1 ELECTRICITY INFRASTRUCTURE DEVELOPMENT FOR ECONOMIC GROWTH BY CHRISTOPHER MUBEMBA DIRECTOR TRANSMISSION - ZESCO LTD

2 TABLE OF CONTENTS 1.Background 2.Current Status 3.Investment Portfolio 3.1 Generation Projects 3.2 Transmission Projects 3.3 Distribution Projects 4.Conclusion 2

3 INTRODUCTION ELECTRICITY IS A KEY DRIVER OF ECONOMIC GROWTH & MAJOR INPUT IN ALL ECONOMIC SECTORS - AGRICULTURE, MINING, MANUFACTURING AND TOURISM UNTIL RECENTLY ZESCO S ELECTRICITY GENERATING CAPACITY WAS AT 1.6GW (99% HYDRO) NET EXPORTS ROUGHLY 5% OF TOTAL GENERATION (MOSTLY TO NAMIBIA, BOTSWANA AND CONGO D.R.) UNTIL RECENTLY THE PEAK DEMAND FOR ELECTRICITY WOULD EXCEED GENERATION CAPACITY BY ABOUT 300MW DURING PEAK ZAMBIA HAS EXPERIENCED A SUSTAINABLE ECONOMIC GROWTH OVER THE LAST FIVE YEARS DESPITE GLOBAL RECESSION, RESULTING IN: INCREASED DEMAND FOR ELECTRICITY FROM ALL SECTORS DEMAND OUTSTRIPPING AVAILABLE CAPACITY DURING PEAK HOURS (250MW SHORTFALL) ZESCO IS INVESTING IN NEW INFRASTRUCTURE TO COPE WITH GROWING DEMAND 3

4 MW FACTFILE ELECTRICITY DEMAND NATIONAL MAXIMUM DEMAND IS NOW ESTIMATED AT MORE THAN 1650 MW WITH PROJECTED GROWTH OF 3-4% p.a. ACCESS TO ELECTRICITY: 22% IN URBAN AREAS AND 3% IN RURAL AREAS Demand Forecast for Zambia Demand Years 4

5

6 ZESCO 18/06/13 6

7 GENERATION PROJECTS REHABILITATION PROJECTS COMPLETED IN MAJOR GENERATING STATIONS STATION CAPACITY BEFORE PRP CAPACITY AFTER PRP KAFUE GORGE 900 MW 990 MW KARIBA NORTH BANK 600MW 720MW VICTORIA FALLS 108 MW 108 MW 7

8 GENERATION PROJECTS REHABILITATION AND UP-RATING PROJECT COVERING SMALL HYDROPOWER GENERATING STATIONS STATION CAPACITY BEFORE CAPACITY AFTER LUNZUA 0.75 MW 14.8 MW - (2014) MUSONDA FALLS 5.0 MW 10.0 MW - (2015) CHISHIMBA FALLS 6.0 MW 14.8 MW - (2016) LUSIWASI LOWER 12.0 MW 86.0 MW - (2018) 8

9 GENERATION PROJECTS NEW HYDROPOWER GENERATION PROJECTS INSTALLED CAPACITY TARGET YEAR OF COMPLETION KARIBA NORTH BANK - EXTENSION (PEAKING PLANT) 360 MW MW MW ITEZHI-TEZHI MW 2015 LUSIWASI UPPER 15.0 MW

10 TRANSMISSION PROJECTS TRANSMISSION ASSETS VOLTAGE DISTANCE (KM) 330 KV 2, KV KV KV KV 1,037 HIGH VOLTAGE SUBSTATIONS 27 NATIONAL CONTROL CENTER 01 REGIONAL CONTROL CENTERS 03 DISTRIBUTION ASSETS 66KV 2,180 33KV 2,100 11KV 1,037 SUBSTATIONS 5,000 10

11 LOAD FORECAST Year FORECAST MAXIMUM DEMAND (MW) FORECAST SHORTFALL (MW) 1,579 1,592 2,389 2,595 3, ,179

12 POWER REHABILITATION PROJECT (PRP) OVERALL OBJECTIVE WAS TO SUPPORT THE GOVERNMENT S OBJECTIVES OF ENHANCING THE ABILITY OF ZAMBIA S ELECTRICITY SUPPLY INDUSTRY TO PROVIDE ELECTRICITY AT LEAST COST AND IN AN EFFICIENT AND SUSTAINABLE MANNER TO STIMULATE MORE AND INCLUSIVE GROWTH IN THE ZAMBIAN ECONOMY. THE REHABILITATION WORKS INVOLVED TWO MAJOR COMPONENTS; GENERATION INFRASTRUCTURE AND TRANSMISSION AND DISTRIBUTION PRP WAS FUNDED BY BILATERAL AND MULTILATERAL AGENCIES LED BY THE WORLD BANK. GOVERNMENT AND ZESCO ALSO PARTICIPATED PROJECT COST: OVER USD320 MILLION 12

13 POWER REHABILITATION PROJECT (PRP) Scope included rehabilitation and uprating of the three major hydropower stations, i.e. Kafue Gorge, KNBPS and Victoria Falls Other works included reinforcement and rehabilitation of some transmission and distribution infrastructure The major achievements of the PRP has been the uprating of the Kafue Gorge Power Station from 900 to 990 MW, the reinstating of the Victoria Falls Power Station to its full generating capacity of 108 MW as well as the up-rating of Kariba North Bank power station from 600 MW to 720 MW. Total generation capacity added to system from the PRP is 210 MW 13

14 ESTIMATE OF EXPENDITURES ON POWER REHABILITATION PROJECT (PRP) VICTORIA FALLS POWER STATION USD53.7MILLION KAFUE GORGE POWER STATION - USD 85.5 MILLION KARIBA NORTH BANK POWER STATION USD81.4MILLION THEREFORE TOTAL COST USD MILLION ESTIMATED COST FOR A NEW 210 MW POWER STATION >US$ 500 MILLION 14

15 NEW GENERATION PROJECTS KARIBA NORTH BANK EXTENSION 2x180MW OWNER: ZESCO LIMITED/KNBEPC COST: USD 420M DURATION: 4 YEARS OPERATION: 2013/14 Unit No. 5 commissioned in December 2013 Unit No. 6 commissioning in progress 15

