DEEP FOUNDATION. Improving Reliability of Foundations for Tall Buildings. By : Ir. Chow Chee Meng Date: th March 2014

Size: px
Start display at page:

Download "DEEP FOUNDATION. Improving Reliability of Foundations for Tall Buildings. By : Ir. Chow Chee Meng Date: th March 2014"

Transcription

1 DEEP FOUNDATION Improving Reliability of Foundations for Tall Buildings By : Ir. Chow Chee Meng Date: th March 2014 G&P Geotechnics Sdn Bhd (

2 VIRTUALLY EVERY STRUCTURE IS SUPPORTED BY SOIL OR ROCK. THOSE THAT AREN T EITHER FLY, FLOAT, OR FALLOVER -RICHARD L. HANDY-

3

4

5 REACHING FOR THE SKY

6

7

8

9 DEEP FOUNDATION

10 WHAT IS A DEEP FOUNDATION It is a foundation system that transfers loads to a deeper and competent soil layer. To support: Axial compression load Uplift/tension Lateral load Traditional function of piles for high-rise Marine structures, slender structures, etc. Reduce overall settlement / differential settlement

11 DEEP FOUNDATION FOR HIGH-RISE Deep foundation for high-rise: Bored piles Barrette piles Caisson piles Driven piles Jack-in spun piles Micropiles, etc. Traditionally used for high-rise

12 DEEP FOUNDATION FOR HIGH-RISE Design aspects for conventional bored piles, caisson, etc. normally covered in various seminar/conferences Focuses on relatively new or innovative design approach for optimum foundation design

13 DESIGN CONSIDERATIONS

14 Allowable Settlement of Building Settlement of high-rise building < 12mm or 25mm? Myth or fact?

15

16 Actual Building Settlement Actual recorded settlement of high-rise building 20mm to 125mm Important design considerations NOT total settlement Differential settlement governs

17 Definitions of foundation movement

18

19

20 Not designed by Author or G&P SHIFT??????????? Ground Conditions? Limestone

21 PILED RAFT FOUNDATION Using conventional approach where part of the superstructure load is transferred to the slab/pilecap in contact with the ground At least 25% to 40% reduction of numbers of piles depending on soil conditions

22 DESIGN METHODOLOGY Relatively higher loads imposed onto foundation Piles of varying length Longest piles in the middle and progressively shorter piles towards the edge Strip-raft structural system

23 Strip-raft Piles with varying length SCHEMATIC OF PILED RAFT SYSTEM WITH VARYING PILE LENGTHS

24 ANALYSIS Interaction between pile-soilstructure important Iterative analysis using pile interaction software (e.g. PIGLET, PIGEON) and structural analysis software (e.g. SAFE)

25 ANALYSIS Interaction of piles based on modified solution of Randolph & Wroth (1979) incorporated in the software, PIGEON

26 PILED RAFT FOUNDATION Settlement reducing piles/full piled raft Piles introduced to control settlement Piles required may be as little as 10% of conventional pile design Refer to publications by Randolph, Poulos, Katzenbach, etc.

27 DESIGN METHODOLOGY Settlement reducing piles at concentrated loads (i.e. columns and walls): Condition 1: Moment in structural member Condition 2: Shear in structural member Condition 3: Contact pressure below foundation Condition 4: Local settlement Mainly governed by structural design

28 DESIGN METHODOLOGY Settlement reducing piles To control differential settlement Overall bearing capacity sufficient Smoothened settlement profile Column Loads Settlement reducing piles Large local settlement

29 CASE HISTORIES

30 MEDIUM RISE BUILDINGS 200mm x 200mm reinforced concrete (RC) square piles with pile length varying from 18m to 24m 350mm x 700mm strips and 300mm thick raft

31 Foundation Design for 5-Storey Low Cost Apartment

32 SETTLEMENT MONITORING Total of 14 numbers of precise settlement markers Monitored results up to 313 days CSM02 CSM05 CSM10 CSM1 4 CSM01 CSM04 CSM06 CSM07 CSM09 CSM11 CSM13 CSM03 Legend: CSM Settlement markers (14 Nos.) CSM08 CSM12

33 Settlement (mm) Settlement Profile Across Edge of Building CSM02 = 1/ Distance (m) CSM05 = 1/13950 Centreline = 1/17595 Maximum differential settlement: 27mm CSM10 Maximum local angular distortion: 1/1215 CSM14 = 1/

34 COMPLETED APARTMENT TAN, Y.C., CHOW, C.M. & GUE, S.S. (2005). Piled raft with different pile length for medium-rise buildings on very soft clay, 16 th ICSMGE, September 12-16, 2005, Osaka, Japan.

35 2500 Ton Silo on Very Soft Marine Deposits

36 Foundations for Highrise Bistari Condominiums, KL. Alternative design has reduced the foundation cost by more than 50%, A saving of more than RM5 million An Award of Merit (1998) was given by ACEM

37 Concrete Raft Fill / Alluvium

38

39 JACK-IN PILES ONLY FOR LOW- RISE BUILDINGS?

40 HIGH-CAPACITY JACK-IN PILES Myth: Jack-in piles cannot be used for high-rise buildings or in limestone formation Truth: Jack-in piles can be used for high-rise buildings and limestone formation - With proper design and input from experienced geotechnical engineer

41 BEHAVIOUR OF JACK-IN PILES G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

42 BEHAVIOUR OF JACK-IN PILES Rankine Lecture by Prof. Mark Randolph (2003): Bored piles zero residual pressures End-bearing can only be mobilised at relatively large displacement G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

43 BEHAVIOUR OF JACK-IN PILES Driven and jacked in piles - significant residual pressures are locked in at the pile base during installation Higher end-bearing can be mobilised at working load G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

44 BEHAVIOUR OF JACK-IN PILES White & Lehane (2004): Greater number of cycles during pile installation larger reduction in shaft friction G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

45 White & Lehane, 2004 Reduction in shaft resistance!!! G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

46 BEHAVIOUR OF JACK-IN PILES Deeks, White & Bolton (2005): The measured jacking force during installation indicates plunging capacity of the pile G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

47 BEHAVIOUR OF JACK-IN PILES Jacked piles have a high base stiffness Stiffness of jacked piles > 2 times stiffness of driven piles > 10 times stiffness of bored piles G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

48 CASE HISTORIES

49 1 st Site Starting of Jack-In Pile system using large size pile in Malaysia (Year 1999) Installed through municipal dumping site with mine tailings overlying Karstic Kuala Lumpur Limestone bedrock. Use 450mm Spun Pile with Working Load of 1500kN G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

50 1 st Site G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

51 1 st Site G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

52 1 st Site G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

53 Case Histories Four sites in Kuala Lumpur and Selangor, Malaysia : Site A: 31-storey apartment Site B: 45-storey apartment Site C: 40 to 43-storey apartment Site D: 15-storey apartment G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

