connector port (there are 4 sets, however the connectors can be tested separately, so only one is needed). 7. Choose a location for testing. Ideally, this should be tested in the environment of its final use (aka a calm body of fresh water), but for our purposes, a lab will suffice since the test is limited to the lead acid batteries through to the robofish. Solar panels are tested under section 4.4 Energy Harvesting Test. 8. Set up the robofish for testing: a. NOTE: The robofish should charge with most of the load disconnected, but this is done through internal configurations. Therefore, the robofish must be on. If the robofish attempts to swim while connected to the lead acid batteries, there is an error. b. One option is to hook up the robofish s McKibben style muscles to the gas lines, then turn on. c. Another option is to submerge the robofish and connect the connectors out of the water. i. CAUTION: Do NOT allow the robofish battery or the RCS batteries to get wet! The connectors may get wet, but should not be submerged while connected. Energy Delivery Test Procedure 1. Once the preparations above ( ) are complete, attach the connectors. 2. Measure and record the current flow and voltages. 3. Set a timer for one hour. 4. Calculate and record power transfer (Watts per hour) and current wattages. 5. Use this data to predict the time to charge. 6. Wait. Once the timer goes off, repeat steps 2 through 5 until the predicted time to charge is less than the timer time. a. If the results are as predicted, the timer time may be increased. Otherwise, a decrease in timer time may be in order for more accurate results. b. Once the predicted time to charge is less than the timer time, set the timer to allow a 30 minute range of accuracy (+/- 15 minutes). 7. Disconnect the connectors. Graph the data. a. It is good practice to dissipate the charge to 50% for storage, so it is best to not leave any batteries with a full charge, although lead acid batteries will hold a high charge for a long period of time better than a LiPo battery. 10

11 Figure 4.3: Schematic of Energy Delivery Test Setup 4.4. Energy Harvesting Test Energy Harvesting Test Preparation 1. Set RCS, or solar panel from RCS, flat on the ground so that no portion of it is shaded by buildings, trees, or other objects/structures. Shade from clouds is acceptable. 2. Ensure the positive and negative lead wires on the panel are disconnected from any other wires or batteries. Energy Harvesting Test Procedure 1. Connect the multimeter between the positive and negative lead wires coming off the solar panel. 2. With the multimeter in a DC voltage measurement mode, measure and record the voltage across the leads. 3. With the multimeter in a current measurement mode, measure and record the current across the leads. This step must be completed within 1 minute of completing step Repeat steps 1-3 on five different days, twice each day, for a total of ten data sets. One of the five days must have no visible cloud cover and one of the five days must have visible cloud cover. The two measurements in an individual day must be taken at least 2 hours apart. 11

12 Figure 4.4.1: Data collection set-up Energy Harvesting Data Analysis Procedure 1. Multiply the measured voltage by the measured current to get the measured power output of the panel at the time those measurements were taken. 2. Multiply the power by an average 11 hours of daylight in a day to determine the amount of power generated each day by each solar panel. 3. Multiply the power harvested each day by the number of solar panels to find the total power harvested each day. 4. On average 148 Wh must be harvested each day based on the battery capacity of the Robofish. The final measurements must all lie within 2 standard deviations of this requirement*. *The station has enough battery capacity to charge the Robofish from zero to full at least 3 times Robofish Attachment Strength Test 1. Fix RCS Connector utilizing clamps 2. Push the Robofish connector into the RCS Connector until the microswitch (in the RCS Connector) is tripped, and the motor actuates 12

13 3. Robofish and RCS Connectors will undergo normal connection operation, using a motor to turn a screw, that will lock the connectors together. 4. Apply 5 N force utilizing force gauge/weights to the Robofish Connector in the ±X, Y, and Z directions. 5. Record whether or not connection is still maintained after the force is applied. 6. Repeat Steps 4 & 5 using a 10 N force. 7. Repeat Steps 4 & 5 using a 15 N force Buoyancy and Stability Test 1. Place the fully assembled RCS into a body of water 2. Apply 50 lbs of force to the center of the RCS 3. Record whether or not the station can support the applied force without the station platform falling below the water's surface. 4. Repeat steps 2 and 3, except applying the force to all 4 corners of the RCS as shown in fig The center of mass of the weights must be within a 10 cm radius of each corner Waterproof Test Figure 4.6.1: Buoyancy and Stability test load points 1. Perform test to IP4 waterproof standard 4.8. Automated Process Test Automated Test Procedure* 1. Record steps 2-4 on video to provide evidence of completed test. 2. Position the Robofish so that its front grasper is around the docking pole on the RCS. 13

14 3. Ensure the Robofish is buoyant and release its grasp on the pole a. Test condition 1 - The Robofish must float up into a docking port without any human intervention and its connector must enter its counterpart on the station for attachment. b. Test condition 2 - The attachment system must automatically make the electrical connection between the Robofish and the RCS. This connection must be confirmed through the monitoring of the 12v loopback pin on the RCS side connector. 4. Press the abort charge button to abort the charging process and release the Robofish. a. Test condition 3 - The attachment mechanism must automatically detach the Robofish (physically and electrically) from the station. After changing the buoyancy, the Robofish must fall down out of its docking port. 5. Repeat steps 2-4 for all 8 positions shown in fig All three test conditions must be satisfied at every tested position for the test to be passed. *If the Robofish cannot perform its functions automatically, move it through the required positions by hand Figure 4.8.1: Test positions of Robofish for automated process test 14

