1 The Filling Procedure Model(s): ECO Series

2 What is needed! 1. Pump 2. 3 water hoses with metric adapters (found on the chiller pump) 3. Glycol (Premixed 37% of KKT Protect) 4. Hand tools 5. Pressure gauge 6. Chiller key 4/6/2016 Filling Procedure/ TSG Manager AF 2

3 Method of Filling What is The Push-Through Method? It is the most effective method for purging air out of the closed water loop system. The trap air will travel throughout the system and make its way back to the chiller by means of an external pump. The external pump is used to push through the chiller, IFP, and MRI system. In a form of a bypass at the chiller, a bucket is ran inline of the external pump to collect the purged glycol to be recirculated into the system. 4/6/2016 Filling Procedure/ TSG Manager AF 3

4 Connecting to the Chiller 1. Remove the pump compartment panel. 2. Connect the discharge port of the pump to the drain valve of the chiller via hose. 3. Connect inlet port of the pump to the glycol bucket via hose. 4. Connect a hose from the drain valve before the filter ball valve to the glycol bucket. 5. Verify connections 4/6/2016 Filling Procedure/ TSG Manager AF 4

5 Step 1 Remove pump compartment panel. Chiller key needed 4/6/2016 Filling Procedure/ TSG Manager AF 5

6 Step 2 Connect discharge port of the pump to the drain valve of the chiller via hose. 4/6/2016 Filling Procedure/ TSG Manager AF 6

7 Step 3 Connect inlet port of the pump to the glycol bucket via hose. 4/6/2016 Filling Procedure/ TSG Manager AF 7

8 Step 4 Connect a hose from the drain valve before the filter ball valve to the glycol bucket. 4/6/2016 Filling Procedure/ TSG Manager AF 8

9 Step 5 Verify connections 4/6/2016 Filling Procedure/ TSG Manager AF 9

10 Steps before filling 1. Verify the chiller is powered off! 2. Remove fuses from the 17F1 pump fused breaker! 3. Verify IFP is powered off! 4. Verify filter ball valve to the chiller is closed! 5. Verify all valves to the IFP are open. 6. Verify air bleeders are open. 7. Verify pipe run and check for any bypass loops installed on the contractors piping from the chiller to the IFP. (If installed, close the valve) 8. Verify chiller height from scanner. 9. Verify expansion tank nitrogen pressure. 4/6/2016 Filling Procedure/ TSG Manager AF 10

11 Step 1 Verify the chiller is powered off! 4Q1 should be on the 0 position 4/6/2016 Filling Procedure/ TSG Manager AF 11

12 Step 2 Remove fuses from the 17F1 pump fused breaker! 4/6/2016 Filling Procedure/ TSG Manager AF 12

13 Step 3 Verify IFP is powered off! 4F1 should be on the 0ff position 4/6/2016 Filling Procedure/ TSG Manager AF 13

14 Step 4 Verify filter ball valve is closed! Valve handle should be pointing upwards 4/6/2016 Filling Procedure/ TSG Manager AF 14

15 Step 5 Verify all valves to the IFP are open. 4/6/2016 Filling Procedure/ TSG Manager AF 15

16 Step 6 Verify all air bleeders are open. IFP, Chiller, and Water Loop 4/6/2016 Filling Procedure/ TSG Manager AF 16

17 Step 7 Verify pipe run and check for any bypass loops installed on the contractors piping from the chiller to the IFP. (If installed, close the valve) Ball valve handle should be positioned away from flow 4/6/2016 Filling Procedure/ TSG Manager AF 17

18 Step 8 Verify chiller height from scanner. Important factor in determining IFP static fill 4/6/2016 Filling Procedure/ TSG Manager AF 18

19 Step 9 Verify expansion tank nitrogen pressure! The reserve and operating tank should be pressurized at 0.6 Bar. Remove cap and check with a pressure gauge. 4/6/2016 Filling Procedure/ TSG Manager AF 19

20 Filling the System 1. Power on the chiller! 2. Power on the IFP! 3. Verify that the 3 way valve at the IFP is open. 4. Power on external filling pump and open the drain valves. Perform The Push-Through Method. 5. Fill the system to static on the IFP. 6. After desired pressure, close the drain valves and power off the external pump. 4/6/2016 Filling Procedure/ TSG Manager AF 20

21 Step 1 Power on the chiller! 4Q1 should be on the I position. 17F1 should have the fuses removed! Powering on the chiller will ensure the chiller sends a signal to the IFP to activate the 3 way valve to the open position. This makes it easier to purge the system while performing The Push-Through Method. 4/6/2016 Filling Procedure/ TSG Manager AF 21

22 Step 2 Power on the IFP! 4F1 should be on the ON position 4/6/2016 Filling Procedure/ TSG Manager AF 22

23 Step 3 Verify that the 3 way valve at the IFP is open. Position should be at 9 4/6/2016 Filling Procedure/ TSG Manager AF 23

24 Step 4 Power on the external filling pump and open the drain valves. Perform The Push-Through Method. Allow the external pump to run for 5-10 minutes. Inspect the amount of air pouring out the hose. If a great amount of air remains pouring out, allow more time to circulate the external pump. It is important not to fully open both drain valves while performing The Push-Through Method, glycol may over-fill the glycol bucket. 4/6/2016 Filling Procedure/ TSG Manager AF 24

25 Step 5 Fill the system to static on the IFP. Chiller lower than the IFP panel or on the same level bar, Read at the IFP Limitation: 30m below IFP Chiller higher than the IFP panel bar, Read at the IFP Limitation: 10m above IFP 4/6/2016 Filling Procedure/ TSG Manager AF 25

26 Step 6 After desired pressure, close the drain valves and power off the external pump. 4/6/2016 Filling Procedure/ TSG Manager AF 26

