INSTRUCTION MANUAL FOR

Size: px
Start display at page:

Download "INSTRUCTION MANUAL FOR"

Transcription

1 INSTRUCTION MANUAL FOR VOLTAGE REGULATOR Model: SR32A Part Number: Publication Number: Date: January, 1979 Revision G: March, 1997

2 SECTION 1 GENERAL INFORMATION 1-1. INTRODUCTION The SR32A Voltage Regulator is designed to regulate the output voltage of 50/60 Hertz generators with 32 Vdc fields. Regulation is achieved by controlling the current that the SR32A supplies to the generator or exciter field. The SR32A can be used on any generating system with a field excitation requirement within its rating SPECIFICATIONS Refer to Table 1-1 for the electrical specifications and to Table 1-2 for the physical specifications. Input Voltage Frequency: Volt Amps: Maximum Continuous Output: Maximum 1-Minute Forcing: Sensing Voltage: Maximum Burden Per Phase: Table 1-1. Electrical Specifications. 60 volts; if correct input voltage is not available, a suitable power transformer must be used. 50 Hz, 60 Hz. 1200; when regulator is operated at less than maximum output, power isolation transformer rating can be determined by multiplying input volts by DC output current. 32 volts, 20 amps. 45 volts, 28 amps. NEMA Standard 120, 208, 240, 416, 480, 600; single phase or three phase. 10 VA. Parallel Compensation: 5A input, 25 VA burden, droop adjustable to approximately 5%. Field Resistance: Regulation Accuracy: Regulator Response: Regulator Drift: Regulator Sensing: Power Dissipation: Voltage Adjust Range: 1.6 ohms minimum. Within +0.5% over full range of alternator loading. Less than 17 milliseconds. Less than +0.5% per 104 F (40 C) ambient temperature change. Single-phase or three-phase. Less than 170 watts at continuous rating. Minimum +10% of nominal voltage. 1-1

3 Overall Dimensions: Weight: Finish: Ambient Operating Temperature Range: Storage Temperature Range: Vibration: Shock: Table 1-2. Physical Specifications. 13 inches (330 mm) X 8.53 inches (217 mm) X 7.19 inches (183 mm). Net 18 lbs. (8.16 kg); shipping 20 lbs. (9.07 kg). Dark brown, lusterless, textured, baked enamel. -55 C to +70 C (-67 F to F) without derating. -65 C to +100 C (-85 F to +212 F) without degradation of components. Withstands up to 5 G s at 260 Hz. Withstands up to 15 G s OPTIONAL FEATURES The model number of the voltage regulator indicates which features are included in each particular model. An example model number, with a key showing the manner in which features are identified, is shown in Figure 1-1. Table 1-3 lists all available features along with the model number designator for each. a. Parallel compensation is controlled by either an internal adjustable resistor or an external rheostat. b. Single or three-phase sensing with NEMA standard voltages. c. Internal or external voltage-adjust rheostat. d. Stabilizing networks for use with brush or brushless rotary exciters or as a static exciter. 1-2

4 SR32 A 2 B 15 B 3 B MODEL MOUNTING PARALLEL PROVISIONS VOLTAGE BUILD-UP PROVISIONS SINGLE- OR THREE-PHASE SENSING ENCLOSURE TYPE OF VOLTAGE ADJUSTMENT TYPE OF STABILITY CIRCUIT D Figure 1-1. Sample Model Number Sample Model Number Table 1-3. Model Number Style Chart. SR32 A 3 B 15 B 4 E SR32 A- Surface mounted. 1-No Parallel Provisions. 2-Parallel provisions with adjustable slide wire resistor. 3-Parallel provisions with external parallel rheostat. A-No relay B-Build-up Relay C- Hermetically sealed relay. 15- Selectable 1-phase sensing. 16- Selectable 3-phase sensing w/ Faston connectors. B- Cover 2-Voltage adjust rheostat internally installed. 3-Voltage adjust rheostat, supplied separately with regulator. 4-Voltage adjust rheostat internally installed w/ locking shaft. B-For use as static exciter. E-For use with brushless exciter (primarily on generators rated 150 kw or less) or with all rotary exciters. 1-3

5 1-4. ACCESSORIES Accessories are not designated in the SR model number and must be selected as separate items. Available accessories include the following: 1. Power transformers 2 Paralleling current transformers 3 Exictation Support Systems (Series Boost Options). 4 Underfrequency - Overvoltage Control Modules 5 Manual Voltage Control Module 6 SR Regulator with RFI Suppression 7 Motor Operated Potentiometer 8 Wide Range Voltage Adjust 9 Volts-Per-Cycle Modules 10 DC Generator Voltage Control 11. VAR/Power Factor Controller Information on these accessories may be obtained from the applicable instruction manual or product bulletin. Information is also available from you nearest Basler Electric Sales Representative or from the Factory System Sales Department. 1-4

6 SECTION 2 THEORY OF OPERATION 2-1. FUNCTIONAL CIRCUIT Refer to Figure 2-1. The voltage regulator senses the generator voltage, compares a rectifies sample of that voltage with a reference diode (zener) voltage, and supplies the field current required to maintain a predetermined ratio between the generator voltage and the reference voltage. This unit consists of five basic circuits: a sensing circuit, and error detector, an error amplifier, a power controller, and a stabilization network. With the exception of the power controller and part of the sensing circuit, all of these circuits are contained on printed circuit board assemblies. Figure 2-1. Input Phase Relationship AUTOMATIC VOLTAGE BUILDUP Relay K-1 provides automatic voltage buildup form generator residual voltage. A normally closed contact (relay de-energized) provides a current path to fire the control rectifiers to allow the generator residual voltage to be converted to dc by the diodes (CR13, CR14) and rectifiers (CR11, CR12). This dc voltage is then applied to the exciter field. When the generator voltage reaches approximately 75% of rated, the relay pulls in, removing the buildup circuit and allowing the control rectifiers to regulate the generator output voltage. A minimum 3V generator residual is required for automatic voltage buildup. If residual is less than 3V, external field flashing may be required. 2-1

7 2-3. MOTOR STARTING OR SHORT CIRCUIT OPERATION In brushless exciter (or static exciter) applications, the exciter output is not available for selfexcitation during heavy loading. The addition of a Series Booster Option (SBO), Patent No. 3,316,479, prevents collapse of excitation by providing constant voltage to the regulator for all operating conditions PARALLEL OPERATION A. When parallel operation is required, the following additional components are required in the regulating system: 1. Resistor R25 2. Transformer T3 3. Current Transformer CT1 Two of the components, R25 and T3, are included in a parallel-equipped voltage regulator. Current Transformer CT1 is a separate item and must be interconnected as shown in Figure 3-2. B. These components allow the paralleled generators to share reactive load and reduce circulating reactive currents between them in the following manner: (1) The current transformer (CT1) is installed in line 2 of each generator. It develops a signal that is proportional in amplitude and phase to the line current. This current signal develops a voltage across resistor R25. A slider on R25 supplies a part of this voltage to the primary of transformer T3. The secondaries of T3 are connected in series with the leads from the secondary of the sensing transformer T1 and the sensing rectifiers located on the printed circuit board. The ac voltage applied to the sensing rectifier bridge is the vector sum of the stepped-down sensing voltage (terminals E1 and E3) and the parallel CT signal supplied through T3 (terminals 1 and 2). The voltage supplied to the sensing rectifiers by the parallel CT is very small in relation to the signal supplied by the sensing voltage. The regulator input sensing voltage (terminals E1 and E3) and the parallel compensation signal (terminals 1 and 2) must be connected to the generator system so as to provide the correct phase and polarity relationship. (2) When a resistive (unity power factor) load is applied to the generator, the voltage that appears across R25 (and T3 windings) leads the sensing voltage by 90 degrees. The vector sum of the two voltages is nearly the same as the original sensing voltage. Consequently, almost no change occurs in generator output voltage. (3) When a lagging power (inductive) load is applied to the generator, the voltage across R25 becomes more in phase with the sensing voltage. The combined vectors of the two voltages results in a large voltage being applied to the sensing rectifiers. Since the action of the regulator is to maintain a constant voltage at the sensing rectifiers, the regulator reacts by decreasing the generator output voltage. (4) When a leading power factor (capacitive) load is applied to the generator, the voltage across R25 becomes out of phase with the sensing voltage. The combined vectors of the voltage results in a smaller voltage being applied to the sensing rectifiers. The regulator reacts by increasing the generator voltage. (5) If two generators are operating in parallel and the field excitation on one generator becomes excessive, a circulating current can flow between the generators. This current will appear as a lagging power factor (inductive) load to the generator with excessive field 2-2

8 current and as a leading power factor (capacitive) load to the other. On the generator with the lagging power factor load, the parallel compensation circuit will cause the voltage regulator to decrease the field excitation. On the generator with the leading power factor load, the parallel compensation circuit will cause the voltage regulator to increase the field excitation. This will minimize the circulating current between the generators. This action and circuitry is called parallel droop compensation. It allows two or more paralleled generators to proportionally share inductive loads by causing a decrease or droop in the generator system voltage. C. Parallel cross-current compensation (reactive differential compensation) allows two or more paralleled generators to share inductive reactive loads with no decrease or droop in the generator system output voltage. This is accomplished by the circuitry described above for parallel droop compensation with the addition of cross-connecting leads between the parallel CT secondaries as shown in Figure 3-3, Interconnection Diagram. By connecting the finish of one parallel CT to the start of another, a closed series loop is formed that interconnects the CT s of all generators to be paralleled. The signals from the interconnected CT s cancel each other when the line currents are proportional, in phase, and no system voltage decrease occurs. These regulators provide the circuit isolation necessary for parallel cross-current compensation. 2-3

9 SECTION 3 INSTALLATION AND INTERCONNECTION 3-1. MOUNTING The voltage regulator can be mounted in any position without affecting its operating characteristics; however, the unit should be vertically mounted to obtain optimum cooling. The regulator can be mounted in any location where the ambient temperature remains within -55 C to + 70 C (-67 F to +158 F). Due to its rugged construction, the regulator can be mounted directly on the generator. The overall mounting dimensions are shown in Figure 3-1, Outline Drawing. Figure 3-1. Outline Drawing. 3-1

