Terminator DP/FAK-5LHT Kit for Tee Splice of Electrically Heated TubeTrace Bundles INSTALLATION PROCEDURES

Similar documents
Terminator DP/FAK-4LHT Kit for In-Line Splice of Electrically Heated TubeTrace Bundles INSTALLATION PROCEDURES

Terminator DP/FAK-4 and FAK-4L for In-Line Splice of Electrically Heated TubeTrace Bundles INSTALLATION PROCEDURES

Terminator DP/FAK-5 and FAK-5L

Terminator DP/FAK-2 and FAK-2L. Elbow Splice Kit for Electrically Heated TubeTrace Bundles INSTALLATION PROCEDURES

Terminator ZP/FAK-4L Kit Electrically Heated TubeTrace Bundles

Terminator ZP/FAK-5 and 5L

Terminator. DP Power Connection Kit INSTALLATION PROCEDURES

Terminator TM DL Lighted Power Connection/End Termination Kit INSTALLATION PROCEDURES. For Power Connection or End Termination Applications

Terminator ZP/FAK-1 Kit Electrically Heated TubeTrace Bundles

TracePlus. PCA Power Connection Kit INSTALLATION PROCEDURES. PCA-H for BSX, HTSX, KSX, HPT, FP PCA-V for RSX, TSX, VSX

TracePlus. VIL-6 End of Circuit Light Kit INSTALLATION PROCEDURES. VIL-6-H for BSX, HTSX, KSX, HPT, FP VIL-6-V for RSX, TSX, VSX

Terminator DL-S for use with BSX *, HTSX, KSX self-regulating, HPT power-limiting, and FP constant watt heating cables

PETK Power and End Termination Kit

PETK Power and End Termination Kit

FAK-7HTS High Temperature Tubing Bundle End Seal Kit INSTALLATION PROCEDURES

Power Connection Kit Installation Instructions. Terminator DP-M for use with TEK and HTEK series constant watt heating cables

SCTK INSTALLATION PROCEDURES. Splice Connection Termination Kit. SCTK-1 for BSX, RSX, VSX SCTK-2 for KSX, HTSX SCTK-3 for HPT, FP

In-Line / T-Splice Kit Installation Instructions. Terminator DS-L for use with RSX, TSX, VSX self-regulating heating cables

ZP-XP Power Connection Kit. Terminator. The Heat Tracing Specialists INSTALLATION PROCEDURES

Power Connection Kit Installation Instructions. Terminator ZP-M for use with TEK and HTEK series constant watt heating cables

SCTK Splice Connection Termination Kit

PETK Power and End Termination Kit

TubeTrace Tubing Bundles

Electric Heat Tracing INSTALLATION PROCEDURES

TSRT TSRT Tee Splice Kit Installation Instructions

UPC Power Connection Kit

DEF-Trac. Design and Installation Guide. August 2015

C A HEATING CABLE GLAND KIT INSTALLATION INSTRUCTIONS

C A Heating Cable Gland Kit Installation Instructions

ET-PWR-END-KIT Installation Instructions (part #JSR00)

DEF-Trac. Design and Installation Guide. August 2014

FLX TM Self-Regulating Winterization/Freeze Protection INSTALLATION PROCEDURES

JBM-100-STB NEMA 4X-rated connection kit Installation Instructions

RT FlexiPanel TM Tank and Vessel Heating Panel

C Power Connection Kit

DEVI EasyConnect Heating Cable Connection System

Products and Accessories. Information Guide

Electric Heat Tracing INSTALLATION PROCEDURES

SPC-P Smart Power Connection with Temperature Monitoring Transmitter Pipe Mounted Installation Instructions

JBS-100-A, A6 SINGLE ENTRY POWER CONNECTION WITH JUNCTION BOX INSTALLATION INSTRUCTIONS

Installation Instructions

WarmTrace TM HSX Hot Water Temperature Maintenance INSTALLATION PROCEDURES

PRO-Tect Pipe Freeze Protection Self-Regulating Heating Cable Install Manual (PT-Series)

JBS-100-STB Single Entry Power Connection with Junction Box Installation Instructions

PMKG-JS POLYMATRIX SPLICE CONNECTION KIT INSTALLATION INSTRUCTIONS

SERGE BARIL HA-S HAZARDOUS AREA SEAL KIT

UES-LL End Termination Kit

PMKG-J2LP PolyMatrix Powered Splice Kit Installation Instructions

AutoMatrix Power Connection Kit. (1) This type 4X enclosure is intended for indoor or outdoor use primarily to. (2) May be required (see step 1).

