TPD Mini Hydro Project. Moawhango Concept Design Report

Size: px
Start display at page:

Download "TPD Mini Hydro Project. Moawhango Concept Design Report"

Transcription

1 TPD Mini Hydro Project Moawhango Concept Design Report

2 Contents 1. Introduction 1.1 Short history of the project 1.2 Structure of this report 2. Site Investigation 2.1 Structures and tailrace 2.2 Intakes and valves 2.3 Transmission 2.4 Communications 3. Design Concepts 3.1 Moawhango Mini Hydro Concept 3.2 Protection from spillway 3.3 Access 3.4 Generation potential 3.5 Regulation of compensation flow 3.6 Intake, pipework and valves Intake Pipework 3.7 Turbine 3.8 Generator 3.9 Civil works 3.10 Auxiliary mechanical plant 3.11 Electrical systems 3.12 Generator Protection 3.13 Station Control and communications 4. Construction Phase 4.1 Contract Structure

3 4.2 Contract Interfaces 4.3 M & E Installation Mechanical installation Electrical and Controls installation 4.4 Potential Contractors 4.5 Supervision and Commissioning Appendix A Drawing Schedule

4 1. Introduction 1.1 Short history of the project Lake Moawhango was formed during the construction of the Tongariro Power Development project by the construction of a 60 m high concrete arch dam across the Moawhango River, about 10 km north east of Waiouru. Lake Moawhango stores water diverted from the south eastern slopes of Mt Ruapehu via the Wahianoa Aqueduct and the Mangaio tunnel, and also from the surrounding catchment of the lake. The following figure shows the location of the lake and dam 1. 1 This figure is taken from the July 2002 Tongariro Power Development Assessment of Environmental Effects Figure 4.2 The Eastern Diversion. Most water from the lake is diverted northward via the Moawhango Tunnel to the upper Tongariro River and the headpond of the Rangipo Power Station. However, a compensation flow of 600 l/s is released from the dam down the Moawhango River. This project is to install a mini hydro at the base of the Moawhango dam and utilise the compensation flow to generate electricity. In August 2003, XXXX Power commissioned a feasibility report for the Mangaio and Moawhango Mini-hydro Schemes by Bryan Leyland Consulting Engineer and Pickens Consulting Ltd. The present scheme is based on their feasibility report. Both Bryan Leyland and Alan Pickens have been retained by XXXX to provide guidance and assistance in the preparation of the current work, which is the subject of this report.

5 1.2 Structure of this report The remainder of this report is divided in three sections. Section 2 summarises the main features of the existing plant that are pertinent to the proposed development. This information has been derived from drawings, from queries XXX has directed to XXXX, and from several site visits. Section 3 describes the concept design to date. It also describes some of the alternatives considered. This section should be read in conjunction with an examination of the concept drawings listed in Appendix A. Section 4 outlines a suggested construction methodology. This requires careful planning as the compensation flow must be maintained during construction, and work will need to be carried out in the vicinity of the present release point.

6 2. Site Investigation 2.1 Structures and tailrace There are two fixed cone valves located on the downstream face 12 m above the bottom of the dam, which terminate pipes running directly through the dam. The valve diameters are 84 and 18. The larger one, rated at 65 cumecs, is for rapid dewatering of the lake, and the smaller, rated at 2.5 cumecs, is for compensation flow. The valves are located within a protruding dormer structure, integral with the sloping downstream face of the dam. This valve house structure is provided with two levels. The upper level houses a hydraulic pumping unit, control panels, and a valve actuator. The lower level is divided into two smaller spaces, an isolation valve pit, and a discharge valve gallery. The lower level spaces are accessed from the upper level via floor plates and fixed ladders. The discharge valve gallery is open on the downstream side, and is provided with a safety handrail. Below the valve house is the lowest point of the spillway apron at the foot of the dam. The apron includes an integral raised concrete block plinth, approximately 3.6 m square and 1.2 m high. The upstream side of the plinth is joined to the downstream face of the dam. During construction of the dam, the plinth was provided at the outfall of the dam diversion opening. The diversion opening was plugged after completion of the dam, leaving the plinth exposed and presently redundant. This has been selected as the preferred location for the turbine. 2.2 Intakes and valves The intake to the pipes supplying the discharge valves is located on the vertical upstream face of the dam, slightly to the true right of the bottom of the old Moawhango River channel. The intake is approximately 11 m up the face of the dam. A single arched steel screen covers the entry to both discharge valve pipes. The screen has a total face area of approximately 50 m 2, and a bar gap of 127 mm. The average screen velocity at compensation flow is clearly quite negligible. However, higher local velocities in front of the compensation flow pipe would be expected. Nevertheless screen head loss will be minimal. Although the bar gap is insufficient to stop debris large enough to block a small turbine, this is not considered to be a significant problem. The water is relatively clean, most debris during normal inflows to the lake will accumulate at the entry to the Moawhango Tunnel, and the intake is at an intermediate depth between the bottom and surface of the lake, where both floating and sunken debris are unlikely to enter the intake. The pipe to the compensation flow discharge valve comprises an 18 m length of 2-10 diameter pipe, a 0.9 m long conical transition down to 450 mm NB pipe, and a 2.6 m long section at 450 mm NB, which includes an 450 mm NB gate valve for isolation of the discharge valve. The pipe has an elliptical entry bell-mouth, and is embedded in concrete over most of its length. It was made up of flanged short spools, most of the flanges now being embedded in the concrete. The bell-mouth, and also the exposed spools that mate with the valves are constructed of cast iron. The remaining spools which are embedded are fabricated stainless steel 2. The 8-0 diameter pipe for the draw down valve is similar. However, it is mainly constructed using stainless lined mild steel pipe. Both pipes terminate at the discharge valves. The discharge valves are of the fixed cone type; a type often referred to as Howell-Bunger valves. Both discharge valves have upstream isolation valves.

7 The 450 mm NB discharge valve is electrically actuated, and the 84 discharge valve and its isolation valve are both hydraulically actuated. The 450 mm NB isolation valve is a manually operated gate valve, and the 84 isolation valve is a butterfly valve. It is proposed to divert the compensation flow, presently released at the 450 mm NB discharge valve, to a hydro turbine for generation of electricity. 2.3 Transmission The Moawhango generator will be connected to the existing Tokaanu-Moawhanga 33 kv transmission line system that ends about 800 metres from the Moawhango dam. The backbone of this existing 33 kv system effectively consists of two sections; a 13 km, single circuit 33 kv overhead line that runs from the Tokaanu substation to the Ta Hanga switching station, and a 38 km double circuit 33 kv overhead line that runs from Ta Hanga to the Moawhanga Dam. Presently the line has nine small capacity transformers distributed along it's length (total capacity of 980 kva). These transformers provide electrical supply to the Tongariro tunnel system intakes, Tukino repeater site, and Rangipo dam. 2 While it is not completely clear from the drawings obtained by XXX if these 18 pipe spools embedded in the dam are stainless steel, this is most likely, as the larger 8-0 diameter draw-down pipe is stainless faced on the inside surface. Both pipes are of course very difficult to maintain or replace. 2.4 Communications The data communications requirements for Moawhango machine monitoring and control are minimal and these could be met by interfacing the machine controller to the Kingfisher RTU that has radio microwave communications with Tukino. We understand that the present communications system between Moawhango dam and Tokaanu consists of a Kingfisher telemetry data link connected to a microwave link for data and voice (and video). Discussions with Tokaanu C & I staff confirmed that any new communications installation would also follow this standard. Discussions with the XXXX Microwave contractor, Kevin Box, confirmed these systems are currently utilising Aprisa SE 4RF microwave units for data, voice and WAN interconnections.