15 5. Results 5.1. Depth Test 5.2. Battery Capacity Test 5.3. Energy Delivery Test 5.4. Energy Harvesting Test 5.5. Robofish Attachment Strength Test 5.6. Buoyancy Test 5.7. Waterproof Test 5.8. Automated Process Test 5.9. Budget Review 15

16 6. Conclusions 16

Robofish Charging Station (RCS) Test Plan

Robofish Charging Station (RCS) Test Plan Team P17250 10/26/2016 Rev A Robofish Charging Station (RCS) Test Plan 1 Table of Contents 1. Objectives 2. Test Criteria 3. Test Resources 4. Test Procedures 5. Results 6. Conclusions 1. Objectives 1.1.

More information

Project Name: RoboFish Charging Station (RCS)

Project Name: RoboFish Charging Station (RCS) Project Name: RoboFish Charging Station (RCS) Project Number: P17250 Project Family: P16029, P16229, P15029, P14029 Start Term: 2161 End Term: 2165 Team Members Jack Moore - Mechanical Engineering - Project

More information

SUBJECT AREA(S): Amperage, Voltage, Electricity, Power, Energy Storage, Battery Charging

SUBJECT AREA(S): Amperage, Voltage, Electricity, Power, Energy Storage, Battery Charging Solar Transportation Lesson 4: Designing a Solar Charger AUTHOR: Clayton Hudiburg DESCRIPTION: In this lesson, students will further explore the potential and challenges related to using photovoltaics

More information

AP Physics B Ch 18 and 19 Ohm's Law and Circuits

AP Physics B Ch 18 and 19 Ohm's Law and Circuits Name: Period: Date: AP Physics B Ch 18 and 19 Ohm's Law and Circuits MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question. 1) A device that produces electricity

More information

Investigation Electrical Circuits

Investigation Electrical Circuits ACTIVITY #1 Task: To design and construct a circuit where 2 light bulbs can turn on and off at the same time Materials: - 1 power supply - 2 light bulbs - Connecting wires ( ) - Switch(s) - Multi-meter

More information

ARAI Date of hosting on website: 27 th October 2015 Last date for comments: 27 th November 2015

ARAI Date of hosting on website: 27 th October 2015 Last date for comments: 27 th November 2015 ARAI Date of hosting on website: 27 th October 2015 Last date for comments: 27 th November 2015 CHECK LIST FOR PREPARING AMENDMENT TO AUTOMOTIVE INDUSTRY STANDARD (AIS) Draft Amd. No 01 to AIS-099 : Approval

More information

White Paper. How Do I Know I Can Rely on It? The Business and Technical Cases for Solar-Recharged Video Surveillance Systems

White Paper. How Do I Know I Can Rely on It? The Business and Technical Cases for Solar-Recharged Video Surveillance Systems White Paper How Do I Know I Can Rely on It? The Business and Technical Cases for Solar-Recharged Video Surveillance Systems Introduction Remote cameras are a security professional s eyes at the edges of

More information

Chapter 3. ECE Tools and Concepts

Chapter 3. ECE Tools and Concepts Chapter 3 ECE Tools and Concepts 31 CHAPTER 3. ECE TOOLS AND CONCEPTS 3.1 Section Overview This section has four exercises. Each exercise uses a prototyping board for building the circuits. Understanding

More information

TOTALFLOW Technical Bulletin 59 Lead Acid Battery Inspection and Maintenance Procedures

TOTALFLOW Technical Bulletin 59 Lead Acid Battery Inspection and Maintenance Procedures TOTALFLOW Technical Bulletin 59 Lead Acid Battery Inspection and Maintenance Procedures Totalflow Technical Bulletin Version 1.0, Revision AC (8 January, 2001) \\isntsrv1\tffiles\documentation\techbulls\insert

More information

Battery Capacity Versus Discharge Rate

Battery Capacity Versus Discharge Rate Exercise 2 Battery Capacity Versus Discharge Rate EXERCISE OBJECTIVE When you have completed this exercise, you will be familiar with the effects of the discharge rate and battery temperature on the capacity

More information

Technical Workshop: Electrical December 3, 2016

Technical Workshop: Electrical December 3, 2016 Technical Workshop: Electrical December 3, 2016 ELECTRICAL: CIRCUITS Key terms we will be using today: Voltage (V): The difference in electrical potential at one point in a circuit in relation to another.

More information

Reference: Photovoltaic Systems, p References: Photovoltaic Systems, Chap. 7 National Electrical Code (NEC), Articles 110,

Reference: Photovoltaic Systems, p References: Photovoltaic Systems, Chap. 7 National Electrical Code (NEC), Articles 110, Charge controllers are required in most PV systems using a battery to protect against battery overcharging and overdischarging. There are different types of charge controller design, and their specifications

More information

INVESTIGATION ONE: WHAT DOES A VOLTMETER DO? How Are Values of Circuit Variables Measured?

