Alaska Research CubeSat 1 Separation Switch Sub-Assembly Failure Analysis

Size: px
Start display at page:

Download "Alaska Research CubeSat 1 Separation Switch Sub-Assembly Failure Analysis"

Transcription

1 Alaska Research CubeSat 1 Separation Switch Sub-Assembly Failure Analysis Matt Pacheco Author/Engineer Signature of Approval Date Denise Thorsen Director Signature of Approval Date Alaska Space Grant Program University of Alaska Fairbanks Duckering Hall Tanana Loop Fairbanks, Alaska 99775

2 Revision History Rev Level Description Author Date Approval 1 Initial draft M. Pacheco 3/25/2016 1

3 TBD/TBR Item No. Location Summary Author Due Date 2

4 Table of Contents 1. Introduction Purpose Scope Document Organization Reference Documents Internal Documents Industrial Documents Pre-Launch Testing and Results /9/2015: Vibe Test /10/2015: Vibe Test /11/2015: Vibe Test /24/2015: Mission Readiness Review /12/2015: Vibe Test Post-Launch Testing and Results /28/2016: Vibe Test /5/2016: Vibe Test /25/2016: Vibe Test Analysis

5 Table of Figures Figure 1: ARC1 satellite with anodization removed from one rail due during vibration test Figure 2: Separation switch subassembly in the stowed position... 8 Figure 3: Separation switch subassembly in the deployed position... 8 Figure 4: Photo showing lit LED while in Test Pod Figure 5: Photo showing missing roller lever on separation switch... 7 Figure 6: Revised separation switch sub-assembly design Figure 7: Photos after vibration test showing spring plunger not released Figure 8: Photo showing LED switch indicator on during vibration testing Figure 9: Photo showing the released spring plunger after vibration test Figure 10: Photo and Solid Works drawing of spring plunger engaging the separation switch leaf spring Figure 11: Modeled spring plunger (a) depressed, (b) released, (c) exploded view

6 1. Introduction 1.1 Purpose The ARC1 satellite was launched October 8, 2015 and failed to transmit its beacon. This document analyzes one possible failure mode that could have prevented the ARC1 satellite from turning on. 1.2 Scope Included in this document is a description of the vibration tests required by the Launch Service Provider (LSP) that was performed prior to launch on the complete ARC1 satellite and the actions that resulted from those tests. Also included in this document is a description of the vibration tests performed on the structure subassembly after launch and an analysis of the failure that was observed. 1.3 Document Organization Section 1 Specifies the purpose and content of this document. Section 2 Lists reference documents. Section 3 Provides an overview of the testing that occurred prior to launch and the actions that resulted due to the results of that testing. Section 4 Provides a description of the testing that occurred after launch and the analysis of the failure that was observed. Section 5 Provides an analysis of the cause of the failure. 2. Reference Documents The following documents listed here were used as a reference for this document. Please refer to them for detailed information not included herein: 2.1 Internal Documents 1 ARC1-SMT-MNL- VibrationTestingProcedure-R0.pdf Required procedure for vibration qualification. 2 ARC1MRR-R1.pptx Mission Readiness Review 2/24/2015 PowerPoint slides 2.2 Industrial Documents 3 test_pod_user_guide.pdf Test Pod User s Guide version 6 4 1U_UsersGuide_Rev8.3.pdf 1U TestPOD User s Guide 5 VID_ _ mp4 Video of vibration test showing LED flicker indicating switch chatter. 5

7 3. Pre-Launch Testing and Results All vibration tests are performed according to test procedure [1] with the satellite installed in a Test Pod provided by the Launch Service Provider (LSP). The Test Pod User Guide [3, 4] describes the satellite integration procedure /9/2015: Vibe Test 1 Test Pod User s Guide version 6 [3] was used to integrate the satellite with the Test Pod. During vibration the satellite was observed to be rattling around pretty good in the Test Pod. The test was immediately halted. On closer inspection it was determined that the compression plate on the Test Pod was not properly set. When removed from the Test Pod, the satellite rails were seen to have been gouged in vibration, removing the anodization on one of the rails (see Figure 1). Figure 1: ARC1 satellite with anodization removed from one rail due during vibration test. Results and Actions: Test Pod compression plate not properly set Discussions with the LSP led to the discovery that an incorrect version of the Test Pod User s Guide [3] was being used. An updated version of the Test Pod User s Guide [4] was acquired. Damage to satellite rails Photos were provided to LSP for inspection and were given the approval to continue. 6

8 3.2 2/10/2015: Vibe Test 2 Test Pod User s Guide revision 8.3 [4] was used to integrate the satellite with the Test Pod. This test was halted after the X-axis vibration when a lit LED was observed through the USB port hole indicating that the satellite had turned on in the Test Pod (see Figure 2). Inspection of the satellite showed that the roller lever of the Omron J-V7 switch broke off (see Figure 3). Figure 2: Photo showing lit LED while in Test Pod. Figure 3: Photo showing missing roller lever on separation switch 7

9 The separation switch sub-assembly is shown in Figure 4 and Figure 5. This sub-assembly consists of a rod which runs down through the tab in the X+Y- rail and connects to an aluminum block. The aluminum block is angled on one corner and pushes against the Omron J-V7 switch roller lever when engaged. The aluminum block is held in place by a captive panel screw and is pushed upwards by a spring. Figure 4: Separation switch subassembly in the stowed position Rod Aluminum block Spring Captive Panel Screw OMRON switch Figure 5: Separation switch subassembly in the deployed position 8