27 Running the Pump, Venting the Air 1. Power off the chiller! 2. Add the fuses to the 17F1 pump fused breaker! 3. Close all air vents! 4. Power on the chiller! 5. Pump will begin to run. Allow the pump to run for minutes 6. Power off the chiller! 7. Open all air vents, purge the remaining air. 8. Clean the strainers! 9. Power on the chiller! 10. Verify operation! 4/6/2016 Filling Procedure/ TSG Manager AF 27

28 Step 1 Powered off the chiller! 4Q1 should be on the 0 position 4/6/2016 Filling Procedure/ TSG Manager AF 28

29 Step 2 Add the fuses to the 17F1 pump fused breaker! 4/6/2016 Filling Procedure/ TSG Manager AF 29

30 Step 3 Close all air vents! IFP, Chiller, and Water Loop 4/6/2016 Filling Procedure/ TSG Manager AF 30

31 Step 4 Power on the chiller! 4Q1 should be on the I position 4/6/2016 Filling Procedure/ TSG Manager AF 31

32 Step 5 Pump will begin to run. Allow the pump to run for minutes. 4/6/2016 Filling Procedure/ TSG Manager AF 32

33 Step 6 Powered off the chiller! 4Q1 should be on the 0 position 4/6/2016 Filling Procedure/ TSG Manager AF 33

34 Step 7 Open all air vents, purge the remaining air. If the pressure on the manometers drops. Repeat Steps 4-6 of Filling the System 4/6/2016 Filling Procedure/ TSG Manager AF 34

35 Step 8 Clean the strainers! Clean the filter strainer before the next-to last pass. The filter ball valve allows you to clean the strainers with minimal loss of glycol. Please be sure to clean the strainers at the IFP and chiller! 4/6/2016 Filling Procedure/ TSG Manager AF 35

36 Step 9 Power on the chiller! 4Q1 should be on the I position 4/6/2016 Filling Procedure/ TSG Manager AF 36

37 Step 10 Verify Operation! Pressure at the pump: bar. IFP Pressure differential: (Day Mode) 3-4 Bar (Night Mode) 1.4 Bar 4/6/2016 Filling Procedure/ TSG Manager AF 37

Secondary Coolant 301

Secondary Coolant 301 Secondary Coolant 301 Instructor Rusty Walker Hill PHOENIX Learning Center Secondary Coolant 301 Start-Up Procedures Secondary Coolant 301 Objectives Describe the initial startup procedures for a medium

More information

Single-Valve Powerstation

Single-Valve Powerstation Single-Valve Powerstation Description Powerstation is a complete, fully assembled water tempering system, designed to provide safe water throughout commercial and institutional facilities. Powerstation

More information

GTFLOW EXTENSION MANIFOLD ASSEMBLY INSTRUCTIONS

GTFLOW EXTENSION MANIFOLD ASSEMBLY INSTRUCTIONS Page 1 of 5 Step 1: ASSEMBLE THE MAIN MANIFOLD AND MANIFOLD EXTENSION KIT First and very important step is to properly connect the main manifold and the manifold extension kit together by using the two

More information

Product Instructions. Mixing Station. Features. Specifications. Materials

Product Instructions. Mixing Station. Features. Specifications. Materials Mixing Station The Viega Mixing Station provides supply water temperature modulation when connected to a variety of heat sources such as conventional or condensing boilers, water heaters, or geothermal

More information

AIR COOLED CHILLERS WATER COOLED CHILLERS

AIR COOLED CHILLERS WATER COOLED CHILLERS AIR COOLED CHILLERS WATER COOLED CHILLERS STANDARD UNIT SPECIFICATIONS OF COMMERCIAL AIR COOLED CHILLERS General Description & Assembly Air Cooled Chillers are commercial packaged systems complete with

More information

Providing a constant temperature control and high cooling efficiency.

Providing a constant temperature control and high cooling efficiency. Recirculating Coolers (General) Providing a constant temperature control and high cooling efficiency. Performance Temperature range from 3 to 40. High cooling capacity up to 7.1kW at 20. Powerful circulating

More information

Geo-Prime Tank. Table of Contents. Installation, Operation & Maintenance Instructions AFCG1PT Revision: 7/3/14. Replacing a Pump 12

Geo-Prime Tank. Table of Contents. Installation, Operation & Maintenance Instructions AFCG1PT Revision: 7/3/14. Replacing a Pump 12 Geo-Prime Tank Installation, Operation & Maintenance Instructions AFCG1PT Revision: 7/3/14 Table of Contents General Description 3 Installation 4 Flushing and Purging 7 Initial Start-up 9 Replacing a Pump

More information

Roth NP Manifold System Installation Instructions

Roth NP Manifold System Installation Instructions Roth Industries, Inc. 268 Bellew Avenue South Watertown, NY 360 Ph. 35-755-0 Fax 35-475-0200 www.roth-usa.com info@roth-usa.com ) Product description Constructed of heavy wall extruded nickel plated brass

More information

Industrial Pro FH234 Series Filter/Separator/Warmer Installation Instructions

Industrial Pro FH234 Series Filter/Separator/Warmer Installation Instructions Filter/Separator/Warmer Installation Instructions P M O A B C G U R H I OR N E X J D K L F VENT CAP FUEL PRO COLLAR Note: The Collar/Vent Cap Wrench is only supplied with the Single, Dual and Triple units

More information

PRESSURE CONTROL VALVES SABS 198

PRESSURE CONTROL VALVES SABS 198 PRESSURE CONTROL VALVES SABS 198 1 CALVALVE DOUBLE BLOCK Pressure control combined pressure reducing valve and expansion relief valve, copper by copper compression ends. DZR alloy body. Replaceable cartridge

More information

Geo-Prime Tank U.S. Patent Number 8,544,282

Geo-Prime Tank U.S. Patent Number 8,544,282 www.geo-flo.com Geothermal and Hydronics Specialists Installation, Operating, and Maintenance Manual Part # 3487 Rev. 03JUL2014 Geo-Prime Tank U.S. Patent Number 8,544,282 Geo-Flo Products Corporation