INVESTIGATION ONE: WHAT DOES A VOLTMETER DO? How Are Values of Circuit Variables Measured? How Are Values of Circuit Variables Measured? INTRODUCTION People who use electric circuits for practical purposes often need to measure quantitative values of electric pressure difference and flow rate

More information

Owner and Operating Manual for

Owner and Operating Manual for Owner and Operating Manual for 120VAC Manual Control 12VDC Solar Battery Manual Control 120VAC Remote Control 12VDC Solar Battery Remote Control GEN2 Remote Versions Only Boat Lifts Please read this manual

More information

Laboratory 5: Electric Circuits Prelab

Laboratory 5: Electric Circuits Prelab Phys 132L Fall 2018 Laboratory 5: Electric Circuits Prelab 1 Current and moving charges Atypical currentinanelectronic devicemightbe5.0 10 3 A.Determinethenumber of electrons that pass through the device

More information

Billboard LED Solar System STOP! THIS IS IMPORTANT

Billboard LED Solar System STOP! THIS IS IMPORTANT EcoSolar by Irvin TM Billboard LED Solar System STOP! THIS IS IMPORTANT Take a moment to familiarize yourself with the polarity of the wires included in your solar system. Make sure you connect positive

More information

UPSPro Backup Power System

UPSPro Backup Power System UPS-ST12 / 24 / 48 UPSPro Backup Power System Wireless Base Stations Surveillance Cameras Remote Gate Control Electric Fence Up to 192W loads Congratulations! on your purchase of the UPSPro outdoor backup

More information

SMT. Installation and Operation Manual. Model:SMT WITH MPPT TECHNOLOGY

SMT. Installation and Operation Manual. Model:SMT WITH MPPT TECHNOLOGY SMT WITH MPPT TECHNOLOGY Installation and Operation Manual Model:SMT SMT Dimensions Specification Summary System Voltage 12 V/24V Rated Battery Current 12V, 5A 8A 10A 15A 20A 25A 24V, 5A 8A 10A 15A Rated

More information

Installation Instructions

Installation Instructions SOLAR GARDEN POWER CELL SKU#229120 Rated Voltage 12VDC Thank you for purchasing this quality Lucci product. To ensure correct function and safety, please read and follow all instructions carefully before

More information

AUTOMATE Li-ion Solar Charging Power Panel

AUTOMATE Li-ion Solar Charging Power Panel AUTOMATE Li-ion Solar Charging Power Panel SOLAR POWERED AUTOMATE Li-ion Solar charging power panel provides supplemental power to all Li-ion wirefree motors or rechargeable battery packs. The monosilicon/crystal

More information

Figure 1: Graphs Showing the Energy and Power Consumed by Two Systems on an ROV during a Mission

Figure 1: Graphs Showing the Energy and Power Consumed by Two Systems on an ROV during a Mission Power Systems 3 Cornerstone Electronics Technology and Robotics III Notes primarily from Underwater Robotics Science Design and Fabrication, an excellent book for the design, fabrication, and operation

More information

SK-10. Features. Solar Charge Controller User Manual. Important Safety Information

SK-10. Features. Solar Charge Controller User Manual. Important Safety Information SK-10 Solar Charge Controller User Manual 12V/24V 10Amp Dear Users: Thank you for selecting our product. Please read this manual carefully before you use this product. This product is of cutting edge design,

More information

Team P14029: McKibben Muscle Robotic Fish

Team P14029: McKibben Muscle Robotic Fish Team P14029: McKibben Muscle Robotic Fish Project Manager: Zachary Novak Mechanical Design Lead: John Chiu Lead Engineer: Seaver Wrisley Controls and Instrumentation Lead: Felix Liu AGENDA Project Goal

More information

The Traveler Series TM : Adventurer

The Traveler Series TM : Adventurer The Traveler Series TM : Adventurer 30A PWM Flush Mount Charge Controller w/ LCD Display 2775 E. Philadelphia St., Ontario, CA 91761 1-800-330-8678 Version: 3.4 Important Safety Instructions Please save

More information

12 VOLT 30 AMP DIGITAL SOLAR CHARGE CONTROLLER

12 VOLT 30 AMP DIGITAL SOLAR CHARGE CONTROLLER 12 VOLT 30 AMP DIGITAL SOLAR CHARGE CONTROLLER User s Manual Congratulations on your Coleman solar product purchase. This product is designed to the highest technical specifications and standards. It will

More information

Physics Experiment 9 Ohm s Law

Physics Experiment 9 Ohm s Law Fig. 9-1 Simple Series Circuit Equipment: Universal Circuit Board Power Supply 2 DMM's (Digital Multi-Meters) with Leads 150- Resistor 330- Resistor 560- Resistor Unknown Resistor Miniature Light Bulb

More information

PHY132 Practicals Week 5 Student Guide

PHY132 Practicals Week 5 Student Guide PHY132 Practicals Week 5 Student Guide Concepts of this Module Introducing current and voltage Simple circuits Circuit diagrams Background When water flows through a garden hose, we can characterize the

More information

SOLAR LIGHTING CONTROLLER SUNLIGHT MODELS INCLUDED IN THIS MANUAL SL-10 SL-10-24V SL-20 SL-20-24V

SOLAR LIGHTING CONTROLLER SUNLIGHT MODELS INCLUDED IN THIS MANUAL SL-10 SL-10-24V SL-20 SL-20-24V SOLAR LIGHTING CONTROLLER OPERATOR S MANUAL SUNLIGHT MODELS INCLUDED IN THIS MANUAL SL-10 SL-10-24V SL-20 SL-20-24V 10A / 12V 10A / 24V 20A / 12V 20A / 24V 1098 Washington Crossing Road Washington Crossing,