54 Case Histories (Sites A to D) Pile size: 400mm to 600mm Pile working load: 1520kN to 3000kN All piles generally jacked to 2.0 times working load with holding time of 30- seconds (2 cycles) G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

55 Case Histories (Sites A to D) Silty SAND / sandy SILT overlying Granite Formation (weathered granite) Boulders encountered - Some piles installed after preboring G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

56 Site A Granite Formation G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

57 Site B G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

58 Site B Pile toe at hard weathered granite layer G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

59 Static Load Tests Total of 22 static load tests carried out for the 4 sites All piles selected for testing achieved minimum 2 times working load!!! (No pile failed!) No signs of plunging failure of pile Settlement at working load: mm Settlement at 2*WL: mm G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

60 Static Load Tests Pile as short as 6.5m tested with settlement at working load and 2*WL of 8.32mm and 19.73mm respectively Pile performance are satisfactory for piles where preboring have been carried out Termination criterion adopted adequate G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

61 Preboring through boulders Boulders exposed after preboring G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

62 APPLIED LOAD (kn) Static Load Tests 500mm Spun Pile, Pile length = 6.5m PILE TOP SETTLEMENT (mm) G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd Site B

63 Static Load Tests Site B G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

64 Static Load Tests G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

65 Termination Criteria Termination criterion for jack-in piles in weathered granite: Jack the pile to 2.0 times of the design load for a minimum of two cycles. The corresponding pressure has to be held for minimum 30 seconds with settlement not exceeding 2mm G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

66 Mobilised Resistance Instrumented test piles Site C (3 Nos.) Site D (2 Nos.) Piles instrumented using the Global Strain Extensometer method G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

67 MOBILISED SKIN FRICTION (kn/m 2 ) Mobilised (Shaft) Resistance 600mm Spun Pile, Pile length = 21.4m (Nearest borehole, BH-20) 0.5m to 10.7m 10.7m to 20.9m Site C) DISPLACEMENT (mm) G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

68 MOBILISED END-BEARING RESISTANCE (kn/m 2 ) Mobilised (Base) Resistance mm Spun Pile, Pile length = 21.4m (Nearest borehole, BH-20) End-bearing not fully mobilised DISPLACEMENT (mm) G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

69 SUMMARY Traditional correlations of skin friction based on driven piles (e.g. fs = 2.5*SPT-N) is too conservative for jack-in piles in weathered granite Conservative estimate based on test results: - Ultimate skin friction, f s ~ 5*SPT-N G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

70 SUMMARY Jack-in piles demonstrates higher skin friction possibly due to: - Less disturbance during installation - friction fatigue phenomenon (e.g. White & Lehane, 2004) - Locked-in pressure (residual pressure) effect (e.g. Randolph, 2003) G&P Geotechnics Sdn Bhd ( G&P Geotechnics Sdn Bhd

71 References Tan, Yean-Chin, Chow, Chee-Meng & Gue, See-Sew (2011). Jack-in Pile in Malaysia: A Malaysian Consultant s Perspective, Proceedings of the 2 nd VLA Seminar: New Developments in Jacked Piling, Hong Kong, 18 th March 2011 C.M. CHOW & Y.C. TAN (2010). Performance of Jack-in Pile Foundation in Weathered Granite, 17 th SEAGC, May, Taipei, Taiwan. CHOW, C.M. & TAN, Y.C. (2009). Jack-in Pile Design Malaysian Experience and Design Approach to EC7, IEM Course on Eurocode 7 Geotechnical Design, July 2009, Petaling Jaya, Selangor.

72 HIGH-CAPACITY JACK-IN PILES Myth: Jack-in piles cannot be used for high-rise buildings or in limestone formation Truth: Jack-in piles can be used for high-rise buildings and limestone formation - With proper design and input from experienced geotechnical engineer

73

74

75

76 SOME UNIQUE PROBLEMS

77 Testing Set-up Using Reaction Piles G&P Geotechnics Sdn Bhd (

78 Testing Set-up Long reaction piles at close spacing used Case histories: Load tests using reaction piles give ERRATIC results Reference: Weele (1993)

79 Ref: A.F. van Weele, 1993 Tested using anchor piles 1100kN 2100kN Tested using kentledge Approx. 2 times smaller using reaction piles!

80 Reaction piles Zone of interaction with test pile Test pile

81 Testing Set-up Latest version of ASTM D1143 Published April 2007

82 Testing Set-up ASTM D1143 Normal kentledge 3 times Clear distance of at least 5 times the maximum diameter Caution on factors influencing results: Possible interaction.from anchor piles..

83 Settlement Criteria for Pile Load Test G&P Geotechnics Sdn Bhd (

84 MALAYSIA S PRACTICE A pile tested shall be deemed to have failed if (JKR, 1988): The residual settlement after removal of the test load exceeds 6.50mm; or The total settlement under the Working Load exceeds 12.50mm; or The total settlement under twice the Working Load exceeds 38.0mm, or 10% of pile diameter/width whichever is the lower value.

85 MALAYSIA S PRACTICE No consideration given to pile length and pile size in setting the settlement criteria Too conservative especially for long piles and big diameter piles

86 Pile shaft shortening (after Ng et al., 2001)

87 SETTLEMENT CRITERIA Settlement criteria for pile testing must take into account Elastic compression of pile which is a function of pile length and pile diameter Movement expected to mobilise shaft friction and end-bearing

88

89 SETTLEMENT CRITERIA Proposed settlement criteria for bored piles: For piles founded in soils: M = 12.50mm + ½ PL/AE For piles founded on rocks and/or with short rock sockets and for piles with slip liners: M = 12.50mm + ¾ PL/AE To be adjusted for other specific structural considerations!

90 SETTLEMENT CRITERIA Typically, differential settlement between any two piled foundations unlikely to be greater than 75% of the maximum settlement (Craig, 1998) Typical medium-rise to high-rise building column span = 5.0m to 8.5m Assuming 25m long, 1.2m diameter rock-socketed bored pile with working load = 9800kN Maximum differential settlement = 0.75*18.5mm = 14mm Distortions = 1/350 to 1/600 (Within allowable limits to prevent cracking in walls and partitions and well within the limits for structural damage of 1/150 Skempton & McDonald, 1956) Criteria can be adjusted for specific spans based on fundamental engineering principles!

91 SUMMARY

92 SUMMARY Recent advances and understanding in pile behaviour has improved reliability of foundations for tall buildings Relatively new / innovative design approach: Piled raft/settlement reducing piles High-capacity jack-in spun piles Research findings removed unnecessary conservatism or unsafe design practices, e.g. unrealistic settlement criteria, etc.

