1 NYS Commercial Solar Interconnection Workshop & Roundtable Thomas V. Higgins Lead Technical Support Consultant - 9/29/2016
2 NYSIR what is it? The NYSIR is the New York State Standardized Interconnection Requirements and Application Process for New Distributed Generators 2 MW or Less Connected in Parallel with Utility Distribution Systems. Current Version is the March 2016 Update Projects whose applications were received before April 29, 2016 fall under the rules of the old SIR, dated 2/2014. This is the rule book know it. 2
3 NYSIR Application requirements For systems 50 kw to 5 MW: Completed application form Signed copy of standard contract Letter of authorization (RNM, not CDG) New service? Provide a site plan. Narrative of project details. Technology type Fuel source/configuration Proposed project size in AC kw Net meter, RNM or CDG? Metering configuration UL 1741 certification Manufacturers Data sheet (cutsheets) Manufacturers Test procedures Three line (system) diagram And don t forget a $750 application fee. 3
4 National Grid Website 4
5 The Interconnection Contract 5
6 Form K Important Points Name (Regular project): must be the name of an existing National Grid customer. Name (Community Solar): Owner or Operator of system Address: Address of solar installation File # (CLA): National Grid will assign this it s how we track Utility Account Number: Depends of type of installation Net meter vs. Remote Net Meter Signature must be customer (owner). Does not need to be signed until ready to commit to construction 6
7 Appendix B system specifics 7
8 Appendix B system specifics 8
9 Appendix B system specifics 9
10 Letter of Authorization 10
11 Cut Sheets 11
12 UL1741 Certification 12
13 Three Line Diagrams Necessary for all Interconnection Applications From Appendix F: System diagram A three line diagram for designs proposed on three phase systems, including information on the wiring configuration at the PCC and an exact representation of existing utility service. This is a relatively low hurdle to clear, but a misleading or inadequate three line diagram may not be accepted or will delay your project while problems get resolved. 13
14 The Application Review Process The application review process now follows the Preliminary/ Supplemental Screening Analysis steps (Page 9 in the SIR). The Preliminary Screen is Appendix 6, Screen A F. A. On a Network? B. UL 1741 equipment being used? C. Does it exceed the Electric Power System (EPS) rating? D. Line configuration compatible with Interconnection type? E. 15% Penetration test. F. Voltage fluctuation test. 14
15 The Application Review Process Other items to know about in the New SIR: Pre-application Report Preliminary Analysis Results Meeting Supplemental Screen ($2,500) Screens G I Lots of timelines for activity or to remove projects from the company s inventory (The Queue). And same as the old SIR: The CESIR (Coordinated Electric System Interconnection Review) 15
16 Things you should do Cover sheet describe the project, especially if not obvious. Use a template that covers all the necessary information. Include everything it may be clear to you but not to us. Site Plan Indicate where you plan on installing facilities and interconnecting to us. Pole numbers, GSP coordinates, etc. When submitting, include a photocopy of the Application Fee check and indicate (on the cover sheet) when you mailed it and where you mailed it to. Put the National Grid Account Number on the check! 16
17 Site Plan 17
18 Things you should never do Buy certain equipment before your project and equipment is approved. Install facilities before your project is approved. Make promises before your project is approved, including timelines. Assume that urban environments are OK (Network Systems). Assume that rural environments are OK (Feeder Loading). Assume that a feeder has lots of capacity (that could be bad). Assume that just because it s a small system, it s OK. Assume that because you don t see much DG on a feeder, it s good. Try to go around the Interconnection process (SIR). Try to go around the DG group to the local design or construction people. 18
19 Things you should know The NYSIR. Available at the PSC website. PSC 220. This is the National Grid Electric Tariff. Distributed Generation particulars are Leaves 36, 37 and 53. Also at the PSC website. The National Grid Electric Service Bulletins (ESBs), particularly ESB 756, Appendix B. The ESBs are our standards books. 756 is Requirements for Parallel Generation Connected to a National Grid Owned EPS. Appendix B is the particulars for the NYSIR. Available at the National Grid website. 19
20 Thank you. 20
Considerations for Municipal Solar Projects. Ben Frevert Larsen Engineers November 16, 2016
Considerations for Municipal Solar Projects Ben Frevert Larsen Engineers November 16, 2016 Topic Areas Benefits of going green / solar Actions local governments can take Programs and incentives Implementation
More informationRenewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group
Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group Table of Contents 1. Introduction... 1 2. Purpose... 1 3. Customer Eligibility...