More information

MAGNETIC FORCE ON A CURRENT-CARRYING WIRE

MAGNETIC FORCE ON A CURRENT-CARRYING WIRE MAGNETIC FORCE ON A CURRENT-CARRYING WIRE Pre-Lab Questions Page 1. What is the SI unit for Magnetic Field? Name: Class: Roster Number: Instructor: 2. The magnetic field on a wire is 12.0 x 10 5 Gausses,

More information

Detailed Design Review

Detailed Design Review Detailed Design Review P16241 AUTONOMOUS PEOPLE MOVER PHASE III Team 2 Agenda Problem Definition Review Background Problem Statement Project Scope Customer Requirements Engineering Requirements Detailed

More information

The Traveler Series: Adventurer

The Traveler Series: Adventurer The Traveler Series: Adventurer RENOGY 30A Flush Mount Charge Controller Manual 2775 E. Philadelphia St., Ontario, CA 91761 1-800-330-8678 Version: 2.2 Important Safety Instructions Please save these instructions.

More information

Recommended Tools: Phillips Screwdriver, 13mm and 10mm Wrench, 5/16 nut driver, Flat Blade Screwdriver

Recommended Tools: Phillips Screwdriver, 13mm and 10mm Wrench, 5/16 nut driver, Flat Blade Screwdriver RPST12M/24M RemotePro Remote Power System Wireless Base Stations and Client Devices Surveillance Cameras Remote Sensors Remote Lighting Off Grid Electronics Congratulations! on your purchase of the RemotePro

More information

Self-Testing Industrial Series

Self-Testing Industrial Series Series: AS-I (Maint.-Free) Self-Testing Industrial Series Emergency Lighting Equipment Instructions for INSTALLATION OPERATION SERVICE SPECIFICATIONS 1300650 1300654 1300666 1300754 1300823 1300886 Hubbell

More information

INSTRUCTIONS FOR TRI-METRIC BATTERY MONITOR May 8, 1996

INSTRUCTIONS FOR TRI-METRIC BATTERY MONITOR May 8, 1996 INSTRUCTIONS FOR TRI-METRIC BATTERY MONITOR May 8, 1996 PART 2: SUPPLEMENTARY INSTRUCTIONS FOR SEVEN TriMetric DATA MONITORING FUNCTIONS. A: Introduction B: Summary Description of the seven data monitoring

More information

Installation and Operating Instructions. MPPT Solar System Controller ISC3040

Installation and Operating Instructions. MPPT Solar System Controller ISC3040 Installation and Operating Instructions MPPT Solar System Controller ISC3040 ABOUT THIS MANUAL These operating instructions come with the product and should be kept with it as a reference to all user s

More information

Experiment 6: Induction

Experiment 6: Induction Experiment 6: Induction Part 1. Faraday s Law. You will send a current which changes at a known rate through a solenoid. From this and the solenoid s dimensions you can determine the rate the flux through

More information

Problems with your 12/24V Booster?

Problems with your 12/24V Booster? Problems with your 12/24V Booster? Check this Trouble Shooting Manual for your answer 1. Tools Required 2. First Tests to conduct 2.1 Measure the Voltage at the Clamps 2.2 Testing the power (Amps) 3. Testing

More information

Experiment 3: Ohm s Law; Electric Power. Don t take circuits apart until the instructor says you don't need to double-check anything.

Experiment 3: Ohm s Law; Electric Power. Don t take circuits apart until the instructor says you don't need to double-check anything. Experiment 3: Ohm s Law; Electric Power. How to use the digital meters: You have already used these for DC volts; turn the dial to "DCA" instead to get DC amps. If the meter has more than two connectors,

More information

Advanced Troubleshooting Guide Snorkel V Battery Charger Rev 0 3JAN07

Advanced Troubleshooting Guide Snorkel V Battery Charger Rev 0 3JAN07 Advanced Troubleshooting Guide Snorkel 3050097 24V Battery Charger Rev 0 3JAN07 1. How It Works: The 3050097 charger converts AC voltage to DC voltage, then uses high frequency to re-convert it to DC voltage/current

More information

PHY152H1S Practical 3: Introduction to Circuits

PHY152H1S Practical 3: Introduction to Circuits PHY152H1S Practical 3: Introduction to Circuits Don t forget: List the NAMES of all participants on the first page of each day s write-up. Note if any participants arrived late or left early. Put the DATE

More information

Components for your PV Solar Electric System

Components for your PV Solar Electric System Components for your PV Solar Electric System Here is a brief description of the major components of a Solar Electric System. The components vary depending on whether batteries will be used in your system.

More information

Lab 3 : Electric Potentials

Lab 3 : Electric Potentials Lab 3 : Electric Potentials INTRODUCTION: When a point charge is in an electric field a force is exerted on the particle. If the particle moves then the electrical work done is W=F x. In general, W = dw

More information

PLATINUM SERIES SWITCHBOARD METERS

PLATINUM SERIES SWITCHBOARD METERS PLATINUM SERIES SWITCHBOARD METERS www.sifamtinsley.co.uk DATASHEET E471457 Multifunction Meters Transducers & Isolators PLATINUM SERIES SWITCHBOARD METERS Temperature Controllers Converters & Recorders

More information

UNIVERSAL SOLAR SYSTEM (USS) USER MANUAL. For Millennium Low Power Gas Detectors or other continuous loads less than 0.