8 3. Design Concepts 3.1 Moawhango Mini Hydro Concept Below the valve house on the downstream face of the dam is the lowest point of the spillway apron at the foot of the dam. The apron includes an integral raised concrete block plinth, approximately 3.6 m square and 1.2 m high. The mini hydro turbine and the vertical induction generator will be mounted on this concrete slab. A 450 mm NB steel pipe will be installed from the existing compensation flow valve to connect to the turbine inlet, as shown in drawing AP00821-M-501, a part of which is shown below. The compensation flow valve will be relocated further down the pipe to provide space for a 450 mm NB magnetic flowmeter. In addition, a new turbine isolation valve will be installed below the compensation valve Tee off: 3.2 Protection from spillway The generator-turbine unit would be located near the lowest point on the downstream side at the foot of the dam, which is also under the spillway crest. A deflection slab protruding above the valve gallery will provide shelter against spillway flow from directly above. However, during spilling, the generation plant will be deluged by spillway flow cascading down the spillway apron s stepped banks which border either side of the centre channel. A steep sided gorge just downstream of the dam rules out any possibility of building the hydro station further downstream. It is proposed to locate the generator-turbine unit centrally in the plinth that remained after the diversion opening was plugged, as described in 2.1. The generator-turbine unit will be partly protected from side flows by deflection at the walls of the plinth, and also the location is central under the deflection slab at the top of the valve house which enhances the protection from above.

9 The draft tube will be recessed into a cavity that will be cut into the plinth. The surrounding plinth concrete protects the draft tube, and the cut-out cavity conveys the turbine discharge to the lowest point of the channel, thereby gaining the maximum head. As a final protection the generator-turbine unit will be covered with a robust protection structure. The protection structure is fabricated with a 200 mm universal-column steel frame, and is formed in a truncated A-frame shape. The sloping sides of the A-frame will be covered with heavy steel plates. The upstream end face is partly covered with a removable steel plate panel, and the truncated top face is also plated but with a 500 mm diameter ventilation hole provided. The downstream end is left open apart from a frame cross member for strengthening. The completed protection structure will be a single fully integral unit strongly bolted to the concrete using chemset injection anchors. The unplated openings will allow access for inspection and minor maintenance, but for major disassembly the protection structure unit will be unbolted from its base, and craned clear of the generator-turbine unit. Similarly the generator-turbine unit would also then be unbolted from its base, and craned to a suitable locality for disassembly. Minor components could be craned to the upper level of the valve house for maintenance, using the in- situ monorail crane. However, cranage from the crest of the dam, and transport to a fully equipped workshop is probably preferable. The top surface of the plinth provides a convenient point of anchorage for the turbine, the protection structure, and the bottom of the penstock pipe. 3.3 Access The controls and most of the valves are located well inside in the existing valve house space, and can be safely reached using existing access arrangements via the dam galleries. The bypass valve is mounted in an exposed position, and this will require a special provision. The generator-turbine unit is also located in a position where easy access is not presently possible. This is especially so during winter months when the apron of the dam is ice covered. It is envisaged that the required access to the above equipment should be fairly infrequent. The following options for access have been considered: 1) Bypass valve: crane suspended personnel cage or bucket; permanent stainless steel fabricated platform mounted at the same level as the existing discharge valve gallery; demountable fabricated platform bolted to fixed brackets; harness. rigger clamber access using a safety 2) Generator-turbine unit: crane suspended personnel cage or bucket; a permanent stainless steel caged-ladder from the existing discharge valve gallery down to the mounting plinth; access via a downstream abutment and down the spillway apron steps. We are not presently sure how feasible this would be, and it is assumed that some improvements and extensions to the steps and ladder presently installed, are likely to be required.

10 The above access options as well as any other alternatives, should be examined during the HAZOP phase of the project. Moawhango Concept Design Report 3.4 Generation potential The generation will depend on the future management of storage in the lake. Modelling using historic daily lake levels, from January 1993 to January 2004 as shown in the figure below, indicated an average annual generation of approximately 2.1 GWh pa. 3.5 Regulation of compensation flow The current water permit requires that a minimum compensation flow of 600 l/s is maintained at all times. Conversely avoidance of excess compensation flow from the diversion is an important commercial requirement. The water captured in Lake Moawhango is used to generate electricity in the XXXX Energy Rangipo and Tokaanu hydro stations then, via Lake Taupo, all nine Mighty River Power Waikato River hydros. Previous estimates by ECNZ valued the water captured in this diversion at $149 MWh/(cumec.day). Therefore an accurately regulated release is required, and also a discharge valve must still be retained to release the compensation flow if the generation plant is unavailable. Three options for achieving a constant 600 l/s compensation flow have been considered: A regulated turbine, with a bypass valve for discharge when the turbine is not available,

11 An unregulated turbine sized for 600 l/s at the maximum storage level, with a bypass valve for supplementary discharge when the lake level is lower than maximum storage. In this arrangement the bypass valve would discharge virtually all of the time, An unregulated turbine sized for 600 l/s at the minimum storage level, with a bypass valve for discharge when the turbine is not available. In this arrangement the net head at the turbine would be kept constant by dissipating head through the turbine isolation valve when the lake level is higher than minimum storage. The generation that could be expected from each of the above options was modelled using historic lake levels. The modelling results are tabulated below: The regulated turbine achieved significantly more generation even though the modelling allowed for unregulated turbines having higher efficiency. The modelling suggests that the extra generation from a regulated turbine is likely to justify the extra cost of this option. The actual generation achieved from the Moawhango scheme will be dependent on the future storage management of the lake. 3.6 Intake, pipework and valves Intake No modifications to the existing intake are proposed. Although the screen bar gap of 127 mm is insufficient to stop debris large enough to block a small turbine, as described in 2.2, this is considered unlikely to cause any problems. The possibility of sedimentation build-up at the intake has also been raised. Unfortunately we did not identify any sediment surveys of the lake. However, most sediment from the tributaries would be expected to deposit as dunes near the point of entry to the lake, where the water velocities become low. Also the compensation flow intake is 12 m above the old river bed, and most of the lake outflow goes through the Moawhango Tunnel. To date there has not been any sediment observed in flows from the intake 3. If the sediment ever gets high enough in the future to cause problems, an environmentally acceptable approach may be to open the 84" drawdown valve during floods (when the dam is already spilling). This would probably keep the entry to the compensation flow pipe relatively clear, since the base of the drawdown valve entry bell is approximately 1.2 m lower than for the compensation valve Pipework

12 General All of the proposed new pipework will be installed downstream of the existing isolation valve for the compensation flow valve. Installation of the intake bulkhead during construction should not be necessary. Drawings AP00821-M-502 and AP00821-M-503 show the proposed pipework. The pipe route is kept in close to the face of the dam, and is mostly under the shadow of the valve house. Materials The penstock will be constructed using an 18" (450 mm NB) standard weight ANSI B fabricated carbon steel pipe, which will be extended from the present terminal flange, (where the existing 450 mm NB fixed cone valve is currently installed), down the face of the dam to the proposed turbine. GRP pipes were considered. However, because of the unusual erosion problems that have historically occurred in the TPD structures, it has been decided to continue with a proven conventional steel pipe design. The bends and the tee branch will be made from off-the-shelf forged 1-1/2-diameter-radius buttwelding pipe fittings to ANSI B Flanges will be Class 150 slip-on flanges flat-faced with full-face sheet gaskets. Gasket jointing will probably be an aramid fibre reinforced rubber binder type, as commonly used on water piping. Bolting will be 1-1/4 bolts, to a similar strength as Grade 8.8 galvanized bolts. The pipe will have epoxy coatings inside and out. Possibly an epoxy zinc-rich primer, and vinylacrylic top coatings, as recently proposed for Tuai, could be considered. Pipework equipment items At the existing discharge valve gallery, the following items of pipework equipment will be installed: 450 mm NB magnetic flow meter; tee-branch and relocated 450 mm NB compensation flow valve; wafer-style 450 mm NB butterfly valve for isolation of the turbine. Due to space constraints none of these items have optimum lengths of straight constant diameter pipe upstream. This is not considered problematic, as the velocity at 0.6 m 3 /s is only 3.65 m/s, which is relatively low. However, if higher compensation flows are required in the future, it is likely that the present 2.5 m 3 /s capacity of the compensation flow valve will not be achievable. The actual limit could be established after commissioning, by determining the head/flow limits at which vibration or unstable operation becomes apparent. Strength rating Modelling of the proposed pipework using Autopipe software, applying ANSI B 31.5 design criteria, shows that it will be strong enough with four standard pipe supports anchored to the dam concrete work 4. No additional support framing is necessary.