10 Results and Actions: Broken Omron J-V7 separation switch roller lever Visual inspection of the switch showed that the roller lever was attached to the switch housing with a spot weld. This spot weld appears to be fragile in vibe. The broken switch was replaced and epoxy added at the point of connection to support the spot weld /11/2015: Vibe Test 3 Test Pod User s Guide revision 8.3 [4] was used in this test to integrate the satellite with the Test Pod. This test proceeded to completion with no further structural failures /24/2015: Mission Readiness Review Although ARC1 technically passed the required vibration testing on February 11, the team continued to be concerned about the reliability of the existing separation switch sub-assembly. Specifically, the epoxy used to support the roller lever spot weld also made the lever pivot stiff which caused the lever not to reliably release. The mechanical engineering team explored alternate designs that could be implemented quickly and proposed retrofit actions prior to the Mission Readiness Review. The retrofit was approved (2/20/2016) prior to the Mission Readiness Review with a required re-vibe of the satellite. The retrofit included replacing the current Omron switch with a wraparound leaf spring eliminating the spot weld. Additionally, the previous separation switch plunger mechanism was replaced with a purchased retractable spring plunger. The new plunger required that the switch also be moved. The team believed that with fewer parts, a shorter push rod, and eliminating the roller, would result in a more robust and reliable separation switch sub-assembly (see Figure 6). Figure 6: Revised separation switch sub-assembly design. 9

11 3.5 3/12/2015: Vibe Test 4 During the Mission Readiness Review, and for the two weeks after, the proposed retrofit was created. This required building a new mounting block for the switch, drilling and taping the rail to accept the new spring plunger, modifying the spring plunger to fit the rail, and installing all new components. On March 11 the Day In The Life test was accomplished and on March 12 the final vibration test was performed and passed. At this time, a failure was not suspected because the structural integrity of the satellite was intact. Upon removing the satellite from the Test Pod we noticed that the spring plunger did not immediately release. After a slight disturbance the spring plunger released. At the time it was believed that thermal cycling would release the spring plunger should it become stuck again during launch. This issue was not further investigated. On March 19 the delta MRR was held via teleconference and on March 25 the satellite was delivered. 4. Post-Launch Testing and Results The ARC1 satellite was delivered to the Launch Service Provider on March 25, 2015 and launched on October 8, 2015, 6.5 months later. During this time there was no access to the satellite. After the launch the satellite did not start to beacon. Immediately, investigations into possible failure scenarios were started. Given the difficulties with the separation switch subassembly during pre-launch testing, a second structure assembly with the separation switch subassembly was built in order to perform more detailed tests. Although our complete board stack was not included in these tests, a microcontroller board was attached to the separation switch to measure the degree of chatter on the switch /28/2016: Vibe Test 5 A modified version of the vibration tests, including only the random vibe tests, was performed. The Test Pod access ports were not covered which allowed monitoring a LED connected to a microcontroller board and the separation switch sub-assembly. The switch chatter test was inconclusive since there was enough switching noise with the table idle to make the microcontroller think that the switch was being switched. When the structure assembly was removed from the Test Pod it was observed that the separation switch plunger had not released (see Figure 7). However with a slight bump the separation plunger did release /5/2016: Vibe Test 6 The purpose of this test was to monitor when the spring plunger releases after being removed from the Test Pod. A microcontroller board, powered by a 9 V battery, was used to mark the time that the separation switch closes. The separation switch powers a MOSFET used to signal the MSP430 and a LED was used for visual indication. The intent of the LED was for additional visual verification when the switch pops up after vibration. The expectation was that it would be off during the vibration test. During the X-axis vibration test it was observed that the LED was turning on (see Figure 8). The LED was not visible during the Y-axis test because of the 10

12 mounting brackets. When running the Z-axis profile the LED did not turn on. Additionally, a video of the flickering LED was captured [5]. As with the previous test the spring plunger did not release after being removed from the Test Pod. The structure assembly was placed on a protected shelf for over a week. The spring plunger did not release during this time. Figure 7: Photos after vibration test showing spring plunger not released. Figure 8: Photo showing LED switch indicator on during vibration testing. 11

13 4.3 2/25/2016: Vibe Test 7 During this test the structure assembly without the separation switch leaf spring was vibrated. When the satellite was removed from the Test Pod it was observed that the spring plunger had released (see Figure 9). Figure 9: Photo showing the released spring plunger after vibration test. 5. Analysis The Post-Launch testing showed that the spring plunger did not reliably release after vibration when the separation switch was present. It did reliably release when the separation switch leaf spring was not present. Figure 6 shows the spring plunger in the released state. When the spring plunger is pushed down, it engages the leaf spring of the Omron switch, bending it down as shown in Figure 10. The bent leaf spring puts a horizontal force on the spring plunger causing it to tilt slightly inward at the top. A close examination of Figure 7 shows that the spring plunger appears to be jammed on the inside corner of the housing confirming that the force of the leaf spring causes the spring plunger to tilt inward at the top. It is believed that the force of the leaf spring on the spring plunger causes the spring plunger to strike the inside of the spring plunger housing while under vibration. This results in the spring plunger getting stuck. One suggestion is that the vibration creates a friction weld between the plunger and the housing. At this point the most reliable path forward is to redesign the separation switch assembly to remove the adverse lateral force of the leaf spring. 12

14 Figure 10: Photo and Solid Works drawing of spring plunger engaging the separation switch leaf spring. Figure 11: Modeled spring plunger (a) depressed, (b) released, (c) exploded view 13

Installation Instructions

Installation Instructions Instructions Created by an: Samurai Rear Diamond Plate Corners (Pre-bent) (SKU# SEB-RDP) Installation Instructions CAUTION: Safety glasses should be worn at all times when working with vehicles and related

More information

Fox CubeSat Mechanical Design Robert Davis KF4KSS and Steve Christie

Fox CubeSat Mechanical Design Robert Davis KF4KSS and Steve Christie Fox CubeSat Mechanical Design Robert Davis KF4KSS and Steve Christie Abstract Fox 1 will be AMSAT s first 1U CubeSat, 100x100x100 mm (about 4x4x4 inches) with a weight of up to 1.33 kg (about 2.9 pounds)

More information

Success of the H-IIB Launch Vehicle (Test Flight No. 1)

Success of the H-IIB Launch Vehicle (Test Flight No. 1) 53 Success of the H-IIB Launch Vehicle (Test Flight No. 1) TAKASHI MAEMURA *1 KOKI NIMURA *2 TOMOHIKO GOTO *3 ATSUTOSHI TAMURA *4 TOMIHISA NAKAMURA *5 MAKOTO ARITA *6 The H-IIB launch vehicle carrying

More information

Alliance Towel Dispensing System. Operation Manual

Alliance Towel Dispensing System. Operation Manual Alliance Towel Dispensing System Operation Manual Alliance Towel Dispensing System Table of Contents Safety Information... page 2 Mounting Instructions... page 3 Towel Loading Instructions... page 7 Settings...