UNIVERSAL SOLAR SYSTEM (USS) USER MANUAL. For Millennium Low Power Gas Detectors or other continuous loads less than 0. UNIVERSAL SOLAR SYSTEM (USS) USER MANUAL For Millennium Low Power Gas Detectors or other continuous loads less than 0.8 Watts (12 V dc) Part Number: MAN-0048-00 Rev 3 May 2006 IMPORTANT INFORMATION This

More information

Atlas ESR and ESR + Equivalent Series Resistance and Capacitance Meter. Model ESR60/ESR70. Designed and manufactured with pride in the UK.

Atlas ESR and ESR + Equivalent Series Resistance and Capacitance Meter. Model ESR60/ESR70. Designed and manufactured with pride in the UK. GB60/70-9 Atlas ESR and ESR + Equivalent Series Resistance and Capacitance Meter Model ESR60/ESR70 Designed and manufactured with pride in the UK User Guide Peak Electronic Design Limited 2004/2016 In

More information

Lab #1: Electrical Measurements I Resistance

Lab #1: Electrical Measurements I Resistance Lab #: Electrical Measurements I esistance Goal: Learn to measure basic electrical quantities; study the effect of measurement apparatus on the quantities being measured by investigating the internal resistances

More information

MPPT75HV MAXIMUM POWER POINT TRACKING SOLAR BATTERY CHARGE CONTROLLER

MPPT75HV MAXIMUM POWER POINT TRACKING SOLAR BATTERY CHARGE CONTROLLER MPPT75HV MAXIMUM POWER POINT TRACKING SOLAR BATTERY CHARGE CONTROLLER The Intronics Power Inc. MPPT75HV Solar Charge Controller continually tracks the maximum power point of the solar panel array, adjusting

More information

OPERATING INSTRUCTIONS

OPERATING INSTRUCTIONS Manual No LI-4159-MIL OPERATING INSTRUCTIONS OPERATING INSTRUCTIONS NAVY BATTERY CHARGER / ANALYZER P/N 4159-MIL MODEL CA-1550-MIL NSN: 4920-01-498-2543 Issued By: LamarTechnologies LLC 14900 40th Ave.

More information

Installation and operating instructions. Solar charge controller MPPT 10 A / 20 A Z Z

Installation and operating instructions. Solar charge controller MPPT 10 A / 20 A Z Z Installation and operating instructions Solar charge controller MPPT 10 A / 20 A EN 1 Contents 1. About these instructions... 3 1.1 Applicability... 3 1.2 Users... 3 1.3 Description of symbols... 3 2.

More information

Pre-lab Questions: Please review chapters 19 and 20 of your textbook

Pre-lab Questions: Please review chapters 19 and 20 of your textbook Introduction Magnetism and electricity are closely related. Moving charges make magnetic fields. Wires carrying electrical current in a part of space where there is a magnetic field experience a force.

More information

Nanometrics Solar Power System

Nanometrics Solar Power System Nanometrics Solar Power System Installation Guide Nanometrics Inc. Kanata, Ontario Canada 2003 Nanometrics Inc. All Rights Reserved. Installation Guide The information in this document has been carefully

More information

SOLAR CHARGE CONTROLLER

SOLAR CHARGE CONTROLLER SOLAR CHARGE CONTROLLER SCE 1010 / SCE 1515 / SCE 2020 / SCE 3030 Instruction Manual Please read user manual carefully before use. 1.About this manual These operating instructions are part of the product.

More information

Ohm s Law. 1-Introduction: General Physics Laboratory (PHY119) Basic Electrical Concepts:

Ohm s Law. 1-Introduction: General Physics Laboratory (PHY119) Basic Electrical Concepts: Ohm s Law General Physics Laboratory (PHY119) 1-Introduction: Basic Electrical Concepts: 1- Current (I): Is the flow of electrons through a conductor or semiconductor. For current to flow, it requires

More information

Equivalent Meter Resistance

Equivalent Meter Resistance Equivalent Meter Resistance This installation of N.E.R.D discusses meter resistance. The equipment referenced here is found in the Undergraduate Electronics Lab at the University of Houston. Topics covered

More information

A Study of Lead-Acid Battery Efficiency Near Top-of-Charge and the Impact on PV System Design

A Study of Lead-Acid Battery Efficiency Near Top-of-Charge and the Impact on PV System Design A Study of Lead-Acid Battery Efficiency Near Top-of-Charge and the Impact on PV System Design John W. Stevens and Garth P. Corey Sandia National Laboratories, Photovoltaic System Applications Department

More information

Implementation Notes. Solar Group

Implementation Notes. Solar Group Implementation Notes Solar Group The Solar Array Hardware The solar array is made up of 42 panels each rated at 0.5V and 125mA in noon sunlight. Each individual cell contains a solder strip on the top

More information

Series and Parallel Networks

Series and Parallel Networks Series and Parallel Networks Department of Physics & Astronomy Texas Christian University, Fort Worth, TX January 17, 2014 1 Introduction In this experiment you will examine the brightness of light bulbs

