EXHIBIT D.2.5: Site Technical Overview Documents Bid Alternate Bundle: CDG Sites

Size: px
Start display at page:

Download "EXHIBIT D.2.5: Site Technical Overview Documents Bid Alternate Bundle: CDG Sites"

Transcription

1 EXHIBIT D.2.5: Site Technical Overview Documents Bid Alternate Bundle: CDG Sites Contents Auburn Landfill Auburn Dunning Ave... 7 Cayuga County County House Road Complex Cortland County Chase Field DeWitt Landfill Elbridge Landfill Moravia Wastewater Treatment Plant Oswego Superfund Site Richland Well Fields Salina Landfill Skaneateles Transfer Station Cicero Landfill Union Springs Water Works Page 1 of 67

2 Auburn Landfill 1 Site Overview Address: 311 North Division Street, Auburn NY Utility Provider and Tariff: NYSEG, SC7-1 Electricity Supplier: Energy Cooperative of America Annual Energy Usage: 238,700 kwh Monthly Demand Peak: max 50 kw, average 43 kw over the last 12 months PV System Overview System Size: Expected Output in Year 1: Electricity Offset: 947 kw recommended for RNM. Space for >2,000 kw if CDG pursued. 1,202,238 kwh/yr see chart below PV System Summary This site is landfill #1 which was capped in the 1980 s. The target system size of 947 kw is designed to offset 100% of Auburn municipal electric consumption not including street lighting, and not including usage already offset by other DG. The City electric usage and production summary is as follows: City Electric Consumption and Production Summary Total City electric usage (current) New usage at WWTP (projected) Total City electric usage (projected) Street lighting ineligible for RNM Total usage eligible for RNM North Division Street hydro generation Mill Street hydro generation Total electric usage to be offset by solar City Hall PV array production Remaining usage eligible for RNM 6,096,000 kwh/yr + 4,200,000 kwh/yr = 10,296,000 kwh/yr - 2,363,000 kwh/yr = 7,933,000 kwh/yr - 4,200,000 kwh/yr - 2,451,000 kwh/yr =1,282,000 kwh/yr - 80,000 kwh/yr = 1,202,000 kwh/yr The PV array will connect to an electric meter serving a gas collection and compression skid adjacent to the landfill. The skid takes the methane gas from the landfill and sends it to a 2 MW cogeneration plant (this energy is subsequently sold into a wholesale market, which is why it is not included in the chart above). The primary considerations for this site will be environmental approval and interconnection approval. Environmental approval should not be difficult to obtain; other similar landfills have received approval to install PV arrays in New York. Interconnection approval is less certain, as NYSEG will need to determine whether the distribution line that supplies the skid can handle potential backfeed from an 947 kw PV system. An interconnection application will need to be submitted to receive this determination. Silicon Valley Washington DC Chicago Beijing Page 2 of 67

3 Energy Use and Solar Generation Profile 160, , , ,000 80,000 60,000 Energy Use (kwh) Solar Output (kwh) 40,000 20,000 - JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC This energy profile shows the PV output by month as compared to the electric consumption at the methane compressor. Silicon Valley Washington DC Chicago Beijing Page 3 of 67

4 Proposed Solar PV Design Layout Electric Meter The layout above shows the footprint required for an 947 kw ground mount PV array. The energy yield for the proposed array is 1,270 kwh/kw per year. There is space for >2,000 kw if a community solar installation is pursued. This site is a closed landfill. The interconnection point is at the methane gas collection and compression skid just north of the landfill as labeled above. Site plans are available showing the location of underground methane collection lines, site topography, and an electrical single line diagram for the skid. The grass is mowed once per year currently. Vegetation growth is mostly in control, though some mowing and clearing will be required prior to installation. There are also wellheads throughout that will have to be avoided when installing the solar panels. The wellheads are about 3 ft tall and spaced >100 ft apart, so should not present a major obstacle. Silicon Valley Washington DC Chicago Beijing Page 4 of 67

5 Solar Array Technical Specifications Sub-array Location Description Azimuth Tilt System Size (kw-dc) Landfill 1 Ballasted ground mount system Solar Array Utility Considerations The electrical service to the skid is 400A, 480Y/277V 3-phase 4-wire. The utility drop is from a dedicated NYSEG pole service to the gas skid with (4) 500 MCM conductors. There is room for the solar inverter and equipment either adjacent to the array or within the fenced enclosed at the gas skid. This site will be heavily dependent on net metering as the solar capacity will be upwards of 947 kw and the peak demand on site is only around 50 kw. This site is designed to serve as a host site for remote net metering. This means the array will produce more energy than is consumed on site. Under remote net metering, all solar output each month will first be used to offset the usage charges on the host electric bill. Any excess credits are then converted to a dollar value and used to offset demand and billing charges on the host bill. Finally, the excess credits still remaining are directed to other accounts owned by the City. Due to being oversized, this array will be subject to interconnection approval from the utility and may not be approved at the full size proposed herein. An interconnection application has not been filed for this site, though it should be before this project goes to contract. In either case, a service upgrade will be required as the existing utility drop is not sized to handle the PV system capacity. Technical Assessment Summary Shading Electrical Structural Geotech. Enviro. Comments None Med None Med High The ground condition seems suitable for solar, though the array will have to be ballasted to avoid penetrating the cap. There are no shading concerns. Mowing will be required prior to installation. Environmental approval will be required prior to installation. Interconnection approval of the recommended size is not guaranteed. In either case, the main service will have to be upgraded to accommodate this new PV system. Silicon Valley Washington DC Chicago Beijing Page 5 of 67

6 Site Photos Silicon Valley Washington DC Chicago Beijing Page 6 of 67

7 Auburn Dunning Ave Site Overview Address: Utility Provider and Tariff: PV System Overview System Size: Expected Output in Year 1: Electricity Offset: 213 Dunning Ave, Auburn NY No service to this site currently (NYSEG territory) 2,300 kw possible if used as a community DG host site 947 kw recommended if used as an RNM host site for City meters 1,202,238 kwh/yr see chart below PV System Summary This site is a 36 acre parcel owned by the City. This site could be used as either a host site for remote net metering or as a host site for a community solar array. Scenario 1 Remote Net Metering Host If used as a remote net metering host, the target system size of 947 kw is designed to offset 100% of Auburn municipal electric consumption not including street lighting, and not including usage already offset by other DG. The City electric usage and production summary is as follows: City Electric Consumption and Production Summary Total City electric usage (current) New usage at WWTP (projected) Total City electric usage (projected) Street lighting ineligible for RNM Total usage eligible for RNM North Division Street hydro generation Mill Street hydro generation Total electric usage to be offset by solar City Hall PV array production Remaining usage eligible for RNM 6,096,000 kwh/yr + 4,200,000 kwh/yr = 10,296,000 kwh/yr - 2,363,000 kwh/yr = 7,933,000 kwh/yr - 4,200,000 kwh/yr - 2,451,000 kwh/yr =1,282,000 kwh/yr - 80,000 kwh/yr = 1,202,000 kwh/yr Scenario 2 Community DG Host This site could also serve as a host for a Community DG aka Shared Solar array. In this scenario, a system of up to 2,000 kw AC could be installed. This is the maximize size allowed to net meter. Note: the system size of 2,300 kw indicated above is the total DC rating of the solar panels; this is reduced to 2,000 kw AC during the power conversion process before connection to the grid. Silicon Valley Washington DC Chicago Beijing Page 7 of 67

8 Any electric consumers in Auburn would be able to subscribe to a portion of output from the array and receive credits on their electric bill. The City itself would be eligible to subscribe to up to 40% of the total array output, which would be around 920 kw DC. Conveniently, this is also close to the amount of solar needed to offset 100% of the City s eligible electric consumption. It is outside the scope of this report to cover the Community DG program in detail, though more information could be found here: General Considerations for Either Scenario Technical The PV array will most likely connect to the three phase power line running along Dunning Ave to the east of the parcel. The distance to the street is approximately 800 ft from the NE corner of the array footprint. There is a creek along the road which would have to be crossed. The primary considerations for this site will be environmental approval and interconnection approval. Environmental approval should not be difficult to obtain since this does not seem to be an ecologically sensitive parcel. Interconnection approval is less certain, as NYSEG will need to determine whether the distribution line along Dunning Ave can handle potential backfeed from an 947 kw or 2,300 kw PV system. An interconnection application will need to be submitted to receive this determination. It is possible that only a smaller system size would be approved and that grid upgrades would be required. The costs for grid upgrades would be the responsibility of the City (typically included in the project development costs). Silicon Valley Washington DC Chicago Beijing Page 8 of 67

9 Proposed Solar PV Design Layout Dunning Ave 800 from NE corner of array The layout above shows the footprint required for an 2,300 kw ground mount PV array. The energy yield for this array is 1,270 kwh/kw per year. Silicon Valley Washington DC Chicago Beijing Page 9 of 67

10 The image above shows the property line (light blue) along with topographic lines (red). Each topo line represents an elevation gain of 2 ft. The property line extends to Dunning Ave at the top right corner of the property. The image above is the google street view looking north along Dunning Ave near at the point where the City property meets the road. There is a 3 phase distribution line along the west side of the road. Silicon Valley Washington DC Chicago Beijing Page 10 of 67

11 Solar Array Technical Specifications Sub-array Location Description Azimuth Tilt System Size (kw-dc) Dunning Ave pacel Standard ground mount system or 2,300 Technical Assessment Summary Shading Electrical Structural Geotech. Enviro. Comments None Med None Unknown Low The ground condition has not been assessed, though is presumed to be suitable for solar. There are no shading concerns. Interconnection approval of the recommended size is not guaranteed. In either case, a new service will need to be installed. There could be some challenge with the electrical run as it will have to cross a creek. Silicon Valley Washington DC Chicago Beijing Page 11 of 67

12 Cayuga County County House Road Complex Site Overview Address: Utility Provider and Tariff: Electricity Supplier: Annual Energy Usage: Monthly Demand Peak: 7445 County House Rd, Auburn, NY NYSEG Empire Natural Gas Corporation tbd tbd PV System Overview System Size: 2,300 kw possible Expected Output in Year 1: 2,908,000 kwh/yr at this size Electricity Offset: >100% PV System Summary This site is a complex of county buildings including a nursing home along the road, a jail behind, the County Soil and Water Conservation District, and a digester. There is space to install a ground mount array of the max permissible size under standard interconnection rules. Note: 2,000 kw AC is the maximum permissible size. The system size of 2,300 kw indicated above is the total DC rating of the solar panels; this is reduced to 2,000 kw AC during the power conversion process before connection to the grid. There is an open lot near the several facilities that looks to be a good site for a large ground mounted solar array. This site could be used as a host for either remote net metering or community solar. Scenario 1 Remote Net Metering Host If used as a remote net metering host, the system could interconnect to the jail, nursing home, or digester. Solar output would first offset the host meter with excess energy production directed to other County electric accounts. Electric billing data for all County accounts would need to be reviewed to determine the target system size, though it is presumed the County has enough usage to absorb the output from a 2,300 kw array. If this option is pursued, it is possible that remote net metering arrays won t be needed at the Highway Barn in Venice or the Highway Garage in Auburn as described earlier in this report, though we anticipate the County has enough cumulative usage to absorb the outputs from those systems as well as this one. Scenario 2 Community DG Host This site could also serve as a host for a Community DG aka Shared Solar array. As above, an array of up to 2,300 kw could be installed. Any electric consumers in the County (whom are served by NYSEG) would be able to subscribe to a portion of output from the array and receive credits on their electric bill. The County itself would be eligible to subscribe to up to 40% of the total array output which would be around 920 kw DC. It is outside the scope of this report to cover the Community DG program in detail, though more information could be found here: Silicon Valley Washington DC Chicago Beijing Page 12 of 67

13 General Considerations for Either Scenario Technical The primary considerations for this site will be environmental approval and interconnection approval. Environmental approval should not be difficult to obtain since this does not seem to be an ecologically sensitive parcel. Interconnection approval is less certain, as NYSEG will need to determine whether the distribution line along County House Rd can handle potential backfeed from a 2,300 kw PV system. An interconnection application will need to be submitted to receive this determination. It is possible that only a smaller system size would be approved and that grid upgrades would be required. The costs for grid upgrades would be the responsibility of the County (typically included in the project development costs). Solar Array Technical Specifications Sub-array Location Description Azimuth Tilt System Size (kw-dc) North of digester Standard ground mount racking ,300 Technical Assessment Summary Shading Electrical Structural Geotech. Enviro. Comments Low Med None Low Low The ground condition seems suitable for solar. Standard soil makeup for this area. This field is not flood prone. There are no shading concerns. Interconnection approval of the recommended size is not guaranteed. Approval may be received for a smaller system size only, and grid upgrades may be required. In either case, the chosen main service will have to be upgraded to accommodate a PV system of this size. Silicon Valley Washington DC Chicago Beijing Page 13 of 67