More information

Timing the 9N/2N Steering Sector Gears

Timing the 9N/2N Steering Sector Gears Timing the 9N/2N Steering Sector Gears by John Korschot - www.johnsoldiron.com (May 2010) The procedure for timing a set of steering gears in the 9/2n tractors is published in the I&T FO4 shop manual.

More information

QUADBOSS UTV STRAIGHT PUSH TUBE OWNER S MANUAL

QUADBOSS UTV STRAIGHT PUSH TUBE OWNER S MANUAL PAGE of 6 PART #938 QUADBOSS UTV STRAIGHT PUSH TUBE OWNER S MANUAL This owner s manual covers all aspects of your new push tube including assembly, replacement parts, installation, warranty, and troubleshooting.

More information

P0441-EVAP PURGE SYSTEM PERFO... P0441-EVAP PURGE SYSTEM PERFORMANCE

P0441-EVAP PURGE SYSTEM PERFO... P0441-EVAP PURGE SYSTEM PERFORMANCE P0441-EVAP PURGE SYSTEM PERFO... P0441-EVAP PURGE SYSTEM PERFORMANCE For a complete wiring diagram, refer to the Wiring Information. Theory of Operation EVAP SYSTEM COMPONENTS CALLOUT DESCRIPTION 1 Filter

More information

NOTE: The process described below is for removing the seat FRAME. The seat PLATFORM is welded to the bottom of the cab and cannot be removed.

NOTE: The process described below is for removing the seat FRAME. The seat PLATFORM is welded to the bottom of the cab and cannot be removed. Removing the seat frame on an Advance Design pickup NOTE: The process described below is for removing the seat FRAME. The seat PLATFORM is welded to the bottom of the cab and cannot be removed. STEP 1..

More information

AGREEMENT. done at Vienna on 13 November Addendum 1: Rule No. 1. Revision 1

AGREEMENT. done at Vienna on 13 November Addendum 1: Rule No. 1. Revision 1 6 March 2007 AGREEMENT CONCERNING THE ADOPTION OF UNIFORM CONDITIONS FOR PERIODICAL TECHNICAL INSPECTIONS OF WHEELED VEHICLES AND THE RECIPROCAL RECOGNITION OF SUCH INSPECTIONS done at Vienna on 13 November

More information

Automate Your Designs A Hands-On Experience

Automate Your Designs A Hands-On Experience Craig Ruchti, Solid Edge Field Support Applications Engineer Automate Your Designs A Hands-On Experience Solid Edge University 2014 May 12-14, Atlanta, GA, USA SOLID EDGE UNIVERSITY 2014 Re-imagine What

More information

ASME Human Powered Vehicle

ASME Human Powered Vehicle ASME Human Powered Vehicle By Yousef Alanzi, Evan Bunce, Cody Chenoweth, Haley Flenner, Brent Ives, and Connor Newcomer Team 14 Mid-Point Review Document Submitted towards partial fulfillment of the requirements

More information

Shaver Industries. Assembly Instructions Spring Assist Vertical Vinyl Curtain Door Projection Mount

Shaver Industries. Assembly Instructions Spring Assist Vertical Vinyl Curtain Door Projection Mount Shaver Industries 20 Steckle Place, Kitchener, ON N2E 2C3 Ph 1(888) 766 8328 www.shaverinc.com Assembly Instructions Spring Assist Vertical Vinyl Curtain Door Projection Mount Valued Shaver Customer: We

More information

Gravity Flow Merchandiser (GFM) Gravity Flow Shelf (GFS) Installation & Service Manual

Gravity Flow Merchandiser (GFM) Gravity Flow Shelf (GFS) Installation & Service Manual Gravity Flow Merchandiser (GFM) Gravity Flow Shelf (GFS) Installation & Service Manual 99-13324-S001_D Copyright 2011 by ALL rights reserved. Information in this document is subject to change without notice.

More information

Application Specification Pin&3Pin Miniature waterproof connector 28July2016 REV: C

Application Specification Pin&3Pin Miniature waterproof connector 28July2016 REV: C Application Specification 114-137093 2Pin&3Pin Miniature waterproof connector 28July2016 REV: C 1. INTRODUCTION This specification covers the requirements for application of 2Pin&3Pin Miniature waterproof

More information

Clutches for Automobiles and Light Trucks

Clutches for Automobiles and Light Trucks Clutches for Automobiles and Light Trucks What does the Clutch do? Connects the engine torque to transmission when ENGAGED Unhooks engine from transmission when DISENGAGED Where is the driver s foot when

More information

INSTALLING A 1977 THRU 1982 C3 STEERING COLUMN INTO A EARLIER 1969 THRU 1976 MODEL CORVETTE

INSTALLING A 1977 THRU 1982 C3 STEERING COLUMN INTO A EARLIER 1969 THRU 1976 MODEL CORVETTE Last Revised: 23FE2011 INSTALLING A 1977 THRU 1982 C3 STEERING COLUMN INTO A EARLIER 1969 THRU 1976 MODEL CORVETTE Why Make This Installation Starting in 1977 and carrying thru 1982, the C3 Corvette steering

More information

MIT ICAT M I T I n t e r n a t i o n a l C e n t e r f o r A i r T r a n s p o r t a t i o n

MIT ICAT M I T I n t e r n a t i o n a l C e n t e r f o r A i r T r a n s p o r t a t i o n M I T I n t e r n a t i o n a l C e n t e r f o r A i r T r a n s p o r t a t i o n Standard Flow Abstractions as Mechanisms for Reducing ATC Complexity Jonathan Histon May 11, 2004 Introduction Research

More information

EW Engagement Modelling for Light Armoured Vehicles

EW Engagement Modelling for Light Armoured Vehicles EW Engagement Modelling for Light Armoured Vehicles Vivienne Wheaton Electronic Warfare and Radar Division, DSTO Light Armoured Vehicles (LAVs) have many advantages in military operations but are significantly