93 ON A FINAL NOTE With regard to geotechnical engineering: There are no (insurmountable) weak soils or rocks, there are only weak engineers. Professor Heinz Brandl Vice-President ISSMGE ( )

Terminology, Shaft Comparison & General Discussion

Terminology, Shaft Comparison & General Discussion Helical Foundation Systems: Topics We Will Cover Considerations for the Design and Installation of Helical Pile Foundations Presented by: Kyle Olson, PE Senior Structural Engineer Foundation Supportworks,

More information

Economics of Driven Pile Foundations

Economics of Driven Pile Foundations Economics of Driven Pile Foundations 2013 PDCA Professors Driven Pile Institute ( PDPI ) June 24-28, 2013 Van E. Komurka, P.E., D.GE, F.ASCE Wagner Komurka Geotechnical Group, Inc. 1 Talk Outline Define

More information

A Technique for Selecting Appropriate Allowable Pile Loads for Driven-Pile Projects: Load Matching

A Technique for Selecting Appropriate Allowable Pile Loads for Driven-Pile Projects: Load Matching A Technique for Selecting Appropriate Allowable Pile Loads for Driven-Pile Projects: Load Matching Pile Driving Contractors Association 2015 Professor s Driven Pile Institute June 25, 2015 Van E. Komurka,

More information

345. Fellenius, B.H., Plugging effect of opentoe pipe piles in sandy soil. Discussion. Canadian Geotechnical Journal 52(5):

345. Fellenius, B.H., Plugging effect of opentoe pipe piles in sandy soil. Discussion. Canadian Geotechnical Journal 52(5): 345. Fellenius, B.H., 215. Plugging effect of opentoe pipe piles in sandy soil. Discussion. Canadian Geotechnical Journal 52(5): 664-667.. Fellenius 215 [Canadian Geotechnical Journal 52(5) 664-667] Plugging

More information

The FRACOF Composite Slab Test

The FRACOF Composite Slab Test The FRACOF Composite Slab Test Experiment, Predictions & Results Anthony Abu & Ian Burgess Fire Resistance Assessment of partially protected COmposite Floors - FRACOF Introduction To increase the use of

More information

Overburden drilling catalogue

Overburden drilling catalogue Atlas Copco Ground Engineering Products Overburden catalogue Symmetrix overburden systems Overburden Drilling Catalogue Atlas Copco Overburden Drilling System... 3 The Symmetrix System... 4 Drilling overburden...

More information

7. PRELIMINARY DESIGN OF A SINGLE AISLE MEDIUM RANGE AIRCRAFT

7. PRELIMINARY DESIGN OF A SINGLE AISLE MEDIUM RANGE AIRCRAFT 7. PRELIMINARY DESIGN OF A SINGLE AISLE MEDIUM RANGE AIRCRAFT Students: R.M. Bosma, T. Desmet, I.D. Dountchev, S. Halim, M. Janssen, A.G. Nammensma, M.F.A.L.M. Rommens, P.J.W. Saat, G. van der Wolf Project

More information

GOPALAN COLLEGE OF ENGINEERING AND MANAGEMENT Department of Civil Engineering COURSE PLAN

GOPALAN COLLEGE OF ENGINEERING AND MANAGEMENT Department of Civil Engineering COURSE PLAN Appendix - C GOPALAN COLLEGE OF ENGINEERING AND MANAGEMENT Department of Civil Engineering Academic Year: 2016-17 Semester: EVEN COURSE PLAN Semester: VI Subject Code& Name: 10CV64 & Geotechnical Engineering-II

More information

Evaluation of Pile Setup using Dynamic Restrike Analysis in Alabama Soils

Evaluation of Pile Setup using Dynamic Restrike Analysis in Alabama Soils 45 th STGEC - Mobile, AL Oct. 29, 2014 CE Pile 360 Setup Spring AL 13 Evaluation of Pile Setup using Dynamic Restrike Analysis in Alabama Soils Eric Steward, Ph.D. Assistant Professor University of South

More information

Latest Advancements in DrillString Mechanics

Latest Advancements in DrillString Mechanics Services, Trainings, Softwares Latest Advancements in DrillString Mechanics SPE Gulf Coast Section 03/09/2016 Stephane Menand, Ph.D. stephane.menand@drillscan.com 1 DrillScan Intro Directional Drilling

More information

Opportunities and Challenges for the. Friday September 24,

Opportunities and Challenges for the. Friday September 24, LRFD Facts and Misconceptions: Opportunities and Challenges for the Micropile il Community Friday September 24, 2010 By Jerry A. DiMaggio, PE, M.ASCE Email: jdimaggio2@verizon.net Email: jdimaggio@nas.edu

More information

Build-A-Box. Modular Trench Shielding System. Tabulated Data Effective January 4, Revised: April 21, with CHANGE THREE

Build-A-Box. Modular Trench Shielding System. Tabulated Data Effective January 4, Revised: April 21, with CHANGE THREE Build-A-Box AMERICA S TRENCH BOX BUILDER Modular Trench Shielding System EFFICIENCY PRODUCTION, INC. Build-A-Box Tabulated Data Tabulated Data Effective January 4, 2010 Revised: April 21, 2015 - with CHANGE

More information

TITLE: EVALUATING SHEAR FORCES ALONG HIGHWAY BRIDGES DUE TO TRUCKS, USING INFLUENCE LINES

TITLE: EVALUATING SHEAR FORCES ALONG HIGHWAY BRIDGES DUE TO TRUCKS, USING INFLUENCE LINES EGS 2310 Engineering Analysis Statics Mock Term Project Report TITLE: EVALUATING SHEAR FORCES ALONG HIGHWAY RIDGES DUE TO TRUCKS, USING INFLUENCE LINES y Kwabena Ofosu Introduction The impact of trucks

More information

Pipe Strut vs. Laced Strut

Pipe Strut vs. Laced Strut Pipe Strut vs. Laced Strut Chiew Sing-Ping School of Civil and Environmental Engineering NANYANG TECHNOLOGICAL UNIVERSITY 9 July 2015 Pipe Strut vs. Laced Strut Pipe Strut Laced Strut 2 PLAXIS Soil-Structure

More information

PASSING ABILITY OF SCC IMPROVED METHOD BASED ON THE P-RING

PASSING ABILITY OF SCC IMPROVED METHOD BASED ON THE P-RING PASSING ABILITY OF SCC IMPROVED METHOD BASED ON THE P-RING K D Chan*, Leppo Concrete Sdn Bhd, Malaysia K C G Ong, National University of Singapore, Singapore C T Tam, National University of Singapore,

More information

Build-A-Box Modular Trench Shielding System

Build-A-Box Modular Trench Shielding System AMERICA S TRENCH BOX BUILDER Build-A-Box Modular Trench Shielding System EFFICIENCY PRODUCTION Build-A-Box Tabulated Data Tabulated Data Effective January 4, 2010 Revised: January 4, 2018 - with CHANGE

