Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Similar documents
Local Transmission Plan. Rev. 1: April 2018

2017 Interim Area Transmission Review of the New York State Bulk Power Transmission System

2016 Load & Capacity Data Report

2015 Preliminary Weather Normalized MW and 2016 ICAP Forecast (V3)

TRANSMISSION PLANNING CRITERIA

The Long-Range Transmission Plan

National Grid s 2017 Local Transmission Plan

Falcon-Midway 115 kv Line Uprate Project Report

National Grid s 2018 Local Transmission Plan

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Hurricane Sandy. Preparations, Response & Recovery. Wes Yeomans Vice President Operations Management Committee Meeting November 2, 2012

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

2018 Load & Capacity Data Report

EXCEPTIONS TO RELIABILITY RULES REVISION 4 MAY 8, 2015

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

EXCEPTIONS TO NYSRC RELIABILITY RULES

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

EXCEPTIONS TO RELIABILITY RULES Revision 11 February 9, 2018

MILLIGAN SOLAR PROJECT

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Knickerbocker to Pleasant Valley 345 kv Transmission Line Project (KB-PV)

DFO STATEMENT OF NEED REPORT

West Station-West Cañon 115 kv Transmission Project

EXCEPTIONS TO RELIABILITY RULES Revision 10 August 11, 2017

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Illinois State Report

2013 CARIS Phase 1 Report

LOCAL TRANSMISSION PLAN

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

2019 Preliminary ICAP Forecast

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Interconnection System Impact Study Report Request # GI

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

2013 ANNUAL PROGRESS REPORT

SPS Planning Criteria and Study Methodology

CUSTOMER/ TWIN ARROWS PROJECT

100 MW Wind Generation Project

Appendix D Black Hills Project Summary

Overview of ISO New England and the New England Wholesale Power Markets

Sub Regional RTEP Committee Mid-Atlantic

Merger of the generator interconnection processes of Valley Electric and the ISO;

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan

SPP Notification to Construct

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

2013 Intermediate Area Transmission Review Of the New York State Bulk Power Transmission System (Study Year 2018) DRAFT REPORT

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Sub Regional RTEP Committee South

Interconnection Feasibility Study Report GIP-226-FEAS-R3

SERTP rd Quarter Meeting

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Western NY Public Policy Transmission Report

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Interconnection Feasibility Study Report GIP-222-FEAS-R3

New Jersey State Report

2018 Final ICAP Forecast

Key to Status Fields in the Project List

ATTACHMENT - DFO STATEMENT OF NEED

Sub Regional RTEP Committee Mid-Atlantic

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Supplemental Report on the NCTPC Collaborative Transmission Plan

Sub Regional RTEP Committee South

Transit Access Study

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

APPENDIX E: Project Need and Description

MINIMUM OIL BURN/AUTOMATIC FUEL SWAPPING CAPABILITY

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

New 115 kv Disconnect Switches at Bloomsburg MTS

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

2014 Intermediate Area Transmission Review Of the New York State Bulk Power Transmission System (Study Years 2015, 2019, 2024)

The Green Line Project

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

NYCA LOLE Violations (Methods D and E )

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

SMUD 2014 Ten-Year Transmission Assessment Plan. Final. December 18, 2014

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Feasibility Study Report

Imperial Irrigation District Energy Consumers Advisory Committee Agenda Report

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

Gateway South Transmission Project

Effects of Smart Grid Technology on the Bulk Power System

System Impact Study Report

Energy Policy Implications: PJM Planning

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Meeting Policy Objectives Transmission: A Path to Compliance

New York s Mandatory Hourly Pricing Program

Western Area Power Administration Sierra Nevada Region

Fire Station Location Study

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

Black Hills Project Summary

APPENDIX E: Project Need and Description

Transcription:

Local Transmission Plan October 11, 2013 Revised August 25, 2014

2

Central Hudson s System Zone G: Majority of Central Hudson s load Zone E: One small distribution substation Interconnections with Consolidated Edison, Orange & Rockland, NYSE&G, National Grid, Northeast Utilities, First Energy, NYPA Own & Operate approximately 622 miles of 69 kv, 115 kv & 345 kv transmission lines; three 345 kv stations. 3

Historic Peak Load Summer Peak Loads Winter Peak Loads Year NYCA Zone G CHG&E+ Year NYCA Zone G CHG&E+ 2004 28433 2041 1051 2004-05 25541 1766 988 2005 32075 2236 1204 2005-06 24947 1663 960 2006 33939 2436 1295 2006-07 25057 1638 934 2007 32169 2316 1185 2007-08 25021 1727 960 2008 32432 2277 1187 2008-09 24673 1634 911 2009 30844 2159 1107 2009-10 24074 1527 909 2010 33452 2399 1229 2010-11 24654 1586 905 2011 33865 2415 1225 2011-12 23901 1618 861 2012 32439 2273 1168 2012-13 24658 1539 907 2013 33956 2358 1202 2013-14 25738 1700 938 + CHG&E Loads not coincident with other NYCA loads 4