More information

STARTING SYSTEMS 8B - 1 STARTING SYSTEMS CONTENTS

STARTING SYSTEMS 8B - 1 STARTING SYSTEMS CONTENTS TJ STARTING SYSTEMS 8B - 1 STARTING SYSTEMS CONTENTS page DESCRIPTION AND OPERATION STARTER MOTOR... 2 STARTER RELAY... 3 STARTING SYSTEM... 1 DIAGNOSIS AND TESTING STARTER MOTOR... 8 STARTER MOTOR NOISE

More information

Data Sheet for Series and Parallel Circuits Name: Partner s Name: Date: Period/Block:

Data Sheet for Series and Parallel Circuits Name: Partner s Name: Date: Period/Block: Data Sheet for Series and Parallel Circuits Name: Partner s Name: Date: _ Period/Block: _ Build the two circuits below using two AAA or AA cells. Measure and record Voltage (Volts), Current (A), and Resistance

More information

UPS-ST12xx UPSPro Backup Power System

UPS-ST12xx UPSPro Backup Power System UPS-ST12xx UPSPro Backup Power System Wireless Base Stations Surveillance Cameras Lighting Applications Up to 30W loads Congratulations! on your purchase of the UPSPro outdoor backup power system. Please

More information

Phoenix User Guide V2.0

Phoenix User Guide V2.0 Phoenix User Guide V2.0 AC Charge Cord MC4 to 4.5mm DC IN Cord CIG to 4.5mm DC IN Cord 5.5mm DC to 4.5mm DC IN Cord 5.5mm DC to Light Bulb Socket Be sure to charge your Phoenix to 100% before operating.

More information

Electric Circuits. Lab. FCJJ 16 - Solar Hydrogen Science Kit. Next Generation Science Standards. Initial Prep Time. Lesson Time. Assembly Requirements

Electric Circuits. Lab. FCJJ 16 - Solar Hydrogen Science Kit. Next Generation Science Standards. Initial Prep Time. Lesson Time. Assembly Requirements Next Generation Science Standards NGSS Science and Engineering Practices: Asking questions and defining problems Developing and using models Planning and carrying out investigations Analyzing and interpreting

More information

Spectron Industrial Series

Spectron Industrial Series 1300650 1300654 1300666 1300754 1300823 1300886 Table B Constant Value per Voltage System Wire Size (Maximum Voltage Drop 5%) System 6 Volt 12 Volt 24 Volt Wire Size #12 #10 #8 #6 #12 #10 #8 #6 #10 #12

More information

How to design and build a solar lunch box

How to design and build a solar lunch box How to design and build a solar lunch box Presented by May 2016 The North Texas Renewable Energy Group () is the North Texas Chapter of the Texas Solar Energy Society. The mission of NTEG to educate North

More information

Installation and User Manual. with RAIN SENSOR.

Installation and User Manual. with RAIN SENSOR. with RAIN SENSOR www.solarsmartopener.com Revision..0 TABLE OF CONTENTS Features In The Box Further Items Required Basic Operation Solar Panel and Operator Installation Operator Installation Solar Panel

More information

Electric Circuits. Lab. FCJJ 16 - Solar Hydrogen Science Kit. Goals. Background

Electric Circuits. Lab. FCJJ 16 - Solar Hydrogen Science Kit. Goals. Background Goals Build a complete circuit with a solar panel Power a motor and electrolyzer with a solar panel Measure voltage and amperage in different circuits Background Electricity has fundamentally changed the

More information

Name: Base your answer to the question on the information below and on your knowledge of physics.

Name: Base your answer to the question on the information below and on your knowledge of physics. Name: Figure 1 Base your answer to the question on the information below and on your knowledge of physics. A student constructed a series circuit consisting of a 12.0-volt battery, a 10.0-ohm lamp, and

More information

TEST REPORT. Test Report for Mating Cycle Validation of Mini Circuits QBL Series Quick-Lock Test Cables.

TEST REPORT. Test Report for Mating Cycle Validation of Mini Circuits QBL Series Quick-Lock Test Cables. TITLE: Test Report for Mating Cycle Validation of Mini Circuits QBL Series Quick-Lock Test Cables. 1. Background & Introduction Mini-Circuits has introduced a QBL Series of test cables is based upon an

More information

General Installation Manual 2007 Sanyo Electric Co., Ltd. All Rights Reserved 6/15/07

General Installation Manual 2007 Sanyo Electric Co., Ltd. All Rights Reserved 6/15/07 General Installation Manual for SANYO HIT Photovoltaic Modules. Please read this manual completely before use or installation of SANYO modules. This manual applies to the following models: HIP-205BA3,

More information

The Traveler Series: Wanderer

The Traveler Series: Wanderer The Traveler Series: Wanderer RENOGY 30A Charge Controller Manual 2775 E. Philadelphia St., Ontario, CA 91761 1-800-330-8678 Version: 2.0 Important Safety Instructions Please save these instructions. This

More information

Write the term that correctly completes the statement. Use each term once. ampere. electric current. resistor battery.

Write the term that correctly completes the statement. Use each term once. ampere. electric current. resistor battery. Date Period Name CHAPTER 22 Study Guide Current Electricity Vocabulary Review Write the term that correctly completes the statement. Use each term once. ampere electric current resistor battery kilowatt-hour

More information

Academic Year

Academic Year EXCELLENCE INTERNATIONAL SCHOOL First Term, Work sheet (1) Grade (9) Academic Year 2014-2015 Subject: quantities Topics:- Static electricity - Eelectrical NAME: DATE: MULTIPLE CHOICE QUESTIONS: 1 - A circuit

More information

Owner s Manual. Contents GP-PWM-10-SQ

Owner s Manual. Contents GP-PWM-10-SQ Owner s Manual Contents 1.0 Installation Overview... 2 2.0 Warnings... 2 3.0 Choosing a Location... 3 4.0 Installation Instructions... 3 5.0 Operating Instructions... 4 6.0 Frequently Asked Questions (FAQs)...