13 The 450 mm NB pipe will also support smaller external pipe ducts for hydraulic hoses and generator cables. Three 80 mm NB pipes are proposed. One pipe is for the hydraulic hoses, and two for the generator cables. Two multicore flexible and waterproof cables, connected in parallel, are envisaged for the generator main connections. 4 A seismic factor of 0.7, 8 bar gauge design pressure, and temperature range from 5 C to + 35 C was applied. 3.7 Turbine The turbine is expected to be a small (300 kw) vertical Francis unit, with hydraulically actuated regulation, and a vertical cone draft tube. The scroll case will have integral brackets for anchoring directly onto the top of the existing concrete plinth (as described in 3.2). Anchoring using chemset injection anchors, or similar, is envisaged. The scroll case will have a long life surface coating provided by the manufacturer. The scroll case will also have access nozzles to allow clearance of minor debris from the stay vanes and guide vanes. It is possible that the regulation linkages will be located on the underside of the scrollcase for better physical protection. Preliminary turbine operational data is as follows: Rated power: 278 kw Net head and flow at rated power: 52 m at 0.6 m 3 /s Expected speed: 1,000 rpm Best efficiency head: 47m 3.8 Generator The generator will be an IP 68 rated, close-coupled, AC 3 phase motor. It is proposed to specify the motor so that it will operate as a generator at the rated power without requiring an external cooling fan. The generator will be capable of operating both submerged in water and in air. It will not be reliant on internal water circulation for its cooling. A double mechanical shaft seal, incorporating leakage detection, as used in submersible pumps will also be specified. The close-coupling should permit relatively simple disconnection of the generator, complete with the turbine runner, from the scroll case. This will allow access to remove any debris that becomes jammed in the runner after penetrating through the guide vanes. This type of disassembly for cleaning is very common on larger sewage pumps. The generator will be rated to operate for a sustained period at the maximum runaway speed of the turbine. This will avoid the need for a hydraulic accumulator for fast closure of the guide vanes, and/or for the turbine-isolation valve. 3.9 Civil works The civil works are minimal for this scheme, comprising only the concrete cutting of the mounting slab to accommodate the draft tube, turbine and the penstock anchors. The strength of the mounting plinth, after concrete cutting, will be determined at the detail design stage, and additional reinforcement or special long anchor bolts may be required Auxiliary mechanical plant

14 The only auxiliary mechanical plant is the hydraulic oil system. We have not yet determined whether the existing drawdown valve hydraulic pumping unit and reservoir will be utilisable for the mini hydro turbine and valve actuators. If this is the case, it is likely the only modifications that will be required will comprise a new hydraulic valve panel, and probably additional and updated oil filtering/monitoring Electrical systems The Moawhango dam electrical services are presently supplied from the 33/0.4 kv 50 kva transformer T70, located about 800 metres from the dam on the pole mounted end structure of the dual circuit 33kV overhead line. The existing 400 V underground cable from this transformer to the dam will be retained as the station services supply. A new single circuit 33 kv overhead line erected from the 33 kv end structure to the western end of the dam. The mini hydro generator output will be connected to the 33 kv line via short length of 33kV cable from a ground mounted 400/33 kv 400 kva power transformer. The following figure shows the intended route for the Moawhango and Mangaio 33 kv line extensions: TPD Minihydro Transmission line extensions (lower section of Tokaanu-Moawhango 33kV system) Mangaio powerhouse site New 0.7km 33kV Mangaio line The proposed single line diagram for the Moawhango scheme is shown on drawing AP00821-E-501, part of which is repeated below:

15 A 33 kv air break fuse switch will be installed at the terminal pole next to the transformer. A 33 kv air break switch will be installed at the existing Moawhango end structure to allow isolation of the new 33 kv line. The generator output of nominally 300 kw will be switched, at generator voltage, by a suitably rated moulded case circuit breaker installed in a switchboard in the dam valve house, located on the west wall next to the recently installed Kingfisher RTU control panel. The mains cable from the generator will terminate in this switchboard. The cable from the switchboard to the generator transformer will be run through the dam galleries along the same route as the existing cables. The generator voltage will be determined on receipt of the generator tenders. There is a potential cost saving in the interconnection cabling from the generator to the 33kV generator transformer if the generator is rated for operation at 600 V rather than the more common 400 V as used in New Zealand. The finally selected voltage will also be the low voltage winding voltage for the generator transformer.

16 3.12 Generator Protection Drawing AP00821-E-502 shows the intended protection concept for the Moawhango generator. This system will be based on two multifunction relays as shown in the diagram below. Both relays will be mounted in the Generator switchboard. Relay 1 - Generator protection: Neutral Overcurrent, Negative Phase sequence, Phase overcurrent, Overload, Winding overtemperature, Bearing overtemperature. Relay 2 - Interconnector protection: Under/over frequency, Under/over voltage, Reverse power, Neutral voltage displacement.

17

18 Auxiliary supplies, at 400/230V AC, for the Moawhango hydro turbine will be taken from the existing dam distribution panel. A battery backed 24V DC supply will be used for controls, in a similar manner to that proposed for Mangaio Station Control and communications Although the Moawhango mini hydro scheme is conceptually very simple, the control and monitoring system is not significantly less complex than that for Mangaio. The control equipment and a PLC will be installed in a separate control panel located next to the generator switchboard in the dam valve house. A 450 mm NB, full bore, magnetic flowmeter will be installed in the compensation pipe, upstream of the turbine and compensation valve, to monitor the instantaneous flow through the pipe. The flowmeter signal will be used by the PLC to control the station flow. The station will operate fully automatically by monitoring the water flow in the discharge pipe and maintain the set flow of 600l/s by controlling the turbine and/or the compensation valve output. If the turbine trips off, the control system will regulate the position of the compensation valve to maintain the required compensation flow. We expect to achieve very accurate flow control from the station. The station control system is expected to utilise a Unitronics Vision 280s PLC, ( with integrated graphics touch screen. Monitoring and control of the turbine/generator system and compensation valve will be possible from the graphics panel. Suggested control system architecture is shown on drawing AP00821-E-003 Data Communication Block Diagram and is described below: Moawhango generator PLC with graphic panel located in the valve house control panel, RS232 serial communications from the PLC to the existing Kingfisher RTU located in the valve house, Existing RS485 serial communications from the existing Kingfisher RTU located in the valve house to the existing Kingfisher RTU located in the dam gallery entrance, Remote communications to Tokaanu via microwave from the existing Kingfisher RTU located in the dam gallery entrance, Software Driver at the Tokaanu Plantscape HMI using Unitronics OPC Server or similar software. The station will be controlled by the programmable logic controller in the valve house which will provide all the necessary control facilities and also monitor and log bearing and winding temperatures, protection conditions and the like. Remote supervision would be provided from the Tokaanu Plantscape HMI. The station output and status will be transmitted to the Tokaanu control room at regular intervals. In the event of an alarm or trip, someone could travel to site to solve the problem.