16 NEW GENERATION PROJECTS ITEZHI TEZHI HYDROPOWER PROJECT (120 MW) OWNER: PPP (ZESCO/TATA) COST: USD 232M DURATION: 3.5 YEARS OPERATION: 2015 STATUS: ENABLING WORKS COMPLETED, MAIN WORKS IN PROGRESS AT OVER 40% COMPLETE 16

17 NEW GENERATION PROJECTS Kafue Gorge Lower Hydropower Project (750 MW) OWNER:PPP (ZESCO/EQUITY PARTNER) COST:USD 2 BILLION DURATION: 6 YEARS OPERATION: 2019 STATUS: FEASIBILITY REPORT COMPLETE, PROJECT PREPARATORY ACTIVITIES UNDERWAY. PROCUREMENT OF CONSULTANTS & ADVISORS IN PROGRESS. GRZ HAS ALLOCATED US$ 186 M (ZMK930 TR) FROM THE EURO BOND FOR THE KGL PROJECT 17

18 NEW GENERATION PROJECTS SMALL HYDROS LUSIWASI LOWER 86 MW US$164M EPC CONTRACT AWARDED LUNZUA-15 MW US$52M OVER 65% PROGRESS, COMPLETION ON SCHEDULE FOR SEPTEMBER 2014 LUSIWASI UPPER -15 MW US$47M EPC CONTRACT AWARDED REHABILITATION AND UPRATING OF CHISHIMBA FALLS: MW US$46M EIA APPROVED, TENDER DOCUMENT PREPARATION UNDERWAY REHABILITATION AND UPRATING OF MUSONDA FALLS: 5-10 MW US$32M EPC CONTRACT AWARDED SHIWANG ANDU 1 MW USD4.15 MILLION PLANT COMMISSIONED IN DECEMBER

19 NEW GENERATION PROJECTS POTENTIAL SITES BATOKA GORGE 1600 MW MPATA GORGE 540 MW DEVIL S GORGE 500 MW MUMBOTUTA FALLS MW MAMBILIMA FALLS SITE I 202 MW MAMBILIMA FALLS SITE I 124 MW KABWELUME FALLS - 62 MW KUNDABWIKA FALLS 101 MW MUTINONDO - 40 MW LUCHENENE 30 MW MKUSHI 65 MW 19

20 TRANSMISSION PROJECTS PENSULO KASAMA AND PENSULO CHIPATA 330 KV PROJECT The objective is to improve power quality in Eastern, Muchinga, Northern and Luapula provinces and to increase transmission capacity to these areas Scope: about 382 km of 330 kv lines (Pensulo - Kasama) and 285 km of 330 kv lines (Pensulo - Chipata) with associated substations Cost: USD335 million Status: funds secured, EPC contractor is TBEA, EIA approved, survey works completed, tower spotting and foundations being done Funding: Industrial and Commercial Bank of China Construction Period: 30 months from August

21 CONNECTION OF NORTH WESTERN PROVINCE TO NATIONAL GRID The objective is to support the increased access to electricity and improved quality of service by displacing the expensive diesel generators Scope: about 800 km of 132 km transmission lines, 330/132 kv substation and 132/33 kv substations in Mwinilunga, Kabompo, Mufumbwe, Zambezi, Lukulu and Chavuma Cost: USD150 million Funding: Loan agreement signed with NORDEA of Sweden and Standard Bank of South Africa Status: Contract signed with ELTEL of Sweden Construction period 24 months 21

22 TRANSMISSION PROJECTS KARIBA NORTH BANK EXTENSION POWER EVACUATION PROJECT The objective is to increase transmission capacity from KNBPS to the grid for the evacuation of power from KNBE project Scope: 123 km of 330 kv lines and substation works Cost: USD62 million Status: EPC contractor is Sinohydro, EIA approved, survey works and bush clearing completed. Towers being erected. Substations works complete Funding: China EXIM Bank Construction Period: 18 months (by November 2013 now May 2014) 22

23 KAFUE TOWN MUZUMA VICTORIA FALLS TRANSMISSION LINE UPGRADE The objective is to increase transmission capacity southwards for export to and from SAPP and provide evacuation path for new generation projects Scope: Upgrade 348 km of 220 kv line to 330 kv Cost: USD100 million Status: Consultant Mott McDonald. Three lots for the tenders Transformers and reactors, substations and lines Funding: World Bank and European Investment Bank Construction Period: 18 months 23

24 ITT MUMBWA LUSAKA WEST TRANSMISSION LINE PROJECT The objective is to provide power evacuation for the ITT power station Scope: 142 km of 220 kv line and 134 km of 330 kv line and associated substation at Mumbwa Cost: USD133 million Funding: EIB, AfDB and AFD Status: EIA completed and approved, survey and soil investigations completed. Procurement in progress lines and substations. Award given for substations 24

25 SUPPLY TO KALUMBILA MINE The objective is to supply power to the proposed FQM Kalumbila mine Scope: 500km of 330 kv double circuit line and 66 km of 330 kv single circuit line and associated substation at Kalumbila Cost: USD300 million Funding from Kalumbila Minerals Limited/ZESCO Status: EIA study completed, survey in progress, bush clearing and tower spotting Line by Kalpataru of India substations by ABB of Germany 25

26 CONNECTION OF LUANGWA DISTRICT TO THE GRID The objective is to support the increased access to electricity and improved quality of service by displacing the expensive diesel generators Scope: 187km of 132kV transmission, 2x10MVA 132/33kV Substations at Rufunsa and Luangwa, 60km of 33kV lines in Mpanshya, service connection to GRZ institution and 100km of 33kV lines in Luangwa Cost; USD63million Funding: EXIM Bank of India Status: PME of India. Line and substation works in progress. Construction period: 24 months (December 2014) 26

27 TRANSMISSION PROJECTS LUSAKA 132KV RING REINFORCEMENT PROJECT PHASE I The objective is to increase the transmission capacity of the Leopards Hill Coventry 132kV transmission line Scope: Reconductoring 28km of 132kV transmission, Installation of 2x45MVA 132/11kV transformers at Coventry substation Cost: USD6.3million Funding: ZESCO Limited Status: Tenders awarded for supply of conductor, supply of transformers and services 27