More information

MKII Motorized Lightband Operating Procedure

MKII Motorized Lightband Operating Procedure MKII Motorized Lightband Operating Procedure THIS PROCEDURE IS NOT HAZARDOUS PSC Document 2000781 Rev E Planetary Systems Corporation 2303 Kansas Avenue Silver Spring, MD 20910 301-495-0737 info@planetarysystemscorp.com

More information

REMOVAL & INSTALLATION

REMOVAL & INSTALLATION REMOVAL & INSTALLATION Removal 1. Center steering wheel. Disconnect negative battery cable. Remove steering coupling shield (if equipped). Disconnect steering shaft at flexible coupling or pot joint. Note

More information

MANUAL VERSION FEBRUARY

MANUAL VERSION FEBRUARY MANUAL VERSION FEBRUARY 2008 MAINTENANCE AND TROUBLESHOOTING Quick Troubleshooting: WARNING For your safety and to reduce risk of damage to your game read the Important Safety Information in Chapter 1-2

More information

Automatic Transmission Basics

Automatic Transmission Basics Section 1 Automatic Transmission Basics Lesson Objectives 1. Describe the function of the torque converter. 2. Identify the three major components of the torque converter that contribute to the multiplication

More information

accompanying the up-dated working document on the Review of Regulation (EC) No 278/2009 regarding External Power Supplies

accompanying the up-dated working document on the Review of Regulation (EC) No 278/2009 regarding External Power Supplies Explanatory Note accompanying the up-dated working document on the Review of Regulation (EC) No 278/2009 regarding External Power Supplies 1. Context A Consultation Forum was held on 18 April 2013 which

More information

ECE/RCTE/CONF/4/Add.1/Rev.2

ECE/RCTE/CONF/4/Add.1/Rev.2 ECE/RCTE/CONF/4/Add.1/Rev.2 8 May 2018 Agreement Concerning the adoption of uniform conditions for periodical technical inspections of wheeled vehicles and the reciprocal recognition of such inspections

More information

1250 LB. CAPACITY MECHANICAL WHEEL DOLLY

1250 LB. CAPACITY MECHANICAL WHEEL DOLLY 1250 LB. CAPACITY MECHANICAL WHEEL DOLLY 67287 SET-UP AND OPERATING INSTRUCTIONS Visit our website at: http://www.harborfreight.com Read this material before using this product. Failure to do so can result

More information

Property of American Airlines

Property of American Airlines Section 2: Operation 1. GENERAL INFORMATION Safety First! is the motto at Tesco; therefore, the first part of the Operation section begins with safety features and procedures. Operation of the Tesco CL80-20

More information

Lessons Learned in the Flight Qualification of the S-NPP and NOAA-20 Solar Array Mechanisms

Lessons Learned in the Flight Qualification of the S-NPP and NOAA-20 Solar Array Mechanisms Lessons Learned in the Flight Qualification of the S-NPP and NOAA-20 Solar Array Mechanisms Daniel Helfrich * and Adam Sexton ** Abstract Deployable solar arrays are the energy source used on almost all

More information

CONTROLLER DIAGNOSTIC GUIDE

CONTROLLER DIAGNOSTIC GUIDE Proprietary tice: This document contains proprietary information which not to be reproduced, transferred, to other documents, disclosed to others, used for manufacturing or any other purpose without the

More information

NOTE: Hard copies of this document may not be the current version. Refer to the IAmTheKey to verify the current version.

NOTE: Hard copies of this document may not be the current version. Refer to the IAmTheKey to verify the current version. 6 - FUME HOOD 1 MERCURY ACCESS Title: Fume Hood 1 Mercury Access Doc. No. 2016-MMTS-6 NOTE: This document will be reviewed at least annually to ensure its suitability. Revision History Rev. No. Change

More information

GTpro1 Pedals Setup Guide. (all models)

GTpro1 Pedals Setup Guide. (all models) GTpro1 Pedals Setup Guide (all models) Features and Benefits Built using real after-market automotive pedals Throttle pedal is floor-mounted and angled to optimize heel-toe Adjustable pedal stop on throttle

More information

A Derailment Investigation Leads to Broken Spikes. Brad Kerchof Research & Tests

A Derailment Investigation Leads to Broken Spikes. Brad Kerchof Research & Tests A Derailment Investigation Leads to Broken Spikes Brad Kerchof Research & Tests 1 Google Earth image of the derailment site Vandergrift, PA, January 2014 8.3 curve, river grade (0.3% descending to 0%)

More information

CIRRUS AIRPLANE MAINTENANCE MANUAL

CIRRUS AIRPLANE MAINTENANCE MANUAL MODEL SR PASSENGER AND CREW DOORS. DESCRIPTION AND OPERATION Serials 000 thru 00: The two crew/passenger doors incorporate a flush-mount outside door handle, key-operated door lock, and a conventional

More information

INSTALLATION GUIDE. Doc ID Revision

INSTALLATION GUIDE. Doc ID Revision REKLUSE MOTOR SPORTS INSTALLATION GUIDE OVERVIEW Doc ID 191-6300 Revision 013017 Read the separate included Safety Information document before operating the vehicle with the product installed. If you are

More information

Capacity Market Rules for Energy Storage Resources

Capacity Market Rules for Energy Storage Resources Capacity Market Rules for Energy Storage Resources Zachary T Smith Manager, Capacity Market Design ICAPWG August 23 rd, 2018 Agenda Background Energy Storage Resource (ESR) overview Capacity Market Rules

More information

SuperQuest Salem Arms Best Practices

SuperQuest Salem Arms Best Practices SuperQuest Salem Arms Best Practices VEX Arm Designs Single 4-Bar 6-Bar 8-Bar Linear Slide Scissor Double Reverse 4-Bar Single Arms Arms These manipulators consist of a pivot point and at least 1 motor.

More information

Open Center Compact Valve Custom Installation Guide Rev A

Open Center Compact Valve Custom Installation Guide Rev A 200-0762-01 Open Center Compact Valve Custom Installation Guide 602-0575-01 Rev A 2014-12 Overview This guide provides information for completing a custom AutoSteer valve installation on wheeled farm vehicles

More information

Installation Instructions

Installation Instructions FORD 20K Industry Standard Rail Custom Mounting Kit #2766 Gross Trailer Weight (Maximum)...20,000 lbs. Vertical Load Weight (Max. Pin Weight)...5,000 lbs. SYSTEM TOW CAPACITY Please note, in order to determine

More information

Electronic Shifter. Lee Redstone V Lewis Weston V Jason Deglint V Group #5. Supervisor Ashoka K. S. Bhat. Due Oct.