10 3-2. INTERCONNECTION CAUTION Meggers and high potential test equipment should be used with extreme care. Incorrect use of such equipment could damage components contained in the device. A. Wire Gauge The regulator must be connected to the generator system as instructed in this section and as shown in Figure 3-3, Interconnection Diagram. Number 16 gauge wire (or larger) should be used for all connections to the regulator. WARNING All SR32 Voltage Regulators are shipped factory preset for 120 Vac sensing. B. Regulator Sensing (Terminals E1, E2, and E3) (1) The regulator has one or two internal sensing transformers (T1 or T1+T2). These are provided with taps for input sensing voltages of 120, 208, 240, 416, 480, and 600 Vac (refer to Figure 3-2). The model number of the unit designates single phase (T1) or three-phase (T1+T2) sensing. See the Optional Features section for model number interpretation. For operation with generator voltages above 600 volts, a potential transformer (or transformers) must be used to supply the regulator sensing voltage. This transformer should be of metering quality. The regulator sensing circuit load is less then 10 VA; correct polarity must be maintained to the regulator sensing input. (2) On single-phase sensing models, the voltage sensing leads are connected to terminals E1 and E3. For three-phase sensing, terminals E1, E2, and E3 are used. For precise voltage regulation, the sensing leads should be connected as close as possible to the point where regulation is desired. (3) SR32A Voltage Regulators are factory preset for 120 Vac sensing voltage. If the sensing voltage needs to be changed for your installation, perform the following steps. Step 1. Step 2. Step 3. Step 4. Remove the cover if applicable. Remove 9 hex screws. Remove the printed circuit board without disconnecting the wires. Locate transformer(s) T1 for single-phase sensing units (T1 and T2 for threephase sensing units). These transformers are equipped with Faston connectors for changing sensing taps. Step 5. For single-phase sensing units, move the wire that is factory connected to T1-120 terminal to the T1 terminal labeled with the desired sensing voltage. Step 6. For three-phase sensing units, move the wire that is factory connected to T1-120 terminal to the T1 terminal labeled with the desired sensing voltage. Also, move the wire from T2-120 terminal to the T2 terminal labeled with the desired sensing voltage. 3-2

11 Figure 3-2. Top View of Voltage Regulator. (4) The regulator regulates the voltage that is applied to its sensing terminals. Therefore, it cannot correct for voltage drop in leads that may occur at points other than where the regulator sensing leads are connected. The leads that supply regulator sensing should not be used to supply power to any other equipment or to the regulator power stage (terminals 3 and 4). (5) If the generator is to be operated in parallel with other generators, the phase relationship of sensing voltage and the parallel current transformer is very important. See Parallel Compensation below for further information. C. Field Power (Terminals F+ and F-) (1) The model number prefix SR32 defines the amount of power (32 volts, 20 amps, continuous) the unit is designed to deliver. See the Optional Features section for model number interpretation. (2) The dc resistance of the field to which the regulator is connected (terminals F+ and F-) must be equal to or greater than 1.57 ohms for the SR32. If the resistance is less than the specified minimum, a resistor must be added in series with the field. This resistor value plus the field resistance must exceed the minimum preceding value. 3-3

12 (3) Good generator voltage stability usually results when the regulator output is above 10 Vdc at no load. If the voltage is less and a voltage stability problem exists, it may be necessary to add resistance in series with the field. The resistance raises the regulator output voltage, thereby increasing the stability signal. Figure 3-3. Interconnection Diagram (4) When adding resistance in series with the field, the resistor value must not restrict field forcing during full load conditions. The following example explains how to compute the proper resistance: 3-4

13 EXAMPLE An SR32 voltage regulator is required to operate with an exciter field that has a dc resistance of 1 ohm and current requirements of 7.0 Adc at no load and 15 Adc at full load. Since the SR32 requires a minimum field resistance of 1.57 ohms, a resistor of at least 0.57 ohms must be connected in series with the field. The regulator output will be 1.57 ohms times 7.0 A, or 11.0 Vdc, and 1.57 ohms times 15 A, or 23.5 Vdc, at full load. This conforms to the 10 volts minimum at no load and provides a sufficient amount of forcing at full load (up to 45 Vdc). D. Input Power (Terminals 3 and 4) (1) For input power maximums, see the Optional Features section. The current requirement of the field with which the regulator is operating will determine the actual input current. The nominal voltage applied to the regulator input power stage (terminals 3 and 4) must be 60V for the SR32. The input power may be taken from any generator line that provides the correct voltage (line to line or line to neutral). The phase relationship of this input to the other circuits is not important. CAUTION Excessive input voltage can destroy the diodes and SCR s in the power controller circuit. Also, failure to isolate the regulator input from ground can result in destruction of the SCR bridge. (2) When the generator output voltage is other than 60V, a power transformer must be used to match the generator voltage to the regulator input. If excessive voltage is applied to the regulator input (terminals 3 and 4), the diodes and SCR s in the power controller circuit may be destroyed. (3) If the field or field flashing circuit is grounded, a power transformer must be used to isolate the regulator input from ground. Without the use of this transformer, a ground at any point in the field circuit and another ground in the generator output will destroy the SCR bridge. (4) On single phase sensing models, it is recommended that the input power be taken from a phase other than the one used for input sensing. E. Parallel Compensation (Terminals 1 and 2) (1) In addition to the regulator provisions, a 25 VA current transformer (CT) is also required (see Figure 3-3, Interconnection Diagram ). The CT is connected in a generator line and should deliver form 3 to 5 amperes secondary current at rated load. (2) The CT signal/regulator sensing voltage phase relationship must be correct or the systems will not parallel properly. On three-phase sensing models, the CT must be installed in the line that supplies sensing voltage to regulator terminal E2. On single-phase models, the CT must be installed in the line that does not supply sensing to the regulator. (3) Figure 3-4, Reactive Differential Compensation (Cross-Current Compensation) CT s Interconnection, shows the correct CT polarity for L1-L2-L3 phase rotation. If the phase sequence is L1-L3-L2, the CT secondary leads must be interchanged. The correct CT secondary polarity can be determined by the test found in paragraph 4.8.C. Preliminary Operation. (4) For droop compensation, connect the CT to its respective regulator as shown in Figure 3-4. (5) For cross-current compensation, connect each CT to its respective regulator and connect the CT s in series; connect the finish of the first CT to the start of the second CT, the finish of the second CT to the start of the third CT, etc. until all CT s are connected. The final step will be to connect the finish of the last CT to the start of the first CT (see Figure 3-4). 3-5

14 (6) A Unit-Parallel switch shorts the parallel CT secondary to prevent any droop signal from being applied to the regulating system during single unit operation. The switch may not be required on parallel droop compensation applications in which a voltage drop is unobjectionable. (7) On parallel cross-current compensation applications consisting of more than two generators, a Unit-Parallel switch should be used if all the generators are not always on the load bus. If the switch is not used, a voltage droop will be introduced into the system. This is because the unloaded generator voltage CT does not supply a compensating signal, but instead allows a voltage drop across the CT. This drop also causes the voltage of the incoming generator to fluctuate prior to paralleling. Ideally, this switch is an auxiliary contact on the circuit breaker that opens when the circuit breaker is closed. 3-6

15 Figure 3-4. Reactive Differential Compensation (Cross-Current Compensation) CT s Interconnection 3-7

16 SECTION 4 OPERATING INSTRUCTIONS 4-1. INTRODUCTION The following procedures should be reviewed before initial operation is attempted. Startup procedures are detailed in the Initial Operation and Field Flashing sections. WARNING All SR32A Voltage Regulators are shipped factory preset for 120 Vac sensing OPERATION AT REDUCED SPEEDS CAUTION Without adequate protection, prolonged operation at speeds lower than normal can cause the complete destruction of the voltage regulator and the exciter field. Do not operate the generating system at reduced speeds with the voltage regulator in operation unless adequate precautions are taken to protect the regulator. If operation at reduced speed is essential, either remove input power from the regulator or add an Underfrequency/Overvoltage Module to the system. For information on this module, see the Optional Features section VOLTAGE SHUTDOWN Your regulator may be equipped with an input power switch to allow the removal of excitation from the field in an emergency or when the generator prime mover must be operated at reduced speed. This switch is shown in Figure 3-3, Interconnection Diagram. If this switch is not used, it is recommended that the input power switch be temporarily installed for initial operation. CAUTION If the input power switch is installed in the field circuit (terminals F+ of F-), a high flyback voltage will develop. To avoid high voltage arcing, the field circuit must never be opened during operation. When used, the input power switch must always be installed in the input power line to the regulator (terminals 3 or 4). Do not install a switch in the field circuit (terminals F+ of F-). Also a shutdown circuit using field discharge resistors is not required and should not be used. 4-1

17 4-4. ADJUSTMENTS The adjustments pertaining to the regulator and system operation are described in the following paragraphs. These adjustments are made during initial operation and normally do not have to be repeated during the life of the regulator. A. Stability Adjustment (R4) This adjustment provides stable regulator operation. It controls the amount of feedback that is applied to the error amplifier stage. Normally, the stability adjustment is factory set in the extreme clockwise (CW) position. This setting normally assures good stability, but tends to slow the generator response time. If rotated counterclockwise (CCW), system response time quickens. However, if rotated too far CCW, the generator voltage may oscillate (hunt). If the generator voltage hunts, the adjustment should be rotated CW well ahead of the point where oscillation occurs. The system voltage stability is critical at no load. If a setting is desired that provides the fastest possible voltage response with good generator stability, an oscilloscope or some voltage recording device should be used. B. Generator Voltage Adjust Rheostat (R1) This adjustment controls the generator voltage. When adjusted to its maximum resistance position (CCW), minimum generator voltage is obtained. Maximum generator voltage is obtained with minimum resistance (CW). C. Nominal Voltage Range Set Adjust (R3) This adjustment varies the limits of R1. Normally R3 is set to provide R1 with and adjustment range of +10% of rated voltage WIRING VERIFICATION Before initial operation is attempted, verify that the regulator is connected correctly as shown in Figure 3-3, Interconnection Diagram INITIAL OPERATION The initial operating instructions should be completely reviewed and understood before system operation is attempted. Controls and adjustments pertinent to system operations also should be reviewed. A. Single Unit Operation (No Load) (1) Start the prime mover and bring up to rated speed. If a voltage shutdown switch is used (see the Voltage Shutdown section), close the switch to apply excitation. If this switch is not used, generator voltage will build up automatically. If field flashing is necessary, see the Field Flashing section below. (2) Verify generator voltage; check for the following conditions: a. If overvoltage (+15% or more) exists, immediately open the shutdown switch or stop the prime mover. Determine the cause of the overvoltage. If necessary, refer to the Troubleshooting section. 4-2