28 LUSAKA 132KV RING REINFORCEMENT PROJECT PHASE II The objective is to increase the transmission capacity of the Lusaka Transmission and Distribution Network Scope: Upgrade of capacity of 132kV transmission lines, increase capacity of existing substations, create new substations at 132/33kV, 33/11kV levels, construction new 33kV and 11kV lines Cost: USD210million Funding: World Bank, European Investment Bank and ZESCO Limited Status: Financing discussions completed. WB approved on 31 st May 2013, EIB approved March Construction period: phased 3 5 years 28

29 ZIZABONA The objective is to increase regional trade in power by increasing transmission capacity for north to south and east to west power trading Project promoted by Zimbabwe, Zambia, Botswana and Namibia Cost: USD230million Funding: Discussions initiated with potential financiers. DBSA, AFDB, KfW Status: technical and market studies completed, project governance documents prepared IUMOU, IGMOU signed. Joint Development Agreement to be signed by BPC. Will lead to signing of Shareholders Agreement TA, Consultantsto be engaged soon and SPV registration is underway 29

30 DISTRIBUTION PROJECTS ZESCO carrying out various projects to reinforce and rehabilitate the distribution infrastructure Distribution and expansion reinforcement project USD 100 million in progress Increased Access to Electricity Services, sponsored by WB, JICA and other financiers in progress 30

31 PLANNED CAPITAL INVESTMENT 2012/13 RESULTS FROM LOAD FORECASTS REVEAL FUTURE DEMAND/SUPPLY IMBALANCES. GRZ VISION OF ACHIEVING MIDDLE INCOME STATUS BY 2030 THIS DRIVES LONG TERM GENERATION, TRANSMISSION AND DISTRIBUTION INVESTMENT PLANS ZESCO PLANS TO SPEND ABOUT ZMK 29BN (US$5bn) ON ASSETS AND INFRASTRUCTURE OVER THE NEXT FIVE YEARS

32 THANK YOU 32

ELECTRICITY SUPPLY INDUSTRY OF ZAMBIA

ELECTRICITY SUPPLY INDUSTRY OF ZAMBIA ELECTRICITY SUPPLY INDUSTRY OF ZAMBIA General Information for Potential Investors March 2008 This publication was produced for review by the United States Agency for International Development. It was prepared

More information

ZESCO LIMITED BUSINESS DEVELOPMENT DEPARTMENT

ZESCO LIMITED BUSINESS DEVELOPMENT DEPARTMENT ZESCO LIMITED BUSINESS DEVELOPMENT DEPARTMENT GENERAL DESCRIPTION OF THE ELECTRICITY SYSTEM 1. 2009 Degree of electrification; percentage of population with direct access to grid electricity, to isolated

More information

ENERGY REGULATION BOARD

ENERGY REGULATION BOARD ENERGY REGULATION BOARD ZAMBIA NATION-WIDE POWER BLACKOUT OF JUNE 4, 2006 REPORT BY THE EXPERT TEAM CONSTITUTED TO INVESTIGATE THE POWER OUTAGE JULY 2006, LUSAKA, ZAMBIA. i Report submitted to the Executive

More information

Electricity industry structure and key players

Electricity industry structure and key players Electricity industry structure and key players Growth in capacity, production and consumption, 2006 2017 Expected demand and addition to generation capacity, 2018 2027 Growth in transmission network and

More information

A Forward March towards an Energy Empowered Nation Case Study in Sri Lanka

A Forward March towards an Energy Empowered Nation Case Study in Sri Lanka A Forward March towards an Energy Empowered Nation Case Study in Sri Lanka Menaka Rajaguru Department of External Resources Ministry of National Policies and Economic Affairs Country Profile Country Profile

More information

STATUS OF RURAL ELECTRIFICATION IN ZAMBIA

STATUS OF RURAL ELECTRIFICATION IN ZAMBIA STATUS OF RURAL ELECTRIFICATION IN ZAMBIA Date: 11 th April 2017 Venue: Lusaka Presentation by Mr. Geoffrey Musonda Rural Electrification Authority (REA) Chief Executive Officer (CEO) Presentation outline

More information

Business opportunities and major projects in India

Business opportunities and major projects in India Business opportunities and major projects in India Rajesh Sharma Vice President, Financing Why India? Fastest growing economy now and in future India to become one of the world's three largest economies

More information

PRESENTATION ON ELECRICITY SUPPLY IN BOTSWANA. Botswana China Business Forum. 31 August 2018

PRESENTATION ON ELECRICITY SUPPLY IN BOTSWANA. Botswana China Business Forum. 31 August 2018 PRESENTATION ON ELECRICITY SUPPLY IN BOTSWANA Botswana China Business Forum 31 August 2018 PRESENTATION PLAN 1. THE ELECTRICITY SUPPLY INDUSTRY IN BOTSWANA 2. ELECTRICITY CONSUMPTION AND SOURCES OF SUPPLY

More information

Sentinel & Enterprise Mines. Introductory presentation 28 August 2015

Sentinel & Enterprise Mines. Introductory presentation 28 August 2015 Sentinel & Enterprise Mines Introductory presentation 28 August 2015 1 Trident Project location 2 Orientation project layout 3 Sentinel - Zambia s newest Cu mine Updated resource published March 2012:

More information

Southern African Power Pool

Southern African Power Pool Southern African Power Pool www.sapp.co.zw Status of the SAPP Regional Interconnection Projects and Other Updates Dr. Lawrence Musaba SAPP Coordination Centre Manager Consultative Meeting of the African

More information

ELECTRICITY SUPPLY INDUSTRY OF BOTSWANA

ELECTRICITY SUPPLY INDUSTRY OF BOTSWANA ELECTRICITY SUPPLY INDUSTRY OF BOTSWANA General Information for Potential Investors May 2008 This publication was produced for review by the United States Agency for International Development. It was prepared

More information

SOURCE OF FUNDING ESTIMATE D PROJECT COST. Government funding. USD 344million. GoT - 15% JBIC 85% Contractor: Sumitomo Corporation

SOURCE OF FUNDING ESTIMATE D PROJECT COST. Government funding. USD 344million. GoT - 15% JBIC 85% Contractor: Sumitomo Corporation NEW & ON-GOING POWER PROJECTS TO BE IMPLEMENTED UP TO 2017 SN PROJECT NAME 1. Kinyerezi I Extension 185MW gas fired power plant PROJECT DESCRIPTION construction of 185MW simple cycle gas fired at Kinyerezi