14 Proposed Solar PV Design Layout Community Digester 250ft Nursing Home 900ft Jail 400ft The layout above shows viable areas for solar PV project development highlighted in blue with individual modules in dark blue. The layout above can accommodate 2,300 kw. The energy yield for the proposed array is 1,266 kwh/kw per year. The area chosen is relatively level; a topography available for the site shows a total elevation gain of less than 10ft across the field. There are no major shading impacts. The soil condition is good for hosting a ground mounted solar array. Utility data for adjacent County properties has not been evaluated, nor have the electric services been evaluated. As such the target interconnection location is unknown. Presumably either the jail or nursing home (both County-owned) will have a large 3 phase service suitable for interconnection, though a service upgrade would likely be required if this large solar array size is pursued. Silicon Valley Washington DC Chicago Beijing Page 14 of 67

15 Site Photos Proposed Array Location Jail Digester Nursing Home The image above shows the property lines (blue) and topography (red). Topo lines are 2ft contours. Silicon Valley Washington DC Chicago Beijing Page 15 of 67

16 Looking west at array location Looking northwest at array location Silicon Valley Washington DC Chicago Beijing Page 16 of 67

17 Cortland County Chase Field Site Overview Address: Utility Provider and Tariff: Electricity Supplier: Annual Energy Usage: Monthly Demand Peak: PV System Overview System Size: Expected Output in Year 1: Electricity Offset: 922 NY Route 222,Cortland, NY No service to this parcel currently (National Grid territory) n/a 476,337 kwh total consumption on all County meters n/a Up to 2,100 kw is possible. 375 kw needed for 100% offset. 2,664,000 kwh/yr (at 2,100 kw-dc) or 475,500 kwh/yr (at 375 kw) TBD PV System Summary The County recently bought and cleared a parcel across Route 222 off the north-east corner of the airport. The County is updating the Airport Master Plan and is interested in installing solar on the property. A solar array at this parcel could be used as either a host site for remote net metering or as a host site for a community solar array. Scenario 1 Remote Net Metering Host If used as a remote net metering host, a new electric service in the County s name would be set up on the parcel to serve a small load. The PV array would be connected to this meter and National Grid would virtually credit excess generation to other County electric accounts of the County s choosing. The target system size would be 375 kw which is sufficient to offset usage on all eligible County-owned meters. Scenario 2 Community DG Host This site could also serve as a host for a Community DG aka Shared Solar array. In this scenario, any electric consumers in the County and surrounding areas would be able to subscribe to a portion of output from the array and receive credits on their electric bill. The County itself would be eligible to subscribe to up to 40% of the total array output, though a subscription to 375 kw would be sufficient to offset County usage as described above. It is outside the scope of this report to cover the Community DG program in detail, though more information could be found here: If the County chooses to host community solar, systems could be installed at both the landfill and Chase Field, and the County could subscribe to output from one or both arrays as desired. General Considerations for Either Scenario Technical The primary considerations for this site will be environmental approval and interconnection approval. Environmental approval should not be difficult to obtain since this does not seem to be an ecologically sensitive parcel. Silicon Valley Washington DC Chicago Beijing Page 17 of 67

18 Interconnection approval is less certain, as National Grid will need to determine whether the local feeder can handle backfeed from a large solar array. An interconnection application will need to be submitted to receive this determination. It is possible that only a smaller system size would be approved and that grid upgrades would be required. The costs for grid upgrades would be the responsibility of the County (typically included in the project development costs). There is no electric service to the parcel currently. The nearest 3 phase feeder is a 13.2 kv line that runs along West Rd and terminates about 500 ft east of the parcel. To the west, the nearest 3 phase line is a 13.2 kv line along Highland Rd, about a half mile from the parcel. State Route 222 itself between Highland and West is served by a 2-phase 4.8 kv line. The most viable interconnection will likely be extending a dedicated line from the 13.2 kv feeder on West Rd to the parcel (see drawing on the next page for the current termination point of this feeder). Silicon Valley Washington DC Chicago Beijing Page 18 of 67

19 Proposed Solar PV Design Layout Termination of Natl Grid 13.2kV 3-phase feeder The layout above shows viable areas for solar PV project development highlighted in blue. The layout above can accommodate 2,100 kw-dc assuming ground mount arrays with a 20 degree tilt. The energy yield for this configuration is 1,268 kwh/kw per year. As noted previously, a smaller 375 kw system would be sufficient under remote net metering. There are 15 medium sized trees on the parcel which will have to be removed to maximize the available space. The tree line along the west edge of the property is ft tall and poses a shading concern; an appropriate setback will need to be maintained. The topography is level and the ground is of good condition to host a solar array. Vegetation growth is minimal; this property is regularly mowed. Environmental approval via the SEQR process will be necessary for this array though major impacts are not expected. Interconnection could be a challenge for this array. There is a 13.2 kv 3-phase service along West Road which terminates 500 ft east of the parcel (labeled above). At the very least, this line will need to be extended to the property, though connection of a large array may require additional protections. An interconnection application will need to be filed with National Grid to determine whether interconnection of the proposed array size is feasible and the corresponding cost of grid upgrades to accommodate. Silicon Valley Washington DC Chicago Beijing Page 19 of 67

20 Solar Array Technical Specifications Sub-array Location Description Azimuth Tilt System Size (kw-dc) Vacant parcel NE of airport Standard ground mount array up to 2,100 Solar Array Utility Considerations There is no electric service to the parcel currently; a new meter and service will need to be requested. See discussion of the local distribution system in the previous section. This site will be heavily dependent on net metering as the solar capacity will be significantly in excess of any demand for power on site. This site is designed to serve as either a host for remote net metering or for a community solar array. Under remote net metering, all solar output each month will first be used to offset the usage charges on the host electric bill. Any excess credits are then converted to a dollar value and used to offset demand and billing charges on the host bill. Finally, if excess credits are still remaining, they are directed to other accounts owned by the County. Under community solar, individual subscribers will be credited for excess energy produced by the array. Due to being oversized, this array will be subject to interconnection approval from the utility and may not be approved at the full size proposed herein. It is likely that grid upgrades will be required to accommodate a large solar array at this location, and it is possible that only a smaller array will be approved. An interconnection application has not been filed for this site. In either case, a new utility service and meter will need to be installed by National Grid. Technical Assessment Summary Shading Electrical Structural Geotech. Enviro. Comments Low High None Low Low Ground condition is good for solar. Topography is level. The site is mowed regularly. The tree line along with west edge of the property (50-75 ft tall) is a shading concern. Removal or appropriate setback required. Interconnection approval of the recommended size is not guaranteed. In either case, a new service will have to be ordered. Silicon Valley Washington DC Chicago Beijing Page 20 of 67

21 Site Photos View from street looking north at parcel Center of parcel looking west Center of parcel looking south Looking east along street (termination of 3-phase line in distance) Silicon Valley Washington DC Chicago Beijing Page 21 of 67

22 DeWitt Landfill Site Overview Address: Fisher Rd, East Syracuse NY Utility Provider and Tariff: No service to this site (National Grid provides service in this area) Electricity Supplier: n/a (Town has accounts supplied by National Grid Supply Service and Integrys) Annual Energy Usage: 0 kwh at landfill, total usage on Town meters is 2,472,293 kwh/yr Monthly Demand Peak: n/a PV System Overview System Size: Expected Output in Year 1: Electricity Offset: 1,880 kw recommended for RNM. Space for >2,000 kw if CDG pursued. 2,404,230 kwh/yr 97% of total municipal usage including outdoor lighting PV System Summary This site is a closed landfill (closed in the 1980 s) with space to install enough solar to offset all of the Town s municipal electric consumption. The landfill is designed to be a remote net metering host site, which means energy produced here will be virtually distributed to other Town accounts. The recommended size of 1,880 kw is enough to offset 100% of eligible DeWitt municipal electric consumption. Town Electric Consumption Summary Total Town usage (facilities, water, pumps) Total Town usage (street lighting) Total Town usage Unmetered lighting (ineligible) Total usage eligible for solar offset 991,776 kwh/yr + 1,480,517 kwh/yr = 2,472,293 kwh/yr - 62,644 kwh/yr = 2,409,649 kwh/yr Note: This report has been updated to reflect Town Hall as an eligible recipient of remote net metering credits. The Town Hall was ineligible under old rules which prevented a site that hosts a net metered system from also being a satellite account. This restriction was removed by a PSC ruling in October The Town Hall s net usage (345,920 kwh/yr) is now included in the eligible amount above. There are some street lighting accounts that are unmetered and thus are also ineligible to be recipient accounts. The primary hurdles for this site will be environmental approval and interconnection approval. A 2MW interconnection application has been filed. The National Grid response indicated a CESIR study would be required at a $25,000 cost. Some grid upgrades will be necessary though a new feeder is not likely to be required. Environmental approval should not be difficult to obtain; other similar landfills have received approval to install PV arrays in New York. Silicon Valley Washington DC Chicago Beijing Page 22 of 67

23 Proposed Solar PV Design Layout Substation 500 ft Landfill entrance 400 ft Canal Museum The layout above shows the footprint required for an 1,880 kw ground mount PV array. The energy yield for the proposed array is 1,279 kwh/kw per year. There is space for >2,000 kw if CDG is pursued. This site is a closed landfill (closed in the 1980 s). The grass is mowed by the Highway Department a few times per year. Vegetation growth is relatively in control, though some mowing and minor clearing will be required prior to installation. The vents are very sparsely located and will not present an obstacle to the array. The topography is relatively flat in the southeast corner of the property where the array is shown. Otherwise, there are large mounds in the northeast and southwest corners of the property, and the topography generally slopes away from those two mounds. There are a couple key issues to consider for this installation: 1) New York s State Environmental Quality Review Act (SEQR) requires the analysis and disclosure of environmental impacts of proposed projects. The array will need to use ballasted racking to avoid penetrating the landfill cap. Silicon Valley Washington DC Chicago Beijing Page 23 of 67

24 2) Interconnection cost is a question mark. There was an interconnection application filed and accepted for a 1,995 kw-ac system connecting to feeder on Fisher Rd. The response from National Grid indicated a final CESIR at a cost of $25,000 would be required. The preliminary findings indicated the interconnection was feasible though some upgrades would be necessary, including additional 3V0 protection at the substation and a new EMS RTU. Feeder upgrades were not anticipated to be necessary. Solar Array Technical Specifications Sub-array Location Description Azimuth Tilt System Size (kw-dc) Southeast corner of landfill property Ballasted ground mount ,880 Solar Array Utility Considerations There is no electric service on site currently. This site will be heavily dependent on net metering as the solar capacity will be upwards of 1,880 kw and the peak demand on site is minimal. This site is designed to serve as a host site for remote net metering. This means the array will produce more energy than is consumed on site. Under remote net metering, all solar output each month will first be used to offset the usage charges on the host electric bill. Any excess credits are then converted to a dollar value and used to offset demand and billing charges on the host bill. Finally, the excess credits still remaining are directed to other accounts owned by the Town. Due to being oversized, this array will be subject to interconnection approval from the utility. An interconnection application was filed for this site at a 2MW size. The National Grid response indicated a CESIR study would be required at a $25,000 cost. Preliminary analysis showed a feeder upgrade was not likely to be necessary, but some upgrades would be necessary including a new EMS RTU, expanded capacitor banks, and anti-islanding protection. Technical Assessment Summary Shading Electrical Structural Geotech. Enviro. Comments None Med None Med Med The ground condition seems suitable for solar. The array will have to be ballasted to avoid penetrating the cap. There are no shading concerns. Environmental approval will be required prior to installation. A new electric service will have to be established. A CESIR study with National Grid will also be necessary. Silicon Valley Washington DC Chicago Beijing Page 24 of 67

25 Site Photos Looking southeast toward array location Looking south toward array location Looking southwest across landfill property Looking west across landfill property Old canal museum Silicon Valley Washington DC Chicago Beijing Page 25 of 67