Electronic Shifter. Lee Redstone V Lewis Weston V Jason Deglint V Group #5. Supervisor Ashoka K. S. Bhat. Due Oct. Electronic Shifter Lee Redstone V00662175 Lewis Weston V00766616 Jason Deglint V00730963 Group #5 Supervisor Ashoka K. S. Bhat Due Oct. 16, 2012 Dept. Electrical and Computer Engineering University of

More information

Installation Instructions

Installation Instructions DODGE 20K Industry Standard Rail Custom Mounting Kit #2742 Gross Trailer Weight (Maximum)...20,000 lbs. Vertical Load Weight (Max. Pin Weight)...5,000 lbs. SYSTEM TOW CAPACITY Please note, in order to

More information

TAPE EXTENSOMETER Model CONVEX-D. Roctest Limited, All rights reserved.

TAPE EXTENSOMETER Model CONVEX-D. Roctest Limited, All rights reserved. INSTRUCTION MANUAL TAPE EXTENSOMETER Model Roctest Limited, 2013. All rights reserved. This product should be installed and operated only by qualified personnel. Its misuse is potentially dangerous. The

More information

GXS14 - Civic Natural Gas Fuel Tank Solenoid Valve Replacement

GXS14 - Civic Natural Gas Fuel Tank Solenoid Valve Replacement Objective Remove In-Tank Solenoid Valve Inspect Fuel Tank for Liquid Contamination Evaluate Replacement Valve Condition Install In-Tank Solenoid Valve and Leak Check Align New Solenoid Valve and Connect

More information

Kotzebue Electric Association Flow Battery Storage Systems Quarterly Report 7/2012 Prepared by Jesse Logan (KEA)

Kotzebue Electric Association Flow Battery Storage Systems Quarterly Report 7/2012 Prepared by Jesse Logan (KEA) Kotzebue Electric Association Flow Battery Storage Systems Quarterly Report 7/2012 Prepared by Jesse Logan (KEA) Funding Denali Commission $425,000 AEA $300,000 CREBS Loan $575,000 Total $1,300,000 Premium

More information

HAND CONTROL SYSTEM FOR THE PHYSICALLY DISABLED

HAND CONTROL SYSTEM FOR THE PHYSICALLY DISABLED INSTALLATION Push/Twist HAND CONTROL SYSTEM FOR THE PHYSICALLY DISABLED with Howell Ventures Ltd Sure Grip Hand Control Systems and Accessories are warranted against manufacturing or material defects for

More information

May08 Rev C

May08 Rev C Product Specification 0.64 mm Generation Y Terminal 108-2296 20May08 Rev C 1. SCOPE 1.1. Content This specification covers performance, tests and quality requirements for the Tyco Electronics 0.64 mm Generation

More information

Forklift and Industrial Trucks

Forklift and Industrial Trucks Forklift and Industrial Trucks University Facilities Internal Procedure: July 1, 2013 Effective date: July 1, 2013 Last Modified: April 2013 Approved by: Bob Wells 1.0 Program Objective This program for

More information

Eastman Chemical Company Motor Analysis Stepping out of the Box

Eastman Chemical Company Motor Analysis Stepping out of the Box Eastman Chemical Company Motor Analysis Stepping out of the Box By: Tom Whittemore, Jr., P.E.; Paul Aesque; and Danny Hawkins, Eastman Chemical Company Eastman Chemical Company started its Motor Analysis

More information

June Safety Measurement System Changes

June Safety Measurement System Changes June 2012 Safety Measurement System Changes The Federal Motor Carrier Safety Administration s (FMCSA) Safety Measurement System (SMS) quantifies the on-road safety performance and compliance history of

More information

INSTALLATION INSTRUCTIONS

INSTALLATION INSTRUCTIONS INSTALLATION INSTRUCTIONS REAR DISC CONVERSION KIT A126-2 1988-98 C1500 2WD 10" REAR DRUM Thank you for choosing STAINLESS STEEL BRAKES CORPORATION for your braking needs. Pleases take the time to read

More information

INSTALLATION INSTRUCTIONS

INSTALLATION INSTRUCTIONS Aero Twin, Inc. Single Place Folding Seat P/N DFS1-01W TSO-C127a INSTALLATION INSTRUCTIONS Document No. DFS1W-IM1-T Note: This installation and weight and balance data is identical to that contained within

More information

Bus Stop Optimization Study

Bus Stop Optimization Study Bus Stop Optimization Study Executive Summary February 2015 Prepared by: Passero Associates 242 West Main Street, Suite 100 Rochester, NY 14614 Office: 585 325 1000 Fax: 585 325 1691 In association with:

More information

Reliable Reach. Robotics Unit Lesson 4. Overview

Reliable Reach. Robotics Unit Lesson 4. Overview Robotics Unit Lesson 4 Reliable Reach Overview Robots are used not only to transport things across the ground, but also as automatic lifting devices. In the mountain rescue scenario, the mountaineers are

More information

Installation Instructions

Installation Instructions 86-95 Suzuki Samurai Hood Latch & Release Cable (SKU# SEB- HLCK) Installation Instructions Note: S u z u k i h a s upgraded both of these parts and they will not work with the hood latches and release

More information

The CMPE 118 Cockroach Robot Dept. of Computer Engineering, UCSC

The CMPE 118 Cockroach Robot Dept. of Computer Engineering, UCSC The CMPE 118 Cockroach Robot Dept. of Computer Engineering, UCSC Background: The CMPE-118 Cockroach robot is designed to be an accessible mobile platform to teach you basic state machine programming. This

More information

Type N550 Snappy Joe Emergency Shutoff Valves

Type N550 Snappy Joe Emergency Shutoff Valves Instruction Manual MCK-1149 Type N550 March 2010 Type N550 Snappy Joe Emergency Shutoff Valves Failure to follow these instructions or to properly install and maintain this equipment could result in an