18 b. If voltage fails to build up, field flashing may be required. Refer to the Field Flashing section. c. If undervoltage (-15% or more) exists, stop the prime mover and determine the cause of the undervoltage. If necessary, refer to the Troubleshooting section. d. If voltage build up and collapses, stop the prime mover and determine the cause of the collapse. If necessary, refer to the Troubleshooting section. e. If voltage oscillates (hunts), refer to the Troubleshooting section. Voltage hunting can be caused by an unstable prime mover. (3) If voltage is unstable, perform the following step: a. Loosen the locking nut on R4. b. Rotate R4 clockwise (CW) approximately 30 beyond the point where stable operation is obtained. If this step does not stabilize the voltage, refer to the Interconnection section, paragraph 3.2.C, Field Power. c. Tighten lock nut on R4. (4) To adjust the voltage range +10%, perform the following steps: a. Verify R1 is adjusted to the center of its travel. b. Loosen the locking nut on R3 and adjust to obtain the rated generator voltage. c. Tighten the lock nut on R3. (5) Load test the voltage regulator as follows: a. Apply load to the generator. b. Verify the voltage regulation is within +0.5%. If regulation is not within this range, refer to the Troubleshooting section. c. Alternately remove and apply the load to determine if the generator voltage is stable. d. If the generator voltage becomes unstable, adjust R4 for stable operation. If adjusting R4 does not stabilize the voltage, see paragraph 4.6.B below, Increasing Stability. B. Increasing Stability (1) Instability may occur when the no-load field requirements of the exciter or generator are near the minimum working voltage of the regulator. Increased stability may be obtained by adding a resistor in series with the field. See the Interconnection section, paragraph 3.2.C, Field Power. (2) An unstable governor is frequently the cause of generator voltage instability. If a stability problem persists after performing the steps in 4.6.A, and 4.6.B, thoroughly check the governor. 4-3

19 4.7 FIELD FLASHING The following procedure is for use on systems that do not build up generator voltage and have no field flash provision incorporated. Usually, there is sufficient residual magnetism to allow the generator voltage to build up without an additional flashing circuit. See the Automatic Voltage Buildup section. A. With the prime mover at rest (not rotating), apply a dc flashing source across terminal F+ and F- on the regulator. The positive of the flashing source must be connected to F+ and the negative must be connected to F-. CAUTION The flashing source cannot be grounded unless a power isolation transformer is used. B. If automatic field flashing is required, a dc source not in excess of 125V should be used. The circuit must be interconnected as shown in Figure 3-3, Interconnection Diagram. The flashing source must not provide more than 50% of the current required for no-load output. The blocking diode in series with the regulator F- terminal prevents the regulator output from flowing into the flashing source PARALLEL OPERATION The following paragraphs describe the procedure for operating two or more generator sets in parallel. A. Prerequisites To ensure proper parallel operation, the following requirements must be met: (1) The voltage regulating systems must cause the generators to share the total KVAR load. (2) The speed governing system must cause the generators to share the total KW load. B. Preliminary Instructions (1) A review of the operation of components that facilitate operation is recommended. These include components external to the regulator as well as components within the regulator. See section 2.4, Parallel Operation. (2) It is essential that the paralleling signal at terminal 1 and 2 of the regulator have the proper phase relationship with the sensing voltages at terminals E1, E2 (if used), and E3. Verify the connections to these terminals are exactly as shown in Figure 3-3, Interconnection Diagram. (3) If cross-current compensation is desired, the paralleling CT s must be connected as described in paragraph 3.2.E, Parallel Compensation. A CT must be selected that will furnish 3 to 5 amperes at rated generator load current. (4) Prior to operation, the slide adjustment of resistor R25 on each regulator should be set to the same position: near the end of R25 (farthest from the terminal strip). This adjustment provides maximum droop signal. 4-4

20 C. Preliminary Operation (1) Before attempting to parallel two or more generator sets, it is recommended that the individual sets be tested as follows to verify that the paralleling features function properly: a. Place each set in operation in accordance with paragraph 4.6.A, Single Unit Operation, No Load. b. Verify the paralleling CT secondary is not shorted; unit/parallel switch in PARALLEL position. c. Apply 25% to 100% unity power factor load to set under test. Generator voltage should change less than 1%. If governor is set for droop operation, frequency should decrease. d. Apply 25% to 100% 0.8 power factor (inductive) load. Voltage should droop from 4% to 6% with rated load. If voltage rises instead of drooping, reverse the CT sensing leads. (2) During the tests, verify voltage and speed do not drift or jump erratically. Also, generator voltage sequence can be verified during the tests. D. Conditions Necessary for Paralleling To prevent damage to the generator or the prime mover or both, paralleling should be attempted only when the speeds (frequencies) are equal, at the instant when the generator voltages are also equal. That is, the generators have the same phase sequence of voltage and the voltages are in phase. E. Metering To initiate paralleling and to check for proper parallel operation, all generators should be equipped with the following monitoring equipment: (1) AC Voltmeter (1 or 2) (2) Frequency Meter (1 or 2) (3) Synchroscope or set of lights; used to indicate an in-phase condition (4) Ammeter, ac (1 per set) (5) KW meter (1 per set) (6) KVAR or Power Factor Meter (1 per set) (7) Field ammeters F. Sequence of Operation (Parallel) (1) The following instructions contain the proper procedure for paralleling generators. This procedure should be completely reviewed, understood and walked through before paralleling is attempted. a. Start generator set No. 1. b. Close circuit breaker connecting No. 1 to bus. c. Adjust voltage and frequency to nominal. d. Apply load. If possible, load should be 10% or more of unit KW rating. 4-5

21 e. Start generator set No. 2. f. Adjust No. 2 voltage to nominal. g. Adjust No. 2 speed to slightly higher than speed of No. 1. h. Observe synchroscope or synch lights. When No. 2 is in phase with No. 1, close the circuit breaker connecting No. 2 to the bus. i. Immediately after closing breaker, verify indication on ammeter for set No. 2. Ammeter should read well within the rating of the generator. If reading is beyond the generator s rating, shut down the system and refer to the Troubleshooting section. If operation is unstable, see paragraph 4.8.F(3). If stable, proceed to the next step. j. Adjust speed of No. 2 to the point where each set is carrying the desired share of kw load. k. Adjust voltage of No. 2 until ammeter readings of both sets are near minimum. l. If KVAR or power factor meters are available, adjust voltage adjust rheostat for equal or proportional KVAR or power factor readings. m. If sets are equipped with power factor meters instead of kw meters, alternately adjust the speed and voltage on No. 2 until the ammeter readings are proportional and the power factor readings are equal. NOTE To obtain best results, final adjustments should be made with full load on the bus. n. With full load applied, readjust the speed and voltage on No. 2 until the desired load division is obtained. (2) The best adjustment is obtained when both sets are supplying the same percentage of rated current, kw or power factor readings are equal, or the sum of the ammeter currents of the sets is minimum. (3) Closing the circuit breaker for set No. 2, step 4.8.F(1)h, may result in improper operation. The ammeter reading may be very high and the circuit breaker may open due to current overload or reverse power play, Isolate this problem to a faulty speed or faulty voltage regulating system by performing the following steps: a. Parallel the generators as instructed in 4.8.F(1), steps (a) through (h). b. Immediately after closing the circuit breaker, observe the kw or power factor meters. If a high ammeter reading is accompanied by a large kw unbalance, a faulty speed regulating system is indicated. If a high ammeter reading is accompanied by a KVAR unbalance, a faulty voltage regulating system is indicated. (4) An alternate method of isolating the cause for the preceding problem is to parallel the generators using manual voltage control (if available). If proper operation is obtained, a faulty voltage regulating system is indicated. If not, a faulty speed regulating system is indicated. 4-6

22 (5) If a faulty voltage regulating system is indicated, verify the wiring and review paragraph 3.2.E, Parallel Compensation (Terminals 1 and 2), before removing the regulator. It has been found that most problems encountered with the voltage regulator in attempting to parallel generators are due to improper wiring. (6) To parallel additional generator sets, repeat the procedure for paralleling set No

23 SECTION 5 MAINTENANCE, REPLACEMENT PARTS, AND TROUBLESHOOTING 5-1. PREVENTIVE MAINTENANCE The Voltage Regulator should be inspected on a regular basis to ensure that the unit is free from moisture and accumulations of dust. When inspecting the unit, check that all parts are securely mounted and that all electrical connections are clean and secure. Any accumulation of dust should be removed from the unit with a soft brush or with an air line that has a moisture trap CORRECTIVE MAINTENANCE Repairs to the regulator can be made by following the Troubleshooting section. Due to a protective transparent conformal coating, repairs to the printed circuit board are difficult and should not be attempted REPLACEMENT PARTS Table 5-1 lists parts and assemblies that have maintenance significance. When ordering any part from Basler Electric Company, always specify the description of the item, the complete model number, the unit serial number, the part number, and the quantity required. Table 5-1. Replacement Part List. Reference Description Basler Part Number CB Circuit Board Assembly Used on SR32 * CR11, CR12 Silicon Controlled Rectifier CR8, CR13, CR14, CR15, CR16 Diode T3 Transformer BE Sensing Transformer(s) Used on SR32 * L1 Filter Choke BE K1 Relay R25 Paralleling Rheostat R1 Voltage Adjust Rheostat TROUBLESHOOTING *Use model number. See Optional Features section for interpretation of model number. The more common generator system malfunctions and the appropriate repair actions are listed in Table

24 Table 5-2. Troubleshooting Chart MALFUNCTION TEST OR INSPECTION CORRECTIVE ACTION 1. VOLTAGE DOES NOT BUILD UP TO RATED VALUE. Step 1. Check for low residual voltage and/or incorrect polarity relationship between exciter output and generator field. If either condition exists, flash the generator field. If neither condition exists, proceed to Step 2. Step 2. Verify that the Voltage Shutdown Switch is closed. If the Voltage Shutdown Switch is open, close the switch. If the Voltage Shutdown Switch is closed, proceed to Step 3. Step 3. Verify that the prime mover is operating at rated speed. If the prime mover is not operating at rated speed, adjust speed. If prime mover is operating at rated speed, proceed to step 4. Step 4. Incorrect or missing voltage at regulator power input terminals (3 & 4). If this condition exists, repair wiring. If this condition does not exist, proceed to step 5. Step 5. Verify regulator output voltage at terminals F+, F-, and A-. If voltage is incorrect or missing, repair wiring and/or adjust/repair regulator. If voltage is correct, proceed to step 6. Step 6. Verify that generator output is neither shorted nor overloaded. If generator output is shorted, remove short and repair wiring. If generator is overloaded, shed excess load. If generator output is not overloaded or shorted, proceed to step 7. Step 7. Verify that the External Voltage Adjust Potentiometer (R1) is properly wired. If the External Voltage Adjust Potentiometer is incorrectly wired, reconnect wiring properly. If the External Voltage Adjust Potentiometer is correctly wired, proceed to step