Forecast Peak Load Summer Forecast Year NYCA* Zone G* CHG&E+ 2014 33725 33666 2288 2290 1171 1150 2015 34138 34066 2319 2309 1173 1153 2016 34556 34412 2347 2324 1176 1148 2017 34818 34766 2368 2336 1179 1151 2018 35103 35111 2388 2347 1182 1150 2019 35415 35454 2408 2355 1185 1149 2020 35745 35656 2425 2363 1187 1147 2021 36068 35890 2440 2370 1190 1146 2022 36355 36127 2456 2377 1192 1145 2023 36613 36369 2472 2383 1195 1144 2024 36580 2388 1143 * From 2013 2014 Gold Book Table I-2a + CHG&E Forecast (includes impact of energy efficiency) 5

Facilities Covered by Central Hudson s Local Transmission Plan Central Hudson s Local Transmission Plan is intended to provide safe & reliable service to the load within our franchise area. This plan does not address state-wide issues such as intra-state and inter-state transfer limits. This plan does not address in-kind equipment replacements 6

Facilities Covered by Central Hudson s Local Transmission Plan Transmission lines: 69 kv and 115 kv Transmission system transformers: 345/115 kv 115/69 kv Substation facilities (69 kv, 115 kv, 345 kv) 7

Planning Horizon Annual planning process First 5 years - corporate capital forecast generally firm projects budgetary estimates and timing Additional 5 years (years 6 through 10) generally potential projects planning estimates and timing 8

Data & Models Load Flow cases produced by NYISO Staff NYISO Staff solicits input from all Transmission Owners Individual historic substation loads coincident with Central Hudson s peak hour Compliance requirements 9

Issues Addressed Return of Danskammer Generation to Service Complete 115 kv Danskammer Bus Reinforcement. Portions of this project were completed in 2013. The remaining portions were discontinued following Danskammer s out of service status. 10

Issues Addressed Central Hudson s System Load Serving Capability Consideration of through-flows Consideration of proposed interconnections Central Hudson Local Areas Load Serving Capabilities Northwest 69 kv Southwest 69 kv Southern Dutchess 115 kv Mid-Dutchess 115 kv Ellenville Area Newburgh Area Eastern Dutchess 69 kv Kingston Rhinebeck Load Serving Capabilities determined for More Probable Contingencies* * CHG&E Transmission Planning Guidelines, pg. 5 11

Issues Addressed Central Hudson Transmission System Infrastructure facility inspection reports, condition assessments and diagnostic test data Maintain sufficient reactive support for local needs The typical distribution circuit is designed for a power factor = 1.0 at time of peak The peak system power factor is monitored to determine aggregate power factor of distribution system Transmission capacitors installed for voltage support 12

Project Addressing System Load Serving Capability 13

Project Addressing System Load Serving Capability Firm Project 115 kv Fishkill Plains East Fishkill Rebuild Need Post contingency overload Proposed In Service 2020 (Under reevaluation) 14

Project Addressing System Load Serving Capability Firm Project 115 kv Danskammer Bus Reinforcement -upgrade disconnect switches -upgrade strain bus Need Post contingency overload Proposed In Service 2016 (Partially Complete) 15

Project Addressing Local Area Load Serving Capability 16

Project Addressing Local Area Load Serving Capability Local Area Firm Project Need Proposed In Service Ellenville Area Convert from 69 kv to 115 kv (Lines are constructed for 115 kv operation) Post contingency overload 2020 17

Projects Addressing Infrastructure Condition Issues 18

Projects Addressing Infrastructure Condition Issues Firm Project Issue Proposed In Service 115 kv Pleasant Valley Todd Hill Rebuild Tests have shown a loss of 2015 115 kv Todd Hill Fishkill Plains Rebuild tensile strength for certain ACSR conductors 2015 19

Projects Addressing Infrastructure Condition Issues Firm Project Issue Proposed In Service Rebuild existing 69 kv Knapps Corners to Pleasant Valley (Northern Section) -Rebuild for 69 kv -Install 115/69 kv transformer at Todd Hill Detailed condition assessment has identified need for comprehensive rebuild 2017 20

Projects Addressing Infrastructure Condition Issues Firm Project Issue Proposed In Service 69 kv Honk Falls West Woodbourne Rebuild Tests have shown a loss of tensile strength for certain ACSR conductors 2017 21

Projects Addressing Infrastructure Condition Issues Firm Project Issue Proposed In Service Rebuild existing 69 kv Hurley Avenue to North Catskill for 115 kv Detailed condition assessment has identified need for comprehensive rebuild 2018 22

Potential Projects Addressing Local Area Load Serving Capability 23

Potential Projects Under Consideration Local Area Potential Solution Need Proposed In Service Southern Dutchess Area Additional 115 kv Area Input (e.g., East Fishkill to Merritt Park 115 kv) Post contingency overload 2019 (Under Study) 24

Potential Projects Under Consideration Local Area Potential Solution Need Proposed In Service Northwest Area Additional 115 kv Area Input Post contingency overload 2020 (Under Study) 25

Potential Project Under Consideration Local Area Potential Solution Issue Proposed In Service Mid- Dutchess Area Rebuild existing 69 kv Knapps Corners to Pleasant Valley (Southern Section) for 115 kv Post contingency overload and detailed condition assessment has identified need for comprehensive rebuild 2020 (Under Study) 26

Comments Interested parties should forward any comments to: Richard B. Wright Senior Engineer Electric Transmission Planning Central Hudson Gas & Electric Corporation 284 South Avenue Poughkeepsie, NY 12601 rwright@cenhud.com 27