More information

Fuel System Diagnosis

Fuel System Diagnosis Page 1 of 6 2004 Chevrolet Chevy K Silverado - 4WD Sierra, Silverado (VIN C/K) Service Manual Engine Engine Controls - 6.6L (LLY) Diagnostic Information and Procedures Document ID: 1460257 Fuel System

More information

Force Flow 100. Owners Manual. Rev 8/03. PO Box 2626, W. Hardy Rd., Spring, Texas 77383, Order , Fax

Force Flow 100. Owners Manual. Rev 8/03. PO Box 2626, W. Hardy Rd., Spring, Texas 77383, Order , Fax Force Flow 100 Owners Manual Rev 8/03 Air Motor Air Motor On/Off Bucket Blow Off Valve Discharge Hose Coupler Air Motor Base Assy Lower Pump Assy Up / Down Toggle Switch Inline Needle Regulator Air Bleed

More information

SECTION PIPING SPECIALTIES PART 1 GENERAL 1.1 SUMMARY

SECTION PIPING SPECIALTIES PART 1 GENERAL 1.1 SUMMARY SECTION 230533 - PIPING SPECIALTIES PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Pressure gages. 2. Pressure gage taps. 3. Thermometers. 4. Thermometer supports. 5. Test plugs. 6. Static pressure

More information

MOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION

MOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION MOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION Fire Pump Acceptance Inspection Date of Review / / BLD20 - Project Address: Project Name: Numbers following worksheet comments represent an NFPA

More information

Armstrong Double Duty 6 Steam Trap/Pump Combination Installation and Maintenance

Armstrong Double Duty 6 Steam Trap/Pump Combination Installation and Maintenance Armstrong Double Duty 6 Steam Trap/Pump Combination Installation and Maintenance 119 Overview Warning: This bulletin should be used by experienced personnel as a guide to the installation and maintenance

More information

Thermo-Bob 4 Installation Manual. TB4-KT4A Kit KTM 450 SX-F KTM 450 XC-F Husky FC450

Thermo-Bob 4 Installation Manual. TB4-KT4A Kit KTM 450 SX-F KTM 450 XC-F Husky FC450 Thermo-Bob 4 Installation Manual TB4-KT4A Kit 2013-2015 KTM 450 SX-F 2013-2015 KTM 450 XC-F 2013-2015 Husky FC450 Watt-man.com October 2016 Thermo-Bob 4 Installation: TB4-KT4A Kit Proper installation is

More information

Axiom Industries Ltd Wentz Avenue Saskatoon, SK S7K 5J1 Ph: (306) Fax: (306)

Axiom Industries Ltd Wentz Avenue Saskatoon, SK S7K 5J1 Ph: (306) Fax: (306) INDUSTRIES LIMITED Installation, Operation & Maintenance Instructions for MF Series Solution Feeders Axiom Industries Ltd. 2615 Wentz Avenue Saskatoon, SK S7K 5J1 Ph: (306) 651-1815 Fax: (306) 242-3373

More information

Generator, Unit Hydrogen, Seal Oil, Stator Coolant, Demin Water Plant Operations Training Huntly Power Station: Units 1-4 Assessment ID: 8014, 8012, 8009, 8015, 8016 NZQA Unit Standard: 17413 Assessment

More information

Inspection, Testing, and Maintenance Fire Pumps NFPA 25, Chapter 8 as amended by CCR, Title 19 Page 1 of 8

Inspection, Testing, and Maintenance Fire Pumps NFPA 25, Chapter 8 as amended by CCR, Title 19 Page 1 of 8 , Chapter 8 as amended by CCR, Title 19 Page 1 of 8 Address: City: Date of Pump Test: Shaft Orientation: Horizontal Vertical Annual Fire Pump Test Results Number of pumps at this location: If multiple

More information

Fluid Coil Installation, Operation and Maintenance

Fluid Coil Installation, Operation and Maintenance Bulletin FCO&I 001 REV A Fluid Coil Installation, Operation and Maintenance Monika Hewlett Packard Company [Pick the date] FLUID COIL INSTALLATION, OPERATION & MAINTENANCE GUIDELINES Fluid Coil Installation,

More information

Installation, Operation & Maintenance Instructions for MF Series Solution Feeders

Installation, Operation & Maintenance Instructions for MF Series Solution Feeders INDUSTRIES LIMITED Installation, Operation & Maintenance Instructions for MF Series Solution Feeders Startup Procedure ) Close isolation valve between feeder and system connection point 2) Fill reservoir,

More information

SAMPLE COOLER and SLUDGE TRAP OPERATION & MAINTENANCE MANUAL

SAMPLE COOLER and SLUDGE TRAP OPERATION & MAINTENANCE MANUAL SAMPLE COOLER and SLUDGE TRAP OPERATION & MAINTENANCE MANUAL PLEASE RECORD THE FOLLOWING DATA (Information is located on the product label or packing slip) Product: Model No: Serial No: Installation Date:

More information

DESIGN, OPERATION & MAINTENANCE OF L.A.C.T. UNITS

DESIGN, OPERATION & MAINTENANCE OF L.A.C.T. UNITS DESIGN, OPERATION & MAINTENANCE OF L.A.C.T. UNITS INTRODUCTION The two most common methods of measuring the volume of petroleum liquids are tank gauging and liquid metering. The problems associated with

More information

ECS Pre-Engineered Nitrogen Generator. ECS Pre-Engineered Nitrogen Generator PGEN-20 (Patent Pending) Specifications. circuit) for the 2 hp compressor

ECS Pre-Engineered Nitrogen Generator. ECS Pre-Engineered Nitrogen Generator PGEN-20 (Patent Pending) Specifications. circuit) for the 2 hp compressor ECS Pre-Engineered PGEN-20 (Patent Pending) Specifications PATENT PENDING Dimensions: Weight: Power Supply: Power Supply: Nitrogen/air connection: Drain connection: Nitrogen Gas Output (scfh): 32 (W) X

More information

Check Valves Check Valves are the simplest form of directional control valves, but they can also be used as pressure controls.