25 Table 5-2. Troubleshooting Chart - Continued. MALFUNCTION TEST OR INSPECTION CORRECTIVE ACTION 1. VOLTAGE DOES NOT BUILD UP TO RATED VALUE - Continued. Step 8. Verify that the exciter wiring is correct. If the exciter wiring in incorrect, reconnect the exciter. If the exciter wiring is correct, proceed to step 9. Step 9. Check for a defective exciter. If exciter is defective, repair or replace the exciter. If the exciter is not defective, proceed to step 10. Step 10. Verify the regulator s sensing transformers are on the correct taps. Change taps for the correct nominal voltage. Step 11. If the above steps fail to correct the malfunction, replace or repair the voltage regulator. 2. VOLTAGE BUILDS UP UNTIL RELAY ACTUATES, THEN DECAYS. Step 1. Check for a defective Voltage Adjust Rheostat (R1) and/or defective associated circuitry. If the circuitry is defective, repair the circuit/wiring. If the rheostat is defective, replace the rheostat. If neither the rheostat or the circuit is defective, proceed to step 2. Step 2. Check for input power to terminals 3 and 4 (Brush-type Rotary Exciters ONLY. All others proceed to step 3.) If power is not present, check and repair wiring as necessary. If power is present, proceed to step 3. Step 3. If the above steps do not correct the malfunction, replace or repair the voltage regulator as necessary. 5-3

26 Table 5-2. Troubleshooting Chart - Continued. MALFUNCTION TEST OR INSPECTION CORRECTIVE ACTION 3. VOLTAGE HIGH AND UNCONTROLLABLE WITH VOLTAGE ADJUST RHEOSTAT - Step 1. Check for sensing voltage at terminals E1, E2, and E3. If sensing voltage is not present, repair wiring. If sensing voltage is present, proceed to step 2. Step 2. Check that the transfer switch (if used) is in AUTO position. (If transfer switch is not used, proceed to step 3.) If transfer switch is not in AUTO position, place in AUTO. If transfer switch is in AUTO position, proceed to step 3. Step 3. Check for a shorted external Voltage Adjust Potentiometer (R1). If Voltage Adjust Potentiometer is shorted, replace Voltage Adjust Potentiometer. If Voltage Adjust Potentiometer is not shorted, proceed to step 4. Step 4. Verify that the sensing transformer is set to the proper tap. If transformer tap is improperly selected, reconnect to proper tap. If transformer tap is properly selected, proceed to step 5. Step 5. Check for a faulty relay (K1). If relay K1 is defective, replace relay. If relay K1 is not defective, proceed to step 6. Step 6. If the above steps fail to correct the malfunction, replace or repair the voltage regulator as necessary. 4. VOLTAGE HIGH AND CONTROLLABLE WITH VOLTAGE ADJUST RHEOSTAT. Step 1. Check that the sensing transformer is set to the proper tap. If transformer tap is improperly selected, reconnect to proper tap. If transformer tap is properly selected, proceed to step 2. Step 2. Check that Voltage Range Adjust Potentiometer (R3) is not set too high. If Voltage Range Adjust Potentiometer is set too high, adjust potentiometer. If Voltage Range Adjust Potentiometer setting is within limits, proceed to step

27 Table 5-2. Troubleshooting Chart - Continued. MALFUNCTION TEST OR INSPECTION CORRECTIVE ACTION 4. VOLTAGE HIGH AND CONTROLLABLE WITH VOLTAGE ADJUST RHEOSTAT - Continued. Step 3. Check that the Voltage Adjust Potentiometer (R1) resistance is not too low. If the Voltage Adjust Potentiometer resistance is too low, replace potentiometer with one of the proper value. If the Voltage Adjust Potentiometer resistance is proper, proceed to step 4. Step 4. Verify that the sensing leads are properly connected to the generator and regulator. If the sensing leads are improperly connected, reconnect properly. If the sensing leads are properly connected, proceed to step 5. Step 5. Verify that three-phase sensing is applied to regulator. (Three-phase sensing models only. For single-phase sensing models, proceed to step 6.) If single-phase sensing is applied, reconnect for three-phase sensing. If three phase sensing is applied, proceed to step 6. Step 6. Verify the accuracy and connection of the voltmeter. If voltmeter is improperly connected, reconnect voltmeter properly. If voltmeter is defective, replace voltmeter. If voltmeter is connected properly and not defective, proceed to step 7. Step 7. If the above steps fail to correct the malfunction, replace or repair the voltage regulator as necessary. 5. VOLTAGE LOW AND CONTROLLABLE WITH VOLTAGE ADJUST RHEOSTAT. Step 1. Check that the sensing transformer is set to the proper tap. If transformer tap is improperly selected, reconnect to proper tap. If transformer tap is properly selected, proceed to step 2. Step 2. Check that Voltage Range Adjust Potentiometer (R3) is not set too low. If Voltage Range Adjust Potentiometer is set too low, adjust potentiometer. If Voltage Range Adjust Potentiometer setting is within limits, proceed to step

28 MALFUNCTION TEST OR INSPECTION CORRECTIVE ACTION Table 5-2. Troubleshooting Chart - Continued. 5. VOLTAGE LOW AND CONTROLLABLE WITH VOLTAGE ADJUST RHEOSTAT - Continued. Step 3. Check that prime mover is operating at rated speed. If prime mover is operating below rated speed, adjust prime mover speed to rated. If prime mover is operating at rated speed, proceed to step 4. Step 4. Verify that the sensing leads are properly connected to the generator and regulator. If the sensing leads are improperly connected, reconnect properly. If the sensing leads are properly connected, proceed to step 5. Step 5. Verify the accuracy and connection of the voltmeter. If voltmeter is improperly connected, reconnect voltmeter properly. If voltmeter is defective, replace voltmeter. If voltmeter is connected properly and not defective, proceed to step 6. Step 6. If the above steps fail to correct the malfunction, replace or repair the voltage regulator as necessary. 6. POOR REGULATION. Step 1. Verify that exciter/generator field requirements are not in excess of voltage regulator capability. If regulator application is incorrect for regulator, contact Basler Electric. If regulator application is within regulator limits, proceed to step 2. Step 2. Verify that input voltage at terminals 3 and 4 is of the correct value. If input voltage is incorrect, apply correct voltage to terminals 3 and 4. If input voltage is correct, proceed to step 3. Step 3. Check that the voltmeter is connect to the same location as the regulator sensing. If voltmeter is not connected to same location as the regulator sensing, reconnect voltmeter. If voltmeter is properly connected, proceed to step

29 Table 5-2. Troubleshooting Chart - Continued. MALFUNCTION TEST OR INSPECTION CORRECTIVE ACTION 6. POOR REGULATION - Continued. Step 4. Check that the generator output waveform is not distorted due to harmonic content (Regulator senses average voltage; meter may be indicating RMS values.) If this condition exists, consult the generator manufacturer. If this condition does not exist, proceed to step 5. Step 5. Check that the UNIT/PARALLEL switch (if installed, if not go to step 6) is in the PARALLEL position when the generator is paralleled and in the UNIT position when the generator is operating alone. Also check that the switch functions properly. If the switch is not in the proper position, set switch to correct position. If the switch is defective, replace switch. If the switch is set to the proper position, proceed to step 6. Step 6. Check that load is not unbalanced as regulator averages all three phases together. (Three-Phase Sensing ONLY. All others proceed to step 7.) If load is unbalanced, balance load. If load is balanced, proceed to step 7. Step 7. Verify that prime mover is operating at rated speed. If prime mover is not operating at rated speed, change prime mover speed to rated. If prime mover is operating at rated speed, proceed to step 8. Step 8. Check for fault in either exciter or generator. If a fault exists, correct fault condition. If a fault does not exist, proceed to step 9. Step 9. If the above steps fail to correct the malfunction, replace or repair the voltage regulator as necessary. 7. POOR VOLTAGE STABILITY. Step 1. Verify that the generator frequency is stable. If the frequency is unstable, consult with the governor manufacturer. If the frequency is stable, proceed to step

30 Table 5-2. Troubleshooting Chart - Continued. MALFUNCTION TEST OR INSPECTION CORRECTIVE ACTION 7. POOR VOLTAGE STABILITY - Continued. Step 2. Verify that voltage does not fluctuate to the point when K1 either energizes or deenergizes. If this condition occurs, refer to MALFUNCTION 2. If this condition does not exist, proceed to step 3. Step 3. Verify that the sensing voltage and input power are not taken from the same power isolation transformer secondary. If the above condition exists, reconnect sensing to a separate source. If the above condition does not exist, proceed to step 4. Step 4. Verify that R4 is not maladjusted. If R4 is maladjusted, adjust R4 to proper setting. If R4 is not maladjusted, proceed to step 5. Step 5. Verify that the no-load field voltage is at rated. If the no-load field voltage is below rated, refer to paragraph 3-2c, If the no-load field voltage is at rated, proceed to step 6. Step 6. Check for fault in either exciter or generator. If a fault exists, correct fault condition. If a fault does not exist, proceed to step 7. Step 7. If the above steps fail to correct the malfunction, replace or repair the voltage regulator as necessary. 8. VOLTAGE RECOVER SLOW WITH LOAD CHANGE. Step 1. Verify that the correct regulator is being used for the application. If the incorrect regulator is being used, contact Basler Electric. If the correct regulator is being used, proceed to step 2. Step 2. Verify that R4 is not maladjusted. If R4 is maladjusted, adjust R4 to proper setting. If R4 is not maladjusted, proceed to step

31 Table 5-2. Troubleshooting Chart - Continued. MALFUNCTION TEST OR INSPECTION CORRECTIVE ACTION 8. VOLTAGE RECOVER SLOW WITH LOAD CHANGE - Continued. Step 3. Verify that the generator frequency is stable. If the frequency is unstable, consult with the governor manufacturer. If the frequency is stable, proceed to step 4. Step 4. If the above steps fail to correct the malfunction, replace or repair the voltage regulator as necessary. 9. PARALLEL GENERATORS DO NOT DIVIDE REAL KW LOAD EQUALLY. Consult with the governor manufacturer for improving the power sensing of the governor and/or adjustment of the governor droop setting. 10. NO REACTIVE DROOP COMPENSATION CAN BE OBTAINED FOR PARALLEL GENERATORS. Step 1. Verify that the tap on R25 is not set to the minimum position. If the tap is set to the minimum position, adjust R25 to obtain the required droop. If the tap is set properly, proceed to step 2. Step 2. Verify that the Parallel CT provides the required 3 to 5 A secondary current. If the CT does not provide the required 3 to 5 A secondary current, refer to paragraph 3-3. If the CT does provide the required 3 to 5 A secondary current, proceed to step 3. Step 3. Verify that terminals 1 and 2 of the regulator are not shorted by the UNIT/PARALLEL switch. If the switch is set to UNIT, set switch to PARALLEL. If the terminals are shorted, replace the switch and/or repair the wiring. If the terminals are shorted, proceed to step 4. Step 4. If the above steps fail to correct the malfunction, replace or repair the voltage regulator as necessary. 5-9