More information

USER'S MANUAL and INSTALLATION GUIDE

USER'S MANUAL and INSTALLATION GUIDE AM Inlet Series 8" and 2" baffle AM0896GS AM296GS USER'S MANUAL and INSTALLATION GUIDE TABLE OF CONTENTS Section Page...Requirements for Installation...2 2...Unpacking the AirManager... 3-5...Exploded

More information

OPERATIONAL INSTRUCTION OVERVIEW MAINTENANCE CHECKLIST

OPERATIONAL INSTRUCTION OVERVIEW MAINTENANCE CHECKLIST OPERATIONAL INSTRUCTION OVERVIEW Operation Both manual and electrically powered winches develop tremendous forces; therefore, all backstops must be operated by qualified personnel only to avoid structural

More information

A Prototype Oil-Less Compressor for the International Space Station Refrigerated Centrifuge

A Prototype Oil-Less Compressor for the International Space Station Refrigerated Centrifuge Purdue University Purdue e-pubs International Compressor Engineering Conference School of Mechanical Engineering 2000 A Prototype Oil-Less Compressor for the International Space Station Refrigerated Centrifuge

More information

Troubleshooting: Installation 10. Troubleshooting: Door Jamming and Door Handing 11. Troubleshooting: Touchscreen 14

Troubleshooting: Installation 10. Troubleshooting: Door Jamming and Door Handing 11. Troubleshooting: Touchscreen 14 Programming and Troubleshooting Guide 1 2 3 4 5 6 7 Mastercode 2 Troubleshooting: Installation 10 Troubleshooting: Door Jamming and Door Handing 11 Troubleshooting: Touchscreen 14 Troubleshooting: Smart

More information

INSTALLATION INSTRUCTIONS

INSTALLATION INSTRUCTIONS INSTALLATION INSTRUCTIONS REAR DISC BRAKE CONVERSION KIT A126-3 1988-98 CHEVY K1500 4WD 10" DRUMS Thank you for choosing STAINLESS STEEL BRAKES CORPORATION for your braking needs. Pleases take the time

More information

The Ryan Overdrive by Tom Endy

The Ryan Overdrive by Tom Endy The Ryan Overdrive by Tom Endy The Ryan overdrive is a factory built overdrive designed for the Model a Ford. They were manufactured in Denver, Colorado and marketed between 1990 and 2000. They were discontinued

More information

Fisher 657 Diaphragm Actuator Sizes and 87

Fisher 657 Diaphragm Actuator Sizes and 87 Instruction Manual 657 Actuator (30-70 and 87) Fisher 657 Diaphragm Actuator Sizes 30 70 and 87 Contents Introduction... 1 Scope of Manual... 1 Description... 2 Specifications... 2 Installation... 3 Mounting

More information

Cetra Assembly Instructions

Cetra Assembly Instructions 99877 Revision F- Complete Series Master Packet If you have any questions concerning these instructions, please call Kimball Office Customer Service. 0 Kimball International, Inc. T 800.8.88 F 8.8.800

More information

Aftermarket Part Quality: A Report on Parts that Fail CAPA s Certification Requirements

Aftermarket Part Quality: A Report on Parts that Fail CAPA s Certification Requirements Aftermarket Part Quality: A Report on Parts that Fail CAPA s Certification Requirements Study Dates: March 1999 May 2003 Prepared By Certified Automotive Parts Association 1518 K Street NW, Suite 306 Washington,

More information

ASTM D4169 Truck Profile Update Rationale Revision Date: September 22, 2016

ASTM D4169 Truck Profile Update Rationale Revision Date: September 22, 2016 Over the past 10 to 15 years, many truck measurement studies have been performed characterizing various over the road environment(s) and much of the truck measurement data is available in the public domain.

More information

TECHNICAL SERVICE BULLETIN: TSB

TECHNICAL SERVICE BULLETIN: TSB TECHNICAL SERVICE BULLETIN: TSB2015-007 To: From: Global Service Organization, ichem VELOCITY and iricell Distributors Iris Diagnostics Service and Support Date: 10 June 2015 Subject: STRIP PROVIDER MODULE

More information

CONTROL SYSTEM FOR THE PHYSICALLY DISABLED

CONTROL SYSTEM FOR THE PHYSICALLY DISABLED INSTALLATION Push/Rock HAND CONTROL SYSTEM FOR THE PHYSICALLY DISABLED With Howell Ventures Ltd Sure Grip Hand Control Systems and Accessories are warranted against manufacturing or material defects for

More information

Installation Instructions

Installation Instructions FORD 20K Industry Standard Rail Custom Mounting Kit #2738 Gross Trailer Weight (Maximum)...20,000 lbs. Vertical Load Weight (Max. Pin Weight)...5,000 lbs. SYSTEM TOW CAPACITY Please note, in order to determine

More information

Rocketry Projects Conducted at the University of Cincinnati

Rocketry Projects Conducted at the University of Cincinnati Rocketry Projects Conducted at the University of Cincinnati 2009-2010 Grant Schaffner, Ph.D. (Advisor) Rob Charvat (Student) 17 September 2010 1 Spacecraft Design Course Objectives Students gain experience

More information

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1 Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide Version 1.1 October 21, 2016 1 Table of Contents: A. Application Processing Pages 3-4 B. Operational Modes Associated

More information

Model 3060 Emitter Installation & Operation (REV 1) ATTENTION

Model 3060 Emitter Installation & Operation (REV 1) ATTENTION TOMAR TOMAR ELECTRONICS Strobecom II Model 3060 Emitter Installation & Operation (REV 1) ATTENTION THE STROBECOM II SYSTEM IS DESIGNED TO AID IN THE TRANSIT OF DESIGNATED VEHICLES THROUGH THE TRAFFIC CONTROL

More information

M3 Design Product Teardown Kobalt Double-Drive Screwdriver

M3 Design Product Teardown Kobalt Double-Drive Screwdriver 19 Jun, 2013 Why do the product teardowns? M3 Design Product Teardown Kobalt Double-Drive Screwdriver Part of the product development process is to apply knowledge gained from prior experience during the

More information

Cruise Control Wiring

Cruise Control Wiring Cruise Control Wiring By Matt Sandt, Revised 3-28-16 The approach described in this writing applies to solar car motor controls which use a potentiometer connected to a gas pedal. The potentiometer is

More information

Installation Instructions

Installation Instructions DODGE 20K Industry Standard Rail Custom Mounting Kit #2740 Gross Trailer Weight (Maximum)...20,000 lbs. Vertical Load Weight (Max. Pin Weight)...5,000 lbs. SYSTEM TOW CAPACITY Please note, in order to

More information

Something to use as a ramp (preferably a flat surface that would enable the buggy to roll for 25 cm or more) STUDENT PAGES.