More informationLong Island Solar Installer Workshop
Long Island Solar Installer Workshop Jossi Fritz-Mauer February 3, 2016 1 Agenda Solar Basics Solar PV Technology NY-Sun Incentive Program Financial Considerations Return on Investment Purchase or Leasing
More informationRenewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group
Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group Table of Contents 1. Introduction... 1 2. Purpose... 1 3. Customer Eligibility...
More informationInterconnection Process Simplification Webinar
Please stay tuned for the 1 Interconnection Process Simplification Webinar We will be starting momentarily last updated 3.4.13 2 Agenda Overview of PG&E s NEM Program What you need to know about NEM interconnections
More informationWind Interconnection and Net-Metering in MA. Tim Roughan - National Grid Joe Feraci - NStar
Wind Interconnection and Net-Metering in MA Tim Roughan - National Grid Joe Feraci - NStar Electric Transmission and Distribution System The Electric Power System (EPS) is designed to safely and reliably
More informationDistributed Generation Guide. Version 1 / September 2011
Distributed Generation Guide Version 1 / September 2011 LEGAL DISCLAIMER: This guide is for informational purposes only and does not constitute legal advice. This does not substitute for any applicable
More informationVersion 1, June Energy Storage System Guide Version 1 / June 2018
Energy Storage System Guide Version 1 / June 2018 1 Consolidated Edison Company of New York: Guide to ESS Interconnection Introduction This guide is for Con Edison customers who are considering installing
More informationJEA Distributed Generation Policy Effective April 1, 2018
Summary This JEA Distributed Generation Policy is intended to facilitate generation from customer-owned renewable and non-renewable energy generation systems interconnecting to the JEA electric grid. The
More informationDistributed Generation Guide Version 4 / May 2017
Distributed Generation Guide Version 4 / May 2017 LEGAL DISCLAIMER: This guide is for informational purposes only and does not constitute legal advice. This does not substitute for any applicable laws,
More informationInstructions for Completing Oncor s Interconnection Application For Solar PV Projects
Instructions for Completing Oncor s Interconnection Application For Solar PV Projects Program Year 2009 Take a Load Off, Texas SM is provided by Oncor Electric Delivery LLC as part of the company s commitment
More informationNew York City Solar Installer Workshop
New York City Solar Installer Workshop March 12, 2018 Con Edison Cliff Baratta, Sr Specialist Kevin Bishop, Sr Specialist Beatrice Troiano, Specialist Distributed Generation Group 1 Agenda 2017 Overview
More informationSolar*Rewards Community Engineering Frequently Asked Questions For Garden Operators Minnesota
P a g e 1 Solar*Rewards Community Engineering Frequently Asked Questions For Garden Operators Minnesota The purpose of this document is to provide Garden Operators further documentation of engineering
More informationUmatilla Electric Cooperative Net Metering Rules
Umatilla Electric Cooperative Net Metering Rules Version: July 2017 Umatilla Electric Cooperative NET METERING RULES Rule 0005 Scope and Applicability of Net Metering Facility Rules (1) Rule 0010 through
More informationPresentation to the PJM NEMSTF Interconnection Issues. Interconnecting Solar Projects on the PSE&G Distribution System
Interconnecting Solar Projects on the PSE&G Distribution System This presentation is intended to be a brief discussion of the effects of interconnecting of large amounts of solar generation on the distribution
More informationMaryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less)
Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less) Interconnection Customer Contact Information Name: Address: Alternative Contact Information
More informationProducing your own energy? Great Decision. ComEd.com/Interconnection. Let s connect you to our smart grid.