26 Elbridge Landfill Site Overview Address: Utility Provider and Tariff: Electricity Supplier: Annual Energy Usage: Monthly Demand Peak: PV System Overview System Size: Expected Output in Year 1: Electricity Offset: 801 Peru Road, Jordan, NY no service to this site currently (NYSEG service territory) n/a (Town receives supply through an ESCO for other accounts) n/a n/a 2,300 kw possible (only 80 kw needed to offset usage on all Town accounts) 2,954,000 kwh/yr n/a PV System Summary This site is a closed and capped landfill owned by the Town. The Town s electric consumption is summarized below: Location Annual Usage (kwh/yr) Rate Tariff Town Hall (2 meters) 66,515 SC2 Community Center 22,870 SC6 Water District Wheeler Rd 9,501 SC2 Water District Crossett Rd 3,300 SC6 Unmetered Street Lighting (5 meters) (ineligible) 56,958 varies TOTAL ELIGIBLE LOAD 102,186 There is 102,186 kwh/yr of consumption on Town electric accounts (not including the unmetered street lighting, which is not eligible for offset). It would require a solar array of around 80 kw to offset this usage. The landfill could be used as either a host site for remote net metering or as a host site for a community solar array. However, due to the small system size associated with RNM, only community solar is being considered for this RFP. In the Community DG aka Shared Solar array scenario, a system of up to 2,000 kw AC could be installed. This is the maximize size allowed to net meter. Note: the system size of 2,300 kw indicated above is the total DC rating of the solar panels; this is reduced to 2,000 kw AC during the power conversion process before connection to the grid. Any electric consumers in Elbridge and surrounding areas would be able to subscribe to a portion of the output from the array and receive credits on their electric bill. The Town itself would be eligible to subscribe to the 80 kw required to offset Town usage. Silicon Valley Washington DC Chicago Beijing Page 26 of 67

27 It is outside the scope of this report to cover the Community DG program in detail, though more information could be found here: General Considerations Technical The PV array will most likely connect to the three phase power line running along Peru Road to the south of the parcel. The distance to the street is approximately 800 ft from the SE corner of the array footprint. There is a creek along the road which would have to be crossed. The primary challenges for this site will be environmental approval and interconnection approval. Environmental approval should not be difficult to obtain; other similar landfills have received approval to install PV arrays in New York. However a SEQR review will be required. Interconnection approval is less certain, as NYSEG will need to determine whether the distribution line along Peru Road can handle potential backfeed from a large solar installation. An interconnection application will need to be submitted to receive this determination. It is possible that only a smaller system size would be approved and that grid upgrades would be required. The costs for grid upgrades would be the responsibility of the Town (typically included in the project development costs). The topography may also present a challenge. The landfill is heavily rounded and the slope around the edges is likely too steep for a ballasted racking system. The middle portions of the landfill are flat enough to host an array, though the terrain still undulates in this area. The layout on the next page attempts to keep the boundaries of the array within these upper portions of the landfill where the topography is flatter. Silicon Valley Washington DC Chicago Beijing Page 27 of 67

28 Proposed Solar PV Design Layout Peru Road 800ft The layout above shows viable areas for solar PV project development. The layout above can accommodate 2,300 kw. The energy yield for the proposed array is 1,285 kwh/kw per year. The layout above attempts to maximize use of the flatter topography in the center portions of the landfill. Site conditions may dictate an alternate section of the parcel is best. The Town will need to conduct a SEQR review to determine any impacts of the array and to determine mitigation measures, if required. At a minimum the array will need to use a non-penetrating ballasted racking system to avoid disturbing the cap. Interconnection will be a challenge for this array. There is 3 phase service along Peru Road about 600 ft south of the creek which runs adjacent to the landfill. The AC wiring run will need to cover this distance and also cross over the creek, most likely running along the access road. The capacity of the feeder along Peru Road is unknown; an interconnection application will need to be filed with NYSEG to determine whether interconnection of the proposed array size is feasible and the corresponding cost of grid upgrades to accommodate. Silicon Valley Washington DC Chicago Beijing Page 28 of 67

29 Solar Array Technical Specifications Sub-array Location Description Azimuth Tilt System Size (kw-dc) Southwest portion of landfill Ballasted ground mount ,300 Solar Array Utility Considerations This site has not been visited so the electric service details are unknown. There is a 3 phase distribution line along Peru Road, about 1000 ft south of the array. There is a single phase feeder which serves an antenna at the landfill. If there is no Town utility account at this property, a new meter and service will need to be requested. This site will be heavily dependent on net metering as the solar capacity will be significantly in excess of any demand for power on site. This site is designed to serve as either a host for remote net metering or for a community solar array. Under remote net metering, all solar output each month will first be used to offset the usage charges on the host electric bill. Any excess credits are then converted to a dollar value and used to offset demand and billing charges on the host bill. Finally, if excess credits are still remaining, they are directed to other accounts owned by the Town. Under community solar, individual subscribers will be credited for excess energy produce by the array Due to being oversized, this array will be subject to interconnection approval from the utility and may not be approved at the full size proposed herein. It is likely that grid upgrades will be required to accommodate a large solar array at this location, and it is possible that only a smaller array will be approved. An interconnection application has not been filed for this site. In either case, a new utility service and meter will need to be installed by NYSEG. Technical Assessment Summary Shading Electrical Structural Geotech. Enviro. Comments None High None Med Med Ground condition is suitable for solar, though cap penetration will most likely need to be avoided. Topography is also sloped, particularly around the edges of the landfill. Environmental approval will be required prior to installation. Interconnection approval of the recommended size is not guaranteed and may be expensive. In either case, a new service will be required. Silicon Valley Washington DC Chicago Beijing Page 29 of 67

30 Site Photos Bing maps aerial looking south Looking north at the landfill from the access road Silicon Valley Washington DC Chicago Beijing Page 30 of 67

31 Looking north along the access road at the creek Looking north Looking northeast toward antenna tower Silicon Valley Washington DC Chicago Beijing Page 31 of 67

32 Moravia Wastewater Treatment Plant Site Overview Address: Utility Provider and Tariff: Electricity Supplier: Annual Energy Usage: Monthly Demand Peak: PV System Overview System Size: Expected Output in Year 1: Electricity Offset: 83 Aurora St, Moravia, NY NYSEG, SC7-1 NYSEG Supply Service 585,400 kwh 116 kw max, 94 kw average over the last 12 months at least 2,300 kw possible, 843 kw needed for offset of all Village accounts 1,070,000 kwh/yr (for 843 kw) (scales linearly with system size) 183% this site, 100% community-wide PV System Summary The Water Plant has a large area of open land which is suitable for a ground mounted solar array. This site could be used as either a host site for remote net metering or as a host site for a community solar array. Scenario 1 Remote Net Metering Host If used as a remote net metering host, the target system size would be 843 kw in order to offset 100% of eligible Village electric consumption (including street lighting). The solar array would be connected behind the existing WTP meter and all output from the array would first be used to offset usage on this meter. Excess credits would be distributed to other Village electric accounts using NYSEG s remote net metering policy. Scenario 2 Community DG Host This site could also serve as a host for a Community DG aka Shared Solar array. In this scenario, a system of up to 2,000 kw AC could be installed. This is the maximize size allowed to net meter. Note: the system size of 2,300 kw indicated above is the total DC rating of the solar panels; this is reduced during the power conversion process before connection to the grid. Any electric consumers in Moravia and surrounding areas would be able to subscribe to a portion of the output from the array and receive credits on their electric bill. The Village itself would be eligible to subscribe to up to 40% of the total array output. As above, it would make sense for the Village to subscribe to 843 kw in order to offset 100% of Village usage. Note: if the community DG array is connected to the existing WTP meter, then all output would first be used to offset usage of the WTP meter, with excess then going to subscribers. The Village could still be one of these subscribers in order to offset their other non-wtp electric accounts. It is outside the scope of this report to cover the Community DG program in detail, though more information could be found here: Silicon Valley Washington DC Chicago Beijing Page 32 of 67

33 General Considerations for Either Scenario Technical The primary challenges for this site will be environmental approval and interconnection approval. Environmental approval should not be difficult to obtain. A Village-led SEQR review may be required but this does not seem to be an ecologically sensitive parcel and major impacts are unlikely. Interconnection approval is less certain as NYSEG will need to determine whether the local distribution line can handle potential backfeed from a large solar installation. An interconnection application will need to be submitted to receive this determination. It is possible that only a smaller system size would be approved and that grid upgrades would be required. The costs for grid upgrades would be the responsibility of the Village (typically included in the project development costs). Energy Use and Solar Generation Profile 140, , ,000 80,000 60,000 Energy Use (kwh) Solar Output (kwh) 40,000 20,000 - JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC Silicon Valley Washington DC Chicago Beijing Page 33 of 67

34 Proposed Solar PV Design Layout Main Service The layout above shows viable areas for solar PV project development highlighted in blue. The layout above can accommodate approximately 2,300 kw with an energy yield of 1,271 kwh/kw per year. Note: if the Village decides to pursue an 843 kw array for remote net metering only the four sub-arrays adjacent to the plant are sufficient to provide this capacity. The larger sub-array on the old ball field is needed to expand the system size to 2,300 kw. There are some trees around the perimeter, though there is space for sufficient setback to avoid shading. A minimum 100 ft setback from the ball fields is also maintained to avoid damage. The largest subarray is overlaid on an old little league field. Per the Village, this field is seldom used and can go (light demo required). The ground is very flat and in good condition for solar. This area was historically prone to flooding at certain times of year, though the DEC made drainage improvements a few years ago and flooding has not been an issue since. Silicon Valley Washington DC Chicago Beijing Page 34 of 67

35 Solar Array Technical Specifications Sub-array Location Description Azimuth Tilt System Size (kw-dc) West Standard ground mount array East upper Standard ground mount array East middle Standard ground mount array East lower Standard ground mount array Solar Array Utility Considerations The electrical service is 800A, 480V 3-phase with an 800A main breaker. The main service is located in an enclosure just outside the office building near the service drop (as labeled on the previous page). There is room for the solar equipment outside adjacent to the service. This site will be heavily dependent on net metering as the solar capacity will be much higher than the peak demand on site (peak demand is 116 kw). This site is also designed to serve as a host site for remote net metering. This means the array will produce more energy than is consumed on site. Under remote net metering, all solar output each month will first be used to offset the usage charges on the host electric bill. Any excess credits are then converted to a dollar value and used to offset demand and billing charges on the host bill. Finally, if excess credits are still remaining, they are directed to other accounts owned by the Village. Due to being oversized, this array will be subject to interconnection approval from the utility and may not be approved at the full size proposed herein. An interconnection application has not been filed for this site. In either case, a service upgrade will be required as the existing utility drop is not sized to handle the PV system capacity. Technical Assessment Summary ID Shading Electrical Structural Geotech. Enviro. Comments MV1 Low Med None High Low Ground is flat and good condition for solar. Flooding a historical problem but not since DEC drainage improvements 4 years ago. Minimal shading concerns. Some trees around perimeter but there is space for a sufficient setback. Interconnection approval of the recommended size is not guaranteed. In either case, the main service will have to be upgraded to accommodate this new PV system. Silicon Valley Washington DC Chicago Beijing Page 35 of 67

36 Site Photos Satellite Image Looking east Looking south near east edge of plant Silicon Valley Washington DC Chicago Beijing Page 36 of 67

37 Service drop from street NEMA-3R cabinet with main service panel NYSEG meter # Two dugouts and fencing will have to be removed Silicon Valley Washington DC Chicago Beijing Page 37 of 67

38 Oswego Superfund Site Site Overview Address: 703 E Seneca St, Oswego NY Utility Provider and Tariff: no service at this site currently (this area served by National Grid) Electricity Supplier: n/a Annual Energy Usage: n/a Monthly Demand Peak: n/a PV System Overview System Size: Expected Output in Year 1: Electricity Offset: 1,182 kw (constrained by available space) 1,425,638 kwh/yr about 68% of total municipal street lighting usage PV System Summary This is a Superfund Pollution Abatement Site. There were oil drums buried at the site formerly which were leaking into the creek; this is the reason for the Superfund tag. This site is designed to be a remote net metering host site, which means energy produced here will be virtually distributed to other City accounts. There is no electric service on site currently. The recommended size of 1,182 kw is enough to offset about 68% of City municipal street lighting consumption which is around 2,082,259 kwh/yr. Street lighting accounts have higher usage charges and will provide a better return on investment if they are determined to be eligible recipient accounts for remote net metering credits. For the analysis of this site, street lighting accounts are assumed to be the recipient accounts. If they are later determined to be ineligible, this project is less likely to pencil out economically. The primary hurdles for this site will be environmental approval, interconnection approval, and the AC wiring run. The uncertainty around these issues is the reason this site is given only a B rating. Environmental approval should not be difficult to obtain; other similar landfills have received approval to install PV arrays in New York. A ballasted array will be required to avoid penetrating the cap. Interconnection approval is less certain, as National Grid will need to determine whether the distribution line that supplies this area can handle potential backfeed from an 1,182 kw PV system. An interconnection application will need to be submitted to receive this determination. The best interconnection location is to be determined. There is no electric service at the Superfund site currently, though a new connection could be established. This is most likely the best approach. The closest existing meters owned by the City are at the Animal Shelter or the pump station at the corner of St Paul St and Mitchell St, though both of these sites have small electric services currently which would need to be upgraded. Both of these sites are also a long way from the Superfund site, and there is a creek running in between. Silicon Valley Washington DC Chicago Beijing Page 38 of 67