More information

Table 1 ANTIGUA AND BARBUDA: MAIN ECONOMIC INDICATORS

Table 1 ANTIGUA AND BARBUDA: MAIN ECONOMIC INDICATORS Antigua Tables 2006 1 Main Indicators 03/11/2006 08:05 AM Table 1 ANTIGUA AND BARBUDA: MAIN ECONOMIC INDICATORS 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 a/ Annual growth rates b/ Gross domestic

More information

EU Development Cooperation in the Energy Sector Update on the activity of the Technical Assistance Facility (TAF)

EU Development Cooperation in the Energy Sector Update on the activity of the Technical Assistance Facility (TAF) EU Development Cooperation in the Energy Sector Update on the activity of the Technical Assistance Facility (TAF) Delivering results in the Decade of Sustainable Energy for All EUROPEAN COMMISSION Directorate

More information

ENERGY SECTOR REPORT. Energy Sector Report 2016

ENERGY SECTOR REPORT. Energy Sector Report 2016 ENERGY SECTOR REPORT 2016 1 Energy Regulation Board 2 VISION A proactive, firm and fair energy regulator MISSION STATEMENT To regulate the energy sector in order to ensure efficient provision of reliable

More information

9 th Germany Africa Energy Forum. Overview of the Copperbelt Energy Corporation (CEC) Business. Tuesday, 26 May 2015

9 th Germany Africa Energy Forum. Overview of the Copperbelt Energy Corporation (CEC) Business. Tuesday, 26 May 2015 9 th Germany Africa Energy Forum Overview of the Copperbelt Energy Corporation (CEC) Business Tuesday, 26 May 2015 Republic of Zambia 2 Introduction 3 Historical Background: CEC was formed in 1997 from

More information

Rwanda Biofuels Limited. Powering Rwanda s Development

Rwanda Biofuels Limited. Powering Rwanda s Development Rwanda Biofuels Limited Powering Rwanda s Development 1. Global Bio-Fuel Industry Trans esterification of vegetable oil was conducted as early as 1853, many years prior to the first diesel engine. Trans

More information

COMMERCIALISATION OF UGANDA S OIL AND GAS SECTOR: REFINERY AND ATTENDANT INFRASTRUCTURE DEVELOPMENT

COMMERCIALISATION OF UGANDA S OIL AND GAS SECTOR: REFINERY AND ATTENDANT INFRASTRUCTURE DEVELOPMENT MINISTRY OF ENERGY AND MINERAL DEVELOPMENT COMMERCIALISATION OF UGANDA S OIL AND GAS SECTOR: REFINERY AND ATTENDANT INFRASTRUCTURE DEVELOPMENT Dr. Stephen Robert Isabalija PERMANENT SECRETARY 13 th -15

More information

The first successful concessioner

The first successful concessioner The first successful concessioner Our mission Promoting the development of electric power industry through participating in the improvement of the structure of the unified power system of Kazakhstan. Support

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

Title of presentation

Title of presentation Title of presentation Power Projects Selection, Risk, Financing & Operation by Professor Bart Nnaji Chairman & CEO ipad West Africa 2008, Abuja, NIGERIA The State of Power in Africa Installed Capacity

More information

Transportation Electrification Public Input Workshop. August 3, 2016

Transportation Electrification Public Input Workshop. August 3, 2016 Transportation Electrification Public Input Workshop August 3, 2016 1 Agenda Welcome and Introductions Company Overview Existing Transportation Electrification Initiatives Accelerating Transportation Electrification

More information

Success Story Scaling Up Energy Efficiency An Indian Experience

Success Story Scaling Up Energy Efficiency An Indian Experience ASIA CLEAN ENERGY FORUM 2017 Success Story Scaling Up Energy Efficiency An Indian Experience Nitin Bhatt Regional Manager - UJALA Energy Efficiency Services Ltd. (EESL), India Largest ESCO in the world

More information

SUPPLEMENTARY EVIDENCE FROM SCOTTISH AND SOUTHERN ENERGY

SUPPLEMENTARY EVIDENCE FROM SCOTTISH AND SOUTHERN ENERGY SUPPLEMENTARY EVIDENCE FROM SCOTTISH AND SOUTHERN ENERGY Scottish Parliament - Economy, Energy & Tourism Committee National Planning Framework - Evidence Session 14 th January 2009 SHETL Response 1. Key

More information

PARLIAMENTARY REFORM ON ENERGY LEGISLATION AND SUSTAINABLE DEVELOPMENT 5 7 OCTOBER, 2005, CAPE TOWN, SOUTH AFRICA

PARLIAMENTARY REFORM ON ENERGY LEGISLATION AND SUSTAINABLE DEVELOPMENT 5 7 OCTOBER, 2005, CAPE TOWN, SOUTH AFRICA PARLIAMENTARY REFORM ON ENERGY LEGISLATION AND SUSTAINABLE DEVELOPMENT 5 7 OCTOBER, 2005, CAPE TOWN, SOUTH AFRICA PAPER ON ZAMBIA S EXPERIENCE WITH POWER SECTOR REFORM BY: HON. DR. PETER D MACHUNGWA, MP

More information

Workshop on International Good Practices of Sustainable Energy Technologies. Beirut Energy Forum 9-11 Sep 2015

Workshop on International Good Practices of Sustainable Energy Technologies. Beirut Energy Forum 9-11 Sep 2015 Workshop on International Good Practices of Sustainable Energy Technologies Beirut Energy Forum 9-11 Sep 2015 Eng. Ziad Jebril Sabra Advisor to the Minister Ministry of Energy and Mineral Resources JORDAN

More information

Delivering Power Solutions to our Private & Public Sector Clients INVESTING IN AFRICA

Delivering Power Solutions to our Private & Public Sector Clients INVESTING IN AFRICA Delivering Power Solutions to our Private & Public Sector Clients INVESTING IN AFRICA Executive Summary TransCentury ( TCL ) is pleased to sponsor the 14 th Annual East Africa Power Industry Convention

More information

ABB. Carlos Poñe, ABB South Africa, 14/02/2013 ABB South Africa Media Presentation 2012 Annual Results

ABB. Carlos Poñe, ABB South Africa, 14/02/2013 ABB South Africa Media Presentation 2012 Annual Results ABB Carlos Poñe, ABB South Africa, 14/02/2013 ABB South Africa Media Presentation 2012 Annual Results A global leader in power and automation technologies Formed in 1988 through the merger of Swiss and

More information

EBRD Transport & Energy in Serbia

EBRD Transport & Energy in Serbia EBRD Transport & Energy in Serbia April, 2013 Aleksandar Nikcevic, Principal Banker 1 The European Bank for Reconstruction and Development An international financial institution promoting transition to

More information

Electricity industry structure and capacity growth trends

Electricity industry structure and capacity growth trends Electricity industry structure and capacity growth trends Restructuring since 1997 has resulted in the separation of electricity generation from transmission and distribution. However, the sector continues

More information

EIB -ACP Climate Action

EIB -ACP Climate Action EIB -ACP Climate Action Moses Wekesa Business Development Director Disclaimer: No part of this report may be circulated, quoted, or reproduced for distribution without prior written approval from KenGen.