32 Table 5-2. Troubleshooting Chart - Continued. MALFUNCTION TEST OR INSPECTION CORRECTIVE ACTION 11. PARALLEL GENERATORS DO NOT DIVIDE REACTIVE KVAR LOAD EQUALLY. (Circulating Reactive Current Between Generators. Step 1. Verify that the tap on R25 is not set to the minimum position. If the tap is set to the minimum position, adjust R25 to obtain the required droop. If the tap is set properly, proceed to step 2. Step 2. Verify that the Parallel CT provides the required 3 to 5 A secondary current. If the CT does not provide the required 3 to 5 A secondary current, refer to paragraph 3-3. If the CT does provide the required 3 to 5 A secondary current, proceed to step 3. Step 3. Verify that the paralleling CT's polarity is correct. If the CT's polarity is incorrect, reverse the CT secondary leads. If the CT's polarity is correct, proceed to step 4. Step 4. Verify that the paralleling CT is in the correct generator phase (line). If the CT is not in the correct phase, place CT in correct line. If the CT is in the correct phase, proceed to step 5. Step 5. Check that all paralleled generators have the same type of sensing (either single-phase or three-phase). If all paralleled generators do not have the same type of sensing, adjust R25 to compensate. If all paralleled generators do have the same type of sensing, proceed to step 6. Step 6. If the above steps fail to correct the malfunction, replace or repair the voltage regulator as necessary. 5-10

33 ATTACHMENT A GENERATING UNIT DATA SHEET This sheet, when filled out at the time of installation, will save valuable time in any future emergency as a ready reference for generator equipment specifications. Use the back of the sheet for additional data or records of maintenance. Unit No. Location Date Installed Installed by Date in Service 1. ENGINE Manufactured by Model No. Serial No. HP RPM Type: { Gas { Gasoline { Diesel { Gas Turbine { Steam Turbine { Normally Aspirated { Supercharged { Turbosupercharged 2. GOVERNOR Manufactured by Model No. Serial No. Sensing 3. GENERATOR Manufactured by Model No. Serial No. RPM Service Factor Output : KV/KVA CPS PF Volts Phase Delta Wye Short Circuit Parallel Operation Number of Leads Field: No Load Volts Amps: Full-Load Volts Amps Overload Volts Amps: Resistance Cold Hot 4. EXCITER Manufactured by Model No. Serial No. kw: RPM Type: { Brush Rotary { Brushless Rotary { Static Output: No Load Volts Amps: Full-Load Volts Amps Overload Volts Amps: Resistance Cold Hot 5. REGULATOR Basler Electric Model Serial No. Series Boost Option Model No. RFI Model No. CT s PT s Parallel Operation Isolation Transformer

INSTRUCTION MANUAL FOR VOLTAGE REGULATOR APR P/N

INSTRUCTION MANUAL FOR VOLTAGE REGULATOR APR P/N INSTRUCTION MANUAL FOR VOLTAGE REGULATOR APR 125-5 P/N 9168800100 Publication: 9168800990 Revision: J 03/09 INTRODUCTION This instruction manual provides information about the operation and installation

More information

INSTRUCTION MANUAL FOR. VOLTAGE REGULATOR Model: APR Part Number:

INSTRUCTION MANUAL FOR. VOLTAGE REGULATOR Model: APR Part Number: INSTRUCTION MANUAL FOR VOLTAGE REGULATOR Model: APR 125-5 Part Number: 9 1688 00 100 Publication Number: 9 1688 00 990 Revision H: 07/2001 CONTENTS SECTION 1 GENERAL INFORMATION...1-1 DESCRIPTION... 1-1

More information

MAGNAMAX DVR DIGITAL VOLTAGE REGULATOR

MAGNAMAX DVR DIGITAL VOLTAGE REGULATOR MAGNAMAX DVR DIGITAL VOLTAGE REGULATOR TECHNICAL MANUAL MODEL DVR 2000 AND DVR 2000C FIGURE 1 - FRONT AND REAR VIEW OF VOLTAGE REGULATOR...4 SECTION 1- INTRODUCTION...5 GENERAL DESCRIPTION...5 SPECIFICATIONS...5

More information

ELECTRONIC MANUAL VOLTAGE CONTROL Model: MVC 300. Part Number:

ELECTRONIC MANUAL VOLTAGE CONTROL Model: MVC 300. Part Number: ELECTRONIC MANUAL VOLTAGE CONTROL Model: MVC 300 Part Number: 9 1210 00 106 Publication Number: 9 1210 00 993 Date: July, 1993 Revision F: July, 1996 WARNING To prevent personal injury or equipment damage,

More information

Instruction Manual. Installation Operation Maintenance. KCR 760 Voltage Regulator

Instruction Manual. Installation Operation Maintenance. KCR 760 Voltage Regulator Publication 351-01002-00A, 09/23/05 Instruction Manual Installation Operation Maintenance KCR 760 Voltage Regulator Page 1 Kato Engineering Inc. P.O. Box 8447 Mankato, MN USA 56002-8447 Tel: 507-625-4011

More information

ENGINE GOVERNING SYSTEMS LSM672 LOAD SHARING MODULE. GOVERNORS AMERICA CORP. 720 Silver Street Agawam, MA , USA MEMBER

ENGINE GOVERNING SYSTEMS LSM672 LOAD SHARING MODULE. GOVERNORS AMERICA CORP. 720 Silver Street Agawam, MA , USA MEMBER ENGINE GOVERNING SYSTEMS LSM672 LOAD SHARING MODULE MEMBER GOVERNORS AMERICA CORP. 720 Silver Street Agawam, MA 01001-2907, USA LSM672 LOAD SHARING MODULE PRODUCT TECHNICAL INFORMATION PTI 4000 AUGUST

More information

PM300 VOLTAGE REGULATOR INSTRUCTION MANUAL

PM300 VOLTAGE REGULATOR INSTRUCTION MANUAL PM300 VOLTAGE REGULATOR INSTRUCTION MANUAL INTRODUCTION The PM300 voltage regulator is an encapsulated electronic voltage regulator that controls the output of a brushless AC generator by regulating the

More information

INSTALLATION AND SET-UP MANUAL FOR THE NEW: AVR-07. A CONTROLPAK AVR Automatic Voltage Regulator for three-phase and single-phase alternators

INSTALLATION AND SET-UP MANUAL FOR THE NEW: AVR-07. A CONTROLPAK AVR Automatic Voltage Regulator for three-phase and single-phase alternators INSTALLATION AND SET-UP MANUAL FOR THE NEW: AVR-07 A CONTROLPAK AVR Automatic Voltage Regulator for three-phase and single-phase alternators This is a premium quality product at a reasonable price, and

More information

XR500B Universal Voltage Regulator

XR500B Universal Voltage Regulator XR500B Universal Voltage Regulator The XR500B is a unique voltage regulator that is designed specifically for Professional Electrical Generator Service and Repair Technicians. The XR500B incorporates patented

More information

James Hamilton Electrical Pty Ltd (Inc in Qld) A.C.N trading as. Power Drive Systems. Generator Control Specialists

James Hamilton Electrical Pty Ltd (Inc in Qld) A.C.N trading as. Power Drive Systems. Generator Control Specialists James Hamilton Electrical Pty Ltd (Inc in Qld) A.C.N. 010 848 389 trading as Power Drive Systems Generator Control Specialists 48A Ainsdale Street Telephone: 0500 800 225 P.O. Box 30 West Chermside, Qld

More information

PM300E Voltage Regulator Instruction Manual

PM300E Voltage Regulator Instruction Manual PM300E Voltage Regulator Instruction Manual A Regal Brand 1. INTRODUCTION The PM300E voltage regulator is an encapsulated electronic voltage regulator which controls the output of a brushless AC generator

More information

ADVR-12. Hybrid Universal Analog Digital Voltage Regulator Operation Manual

ADVR-12. Hybrid Universal Analog Digital Voltage Regulator Operation Manual ADVR-12 Hybrid Universal Analog Digital Voltage Regulator Operation Manual Adapter plugs for Digital Regulator Self Excited Automatic Voltage Regulator For use in Brushless PMG and Auxiliary Winding 4501

More information

MX431 Generator Automatic Voltage Regulator Operation Manual

MX431 Generator Automatic Voltage Regulator Operation Manual Generator Automatic Voltage Regulator Operation Manual Self Excited Automatic Voltage Regulator 1 1. SPECIFICATION Sensing Input Voltage Frequency 190 ~ 264 VAC Max, 1 phase, 2 wire 50 / 60 Hz, selectable

More information

EA07. Generator Automatic Voltage Regulator Operation Manual

EA07. Generator Automatic Voltage Regulator Operation Manual EA07 Generator Automatic Voltage Regulator Operation Manual Suitable for Single or Three Phase Self Excited Brushless Generator Compatible replacement for Mecc Alte SR-7 * Not a genuine Mecc Alte product.