More information

0 Issued for Information SHS 10/06/16 JAL 10/10/16 JCP 10/10/16

0 Issued for Information SHS 10/06/16 JAL 10/10/16 JCP 10/10/16 Project/Plant: Unit(s): Plant Gorgas Gypsum Pond Units 6-7 Title/Subject: Slope Stability Analysis of Plant Gorgas Gypsum Pond Dam Purpose/Objective: Analyze slope stability of the Plant Gorgas Gypsum

More information

Lateral Resistance Characteristics of Sleepers in Railway Ballasted Tracks from Laboratory Model Tests

Lateral Resistance Characteristics of Sleepers in Railway Ballasted Tracks from Laboratory Model Tests 1st China Japan Mini Workshop Lateral Resistance Characteristics of Sleepers in Railway Ballasted Tracks from Laboratory Model Tests Kimitoshi Hayano (Yokohama National University) Contents 1) Effects

More information

Motorcycle ATV Braking Data Analysis. Progress Report

Motorcycle ATV Braking Data Analysis. Progress Report Motorcycle ATV Braking Data Analysis Progress Report Mark D. Osborne And Russ G. Alger Keweenaw Research Center Houghton, MI 49931 February 14 TABLE OF CONTENTS Page 1. INTRODUCTION... 1 2. MOTORCYCLE

More information

Eurocode Compliant. supplement. groundworks technical reference section 4: double acting hydraulic braces. supershaft plus technical details

Eurocode Compliant. supplement. groundworks technical reference section 4: double acting hydraulic braces. supershaft plus technical details groundworks technical reference section 4 : double acting hydraulic braces supplement supershaft plus technical details Page 1 Eurocode Compliant Issue 1 supershaft plus (SSP) 1. Introduction Supershaft

More information

Propeller Blade Bearings for Aircraft Open Rotor Engine

Propeller Blade Bearings for Aircraft Open Rotor Engine NTN TECHNICAL REVIEW No.84(2016) [ New Product ] Guillaume LEFORT* The Propeller Blade Bearings for Open Rotor Engine SAGE2 were developed by NTN-SNR in the frame of the Clean Sky aerospace programme.

More information

SETTLEMENT AGREEMENT BETWEEN D.J. DESIGN SUPPLIERS SDN. BHD., SOLID PROMENADE SDN. BHD. AND IKHMAS JAYA SDN. BHD., A WHOLLY OWNED SUBSIDIARY OF IJGB

SETTLEMENT AGREEMENT BETWEEN D.J. DESIGN SUPPLIERS SDN. BHD., SOLID PROMENADE SDN. BHD. AND IKHMAS JAYA SDN. BHD., A WHOLLY OWNED SUBSIDIARY OF IJGB IKHMAS JAYA GROUP BERHAD ( IJGB OR THE COMPANY ) SETTLEMENT AGREEMENT BETWEEN D.J. DESIGN SUPPLIERS SDN. BHD., SOLID PROMENADE SDN. BHD. AND IKHMAS JAYA SDN. BHD., A WHOLLY OWNED SUBSIDIARY OF IJGB 1.

More information

11 Annual Report 2013 OPERATIONS REVIEW

11 Annual Report 2013 OPERATIONS REVIEW 11 Annual Report 2013 REVIEW Construction and Project Management Division For the financial year under review, total revenue from the Construction and Project Management division improved to RM194.8 million

More information

Low-torque Deep-groove Ball Bearings for Transmissions

Low-torque Deep-groove Ball Bearings for Transmissions New Product Low-torque Deep-groove Ball Bearings for Transmissions Katsuaki SASAKI To achieve low fuel consumption in response to environmental concerns, we have focused on reducing the friction of tapered

More information

8. The backhoe or Dipper dredger

8. The backhoe or Dipper dredger 8. The backhoe or Dipper dredger Figure 8. 1 BHD IJZEREN HEIN, 8. The backhoe or Dipper dredger...1 8.1. General considerations...1 8.2. Working method...2 8.3. Area of application...4 8.4. Main Layout...5

More information

MAIN SHAFT SUPPORT FOR WIND TURBINE WITH A FIXED AND FLOATING BEARING CONFIGURATION

MAIN SHAFT SUPPORT FOR WIND TURBINE WITH A FIXED AND FLOATING BEARING CONFIGURATION Technical Paper MAIN SHAFT SUPPORT FOR WIND TURBINE WITH A FIXED AND FLOATING BEARING CONFIGURATION Tapered Double Inner Row Bearing Vs. Spherical Roller Bearing On The Fixed Position Laurentiu Ionescu,

More information

First published June 2007 Copyright China Trend Building Press Limited

First published June 2007 Copyright China Trend Building Press Limited First published June 2007 Copyright China Trend Building Press Limited trend@building.com.hk In order to construct the foundations, piers and portal frames for the viaduct, a 1.8 km-long temporary access

More information

Introduction to Remanufacturing

Introduction to Remanufacturing 2012/MAG/WKSP/007 Introduction to Remanufacturing Submitted by: Universiti Teknologi Malaysia (UTM) Workshop on Remanufactured Goods Kuala Lumpur, Malaysia 22-23 October 2012 Introduction to Remanufacturing

More information

Ch# 11. Rolling Contact Bearings 28/06/1438. Rolling Contact Bearings. Bearing specialist consider matters such as

Ch# 11. Rolling Contact Bearings 28/06/1438. Rolling Contact Bearings. Bearing specialist consider matters such as Ch# 11 Rolling Contact Bearings The terms rolling-contact bearings, antifriction bearings, and rolling bearings are all used to describe the class of bearing in which the main load is transferred through

More information

COMPFIRE. Reaction Frame. Camera 3. Macalloy Bars. Camera 2. Link Bar. Support Beam. Oven Bar. Camera 1. Jack Bar.

COMPFIRE. Reaction Frame. Camera 3. Macalloy Bars. Camera 2. Link Bar. Support Beam. Oven Bar. Camera 1. Jack Bar. Reaction Frame Macalloy Bars Camera 3 Support Beam α Oven Bar Camera 2 Link Bar Camera 1 Tested Connection Jack Bar Electrical Furnace Reaction Frame Load Jack 22 September 2010 1 Oven Bar Link Bar View

More information

Pipex px PROTECTION SYSTEMS Pipex px Subsea Cable Protection Systems

Pipex px PROTECTION SYSTEMS Pipex px Subsea Cable Protection Systems Pipex px PROTECTION SYSTEMS Pipex px Subsea Cable Protection Systems (Robust scour zone high visibility Cable Protection Systems (CPS) during deployment) Project Offshore Wind Farm CPS Location United

More information

DESIGN OF MACHINE MEMBERS - I

DESIGN OF MACHINE MEMBERS - I R10 Set No: 1 III B.Tech. I Semester Regular and Supplementary Examinations, December - 2013 DESIGN OF MACHINE MEMBERS - I (Mechanical Engineering) Time: 3 Hours Max Marks: 75 Answer any FIVE Questions

More information

SKF Energy Efficient deep groove ball bearings. Reduced friction for reduced energy use

SKF Energy Efficient deep groove ball bearings. Reduced friction for reduced energy use SKF Energy Efficient deep groove ball bearings Reduced friction for reduced energy use SKF Energy Efficient bearings Engineered to promote sustainability As the need to conserve energy grows more apparent

More information

Innovative pile plugging Musandam Rock Loading Facility

Innovative pile plugging Musandam Rock Loading Facility DGF meeting 2010-02-11: Pile foundation Innovative pile plugging Musandam Rock Loading Facility Jørgen S. Steenfelt COWI A/S, Denmark 1 Innovative pile plugging Outline - introduction Project location

More information

RETRIEVABLE BOREHOLE EXTENSOMETER. Model BOF-EX. Roctest Limited, All rights reserved.