More information

Priority Transport Projects in Republic of Armenia. 10th Eastern Partnership transport panel Brussels, 11 May 2016

Priority Transport Projects in Republic of Armenia. 10th Eastern Partnership transport panel Brussels, 11 May 2016 Priority Transport Projects in Republic of Armenia 10th Eastern Partnership transport panel Brussels, 11 May 2016 Brief Presentation of North-South Road Corridor Investment Project Estimated length of

More information

Voith Group On a good footing for future growth

Voith Group On a good footing for future growth Voith Group On a good footing for future growth Stuttgart, December 7, 2017 Annual press conference Stuttgart December 7, 2017 Public 1 Contents 1. Where we now stand 1.1 Highlights in the 2016/17 fiscal

More information

Bangladesh s Power Sector : At a Glance

Bangladesh s Power Sector : At a Glance Bangladesh s Power Sector : At a Glance December, 2014 Installed Capacity (MW) : 10,709 De-rated Capacity (MW) : 10,130 Maximum Generation (MW) : 7,418 Total Consumers (in Million) : 15.4 Transmission

More information

AGENDA Introduction: Artumas, Overview

AGENDA Introduction: Artumas, Overview AGENDA Introduction: Artumas, Overview WHERE: Mtwara Concession, SE Tanzania EAPIC Forum Gas Utilization for Power Generation (Mtwara Energy Project) September, 2008 Nairobi, Kenya Mtwara Energy Project:

More information

Government of Sierra Leone. Directions in. Energy. Opportunities for Investment and Partnerships

Government of Sierra Leone. Directions in. Energy. Opportunities for Investment and Partnerships Government of Sierra Leone Directions in Energy Opportunities for Investment and Partnerships Background to Energy Transmission and Distribution In 2011, as part of the reforms in the energy sector the

More information

The SAARC Power Grid Nepal s Perspective

The SAARC Power Grid Nepal s Perspective The SAARC Power Grid Nepal s Perspective Anil Rajbhandary Director, Power Trade Department, NEA Medium Term Vision for Energy Connectivity in the SAARC Region 10 March, 2015; Islamabad Energy Resources

More information

Feasibility Study for Promotion of International Infrastructure Projects in FY2011

Feasibility Study for Promotion of International Infrastructure Projects in FY2011 Feasibility Study for Promotion of International Infrastructure Projects in FY2011 STUDY ON THE EXPANSION OF RAIL TRANSPORT CAPACITY FOR ROCK PHOSPHATE, THE KINGDOM OF MOROCCO FINAL REPORT SUMMARY November

More information

Wessel Bakker Business Line Director ETD BMEA DNV KEMA The Netherlands

Wessel Bakker Business Line Director ETD BMEA DNV KEMA The Netherlands Transmission grid extension for Lake Turkana Wind Farm Wessel Bakker Business Line Director ETD BMEA DNV KEMA The Netherlands wessel.bakker@dnvkema.com Contents Drivers for grid expansion Suswa and Loyangalani

More information

Presented By: Omane Frimpong President: Association of Ghana Solar Industries 10 th December

Presented By: Omane Frimpong President: Association of Ghana Solar Industries 10 th December Presented By: Omane Frimpong President: Association of Ghana Solar Industries 10 th December 2013 www.ghanasolarindustries.com TOPIC: Status and Development of the Local PV Market Structure SCOPE Background

More information

Electricity Infrastructure: The NamPower Perspective

Electricity Infrastructure: The NamPower Perspective Electricity Infrastructure: The NamPower Perspective A PRESENTATION AT THE Infrastructures Partnerships for African Development (ipad) Southern Africa - Power Industry Forum Luanda, Angola by Mr. P.I Shilamba

More information

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden Conference-1 Latest Technologies in T & D, Renewable Energy Integration, Smart Grid, Energy Efficiency, Communication Next Generation of UHVDC System R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC

More information

GLOBAL ENERGY STORAGE MARKET UPDATE: AUSTRALIAN ENERGY STORAGE ASSOCIATION

GLOBAL ENERGY STORAGE MARKET UPDATE: AUSTRALIAN ENERGY STORAGE ASSOCIATION GLOBAL ENERGY STORAGE MARKET UPDATE: AUSTRALIAN ENERGY STORAGE ASSOCIATION JUNE 2, 2016 ANISSA DEHAMNA PRINCIPAL RESEARCH ANALYST NAVIGANT RESEARCH 1 TABLE OF CONTENTS SECTION 1: SECTION 2: SECTION 3:

More information

Global Energy Network for Urban Settlements

Global Energy Network for Urban Settlements Global Energy Network for Urban Settlements Promoting Energy Access for the Urban Poor in Africa Electrification for the Urban poor in Uganda experiences and coverage plans PRESENTATION BY Eng. M.Murengezi

More information

Pilbara Undergrounding Program Smart Grid Opportunities November 2009 DMS#

Pilbara Undergrounding Program Smart Grid Opportunities November 2009 DMS# Pilbara Undergrounding Program Smart Grid Opportunities November 2009 1 Smart Grid? A Smart Grid is an electricity network that can intelligently integrate the actions of all users connected to it generators,

More information

LOGO. August 16,2010

LOGO. August 16,2010 LOGO Opportunity Day TIRATHAI PUBLIC COMPANY LIMITED August 16,2010 Contents Company Profile Business Products Electrical Demand Overview Structure of Income & Q2 Operating Results Business Forecast for

More information

Christine Shearer & Ted Nace, CoalSwarm

Christine Shearer & Ted Nace, CoalSwarm Christine Shearer & Ted Nace, CoalSwarm Global Coal Plant Tracker First public map and database of proposed coal plants: EndCoal.org Wiki pages on CoalSwarm.org for each proposed plant Multi-national effort

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: India Project: Delhi Mass Rapid Transport System Project Phase 2 (V) Loan Agreement: March 31, 2010 Loan Amount:

More information

(1) Current State and Issues of the Electricity Sector in Indonesia

(1) Current State and Issues of the Electricity Sector in Indonesia Japanese ODA Loan Ex-ante Evaluation 1. Name of the Project Country: The Republic of Indonesia Project: Java-Sumatra Interconnection Transmission Line Project (I) Loan Agreement: April 30, 2010 Loan Amount:

More information

MONTHLY REPORT June 2015 Issue No. R06-15

MONTHLY REPORT June 2015 Issue No. R06-15 Southern African Power Pool Energising the region for economic development 1 MONTHLY REPORT June Issue No. R06-15 CONTENTS Meetings, Workshops and Conferences... 1 Quality of Supply Workshop, Lusaka, Zambia...