More information

ESD5500E Series Speed Control Unit

ESD5500E Series Speed Control Unit ESD5500E Series Speed Control Unit 1 SPECIFICATIONS INTRODUCTION PERFORMANCE Isochronous Operation ± 0.25% or better Speed Range / Governor 1-7.5 KHz Continuous Speed Drift with Temperature ±1% Maximum

More information

MODEL 422 Submersible Pump Controller

MODEL 422 Submersible Pump Controller MODEL 422 Submersible Pump Controller Monitors True Motor Power (volts x current x power factor) Detects Motor Overload or Underload Operates on 120 or 240VAC, Single-phase or 3-phase Built-in Trip and

More information

AVR Hybrid Universal Analog Digital Voltage Regulator Operation Manual

AVR Hybrid Universal Analog Digital Voltage Regulator Operation Manual AVR 63-12 Hybrid Universal Analog Digital Voltage Regulator Operation Manual Self Excited Automatic Voltage Regulator For use in Brushless PMG and Auxiliary Winding 1. SUMMARY The AVR 63-12 is a totally

More information

FAULT FINDING MANUAL. For Stamford AC Generators

FAULT FINDING MANUAL. For Stamford AC Generators FAULT FINDING MANUAL For Stamford AC Generators 1 SAFETY PRECAUTIONS Test procedures recommended in this manual assume that the reader is fully conversant with electrical safety principles, and is familiar

More information

AIR COOLED RECTIFIER SPECIFICATION S-50-A

AIR COOLED RECTIFIER SPECIFICATION S-50-A SPECIFICATIONS AIR COOLED RECTIFIER Spec50a1 5JAN1999 SPECIFICATION S-50-A HIGH VOLTAGE SINGLE TRANSFORMER AIR COOLED RECTIFIER Standard output power range: 250 to 600 volts at 100 to 1,200 amperes TECHNICAL

More information

ENGINE GOVERNING SYSTEMS

ENGINE GOVERNING SYSTEMS ENGINE GOVERNING SYSTEMS ESD5400 Series Speed Control Unit INSTALLATION The speed control unit is rugged enough to be placed in a control cabinet or engine mounted enclosure with other dedicated control

More information

C.E. Niehoff & Co. C653/C653A and C625 Alternators Troubleshooting Guide NOTICE. Hazard Definitions. Battery Charge Volt and Amp Values

C.E. Niehoff & Co. C653/C653A and C625 Alternators Troubleshooting Guide NOTICE. Hazard Definitions. Battery Charge Volt and Amp Values C.E. Niehoff & Co. C653/C653A and C625 Alternators Troubleshooting Guide Hazard Definitions These terms are used to bring attention to presence of hazards of various risk levels or to important information

More information

ENGEN -100/ENGEN -200 ENGINE GENERATOR CONTROLLER

ENGEN -100/ENGEN -200 ENGINE GENERATOR CONTROLLER ENGEN -100/ENGEN -200 ENGINE GENERATOR CONTROLLER The engine/generator controller is an integrated genset controller contained in a single, easy to install package. The controller contains a microprocessor-based

More information

UNIVERSAL VOLTAGE REGULATOR Manufactured in the USA by

UNIVERSAL VOLTAGE REGULATOR Manufactured in the USA by Model 348 UNIVERSAL VOLTAGE REGULATOR Manufactured in the USA by FLIGHT SYSTEMS www.flightsystems.com Description INSTALLATION and ADJUSTMENT INSTRUCTIONS The Model 348 Universal Regulator is a fully encapsulated

More information

SE2000BX Static Exciter

SE2000BX Static Exciter Rev 3 SE2000BX Static Exciter The SE2000BX Static Exciter is designed to replace most electronic, saturable reactor and rotary exciters used on slip ring or rotor fed electric generators. The SE2000BX

More information

PF Guard Power Factor Capacitor Bank Installation, Operation, and Maintenance Manual

PF Guard Power Factor Capacitor Bank Installation, Operation, and Maintenance Manual PF Guard Power Factor Capacitor Bank Installation, Operation, and Maintenance Manual No part of this publication may be reproduced, stored in a retrieval system, or transmitted in any form or by any means,

More information

A3Z OPERATING MANUAL

A3Z OPERATING MANUAL A3Z OPERATING MANUAL TABLE OF CONTENTS Introduction... p. 2 Features... p. 2 Description... p. 3 Theory of Operation... p. 3 Installation... p. 4 Electrical Connections... p. 5 Options... p. 6 Warranty...

More information

PM500. Voltage Regulator User Manual. A Regal Brand. Scan here for other languages.

PM500. Voltage Regulator User Manual. A Regal Brand. Scan here for other languages. PM500 Voltage Regulator User Manual A Regal Brand Scan here for other languages. Introduction The PM500 is an encapsulated electronic voltage regulator intended for use with Marathon Generators PMG system.

More information

A6Z OPERATING MANUAL

A6Z OPERATING MANUAL A6Z OPERATING MANUAL TABLE OF CONTENTS Introduction... p. 2 Features... p. 2 Description... p. 3 Theory of Operation... p. 3 Installation... p. 4 Electrical Connections... p. 5 Options... p. 6 Warranty.p.

More information

MaxPak Plus Analog DC V S Drive

MaxPak Plus Analog DC V S Drive Three-Phase 3-600 HP non-regenerative and 5-150 HP regenerative drives Designed to accommodate a wide range of industrial requirements, the DC V S Drive has been widely applied worldwide. Selected ratings

More information

2301A Load Sharing & Speed Control with Dual Dynamics. Product Manual (Revision NEW, 1990) Original Instructions

2301A Load Sharing & Speed Control with Dual Dynamics. Product Manual (Revision NEW, 1990) Original Instructions Product Manual 82046 (Revision NEW, 1990) Original Instructions 2301A Load Sharing & Speed Control with Dual Dynamics Installation and Operation Manual General Precautions Read this entire manual and all

More information

EA16. Generator Automatic Voltage Regulator Operation Manual

EA16. Generator Automatic Voltage Regulator Operation Manual EA16 Generator Automatic Voltage egulator Operation Manual Universal 16Amp elf Excited Automatic Voltage egulator for use in 220 / 380 / 440 / 480 VAC brushless generators with paralleling compatibility

More information

Specifications. Minimum Build Up Volts 3.5vac. Voltage Regulator

Specifications. Minimum Build Up Volts 3.5vac. Voltage Regulator SE1500AX Static Exciter The SE1500AX Static Exciter is a 100amp complete static exciter designed to replace older rotary, electronic and magnetic amplifier types of exciters. Installation of the SE1500AX

More information

ESC2301. Universal Electronic Governor Controller Operation Manual

ESC2301. Universal Electronic Governor Controller Operation Manual ESC2301 Universal Electronic Governor Controller Operation Manual *Replaces most Woodward, Barber Colman & Cummins Speed Controls Features Smoke Limit Control, Idle Speed Control, 12V or 24V input Suitable

More information

Product Manual (Revision B) Original Instructions. EPG Electrically Powered Governor Models 501 and Installation and Operation Manual

Product Manual (Revision B) Original Instructions. EPG Electrically Powered Governor Models 501 and Installation and Operation Manual Product Manual 82448 (Revision B) Original Instructions EPG Electrically Powered Governor Models 501 and 1701 Installation and Operation Manual General Precautions Read this entire manual and all other

More information

INSTALLING, OPERATING AND MAINTAINING THE MODEL D1028 COMPUTER INPUT BI-DIRECTIONAL GENERATOR FIELD REGULATOR INSTRUCTION MANUAL # S-225

INSTALLING, OPERATING AND MAINTAINING THE MODEL D1028 COMPUTER INPUT BI-DIRECTIONAL GENERATOR FIELD REGULATOR INSTRUCTION MANUAL # S-225 INSTALLING, OPERATING AND MAINTAINING THE MODEL D1028 COMPUTER INPUT BI-DIRECTIONAL GENERATOR FIELD REGULATOR INSTRUCTION MANUAL # S-225 INSTALLING, OPERATING AND MAINTAINING THE MODEL D1028 BI-DIRECTIONAL

More information

Maintenance Manual 13 AMPERE POWER SUPPLY 19A704647P1-P3. Mobile Communications LBI-31801C

Maintenance Manual 13 AMPERE POWER SUPPLY 19A704647P1-P3. Mobile Communications LBI-31801C C Mobile Communications 13 AMPERE POWER SUPPLY 19A704647P1-P3 CAUTION THESE SERVICING INSTRUCTIONS ARE FOR USE BY QUALI- FIED PERSONNEL ONLY. TO AVOID ELECTRIC SHOCK DO NOT PERFORM ANY SERVICING OTHER

More information

EG3000. Generator Electronic Governor Controller Operation Manual

EG3000. Generator Electronic Governor Controller Operation Manual EG3000 Generator Electronic Governor Controller Operation Manual Smoke Limit Control, Idle Speed Control, suitable for Builtin, Non-Built-in and PT Pump Type Actuator. SP POWERWORLD LTD Willows, Waterside,

More information

VoltPro VP4 Automatic Voltage Regulator

VoltPro VP4 Automatic Voltage Regulator VoltPro VP4 Automatic Voltage Regulator The VoltPro VP4 Automatic Voltage Regulator is an affordable generator voltage regulator that is designed for the consumer market and can replace many popular voltage

More information

2. AC SERVICE AND MOTOR REQUIRED 1. ENCLOSURE REQUIRED

2. AC SERVICE AND MOTOR REQUIRED 1. ENCLOSURE REQUIRED 1. ENCLOSURE REQUIRED If the OC1 control is furnished as an open-chassis unit (standard), mount control in an enclosure 12 x 10 x 5 or larger and mount enclosure where room temperature does not exceed

More information

Load Sharing Module. Analog Output Installation, Operation, and Calibration Manual. Manual 26011

Load Sharing Module. Analog Output Installation, Operation, and Calibration Manual. Manual 26011 26011 Load Sharing Module Analog Output 9907-173 Installation, Operation, and Calibration Manual Manual 26011 ! WARNING Read this entire manual and all other publications pertaining to the work to be performed

More information

Power-Tronics, Inc. Electronic Voltage Regulators and Static Exciters P.O. Box , Kerrville, Texas 78029

Power-Tronics, Inc. Electronic Voltage Regulators and Static Exciters P.O. Box , Kerrville, Texas 78029 Power-Tronics, Inc. Electronic Voltage Regulators and Static Exciters P.O. Box 291509, Kerrville, Texas 78029 Phone: 830.895.4700 Fax: 830.895.4703 Email: pwrtron@power-tronics.com Web: www.power-tronics.com

More information

4.0 OPERATION Type ITH-T Relay

4.0 OPERATION Type ITH-T Relay 41-771.2 Type ITH-T Relay 3.3 OPERATION INDICATOR This operation indicator is a small solenoid coil connected in the trip circuit. When the coil is energized a spring-restrained armature releases the white

More information

Matrix APAX. 380V-415V 50Hz TECHNICAL REFERENCE MANUAL

Matrix APAX. 380V-415V 50Hz TECHNICAL REFERENCE MANUAL Matrix APAX 380V-415V 50Hz TECHNICAL REFERENCE MANUAL WARNING High Voltage! Only a qualified electrician can carry out the electrical installation of this filter. Quick Reference ❶ Performance Data Pages

More information

2.0 CONSTRUCTION 3.0 OPERATION. SA-1 Generator Differential Relay - Class 1E 2.5 TRIP CIRCUIT

2.0 CONSTRUCTION 3.0 OPERATION. SA-1 Generator Differential Relay - Class 1E 2.5 TRIP CIRCUIT 41-348.11C SA-1 Generator Differential Relay - Class 1E 2.0 CONSTRUCTION The type SA-1 relay consists of: Restraint Circuit Sensing Circuit Trip Circuit Surge Protection Circuit Operating Circuit Amplifier

More information

ESD5550 / 5570 Series Speed Control Units

ESD5550 / 5570 Series Speed Control Units ESD5550 / 5570 Series Speed Control Units 1 The speed control unit is rugged enough to be placed in a control cabinet or engine mounted enclosure with other dedicated control equipment. If water, mist,