RETRIEVABLE BOREHOLE EXTENSOMETER. Model BOF-EX. Roctest Limited, All rights reserved. INSTRUCTION MANUAL RETRIEVABLE BOREHOLE EXTENSOMETER Model Roctest Limited, 2004. All rights reserved. This product should be installed and operated only by qualified personnel. Its misuse is potentially

More information

In either case, separate tail ropes are looped in the shaft and connected to the bottom of each conveyance or counterweight.

In either case, separate tail ropes are looped in the shaft and connected to the bottom of each conveyance or counterweight. Friction Hoists The friction (or Koepe) hoist is a machine where one or more ropes pass over the drum from one conveyance to another or from a conveyance to a counterweight. In either case, separate tail

More information

Plastic Hinging Considerations for Single-Column Piers Supporting Highly Curved Ramp Bridges

Plastic Hinging Considerations for Single-Column Piers Supporting Highly Curved Ramp Bridges Plastic Hinging Considerations for Single-Column Piers Supporting Highly Curved Ramp Bridges Western Bridge Engineers Seminar Reno, NV Greg Griffin, P.E., S.E. - Senior Bridge Engineer e Griffin, P.E.,

More information

S TRUCTUR A L PR E- A N A LYSIS TA B LES

S TRUCTUR A L PR E- A N A LYSIS TA B LES M A D E F O R U I L D I N G U I L T F O R L I V I N G S TRUTUR A L PR E- A N A LYSIS TA LES I M P R I N T KLH Massivholz GmbH Publisher and responsible for the content: KLH Massivholz GmbH Version: Structural

More information

Multideck 80-V2 Features and Applications

Multideck 80-V2 Features and Applications Features and Applications is designed to incorporate all the advantages of the Multideck 60-V2 but in a deeper profile to provide longer spans up to 5.4m unpropped. Concrete Volume Savings Due to its unique

More information

Effect of Lubricating Oil Behavior on Friction Torque of Tapered Roller Bearings

Effect of Lubricating Oil Behavior on Friction Torque of Tapered Roller Bearings TECHNICAL PAPER Effect of Lubricating Oil Behavior on Friction Torque of Tapered Roller Bearings H. CHIBA H. MATSUYAMA K. TODA Low-friction tapered roller bearings were developed to improve the fuel efficiency

More information

Wirth pile top drill rigs. Reliable systems for on- and offshore

Wirth pile top drill rigs. Reliable systems for on- and offshore Wirth pile top drill rigs Reliable systems for on- and offshore 2 About us Solid foundations with Wirth pile top systems About Aker Solutions Aker Solutions provides oilfield products, systems and services

More information

Super-low Friction Torque Technology of Tapered Roller Bearings for Reduction of Environmental Burdens

Super-low Friction Torque Technology of Tapered Roller Bearings for Reduction of Environmental Burdens TECHNICAL REPORT Super-low Friction Torque Technology of Tapered Roller Bearings for Reduction of Environmental Burdens H. MATSUYAMA K. KAWAGUCHI A. UEMURA N. MASUDA We developed a tapered roller bearing

More information

Abaqus Technology Brief. Prediction of B-Pillar Failure in Automobile Bodies

Abaqus Technology Brief. Prediction of B-Pillar Failure in Automobile Bodies Prediction of B-Pillar Failure in Automobile Bodies Abaqus Technology Brief TB-08-BPF-1 Revised: September 2008 Summary The B-pillar is an important load carrying component of any automobile body. It is

More information

TEST REPORT. Ceram Reference: (QT21489/2/SL)/Ref: 1.0A. Tensile and Frictional Tests on the Fast Fit BeamClamp Systems.

TEST REPORT. Ceram Reference: (QT21489/2/SL)/Ref: 1.0A. Tensile and Frictional Tests on the Fast Fit BeamClamp Systems. TEST REPORT Ceram Reference: 121557 (QT21489/2/SL)/Ref: 1.0A Project Title: Tensile and Frictional Tests on the Fast Fit BeamClamp Systems Client: Kee Safety Limited For The Attention of: Mr Phil Higgs

More information

Cylindrical roller bearings for large electric motors

Cylindrical roller bearings for large electric motors Cylindrical roller bearings for large electric motors Cylindrical roller bearings are typically used in belt or gear driven medium- to largesized electric motors, where heavy radial loads prevail. These

More information

Multideck 50-V2 Features and Applications

Multideck 50-V2 Features and Applications Features and Applications is a dovetail profile deck with a depth of 50mm providing spans up to 4m unpropped. Greater Design Efficiency The larger range of Multideck gauge thicknesses available allow much

More information

Technical Information. (Innovative Transport Technology for Open Pit Mines)

Technical Information. (Innovative Transport Technology for Open Pit Mines) Technical Information TruckLift System (Innovative Transport Technology for Open Pit Mines) WWW.sieMaG-tecBerG.coM Technical Information SIEMAG TECBERG TruckLift Ore deposits close to the surface are generally

More information

BACKACTER 1100 World s strongest dredge

BACKACTER 1100 World s strongest dredge BACKACTER 1100 World s strongest dredge Introduction Yard De Donge designed and build the strongest type of dredger; the Backacter 1100. The first very large dedicated marine dipperdredger excavator in

More information

MALAYSIAN STANDARD. Earthworks - Code of practice. NOTE. This Malaysian Standard has been reviewed and confirmed as being current.