Check Valves Check Valves are the simplest form of directional control valves, but they can also be used as pressure controls. Check Valves Check Valves are the simplest form of directional control valves, but they can also be used as pressure controls. Standard Check Valve The standard check valve permits free flow in one direction

More information

SCROLL - AIR COOLED PACKAGED & SPLIT SYSTEM ICE CHILLERS

SCROLL - AIR COOLED PACKAGED & SPLIT SYSTEM ICE CHILLERS SCROLL - AIR COOLED PACKAGED & SPLIT SYSTEM ICE CHILLERS 1 to 40 Nominal Tons Rev-01 TABLE OF CONTENTS Page: Description 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Product Nomenclature Air Cooled Chiller

More information

Instruction Sheets for ECM Variable Speed Pumps. AM55 Pages 2-3 AM99 Pages 4-7

Instruction Sheets for ECM Variable Speed Pumps. AM55 Pages 2-3 AM99 Pages 4-7 Instruction Sheets for ECM Variable Speed Pumps AM55 Pages 2-3 AM99 Pages 4-7 Instruction Sheet for High Efficiency, Effective 8/11/15 Variable Speed ECM Circulators Supersedes New AM55 (Einstein) IS-AM09-618

More information

Installation instruction

Installation instruction 1 Safety Before installing the device, please read this manual carefully. Please note that the installation must be executed according to relevant technical rules. The installation must also be adapted

More information

Includes electric operated valve Pressure gauge with siphon, vacuum breaker and air vent BOILER UNITS

Includes electric operated valve Pressure gauge with siphon, vacuum breaker and air vent BOILER UNITS STEAM / HOT WATER MODELS HWG FEATURES A. O. Smith hot water generators are available for operation with steam or boiler water as the energy source. They are completely assembled with components sized,

More information

Liebert CSU3000 DISCONTINUED PRODUCT. CSI Mainframe Cooling Systems. CT(Three Module) Model 20, 30 & 37 ton Mainframe Chiller

Liebert CSU3000 DISCONTINUED PRODUCT. CSI Mainframe Cooling Systems. CT(Three Module) Model 20, 30 & 37 ton Mainframe Chiller DISCONTINUED PRODUCT CSI 15621 - Mainframe Cooling Systems 1.1 SUMMARY Liebert CSU3000 CT(Three Module) Model 20, 30 & 37 ton Mainframe Chiller GUIDE SPECIFICATIONS 1.0 GENERAL These specifications describe

More information

OIL HANDLING SYSTEMS

OIL HANDLING SYSTEMS OIL HANDLING SYSTEMS Oil is treated and stored at HI 376 A before it is pumped through a LACT unit to the Departing Oil Pipeline. The Oil Handling System is composed of the Primary Oil Handling System

More information

2013 Kia Optima L4-2.0L Turbo

2013 Kia Optima L4-2.0L Turbo 1 of 13 5/29/2016 11:34 AM 2013 Kia Optima L4-2.0L Turbo Vehicle» Engine, Cooling and Exhaust» Engine» Service and Repair» Removal and Replacement Removal CAUTION: Use fender covers to avoid damaging painted

More information

SEASONAL MAINTENANCE CHECKLISTS Johnson Controls

SEASONAL MAINTENANCE CHECKLISTS Johnson Controls SPRING CHECK LIST ABSORPTION CHILLERS Check starter and control panel. Leak test. Check hand valve diaphragms and replace as required. Check operation of purge unit. Change oil in the purge pump. Lubricate

More information

Installation, Operation & Maintenance Instructions for MF-Solar Series Solution Feeders

Installation, Operation & Maintenance Instructions for MF-Solar Series Solution Feeders INDUSTRIES LIMITED Installation, Operation & Maintenance Instructions for MF-Solar Series Solution Feeders Startup Procedure 1) Close isolation valve between feeder and system connection point 2) Fill

More information

Components for central heating

Components for central heating 01 01 Components for central heating Booster units and spare parts 18 Hydraulic separator and spare parts 21 Dirt separators - Deaerators 23 By-Pass differential valve - Air separator units 32 Filling

More information

MRC 150/300 USER MANUAL. 1 Laird Technologies

MRC 150/300 USER MANUAL. 1   Laird Technologies MRC 150/300 USER MANUAL 1 www.lairdtech.com Laird Technologies THR-UM-MRC150-300 0912 Americas: +1 888.246.9050 Europe: +44.1342.315044 Asia: +886.3.312.9292 clv.customerpos@lairdtech.com 2 www.lairdtech.com

More information

Air Cooled Water Chillers. CLS 182 to to 150 kw. Technical Brochure TM CLS-W.3GB Date : October 2004 Supersedes : TM CLS-W.2GB/07.

Air Cooled Water Chillers. CLS 182 to to 150 kw. Technical Brochure TM CLS-W.3GB Date : October 2004 Supersedes : TM CLS-W.2GB/07. Air Cooled Water Chillers CLS 182 to 602 41 to 150 kw Technical Brochure TM CLS-W.3GB Date : October 2004 Supersedes : TM CLS-W.2GB/07.04 R Specifications General characteristics The CLS air cooled water

More information

OFX7 Operating Maintenance and Troubleshooting Manual L-4219

OFX7 Operating Maintenance and Troubleshooting Manual L-4219 OFX7 Operating Maintenance and Troubleshooting Manual L-4219 L-2999 Created 9.2012 User Manual OFX7 L-4219 - Table of Contents - Preface. 4 Customer Service. 4 Modifications to the Product 4 Warranty.