39 Proposed Solar PV Design Layout Pump station 200ft Animal Shelter 100ft The layout above shows viable areas for solar PV project development highlighted in blue with individual modules in dark blue. The layout above can accommodate approximately 1,182 kw as a ground-mount array on open land. The energy yield for the proposed array is 1,206 kwh/kw per year. The field is relatively flat and vegetation growth is under control. There will be some mowing required prior to installation, but no major vegetation clearing should be necessary. Sufficient setback must be maintained from the trees around the perimeter to avoid shading. The two nearest City meters are labeled above. The electric service at the Shelter is 150A, 208V 3-phase and the service at the pump station is 225A, 480V 3-phase. A new electric service could be applied for at the Superfund site along with roadway; this is probably the best option. Silicon Valley Washington DC Chicago Beijing Page 39 of 67

40 Solar Array Technical Specifications Sub-array Location Description Azimuth Tilt System Size (kw-dc) Superfund site Ballasted ground mount array ,182 Solar Array Utility Considerations Utility considerations have been described previously. Technical Assessment Summary Shading Electrical Structural Geotech. Enviro. Comments Low High None Med High Ground condition seems suitable for solar, though a ballasted racking system will be necessary to avoid penetration the surface. Shading from perimeter trees can be avoided with a sufficient setback. Mowing will be required prior to install, though no significant vegetation clearing is anticipated. Interconnection approval of the recommended size is not guaranteed. The best interconnection method will need to be determined at a later date. Silicon Valley Washington DC Chicago Beijing Page 40 of 67

41 Site Photos Looking at field from street Looking at field from street Looking at field from street Utility distribution line along roadway Silicon Valley Washington DC Chicago Beijing Page 41 of 67

42 Richland Well Fields Site Overview Address: Stowell Drive, Richland, NY Utility Provider and Tariff: no service to this property currently (National Grid territory) Electricity Supplier: n/a Annual Energy Usage: None at this site. 429,428 kwh/yr on all Town meters. Monthly Demand Peak: n/a PV System Overview System Size: Expected Output in Year 1: Electricity Offset: over 2,300 kw possible, 337 kw required to offset usage on all Town accounts 429,000 kwh/yr at 337 kw (scales linearly) 100% of usage on all Town accounts PV System Summary This site is open land owned by the Town. It is currently vacant and the Town is interested in hosting solar. A solar array at this parcel could be used as either a host site for remote net metering or as a host site for a community solar array. The Town s electricity consumption is below: Location Annual Usage (kwh/yr) Hockey Rink 162,240 Water Delivery 145,541 Other Buildings and Facilities 87,911 Street Lighting 33,736 TOTAL 429,428 Scenario 1 Remote Net Metering Host If used as a remote net metering host, a new electric service in the Town s name would be set up on the parcel to serve a small load. The PV array would be connected to this meter and National Grid would virtually credit excess generation to other Town electric accounts of the Town s choosing. The target system size would be 337 kw which is sufficient to offset usage on all eligible Town-owned meters. Scenario 2 Community DG Host This site could also serve as a host for a Community DG aka Shared Solar array. In this scenario, a system of up to 2,000 kw AC could be installed. This is the maximize size allowed to net meter. Note: the system size of 2,300 kw indicated above is the total DC rating of the solar panels; this is reduced to 2,000 kw AC during the power conversion process before connection to the grid. Any electric consumers in the surrounding area would be able to subscribe to a portion of output from the array and receive credits on their electric bill. The Town itself would be eligible to subscribe to up to 40% of the total array output, though a subscription to 337 kw would be sufficient to offset Town usage as described above. Silicon Valley Washington DC Chicago Beijing Page 42 of 67

43 It is outside the scope of this report to cover the Community DG program in detail, though more information could be found here: General Considerations for Either Scenario Technical The primary considerations for this site will be environmental approval and interconnection approval. Environmental approval should not be difficult to obtain since this does not seem to be an ecologically sensitive parcel. Interconnection approval is less certain, as National Grid will need to determine whether the local feeder can handle potential backfeed from a large solar array. An interconnection application will need to be submitted to receive this determination. It is possible that only a smaller system size would be approved and that grid upgrades would be required. The costs for grid upgrades would be the responsibility of the Town (typically included in the project development costs). There is a 12.47kV 3-phase distribution line along Richland-Orwell Rd to the north of our project site, and a 3- phase feeder off this line that serves the site. There is already a 100 kw wind turbine connected to this feeder. According to National Grid s DG Interconnection Siting Map, the distribution line has possible higher costs to interconnect DG greater than 1,000 kw (circuit ID 36_16_6144 with color code purple, indicating possible higher cost). Silicon Valley Washington DC Chicago Beijing Page 43 of 67

44 Proposed Solar PV Design Layout Service point National Grid Feeder 100kW wind turbine 1,000 ft. Richland-Orwell Rd 0.5 miles. National Grid Feeder Pictures on p.19 taken from this point Service point The layout above shows viable areas for solar PV project development highlighted in blue. The layout above can accommodate 2,300 kw as a ground-mount array on open land. The energy yield for the proposed array is 1,273 kwh/kw per year. Note the footprint required for a 337 kw remote net metered array would be much smaller. The actual location of the array within the parcel could be adjusted as needed to accommodate the Town or the developer. The ground condition is good for solar and the topography of this parcel is flat. No tree removal or other site demo is required. The field would need to be cleared; it is currently covered in low growth grasses and weeds which a standard commercial mower should be able to clear. Three phase 12.47kV power is routed throughout the property, serving several well pumps and control panels at distinct locations. The power is stepped down to 480/277V at each of these individual service points. Two such points near the proposed array are shown in the image above. The capacity of these feeder lines is unknown, but it seems likely that a new dedicated line for the array would have to be run from the distribution line along Richland-Orwell Rd (a half mile from the array). An interconnection application will need to be filed to receive this determination. Silicon Valley Washington DC Chicago Beijing Page 44 of 67

45 Solar Array Technical Specifications Sub-array Location Description Azimuth Tilt System Size (kw-dc) Well Fields Standard ground mount up to 2,300 Solar Array Utility Considerations There is no electric service to this site currently. A new meter serving a nominal load will need to be requested for the site. There is a 12.47kV 3-phase distribution line along Richland-Orwell Rd a half mile north of the array, and a 3-phase feeder off this line that serves several locations on the property. There is already a 100 kw wind turbine connected to this feeder. This site will be heavily dependent on net metering as the solar capacity will be upwards of 337 kw and the peak demand on site is minimal. This site is also designed to serve as a host for remote net metering. This means the array will produce more energy than is consumed on site. Under remote net metering, all solar output each month will first be used to offset the usage charges on the host electric bill. Any excess credits are then converted to a dollar value and used to offset demand and billing charges on the host bill. Finally, excess credits still remaining are directed to other accounts owned by the Town. Under community solar, these excess credits are allocated to subscribers. Due to being oversized, this array will be subject to interconnection approval from the utility and may not be approved at the full size proposed herein. According to National Grid s Distributed Interconnection Siting Map, there are possible higher interconnection costs on this feeder. An interconnection application has not been filed for this site. In either case, a new service will be required. Technical Assessment Summary Shading Electrical Structural Geotech. Enviro. Comments None High None Low Low Ground condition is suitable for solar. SEQR review may be required depending on system size, though this is not an ecologically sensitive parcel and approval should not be problematic. No tree removal is necessary. There is plenty of space on site to avoid shading from perimeter trees. Interconnection approval of the recommended size is not guaranteed. In either case, a new service will be required. Silicon Valley Washington DC Chicago Beijing Page 45 of 67

46 Site Photos Bing Maps aerial image of site and surrounding area Distribution line along Richland-Orwell Rd (picture taken looking east) Silicon Valley Washington DC Chicago Beijing Page 46 of 67

47 Looking northwest Looking north Looking west See p.13 for an indication of where these pictures were taken in relation to the proposed array Silicon Valley Washington DC Chicago Beijing Page 47 of 67

48 Salina Landfill Site Overview Address: Near Brewerton Rd & Interstate 90, Syracuse NY Utility Provider and Tariff: no service (National Grid supplies this area) Electricity Supplier: n/a Annual Energy Usage: 0 kwh at landfill, total usage on Town meters is 2,260,551 kwh/yr Monthly Demand Peak: n/a PV System Overview System Size: Expected Output in Year 1: Electricity Offset: 1,800 kw recommended for RNM. Space for >2,000 kw if CDG pursued. 2,270,127 kwh/yr 100% of total municipal usage not including load at new pretreatment plant PV System Summary This site is a closed landfill with plenty of space to install enough solar to offset all of the Town s municipal electric consumption. The landfill looks like a good install site for solar; it is flatter than most landfill sites and well maintained. The interconnection location is at a groundwater pretreatment facility adjacent to the landfill. This is a new facility and projected electric usage here is not known. The landfill is designed to be a remote net metering host site, which means energy produced here will be virtually distributed to other Town accounts. The recommended size of 1,800 kw is enough to offset 100% of Salina municipal electric consumption including outdoor lighting, but not including the usage at the new pretreatment facility. Town Electric Consumption and Production Summary Total Town usage (facilities) Total Town usage (outdoor lighting) New usage at pretreatment Total Town usage 538,615 kwh/yr 1,721,936 kwh/yr TBD kwh/yr = 2,260,551 kwh/yr The primary hurdles for this site will be environmental approval and interconnection approval. Environmental approval should not be difficult to obtain; other similar landfills have received approval to install PV arrays in New York. Interconnection approval is less certain, as National Grid will need to determine whether the distribution line that supplies the skid can handle potential backfeed from an 1,800 kw PV system. An interconnection application will need to be submitted to receive this determination. The Town is also considering a community solar installation for this property. There is space to expand to over 2,000 kw if this option is pursued. Silicon Valley Washington DC Chicago Beijing Page 48 of 67

49 Energy Use and Solar Generation Profile 300, , , , ,000 Energy Use (kwh) Solar Output (kwh) 50,000 - JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC This energy profile shows the PV output by month as compared to the electric consumption across all Town electric accounts. The Town usage is higher in winter months, as about 75% of Town usage is for outdoor lighting which runs longer in the winter. Silicon Valley Washington DC Chicago Beijing Page 49 of 67

50 Proposed Solar PV Design Layout National Grid high voltage lines Electric Meter at pretreatment plant Ley Creek The layout above shows the footprint required for an 1,800 kw ground mount PV array. The energy yield for the proposed array is 1,261 kwh/kw per year. There is space for >2,000 kw if CDG is pursued. This site is a closed landfill. The interconnection point is at the groundwater pretreatment plant across the creek from the landfill, as labeled above. The landfill is well maintained; the grass is mowed four times per year and there is minimal vegetation growth. There are vents throughout that will have to be avoided when installing the solar panels, however these vents are sparsely located and will not present a major obstacle. The topography is flatter than most landfills; there is some downward slope around the edges, though the array locations shown above are on relatively flat ground. There are a couple key issues to consider for this installation: 1) New York s State Environmental Quality Review Act (SEQR) requires the analysis and disclosure of environmental impacts of proposed projects. The array will need to use ballasted racking to avoid Silicon Valley Washington DC Chicago Beijing Page 50 of 67