MALAYSIAN STANDARD. Earthworks - Code of practice. NOTE. This Malaysian Standard has been reviewed and confirmed as being current. MALAYSIAN STANDARD MS 1754:2004 (CONFIRMED:2015) Earthworks - Code of practice ICS: 93.020 Descriptors: earthworks, design, safety, excavation and filling, cutting and embankments, grading, levelling,

More information

Araquari Experimental Testing Site, Brazil. Prediction Event

Araquari Experimental Testing Site, Brazil. Prediction Event Araquari Experimental Testing Site, Brazil Prediction Event Araquari Experimental Testing Site Pile Installation Araquari Experimental Testing Site Reaction frame Araquari Experimental Testing Site Instrumentation

More information

COMPFIRE SCFT-FP_20_55_ November 2010 Fin Plate Connection to Square Concrete-Filled Tube Test Result

COMPFIRE SCFT-FP_20_55_ November 2010 Fin Plate Connection to Square Concrete-Filled Tube Test Result Reaction Frame Macalloy Bars Camera 3 Support Beam α Oven Bar Camera 2 Link Bar Camera 1 Tested Connection Jack Bar Electrical Furnace Reaction Frame Load Jack 16 November 2010 1 Oven Bar Link Bar View

More information

Implementation and Thickness Optimization of Perpetual Pavements in Ohio

Implementation and Thickness Optimization of Perpetual Pavements in Ohio Implementation and Thickness Optimization of Perpetual Pavements in Ohio OTEC 2015 Issam Khoury, PhD, PE Russ College of Engineering and Technology Ohio University, Athens, Ohio Outline Background prior

More information

Special Condition C-04 on Interaction of Systems and Structure on helicopters configured with Fly-by-Wire (FBW) Flight Control System (FCS)

Special Condition C-04 on Interaction of Systems and Structure on helicopters configured with Fly-by-Wire (FBW) Flight Control System (FCS) Special Condition C-04 on Interaction of Systems and Structure on helicopters configured with Fly-by-Wire (FBW) Flight Control System (FCS) This Special Condition is published for public consultation in

More information

Finite Element Analysis of Clutch Piston Seal

Finite Element Analysis of Clutch Piston Seal Finite Element Analysis of Clutch Piston Seal T. OYA * F. KASAHARA * *Research & Development Center Tribology Research Department Three-dimensional finite element analysis was used to simulate deformation

More information

Technical Lecture CRET Series 100 Design Stefan Lips

Technical Lecture CRET Series 100 Design Stefan Lips Mehr Leistung. Mehr Wert. Technical Lecture CRET Series 100 Design Stefan Lips 19.03.2014 Contents Scope of application Component structure Design concept 2 Scope of application The main area of application

More information

Solutions to Failures of Shaft Bearings on Vessels Fitted with Z-Drive Thrusters No. 27

Solutions to Failures of Shaft Bearings on Vessels Fitted with Z-Drive Thrusters No. 27 INTERNATIONAL COOPERATION ON MARINE ENGINEERING SYSTEMS Paper presented at the 9 TH International Conference on Marine Engineering Systems at the Helsinki University of Technology (HUT) Ship Laboratory

More information

Media Release FOR IMMEDIATE RELEASE

Media Release FOR IMMEDIATE RELEASE FOR IMMEDIATE RELEASE Establishment of PanaHome MKH Malaysia Joint venture between Panasonic housing subsidiary, PanaHome Malaysia, and local developer MKH Berhad to boost property developments in the

More information

Tutorial: Calculation of two shafts connected by a rolling bearing

Tutorial: Calculation of two shafts connected by a rolling bearing Tutorial: Calculation of two shafts connected by a rolling bearing This tutorial shows the usage of MESYS shaft calculation with multiple shafts. The shaft calculation software provides different views

More information

DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS REPORT COVER SHEET

DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS REPORT COVER SHEET LD-4 7/1/9 DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS REPORT COVER SHEET Geotechnical Engineering Report March 31, 216 AECOM Technical Services, Inc. Virginia Beach, Virginia AECOM Germantown, Maryland

More information

JOINTING OF LARGE BORE PE PIPES: THINK BIG AND EVEN BIGGER!

JOINTING OF LARGE BORE PE PIPES: THINK BIG AND EVEN BIGGER! JOINTING OF LARGE BORE PE PIPES: THINK BIG AND EVEN BIGGER! Robert Eckert FRIATEC AG, Germany Abstract A New Generation of Electrofusion: A technical comparison between the new wedge coupler and the traditional

More information

EXPERIMENTAL STUDY ON EFFECTIVENESS OF SHEAR STRENGTHENING OF RC BEAMS WITH CFRP SHEETS

EXPERIMENTAL STUDY ON EFFECTIVENESS OF SHEAR STRENGTHENING OF RC BEAMS WITH CFRP SHEETS EXPERIMENTAL STUDY ON EFFECTIVENESS OF SHEAR STRENGTHENING OF RC BEAMS WITH CFRP SHEETS Yasuhiro Koda and Ichiro Iwaki Dept. of Civil Eng., College of Eng., Nihon University, Japan Abstract This research

More information

Beyond Design Basis Analysis:

Beyond Design Basis Analysis: Executive Beyond Design Basis Analysis: Developments in UK s Approach and Perspective IAEA International Expert s Meeting on Severe Accident Prof. Ali Tehrani Principal Inspector Nuclear Safety March 2014

More information

Fatigue Life Estimation of Chassis Frame FESM Bracket for Commercial Vehicle

Fatigue Life Estimation of Chassis Frame FESM Bracket for Commercial Vehicle Fatigue Life Estimation of Chassis Frame FESM Bracket for Commercial Vehicle Shivakumar M.M 1, Nirmala L 2 ¹M-Tech Student, Dept. of Mechanical Engineering,K.S Institute of Technology, Bangalore, India

More information

BEHAVIOUR OF LATERALLY LOADED PILE GROUPS EMBEDDED IN OIL-CONTAMINATED SAND

BEHAVIOUR OF LATERALLY LOADED PILE GROUPS EMBEDDED IN OIL-CONTAMINATED SAND BEHAVIOUR OF LATERALLY LOADED PILE GROUPS EMBEDDED IN OIL-CONTAMINATED SAND Chamandeep 1, Anupam Mittal 2 1 M.Tech Student, Civil Engineering Department, NIT Kurukshetra, Haryana, (India) 2 Professors,

More information

Hydraulic Drive Head Performance Curves For Prediction of Helical Pile Capacity

Hydraulic Drive Head Performance Curves For Prediction of Helical Pile Capacity Hydraulic Drive Head Performance Curves For Prediction of Helical Pile Capacity Don Deardorff, P.E. Senior Application Engineer Abstract Helical piles often rely on the final installation torque for ultimate

More information

Improvements of Existing Overhead Lines for 180km/h operation of the Tilting Train

Improvements of Existing Overhead Lines for 180km/h operation of the Tilting Train Improvements of Existing Overhead Lines for 180km/h operation of the Tilting Train K. Lee, Y.H. Cho, Y. Park, S. Kwon Korea Railroad Research Institute, Uiwang-City, Korea Abstract The purpose of this