More information

LACT MEASUREMENT. Total Head = Or PSI = S.G. 2.31

LACT MEASUREMENT. Total Head = Or PSI = S.G. 2.31 LACT MEASUREMENT Prepared By: Ken A. Steward. P.E. Linco-Electromatic, Inc. 4580 West Wall Street Midland, Texas 79703 The Operation of L.A.C.T. Units The simplest approach to the understanding of the

More information

Proper Propane Pump Installation

Proper Propane Pump Installation Spring 2014 Proper Propane Pump Installation If installed correctly, a propane pump can operate many years with few or no problems. So often shortcuts are taken. Practical thinking goes out the window

More information

8000 Pump Maintenance

8000 Pump Maintenance 8000 Pump Maintenance Perform Forward System Purge Before Performing Pump Maintenance Pump Must Be Removed From Enclosure To Service. Use Repair Kit P/N D3-0102 8000 Pump Removed From Enclosure Special

More information

Technical Information

Technical Information Technical Information Installation, Operation, Installation, Operation and Maintenance and Maintenance Manual Manual Balston Series "SR" Steam Filters USFDA, USDA, and 3A Compliance Balston SR Steam Filters

More information

CHILLER START UP PROCEDURE FORM DOC. N (DOC.N BELOW TO BE RETURN TO AERMEC)

CHILLER START UP PROCEDURE FORM DOC. N (DOC.N BELOW TO BE RETURN TO AERMEC) CHILLER START UP PROCEDURE FORM DOC. N 061103 (DOC.N 071103 BELOW TO BE RETURN TO AERMEC) 1. Preliminary Operation WARNING: The following operation must be done without the power supply (unit with the

More information

Series 1 Pump. Series 2 Pump. Series 3 Pump

Series 1 Pump. Series 2 Pump. Series 3 Pump Series 1 Pump PROCON's Series 1 pumps have the protection of an integral inlet strainer. The standard strainer is a 100 mesh wire screen. It traps particles that can cause serious damage to the pump. The

More information

1995 Chevrolet S10 Pickup - 2WD

1995 Chevrolet S10 Pickup - 2WD 1995 Chevrolet S10 Pickup - 2WD Submodel: Engine Type: Liters: Fuel Delivery: Fuel: Draining Procedure Caution: Gasoline or gasoline vapors are highly flammable. A fire could occur if an ignition source

More information

INSTRUCTION MANUAL. Leakfinder. Model No. 625-WV609. BMW Smoke Tester. Diagnostic Smoke Vapor. with UltraTraceUV Dye Solution

INSTRUCTION MANUAL. Leakfinder. Model No. 625-WV609. BMW Smoke Tester. Diagnostic Smoke Vapor. with UltraTraceUV Dye Solution INSTRUCTION MANUAL Leakfinder Model No. 625-WV609 BMW Smoke Tester Diagnostic Smoke Vapor with UltraTraceUV Dye Solution Leak Detection System for the Professional Technician USA Canada Patents 6,392,227

More information

Pilot Oil Supply Circuit

Pilot Oil Supply Circuit Pilot Oil Supply Circuit Introduction Pilot system oil output from pilot pump (42) has the following three main functions: 1. To control main pump output. 2. To provide easier operation of control levers.

More information

H:\SC218\17_Ersatzteile\Spare Parts SC 218.doc

H:\SC218\17_Ersatzteile\Spare Parts SC 218.doc page 1 / 14 Version: V2016-07 2,2a 3 4 5 6 7 8 13 Air bleeder 9 12 Flow switch 1 10 11,11a page 2 / 14 Version: V2016-07 description electrical item 1 ball valve (drain and fillin valve red handle bar)

More information

NeoProducts, LLC New Orleans, LA USA Ph:

NeoProducts, LLC New Orleans, LA USA Ph: NeoHybridPositiveDisplacementBailer Systems General Preparation & Run-in Procedures (NeoHybridPDB Systems) Document # ********************************************************************************************

More information

CHAPTER 79 ENGINE OIL SYSTEM

CHAPTER 79 ENGINE OIL SYSTEM Section Title CHAPTER 79 ENGINE OIL SYSTEM 79-00 Description............................................... 79.1 79-10 Scroll and Fanwheel Assemblies................................ 79.3 79-11 Fanwheel-to-Inlet

More information

Instructions for Installation, Operation, Care and Maintenance

Instructions for Installation, Operation, Care and Maintenance Bulletin 407 Rev. T Model E Alarm Check Valve Bulletin 407 Rev. T Instructions for Installation, Operation, Care and Maintenance 4 (100 mm), 6 (150 mm), 8 (200 mm) Sizes With Model E3 Trim Listed by Underwriters

More information

Industrial Pro FH239 Series Filter/Separator/Warmer Installation Instructions

Industrial Pro FH239 Series Filter/Separator/Warmer Installation Instructions Industrial Pro FH239 Series Filter/Separator/Warmer Installation Instructions K L Cover Industrial Pro Single Short H I W A B D F P C E J Bottom Bowl G Vent Cap Filter Element (includes part C) I R S T

More information

HIGH PERFORMANCE HEAT EXCHANGER INSTALLATION INSTRUCTIONS PART NUMBER D A APPLICATION: F80 M F82/F83 M4

HIGH PERFORMANCE HEAT EXCHANGER INSTALLATION INSTRUCTIONS PART NUMBER D A APPLICATION: F80 M F82/F83 M4 HIGH PERFORMANCE HEAT EXCHANGER INSTALLATION INSTRUCTIONS PART NUMBER D780-0001A APPLICATION: 2015-17 F80 M3 2015-17 F82/F83 M4 Congratulations for being selective enough to use a Dinan High Performance

More information

PRODUCT: SERIES DESCRIPTION PAGE TRAPS

PRODUCT: SERIES DESCRIPTION PAGE TRAPS PRICE SHEET HS-113 Effective January 14, 2013 Replaces Price Sheet HS-112 Dated January 30, 2012 These prices are subject to change without notice. All shipments will be billed at the price in effect at

More information

Troubleshooting Guide

Troubleshooting Guide Troubleshooting Guide This guide contains information for identifying and correcting issues that may arise. Applicable Models: i200 i200p i250 i250p i200x i201x i250x i251x iq251 iq251d iq751 iq1001 iq1501

More information

WARCO CHEMAG SERIES GH FILTERS

WARCO CHEMAG SERIES GH FILTERS WARCO CHEMAG SERIES GH FILTERS High Performance Pleated & Bag Type Filtration Systems INSTALLATION, OPERATION, AND MAINTENANCE INSTRUCTIONS Thank you for your purchase of a WARCO Series GH Filtration System.