More information

Pretest Module 21 Units 1-4 AC Generators & Three-Phase Motors

Pretest Module 21 Units 1-4 AC Generators & Three-Phase Motors Pretest Module 21 Units 1-4 AC Generators & Three-Phase Motors 1. What are the two main parts of a three-phase motor? Stator and Rotor 2. Which part of a three-phase squirrel-cage induction motor is a

More information

C.E. Niehoff & Co. N1601, N1602, N1603, and N1604 Alternator Troubleshooting Guide NOTICE. Hazard Definitions. Battery Charge Volt and Amp Values

C.E. Niehoff & Co. N1601, N1602, N1603, and N1604 Alternator Troubleshooting Guide NOTICE. Hazard Definitions. Battery Charge Volt and Amp Values C.E. Niehoff & Co. N1601, N1602, N1603, and N1604 Alternator Troubleshooting Guide Hazard Definitions These terms are used to bring attention to presence of hazard(s) of various risk levels or to important

More information

Graham. Vari Speed S1000 Instruction Manual. TRANSMISSIONS, Inc. Installation, Operation and Maintenance Manual

Graham. Vari Speed S1000 Instruction Manual. TRANSMISSIONS, Inc. Installation, Operation and Maintenance Manual Graham TRANSMISSIONS, Inc. Installation, Operation and Maintenance Manual Vari Speed S1000 Instruction Manual TABLE OF CONTENTS Introduction 4 Unit Features 5 Operating Conditions 6 Specifications 7 Ratings

More information

5001TCP SPEED CONTROLLER

5001TCP SPEED CONTROLLER VARIABLE SPEED DRIVE CONTROLLER INSTALLATION AND SETTING UP MANUAL 5001TCP SPEED CONTROLLER With PC101 Torque Limit Control WARNING Disconnect all incoming power before working on this equipment. Follow

More information

High Frequency SineWave Guardian TM

High Frequency SineWave Guardian TM High Frequency SineWave Guardian TM 380V 480V INSTALLATION GUIDE FORM: SHF-IG-E REL. January 2018 REV. 002 2018 MTE Corporation High Voltage! Only a qualified electrician can carry out the electrical installation

More information

M T E C o r p o r a t i o n MATRIX FILTER. SERIES B Volts, 50HZ USER MANUAL PART NO. INSTR REL MTE Corporation

M T E C o r p o r a t i o n MATRIX FILTER. SERIES B Volts, 50HZ USER MANUAL PART NO. INSTR REL MTE Corporation M T E C o r p o r a t i o n MATRIX FILTER SERIES B 380-415 Volts, 50HZ USER MANUAL PART NO. INSTR - 015 REL. 060628 2006 MTE Corporation IMPORTANT USER INFORMATION NOTICE The MTE Corporation Matrix Filter

More information

10V. the rack of the oil pump must be on the

10V. the rack of the oil pump must be on the P.E.D 20.. ESG2002 series ELECTRONIC GOVERNOR INSTRUCTION A1000C-W ELECTROMAGNETIC ACTUATOR Before inst al l el ectromag neti c, p lea se inspect that the rack of the oil pump shouldn' t be stuck in any

More information

SECTION DC POWER SUPPLY/BATTERY CHARGER

SECTION DC POWER SUPPLY/BATTERY CHARGER SECTION 26 33 05 PART 1 - GENERAL 1.1 THE REQUIREMENT A. The CONTRACTOR shall provide the single-phase heavy-duty industrial battery charger and all accessories required, complete and operable, in accordance

More information

TECHNICAL DATA SHEET AIRCRAFT GROUND POWER UNIT MODEL NO. B809D-1

TECHNICAL DATA SHEET AIRCRAFT GROUND POWER UNIT MODEL NO. B809D-1 COGNIZANT SERVICE: U.S.A.F. NATIONAL STOCK NUMBER: 6115-01-502-7927 OVERALL DIMENSIONS AND WEIGHT: Height: 63 Inches Length: 103 Inches Width: 66 Inches Weight (Dry): 4,372 Lbs. FUNCTIONAL DESCRIPTION:

More information

5001TCP SPEED CONTROLLER

5001TCP SPEED CONTROLLER INSTALLATION AND SETTING UP MANUAL 5001TCP SPEED CONTROLLER WARNING Disconnect all incoming power before working on this equipment. Follow power lockout procedures. Use extreme caution around electrical

More information

Product Manual (Revision C) Original Instructions. Air/Fuel Ratio Control. Installation and Operation Manual

Product Manual (Revision C) Original Instructions. Air/Fuel Ratio Control. Installation and Operation Manual Product Manual 36044 (Revision C) Original Instructions Installation and Operation Manual General Precautions Read this entire manual and all other publications pertaining to the work to be performed before

More information

EG1069X. Generator Electronic Governor Controller Operation Manual

EG1069X. Generator Electronic Governor Controller Operation Manual EG1069X Generator Electronic Governor Controller Operation Manual Smoke Limit Controller Compatible with Barber Colman Dyn1-1069X series *Use for reference purpose only and not a genuine Barber Colman

More information

AFM500X Automatic Flashing Module

AFM500X Automatic Flashing Module AFM500X Automatic Flashing Module The Power-Tronics AFM500X Automatic Flashing Module is a convenient and compact optional build up module for all Power-Tronics UVR and XR series Universal Voltage Regulators.

More information

ESD5100 Series Speed Control Unit PART NUMBER ESD5120 ESD (127)

ESD5100 Series Speed Control Unit PART NUMBER ESD5120 ESD (127) ESD5100 Series Speed Control Unit 1 INTRODUCTI The ESD5100 Series speed control unit is an all electronic device designed to control engine speed with fast and precise response to transient load changes.

More information

CONTROL FEATURES AVAILABLE OPTIONS

CONTROL FEATURES AVAILABLE OPTIONS Vari Speed A2000 TABLE OF CONTENTS Control Features Options Application Data Operating Condition s Control Ratings Chart Mounting Dimensions Installation and Wiring Typical Wiring Diagram Schematic (Block

More information

Product Manual (Revision D, 5/2015) Original Instructions. 2301A Speed Control. Installation and Operation Manual

Product Manual (Revision D, 5/2015) Original Instructions. 2301A Speed Control. Installation and Operation Manual Product Manual 82020 (Revision D, 5/2015) Original Instructions 2301A Speed Control Installation and Operation Manual General Precautions Read this entire manual and all other publications pertaining to

More information

SE-3SCR-LM MANUAL MOTOR LOAD MANAGER

SE-3SCR-LM MANUAL MOTOR LOAD MANAGER 3714 Kinnear Place Saskatoon, SK Canada S7P 0A6 Ph: (306) 373-5505 Fx: (306) 374-2245 www.littelfuse.com/relayscontrols SE-3SCR-LM MANUAL MOTOR LOAD MANAGER MARCH 5, 2013 REVISION 4 MOTOR LOAD MANAGER

More information

Features IN THIS CHAPTER

Features IN THIS CHAPTER CHAPTER THREE 3Special Features IN THIS CHAPTER Motor Braking Regeneration Solutions Sharing the Power Bus: V Bus+ and V Bus- Current Foldback (I T Limit) Front Panel Test Points Resolver Alignment ➂ Special

More information

3. OPERATION 2.1. RESTRAINT CIRCUIT 2.6. INDICATING CIRCUIT 2.2. OPERATING CIRCUIT 2.7. SURGE PROTECTION CIRCUIT 2.3.

3. OPERATION 2.1. RESTRAINT CIRCUIT 2.6. INDICATING CIRCUIT 2.2. OPERATING CIRCUIT 2.7. SURGE PROTECTION CIRCUIT 2.3. 41-348.1H Type SA-1 2.1. RESTRAINT CIRCUIT The restraint circuit of each phase consists of a center-tapped transformer, a resistor, and a full wave rectifier bridge. The outputs of all the rectifiers are

More information

PROCESS ELECTRONICS CORPORATION

PROCESS ELECTRONICS CORPORATION MINIVERTER MANUAL PROCESS ELECTRONICS CORPORATION 100 BRICKYARD ROAD MOUNT HOLLY, NORTH CAROLINA 28120 TELEPHONE (800) 421-9107 FAX (704) 827-9595 SALES@PECRECTIFIER.COM WWW.PECRECTIFIER.COM SOLID STATE

More information

A1P OPERATING MANUAL

A1P OPERATING MANUAL A1P OPERATING MANUAL TABLE OF CONTENTS Introduction... p. 2 Features... p. 2 Description... p. 3 Theory of Operation... p. 3 Installation... p. 4 Electrical Connections... p. 5 Options... p. 6 Warranty...

More information

REFERENCE MANUAL FORM: MX-TRM-E REL REV MTE

REFERENCE MANUAL FORM: MX-TRM-E REL REV MTE Matrix APAX 380V-415V 50Hz TECHNICAL REFERENCE MANUAL FORM: MX-TRM-E REL. September 2014 REV. 002 2014 MTE Corporation WARNING High Voltage! Only a qualified electrician can carry out the electrical installation

More information

Basics of Paralleling

Basics of Paralleling Basics of Paralleling Revised: February 1, 2017 2017 Cummins All Rights Reserved Course Objectives Participants will be able to: Discuss basic paralleling control functions to gain a better understanding

More information

INSTALLATION, OPERATION & MAINTENANCE SERIES ABC11B-120-XX BATTERY CHARGERS

INSTALLATION, OPERATION & MAINTENANCE SERIES ABC11B-120-XX BATTERY CHARGERS MANUAL NUMBER: 64073 REV: 2 DATE: October 3, 2006 INSTALLATION, OPERATION & MAINTENANCE SERIES ABC11B-120-XX BATTERY CHARGERS AMERICAN BATTERY CHARGING, INC. P.O. BOX 17040 28 MAPLE AVENUE SMITHFIELD,

More information

Product Manual (Revision C) Original Instructions. Load Sharing Module. Analog Output Installation and Operation Manual

Product Manual (Revision C) Original Instructions. Load Sharing Module. Analog Output Installation and Operation Manual Product Manual 26011 (Revision C) Original Instructions Load Sharing Module Analog Output 9907-173 Installation and Operation Manual General Precautions Read this entire manual and all other publications

More information

Medium Voltage Standby non-paralleling Control GUIDE FORM SPECIFICATION

Medium Voltage Standby non-paralleling Control GUIDE FORM SPECIFICATION Medium Voltage Standby non-paralleling Control 1. GENERAL GUIDE FORM SPECIFICATION A. The requirements of the contract, Division 1, and part 16 apply to work in this section. 1.01 SECTIONS INCLUDE A. Medium

More information

600 Series Troubleshooting Guide for C651 and C654 Alternators

600 Series Troubleshooting Guide for C651 and C654 Alternators 600 Series Troubleshooting Guide for C651 and C654 Alternators Hazard Definitions These terms are used to bring attention to presence of hazards of various risk levels or to important information concerning

More information

Reproduction or other use of this Manual, without the express written consent of Vulcan, is prohibited.