More information

Skid against Curb simulation using Abaqus/Explicit

Skid against Curb simulation using Abaqus/Explicit Visit the SIMULIA Resource Center for more customer examples. Skid against Curb simulation using Abaqus/Explicit Dipl.-Ing. A. Lepold (FORD), Dipl.-Ing. T. Kroschwald (TECOSIM) Abstract: Skid a full vehicle

More information

Generators for the age of variable power generation

Generators for the age of variable power generation 6 ABB REVIEW SERVICE AND RELIABILITY SERVICE AND RELIABILITY Generators for the age of variable power generation Grid-support plants are subject to frequent starts and stops, and rapid load cycling. Improving

More information

Multi anchored sheet pile wall in soft clay standing on rock

Multi anchored sheet pile wall in soft clay standing on rock DGF møde, 29.10.2015 i Øst, DTU, Kgs. Lyngby Geoteknikerens hverdag Multi anchored sheet pile wall in soft clay standing on rock by Kristoffer Lauridsen, COWI Carsten S. Sørensen, COWI Søren Juel Christensen,

More information

Optimizing haul road design a challenge for resource development in Northern Canada

Optimizing haul road design a challenge for resource development in Northern Canada Optimizing haul road design a challenge for resource development in Northern Canada Robert A Douglas, BASc(CE), PhD, PEng Senior Geotechnical Engineer Low-Volume Roads Golder Associates Ltd., Mississauga,

More information

BLAST CAPACITY ASSESSMENT AND TESTING A-60 OFFSHORE FIRE DOOR

BLAST CAPACITY ASSESSMENT AND TESTING A-60 OFFSHORE FIRE DOOR BLAST CAPACITY ASSESSMENT AND TESTING Final Report December 11, 2008 A-60 OFFSHORE FIRE DOOR Prepared for: JRJ Alum Fab, Inc. Prepared by: Travis J. Holland Michael J. Lowak John R. Montoya BakerRisk Project

More information

WESTERN SPECIFIER. Technical Data for PWI Joists, PWLVL Headers, Beams, Rim Board, Stud, and Dimension

WESTERN SPECIFIER. Technical Data for PWI Joists, PWLVL Headers, Beams, Rim Board, Stud, and Dimension E N G I N E E R E D W O O D WESTERN SPECIFIER Technical Data for PWI Joists, PWLVL Headers, Beams, Rim Board, Stud, and Dimension P R O D U C T S JOIST DIMENSIONS 9½ LVL FLANGE PWI JOIST SERIES JOIST DIMENSIONS

More information

Development of Large Scale Recuperator for Gas Turbine

Development of Large Scale Recuperator for Gas Turbine Proceedings of the International Gas Turbine Congress 23 Tokyo November 2-7, 23 IGTC23Tokyo TS-112 Development of Large Scale Recuperator for Gas Turbine Ryo AKIYOSHI 1, Kiwamu IMAI 2, Tatsuya SIODA 3,

More information

Multideck 60-V2. Contents

Multideck 60-V2. Contents The original and still the most popular deck in the market is a 60mm high, structurally efficient trapezoidal profile providing an excellent composite union between steel and concrete to maximise the load

More information

P.12 P.23 P.24 P.26 DRILLING RIGS AND ACCESSORIES

P.12 P.23 P.24 P.26 DRILLING RIGS AND ACCESSORIES DRILLING RIGS AND ACCESSORIES P.12 HEAVY DYNAMIC PENETROMETER AND DRILLING RIGS APAFOR APAFOR 50 APAFOR 100 APAFOR 200 APAFOR 220 APAFOR 330 AND 340 APAFOR 430 APAFOR 450 RS APAFOR 450 APAFOR 550 AND 560

More information

ABC Anchors & Autoguide Equipment product information

ABC Anchors & Autoguide Equipment product information ABC Anchors & Autoguide Equipment product information www.autoguide.co.uk www.abcanchors.co.uk ABC Anchors Stockley Road Heddington Wiltshire SN11 0PS ENGLAND +44 (0) 1380 850 885 ABC Anchors & Autoguide

More information

Design And Analysis Of Two Wheeler Front Wheel Under Critical Load Conditions

Design And Analysis Of Two Wheeler Front Wheel Under Critical Load Conditions Design And Analysis Of Two Wheeler Front Wheel Under Critical Load Conditions Tejas Mulay 1, Harish Sonawane 1, Prof. P. Baskar 2 1 M. Tech. (Automotive Engineering) students, SMBS, VIT University, Vellore,

More information

AGSSEA 19 TH SOUTHEAST ASIAN GEOTECHNICAL CONFERENCE & 2 ND AGSSEA CONFERENCE. Bulletin No. 1. Deep Excavation and Ground Improvement

AGSSEA 19 TH SOUTHEAST ASIAN GEOTECHNICAL CONFERENCE & 2 ND AGSSEA CONFERENCE. Bulletin No. 1. Deep Excavation and Ground Improvement AGSSEA 19 TH SOUTHEAST ASIAN GEOTECHNICAL CONFERENCE & 2 ND AGSSEA CONFERENCE Deep Excavation and Ground Improvement 31 May 3 June 2016 Dorsett Grand Subang, Subang Jaya, Malaysia Bulletin No. 1 Malaysian

More information

ISO 2953 INTERNATIONAL STANDARD. Mechanical vibration Balancing machines Description and evaluation

ISO 2953 INTERNATIONAL STANDARD. Mechanical vibration Balancing machines Description and evaluation INTERNATIONAL STANDARD ISO 2953 Third edition 1999-04-15 Mechanical vibration Balancing machines Description and evaluation Vibrations mécaniques Machines à équilibrer Description et évaluation A Reference

More information

Offshore Application of the Flywheel Energy Storage. Final report

Offshore Application of the Flywheel Energy Storage. Final report Page of Offshore Application of the Flywheel Energy Storage Page 2 of TABLE OF CONTENTS. Executive summary... 2 2. Objective... 3 3. Background... 3 4. Project overview:... 4 4. The challenge... 4 4.2

More information

Damaging Effect of Static and Moving Armoured Vehicles with Rubber Tires on Flexible Pavement

Damaging Effect of Static and Moving Armoured Vehicles with Rubber Tires on Flexible Pavement Nahrain University, College of Engineering Journal (NUCEJ) Vol.14 No.1, 2011 pp.19-33 Damaging Effect of Static and Moving Armoured Vehicles with Rubber Tires on Flexible Pavement Dr. Saud A. Sultan Civil

More information

Buckling of Pump Barrel and Rod String Stability in Pumping Wells

Buckling of Pump Barrel and Rod String Stability in Pumping Wells This is a revised version of manuscript PO-1115-0011 "Stability of Pump Barrels and Rod String in Pumping Wells" (2015). This manuscript has been submitted to SPE Production & Operations. Manuscript has

More information

MECHANICAL EQUIPMENT. Engineering. Theory & Practice. Vibration & Rubber Engineering Solutions