More information

Exercise 3-1. Basic Hydraulic Circuit EXERCISE OBJECTIVE DISCUSSION OUTLINE DISCUSSION. Complete hydraulic circuit

Exercise 3-1. Basic Hydraulic Circuit EXERCISE OBJECTIVE DISCUSSION OUTLINE DISCUSSION. Complete hydraulic circuit Exercise 3-1 Basic Hydraulic Circuit EXERCISE OBJECTIVE When you have completed this exercise, you will be familiar with the hydraulic schematic and components of the nacelle trainer. You will identify

More information

Ph: (07) Fax: (07) Pump Manual

Ph: (07) Fax: (07) Pump Manual sales@scintex.com.au www.scintex.com.au Ph: (07) 3137 0135 Fax: (07) 3041 0541 Pump Manual 12V 75LPM Vane Pump & Vane Pump Station SPEP12V75 & SP12VFS75 SPEP12V75 SP12VFS75 Parts List No. Part Name QTY

More information

Optional Pump Packages for

Optional Pump Packages for Installation, Operating and Maintenance Manual IOMM AGSD Pump Pkg Group: Chiller Part Number: 331376801 Part Number: 331376901 Date: June 2010 Supersedes: October 2008 Optional Pump Packages for AGS 140D

More information

Fuel Pro Series Filter/Separator/Warmer Installation Instructions

Fuel Pro Series Filter/Separator/Warmer Installation Instructions Fuel Pro Series Filter/Separator/Warmer Installation Instructions Standard and Plus Series A B C D Vent Cap and Assembly (part no SP1053) Includes Vent Cap and Vent Cap Seal Part Description Part Number

More information

Fuel Pro FH230 Series Filter/Separator/Warmer Installation Instructions

Fuel Pro FH230 Series Filter/Separator/Warmer Installation Instructions Fuel Pro FH230 Series Filter/Separator/Warmer Installation Instructions A B C Vent Cap and Assembly (part no. 3944440 S) Includes Vent Cap and Vent Cap Seal Parts List Part Description Part Number A Collar

More information

Installation Manual FTI-10A & FTI-20A SINGLE TANK. Automated Fuel Maintenance System FUEL TECHNOLOGIES INTERNATIONAL

Installation Manual FTI-10A & FTI-20A SINGLE TANK. Automated Fuel Maintenance System FUEL TECHNOLOGIES INTERNATIONAL Installation Manual Automated Fuel Maintenance System FTI-10A & FTI-20A SINGLE TANK FUEL TECHNOLOGIES INTERNATIONAL 05/01/2016 Rev A Fuel Technologies FTI-10A & FTI-20A Single Tank Installation Manual

More information

KJ4000LW Operating Instructions & Parts Manual NSN

KJ4000LW Operating Instructions & Parts Manual NSN KJ4000LW Operating Instructions & Parts Manual NSN Mandus Group Ltd. KJ4000LW Operators Manual Date: 1 Oct. 2004 TABLE OF CONTENTS General Safety Instructions...Page 1 Operator Instructions...Page 2 KJ4000LW

More information

ENGINE COOLING SECTION GENERAL DESCRIPTION / 1 ENGINE COOLING. Figure 1 - Cooling System Flow

ENGINE COOLING SECTION GENERAL DESCRIPTION / 1 ENGINE COOLING. Figure 1 - Cooling System Flow SECTION 09-302.03 09-302.03/ 1 2006JA26 1. COOLANT INLET FROM RADIATOR 2. WATER PUMP SUCTION 3. COOLANT FILTER INLET 4. COOLANT FILTER OUTLET 5. COOLANT SUPPLY TO CYLINDER HEAD 6. COOLANT RETURN FROM CYLINDER

More information

DESCRIPTION AND OPERATION

DESCRIPTION AND OPERATION Page 1 of 10 DESCRIPTION AND OPERATION AIR DELIVERY DESCRIPTION AND OPERATION The air delivery description and operation is divided into five areas: HVAC Control Components Air Speed Air Delivery Recirculation

More information

Instruction Manual For MrPEX Composite Radiant Manifold

Instruction Manual For MrPEX Composite Radiant Manifold Instruction Manual For MrPEX Composite Radiant Manifold For Radiant Floor Heating and Cooling Applications Read manual before use! Observe all safety information! Keep manual for future use! A Division

More information

BLACKMER BYPASS VALVES

BLACKMER BYPASS VALVES BLACKMER BYPASS VALVES INSTALLATION OPERATION AND MAINTENANCE INSTRUCTIONS EBSRAY MODEL: RV18 RV18CBS2, RV18CBS3, RV18VRS10, RV18VRS14, RV18VRS19 967020 INSTRUCTIONS NO. 551-E00 Section Effective Replaces

More information

OPERATION AND INSTALLATION

OPERATION AND INSTALLATION OPERATION AND INSTALLATION RESIDENTIAL SOLAR PUMP STATION» SE FLOWSTAR PUMP STATION Table of Contents 1 For your safety 1.1 About this manual 1.2 Designated use 1.3 Qualification of the installer 1.4 Hand-over

More information

SECTION LAUNDRY WASHER-EXTRACTOR, 100 LB. (45.4 KG) CAPACITY

SECTION LAUNDRY WASHER-EXTRACTOR, 100 LB. (45.4 KG) CAPACITY SECTION 11110 LAUNDRY WASHER-EXTRACTOR, 100 LB. (45.4 KG) CAPACITY PART 1 GENERAL 1.01 SECTION INCLUDES: A. Automatic laundry washer-extractor for processing water-washed linen items 1.02 SYSTEM DESCRIPTION

More information

Sinking of Nordhavn 75 hull #2

Sinking of Nordhavn 75 hull #2 Sinking of Nordhavn 75 hull #2 The details of the sinking accident in Cabo San Lucas are pretty clear at this stage and the problem was completely associated with the installation of a Tuna Tube bait system

More information

Introduction... 2 Water/Foam Solution Distribution Components... 3, 4 Lubrication:

Introduction... 2 Water/Foam Solution Distribution Components... 3, 4 Lubrication: Eclipse Compressed Air System with Advantus Installation Instructions Form No. F-1031 Section 3025 Issue Date Rev. Date 10/05/07 4/3/17 Table of Contents Introduction......................................