More information

Eclipse Solar Suitcase

Eclipse Solar Suitcase Eclipse Solar Suitcase Renogy 100W 200W 2775 E. Philadelphia St., Ontario, CA 91761 1-800-330-8678 Version 1.0 Important Safety Instructions Please save these instructions. This manual contains important

More information

Circuits-Circuit Analysis

Circuits-Circuit Analysis Base your answers to questions 1 through 3 on the information and diagram below. 4. A 9-volt battery is connected to a 4-ohm resistor and a 5-ohm resistor as shown in the diagram below. A 3.0-ohm resistor,

More information

HOW TO MAKE YOUR OWN BATTERIES

HOW TO MAKE YOUR OWN BATTERIES HOW TO MAKE YOUR OWN BATTERIES 1 Page TABLE OF CONTENTS Introduction....3 Usage....4 Aluminum Can Batteries/Cells....8 A Long Lasting, Yet Powerful Battery....10 PVC Pipe Batteries...13 Lab Notes....17

More information

SCOUT & NAVIGATOR Class Safety Inspection Sheet Tutorial

SCOUT & NAVIGATOR Class Safety Inspection Sheet Tutorial DOC-001: Companies must provide a system interconnection diagram (SID) of their vehicle control system. An SID is an electrical diagram of their wiring, including their control box, motors, and any other

More information

PWM Charge Controller with LCD Display 30A. User Manual

PWM Charge Controller with LCD Display 30A. User Manual PWM Charge Controller with LCD Display 30A User Manual 1 Product Features 1. 12V/ 24 V system voltages are automatically recognized. 2. Charging program options for sealed, GEL and flooded lead-acid batteries

More information

M T E C o r p o r a t i o n. dv/dt Filter. Series A VAC USER MANUAL PART NO. INSTR REL MTE Corporation

M T E C o r p o r a t i o n. dv/dt Filter. Series A VAC USER MANUAL PART NO. INSTR REL MTE Corporation M T E C o r p o r a t i o n dv/dt Filter Series A 440-600 VAC USER MANUAL PART NO. INSTR - 019 REL. 041119 2004 MTE Corporation IMPORTANT USER INFORMATION NOTICE The MTE Corporation dv/dt Filter is designed

More information

Instruction of Solar Charge Controller. User s Manual

Instruction of Solar Charge Controller. User s Manual Instruction of Solar Charge Controller User s Manual 12V/24V 30A Dear Users: Thank you for selecting our product. Please read this manual carefully before you use this product. The controller is for off-grid

More information

The transducer head needs to be placed in such a manner that as much of the water surface as possible comes into direct contact with the sound waves.

The transducer head needs to be placed in such a manner that as much of the water surface as possible comes into direct contact with the sound waves. STEP 1: Determine the optimal location of the transducer within the water body. The transducer transforms the electrical signals produced by the control panel into ultrasonic sound signals. These signals

More information

Electricity and Magnetism Module 2 Student Guide

Electricity and Magnetism Module 2 Student Guide Concepts of this Module Introducing current and voltage Simple circuits Circuit diagrams Background Electricity and Magnetism Module 2 Student Guide When water flows through a garden hose, we can characterize

More information

SL12 SL12 SOLAR LED STREET / PARKING LOT LIGHT 10W,15W, 20W, 25W LED Lamp & Complete Solar Sytem

SL12 SL12 SOLAR LED STREET / PARKING LOT LIGHT 10W,15W, 20W, 25W LED Lamp & Complete Solar Sytem Modular design allows for longer life and greater efficiency. Philips LUMILEDS LUXEON T Up to 142 lm/w efficiency. Sold as a complete lighting system with all components necessary for a typical installation.

More information

XLR Energy Storage Module

XLR Energy Storage Module Technical Note 19 XLR Energy Storage Module XLR Energy Storage Module Safety The XLR 48 V module contains stored energy of 54 watt-hours and can discharge up to 97 amps if short circuited. Only personnel

More information

LP Portable Wind Power Generation Kit

LP Portable Wind Power Generation Kit LP-2025 Portable Wind Power Generation Kit 1. Introduction: The wind generator, electrical storage devices, wind-and-solar complement charge controller and output system are all in the suitcase. The blade

More information

Installation and operating instructions. Solar charge controller 10 A / 15 A / 0 A / 30 A PHOTOVOLTAIK - PHOTOVOLTAICS - PHOTOVOLTAIQUE - FOTOVOLTAICA

Installation and operating instructions. Solar charge controller 10 A / 15 A / 0 A / 30 A PHOTOVOLTAIK - PHOTOVOLTAICS - PHOTOVOLTAIQUE - FOTOVOLTAICA PHOTOVOLTAIK - PHOTOVOLTAICS - PHOTOVOLTAIQUE - FOTOVOLTAICA Installation and operating instructions Solar charge controller 10 A / 15 A / 0 A / 30 A EN 74.86 08.4 1. About this manual These operating