19 XXXX will also be able to control the flow set point, stop and start and trip the station from the Plantscape HMI at Tokaanu. Control and protection power supplies will be dual 24V dc battery systems with automatic changeover on primary battery failure. If the 33 kv power supply was lost, the station would trip off and go to bypass mode, maintaining flow control via the compensation valve. If the station programmable logic controller failed, the station would continue operating at the last flow setting and send an alarm to the Tokaanu control room. If the electrical protection operated or a bearing temperature was excessive, the station would trip off. This implies that the PLC cannot be used for bearing temperature trips etc that are required to allow the machine to continue running. The use of a Multifunction electrical protection relay with RTD temperature inputs meets this requirement.

20 4. Construction Phase 4.1 Contract Structure Recent meetings between XXXX Energy and XXX have resulted in an agreement that the Mangaio and Moawhango mini hydro projects will be structured in the following way: 4.2 Contract Interfaces Turbine and Generator contracts may be awarded to separate suppliers, depending on the results of the tender evaluation. Coordination between the equipment suppliers will be carefully controlled by XXX in accordance with the requirements of the technical specifications. It is unlikely that a separate civil contractor will be necessary for the Moawhango project. The M & E contractor can arrange for the civil works associated with the turbine mounting slab cutout and then commence preparation for the installation of the turbine, generator and balance of plant. It is likely that the construction of the 33kV transmission lines will be undertaken by specialist subcontracts to the M & E Installation Contractor. Due to the simple nature of the Moawhango contract, a Contract Termination Point Diagram and accompanying schedule have not been created for this project. 4.3 M & E Installation Mechanical installation The main considerations during mechanical installation that will need special attention are: ensuring satisfactory working conditions, i.e. safe access, and a dry site; maintaining the compensation flow during construction; prevention of watercourse pollution, (concrete cutting, and any site painting being particular areas of concern); availability of services, e.g. temporary power supply from the valve gallery, or craned-in portable gen-sets, etc. One methodology is to prepare the site as follows: install special ladders, and handrails, etc. as may be required to permit safe pedestrian access from the dam abutments down to the mounting plinth (all equipment will be craned in using a mobile

21 crane on the dam crest, although some minor lifting may be possible using the valve house monorail); prefabricate and install a special anchored mounting frame for the fixed cone valve, that will allow the valve to be temporarily installed on one of the apron steps downstream of the plinth, and access route (the frame will also include a simple adjustable link mechanism to allow manual regulation of the valve); prefabricate special temporary reducing fittings, with extension pipe stubs which can be bolted onto the existing terminal flange, and the fixed cone valve flange; deploy a 300 mm contractors hose string, with flanged ends, and around 30 to 40 m total length; crack open the drawdown valve, and close the 450 mm NB isolation valve; then relocate the fixed cone valve on the special mounting frame, and (using the hose and reducing fittings) reconnect to the terminal flange at the valve gallery; close the drawdown valve, and open the 450 mm NB isolation valve. It is envisaged that the mechanical installation will proceed as follows: contractor review of drawings and completion of prefabrication site measurements; prefabricate and surface coat most of the pipework, (postponing selected shop-welds-to-precisefield-measurement as deemed prudent); manufacture hydraulic actuator for fixed cone valve, and new hydraulic valve panel; concrete cut the proposed draft tube cavity in the plinth; install and anchor turbine and generator unit; install and anchor protection structure; install and anchor penstock pipe up as far as the lower flange of the turbine isolation valve; obtain precise measurements of the flange to flange dimensions to allow accurate shop fabrication of the upper penstock assembly (the magnetic flow meter, bend with tee-branch, and turbine isolation valve); complete fabrication and trial shop fit-up, and surface coating of the upper penstock assembly; install hydraulics for actuation of fixed cone valve and turbine isolation valve; crack open the drawdown valve, and close the 450 mm NB isolation valve; then install the upper penstock assembly, and commission the hydraulic actuation of the fixed cone valve and turbine isolation valve; close the drawdown valve, and open the 450 mm NB isolation valve and the fixed cone valve; complete installation of generator cables, and turbine hydraulics; complete remaining electrical work, and commission the turbine and generator Electrical and Controls installation The Electrical and Controls installation for this project is relatively straight forward and within the capability of several leading contractors.

22 The long lead time items are the generator transformer and generator. All other items are likely to be available at less than 6 weeks delivery. Off site fabrication of the generator control panel and the generator switchboard will be specified. Following delivery of all items to site, an on-site construction period of about four weeks is probably sufficient for this section of the project. Off site programming and testing of the control PLC will be specified. The configuration and testing of the Tokaanu HMI interface will also be undertaken off site, prior to installation. 4.4 Potential Contractors Discussions with XXXX Energy Tokaanu management and XXX knowledge of suitable contractors have resulted in the following list of potential contractors for the M & E work: 4.5 Supervision and Commissioning XXX will provide skilled and experienced engineers to observe the construction and provide the technical interface between the Contractors and the XXX design team during the site construction, precommissioning, and commissioning of the mini hydro station. XXX recommend the following staff be provided on a part time basis to ensure adequate control during the construction phase: Hydro Mechanical erection supervisor Hydro Mechanical engineer Electrical and Instrumentation engineer Commissioning will require the services of XXXX operations staff, the Hydro Mechanical erection supervisor, a Hydro Mechanical engineer and a Hydro Electrical and Instrumentation engineer.

23 Appendix A Drawing Schedule

THE HEMSIL POWER PLANT

THE HEMSIL POWER PLANT THE HEMSIL POWER PLANT s" ' r- A.S.KMERNER BRUG.OSLO Kvaernervn. 10 - Postal Address: Box 3610 - Cable Address: Kvaerner - Telephone: 68181O - Telex: 1650 NORWAY C. HEMSEDAL Hallingdalselvcn I i i i i

More information

TRASH RACK CLEANING MACHINE

TRASH RACK CLEANING MACHINE TRASH RACK CLEANING MACHINE 1 SCOPE The work includes the design, manufacturing, supply, transportation, handling, storage, installation (including 1 st and 2 nd Stage embedded parts and any other necessary

More information

Rodney Hunt. A GA Industries Company Bascule and Pelican Gates

Rodney Hunt. A GA Industries Company Bascule and Pelican Gates Rodney Hunt A GA Industries Company Bascule and Pelican Gates Hinged Crest Gates Precise Flow and Level Control Fully Functional in Ice Conditions Proven Performance One Source: Design, Build, Actuate

More information

TOWER MAXI T SINGLE CONVERSION ON LINE UPS SYSTEMS

TOWER MAXI T SINGLE CONVERSION ON LINE UPS SYSTEMS INSTRUCTION MANUAL TOWER MAXI T SINGLE CONVERSION ON LINE UPS SYSTEMS September 2000 TOWER UPS DISTRIBUTION (PTY) LTD 1 1. INTRODUCTION T A B L E O F C O N T E N T S 1.1 General Description... 3 1.2 Features...

More information

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS 1. PURPOSE AND SCOPE OF THIS DOCUMENT... 3 2. DEFINITIONS...