CONNECTING PRIVATE SOLAR ENERGY SYSTEMS AND NET METERING Producing your own energy? Great Decision. Let s connect you to our smart grid. ComEd.com/Interconnection CONNECTING PRIVATE SOLAR ENERGY SYSTEMS
More informationApplication for Commission Approval to Construct a Generating Station Pursuant to Public Utilities Article Section and
Application for Commission Approval to Construct a Generating Station Pursuant to Public Utilities Article Section 7-207.1 and 7-207.2 APPLICABILITY The Public Service Commission of Maryland ( Commission
More informationInterconnection Process Simplification Webinar
12.02.09 Interconnection Process Simplification Webinar The slides for today s presentation can be downloaded/printed at www.pge.com/solareducation 2 Agenda Overview of PG&E s NEM interconnection process
More informationMunicipality Generator Interconnection Application Single Meter Application Part I
Municipality Generator Interconnection Application Single Meter Application Part I New Application Revised Application A single customer interconnecting to a single meter at a single premise makes a new
More informationParticipation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market
Beacon Power Corporation Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market Prepared for: New York Business Issues Committee May 21, 2008 Safe Harbor
More informationUpdate on State Solar Net Metering Activities Lori Bird, NREL RPS Collaborative Summit Washington, DC September 23, 2014
Update on State Solar Net Metering Activities Lori Bird, NREL RPS Collaborative Summit Washington, DC September 23, 2014 NREL is a national laboratory of the U.S. Department of Energy, Office of Energy
More information40kW (and under) Solar/Inverter Installations Generation Interconnection Application to Minnesota Power
40kW (and under) Solar/Inverter Installations Generation Interconnection Application to Minnesota Power WHO SHOULD FILE THIS APPLICATION: Anyone expressing interest to install generation which will interconnect
More informationMaryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less)
Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less) Interconnection Customer Contact Information Name: Address: City: Telephone (aytime):
More informationDuke Energy Carolinas North Carolina Interconnection Request Checklist
Duke Energy Carolinas North Carolina Interconnection Request Checklist The North Carolina Utilities Commission issued North Carolina Interconnection Procedures, Forms, And Agreements For State-Jurisdictional
More informationLevel 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less)
Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less) Interconnection Customer Contact Information Name Alternative Contact Information (if different
More informationCHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.
25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context indicates otherwise, this section and 25.212 of this title (relating to Technical Requirements
More informationTHE EMPIRE DISTRICT ELECTRIC COMPANY P.S.C. Mo. No. 5 Sec. 4 1st Revised Sheet No. 23
P.S.C. Mo. No. 5 Sec. 4 1st Revised Sheet No. 23 Canceling P.S.C. Mo. No. 5 Sec. 4 Original Sheet No. 23 PURPOSE: The purpose of this Rider SR is to implement the solar rebate established through 393.1030
More informationFrequently Asked Questions Trico Proposed Net Metering Tariff Modifications
Frequently Asked Questions Trico Proposed Net Metering Tariff Modifications 1. Who is a self-generation or Net Metering Member? This is a Member who has installed grid-connected renewable generation, such
More informationINTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY
INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY Table of Contents Chapter 1. Purpose and scope. Pg 3 Chapter 2. Application
More informationGENERAL INFORMATION. 13. SERVICE CLASSIFICATION RIDERS (Continued) RIDER N NET METERING FOR CUSTOMER GENERATORS
P.S.C. NO. 3 ELECTRICITY LEAF: 179 ORANGE AND ROCKLAND UTILITIES, INC. REVISION: 6 INITIAL EFFECTIVE DATE: April 27, 2017 SUPERSEDING REVISION: 5 Issued in compliance with Order in Cases 15-E-0751 and
More informationMISSOURI SERVICE AREA
MO.P.S.C. SCHEDULE NO. 6 4th Revised SHEET NO. 88 CANCELLING MO.P.S.C. SCHEDULE NO. 6 3rd Revised SHEET NO. 88 PURPOSE SOLAR REBATE The purpose of this Rider SR is to implement the solar rebate established
More informationHANDBOOK OF GENERAL REQUIREMENTS FOR ELECTRICAL SERVICE TO DISPERSED GENERATION CUSTOMERS
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT SPECIFICATION EO-2115 REVISION 8 March 2006 HANDBOOK OF GENERAL REQUIREMENTS FOR ELECTRICAL
More informationImpact of Distributed Energy Resources on Transmission System Reliability
S E P T E M B E R 1 3, 2 0 1 8 W E B I N A R Impact of Distributed Energy Resources on Transmission System Reliability National Council on Electricity Policy (NCEP) Alan McBride D I R E C T O R, T R A
More informationCIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems
CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems Ben Huckaba, P.E. President & Principal Engineer 317-273-9841 benh@alphaeng.us Indiana University Bloomington,
More informationConsumer Guidelines for Electric Power Generator Installation and Interconnection