More information

Installation and Operating Instructions. Solar System Controller ISC3030

Installation and Operating Instructions. Solar System Controller ISC3030 Installation and Operating Instructions Solar System Controller ISC3030 ABOUT THIS MANUAL These operating instructions come with the product and should be kept with it as a reference to all user s of the

More information

W ECO RIGID-SKID ARROW BOARDS

W ECO RIGID-SKID ARROW BOARDS WSD-1014 7 2018 W ECO RIGID-SKID ARROW BOARDS MODEL WS1S PRODUCT SPECIFICATIONS JULY 2018 W ECO Rigid- Skid Arrow Boards Page 2 of 13 1. DESCRIPTION 1.1. Description Arrow boards direct traffic by flashing

More information

Instruction of Solar Charge Controller. User s Manual

Instruction of Solar Charge Controller. User s Manual Instruction of Solar Charge Controller User s Manual 12V/24V 10A/20A Dear Users: Thank you for selecting our product. Please read this manual carefully before you use this product. 0 The controller is

More information

Owner s Manual. Contents GP-PWM-30-SQ GP-PWM-30-SQ

Owner s Manual. Contents GP-PWM-30-SQ GP-PWM-30-SQ Owner s Manual Contents 1.0 Installation Overview... 2 2.0 Warnings... 2 3.0 Choosing a Location...3 4.0 Installation Instructions... 3 5.0 Operating Instructions...4 6.0 Frequently Asked Questions (FAQs)...6

More information

Hillstone PowerBank HPB54 Series ( 400A 700A )

Hillstone PowerBank HPB54 Series ( 400A 700A ) Technical data Sheet Hillstone PowerBank HPB54 Series ( 400A 700A ) Ref. HPB54-400-700 Page 1 of 6 Features Electronic variable control Manual constant current Full current control range Digital ammeter

More information

A S S E M B L Y G U I D E

A S S E M B L Y G U I D E MODEL SOLAR ELECTRIC POWER BOAT PLUGGING into the sun DRAFT COPY ONLY - SEND US YOUR COMMENTS A S S E M B L Y G U I D E Two flexible solar cells turn sunlight into electricity that flows through the solar

More information

Lab 4. DC Circuits II

Lab 4. DC Circuits II Physics 2020, Spring 2005 Lab 4 page 1 of 7 Lab 4. DC Circuits II INTRODUCTION: This week we will continue with DC circuits, but now with an emphasis on current rather than voltage. Of course, in order

More information

Chapter 2. Battery Charger and Base Assembly

Chapter 2. Battery Charger and Base Assembly Chapter 2 Battery Charger and Base Assembly 11 CHAPTER 2. BATTERY CHARGER AND BASE ASSEMBLY 2.1 Section Overview This Lab teaches students how to assemble a Tekbot, in the following steps: Describe the

More information

EXPERIMENT - 1 OHM S LAW

EXPERIMENT - 1 OHM S LAW NOTE: While you copy the practical record see that you are following the note. Write Aim, theory, materials required, procedure, results, discussion and precautions on the right side of your record. While

More information

BOOK LIGHT MUSIC STAND LIGHT USER S MANUAL

BOOK LIGHT MUSIC STAND LIGHT USER S MANUAL BOOK LIGHT MUSIC STAND LIGHT USER S MANUAL Version 4.0 September 2018. https://ecologicmart.com Page 1 Table of Contents Introduction... 3 How to Use the lamp... 4 Charging Process... 4 Turning On and

More information

SL37 SL37 SOLAR LED STREET / PARKING LOT LIGHT 35W or 65W LED Double Lamp & Complete Solar Sytem

SL37 SL37 SOLAR LED STREET / PARKING LOT LIGHT 35W or 65W LED Double Lamp & Complete Solar Sytem Modular design allows for longer life and greater efficiency. Philips LUMILEDS LUXEON T Up to 142 lm/w efficiency. Supplied Without Pole Sold as a complete lighting system with all components necessary

More information

LABORATORY 2 MEASUREMENTS IN RESISTIVE NETWORKS AND CIRCUIT LAWS

LABORATORY 2 MEASUREMENTS IN RESISTIVE NETWORKS AND CIRCUIT LAWS LABORATORY 2 MEASUREMENTS IN RESISTIVE NETWORKS AND CIRCUIT LAWS The objective of this experiment is to provide working knowledge of the ammeter, voltmeter, and ohmmeter as well as their limitations in

More information

Battery Back-up BBM Owner's Manual. Please read this manual BEFORE installing your inverter

Battery Back-up BBM Owner's Manual. Please read this manual BEFORE installing your inverter Battery Back-up BBM-1225 Owner's Manual Please read this manual BEFORE installing your inverter owner's MAnUAL index section 1 Safety Instructions... 3 section 2 Layout and Dimensions... 4 section 3 Description

More information

Lipo Rider V1.3. The Lipo Rider can be purchased as a separate board or as a kit (Lipo Rider + Lithium Battery + Solar Panel).

Lipo Rider V1.3. The Lipo Rider can be purchased as a separate board or as a kit (Lipo Rider + Lithium Battery + Solar Panel). Lipo Rider V1.3 Power your favourite electronic kit with green energy! The Lipo Rider board allows you ride the solar wave to run your favourite 5V device. The Lipo Rider board is the ideal green power

More information