More information

Appendix 5 Sample Specifications. Specifications for Socioeconomic Survey in Rural Areas in Myanmar

Appendix 5 Sample Specifications. Specifications for Socioeconomic Survey in Rural Areas in Myanmar Part 6-2 Appendix 5 Appendix 5 Sample Specifications Appendix 5-1 Appendix 5-2 Appendix 5-3 Appendix 5-4 Appendix 5-5 Appendix 5-6 Specifications for Socioeconomic Survey in Rural Areas in Myanmar Technical

More information

FINAL LICENSE APPLICATION Exhibit A Description of Project

FINAL LICENSE APPLICATION Exhibit A Description of Project FINAL LICENSE APPLICATION Exhibit A Description of Project PacifiCorp Portland, Oregon April 2004 Copyright 2004 by PacifiCorp Reproduction in whole or in part without the written consent of PacifiCorp

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

AUTOMATIC SELF-ACTUATING DAM OUTLET VALVES

AUTOMATIC SELF-ACTUATING DAM OUTLET VALVES AUTOMATIC SELF-ACTUATING DAM OUTLET VALVES PD Townshend Amanziflow Projects (Pty) Ltd, Johannesburg, South Africa ABSTRACT Many older dams have bottom outlet valves which are now malfunctioning and require

More information

The Pump Matic Range

The Pump Matic Range The Below Ground packaged pumping Stations Ideal for - Sewage, Wastewater, Stormwater Pump Technology Ltd, manufactures its own pumping station tanks. We have complete control over the construction, quality

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner

More information

EDS SUBSTATION LVAC SUPPLIES

EDS SUBSTATION LVAC SUPPLIES Document Number: EDS 08-1112 Network(s): Summary: EPN, LPN, SPN ENGINEERING DESIGN STANDARD EDS 08-1112 SUBSTATION LVAC SUPPLIES The standard details the requirements and options for the provision of LVAC

More information

SECTION DOMESTIC-WATER PACKAGED BOOSTER PUMPS

SECTION DOMESTIC-WATER PACKAGED BOOSTER PUMPS SECTION 221123.13 - DOMESTIC-WATER PACKAGED BOOSTER PUMPS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Chapter 6 Generator-Voltage System

Chapter 6 Generator-Voltage System Chapter 6 Generator-Voltage System 6-1. General The generator-voltage system described in this chapter includes the leads and associated equipment between the generator terminals and the low-voltage terminals

More information

SECTION AXIAL HVAC FANS

SECTION AXIAL HVAC FANS SECTION 233413 - AXIAL HVAC FANS 1. PART 1 GENERAL 1.1. RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

Appendix 11 RETURN TO APPENDICES LIST. High Voltage Power Supply Upgrade (Welcon Technologies Pty Ltd)

Appendix 11 RETURN TO APPENDICES LIST. High Voltage Power Supply Upgrade (Welcon Technologies Pty Ltd) Appendix 11 RETURN TO APPENDICES LIST High Voltage Power Supply Upgrade (Welcon Technologies Pty Ltd) GLADSTONE AREA WATERBOARD AWOONGA DAM HIGH VOLTAGE POWER SUPPLY UPGRADE Document: GJ543-RP-02B Submission

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : June,

More information

RAS & WAS Pumps (FLYGT Pump)

RAS & WAS Pumps (FLYGT Pump) RAS/WAS Pumping Pumping of sludge from the secondary clarifiers to the aeration tanks maintains active biomass in the aeration tanks This is referred to as return activated sludge (RAS) pumping RAS pumps

More information

SECTION DOMESTIC-WATER PACKAGED BOOSTER PUMPS

SECTION DOMESTIC-WATER PACKAGED BOOSTER PUMPS SECTION 22 1123.13 DOMESTIC-WATER PACKAGED BOOSTER PUMPS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1. Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.3, 5/16/18 1.0 Scope This document is currently limited in scope to inverter interfaced PV installations

More information

Exhaust System - 2.2L Diesel

Exhaust System - 2.2L Diesel Page 1 of 9 Published: Mar 8, 2007 Exhaust System - 2.2L Diesel COMPONENT LOCATION - WITH DIESEL PARTICULATE FILTER Item Part Number Description 1 Exhaust manifold (ref only) 2 Pressure differential sensor

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

DAMS, RESERVOIRS & HYDROPOWER SOLUTIONS

DAMS, RESERVOIRS & HYDROPOWER SOLUTIONS DAMS, RESERVOIRS & HYDROPOWER SOLUTIONS Orbinox Glenfield Premier DAMS, RESERVOIRS & HYDROPOWER CONTENT: TECHNICAL CAPABILITIES 4-5 APPLICATION MATRIX 6-7 BOTTOM OUTLETS 8 INTERMEDIATE OUTLETS 9 SPILLWAYS

More information

24-48 HP250II Butterfly Valve. Operation and Maintenance Manual. Job Name: Contractor: Date: Document #: 2448HP250OOOM Revision Date: 1/10/11

24-48 HP250II Butterfly Valve. Operation and Maintenance Manual. Job Name: Contractor: Date: Document #: 2448HP250OOOM Revision Date: 1/10/11 24-48 HP250II Butterfly Valve Operation and Maintenance Manual Job Name: Contractor: Date: Document #: 2448HP250OOOM Revision Date: 1/10/11 SAFETY MESSAGES All safety messages in the instructions are flagged

More information

WHAKAMARU POWER STATION REHABILITATION PROJECT. Author: Glen Twining, PMP, RMU Program Manager - Whakamaru, Mercury NZ Ltd, New Zealand.

WHAKAMARU POWER STATION REHABILITATION PROJECT. Author: Glen Twining, PMP, RMU Program Manager - Whakamaru, Mercury NZ Ltd, New Zealand. WHAKAMARU POWER STATION REHABILITATION PROJECT Author: Glen Twining, PMP, RMU Program Manager - Whakamaru, Mercury NZ Ltd, New Zealand. ABSTRACT Whakamaru Power Station in the North Island of New Zealand

More information

3-20 2FII & Groundhog Bonded Seat Butterfly Valve. Operation and Maintenance Manual. Job Name: Contractor: Date:

3-20 2FII & Groundhog Bonded Seat Butterfly Valve. Operation and Maintenance Manual. Job Name: Contractor: Date: 3-20 2FII & Groundhog Bonded Seat Butterfly Valve Operation and Maintenance Manual Job Name: Contractor: Date: Document #:3202FIIGD Revision Date: 1/10/11 SAFETY MESSAGES All safety messages in the instructions

More information

Modular Standardized Electrical and Control Solutions for Fast Track Projects

Modular Standardized Electrical and Control Solutions for Fast Track Projects Modular Standardized Electrical and Control Solutions for Supporting fast track projects ABB is the leading supplier of electrical and control equipment for power plants. The company offers a comprehensive

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Use and Care Instructions for your new T5 Turgo Micro-Hydroelectric Generator

Use and Care Instructions for your new T5 Turgo Micro-Hydroelectric Generator Use and Care Instructions for your new T5 Turgo Micro-Hydroelectric Generator READ THIS FIRST This manual contains important information concerning your new APR T5 Turgo microhydroelectric generator. You

More information

Guidelines for connection of generators:

Guidelines for connection of generators: Guidelines for connection of generators: Greater than 30 kva, and not greater than 10 MW, to the Western Power distribution network January, 2017. EDM 32419002 / DM 13529244 Page 1 of 14 Contents 1 INTRODUCTION...

More information

DAMS, RESERVOIRS & HYDROPOWER SOLUTIONS

DAMS, RESERVOIRS & HYDROPOWER SOLUTIONS DAMS, RESERVOIRS & HYDROPOWER SOLUTIONS Orbinox Glenfield Premier 2 DAMS, RESERVOIRS & HYDROPOWER CONTENT: TECHNICAL CAPABILITIES 4-5 APPLICATION MATRIX 6-7 BOTTOM OUTLETS 8 INTERMEDIATE OUTLETS 9 SPILLWAYS

More information

3.2. Current Limiting Fuses. Contents

3.2. Current Limiting Fuses. Contents .2 Contents Description Current Limiting Applications................. Voltage Rating.......................... Interrupting Rating....................... Continuous Current Rating................ Fuse

More information

3) The water conductor system consisting of RCC, partly cut and cover, conduit of size 10.5m x 7m and m long to lead the water to the forebay.