Consumer Guidelines for Electric Power Generator Installation and Interconnection Habersham EMC seeks to provide its members and patrons with the best electric service possible, and at the lowest cost
More informationSCHEDULE NO. ACG33 NET METERING SERVICE
Approved by Decision No.: 75408 Effective: January 19, 2016 Applicability Applicable to "Net Metering Facility" as defined below, or applicable Arizona Corporation Commission ("Cmnn1ission") Decision,
More informationGuideline for Using IEEE 1547 for Solar PV Interconnection Page 1
Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1 A Guide for Iowa s Municipal Electric Utilities On the How the IEEE 1547 Distributed Generation Interconnection Standard Affects Solar
More informationMerchant Network Upgrade Proposed Solution
Merchant Network Upgrade Proposed Solution Jason Connell Project Manager, Interconnection Projects Markets & Reliability Committee July 23, 2015 Presentation Approach Presentation Background Four Tariff
More informationElectrical District No. 3 SOLAR Q & A
D3 Electrical District No. 3 SOLAR Q & A What are some things I should consider before going solar? Leasing verses owning: Know the Pros and Cons of each, as well as the Short-term and Long-Term effects
More informationDG Winter Installer Workshop. December 12th, 2018 Con Edison
DG Winter Installer Workshop December 12th, 2018 Con Edison 1 Agenda Overview of progress to date Con Edison Grid Con Edison Interconnection Process How to navigate the DG website Value Stack Open Discussion
More informationEnergy Storage System Application Guidelines
Energy Storage System Application Guidelines Xcel Energy- Wisconsin January 18 th, 2019 Agenda Guidelines Development Process ESS Review Considerations Net Energy Metering (NEM) Integrity Application Process
More informationCommunity Solar Policy
S s Community Solar Policy Renewable Energy Markets 2015 10/20/15 S s S s Clean Energy Collective Community Solar Nation s leading community solar provider 25 utilities spanning 11 states 50+ community
More informationREVISION NO.: 7 EFFECTIVE: 07/07/16
SOLAR PROGRAM INTERCONNECTION PROCESS OVERVIEW FOR RESIDENTIAL AND SMALL GENERAL SERVICE REVISION NO.: 7 EFFECTIVE: 07/07/16 Required Steps for ED3 s Solar Program Interconnection Process for Residential
More informationELECTRIC SERVICE RULES DISTRIBUTED GENERATION Issued Jan 2016
DISTRIBUTED GENERATION CHAPTER 5 500. SCOPE This chapter includes distributed or customer-owned generation connected in parallel and operating with Alliant Energy s electric distribution system. For all
More informationProposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013
Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in 2015 Stakeholder Webconference February 28, 2013 Page 2 Merced Irrigation District (Merced) Background Merced Irrigation
More informationNew Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities
New Ulm Public Utilities Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities INDEX Document Review and History... 2 Definitions... 3 Overview... 3 Application
More informationPowering Your Home With The Sun. Introduction to Residential Solar Energy Systems [Your Name] ISEA Solar Ambassador
Powering Your Home With The Sun Introduction to Residential Solar Energy Systems [Your Name] ISEA Solar Ambassador Illinois Solar Energy Association (ISEA) ISEA s mission is to educate and advocate for
More informationImplementing Net Metering to Meet Policy Objectives
Implementing Net Metering to Meet Policy Objectives EUEC 2015 February 16, 2015 Joseph Daniel & Dr. Tommy Vitolo, Synapse Energy Economics jdaniel@synapse energy.com Synapse Energy Economics Founded in
More information2019 NYC Solar Installer Workshop: Solar and Storage. March 18, 2019
2019 NYC Solar Installer Workshop: Solar and Storage March 18, 2019 2 ConEdison Activity Since MW Block Redesign Commercial MW Block Activity 3 15 MW submitted since redesign - 6/17/2018 10 rooftop canopy
More informationInterconnection Process for Generation Systems
Interconnection Process for Generation Systems I. INTRODUCTION...1 II. GENERAL INFORMATION...2 A. Definitions...2 B. Nodak Electric Cooperative, Inc. Generation Interconnection Contacts...3 C. Engineering
More informationSOUTH HADLEY ELECTRIC LIGHT DEPARTMENT Net Metering Policy As Amended 03/23/16 By the South Hadley Municipal Light Board
SOUTH HADLEY ELECTRIC LIGHT DEPARTMENT Net Metering Policy As Amended 03/23/16 By the South Hadley Municipal Light Board Policy Description: In an effort to ensure fair treatment of all of its customers,
More informationThe Geli Guide to SGIP April 26, 2017
The Geli Guide to SGIP 2017 April 26, 2017 Agenda What is Geli? Intro to SGIP Case Study How to Apply ESyst Demo Next Steps 2 What is Geli? Software that maximizes the value of energy storage Geli s solutions
More informationNew Jersey Solar Roundtable
New Jersey Solar Roundtable Transition to a Market-based REC Financing System Michael Winka, Director NJBPU, Office of Clean Energy Presented at Thomas Edison Institute March 5, 2007 NJ Solar Financing
More informationKANSAS CITY POWER AND LIGHT COMPANY P.S.C. MO. No. 7 Fourth Revised Sheet No. 39 Canceling P.S.C. MO. No. 7 Third Revised Sheet No.