SRK02 Hard Wire Power Connection Kit. Installation, Operation and Maintenance Instructions

Power Connection Kit installation instructions

CONTENTS. This Product is Certified by CANADIAN STANDARDS ASSOCIATION and Bears the Mark:

Specification for Heated Instrument Tubing in Process Applications* (March 29, 2007)

EMK-XP ElectroMelt Power Connection and End Seal Kit Installation Instructions

Heating Cable. Description

Installation Instructions CONSTANT WATT (CW) AND SELF-REGULATING (SR) PIPE TRACING CABLES

HTP PTP/ PTJ Power Connection Kit for Pipes

WarmlyYours ET-SR Series Heating Cable Installation Manual for Roof & Gutter Deicing

Nuheat WEATHER-READY HEAT TRACE PIPE FREEZE PROTECTION SYSTEM. Self-Regulating Heating Cable Installation Guide. UV Resistant Polyolefin Outer Jacket

AquaLumin III - Nicheless Light Installation Guide IMPORTANT SAFETY INSTRUCTIONS READ AND FOLLOW ALL INSTRUCTIONS SAVE THESE INSTRUCTIONS

PRODUCTS&ACCESSORIES INFORMATION GUIDE SELF-REGULATING HEATING CABLES HTSXTM BSXTM VSXTM RSXTM KSRTM KSXTM

Installation Instructions Electric Heaters 5 20 kw

3M Self Regulating Heating Cables

Power-Limiting Cables

TOYOTA VENZA 2009 TRAILER WIRE HARNESS Procedure

POWERHEAT TYPE AHT TERMINATION INSTRUCTIONS. Ref TK/AHT Issue C Date 16 August 1999

WARNING. Important Notice

NAMSR SELF-REGULATING FREEZE PROTECTION HEATING CABLE SELECTION

PFadvantage MF 6850/6855; Ideal 9080/9090

Universal Super Shield & Ultimate Aluminum w/electric Drive Conversion Kits , , Installation Instructions

Instruction Sheet. Subject: Installations Instructions. Air Compressor Kits. Importan

Splicing Procedures 4. 2 Insert the new wire between the parted strands. If more than one wire is being spliced, wrap them in opposite directions. Use

GENUINE PARTS INSTALLATION INSTRUCTIONS

Rated for use on 110/120VAC 60Hz and 220/240VAC 60Hz applications

Heating Cable. Description

Type HLT Self-Regulating Heater Cable For use in Ordinary and Hazardous (Classified) Locations

Selection Guide. Freeze Protection Heating Cable. Thermwire - Wrap. Thermwire - Wrap Pre-Assembled. Thermwire - Comp. Thermwire - Melt.

Introduction to Heat Trace Cable Systems

TOYOTA TRUCKS / SUVs COLD AIR INTAKE Section I Installation Preparation. 4.0L V6 (1GR-FE) Part Number(s): PTR

WARNING TAKE NOTE OF THE FOLLOWING: THIS PRODUCT MUST BE INSTALLED EXACTLY AS PER THESE INSTRUCTIONS USING ONLY THE HARDWARE SUPPLIED.

Utility Distribution Systems Installation, Operation, and Maintenance Manual

Installation Instructions

Installation Instructions Electric Heaters 5 20 kw

w w w. h d o n l i n e s h o p. d e CHROME 1.25 INCH (31.75 MM) DIAMETER HANDLEBAR KIT GENERAL INSTALLATION -J04405 REV Kit Number Models

Installation Instructions

PIPE FREEZE PROTECTION AND FLOW MAINTENANCE XL-TRACE SYSTEM

SWX-100-INT-PCR Internal Isolation Switch

SPECIAL INSTALLATION INSTRUCTIONS

Installation Instructions Table of Contents

IP65 COOLEDGE TILE EXTERIOR R2 INSTALLATION MANUAL. Exterior TILE Jumper Cable. Exterior Cutout TILE. Cable Clamp. T-Cable.