More information

.2 Section Waste Management and Disposal..5 Section Thermometers and Pressure Gauges Piping Systems.

.2 Section Waste Management and Disposal..5 Section Thermometers and Pressure Gauges Piping Systems. Issued 2005/06/01 Section 15440 Plumbing Pumps Page 1 of 9 PART 1 GENERAL 1.1 RELATED SECTIONS.1 Section 01330 Submittal Procedures..2 Section 01355 Waste Management and Disposal..3 Section 01780 Closeout

More information

Low Pressure Transfer Systems

Low Pressure Transfer Systems Chapter 7b Low Pressure Transfer Systems Automotive Diesel Technology Understanding & Servicing Contemporary Clean Diesel Technology Gus Wright Low Pressure Transfer Layout of a low-pressure fuel transfer

More information

SUBMITTAL COVER SHEET

SUBMITTAL COVER SHEET SUBMITTAL COVER SHEET PROJECT NAME LOCATION ARCHITECT ENGINEER CONTRACTOR SUBMITTED BY DATE UNIT SUMMARY Quantity Unit Designation Model No. Total Cooling Sensible Cooling Air Ent. Evaporator Air Lvg.

More information

SECTION GENERAL-DUTY VALVES FOR PLUMBING PIPING

SECTION GENERAL-DUTY VALVES FOR PLUMBING PIPING SECTION 22 05 23 PART 1 - GENERAL 1.1 SUMMARY A. Work Included: 1. Valves, General 2. Gate Valves 3. Balancing Valves 4. Ball Valves 5. Swing Check Valves 6. Backflow Prevention Assemblies 7. Pressure

More information

CA-NV AWWA 2013 Fall Conference. Chemical Metering Pump, Accessories and Systems. By Richard Hopkins Hopkins Technical Products, Inc

CA-NV AWWA 2013 Fall Conference. Chemical Metering Pump, Accessories and Systems. By Richard Hopkins Hopkins Technical Products, Inc CA-NV AWWA 2013 Fall Conference Chemical Metering Pump, Accessories and Systems. By Richard Hopkins Hopkins Technical Products, Inc Mathematics Equation #: 1 for Chlorine Flow(MGD) x Dosage(mg/l) x 3.785/gal

More information

This catalog contains the following geothermal accessory products and specification guides:

This catalog contains the following geothermal accessory products and specification guides: f o r r e s i d e n t i a l s y s t e m s Geothermal systems offer an effective way to cut utility costs while ensuring comfort. Heat Controller s line includes two stage and single stage geothermal heat

More information

M-8100EP. Installation Guide ENGINEERED PLASTIC MANIFOLD SERIES. Introduction. A. Assemble Manifold Components

M-8100EP. Installation Guide ENGINEERED PLASTIC MANIFOLD SERIES. Introduction. A. Assemble Manifold Components Introduction The Pro Manifolds with Integrated adaptor are designed for use in Hydronic radiant panel heating and cooling applications. They are available in various sizes, configurations, and options

More information

F-4600 INLINE ULTRASONIC FLOW METER Installation and Operation Guide

F-4600 INLINE ULTRASONIC FLOW METER Installation and Operation Guide F-4600 INLINE ULTRASONIC FLOW METER Installation and Operation Guide 11451 Belcher Road South, Largo, FL 33773 USA Tel +1 (727) 447-6140 Fax +1 (727) 442-5699 1054-7 / 34405 www.onicon.com sales@onicon.com

More information

Hope Creek Variable Frequency Drive

Hope Creek Variable Frequency Drive Hope Creek Variable Frequency Drive 2018 Power Plant Simulation Conference Houston, TX January 14-18, 2018 Hope Creek Variable Frequency Drive Simulation John Stone Senior Engineer - CORYS Presentation

More information

NMSU FIRE DEPARTMENT FIRE PUMP ACCEPTANCE TEST

NMSU FIRE DEPARTMENT FIRE PUMP ACCEPTANCE TEST Date Documents Submitted: Log No.: File No.: Plan Examiner: Permit No.: Property Information Building Name: Building Address: Building Manager's Name: Building Manager's Phone: Fax: System Designer/Contractor

More information

COMPACT GLYCOL FEED SYSTEMS OPERATION & MAINTENANCE MANUAL

COMPACT GLYCOL FEED SYSTEMS OPERATION & MAINTENANCE MANUAL COMPACT GLYCOL FEED SYSTEMS OPERATION & MAINTENANCE MANUAL Model Number: Service: Serial Number: Installation Date: Installation Location / Application: PLEASE RECORD THE FOLLOWING DATA (Information is

More information

EcoVentTM Recirculator Installation Manual SM-337

EcoVentTM Recirculator Installation Manual SM-337 EcoVentTM Recirculator Installation Manual SM- Fleetguard All Rights Reserved Printed in U.S.A. LT0 /0 Q9 Maintenance Instructions Whenever the manometer shows a reading of." H O positive pressure, you

More information

SBH / SBV Sales Guide BLOWER-COILS HORIZONTAL AND VERTICAL

SBH / SBV Sales Guide BLOWER-COILS HORIZONTAL AND VERTICAL SO TOUGH, WE GUARANTEE IT. SBH / SBV Sales Guide BLOWER-COILS HORIZONTAL AND VERTICAL SBH SBV www.superiorrex.com SO TOUGH, WE GUARANTEE IT! www.superiorrex.com SBH / SBV Series: CONSTRUCTION FEATURES