Something to use as a ramp (preferably a flat surface that would enable the buggy to roll for 25 cm or more) STUDENT PAGES. Design a Lunar Buggy OBJECTIVE To demonstrate an understanding of the Engineering Design Process while utilizing each stage to successfully complete a team challenge. PROCESS SKILLS Measuring, calculating,

More information

INVESTIGATION REPORT PREPARED FOR: UNIVERSITY OF NORTHERN IOWA CEDAR FALLS, IA

INVESTIGATION REPORT PREPARED FOR: UNIVERSITY OF NORTHERN IOWA CEDAR FALLS, IA INVESTIGATION REPORT PREPARED FOR: UNIVERSITY OF NORTHERN IOWA CEDAR FALLS, IA Prepared By: HBK Engineering, LLC. 921 West Van Buren Street, Suite 100 Chicago, IL HBK PROJECT # 18 0788 October 2, 2018

More information

2015 WDC Disturbance and Protection Standards Overview

2015 WDC Disturbance and Protection Standards Overview NERC Update 2015 WDC Disturbance and Protection Standards Overview Rich Bauer Senior Manager Reliability Risk Management / Event Analysis IEEE PSRC meeting Denver, Co May 12, 2016 2 System Protection and

More information

GlaStar / Sportsman Service Bulletin 64- MANDATORY

GlaStar / Sportsman Service Bulletin 64- MANDATORY GlaStar / MANDATORY Note: Subject: Applicability: This service bulletin supersedes 49. The service bulletin applicability was updated to include kits. No other changes were made Inspection of welded cage

More information

Bosch Seat Motor _spec_sheet_-_Bosch_FRC_motor_6_004_.pdf. FRC_Bosch_motor_V2_6_004_RA3_ zip

Bosch Seat Motor _spec_sheet_-_Bosch_FRC_motor_6_004_.pdf. FRC_Bosch_motor_V2_6_004_RA3_ zip Bosch Seat Motor Specification Sheet 2016-12-21_spec_sheet_-_Bosch_FRC_motor_6_004_.pdf CAD File FRC_Bosch_motor_V2_6_004_RA3_194-06.zip Motor Mounting & Shaft Support: Suggested Motor relies on two solid

More information

INSTALLATION & USER S GUIDE

INSTALLATION & USER S GUIDE REKLUSE MOTOR SPORTS The Rekluse Core EXP Kit with Adjustable Slave Cylinder INSTALLATION & USER S GUIDE Doc ID: 191-7704A Doc Rev: 102915 OVERVIEW This kit replaces the OEM core clutch components including

More information

NISSAN #2744. Gross Trailer Weight (Maximum)...16,000 lbs. Vertical Load Weight (Max. Pin Weight)...4,000 lbs. SYSTEM TOW CAPACITY

NISSAN #2744. Gross Trailer Weight (Maximum)...16,000 lbs. Vertical Load Weight (Max. Pin Weight)...4,000 lbs. SYSTEM TOW CAPACITY NISSAN 16K Industry Standard Rail Custom Mounting Kit #2744 Gross Trailer Weight (Maximum)...16,000 lbs. Vertical Load Weight (Max. Pin Weight)...4,000 lbs. SYSTEM TOW CAPACITY Please note, in order to

More information

s_enn Exterior Stainless Steel Shading System by Draper

s_enn Exterior Stainless Steel Shading System by Draper Installation Instructions s_enn Exterior Stainless Steel Shading System by Draper Caution 1 Never push the bottom rail of the system up by hand. This can cause irreparable damage. Access equipment must

More information

E-LIFT II+ SYSTEM WITH SPRING LEVER FOR A-SERIES AND FULL FRAME LOOMS

E-LIFT II+ SYSTEM WITH SPRING LEVER FOR A-SERIES AND FULL FRAME LOOMS Congratulations on your purchase of the E-Lift II+ system. This system replaces the action of treadling, eliminating leg strain and fatigue. When you activate the Foot Switch, the motor turns, and selected

More information

National Board Update

National Board Update National Board Update Presentation to the Valve Repair Council June 2, 2016 Prepared by: Joseph F. Ball, P.E. National Board Update National Board activities Who we are and what we do National Board Inspection

More information

Jeep Wrangler Heavy Duty Drag Link Installation Instructions

Jeep Wrangler Heavy Duty Drag Link Installation Instructions THE INFORMATION CONTAINED IN THIS DRAWING IS THE SOLE PROPERTY OF SYNERGY MFG. ANY REPRODUCTION IN PART OR WHOLE WITHOUT THE WRITTEN PERMISSION OF SYNERGY MFG IS PROHIBITED. Revisions Rev. Description

More information

Setup, Assembly, & Adjustment

Setup, Assembly, & Adjustment Setup, Assembly, & Adjustment 34877 Rev. B 1 of 8 Melco Fast Clamp Instructions The Melco Fast Clamp is a versatile clamping system for your embroidery machine. This document will walk you through the

More information

SE 'LF-PRO PELLED LOWER BELT DRIVE SERVICING

SE 'LF-PRO PELLED LOWER BELT DRIVE SERVICING SE 'LF-PRO PELLED LOWER NOTE Whenever wheel height or handle height is changed, clutch control rod and lever must be readjusted. Loosen clamp, lock drive unit in outof-drive position. Pull up clutch controlever

More information

Power & High Voltage Joslyn Hi-Voltage Overhead Reclosers & Switches H-220. Series HVI Hi-Velocity Interrupter Attachment

Power & High Voltage Joslyn Hi-Voltage Overhead Reclosers & Switches H-220. Series HVI Hi-Velocity Interrupter Attachment Use load interrupter attachments to enable loop sectionalizing, line dropping, load breaking and transformer-magnetizing current interruption. Increase the capability of your disconnect switches by adding

More information

NOTE: Skids and all hardware for the skids are located in the plow blade box.