Self-Regulating Freeze Protection Heating Cable

TOYOTA VENZA 2009 TRAILER WIRE HARNESS Procedure

Instructions for 2-row monitoring only

Fiber Splice Panel Rack Mount User Manual

LED Flat Panel Installation Instructions For 1 x4, 2 x2, and 2 x4 LED Flat Panels (FP Series)

Installation Instructions

Ecoflex potable PEX plus pre-insulated pipe system Installation guide

IMPORTANT SAFETY INSTRUCTIONS READ AND FOLLOW ALL INSTRUCTIONS SAVE THESE INSTRUCTIONS

SITRANS F. Ultrasonic Flowmeters. Hi-Precision Mounts. Operating Instructions. Answers for industry.

US Water ph Booster-Reducer Injection System

Transcription:

Terminator DP/FAK-5LHT Kit for Tee Splice of Electrically Heated TubeTrace Bundles INSTALLATION PROCEDURES

Terminator DP/FAK-5LHT The following installation procedures are suggested guidelines for the installation of the Terminator DP/FAK-5L: Tee Splice kit. They are not intended to preclude the use of other methods and good engineering or field construction practices. Receiving, Storing and Handling... 1. Inspect materials for damage incurred during shipping. 2. Report damages to the carrier for settlement. 3. Identify parts against the packing list to ensure the proper type and quantity has been received. 4. Store in dry location. Terminator DP/FAK-5L Kit Contents... 1 2 4 5 Required: Order Separately for each heater to be fabricated. Refer to PETK Instruction, Form PN50132 for additional information. PETK Power and End Termination Kits (one req d. per heater) PETK-1D for BSX, RSX, VSX PETK-2D for KSX, HTSX PETK-3D for HPT 1 2 3 4 5 6 6 Item Quantity Description 3 1 1 RTV Sealant Tube 2 1 TBX Power Connection Boots 3 1 ET End Cap 7 9 10 11 12 14 4 1 Tape Strip Teflon 6" (PETK-3D only) 5 1 End Termination Caution Label 6 1 GRW-G Grommet (PETK-3D only) 13 Tools Required... 8 15 16 Item Quantity Description 1 1 2 1 Junction Box Lid Expediter Assembly: Flat Mount Base, Grommet, Threaded Grommet Compressor, and Support Cap with O-Ring 3 1 Junction Box Base with O-Ring 4 1 Nut 5 5 Terminal Block (Typical) 6 1 Junction Box Cord 7 1 Tee Splice Top 8 1 Tee Splice Base 9 10 Pan Head S.S. Screws, #10-32 x.75 10 10 KEPT S.S. Nuts, #10-32 11 3 M5 Screw 12 3 M5 Lock Washer 13 1 Fiberglass Rope, 1/2 Dia. X 12 Length 14 1 Heat Reflective Tape, 1.75 Wide 15 1 Glass Fiber Tape, 2 Wide 16 1 RTV Sealant Tube 2