More information

Submittal 30 [762] 36 [914] 40 [1016] 50 [1270] 60 [1524] 70 [1778]

Submittal 30 [762] 36 [914] 40 [1016] 50 [1270] 60 [1524] 70 [1778] FCU-THBP-1.0 08-22-18 THBP Horizontal Low Profile Plenum Return Top View (Drain Pan Omitted) Bottom View Front View Left hand unit shown. All dimensions are inches [millimeters]. Side View Unit Size A

More information

INSTALLATION AND COMMISSIONING MANUAL CONTENTS. Function. Important Product range Technical specifications

INSTALLATION AND COMMISSIONING MANUAL CONTENTS. Function. Important Product range Technical specifications 28237 www.caleffi.com Circulation units for solar thermal systems Copyright 204 Caleffi 278-279 series INSTALLATION AND COMMISSIONING MANUAL CONTENTS Function Important Product range Technical specifications

More information

POWER GENERATION SYSTEMS

POWER GENERATION SYSTEMS POWER GENERATION SYSTEMS The Power Generation Systems on HI 595 CF&D consist of three Waukesha 7042 gas driven generators and two diesel driven generators. Two of the three Gas Generators must run to provide

More information

LMP series

LMP series Low & Medium Pressure fi lters LMP 95-95-95 series Maximum working pressure up to.5 MPa (5 bar) - Flow rate up to 000 l/min 7 Low & Medium Pressure filters Introduction FILTER SIZG DEX CALCULATION CORRECTIVE

More information

Installation, commissioning and servicing instructions

Installation, commissioning and servicing instructions CALEFFI www.caleffi.com NA88156 GeoCal geothermal manifolds Installation, commissioning and servicing instructions 110 Series Function The GeoCal pre-assembled manifold for ground-source geothmal loops

More information

Engine Cooling. Cooling System Component Layout. https://myvpn.dealerconnection.com/extdealerlrprod/xml/parsexml.jsp,danainfo=gtr.fran...

Engine Cooling. Cooling System Component Layout. https://myvpn.dealerconnection.com/extdealerlrprod/xml/parsexml.jsp,danainfo=gtr.fran... Page 1 of 5 Published : Apr 28, 2004 Engine Cooling Cooling System Component Layout Item Part Number Description 1 - Heater hose, inlet and outlet 2 - Heater hose, inlet and outlet for vehicles with rear

More information

RESOL SBS 1000 * * Connection Operation

RESOL SBS 1000 * * Connection Operation RESOL SBS 1000 Connection Operation FlowCon SBS 1000 A www.resol.de *48003820* 48003820 Thank you for buying this RESOL product. Please read this manual carefully to get the best performance from this

More information

GPM Hydraulic Consulting, Inc. P.O. Box 689. Social Circle, GA Hydraulic Consulting, Inc

GPM Hydraulic Consulting, Inc. P.O. Box 689. Social Circle, GA Hydraulic Consulting, Inc Hydraulic Consulting, Inc This special promotional CD is to demonstrate how your hydraulic troubleshooting manual can be ordered as an Adobe Acrobat ebook. It can be installed on any computer with the

More information

Recirculating Coolers

Recirculating Coolers SELECTION GUIDE (General Models) (Low Temp. Models) (Advanced Low Temp. Models) (High Temp. Models) General Models Low Temp. Models Advanced Low Temp. Models High Temp. Models HX-20 Working Cooling Temp.

More information

Parts List. Stackable Crescent Cuber. Models KM-1601MRJ/3. hoshizakiamerica.com

Parts List. Stackable Crescent Cuber. Models KM-1601MRJ/3. hoshizakiamerica.com Parts List Stackable Crescent Cuber Models KM-1601MRJ/3 hoshizakiamerica.com Number: 71394 Issued: 11-1-2017 CONTENTS Auxiliary Codes... 3 Note About Ordering Parts... 3 A. Main Assembly & Refrigeration

More information

Copeland Screw TM Compressors

Copeland Screw TM Compressors Copeland Screw TM Compressors Mechanical Guidelines for SHL & SHM Models using ESC-201 Control System Contents: Start-Up Procedure Operating Specifications Maintenance Trouble Shooting Guidelines Start-up

More information

WEG Cooler. Table of Contents. Introduction and General Description. 3. Operational Specifications.. 4. Dimensional Specifications.

WEG Cooler. Table of Contents. Introduction and General Description. 3. Operational Specifications.. 4. Dimensional Specifications. WEG Cooler Owner s Manual Table of Contents Introduction and General Description. 3 Operational Specifications.. 4 Dimensional Specifications. 5 Component and Connector ID s and Descriptions.. 6-8 Installation

More information

Mild Steel Dosing Pots

Mild Steel Dosing Pots Mild Steel Dosing Pots Data Sheet Features Introduction Materials of Construction Most heating and chilled water systems require chemical dosing and the BOSS range of Dosing Pots provides a controlled

More information

PACKAGED LIQUID CHILLER 6. HUMIDIFIER SECTIONS. C Member. Liquid Chiller. nowlc And noalc Series

PACKAGED LIQUID CHILLER 6. HUMIDIFIER SECTIONS. C Member. Liquid Chiller. nowlc And noalc Series 6. HUMIDIFIER SECTIONS Liquid Chiller nowlc And noalc Series C Member 1 Features and Benefits OMRAN cold generator reciprocating Liquid chiller are designed and built to provide reliable,efficient performance

More information

SeasonPak Packaged Air-Cooled Water Chiller

SeasonPak Packaged Air-Cooled Water Chiller Installation Manual IM 676 Group: Chiller Part Number: 594920Y Date: July 1996 Supersedes: None SeasonPak Packaged Air-Cooled Water Chiller Models ALR 032E Through 185E 1996 McQuay International Table

More information