3) The water conductor system consisting of RCC, partly cut and cover, conduit of size 10.5m x 7m and m long to lead the water to the forebay. Project: Mannapitlu Mini Hydel Scheme - 15 MW Overview: Mannapitlu Mini Hydel Scheme is the first of the 4 cascading Mini Hydro Electric Projects planned on Gurupur river in Dakshina Kannada District of

More information

DELPHYS GP. Green Power 2.0 range 160 to 1000 kva/kw

DELPHYS GP. Green Power 2.0 range 160 to 1000 kva/kw DELPHYS GP Green Power 2.0 range 160 to 1000 kva/kw OBJECTIVES The aim of these specifications is to provide: the information required to choose the right uninterruptible power supply for a specific application.

More information

Uniflex-stow remote valve operating systems

Uniflex-stow remote valve operating systems Flexible shaft system 1 INTRODUCTION The purpose is to provide the user with basic information for the specification, installation, operation, maintenance, repair and parts identification of the Uniflex-stow

More information

Factors to consider when selecting a diverter valve

Factors to consider when selecting a diverter valve Factors to consider when selecting a diverter valve Selecting a diverter valve for your pneumatic conveying system can be a tough job, especially when you consider how many diverter valves are on the market.

More information

Nanometrics Solar Power System

Nanometrics Solar Power System Nanometrics Solar Power System Installation Guide Nanometrics Inc. Kanata, Ontario Canada 2003 Nanometrics Inc. All Rights Reserved. Installation Guide The information in this document has been carefully

More information

EPIC J3413. Uniclass L L2123. CI/SfB (52.5) In6. The most advanced drainage system of its kind. ACO Qmax. Technical Data

EPIC J3413. Uniclass L L2123. CI/SfB (52.5) In6. The most advanced drainage system of its kind. ACO Qmax. Technical Data Uniclass L7315 + L2123 EPIC J3413 CI/SfB (52.5) In6 The most advanced drainage system of its kind ACO Qmax Technical Data ACO Qmax System Contents Load Classes 3 ACO Qmax 600 System Pedestrian and Car

More information

Unified requirements for systems with voltages above 1 kv up to 15 kv

Unified requirements for systems with voltages above 1 kv up to 15 kv (1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) (Corr.1 June 2018) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements

More information

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System This document is intended to be a general overview of PG&E s current technical

More information

Overview of hydro electric dams and how they work Provide background on basic principles of hydropower and its history. Explain features that all

Overview of hydro electric dams and how they work Provide background on basic principles of hydropower and its history. Explain features that all Overview of hydro electric dams and how they work Provide background on basic principles of hydropower and its history. Explain features that all hydro power dams have and compare the design of Revelstoke

More information

Appendix 3. DRAFT Policy on Vehicle Activated Signs

Appendix 3. DRAFT Policy on Vehicle Activated Signs Appendix 3 DRAFT Policy on Vehicle Activated Signs Ealing Council has been installing vehicle activated signs for around three years and there are now 45 across the borough. These signs help to reduce

More information

DAMS, RESERVOIRS AND HYDROPOWER VALVE SOLUTIONS

DAMS, RESERVOIRS AND HYDROPOWER VALVE SOLUTIONS GLENFIELD DAMS, RESERVOIRS AND HYDROPOWER DAMS, RESERVOIRS AND HYDROPOWER SOLUTIONS GLENFIELD is a leading supplier of large diameter valves for dams, reservoirs and hydropower installations around the

More information

Technical Specification

Technical Specification Technical Specification Heavy Industrial Sliding Gates General Notes The works under this subsection shall comprise the design, manufacture, installation, commissioning, training and maintenance of the

More information

DSZ3. EBARA Submersible Propeller Pumps Contents Project: Model: Chk d: Date: Model

DSZ3. EBARA Submersible Propeller Pumps Contents Project: Model: Chk d: Date: Model Contents Model A0553 C1125 V0494 A0713 C1285 V0554 A0843 C1455 V0754 A1003 C1605 V0854 C1915 V0974 C2185 V1154 C2905 Section Page Specifications 3-203 Model Designation 3-206 Impeller Data 3-208 Material

More information

Guri Dam. Ingenuity and energy

Guri Dam. Ingenuity and energy Guri Dam Modernization of the Guri hydroelectric plant s control, protection and instrumentation system Eduardo Colmenares, Daniel Rubinstein, Miguel Florez In 2005, ABB was awarded a contract to design,

More information

Instruction Booklet for the Installation, Operation and Maintenance of Type 5-15 kv VCP-WG Vacuum Circuit Breaker 4000A MiniMod

Instruction Booklet for the Installation, Operation and Maintenance of Type 5-15 kv VCP-WG Vacuum Circuit Breaker 4000A MiniMod Instruction Booklet for the Installation, Operation and Maintenance of Type 5-15 kv VCP-WG Vacuum Circuit Breaker 4000A MiniMod Eaton Corporation Moon Twp, PA. U.S.A. 15108 1 INTRODUCTION READ AND UNDERSTAND

More information

ELVORON HR DESIGN AND PLANNING GUIDE

ELVORON HR DESIGN AND PLANNING GUIDE ELVORON HR DESIGN AND PLANNING GUIDE Hydraulic Home Elevator Quality Elevators by Garaventa www.garaventaelevator.com Table of Contents Elvoron HR - Hydraulic Residential Elevator... 2 Technical Reference:...

More information

MASTERYS IP+ 10 to 80 kva

MASTERYS IP+ 10 to 80 kva MASTERYS IP+ 10 to 80 kva OBJECTIVES The aim of these specifications is to provide: the information required to choose the right uninterruptible power supply for a specific application. the information

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

U n i n t e r r u p t i b l e P o w e r S y s t e m

U n i n t e r r u p t i b l e P o w e r S y s t e m SMART ON-LINE UPS User s Manual U n i n t e r r u p t i b l e P o w e r S y s t e m Smart On-Line UPS 2KVA ~ 20KVA 20KVA Exhaust hole (16)Main breaker (12)Heat exhaust hole (15)Telephone (Rj11) or network

More information

TANZANIA BUREAU OF STANDARDS

TANZANIA BUREAU OF STANDARDS EDC 5 (5235) P3 Mini-Grid Systems DRAFT TANZANIA STANDARD (Draft for comments only) Part 2: Application of Inverters TANZANIA BUREAU OF STANDARDS TBS 2017 First Edition 2017 T able of content 1 2 3 4 5

More information

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES 10-100 KILOWATTS IN THE STATE OF NEW JERSEY January 1, 2005 Rockland Electric Company 390 West Route 59 Spring Valley,

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

EBARA Submersible Propeller Pumps Contents Project: Model: Chk d: Date: Model

EBARA Submersible Propeller Pumps Contents Project: Model: Chk d: Date: Model Contents Model A0553 C1125 V0494 A0713 C1285 V0554 A0843 C1455 V0754 A03 C15 V0854 C1915 V0974 C2185 V1154 C2905 Section Page Specifications 3-3 Model Designation 3-6 Impeller Data 3-8 Material Specifications

More information

III. Substation Bus Configurations & Substation Design Recommendations

III. Substation Bus Configurations & Substation Design Recommendations III. Substation Bus Configurations & Substation Design Recommendations 1.0 Introduction Pre-existing conditions, electrical arrangements or the criticality of the existing facility may limit this flexibility,

More information

TRI-SERVICE ELECTRICAL WORKING GROUP (TSEWG) 03/05/09 TSEWG TP-11: UFC N BEST PRACTICES

TRI-SERVICE ELECTRICAL WORKING GROUP (TSEWG) 03/05/09 TSEWG TP-11: UFC N BEST PRACTICES TSEWG TP-11: UFC 3-500-10N BEST PRACTICES UFC 3-500-10N was developed by NAVFAC and was used as the starting point for the tri-services development of UFC 3-500-10, Design: Electrical Engineering. UFC