INSTALLATION PROCEDURES The Terminator DP/FAK-5L Tee Splice Kit is designed to make a waterproof seal over the end of TubeTrace at the tee splice connections. Review instructions prior to installation. Kit will make one splice connection (Tube fittings not included). See separate instructions for details on splicing heat tracing. Terminator DP Certifications/Approvals... IP66 NEMA/Type 4X -60 C Ta +55 C Ordinary & Hazardous Locations Class I, Division 2, Groups A, B, C, & D, Zone 2 IIC Class II, Division 2, Groups F & G, Class III Listed System 137M Installation Precautions for Electrical Heaters (if required) To minimize the potential for arcing on electric heat tracing and fire caused by product damage or improper installation use ground-fault protection. The National Electrical Code (NEC) and Canadian Electrical Code (CEC) require groundfault protection of equipment for each branch circuit supplying electric heat tracing. Installation must comply with Thermon requirements and be installed in accordance with the NEC, CEC, or any other applicable national and local codes. Component approvals and performance ratings are based on the use of Thermon specified parts only. User supplied power connection fittings must be listed or certified for intended use. De-energize all power sources before opening enclosure. Keep ends of bundles, heating cable and kit components dry before and during installation. Trim as Required for Connection 64mm (2.5 ) Tubing Bundle Insulation 305mm -381mm (12-15 ) Tubing HPT 1. Remove outer jacket and insulation from tubing bundle to the required length for making connections. 2. Strip back bundle jacket and insulation 38mm (1-1/2 ) to 76mm (3 ) beyond buss connection indentation of each heat tracing. If buss connection indentation is less than 305mm-381mm (12-15 ) from end of the heat tracing, proceed stripping the bundle jacket and insulation to the next indentation. Tubing Bundle Tubing Fiberglass Rope (100% Coverage) Reflective Tape (50% Overlap) Tubing Bundle Tube Fitting (Provided by Others) (Outside Insulation) (Outside Tape) 3. Make tube connections with appropriate fittings, provided by others. Test fittings for leaks before proceeding. 4. Wrap high temperature tubing with 1/2 fiberglass rope. Ensure 100% coverage to keep tubing and heat tracing from making contact. DO NOT wrap heat trace with fiberglass rope. 5. Wrap fiberglass rope with 1 pass of reflective tape (50% overlap) and one pass of heat reflective tape (25% overlap). 3

Terminator DP/FAK-5LHT Reflective Tape Glass Fiber Tape (50% Overlap) Reflective Tape Cut and Remove End Pieces to Fit FAK 5L Top FAK 5L Base 6. Wrap with 3 passes of glass fiber tape (50% overlap). 7. Complete with additional wraps of heat reflective tape (25% overlap). 8. Cut FAK-5L top and base to match outside diameter of tubing bundle and remove end pieces. Mounting Screws and Washers FAK-5L Top RTV Sealant Pan Head Screws O-Ring Expediter Base FAK-5L Base FAK-5L Base Weep Hole KEPT Nuts 9. Mount Expediter Base with O-Ring to bottom cover using (3) M5 mounting screws and lock washers. Punch out weep hole. 10. Form a gasket by applying RTV sealant to the FAK-5L top and base. 11. Fit tubing bundle to bottom half of cover and install top half. Screw down firmly. Inspect ends of tubing splice cover for snug fit. Apply additional RTV sealant where needed. Heat Trace 180mm (7 ) Minimum Ground Braid Power Connection Boot Dimple for Center Line Drilled thru (1) Wall 12. Trim heat tracing to 180mm (7 ) minimum from expediter base. v 13. Terminate heat tracing with appropriate PETK termination kit. Refer to PETK installation instructions for details (not addressed here). 14. For power connection applications: Use dimple molded into side of junction box base to locate center hole, drill for user supplied power connection fitting per manufacture s recommendations. 4

INSTALLATION PROCEDURES Align Slot 15. Mount junction box on expediter making sure to align slots to properly orient junction box base. Terminal Blocks (Typical) 16. Install quick mount terminal blocks twist to position and tighten screws. 17. Complete system wiring between fabricated heat tracing and power supply wiring. 30º 18. Install junction box lid and twist hand tight. Insert screwdriver into ratchet slot located on side of junction box base to tighten. 19. Use screwdriver ratchet on junction box lid. Lid will rotate 30. 20. Lid latch mechanism fully engaged. To remove lid, repeat steps 17 and 18 but in opposite direction. FAK 5L Top Tubing Blundle Power Feed Flex Conduit Junction Box 21. Completed Terminator DP/FAK-5L for Tee Splice power assembly for TubeTrace Type SE/ME Bundle (Installation shown is to feed power in kit junction box. Many installations will be for splice only, without power feed to the electrical heat tracing circuits.) 5

Form PN50078-0510 THERMON... The Specialists 100 Thermon Dr. PO Box 609 San Marcos, TX 78667-0609 Phone: 512-396-5801 Facsimile: 512-396-3627 1-800-820-HEAT www.thermon.com In Canada call 1-800-563-8461 Specifications and information subject to change without notice.