Reproduction or other use of this Manual, without the express written consent of Vulcan, is prohibited. SERVICE MANUAL ELECTRIC BRAISING PANS (30 & 40 GALLON) VE30 VE40 ML-126849 ML-126850 VE40 SHOWN - NOTICE - This Manual is prepared for the use of trained Vulcan Service Technicians and should not be used

More information

SERIES 2335 SINGLE-PHASE ADJUSTABLE-SPEED DC MOTOR CONTROLLERS (1/6-2 HP)

SERIES 2335 SINGLE-PHASE ADJUSTABLE-SPEED DC MOTOR CONTROLLERS (1/6-2 HP) Rev. 02/97 SERIES 2335 SINGLE-PHASE ADJUSTABLE-SPEED DC MOTOR CONTROLLERS (1/6-2 HP) TABLE OF CONTENTS SECTION TITLE PAGE I GENERAL INFORMATION 1 Introduction 1 General Description 1 Model Types 1 Motor

More information

C802/C802D/C802TD/C820 Alternators Troubleshooting Guide

C802/C802D/C802TD/C820 Alternators Troubleshooting Guide C802/C802D/C802TD/C820 Alternators Troubleshooting Guide Hazard Definitions These terms are used to bring attention to presence of hazards of various risk levels or to important information concerning

More information

Boston Gear Ratiotrol DC Motor Speed Control

Boston Gear Ratiotrol DC Motor Speed Control Boston Gear Ratiotrol DC Motor Speed Control P-3017-BG Doc. No. 60007 Installation and Operation DCX plus Series II Enclosed Models 1/12-1 HP a division of Altra Industrial Motion Contents l General Information

More information

SALDET SALES & SERVICE, INC. CLINTON TOWNSHIP, MICHIGAN

SALDET SALES & SERVICE, INC. CLINTON TOWNSHIP, MICHIGAN Form 1254 BRAKETRON Electronic Motor Brake Instructions SALDET SALES & SERVICE, INC. CLINTON TOWNSHIP, MICHIGAN TABLE OF CONTENTS SECTION TITLE PAGE I. Introduction 1 II. Specifications 1 III. Principles

More information

SCR Power Controllers

SCR Power Controllers SCR Power Controllers Instruction Manual SCR POWER CONTROLLERS TABLE OF CONTENTS General Description and Specifications...1 Firing Modes....2 Installation and Wiring...4 Operation...9 Troubleshooting...15

More information

Unit Protection System for Pumped-Storage Power Stations

Unit Protection System for Pumped-Storage Power Stations Unit Protection System for Pumped-Storage Power Stations 1. Introduction In many power systems, pumped-storage power stations are used in addition to run-of-river power stations. These power stations serve

More information

UG-5.7, UG-8, UG10 Governor

UG-5.7, UG-8, UG10 Governor 54042D UG-5.7, UG-8, UG10 Governor Installation Manual Manual 54042D ! WARNING Read this entire manual and all other publications pertaining to the work to be performed before installing, operating, or

More information

Series 20 Installation Instructions

Series 20 Installation Instructions Series 20 Installation Instructions Installation Instructions and field service checklist Read these instructions carefully. Failure to follow them could result in a fire or explosion causing property

More information

ACC Series Power Conditioner OPERATION & INSTALLATION MANUAL

ACC Series Power Conditioner OPERATION & INSTALLATION MANUAL ACC Series Power Conditioner OPERATION & INSTALLATION MANUAL PHASETEC digital power conditioners are designed to safely operate electrical equipment in the harshest power quality environments. With a wide

More information

UL/cUL FILE NUMBER E CE See last page of manual for CE Declaration of Conformity.

UL/cUL FILE NUMBER E CE See last page of manual for CE Declaration of Conformity. INSTALLATION, OPERATION and MAINTENANCE MANUAL MODEL SCPF1 15, 25, 40 & 65 AMP SCR POWER CONTROLS UL/cUL FILE NUMBER E151547 CE See last page of manual for CE Declaration of Conformity. AMETEK HDR POWER

More information

Kinetics Industries Inc. 140 Stokes Ave. Trenton, NJ Fax

Kinetics Industries Inc. 140 Stokes Ave. Trenton, NJ Fax Kinetics Industries Inc. 140 Stokes Ave. Trenton, NJ 08638 609-883-9700 609-883-0025 Fax Common optional features include: AC main line contactor, DC undervoltage and / or undercurrent relay, regenerative

More information

ESD-5500E Series - Speed Control Unit

ESD-5500E Series - Speed Control Unit ESD-5500E Series - Speed Control Unit INTRODUCTION The ESD-5500E Series speed control unit is an all electronic device designed to control engine speed with last and precise response to transient load

More information

Operation and Maintenance Manual

Operation and Maintenance Manual OM-2075 430577-31 011596 Operation and Maintenance Manual Model 90C24 Generator Set Part No. 500046 Hobart Brothers Company Airport Systems Group Ground Power Equipment Troy, OH 45373 U.S.A. This page

More information

M T E C o r p o r a t i o n MATRIX FILTER. SERIES B Volts, 50HZ USER MANUAL PART NO. INSTR REL MTE Corporation

M T E C o r p o r a t i o n MATRIX FILTER. SERIES B Volts, 50HZ USER MANUAL PART NO. INSTR REL MTE Corporation M T E C o r p o r a t i o n MATRIX FILTER SERIES B 380-415 Volts, 50HZ USER MANUAL PART NO. INSTR - 015 REL. 040709 2003 MTE Corporation IMPORTANT USER INFORMATION NOTICE The MTE Corporation Matrix Filter

More information

TROUBLESHOOTING GENERATOR UNITS

TROUBLESHOOTING GENERATOR UNITS TROUBLESHOOTING GENERATOR UNITS Figure 3.17 Troubleshooting Flow Chart For Direct Excited (Brush Type) Generators or later. 68 Troubleshooting Direct Excited (Brush Type) Generators Refer to Figure 3.17

More information

TRAC-3 TENSION READOUT AND CONTROL

TRAC-3 TENSION READOUT AND CONTROL Magnetic Power Systems, Inc. 1626 Manufacturers Drive. Fenton, MO 63026 Tel: 636.343.5550 Fax: 636.326.0608 magpowr@magpowr.com INSTRUCTION MANUAL TRAC-3 READOUT AND CONTROL For Control of Magnetic Particle

More information

COM Overcurrent Relay

COM Overcurrent Relay 41-102.1B COM Overcurrent Relay Figure 1: COM-5 Class 1E Relay (Front View) 9664A28 Photo Figure 2: COM-5 Class 1E Relay (Rear View) 9664A29 Photo Photo needed here 2 COM Overcurrent Relay 41-102.1B 3

More information

EG1065X. Compatible with Barber Colman* Dyn1-1065X series * Use for reference purpose only and not a genuine Barber Colman product.

EG1065X. Compatible with Barber Colman* Dyn1-1065X series * Use for reference purpose only and not a genuine Barber Colman product. EG1065X Generator Electronic Governor Controller Operation Manual Compatible with Barber Colman* Dyn1-1065X series * Use for reference purpose only and not a genuine Barber Colman product. Headquarters

More information

Automatic taper of charge rate for superior battery life through good equalization of cells and low water use rate.

Automatic taper of charge rate for superior battery life through good equalization of cells and low water use rate. FEATURES Automatic taper of charge rate for superior battery life through good equalization of cells and low water use rate. Silicon diodes with inherent surge protection operated at a conservative percentage

More information

Standby Power Systems

Standby Power Systems Source: Power Quality in Electrical Systems Chapter 13 Standby Power Systems The term standby power systems describes the equipment interposed between the utility power source and the electrical load to

More information

SECTION MOTOR CONTROL

SECTION MOTOR CONTROL SECTION 26 24 19 MOTOR CONTROL PART 1 - GENERAL 1.1 SECTION INCLUDES A. Manual motor starters B. Magnetic motor starters C. Combination magnetic motor starters D. Solid-state reduced voltage motor starters

More information

MATRIX FILTER USER MANUAL. SERIES D 600 Volts, 60HZ PART NO. INSTR 026 REL MTE Corporation

MATRIX FILTER USER MANUAL. SERIES D 600 Volts, 60HZ PART NO. INSTR 026 REL MTE Corporation MATRIX FILTER SERIES D 600 Volts, 60HZ USER MANUAL PART NO. INSTR 026 REL. 080920 2008 MTE Corporation IMPORTANT USER INFORMATION NOTICE The MTE Corporation Matrix Filter is designed for harmonic mitigation

More information

Product Manual (Revision K) Original Instructions. EG-3C and EG-R Actuators. Installation and Operation Manual

Product Manual (Revision K) Original Instructions. EG-3C and EG-R Actuators. Installation and Operation Manual Product Manual 37710 (Revision K) Original Instructions EG-3C and EG-R Actuators Installation and Operation Manual General Precautions Read this entire manual and all other publications pertaining to the

More information

EG3002. Electronic Engine Governor Controller User Manual

EG3002. Electronic Engine Governor Controller User Manual EG3002 Electronic Engine Governor Controller User Manual Engine Start Smoke Limiting function & IDLE Speed Setting For External, Built-in, PT-Pump type and hydraulic drive actuators Newly added extreme

More information

1329I Integrated Drive/Motor CE Filter Option Kit

1329I Integrated Drive/Motor CE Filter Option Kit Instruction Sheet 1329I Integrated Drive/Motor CE Filter Option Kit CE filter options are designed to be used with the 1329I Integrated Drive/Motor. The main function of the CE filter is to reduce the

More information

1/4HP - 7.5HP 120/240/277 VOLTS 50/60HZ

1/4HP - 7.5HP 120/240/277 VOLTS 50/60HZ Installation & Operating Procedures DG2 Series SINGLE PHASE CONVERTERS 1/4HP - 7.5HP 120/240/277 VOLTS 50/60HZ TABLE OF CONTENTS 1.0 DESCRIPTION... Pg. 1 2.0 INSTALLATION AND START-UP... Pg. 3 3.0 DRAWING

More information

Application Note CTAN #127

Application Note CTAN #127 Application Note CTAN #127 Guidelines and Considerations for Common Bus Connection of AC Drives An important advantage of AC drives with a fixed DC is the ability to connect the es together so that energy

More information