51 penetrating the landfill cap. Ley Creek, which can be seen in the image above running south of the landfill, has had some contamination issues in the past. 2) The wiring run will have to cross a creek to reach the interconnection point at the pretreatment plant. This will require either boring under the creek, or installing aerial lines over the creek. It will also have to cross under National Grid high voltage lines both between the sub-arrays and between the landfill and the interconnection point. The right-of-way situation is unknown. Solar Array Technical Specifications Sub-array Location Description Azimuth Tilt System Size (kw-dc) East sub-array Ballasted ground mount system West sub-array Ballasted ground mount system ,100 Solar Array Utility Considerations The electrical service at the pretreatment plant is 480Y277V 3-phase with a 200A main disconnect switch. There is a pad-mounted step-down transformer on site (13.2/7.6 kv to 480Y/277 V) adjacent to the meter. There is room for the solar inverter outside adjacent to the meter, or adjacent to the array on the landfill. This site will be heavily dependent on net metering as the solar capacity will be upwards of 1,800 kw and the peak demand on site is much lower. This site is also designed to serve as a host site for remote net metering. This means the array will produce more energy than is consumed on site. Under remote net metering, all solar output each month will first be used to offset the usage charges on the host electric bill. Any excess credits are then converted to a dollar value and used to offset demand and billing charges on the host bill. Finally, if excess credits are still remaining, they are directed to other accounts owned by the Town. Due to being oversized, this array will be subject to interconnection approval from the utility and may not be approved at the full size proposed herein. An interconnection application has not been filed for this site. In either case, a service upgrade will be required as the existing utility drop is not sized to handle the PV system capacity. Technical Assessment Summary Shading Electrical Structural Geotech. Enviro. Comments None High None Med High The ground condition seems suitable for solar. The array will have to be ballasted to avoid penetrating the cap. There are no shading concerns. Environmental approval will be required prior to installation. Interconnection approval of the recommended size is not guaranteed. In either case, the main service will have to be upgraded to accommodate this new PV system. Silicon Valley Washington DC Chicago Beijing Page 51 of 67

52 Site Photos National Grid meter # Transformer, meter, possible inverter location Transformer East sub-array, looking toward treatment plant East sub-array, looking northwest East sub-array, looking west Silicon Valley Washington DC Chicago Beijing Page 52 of 67

53 East sub-array, looking southwest East sub-array, looking southwest East sub-array, looking south East sub-array, looking southeast Looking toward east sub-array from the east Looking toward east sub-array from treatment plant Silicon Valley Washington DC Chicago Beijing Page 53 of 67

54 Skaneateles Transfer Station Site Overview Address: 1676 Old Seneca Turnpike, Skaneateles NY Utility Provider and Tariff: National Grid, SC-2 D Electricity Supplier: Constellation Annual Energy Usage: 43,973 kwh Monthly Demand Peak: 22 kw max, 8 kw min, 15 kw average PV System Overview System Size: 190 kw recommended for RNM. Space for >2,000 kw if CDG pursued. Expected Output in Year 1: 232,651 kwh/yr Electricity Offset: >100% PV System Summary This site has a large open field which is available for solar. Up to 2MW could be installed in this area, though significantly less is needed to offset the Town s usage under a remote net metering scenario. Community solar could take advantage of the larger system size. Some of the Town s facilities are served by Village Electric, a local utility with very low power rates. This includes the Town s biggest energy users Austin Park Arena and the Town Hall. Solar is not competitive on these meters and thus offset is only considered for meters served by National Grid. The Transfer Station and two street lighting accounts are the only major accounts on National Grid. In this report, the PV system is designed to offset all usage at the Transfer Station (43,973 kwh/yr) with excess credits being used to offset usage of the street lighting accounts (193,000 kwh/yr) via remote net metering. Energy Use and Solar Generation Profile 30,000 25,000 20,000 15,000 10,000 Energy Use (kwh) Solar Output (kwh) 5,000 - JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC Silicon Valley Washington DC Chicago Beijing Page 54 of 67

55 Proposed Solar PV Design Layout Electric Meter The layout above shows viable areas for solar PV project development highlighted in blue with individual modules in dark blue. The layout above is a 190 kw ground-mount array on open land. This area is mowed regularly and well maintained and no significant site prep will be required. The energy yield for the proposed solar array is 1,224 kwh/kw per year. If a community solar array is installed, there is a significant amount of available space south of the array location shown above. Silicon Valley Washington DC Chicago Beijing Page 55 of 67

56 Solar Array Technical Specifications Sub-array Location Description Azimuth Tilt System Size (kw-dc) Just east of main building Standard ground mount Solar Array Utility Considerations The electrical service is 200A, 208V 3-phase. The drop from National Grid is on site, there is a pole mounted transformer (the shadow of the pole is visible in the layout on the previous page). The meter is located on the north wall of the main building as labeled. The main service is located just inside the building. There is room for the solar inverter and other equipment outside near the meter. This site will be heavily dependent on net metering as the solar capacity will be upwards of 190 kw and the peak demand on site is only around 15 kw. This site is also designed to serve as a host site for remote net metering. This means the array will produce more energy than is consumed on site. Under remote net metering, all solar output each month will first be used to offset the usage charges on the host electric bill. Any excess credits are then converted to a dollar value and used to offset demand and billing charges on the host bill. Finally, if excess credits are still remaining, they are directed to other accounts owned by the Town. For community solar, these excess credits are allocated to subscribers. Due to being oversized, this array will be subject to interconnection approval from the utility and may not be approved at the full size proposed herein. An interconnection application has not been filed for this site. In either case, a service upgrade will be required as the existing utility drop is not sized to handle the PV system capacity. Technical Assessment Summary Shading Electrical Structural Geotech. Enviro. Comments None Med None Low Low The ground seems suitable for solar, no issues are anticipated. The field is regularly mowed and well maintained so there will not be significant site prep required. The terrain does slope slightly to the south-southeast, though the slope is minimal in the area shown. There are no shading concerns. Interconnection approval of the recommended size is not guaranteed and may be problematic. Silicon Valley Washington DC Chicago Beijing Page 56 of 67

57 Site Photos Array area looking south. Main building just visible at right. Utility drop and meter # Utility drop from 3 phase distribution line with pole mounted transformer. There is space for the inverter outside near the meter in this area. Main electrical service Silicon Valley Washington DC Chicago Beijing Page 57 of 67

58 Cicero Landfill Site Overview Address: 6540 State Rt. 31, Cicero, NY Utility Provider and Tariff: no service to this site (National Grid provides service in this area) Electricity Supplier: n/a (Town s accounts are supplied by National Grid Supply Service) Annual Energy Usage: 0 kwh at landfill, total usage on Town meters is 1,321,281 kwh/yr Monthly Demand Peak: n/a PV System Overview System Size: Expected Output in Year 1: Electricity Offset: 1,065 kw recommended for RNM. Space for >2,000 kw if CDG pursued. 1,321,880 kwh/yr 100% of total municipal usage including outdoor lighting accounts PV System Summary This site is a closed landfill (closed in the 1980 s) with space to install enough solar to offset all of the Town s municipal electric consumption. The landfill is designed to be a remote net metering host site, which means energy produced here will be virtually distributed to other Town accounts. The recommended size of 1,065 kw is enough to offset 100% of Cicero municipal electric consumption including street lighting. Total Town usage (facilities) Town Electric Consumption Summary Total Town usage (street lighting) Total Town usage 359,138 kwh/yr 962,143 kwh/yr = 1,321,281 kwh/yr The primary hurdles for this site will be environmental approval, interconnection approval, and AC wiring. Environmental approval should not be difficult to obtain; other similar landfills have received approval to install PV arrays in New York. Interconnection approval is less certain, as National Grid will need to determine whether the distribution line that supplies this area can handle potential backfeed from an 1,065 kw PV system. An interconnection application will need to be submitted to receive this determination. The best interconnection location is to be determined. There is no electric service at the landfill currently, and Fergerson Road, which runs along the west side of the landfill and is the access point, has only a single phase distribution line. There is a Town facility, Central Park, about 1,500 ft north of the landfill. There are four electric meters at the Park served by the 3 phase distribution line that runs along State Route 31, and any of these could be the target meter or a new connection could be established at this location. The AC wiring run back up to State Route 31, however, would be a challenge due to its length and the waterlogged areas in between. Silicon Valley Washington DC Chicago Beijing Page 58 of 67

59 The Town is also interested in hosting community solar at this location, in which case the array could be expanded in size to over 2,000 kw, though steeper topography would have to be utilized to reach this size. Proposed Solar PV Design Layout To Central Park (900 ft) and State Route 31 (1,900 ft) Access from Fergerson Road The layout above shows the footprint required for an 1,065 kw ground mount PV array. The energy yield for the proposed array is 1,241 kwh/kw per year. If CDG is pursued there is room to expand the array going south, though this will encroach on the steeper portions of the landfill cap. This site is a closed landfill (closed in the 1980 s). The grass is mowed by the Highway Department a couple times per year. Vegetation growth is relatively in control, though some mowing and minor clearing will be required prior to installation. The vents are very sparsely located and will not present an obstacle to the array. The topography slopes downhill from the center of the landfill, though the slope has mostly leveled out in the array area shown above. The ground does slope north near the southern portion of the array area. There are a couple key issues to consider for this installation: Silicon Valley Washington DC Chicago Beijing Page 59 of 67

60 1) New York s State Environmental Quality Review Act (SEQR) requires the analysis and disclosure of environmental impacts of proposed projects. The array will need to use ballasted racking to avoid penetrating the landfill cap. 2) The best interconnection point has not yet been determined. There is no electric service to the site currently. The closest distribution line is a single phase line along Fergerson Road. The nearest three phase line is along State Route 31, about 1,900 ft north of the array. The Town does own all the land between the landfill and the Park so right-of-way should not be an obstacle, however there is a pond between the landfill and Park. There is standing water there year-round, which is fed by a creek that runs along the east side of the landfill. If interconnection must be made at State Route 31, the AC wiring run will be a challenge. Solar Array Technical Specifications Sub-array Location Description Azimuth Tilt System Size (kw-dc) Landfill Ballasted ground mount ,065 Solar Array Utility Considerations There are four electric accounts at Central Park, one of which could serve as a potential interconnection point, or a new connection point could be established at the Park. The existing meters are smaller services, 200A or less, and so would need to be upgraded regardless. This site will be heavily dependent on net metering as the solar capacity will be upwards of 1,065 kw and the peak demand on site is very low kw. This site is designed to serve as a host site for remote net metering. This means the array will produce more energy than is consumed on site. Under remote net metering, all solar output each month will first be used to offset the usage charges on the host electric bill. Any excess credits are then converted to a dollar value and used to offset demand and billing charges on the host bill. Finally, if excess credits are still remaining, they are directed to other accounts owned by the Town. Due to being oversized, this array will be subject to interconnection approval from the utility and may not be approved at the full size proposed herein. An interconnection application has not been filed for this site. Technical Assessment Summary Shading Electrical Structural Geotech. Enviro. Comments Low High None Med Med The ground condition seems suitable for solar. The array will have to be ballasted to avoid penetrating the cap. There are no major shading concerns, a sufficient setback can be maintained from the perimeter trees. Environmental approval will be required. Interconnection approval of the recommended size is not guaranteed. A new utility drop will have to be provided at whatever interconnection point is deemed best. Silicon Valley Washington DC Chicago Beijing Page 60 of 67

61 Site Photos Looking north at array location Looking northeast at array location Looking east at array location Looking west toward Fergerson Rd access point Landfill access point Looking north along Fergerson Rd Silicon Valley Washington DC Chicago Beijing Page 61 of 67

62 Single phase distribution line along Fergerson Road Three phase line along State Route 31, with Fergerson Road branch shown. Silicon Valley Washington DC Chicago Beijing Page 62 of 67

63 Union Springs Water Works Site Overview Address: Utility Provider and Tariff: Electricity Supplier: Annual Energy Usage: Monthly Demand Peak: PV System Overview System Size: Expected Output in Year 1: Electricity Offset: 230 Cayuga St, Union Springs, NY NYSEG, SC2 Unknown 335,360 kwh at this site. 667,557 kwh on all Village accounts. Unknown 528 kw is the recommended size to offset all Village usage. Up to 1,600 kw possible if pursuing CDG 658,789 kwh/yr 196% this site, 99% community-wide PV System Summary This site is open land hosting 2 pumps and well heads along with a stripper for the Village water system. This site could be used as either a host site for remote net metering or as a host site for a community solar array. Scenario 1 Remote Net Metering Host Under remote net metering, all output from the PV array is first used to offset usage on the host meter. NYSEG will then distribute excess credits to other Village electric accounts. If used as a remote net metering host, the target system size would be 528 kw which is sufficient to offset 100% of eligible Village electric consumption. Village consumption is summarized below: Account Tariff Type Annual Usage (kwy/yr) Water Works Facility demand 335,360 Water Treatment Plant demand 236,250 Other Facilities non-demand 25,561 Street lighting lighting 70,386 TOTAL 667,557 Scenario 2 Community DG Host This site could also serve as a host for a Community DG aka Shared Solar array. In this scenario, a system of up to 1,600 kw DC could be installed. This is an estimate of the usable space available on this site, though a more detailed system design may arrive at a smaller or larger number. Any electric consumers in the Village and surrounding areas would be able to subscribe to a portion of output from the array and receive credits on their electric bill. The Village itself would be eligible to subscribe to up to 40% of the total array output, though only 528 kw would be needed as described above. Silicon Valley Washington DC Chicago Beijing Page 63 of 67