NOTE: Skids and all hardware for the skids are located in the plow blade box. Description Item Qty. Part# 0 0 ATV PUSH TUBE AND BLADE MOUNTING INSTRUCTIONS P/N: 0-0 CUSTOMER MUST RECEIVE A COPY OF THIS INSTRUCTION SHEET AT THE TIME OF SALE NOTE: Skids and all hardware for the skids

More information

CORPORATION REPAIR MANUAL HWH SPACEMAKER ROOM EXTENSION SYSTEM NO LEVELING SYSTEM FOR NATIONAL RV NON-MOTORIZED VEHICLES

CORPORATION REPAIR MANUAL HWH SPACEMAKER ROOM EXTENSION SYSTEM NO LEVELING SYSTEM FOR NATIONAL RV NON-MOTORIZED VEHICLES HWH R CORPORATION REPAIR MANUAL HWH SPACEMAKER SYSTEM NO LEVELING SYSTEM FOR NATIONAL RV NON-MOTORIZED VEHICLES FEATURING: DUAL CYLINDER "RAIL" (WITH RACK SENSING VALVE) SINGLE CYLINDER DUAL CYLINDER "RAIL"

More information

Heavy Truck Conflicts at Expressway On-Ramps Part 1

Heavy Truck Conflicts at Expressway On-Ramps Part 1 Heavy Truck Conflicts at Expressway On-Ramps Part 1 Posting Date: 7-Dec-2016; Revised 14-Dec-2016 Figure 1: Every day vast numbers of large and long trucks must enter smoothly into high speed truck traffic

More information

DODGE SuperRail Mounting Kit #0848

DODGE SuperRail Mounting Kit #0848 DODGE SuperRail Mounting Kit #0848 #1200 Super 5 th (16K) #0800 Super 5 th (20.5K) Gross Trailer Weight (Maximum) Vertical Load Weight (Max. Pin Weight) 16,000 lbs. 4,000 lbs. Gross Trailer Weight (Maximum)

More information

B&W Turnover Ball Installation

B&W Turnover Ball Installation B&W Turnover Ball Installation by Flopster843 02 Jan 2012 I wanted to start this article out by stating one very important thing. Installing a gooseneck hitch is not a task to be taken lightly. If you

More information

MULTI-FIT BRAIDED THROTTLE/IDLE CABLE KITS

MULTI-FIT BRAIDED THROTTLE/IDLE CABLE KITS -J08 REV. 008-08-5 MULTI-FIT BRAIDED THROTTLE/IDLE CABLE KITS GENERAL Kit Numbers Stainless Steel Kits 560-0 56-00 56-0A 565-0A 5650-0A 5670-0A 567-0A 567-0A 5678-0 569-0 5699-05 5656-0 56579-0A 5670-0

More information

Online Service Center for Monaco Coach

Online Service Center for Monaco Coach Online Service Center for Monaco Coach TROUBLESHOOTING TIPS [ back to the Online Service Center main page ] CAUTION: The Air Suspension System must be turned off at the System Power switch when the vehicle

More information

ATLAS TRANSFER CASES CABLE SHIFTER units built after 5/1/12

ATLAS TRANSFER CASES CABLE SHIFTER units built after 5/1/12 KIT CONSISTS OF: No. Qty Part No. Description P.O. Box 247, 4320 Aerotech Center Way PAGE 1 OF 6 Page Rev. Date: 08-01-17 1 1 302051 BASE- TWIN STICK MOUNT 2 1 302060 BOOT- TWIN STICK 3 1 302063 BOOT RING-

More information

1 of 10 9/3/2011 3:19 PM. This bulletin covers the following issues: Condition #1. Cause. Correction

1 of 10 9/3/2011 3:19 PM. This bulletin covers the following issues: Condition #1. Cause. Correction 1 of 10 9/3/2011 3:19 PM #08-08-67-013G: Snap, Pop, Creak or Rattle Noise from Lift Off Roof Panel While Driving (Verify Condition and Perform Appropriate Repairs) - (Jun 1, 2011) Subject: Models: Snap,

More information

Detroit Speed, Inc. Second Generation Camaro/Firebird Mini-Tub Kit Camaro/Firebird P/N: ,

Detroit Speed, Inc. Second Generation Camaro/Firebird Mini-Tub Kit Camaro/Firebird P/N: , Detroit Speed, Inc. Second Generation Camaro/Firebird Mini-Tub Kit 1970-1981 Camaro/Firebird P/N: 041222, 041223 The Detroit Speed Second Generation Camaro/Firebird Rear Mini-Tub Kit is designed to accommodate

More information

Application Note. First trip test. A circuit breaker spends most of its lifetime conducting current without any

Application Note. First trip test. A circuit breaker spends most of its lifetime conducting current without any Application Note First trip test A circuit breaker spends most of its lifetime conducting current without any operation. Once the protective relay detects a problem, the breaker that was idle for maybe

More information

WARNING. Instructions for Guidelights and Chargers. How SnapPower Products Work

WARNING. Instructions for Guidelights and Chargers. How SnapPower Products Work Instructions for Guidelights and Chargers WARNING Failure to turn OFF electrical power prior to installing or removing the Guidelight or Charger can result in electrical shock, fires, and/or death. www.snappower.com

More information

TEST REPORT. Ceram Reference: (QT21489/2/SL)/Ref: 1.0A. Tensile and Frictional Tests on the Fast Fit BeamClamp Systems.

TEST REPORT. Ceram Reference: (QT21489/2/SL)/Ref: 1.0A. Tensile and Frictional Tests on the Fast Fit BeamClamp Systems. TEST REPORT Ceram Reference: 121557 (QT21489/2/SL)/Ref: 1.0A Project Title: Tensile and Frictional Tests on the Fast Fit BeamClamp Systems Client: Kee Safety Limited For The Attention of: Mr Phil Higgs

More information