MECHANICAL EQUIPMENT. Engineering. Theory & Practice. Vibration & Rubber Engineering Solutions MECHANICAL EQUIPMENT Engineering Theory & Practice Vibration & Rubber Engineering Solutions The characteristic of an anti-vibration mounting that mainly determines its efficiency as a device for storing

More information

ROTARY INDEX TABLES RT Series

ROTARY INDEX TABLES RT Series ROTARY INDEX TABLES RT Series RT100 For mounted accessories up to Ø 800mm. For rapid assembly of small parts, inspection or feeding parts. 14 Fixed Index Drives The rotary index table transforms a constant

More information

Comparison between Super-Cell and O-Cell for Bi-Directional Static Load Test

Comparison between Super-Cell and O-Cell for Bi-Directional Static Load Test 1. 1. SUPER-CELL the NEW GENERATION of PILE TESTING LOAD CELLS The hydraulic jack s cylinder and piston are welded to 50mm thick steel bearing plates. The bearing plate s flat surfaces become detrimental

More information

ISO INTERNATIONAL STANDARD. Mechanical vibration Rotor balancing Part 21: Description and evaluation of balancing machines

ISO INTERNATIONAL STANDARD. Mechanical vibration Rotor balancing Part 21: Description and evaluation of balancing machines INTERNATIONAL STANDARD ISO 21940-21 First edition 2012-07-15 Mechanical vibration Rotor balancing Part 21: Description and evaluation of balancing machines Vibrations mécaniques Équilibrage des rotors

More information

S&C: Understanding Root Causes & Assessing Effective Remedies C4R Final Dissemination Event, Paris 15 th March 2017

S&C: Understanding Root Causes & Assessing Effective Remedies C4R Final Dissemination Event, Paris 15 th March 2017 Capacity for Rail S&C: Understanding Root Causes & Assessing Effective Remedies C4R Final Dissemination Event, Paris 15 th March 2017 Presenter: Dr Yann Bezin Institute of Railway Research, University

More information

SKF Explorer cylindrical roller bearings. Extended range for large, heavy industrial applications

SKF Explorer cylindrical roller bearings. Extended range for large, heavy industrial applications SKF Explorer cylindrical roller bearings Extended range for large, heavy industrial applications 2 A higher level of performance for large, heavy-duty applications The SKF Explorer performance class now

More information

GEOWEB GEOCELL SYSTEM PRESTO PRODUCTS GEOSYSTEMS PERFORMANCE TESTING REINFORCED RAIL BALLAST & SMARTROCK

GEOWEB GEOCELL SYSTEM PRESTO PRODUCTS GEOSYSTEMS PERFORMANCE TESTING REINFORCED RAIL BALLAST & SMARTROCK GEOWEB GEOCELL SYSTEM PRESTO PRODUCTS GEOSYSTEMS PERFORMANCE TESTING REINFORCED RAIL BALLAST & SMARTROCK Summary of University of Kansas Research: GEOWEB geocell confinement is a three-dimensional geosynthetic

More information

for U Sheet Piles mm wide

for U Sheet Piles mm wide for U Sheet Piles 00-00mm wide Modular model applicable to U Sheet Piles (00-00mm wide) Silent Piler F0 Flexible and Functional Formula The F0 features a new modular design developed by optimising all

More information

COMPANY PROFILE since 2004

COMPANY PROFILE since 2004 COMPANY PROFILE since 2004 ABOUT US We produce live events and create experiences. We help brands communicate and motivate. We help customers tell their stories. We help clients express their personalities.

More information

Customized Solutions for Business and Technology Continental Solid Tires Asia

Customized Solutions for Business and Technology Continental Solid Tires Asia Customized Solutions for Business and Technology Continental Solid Tires Asia 1 2 3 1 Highly cut & wear resistant tread compound wears slowly, smoothly and evenly 2 Robust sidewall construction resists

More information

Submitted by: Sr. Engineer. Sr. Product Engineer. Product Engineer. Director Power Market Sales. Approved by: Director of Engineering

Submitted by: Sr. Engineer. Sr. Product Engineer. Product Engineer. Director Power Market Sales. Approved by: Director of Engineering Modeling Victaulic Couplings in Piping System Stress Analysis Programs By David Hudson, BSME Gary Trinker, BSME Osama AlMasri, BSME Dan Christian, BSMC Victaulic Engineering Services Department May 2012

More information

Comparison of Super-Cell and other systems used for Bi-Directional Static Load Test

Comparison of Super-Cell and other systems used for Bi-Directional Static Load Test 1. Comparison of Super-Cell and other systems used for Bi-Directional 1. SUPER-CELL the NEW GENERATION of PILE TESTING LOAD CELLS The hydraulic jack s cylinder and piston are welded to 50mm thick steel

More information

Transverse Distribution Calculation and Analysis of Strengthened Yingjing Bridge

Transverse Distribution Calculation and Analysis of Strengthened Yingjing Bridge Modern Applied Science; Vol. 8, No. 3; 4 ISSN 93-844 E-ISSN 93-85 Published by Canadian Center of Science and Education Transverse Distribution Calculation and Analysis of Strengthened Yingjing Bridge

More information

Higher performance. through longer life of gear units

Higher performance. through longer life of gear units Higher performance through longer life of gear units High-performance gear oils that extend gear life and increase productivity Castrol offers you a complete range of world-class gear oils and product

More information

Adaptive Power Flow Method for Distribution Systems With Dispersed Generation

Adaptive Power Flow Method for Distribution Systems With Dispersed Generation 822 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 17, NO. 3, JULY 2002 Adaptive Power Flow Method for Distribution Systems With Dispersed Generation Y. Zhu and K. Tomsovic Abstract Recently, there has been

More information

Load Analysis and Multi Body Dynamics Analysis of Connecting Rod in Single Cylinder 4 Stroke Engine

Load Analysis and Multi Body Dynamics Analysis of Connecting Rod in Single Cylinder 4 Stroke Engine IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 08, 2015 ISSN (online): 2321-0613 Load Analysis and Multi Body Dynamics Analysis of Connecting Rod in Single Cylinder 4

More information

Next Generation Deep Groove Ball Bearing for High-Speed Servomotor

Next Generation Deep Groove Ball Bearing for High-Speed Servomotor NTN TECHNICAL REVIEW No.72 2004 New Product Next Generation Deep Groove Ball Bearing for High-Speed Servomotor Chikara KATAGIRI Kenichiro NAITO In the past, servomotors have been developed by focusing

More information

ELASTOMERIC ISOLATORS

ELASTOMERIC ISOLATORS ELASTOMERIC ISOLATORS ELASTOMERIC ISOLATORS series SI S02 INTRODUCTION CERTIFICATIONS In 1992, FIP Industriale secured CISQ-ICIM certification for its Quality Assurance System in conformance with EN 29001

More information