64 It is outside the scope of this report to cover the Community DG program in detail, though more information could be found here: General Considerations for Either Scenario Technical The PV array will most likely connect to the three phase power line running along Dunning Ave to the east of the parcel. The distance to the street is approximately 800 ft from the NE corner of the array footprint. There is a creek along the road which would have to be crossed. The primary considerations for this site will be environmental approval and interconnection approval. Environmental approval should not be difficult to obtain since this does not seem to be an ecologically sensitive parcel. Interconnection approval is less certain, as NYSEG will need to determine whether the distribution line along Caygua St can handle potential backfeed from a large PV system. An interconnection application will need to be submitted to receive this determination. It is possible that only a smaller system size would be approved and that grid upgrades would be required. The costs for grid upgrades would be the responsibility of the Village (typically included in the project development costs). Energy Use and Solar Generation Profile 90,000 80,000 70,000 60,000 50,000 40,000 30,000 Energy Use (kwh) Solar Output (kwh) 20,000 10,000 - JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC Silicon Valley Washington DC Chicago Beijing Page 64 of 67

65 Proposed Solar PV Design Layout Pump house, electric meter, main service Last NYSEG pole and transformers The layout above shows viable areas for solar PV project development highlighted in blue. The first shows the footprint required for 528 kw under a remote net metering scenario, while the second shows a 1,600 kw array which is close to a maximum fill and could be used for community solar. The energy yield for the proposed configuration is 1,246 kwh/kw per year. The land is relatively free of trees and little to no tree removal should be required. The terrain does slope east to west at around 3 degrees, and also rolls in the north-south direction at a pitch of up to 5 degrees. The ground condition is suitable for solar. Silicon Valley Washington DC Chicago Beijing Page 65 of 67

66 Solar Array Technical Specifications Sub-array Location Description Azimuth Tilt System Size (kw-dc) Water works site Standard ground mount Solar Array Utility Considerations The main electric service is 200A, 480/277V 3-phase. The NYSEG distribution line terminates adjacent to the pump house (as labeled on the previous page), and three pole mounted transformers serve the facility. There is plenty of room for the solar inverter and other equipment outside adjacent to the pump house. This site will be heavily dependent on net metering as the solar capacity will be upwards of 528 kw and the average demand on site is significantly lower. This site is also designed to serve as a host site for remote net metering. This means the array will produce more energy than is consumed on site. Under remote net metering, all solar output each month will first be used to offset the usage charges on the host electric bill. Any excess credits are then converted to a dollar value and used to offset demand and billing charges on the host bill. Finally, if excess credits are still remaining, they are directed to other accounts owned by the Village. Due to being oversized, this array will be subject to interconnection approval from the utility and may not be approved at the full size proposed herein. An interconnection application has not been filed for this site. In either case, a service upgrade will be required as the existing utility drop is not sized to handle the output from an array of this size. Technical Assessment Summary Shading Electrical Structural Geotech. Enviro. Comments Low Med None Low Low Ground condition is suitable for solar, though terrain does slope toward the road and roll north to south, with slopes up to 5 degrees. Shading concerns are minimal, though the trees are owned by the Village and could be removed if necessary Interconnection approval of the recommended size is not guaranteed. In either case, the main service will need to be upgraded to accommodate a 528 kw PV array. Silicon Valley Washington DC Chicago Beijing Page 66 of 67

67 Site Photos Looking west from southeast corner of property Looking north from southeast corner of property Looking north at well head 1 from pump house Service drop from NYSEG with 3 pole mounted transformers, adjacent to pump house Silicon Valley Washington DC Chicago Beijing Page 67 of 67

Considerations for Municipal Solar Projects. Ben Frevert Larsen Engineers November 16, 2016

Considerations for Municipal Solar Projects. Ben Frevert Larsen Engineers November 16, 2016 Considerations for Municipal Solar Projects Ben Frevert Larsen Engineers November 16, 2016 Topic Areas Benefits of going green / solar Actions local governments can take Programs and incentives Implementation

More information

Energy Savings through Solar Energy for Municipalities

Energy Savings through Solar Energy for Municipalities Energy Savings through Solar Energy for Municipalities May 2015 2014 Sunvestment Group www.sunvestmentgroup.com Solar Market Growth U.S. US Capacity and Generation: Solar Source: National Renewable Energy

More information

Puget Sound Energy Overview

Puget Sound Energy Overview Northwest Electric Meter School Leslie Moynihan Program Manager, Customer Connected Solar August 2018 Puget Sound Energy Overview Service Area - 6,000+ square miles in 10 Counties Electric - Customers

More information

Thomas Alston Director of Business and Policy Development. Presented By N. Scottsdale Rd, Suite 410 Scottsdale Arizona 85257

Thomas Alston Director of Business and Policy Development. Presented By N. Scottsdale Rd, Suite 410 Scottsdale Arizona 85257 Residential Solar Workshop May 7 th 2008 Thomas Alston Director of Business and Policy Development Presented By 1475 N. Scottsdale Rd, Suite 410 Scottsdale Arizona 85257 Workshop Agenda An Overview of

More information

Wind Interconnection and Net-Metering in MA. Tim Roughan - National Grid Joe Feraci - NStar

Wind Interconnection and Net-Metering in MA. Tim Roughan - National Grid Joe Feraci - NStar Wind Interconnection and Net-Metering in MA Tim Roughan - National Grid Joe Feraci - NStar Electric Transmission and Distribution System The Electric Power System (EPS) is designed to safely and reliably

More information

Michigan Renewable Energy Case Study

Michigan Renewable Energy Case Study Michigan Renewable Energy Case Study NARUC ENERGY REGULATORY PARTNERSHIP WITH GEORGIAN NATIONAL ENERGY AND WATER SUPPLY REGULATORY COMMISSION TBILISI, GEORGIA JANUARY 27-31, 2014 GREG R. WHITE, COMMISSIONER

More information

Alameda Unified School District

Alameda Unified School District Alameda Unified School District Alameda Unified School District Solar Master Plan Prepared by KyotoUSA May 2014 The purpose of this analysis is to assess the current feasibility of solar projects in the

More information

PDR Energy Baseline Alternative. Proposal for Discussion October 27, 2015

PDR Energy Baseline Alternative. Proposal for Discussion October 27, 2015 PDR Energy Baseline Alternative Proposal for Discussion October 27, 2015 Update Since Last Meeting Since the October 12 th Working Group Meeting Stem, Solar City, AMS and CESA have had over a half-dozen

More information

Long Island Solar Installer Workshop

Long Island Solar Installer Workshop Long Island Solar Installer Workshop Jossi Fritz-Mauer February 3, 2016 1 Agenda Solar Basics Solar PV Technology NY-Sun Incentive Program Financial Considerations Return on Investment Purchase or Leasing

More information

SEI Overview - Wind Power

SEI Overview - Wind Power SEI Overview - Wind Power Carbondale/Paonia Colorado www.solarenergy.org WHY WIND (renewables)? Gain energy independence from fossil fuels Ease demand on the power grid Reduce vulnerability to volatile

More information

Solar Power. Demonstration Site. Annual Performance Report 2017

Solar Power. Demonstration Site. Annual Performance Report 2017 Solar Power Demonstration Site Annual Performance Report 217 Version :1. July 12, 218 Solar Power Demonstration Site 217 Performance Report Introduction INTRODUCTION The Solar Power Demonstration Site

More information

RE: Advice Schedule 45 Public DC Fast Charger Delivery Service Optional Transitional Rate REPLACEMENT PAGES

RE: Advice Schedule 45 Public DC Fast Charger Delivery Service Optional Transitional Rate REPLACEMENT PAGES January 31, 2017 VIA ELECTRONIC FILING Public Utility Commission of Oregon 201 High Street SE, Suite 100 Salem, OR 97301-3398 Attn: Filing Center RE: Advice 16-020 Schedule 45 Public DC Fast Charger Delivery

More information

Southern California Edison s Preferred Resources Pilot (PRP) Solar Siting Survey. Summary Document

Southern California Edison s Preferred Resources Pilot (PRP) Solar Siting Survey. Summary Document Southern California Edison s Preferred Resources Pilot (PRP) Solar Siting Survey Summary Document Introduction The Southern California Edison (SCE) Preferred Resources Pilot (PRP) Solar Siting Survey,

More information

17 th Annual Caribbean Energy Conference

17 th Annual Caribbean Energy Conference 17 th Annual Caribbean Energy Conference Santo Domingo Jan 26-27 th 2017 Multi-site Solar Project By Clive Hosten Chief Engineer Introduction Grenada Spice Isle situated Lat12 N, Long 61 W, area of 133

More information

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 TODAY WE LL TALK ABOUT Our challenges and how we re meeting them Why we re building this project Our planning process and considerations

More information

Planning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014

Planning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014 Planning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014 The Clean Coalition recommends that state regulators and utilities account for potential

More information

Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017

Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017 Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017 Presentation Outline Understanding LPEA s expenses and what drives them Economics of net metering

More information

Consumer Guidelines for Electric Power Generator Installation and Interconnection

Consumer Guidelines for Electric Power Generator Installation and Interconnection Consumer Guidelines for Electric Power Generator Installation and Interconnection Habersham EMC seeks to provide its members and patrons with the best electric service possible, and at the lowest cost

More information

Capture The Power of Photovoltaics. IEEE Power Engineering Society Meeting May 2005

Capture The Power of Photovoltaics. IEEE Power Engineering Society Meeting May 2005 Capture The Power of Photovoltaics IEEE Power Engineering Society Meeting May 2005 Agenda Photovoltaic Basics Applications Economics Grid Interconnection and Net Metering Grid-Tied System Components Net

More information

Creating A Greener Energy Future For the Commonwealth. Massachusetts RPS Solar Carve-Out: Overview & Program Basics.

Creating A Greener Energy Future For the Commonwealth. Massachusetts RPS Solar Carve-Out: Overview & Program Basics. Massachusetts RPS Solar Carve-Out: Overview & Program Basics November 2, 2011 Outline Learn how the solar PV market has grown in MA since 2007 Understand the policy design of the MA RPS Solar Carve-Out

More information

Frequently Asked Questions Trico Proposed Net Metering Tariff Modifications

Frequently Asked Questions Trico Proposed Net Metering Tariff Modifications Frequently Asked Questions Trico Proposed Net Metering Tariff Modifications 1. Who is a self-generation or Net Metering Member? This is a Member who has installed grid-connected renewable generation, such

More information

Appendix E Water Supply Modeling

Appendix E Water Supply Modeling Supply Modeling Modesto Irrigation District Treatment Plant Expansion Project Modeling I. Introduction The Modesto Irrigation District (MID) is situated adjacent to and north of the Tuolumne River. Over

More information

JEA Distributed Generation Policy Effective April 1, 2018

JEA Distributed Generation Policy Effective April 1, 2018 Summary This JEA Distributed Generation Policy is intended to facilitate generation from customer-owned renewable and non-renewable energy generation systems interconnecting to the JEA electric grid. The

More information

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program As part of our commitment to support renewable energy, Kissimmee Utility Authority

More information

Net Metering & Compensation Seminar

Net Metering & Compensation Seminar Net Metering & Compensation Seminar November 2, 2017 Eversource Energy Hadley, MA Changes Are Here Market Net Metering Credit was introduced: 60% Market equal to 60% of distribution, transition, transmission

More information

This presentation was given as part of a workshop on November 14, Presenters were:

This presentation was given as part of a workshop on November 14, Presenters were: This presentation was given as part of a workshop on November 14, 2017. Presenters were: Andrew Valainis, Montana Renewable Energy Association Bryan Von Lossberg Paul Herendeen, Missoula Federal Credit

More information

40KW Solar System for Apple Sauce Co

40KW Solar System for Apple Sauce Co 2012 40KW Solar System for Apple Sauce Co Document Created for The Apple Sauce Co by Luke M Hardy lmhardy@smartconsult.com.au Smartcom P/L For further details please contact Luke M Hardy SunUp Solar Pty

More information

This presentation was given as part of a workshop on February 7, Presenters were:

This presentation was given as part of a workshop on February 7, Presenters were: This presentation was given as part of a workshop on February 7, 2018. Presenters were: Andrew Valainis, Montana Renewable Energy Association Bryan Von Lossberg, Renewable Energy Consultant Paul Herendeen,

More information

Grasshopper Vision. Accelerate the adoption of sustainable practices by creating accessible and affordable products for everyone.