P.S.C. MO. No. 7 Fourth Revised Sheet No. 39 Canceling P.S.C. MO. No. 7 Third Revised Sheet No. 39 PURPOSE: The purpose of the Solar Subscription Pilot Rider (Program) is to provide a limited number of
More informationRULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)
- (SMUD FORM 2655) A. Applicability: This Generating Facility Interconnection Application (Application) shall be used to request the interconnection of a Generating Facility to Sacramento Municipal Utility
More information2016 Load & Capacity Data Report
Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness
More informationCYPRUS ENERGY REGULATORY AUTHORITY REGULATION OF RENEWABLE ENERGY SOURCES FOR THE FUTURE
CYPRUS ENERGY REGULATORY AUTHORITY REGULATION OF RENEWABLE ENERGY SOURCES FOR THE FUTURE Andreas Frixou Energy Officer (Transmission, Distribution & Supply of Electricity) CONTENTS Legal Status of CERA
More informationWhat, Why, and Where? Brian Lips Senior Project Manager for Policy NC Clean Energy Technology Center
What, Why, and Where? Brian Lips Senior Project Manager for Policy NC Clean Energy Technology Center bclips@ncsu.edu About the 50 States of Solar Quarterly publication detailing state and utility distributed
More informationApplication for Steam Service
Application for Steam Service Welcome! This is your application to Consolidated Edison Company of New York, Inc., for steam service. As a Con Edison steam customer, you agree to pay for the service supplied
More informationGuidelines for Inverter-Based Micro-Generating Facility (10 kw and Smaller)
Guidelines for Inverter-Based Micro-Generating Facility (10 kw and Smaller) Cover: Photos courtesy of Balance Solutions for Today Inc OVERVIEW Today many home, farm and small business owners are considering
More informationSouthern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1
Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide Version 1.1 October 21, 2016 1 Table of Contents: A. Application Processing Pages 3-4 B. Operational Modes Associated
More informationPSE&G Renewable Energy Programs Susanna Chiu Director - Business Development
PSE&G Renewable Energy Programs Susanna Chiu Director - Business Development 1 Advantages of Solar Energy Energy Independence. Solar energy is renewable. We never have to worry about running out of sunlight
More informationPlease Refer to Attached Sample Form
Pacific Gas and Electric Company San Francisco, California U 39 Revised Cal. P.U.C. Sheet No. 32105-E Cancelling Revised Cal. P.U.C. Sheet No. 28313-E Electric Sample Form No. 62-0686 Application for Service
More informationNortheastern Rural Electric Membership Corporation Columbia City, Indiana
Page 1 of 5 SCHEDULE ADG - 1 AGGREGATED DISTRIBUTED GENERATION SERVICE I. AVAILABILITY This Aggregated Distributed Generation Schedule is available to any member in good standing of Northeastern REMC (Northeastern),
More informationCARTHAGE WATER & ELECTRIC PLANT ELECTRIC RATES RESIDENTIAL SERVICE
RESIDENTIAL SERVICE This rate is available by contract for single-phase 120/240 volt service to a single family dwelling through one meter for domestic use, and to separate structures on the same parcel
More informationLevel 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kva to 10 MVA or less)
Section 466.APPENIX C Levels 2 to 4 Application Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kva to 10 MVA or less) Interconnection Customer Contact Information
More informationSolar Photovoltaic (PV) Installation - Updates
Solar Photovoltaic (PV) Installation - Updates Malcolm Brown CCEI Electrical Safety Authority Technical Advisor - Western Region Electrical Safety Authority 2013 1 For Your Safety Topics of discussion
More informationApplication for Interconnection and Net Metering Revision: 1 Revised: November 7, 2017
Net Metering Revision: 1 Revised: November 7, 2017 Net Metering Page 1 of 5 1 Net Metering This Application and Agreement is considered complete when it provides all applicable and correct information
More information2012 INSTALLERS MEETING UES INSTALLER S MEETING