More information

The Regional Municipality of York. Purchase of Six Battery Electric Buses

The Regional Municipality of York. Purchase of Six Battery Electric Buses 1. Recommendations The Regional Municipality of York Committee of the Whole Transportation Services January 10, 2019 Report of the Commissioner of Transportation Services Purchase of Six Battery Electric

More information

The Study for Development of the Rural Electrification Master Plan in Zambia

The Study for Development of the Rural Electrification Master Plan in Zambia No. The Study for Development of the Rural Electrification Master Plan in Zambia Final Report Summary Report January 2008 Japan International Cooperation Agency (JICA) E D J R 08-004 The Study for Development

More information

Emergency Generation Options

Emergency Generation Options Emergency Generation Options Mark Pickering Empower Regional Director: South Africa African Utility Week Cape Town, 20 May 2009 Overview Why consider emergency power? What type of emergency power plant?

More information

SUCCESSFUL GAS TO POWER PLANT DEVELOPMENT CTRG, MOZAMBIQUE

SUCCESSFUL GAS TO POWER PLANT DEVELOPMENT CTRG, MOZAMBIQUE SUCCESSFUL GAS TO POWER PLANT DEVELOPMENT CTRG, MOZAMBIQUE Africa Utility Week Cape Town Kribs Govender Vice President Business Development Power & Gas 13 May 2015 Forward-looking statements Forward-looking

More information

Madhya Pradesh Road Development Corporation: A Case Study of ADB Assistance for Institutional Development in the Transport Sector in India

Madhya Pradesh Road Development Corporation: A Case Study of ADB Assistance for Institutional Development in the Transport Sector in India Madhya Pradesh Road Development Corporation: A Case Study of ADB Assistance for Institutional Development in the Transport Sector in India South Asia Transport Team Presented by Prodyut Dutt Asian Development

More information

How Micro-grids Can Solve Energy Access in Africa while Building the Energy System of the Future

How Micro-grids Can Solve Energy Access in Africa while Building the Energy System of the Future How Micro-grids Can Solve Energy Access in Africa while Building the Energy System of the Future Excellence in green energy in East Africa for 5+ Years Proven Track Record Country Experience Founded in

More information

CONFERENCE ON TRANSMISSION & DISTRIBUTON MR N C VENUGOPAL TRANSMISSION SECTOR GROWTH & CHALLENGES. DATE 2 ND NOVEMBER 2012

CONFERENCE ON TRANSMISSION & DISTRIBUTON MR N C VENUGOPAL TRANSMISSION SECTOR GROWTH & CHALLENGES. DATE 2 ND NOVEMBER 2012 CONFERENCE ON TRANSMISSION & DISTRIBUTON MR N C VENUGOPAL TRANSMISSION SECTOR GROWTH & CHALLENGES. DATE 2 ND NOVEMBER 2012 TRANSMISSION SECTOR GROWTH HIGHLIGHTS Source - POWERLINE Transmission line length

More information

Modernising the Great Western railway

Modernising the Great Western railway Report by the Comptroller and Auditor General Department for Transport and Network Rail Modernising the Great Western railway HC 781 SESSION 2016-17 9 NOVEMBER 2016 4 Key facts Modernising the Great Western

More information

Planning of the HSR Network

Planning of the HSR Network Engineering Services Department A Global Solution in Public Works Project China s High Speed Rail Network Susan Pan, P.E., Manager of Engineering County of Ventura, Planning of the HSR Network Planning

More information

Alstom in South Africa

Alstom in South Africa Alstom s Presence Medupi Kusile Kriel Johannesburg Transport Gibela Factory Koeberg Key Data: Provided major equipment for 12 out of 13 South Africa s coal-fired power plants and for the only nuclear power

More information

REGIONAL MEETING ON SUSTAINABLE ENERGY

REGIONAL MEETING ON SUSTAINABLE ENERGY REGIONAL MEETING ON SUSTAINABLE ENERGY FOR ASIA-PACIFIC LEAST DEVELOPED COUNTRIES SESSION 2: FINANCING INITIATIVES AND BUSINESS PLANS THAT WORK ELMAR ELBLING Senior Energy Access Specialist Asian Development

More information

Automotive Aftermarket Giorgio Brusco

Automotive Aftermarket Giorgio Brusco Automotive Aftermarket Giorgio Brusco Vice President Automotive Aftermarket Europe Agenda The global business today Recent progress in automotive Future growth drivers Summary 2 Worldwide Automotive Aftermarket:

More information

Mikael Dahlgren, ABB Corporate Research, 02 December 2011 ABB Technology providers perspective Energidagen Chalmers Energyinitiative

Mikael Dahlgren, ABB Corporate Research, 02 December 2011 ABB Technology providers perspective Energidagen Chalmers Energyinitiative Mikael Dahlgren, ABB Corporate Research, 02 December 2011 ABB Technology providers perspective Energidagen Chalmers Energyinitiative ABB HVDC Slide 1 ABB Five global divisions Power Products Power Systems

More information

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT Road Network Upgrading Project (RRP TIM 45094) Sector Road Map SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT 1. Sector Performance, Problems, and Opportunities 1. Timor-Leste comprises the eastern half of

More information

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy ENERGY STRATEGY FOR YUKON Independent Power Production Policy May 20, 2014 Page 2 of 11 BACKGROUND The Government of Yukon released the Energy Strategy for Yukon in January 2009. The strategy sets out