Grasshopper Vision. Accelerate the adoption of sustainable practices by creating accessible and affordable products for everyone. Meeting Objective 1. Who are we? 2. Review Commercial Solar Industry 3. Who are the ideal candidates for solar? 4. Key Site Conditions 5. Typical Upfront and On-going Costs Grasshopper Vision Accelerate

More information

Mixed Generation Interconnection, Metering & Settlement

Mixed Generation Interconnection, Metering & Settlement Mixed Generation Interconnection, Metering & Settlement Netmetering Eligible, Class 1 Renewable Energy Generation Combined with Other Distributed Generation/Storage 1 Traditional Distributed Generation

More information

Montana Renewable Energy Association

Montana Renewable Energy Association Montana Renewable Energy Association Mission & Focus areas: Education and Outreach Policy and Advocacy Industry Engagement www.montanarenewables.org SolSmart Solar Ready communities making process of going

More information

NYS Commercial Solar Interconnection Workshop & Roundtable. Thomas V. Higgins Lead Technical Support Consultant - 9/29/2016

NYS Commercial Solar Interconnection Workshop & Roundtable. Thomas V. Higgins Lead Technical Support Consultant - 9/29/2016 NYS Commercial Solar Interconnection Workshop & Roundtable Thomas V. Higgins Lead Technical Support Consultant - 9/29/2016 NYSIR what is it? The NYSIR is the New York State Standardized Interconnection

More information

A 3-Year Case Study of a Residential Photovoltaic System with Microinverters

A 3-Year Case Study of a Residential Photovoltaic System with Microinverters A 3-Year Case Study of a Residential Photovoltaic System with Microinverters Clifford K. Ho Sandia National Laboratories, Albuquerque, NM Sandia National Laboratories is a multi-program laboratory managed

More information

Interconnection and Net Metering Service in Ohio

Interconnection and Net Metering Service in Ohio Interconnection and Net Metering Service in Ohio Partnership between National Association of Regulatory Utility Commissioners and The National Commission for Energy State Regulation of Ukraine June 20,

More information

Electric Vehicle Program

Electric Vehicle Program Cause No. 43960 INDIANAPOLIS POWER & LIGHT COMPANY Electric Vehicle Program Year 3 2013 Report May 2, 2014 Contents Background... 2 Project Objectives... 3 Current Status... 3 Significant Milestones...

More information

Ameren Missouri. AMENDED Renewable Energy Standard Compliance Report Prepared in Compliance with 4 CSR

Ameren Missouri. AMENDED Renewable Energy Standard Compliance Report Prepared in Compliance with 4 CSR Ameren Missouri AMENDED Renewable Energy Standard Compliance Report 2015 Prepared in Compliance with 4 CSR 240-20.100 June 23, 2016 NP Table of Contents Page INTRODUCTION...4 SECTION (8) (A) 1 A: TOTAL

More information

Solar Project Development in Regulated Markets. Smart and Sustainable Campuses Conference 2017

Solar Project Development in Regulated Markets. Smart and Sustainable Campuses Conference 2017 Solar Project Development in Regulated Markets Smart and Sustainable Campuses Conference 2017 Session Outline Overview of renewable energy procurement options Market structure and policy impacts on solar

More information

NJ Solar Market Update As of 10/31/15

NJ Solar Market Update As of 10/31/15 NJ Solar Market Update As of 10/31/15 Prepared by Charlie Garrison Renewable Energy Committee Meeting November 10, 2015 SOLAR INSTALLED CAPACITY DATA The preliminary installed solar capacity as of 10/31/15

More information

ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS. June 18, 2015 E2Tech Presentation

ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS. June 18, 2015 E2Tech Presentation ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS June 18, 2015 E2Tech Presentation AGENDA Energy storage as a grid solution high level Specific CEP project examples The technology

More information

ELECTRIC SERVICE RATE SCHEDULES. Effective November 1, 2017

ELECTRIC SERVICE RATE SCHEDULES. Effective November 1, 2017 ELECTRIC SERVICE RATE SCHEDULES Effective November 1, 2017 SCHEDULE 100 RESIDENTIAL SERVICE Residential Customers for all domestic uses. CHARACTER OF SERVICE: Alternating current, sixty-hertz 120/240 volts

More information

06/05/2018. COMMUNITY SOLAR OVERVIEW For Generation Owners and Subscribers

06/05/2018. COMMUNITY SOLAR OVERVIEW For Generation Owners and Subscribers 06/05/2018 COMMUNITY SOLAR OVERVIEW For Generation Owners and Subscribers No matter what you have heard it called, it all means the same thing. Community Solar Virtual Net Metering Aggregated Net Metering

More information

P.O BOX 429, NUKU ALOFA, Tel: (676) Fax: (676)

P.O BOX 429, NUKU ALOFA, Tel: (676) Fax: (676) P.O BOX 429, NUKU ALOFA, Tel: (676) 27-390 Fax: (676) 23-047 Email: jvanbrink@tongapower.to 22 October 2012 Lord Dalgety Electricity Commission Tu atakilangi Nuku alofa Dear Lord Dalgety Compliance Reporting

More information

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta

More information

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014 1 BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada IEEE PES Meeting July 2014 General BC Hydro Overview Crown Corporation Serving about 95% of province and 1.9 million customers

More information

THE PUBLIC SERVICE COMMISSION OF MARYLAND

THE PUBLIC SERVICE COMMISSION OF MARYLAND THE PUBLIC SERVICE COMMISSION OF MARYLAND Report on the Status of Net Energy Metering In the State of Maryland Prepared for the General Assembly of Maryland Pursuant to 7-306(i) of the Public Utilities

More information

Downtown Lee s Summit Parking Study

Downtown Lee s Summit Parking Study Downtown Lee s Summit Parking Study As part of the Downtown Lee s Summit Master Plan, a downtown parking and traffic study was completed by TranSystems Corporation in November 2003. The parking analysis

More information

115 KV/34.5KV SOLAR PLANT/SUBSTATION

115 KV/34.5KV SOLAR PLANT/SUBSTATION 27 April, 2016 115 KV/34.5KV SOLAR PLANT/SUBSTATION CHASE BENTON: SENKO DIZDAREVIC: ARIF IBRAHIM: MAKOKO MUKUMBILWA: TEAM LEADER COMMUNICATION LEADER WEBMASTER KEY CONCEPT HOLDER SPONSOR/CLIENT: ADVISOR:

More information

Funding Scenario Descriptions & Performance

Funding Scenario Descriptions & Performance Funding Scenario Descriptions & Performance These scenarios were developed based on direction set by the Task Force at previous meetings. They represent approaches for funding to further Task Force discussion

More information

Consumers Energy Net Metering

Consumers Energy Net Metering Consumers Energy Net Metering ELODY SAMUELSON September 20, 2016 Consumers Energy About Us Territory Overview 2 FOURTH-LARGEST COMBINATION UTILITY IN THE UNITED STATES Electric Utility 1.8 million electric

More information

Renewable energy & your co-op Installation procedures & guidelines for Farmers EC members YOU RE IN POWER.

Renewable energy & your co-op Installation procedures & guidelines for Farmers EC members YOU RE IN POWER. DISTRIBUTED GENERATION Renewable energy & your co-op Installation procedures & guidelines for Farmers EC members IPORTANT: Before construction and build of your distributed generation system, read this

More information

Yield Reduction Due to Shading:

Yield Reduction Due to Shading: x Fronius International NA-E35L5 35 W FRONIUS IG Plus 20 V-3 2 0,0kW x Fronius International NA-E35L5 35 W FRONIUS IG Plus 20 V-3 4 0,0kW 84 x SHARP Corporation x Fronius International NA-E35L5 35 W FRONIUS

More information

ARKANSAS PUBLIC SERVICE COMMISSION

ARKANSAS PUBLIC SERVICE COMMISSION ARKANSAS PUBLIC SERVICE COMMISSION IN THE MATTER OF THE APPLICATION ) OF THE CIYT OF FORREST CITY FOR THE ) DOCKET NO. 15-076-U APPROVAL OF AN INCREASE OF THE ) GENERATING CAPACITY LIMIT OF A ) NET METERING

More information

Should I Get a Solar Array for my House? The Regulations, Available Equipment, and Benefits Steven Johnson

Should I Get a Solar Array for my House? The Regulations, Available Equipment, and Benefits Steven Johnson Should I Get a Solar Array for my House? The Regulations, Available Equipment, and Benefits Steven Johnson 1 Scope Explore the considerations in the decision to install a PV System on my house Limited

More information

Energy Technical Memorandum

Energy Technical Memorandum Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter

More information

Study Report. McCredie-Overton Transmission Line Right-of-Way Analysis. City of Columbia, Missouri. prepared for the (S49)

Study Report. McCredie-Overton Transmission Line Right-of-Way Analysis. City of Columbia, Missouri. prepared for the (S49) Study Report McCredie-Overton Transmission Line Right-of-Way Analysis prepared for the City of Columbia, Missouri (S49) May, 2017 S49 McCredie-Overton Transmission Line Right-of-Way Study Report Table

More information

NJ Solar Market Update As of 6/30/15

NJ Solar Market Update As of 6/30/15 NJ Solar Market Update As of 6/30/ Prepared by Charlie Garrison July 17, 20 SOLAR INSTALLED CAPACITY DATA The preliminary installed solar capacity as of 6/30/ is approximately 1,500.7 MW. Approximately

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Solar Opportunities in Mississippi. Presented by: Aaron Hill & Elizabeth Ingram on behalf of Entergy Mississippi, Inc.

Solar Opportunities in Mississippi. Presented by: Aaron Hill & Elizabeth Ingram on behalf of Entergy Mississippi, Inc. Click to edit Master title style Solar Opportunities in Mississippi Presented by: Aaron Hill & Elizabeth Ingram on behalf of Entergy Mississippi, Inc. Mississippi Public Service Commission Working Session

More information

All of Texas Has Excellent Solar Resources. United States Solar Installed (as of mid 2013): 10 GW Germany Solar Installed (end of 2013): 35.