More information

LIQUID MEASUREMENT STATION DESIGN Class No

LIQUID MEASUREMENT STATION DESIGN Class No LIQUID MEASUREMENT STATION DESIGN Class No. 2230.1 Michael Frey Systems Sales Manager Daniel Measurement & Control, Inc. 5650 Brittmoore Rd. Houston, Texas 77041 INTRODUCTION The industry continues to

More information

New Method for Improving On-Line Loading Rates on Mechanical Governors By Gerald G. Runyan

New Method for Improving On-Line Loading Rates on Mechanical Governors By Gerald G. Runyan New Method for Improving On-Line Loading Rates on Mechanical Governors By Gerald G. Runyan Abstract Properly tuned and calibrated, mechanical governors provide excellent frequency control, passing all

More information

Supplement to the Histelect News No. S58 December 2014 CHINA S THREE GORGES DAM HYDRO-ELECTRIC POWER PLANT

Supplement to the Histelect News No. S58 December 2014 CHINA S THREE GORGES DAM HYDRO-ELECTRIC POWER PLANT Supplement to the Histelect News No. S58 December 2014 CHINA S THREE GORGES DAM HYDRO-ELECTRIC POWER PLANT by Peter Luxton Last September Peter Luxton went on a thirteen day tour of China, which involved

More information

pneumatic outflow control

pneumatic outflow control Technical Information pneumatic outflow control Pneumatically driven control elements for precise flow limitation of wastewater and rainwater partly filled pneumatic outflow control IDM-based fully filled

More information

Technical Data Sheet. Uninterruptible Power Supply. Critical Power. imagination at work

Technical Data Sheet. Uninterruptible Power Supply. Critical Power. imagination at work Technical Data Sheet Uninterruptible Power Supply SGSE_400-500_S3_UPS_01 GE Consumer & Industrial SA General Electric Company CH 6595 Riazzino (Locarno) Switzerland T +41 (0)91 / 850 51 51 F +41 (0)91

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

OPTIMISING SEWAGE PUMPING STATION PERFORMANCE

OPTIMISING SEWAGE PUMPING STATION PERFORMANCE OPTIMISING SEWAGE PUMPING STATION PERFORMANCE Andrzej Krawiec, Martin Byrnes Sydney Water Corporation, Sydney, NSW, Australia ABSTRACT At Sewage Pump Stations (SPS) grease, fat and other material such

More information

MHP 5 DEPARTMENT OF ENERGY ENERGY UTILIZATION MANAGEMENT BUREAU

MHP 5 DEPARTMENT OF ENERGY ENERGY UTILIZATION MANAGEMENT BUREAU MHP 5 DEPARTMENT OF ENERGY ENERGY UTILIZATION MANAGEMENT BUREAU Micro-hydropower Operator Training Manual May 2009 This manual was developed by the Department of Energy (DOE) through the technical assistance

More information

SECTION CENTRIFUGAL HVAC FANS

SECTION CENTRIFUGAL HVAC FANS SECTION 233416 - CENTRIFUGAL HVAC FANS 1. PART 1 GENERAL 1.1. RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

Derrick Boltt Southern Region Hydro Generation Eskom South Africa

Derrick Boltt Southern Region Hydro Generation Eskom South Africa Derrick Boltt Southern Region Hydro Generation Eskom South Africa Hydro Power in the S/Region. History of Hydro in the S/Region. In 198 the former Transkei government financed the development of Hydro

More information

Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018

Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018 Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018 Outlined below are the engineering documents and their associated minimum detail requirements for a Distributed Energy Resource (DER)

More information

Generator Fire Safety: Generator assemblies should be located outside the building.

Generator Fire Safety: Generator assemblies should be located outside the building. SECTION 33 70 00 - ELECTRICAL DISTRIBUTION PACKAGED GENERATOR ASSEMBLIES Generator Fire Safety: Generator assemblies should be located outside the building. All fuel piping from the outside of the building

More information

Hydro Plant Risk Assessment Guide

Hydro Plant Risk Assessment Guide September 2006 Hydro Plant Risk Assessment Guide Appendix E8: Battery Condition Assessment E8.1 GENERAL Plant or station batteries are key components in hydroelectric powerplants and are appropriate for

More information

Green Power 2.0 MASTERYS GP

Green Power 2.0 MASTERYS GP Green Power 2.0 MASTERYS GP 60 to 120 kva/kw OBJECTIVES The aim of these specifications is to provide: the information required to choose the right uninterruptible power supply for a specific application.

More information

Renewable Generation Electrical Infrastructure and Grid Connection Services Provided by Power Systems Project and Consultancy Services (PCS) Ltd

Renewable Generation Electrical Infrastructure and Grid Connection Services Provided by Power Systems Project and Consultancy Services (PCS) Ltd Renewable Generation Electrical Infrastructure and Grid Connection Services Provided by Power Systems Project and Consultancy Services (PCS) Ltd Power Systems Project and Consultancy Services (PCS) Ltd

More information

Western Alberta Transmission Line (WATL) HVDC Project

Western Alberta Transmission Line (WATL) HVDC Project Submission for the ACEC Canada Canadian Consulting Engineering Awards 2016 Western Alberta Transmission Line (WATL) HVDC Project Submitted by Teshmont Consultants LP as a Consultant to AltaLink Attachment

More information

ICOMIA Global Conformity Guideline for ISO/ABYC Standards and Canadian TP 1332 requirements. Guideline Number 3 Electrical

ICOMIA Global Conformity Guideline for ISO/ABYC Standards and Canadian TP 1332 requirements. Guideline Number 3 Electrical ICOMIA Global Conformity Guideline for ISO/ABYC Standards and Canadian TP 1332 requirements 1. PURPOSE sponsored by ABYC, BMF, ICOMIA, IMCI, and NMMA Author: Wieger de Wit Guideline Number 3 Electrical

More information

Letter EL652 City of Mercer Island. Page 1. No comments n/a

Letter EL652 City of Mercer Island. Page 1. No comments n/a Letter EL652 City of Mercer Island Page 1 No comments n/a Page 2 Response to comment EL652 1 Section 4.5.3 of the Final EIS presents the range of potential impacts of the project. This project also lists

More information

KAUAI ISLAND UTILITY COOPERATIVE KIUC Tariff No. 1 Lihue, Kauai, Hawaii Original Sheet 5 RULE NO. 2 CHARACTER OF SERVICE

KAUAI ISLAND UTILITY COOPERATIVE KIUC Tariff No. 1 Lihue, Kauai, Hawaii Original Sheet 5 RULE NO. 2 CHARACTER OF SERVICE Lihue, Kauai, Hawaii Original Sheet 5 RULE NO. 2 A. GENERAL 1. The character of service available at any particular location must be ascertained by the Company business office, and will depend upon the

More information

Low and medium voltage service. Power Care Customer Support Agreements

Low and medium voltage service. Power Care Customer Support Agreements Low and medium voltage service Power Care Customer Support Agreements Power Care Power Care is the best, most convenient and guaranteed way of ensuring electrification system availability and reliability.