More information

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta

More information

TER WP2 Transport Challenges and Global Crisis. Dr. Klaus Schierhackl, CFO Bad Gastein,

TER WP2 Transport Challenges and Global Crisis. Dr. Klaus Schierhackl, CFO Bad Gastein, TER WP2 Transport Challenges and Global Crisis Dr. Klaus Schierhackl, CFO Bad Gastein, 23.4.2009 1 ASFINAG Group is the 3rd largest concessionaire in Europe responsible for a network of more than 2.100

More information

KCB GROUP PLC INVESTOR PRESENTATION. Q FINANCIAL RESULTS

KCB GROUP PLC INVESTOR PRESENTATION. Q FINANCIAL RESULTS KCB GROUP PLC INVESTOR PRESENTATION. Q3 2018 FINANCIAL RESULTS MACRO-ECONOMIC HIGHLIGHTS Macro-Economic Highlights: Kenya KENYA 4.9% 5.3% GDP Growth Rate (%) 5.6% 5.8% 4.9% 6.3% 6.2% KENYA 2013 2014 2015

More information

Gordon Molefe Director, Customer Services and Supply Botswana Power Corporation Botswana. 80% Electricity Access by 2016

Gordon Molefe Director, Customer Services and Supply Botswana Power Corporation Botswana. 80% Electricity Access by 2016 Gordon Molefe Director, Customer Services and Supply Botswana Power Corporation Botswana 80% Electricity Access by 2016 PRESENTATION GUIDE BOTSWANA HIGHLIGHTS RURAL ELECTRIFICATION TRIGGERS GUIDING PRINCIPLES

More information

Linu Mathew Philip. Centre for Trade and Development (Centad), New Delhi, India

Linu Mathew Philip. Centre for Trade and Development (Centad), New Delhi, India Linu Mathew Philip Centre for Trade and Development (Centad), New Delhi, India Regional Dialogue in Biofuels in Asia 9-10 November 2009 Relevance of Biofuel in the new context Trends Production Consumption

More information

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT. 1. Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT. 1. Sector Performance, Problems, and Opportunities Road Network Upgrading Sector Project (RRP TIM 46260) Sector Road Map SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT 1. Sector Performance, Problems, and Opportunities 1. Timor-Leste comprises the eastern

More information

The Renewable Energy Market Investment Opportunities In Lithium. Prepared by: MAC Energy Research

The Renewable Energy Market Investment Opportunities In Lithium. Prepared by: MAC Energy Research The Renewable Energy Market Investment Opportunities In Lithium Prepared by: MAC Energy Research 2016 Table of Contents: Introduction. Page 2 What is Lithium?... Page 2 Global Lithium Demand Page 3 Energy

More information

Regional Meeting on Sustainable Energy for Asia -Pacific Least Developed Countries Kathmandu, Nepal. Surendra Rajbhandari

Regional Meeting on Sustainable Energy for Asia -Pacific Least Developed Countries Kathmandu, Nepal. Surendra Rajbhandari Regional Meeting on Sustainable Energy for Asia -Pacific Least Developed Countries Kathmandu, Nepal Surendra Rajbhandari 1 Status of Electrification and Access as of July 2016 NEA, state owned electric

More information

Mohammad Alauddin Deputy Secretary Power Division Ministry of Power, Energy & Mineral Resources Govt. of the People s Republic of Bangladesh

Mohammad Alauddin Deputy Secretary Power Division Ministry of Power, Energy & Mineral Resources Govt. of the People s Republic of Bangladesh Mohammad Alauddin Deputy Secretary Power Division Ministry of Power, Energy & Mineral Resources Govt. of the People s Republic of Bangladesh mohammad_alauddin4124@yahoo.com December 19, 2013 Total area

More information

Our mission is to be the best public service transporter for passengers in the city of Kigali using modern, clean and safe urban city buses.

Our mission is to be the best public service transporter for passengers in the city of Kigali using modern, clean and safe urban city buses. Kigali Bus Services Ltd. was incorporated in January 2006 in Kigali Rwanda. The Company started operations in March 2007 with just a few buses! We now operate a fleet of 50 Buses throughout Kigali City

More information

EUCL AMI Project Experience Share

EUCL AMI Project Experience Share EUCL AMI Project Experience Share James Musoni--Project Manager of Revenue Protection Program(RPP) EUCL COMPANY S STRUCTURE 2 General power system planning Energy infrastructure projects development Electricity

More information

Overview of Electricity Trade Agreement between Québec and Ontario. May 10, 2017 For Information Purposes Only

Overview of Electricity Trade Agreement between Québec and Ontario. May 10, 2017 For Information Purposes Only Overview of Electricity Trade Agreement between Québec and Ontario May 10, 2017 For Information Purposes Only Purpose To provide an overview of the electricity trade agreement between the Independent Electricity

More information

ONGOING PROJECTS. Project Name Client Contract Value. Construction of Solar Powered Mini Piped Water Schemes in Rural Areas in Uganda

ONGOING PROJECTS. Project Name Client Contract Value. Construction of Solar Powered Mini Piped Water Schemes in Rural Areas in Uganda ONGOING PROJECTS Project Name Client Contract Value Construction of Solar Powered Mini Piped Water Schemes in Rural Areas in UGX 5,183,724,104.32 Construct Solar Powered Micro Irrigation Systems in Lot

More information

An Overwhelmingly Solid and Advantageo

An Overwhelmingly Solid and Advantageo JR East s Strengths 1 AN OVERWHELMINGLY SOLID AND ADVANTAGEOUS RAILWAY NETWORK JR EAST S SERVICE AREA TOKYO The railway business of the JR East Group covers the eastern half of Honshu island, which includes

More information

AFRICA CLEAN MOBILITY WEEK March 2018, Conference Room 3 UN Environment Headquarters- Nairobi Kenya

AFRICA CLEAN MOBILITY WEEK March 2018, Conference Room 3 UN Environment Headquarters- Nairobi Kenya AFRICA CLEAN MOBILITY WEEK 2018 12-16 March 2018, Conference Room 3 Headquarters- Nairobi Kenya Monday, 12 March 2018 The GLOBAL FUEL ECONOMY INITIATIVE (GFEI) 08:30-09:00 Registration 09:00-09:15 Welcome

More information

Vattenfall Capital Markets Day 2009

Vattenfall Capital Markets Day 2009 Vattenfall Capital Markets Day 2009 Presentation by: Helene Biström Senior Executive Vice President Head of Business Group Pan Europe Amsterdam, 23 September 2009 Contents Overview Business Group Pan Europe