All of Texas Has Excellent Solar Resources. United States Solar Installed (as of mid 2013): 10 GW Germany Solar Installed (end of 2013): 35. All of Texas Has Excellent Solar Resources United States Solar Installed (as of mid 2013): 10 GW Germany Solar Installed (end of 2013): 35.962 GW Benefits of Solar Investing in Solar Creates Good Local

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

Update on State Solar Net Metering Activities Lori Bird, NREL RPS Collaborative Summit Washington, DC September 23, 2014

Update on State Solar Net Metering Activities Lori Bird, NREL RPS Collaborative Summit Washington, DC September 23, 2014 Update on State Solar Net Metering Activities Lori Bird, NREL RPS Collaborative Summit Washington, DC September 23, 2014 NREL is a national laboratory of the U.S. Department of Energy, Office of Energy

More information

New Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities

New Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities New Ulm Public Utilities Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities INDEX Document Review and History... 2 Definitions... 3 Overview... 3 Application

More information

NEM Aggregation Tariff Overview

NEM Aggregation Tariff Overview 1 NEM Aggregation Tariff Overview Harold Hirsch, Sr. Regulatory Analyst Maggie Dimitrova, Expert Program Manager June 17 th, 2014 Agenda Overview Eligibility Interconnection Billing Other programs and

More information

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER 1 Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER Lisa Dangelmaier Hawaii Electric Light lisa.dangelmaier@hawaiielectriclight.com Hawai'i Electric Light System Overview

More information

Economics of Owning vs. Renting LED Street Lights in National Grid and NYSEG territories

Economics of Owning vs. Renting LED Street Lights in National Grid and NYSEG territories Clean Energy Communities Program Economics of Owning vs. Renting LED Street Lights in National Grid and NYSEG territories Amanda Mazzoni, CNY RPDB Corner of Auburn and Fulton St., Village of Hannibal before

More information

Distribution Capacity Impacts of Plug In Electric Vehicles. Chris Punt, P.E. MIPSYCON 2014

Distribution Capacity Impacts of Plug In Electric Vehicles. Chris Punt, P.E. MIPSYCON 2014 Distribution Capacity Impacts of Plug In Electric Vehicles Chris Punt, P.E. MIPSYCON 2014 1 Outline EV Benefits EV Growth Where are we today? Where are we going? Potential Distribution Capacity Issues

More information

WinnCompanies Community Solar Photovoltaic to Benefit Affordable Housing Darien Crimmin Vice President of Energy & Sustainability

WinnCompanies Community Solar Photovoltaic to Benefit Affordable Housing Darien Crimmin Vice President of Energy & Sustainability WinnCompanies Community Solar Photovoltaic to Benefit Affordable Housing Darien Crimmin Vice President of Energy & Sustainability dcrimmin@winnco.com Massachusetts Solar Policy SREC I Program 2010 through

More information

Currant Lake Transmission Project

Currant Lake Transmission Project Currant Lake Transmission Project September 2010 Why are you receiving this project information package? New transmission facilities are needed in the Monitor area of southeastern Alberta. ATCO Electric

More information

Jean Marie River Solar and Wind Monitoring Update

Jean Marie River Solar and Wind Monitoring Update Jean Marie River Solar and Wind Monitoring Update Source: MACA Prepared for By Jean-Paul Pinard, P. Eng., PhD. 703 Wheeler St., Whitehorse, Yukon Y1A 2P6 Tel. (867) 393-2977; Email jpp@northwestel.net,

More information

Scaling Successful Mini-grid Programs: Experience of Bangladesh

Scaling Successful Mini-grid Programs: Experience of Bangladesh Frontier Developments in Mini-grids Scaling Successful Mini-grid Programs: Experience of Bangladesh Farzana Rahman Unit Head (Investment), Renewable Energy IDCOL, Bangladesh 6 December 2017 Abuja, Nigeria

More information

Renewable Energy. Presented by Sean Flanagan

Renewable Energy. Presented by Sean Flanagan Renewable Energy Presented by Sean Flanagan Background Flanagan and Sun since 2004 Solar electric (PV) off grid and grid tie, solar thermal, pool heating, solar air heating, small wind turbines, microhydro

More information

115 KV/34.5KV SOLAR PLANT/SUBSTATION

115 KV/34.5KV SOLAR PLANT/SUBSTATION 115 KV/34.5KV SOLAR PLANT/SUBSTATION CHASE BENTON TEAM LEADER SENKO DIZDAREVIC COMMUNICATION LEADER ARIF IBRAHIM WEBMASTER MAKOKO MUKUMBILWA KEY CONCEPT HOLDER SPONSOR: BLACK&VEATCH ADAM LITERSKI, RAHUL

More information

Creating A Greener Energy Future For the Commonwealth. Massachusetts Solar Carve-Out (SRECs): Overview & Program Basics.

Creating A Greener Energy Future For the Commonwealth. Massachusetts Solar Carve-Out (SRECs): Overview & Program Basics. Massachusetts Solar Carve-Out (SRECs): Overview & Program Basics December 18, 2012 Outline Learn how the solar PV market has grown in MA since 2007 Understand the policy design of the MA Solar Carve-Out

More information

Graph #1. Micro-Generation Generating Units in Alberta 20

Graph #1. Micro-Generation Generating Units in Alberta 20 2, Graph #1. Micro-Generation Generating Units in Alberta 2 Cumulative # of Generating Units 1,9 1,8 1,7 1,6 1,5 1,4 1,3 1,2 1,1 1, 9 8 7 6 5 4 3 2 Number of MGG Units as of 216 Mar 31 Number of Solar

More information

U.S. manufacturing technology orders kick off 2018 on a high note

U.S. manufacturing technology orders kick off 2018 on a high note Contact: Penny Brown, AMT, 703-827-5275 pbrown@amtonline.org For Release: March 12th, 2018 U.S. manufacturing technology orders kick off 2018 on a high note Orders for manufacturing technology in January

More information

2012 DFW Solar Home Tour October 6, 2012 Reference Solar PV

2012 DFW Solar Home Tour October 6, 2012 Reference Solar PV October 6, 2012 Reference Bill Neukranz bneukranz@verizon.net 972-516-0909 10/6/12 Bill Neukranz - 2012 1 The Basics Grid Tied, No Batteries Power grid Solar panels Electric meter AC loads DC to AC Converter

More information

MCE Napa County Cleaner energy and lower rates. Honig Winery, Rutherford

MCE Napa County Cleaner energy and lower rates. Honig Winery, Rutherford MCE Napa County Cleaner energy and lower rates Honig Winery, Rutherford Public Power by Community Choice Communities collectively purchase electricity as an alternative to investor-owned utility power

More information

40kW (and under) Solar/Inverter Installations Generation Interconnection Application to Minnesota Power

40kW (and under) Solar/Inverter Installations Generation Interconnection Application to Minnesota Power 40kW (and under) Solar/Inverter Installations Generation Interconnection Application to Minnesota Power WHO SHOULD FILE THIS APPLICATION: Anyone expressing interest to install generation which will interconnect

More information

Analysis of Impact of Mass Implementation of DER. Richard Fowler Adam Toth, PE Jeff Mueller, PE

Analysis of Impact of Mass Implementation of DER. Richard Fowler Adam Toth, PE Jeff Mueller, PE Analysis of Impact of Mass Implementation of DER Richard Fowler Adam Toth, PE Jeff Mueller, PE Topics of Discussion Engineering Considerations Results of Study of High Penetration of Solar DG on Various

More information

Solar Photovoltaic (PV) Design Considerations & Issues. By Paul M. Williams, President & CEO

Solar Photovoltaic (PV) Design Considerations & Issues. By Paul M. Williams, President & CEO Solar Photovoltaic (PV) Design Considerations & Issues By Paul M. Williams, President & CEO NEC Article 690 Solar Photovoltaic (PV) Systems The article consists of eight chapters. Chapters 2 through 4

More information

Commercial-in-Confidence Ashton Old Baths Financial Model - Detailed Cashflow

Commercial-in-Confidence Ashton Old Baths Financial Model - Detailed Cashflow Year 0 1 2 3 4 5 6 7 8 9 10 11 12 13 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 2,038 2,922 4,089 4,349 6,256 7,124 8,885 8,885 8,885 8,885 8,885 8,885 9,107

More information

Solar Energy Proposal City of Galesburg WORK SESSION FEBRUARY 26, 2018

Solar Energy Proposal City of Galesburg WORK SESSION FEBRUARY 26, 2018 Solar Energy Proposal City of Galesburg WORK SESSION FEBRUARY 26, 2018 Illinois Solar Overview December 2016 new legislation paves way for solar in the State of Illinois Requires utilities to have 3.0

More information

Transmission Access Charges (TAC) Katie Ramsey Staff Attorney Clean Coalition mobile

Transmission Access Charges (TAC) Katie Ramsey Staff Attorney Clean Coalition mobile Transmission Access Charges (TAC) Katie Ramsey Staff Attorney Clean Coalition 202-709-8063 mobile katie@clean-coalition.org Making Clean Local Energy Accessible Now November 2016 Distributed Generation

More information

ANDERSON PROPERTY SITE ANALYSIS

ANDERSON PROPERTY SITE ANALYSIS ANDERSON PROPERTY SITE ANALYSIS Introduction The Montgomery County Department of Transportation (MCDOT) initiated a feasibility study in the fall of 2012 to evaluate the need for transit service expansion

More information

2016 Load & Capacity Data Report

2016 Load & Capacity Data Report Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness

More information

FARM WASTE GENERATING SYSTEMS

FARM WASTE GENERATING SYSTEMS Page 1 FARM WASTE GENERATING SYSTEMS Customers interested in reducing their energy usage and their carbon footprint are turning their attention to renewable power generation technologies such as farm waste

More information

Thomas Edison, U.S. inventor, in 1931 conversation with Henry Ford and Harvey Firestone

Thomas Edison, U.S. inventor, in 1931 conversation with Henry Ford and Harvey Firestone We are like tenant farmers chopping down the fence around our house for fuel when we should be using nature s inexhaustible sources of energy; sun, wind and tide... I d put my money on the sun and solar

More information

NJ Solar Market Update

NJ Solar Market Update NJ Solar Market Update April 16, 20 Renewable Energy Committee Meeting Trenton, NJ Prepared by Charlie Garrison Solar Installed Capacity Data The preliminary installed solar capacity as of 3/31/ is approximately

More information

Minnesota Dept. of Commerce, Division of Energy Resources. Distributed Generation Workshop Interconnection Standards

Minnesota Dept. of Commerce, Division of Energy Resources. Distributed Generation Workshop Interconnection Standards Minnesota Dept. of Commerce, Division of Energy Resources Distributed Generation Workshop Interconnection Standards Presented by Michael Sheehan, P.E. October 11, 2011 Germans Solar Projected Cost Reductions

More information

SUMMARY OF TOTAL CURRENT PRICES - ELECTRIC

SUMMARY OF TOTAL CURRENT PRICES - ELECTRIC Electric Summary Sheet No. S-1 HOW A CUSTOMER BILL IS CALCULATED 7 RESIDENTIAL SERVICE For a customer who used 1,000 kwh during one month (assuming 30 days of service). Schedule 7 is referred to on customer

More information

THE GENERAL ASSEMBLY OF PENNSYLVANIA HOUSE BILL

THE GENERAL ASSEMBLY OF PENNSYLVANIA HOUSE BILL PRINTER'S NO. THE GENERAL ASSEMBLY OF PENNSYLVANIA HOUSE BILL No. Session of 0 INTRODUCED BY QUINN, DONATUCCI, SCHLOSSBERG, D. MILLER, FREEMAN, STURLA, SCHWEYER, BARRAR AND SIMS, JANUARY, 0 REFERRED TO

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Rate Impact of Net Metering. Jason Keyes & Joseph Wiedman Interstate Renewable Energy Council April 6, 2010

Rate Impact of Net Metering. Jason Keyes & Joseph Wiedman Interstate Renewable Energy Council April 6, 2010 Rate Impact of Net Metering Jason Keyes & Joseph Wiedman Interstate Renewable Energy Council April 6, 2010 1 Scope Impact of net metering on utility rates for customers without distributed generation Proposes

More information

Solar*Rewards Frequently asked questions system size and customer usage

Solar*Rewards Frequently asked questions system size and customer usage Solar*Rewards 1. Will a PV system work with my home? 2. Am I eligible to participate in the Solar*Rewards program? 3. What size system should I get? 4. Can a customer at a service location apply for the

More information

Energy Produced by PV Array (AC):

Energy Produced by PV Array (AC): 4x17 2x16 400 x PHOTON SOLAR 4 x KACO new energy PH-250P-60 (HDS) INT 250 W Powador 30,0 TL3 15 ; 0 25,0kW Location: Climate Data Record: PV Output: Gross/Active PV Surface Area: Antalya Antalya (1961-1990)

More information

Implications of Alberta s Evolving Electricity Market for Solar

Implications of Alberta s Evolving Electricity Market for Solar Implications of Alberta s Evolving Electricity Market for Solar Matt Ayres CEO, Market Surveillance Administrator matt.ayres@albertamsa.ca What does the Market Surveillance Administrator do? Investigation

More information

Solar Farm Leases Q & A

Solar Farm Leases Q & A Cornell Cooperative Extension Sullivan County Gerald J. Skoda Extension Education Center 64 Ferndale-Loomis Road Liberty, NY 12754 p: 845-292-6180 f: 845-292-4946 e: sullivan@cornell.edu w: www.sullivancce.org

More information

Kettle River Transmission Project

Kettle River Transmission Project April 2012 Why are you receiving this project information package? New transmission facilities are needed in the Fort McMurray area. ATCO Electric has been directed by the Alberta Electric System Operator

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

Passenger Rail Solar Electrification: A Primer. Oregon Department of Transportation Rail Division. June 2009

Passenger Rail Solar Electrification: A Primer. Oregon Department of Transportation Rail Division. June 2009 Passenger Rail Solar Electrification: A Primer Oregon Department of Transportation Rail Division June 2009 Betsy Imholt ODOT Rail Division 503.986.4077 phone betsy.imholt@odot.state.or.us Executive Summary

More information