2012 INSTALLERS MEETING UES INSTALLER S MEETING Agenda Welcome & Introductions 2011 Overview Policies and Procedures 2012 Program Overview Program Incentives Questions & Answers UES Conservation and Renewable
More informationAppendix A Technical Specifications Class I, II, III, IV Sewage Pumping Lift Station Wet Well Cleaning and Hauling
Appendix A 075-18 Technical Specifications Class I, II, III, IV Sewage Pumping Lift Station Wet Well Cleaning and Hauling INTENT JEA is soliciting proposals for industrial services to remove & dispose
More informationInformation Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program
Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program As part of our commitment to support renewable energy, Kissimmee Utility Authority
More informationCaution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any
Draft Version 1 Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation,
More informationDistributed Generation
Distributed Generation Presented by: Doug Fairchild & Chris Cooper 1 Agenda Hydro One Overview The state of DG in the Province of Ontario Technical Issues Operational Requirements Overview Control Room
More informationVersion 2, May 2018 Fuel Cell Guide
Fuel Cell Guide Version 2 / May 2018 1 Introduction Consolidated Edison Company of New York: Guide to Fuel Cell Interconnection This guide is for Con Edison Customers who are considering installing or
More informationNET METERING ENROLLMENT APPLICATION REFERENCE GUIDE
NET METERING ENROLLMENT APPLICATION REFERENCE GUIDE March 20, 2006 Updated September 2013 SCOPE The purpose of this Guide is to help you understand sections 2 to 9 of the Net Metering Enrollment Application.
More informationAPPLICATION Net Energy Metering Interconnection For Solar And/Or Wind Electric Generating Facilities Of 30 Kilowatts Or Less
IMPORTANT NOTES: Customers may not operate their Generating Facility while interconnected to the PG&E system until they receive written permission from PG&E. For a non-exporting Generating Facility, RES-BCT
More informationSolar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011
Solar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011 Jim Calore Public Service Electric & Gas Co. Overview This
More informationCaution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any
Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness
More informationROLLOVER RIGHTS OF LONG TERM FIRM TRANSMISSION SERVICE
ROLLOVER RIGHTS OF LONG TERM FIRM TRANSMISSION SERVICE In this Section: Overview Evaluation of Initial Requests Rollover Request Competing Request Competing Examples 1.0 OVERVIEW Pursuant to Section 2.2
More informationSERVICE CLASSIFICATION "CEF" COMMUNITY ENERGY FACILITY
P.S.C. Del. No. 8 - Electric Original Leaf No. 95a SERVICE CLASSIFICATION "CEF" COMMUNITY ENERGY FACILITY A Community Energy Facility (CEF) consists of one or more generators located in Company s service
More informationTopic Small Projects (< 100 kw) Large Projects (>100 kw)
New Hampshire Public Utilities Commission Docket No. DE 16-576 Development of New Alternative Net Metering Tariffs and/or Other Regulatory Mechanisms and Tariffs for Customer-Generators Joint Settlement
More informationCOMMUNITY SOLAR PROGRAM
Original Sheet No. D-22.00 COMMUNITY SOLAR PROGRAM The Cooperative's generation and transmission Cooperative ("G&T") has created a standing offer for 10 MW ofrenewable energy, produced by solar and wind
More informationNet Metering & Compensation Seminar
Net Metering & Compensation Seminar November 2, 2017 Eversource Energy Hadley, MA Changes Are Here Market Net Metering Credit was introduced: 60% Market equal to 60% of distribution, transition, transmission
More informationRenewable Net Metering Program Appendix ESD APX 001 1
CITY OF ST.GEORGE Energy Services Department (SGESD) Renewable Net Metering Program Appendix Document No. Effective Date 10/15/2005 Revision No. 1.0 Review Date 02/18/2016 Review Cycle Annually Creation
More informationBihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna
Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna 800 021 ------------------------------------------------------------------------------------------------------------- ROOFTOP