More information

Metal Bulletin Conference

Metal Bulletin Conference Sakura Ferroalloys Project Metal Bulletin Conference Singapore, 01 st April 2015 P R E S E N T E D BY: T I A A N VA N A S W EG E N D I R E C TO R A S S M A N G C H A I R M A N S A KU R A F E R R OALLOY

More information

Myanmar: Towards Universal Access to Electricity by Yangon, January 30, 2015

Myanmar: Towards Universal Access to Electricity by Yangon, January 30, 2015 Myanmar: Towards Universal Access to Electricity by 2030 Yangon, January 30, 2015 Towards universal access to electricity in Myanmar - What has been done? 2 Development of Myanmar National Electrification

More information

MALDIVES ENERGY SECTOR & SREP IP 4 TH DECEMBER 2017, ABUJA, NIGERIA. Ministry of Environment and Energy Republic of Maldives

MALDIVES ENERGY SECTOR & SREP IP 4 TH DECEMBER 2017, ABUJA, NIGERIA. Ministry of Environment and Energy Republic of Maldives MALDIVES ENERGY SECTOR & SREP IP 4 TH DECEMBER 2017, ABUJA, NIGERIA Ministry of Environment and Energy Republic of Maldives Maldives Overview 26 atolls with 1192 islands land area of about 300 km 2 Population

More information

Corporate Overview. Business Model. Track Record. Target Markets. Contact

Corporate Overview. Business Model. Track Record. Target Markets. Contact MINING 1. 2. 3. 4. 5. Corporate Overview Business Model Track Record Target Markets Contact 12.11.2013 2 Corporate Overview CRONIMET Mining AG CRONIMET Mining AG CRONIMET Holding was established in 1980

More information

UPM THE BIOFORE COMPANY

UPM THE BIOFORE COMPANY UPM THE BIOFORE COMPANY Nordea Forest Products & Paper Seminar 2013 President and CEO Jussi Pesonen Strategic direction of UPM s businesses Advancing in growth markets Label Paper in China, label papers

More information

Report, construction machinery can be produced, and some of these products are exported.

Report, construction machinery can be produced, and some of these products are exported. China Railway a Equipment Industry Report, 2009 Railway transport is the main artery of China's economic development. Over a century of development, China railway equipment industry is self-sufficient

More information

Institutional Approaches to Electrification in Kenya

Institutional Approaches to Electrification in Kenya The World Bank Energy Week on Africa Washington DC, 14 th -16 th March 2011 Institutional Approaches to Electrification in Kenya Presented by Eng. Joseph K. Njoroge, MBS Managing Director & CEO The Kenya

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

The Grid Link Project. Summary of the Report for the Independent Expert Panel

The Grid Link Project. Summary of the Report for the Independent Expert Panel The Grid Link Project Summary of the Report for the Independent Expert Panel Who are EirGrid - and what do we do? EirGrid is responsible for a safe, secure and reliable supply of electricity: now and in

More information

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test: Salisbury Substation 11kV Feeders DISCLAIMER The purpose of this document is to inform customers, Interested Parties,

More information

Building Collaboration Between East African Nations via Transmission Interconnectors

Building Collaboration Between East African Nations via Transmission Interconnectors Building Collaboration Between East African Nations via Transmission Interconnectors Eng. Christian M.A. Msyani Ag. DEPUTY MANAGING DIRECTOR TRANSMISSION - TANESCO CONTENTS 1. TANESCO - Existing Power

More information

Proposed acquisition of Areva Distribution. December 2, 2009

Proposed acquisition of Areva Distribution. December 2, 2009 Proposed acquisition of Areva Distribution December 2, 2009 Disclaimer All forward-looking statements are Schneider Electric management s present expectations of future events and are subject to a number

More information

Country Scenario - Pakistan

Country Scenario - Pakistan NATIONAL TRANSMISSION & DESPATCH COMPANY LIMITED (NTDCL), PAKISTAN Country Scenario - Pakistan SAARC Perspective Workshop on the Past, Present and Future of High Voltage DC (HVDC) Power Transmission 30

More information

Yukon Resource Gateway Project

Yukon Resource Gateway Project Yukon Resource Gateway Project Summary Application for National Infrastructure Component Funding January 2016 Introduction The Government of Yukon is seeking endorsement of the Yukon Resource Gateway

More information

Rural Energy Access: Promoting Solar Home Systems In Rural Areas In Zambia A Case Study. O.S. Kalumiana

Rural Energy Access: Promoting Solar Home Systems In Rural Areas In Zambia A Case Study. O.S. Kalumiana Rural Energy Access: Promoting Solar Home Systems In Rural Areas In Zambia A Case Study O.S. Kalumiana Department of Energy, Ministry of Energy & Water Development, P.O. Box 51254, Lusaka ZAMBIA; Tel:

More information

Money and banking. Flow of funds for the third quarter

Money and banking. Flow of funds for the third quarter Statistical tables Money and banking Page S South African Reserve Bank: Liabilities... 2 South African Reserve Bank: Assets... 3 Corporation for Public Deposits: Liabilities... 4 Corporation for Public

More information

Maritime Link. MITC Canada Day March 2015

Maritime Link. MITC Canada Day March 2015 Maritime Link MITC Canada Day March 2015 About Emera $9.85 billion of assets in Canada, United States and Caribbean Algonquin (21.0%) 2 Emera Maine 154,000 customers in Northern, Central and Downeast Maine

More information

Deepening Green Partnership Agenda among Korea, Japan and China (at the CJK Dialogue 2016) :From the Fine Dusts to the Asia Super Grid

Deepening Green Partnership Agenda among Korea, Japan and China (at the CJK Dialogue 2016) :From the Fine Dusts to the Asia Super Grid 3 rd China-Japan-Korea Cooperation Dialogue Deepening Green Partnership Agenda among Korea, Japan and China (at the CJK Dialogue 2016) :From the Fine Dusts to the Asia Super Grid Sang-Hyup Kim Professor,

More information

Renewable Power for Mines

Renewable Power for Mines Renewable Power for Mines Adding Value. Delivering Results. By Greg Smyth November 2015 Outline Understanding Miners Mines Power Needs Case Studies BC s Mines Knight Piésold KP has a long history developing

More information