More information

DELUGE VALVE MODEL: SD-DVA TECHNICAL DATA : VALVE OPERATION TRIM DESCRIPTION DESCRIPTION PRESSURE THREADED OPENING

DELUGE VALVE MODEL: SD-DVA TECHNICAL DATA : VALVE OPERATION TRIM DESCRIPTION DESCRIPTION PRESSURE THREADED OPENING DELUGE VALVE MODEL: SD-DVA TECHNICAL DATA : NOMINAL SIZE MATERIAL MAXIMUM SERVICE PRESSURE 200, 150, 100, 80 & 50NB Cast Iron 12 Bar (175 PSI) THREADED OPENING MOUNTING FACTORY HYDROSTATIC TEST PRESSURE

More information

FEASIBILITY LAND TRANSPORTATION VENTUS ENERGY. from. covering WIND TURBINE EQUIPMENT PORT OF MOUNT MAUNGANUI TO KAIMAI RANGE SITE. for.

FEASIBILITY LAND TRANSPORTATION VENTUS ENERGY. from. covering WIND TURBINE EQUIPMENT PORT OF MOUNT MAUNGANUI TO KAIMAI RANGE SITE. for. FEASIBILITY from covering LAND TRANSPORTATION Of WIND TURBINE EQUIPMENT PORT OF MOUNT MAUNGANUI TO KAIMAI RANGE SITE for VENTUS ENERGY September 2018 TABLE OF CONTENTS 1. PURPOSE AND SCOPE... 1 1.1. Purpose...

More information

33kV Connection up to 90MVA

33kV Connection up to 90MVA Electricity Specification 217 Issue 2 December 2007 33kV Connection up to 90MVA Contents 1 Scope 2 General 3 Connection Arrangements 4 Equipment Records 5 Documentation 6 Documents Referenced 7 Keywords

More information

Creating An Accessible World ELVORON CPL.

Creating An Accessible World ELVORON CPL. Creating An Accessible World ELVORON CPL Design And Planning Guide www.garaventalift.com Please note: Dimensions provided in this Guide are for REFERENCE ONLY and should not be used for site preparation

More information

Technical Information

Technical Information Date of last update: Sep 12 Ref: Application Engineering Europe COPELAND SCROLL COMPRESSORS USING VAPOUR INJECTION FOR REFRIGERATION CONTENTS 1 Introduction... 2 2 Principle of operation... 2 3 Capacity

More information

10 20KVA 3Ph/1Ph KVA 3Ph / 3Ph

10 20KVA 3Ph/1Ph KVA 3Ph / 3Ph VEGA INDUSTRIAL UNINTERRUPTIBLE POWER SUPPLY 10 20KVA 3Ph/1Ph 10 120KVA 3Ph / 3Ph - 6 pulse SCR rectifier - IGBT inverter - Power output transformer - Low and stable ripple on battery for the highest battery

More information

ECO 250 CUTTER SUCTION DREDGER

ECO 250 CUTTER SUCTION DREDGER ECO 250 CUTTER SUCTION DREDGER RELIABLE BRANDS REPLACEABLE AUGER KNIVES OPTIMIZED PRODUCTION Dredge Yard +31 85 3035 866 www.dredgeyard.com MULTI-PURPOSE DREDGERS QUALITY FROM START TO FINISH Dredge Yard

More information

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation Basis of Design This section applies to the design relating to low voltage switchboards. Design Criteria UW Class N1 facilities main switchboards shall be rear accessible. The main, tie and feeder breakers

More information

Industrial Turbo Meters, Sizes 2" through 6"

Industrial Turbo Meters, Sizes 2 through 6 Industrial Turbo Meters Sizes 2" through 6" TUR-UM-00530-EN-19 (October 2014) User Manual Industrial Turbo Meters, Sizes 2" through 6" User Manual CONTENTS Scope of the Manual 5 Specifications 5 Product

More information

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655) - (SMUD FORM 2655) A. Applicability: This Generating Facility Interconnection Application (Application) shall be used to request the interconnection of a Generating Facility to Sacramento Municipal Utility

More information

NC State University Design and Construction Guidelines Division 23 Energy Management

NC State University Design and Construction Guidelines Division 23 Energy Management 1.1 Purpose A. The following guidelines provide the methodology and requirements to assure that designs meet NC State standards for campus utility metering. 2.1 General Requirements A. Meters shall have

More information

SJP Vertical Propeller Pumps

SJP Vertical Propeller Pumps Sulzer Pumps SJP Vertical Propeller Pumps The Heart of Your Process Sulzer Pumps Sulzer Pumps is a world leader in reliable products and innovative pumping solutions. Our advanced research and development,

More information

E-15 Uninterruptible Power Systems (UPS)

E-15 Uninterruptible Power Systems (UPS) Guideline No.E-15 (201510) E-15 Uninterruptible Power Systems (UPS) Issued date:20 October, 2015 China Classification Society Foreword This Guide is a part of CCS Rules, which contains technical requirements,

More information

FINAL REPORT CATHODIC PROTECTION EVALUATION. 42-Inch Water Transmission Pipeline Contract 1 Station 0+00 to South Texas Water Authority

FINAL REPORT CATHODIC PROTECTION EVALUATION. 42-Inch Water Transmission Pipeline Contract 1 Station 0+00 to South Texas Water Authority FINAL REPORT CATHODIC PROTECTION EVALUATION 42-Inch Water Transmission Pipeline Contract 1 Station 0+00 to 50+00 South Texas Water Authority Prepared for: South Texas Water Authority P.O. Box 1701 Kingsville,

More information

Defender Mini Online Emergency Central Lighting Inverter (CLI) Technical Specifications

Defender Mini Online Emergency Central Lighting Inverter (CLI) Technical Specifications Defender Mini Online Emergency Central Lighting Inverter (CLI) Technical Specifications PART 1 GENERAL 1.1 SUMMARY A. The Defender Mini CLI specification describes a single phase, online, solid state Lighting

More information

SECTION HYDRAULIC FOUR FOLD DOORS MODEL 48 LOUVERS

SECTION HYDRAULIC FOUR FOLD DOORS MODEL 48 LOUVERS SECTION 08350 HYDRAULIC FOUR FOLD DOORS MODEL 48 LOUVERS PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division-1

More information

Quick guide. Plug-in fans GPPM with FC101_106 August 2014

Quick guide. Plug-in fans GPPM with FC101_106 August 2014 Quick guide Plug-in fans GPPM with FC101_106 August 2014 Fläkt Woods permanent magnet motors and speed controllers for plug fans GPPM 1. General Fläkt Woods offers a wide range of permanent magnet motors

More information

In general this document presents specific safety procedures for systems with potentially lethal voltages on bare or exposed conductors.

In general this document presents specific safety procedures for systems with potentially lethal voltages on bare or exposed conductors. 1. Introduction All safety rules presented in this document are intended to ensure safe working conditions while working with potentially dangerous voltages. It is assumed that all personnel working with

More information

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test: Salisbury Substation 11kV Feeders DISCLAIMER The purpose of this document is to inform customers, Interested Parties,

More information

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER E: THE REACTOR COOLANT SYSTEM AND RELATED SYSTEMS

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER E: THE REACTOR COOLANT SYSTEM AND RELATED SYSTEMS PAGE : 1 / 13 4. PRESSURISER 4.1. DESCRIPTION The pressuriser (PZR) is a pressurised vessel forming part of the reactor coolant pressure boundary (CPP) [RCPB]. It comprises a vertical cylindrical shell,

More information

F SPS Commissioning Check Sheet Template

F SPS Commissioning Check Sheet Template F8943 - SPS Commissioning Check Sheet Document Details This document is only valid on the day it was printed. Document Owner References Manager Capital Delivery SPS Commissioning Worksheet End to End Test

More information

WIRING DESIGN & PROTECTION REQUIREMENTS CHECKLIST

WIRING DESIGN & PROTECTION REQUIREMENTS CHECKLIST WIRING DESIGN & PROTECTION REQUIREMENTS CHECKLIST Use & Identification of Grounded and Grounding Conductors YES NO N/A Grounded conductors are identifiable and distinguishable from all other conductors.

More information