More informationREQUIREMENTS FOR PARALLEL OPERATION FOR CUSTOMERS WITH GENERATION NOT EXCEEDING 50 kw
REQUIREMENTS FOR PARALLEL OPERATION FOR CUSTOMERS WITH GENERATION NOT EXCEEDG 50 kw FOREWARD Requirements for Parallel Operations for Customers with Generation Not Exceeding 50 kw is intended to be used
More informationLegal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:
Generating Facility Level 2 or 3 Interconnection Review (For Generating Facilities with Electric Nameplate Capacities no Larger than 20 MW) Instructions An Interconnection Customer who requests a Utah
More informationMISSOURI SERVICE AREA
MO.P.S.C. SCHEDULE NO. 6 1st Revised SHEET NO. 171.5 CANCELLING MO.P.S.C. SCHEDULE NO. 6 Original SHEET NO. 171.5 INTERCONNECTION APPLICATION/AGREEMENT FOR NET METERING SYSTEMS WITH CAPACITY OF 100 kw
More informationEgyptian Solar PV Feed-in-Tariff Procedures for Small Scale Projects
Egyptian Solar PV Feed-in-Tariff Procedures for Small Scale Projects 1 SELECTION OF QUALIFIED COMPANY A short list of Qualified Companies (QCs, installer) is available through NREA website or Electricity
More informationSALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-27 CUSTOMER GENERATION PRICE PLAN FOR RESIDENTIAL SERVICE
SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-27 CUSTOMER GENERATION PRICE PLAN FOR RESIDENTIAL SERVICE Effective: April 2015 Billing Cycle AVAILABILITY: The E-27 Price Plan is subject
More informationTHE CONNECTICUT LIGHT AND POWER COMPANY dba EVERSOURCE ENERGY AND THE UNITED ILLUMINATING COMPANY
THE CONNECTICUT LIGHT AND POWER COMPANY dba EVERSOURCE ENERGY AND THE UNITED ILLUMINATING COMPANY Virtual Net Metering Application Effective November 18, 2016 This application form addresses virtual net
More informationRevised Cal. P.U.C. Sheet No E Cancelling Revised Cal. P.U.C. Sheet No E. San Francisco, California
Revised Cal. P.U.C. Sheet No. 42736-E Cancelling Revised Cal. P.U.C. Sheet No. 41884-E ELECTRIC SCHEDULE EL-1 Sheet 1 APPLICABILITY: This schedule is applicable to single-phase and polyphase residential
More informationInterconnection and Net Metering Service in Ohio
Interconnection and Net Metering Service in Ohio Partnership between National Association of Regulatory Utility Commissioners and The National Commission for Energy State Regulation of Ukraine June 20,
More informationPreface PREFACE. Comments and inquiries can be ed to:
Preface Distributed Generation PREFACE The Conditions of Service of Toronto Hydro requires to include terms and conditions of interconnecting generation facilities to the Toronto Hydro distribution system.
More informationApplication for Service Residential Subdivision / Development
Application for Service Residential Subdivision / Development Please complete this application and submit the completed form and attachments to PG&E Application for Service at P.O. Box 24047 Fresno CA
More informationCalifornia s Interconnection Rule 21 Smart Inverter & the Smart Inverter Working Group
California s Interconnection Rule 21 Smart Inverter & the Smart Inverter Working Group Jamie Ormond 415-703-1193 jo2@cpuc.ca.gov Lead Analyst - Grid Planning & Reliability - Energy Division California
More informationSmall Electrical Systems (Microgrids)
ELG4126: Microgrids Small Electrical Systems (Microgrids) A microgrid is a localized, scalable, and sustainable power grid consisting of an aggregation of electrical and thermal loads and corresponding
More informationSmall Generator Interconnection Program Interconnection Technical Requirements
General Program Information What is the purpose of the PGE Small Generator Interconnection Program? How do I initiate a distribution interconnection request for my project? The purpose of our Small Generator
More informationElectrical Guidelines for Inverter-Based Micro-Generating Facility
Electrical Guidelines for Inverter-Based Micro-Generating Facility (10 KW and Smaller) Electrical Safety Authority Contents Section Page 1 Scope 2 2 Overview 2 Types of Distributed Generation 3 Typical
More information