Present and Future Cryogenics at Cornell

Similar documents
Low Beta Cryomodule Development at Fermilab. Tom Nicol March 2, 2011

THE 12 GeV ENERGY UPGRADE AT JEFFERSON LABORATORY

Cryogenic Improvements for the ATLAS Energy Upgrade

JLab. By JLab Cryo Group. Presenter: VenkataRao Ganni January 25, 2011

Task Cryomodule. Paolo Pierini INFN Sezione di Milano - LASA

Central Region Group Status and Positron Region

M. A. Green, and S. Yu Lawrence Berkeley National Laboratory, Berkeley CA 94720, USA

SNS Operation and Upgrade Plans

9-O-3A-4 Cryogenic system for the 43 T Hybrid Magnet at LNCMI Grenoble From the needs to the commissioning

Major Upgrade Activity of the PLS in PAL: PLS-II

Hall C SHMS Progress

Solenoid Magnets for the Front End of a Neutrino Factory

Energy Storage. Part 2. Some case studies Alternatives. Thomas Taylor CERN and AT Scientific LLC

Support and Infrastructure

Beam Energy Absorber and

Magnet, Support and Infrastructure. Whit Seay November 7, 2014

The g-2 Project at FNAL. Horst Friedsam John Kyle IWAA 2014 at Beijing October 2014

Summary of Working Group C: Injection, Extraction, Accelerator Systems

Coreless Concept for High Gradient Induction Cell

Gazprom s Helium Facility in Orenburg Supply & Start-Up of a Linde Liquefier. Klaus Ohlig Twente, July 9 th, 2014

AUTOMOTIVE EMC TEST HARNESSES: STANDARD LENGTHS AND THEIR EFFECT ON RADIATED EMISSIONS

1100 lbs Q2/D lbs lbs lbs lbs Q1/D1

Advant OCS controls cryogenic installations of CERN s particle accelerator

Mu2e Solenoids! Michael Lamm! L2 for the Mu2e Solenoid! July 27, 2015!

DEMONSTRATION OF A HYDROGEN FUEL CELL LOCOMOTIVE

UHV Flow Cryostat - Helitran

Overview. Selection of System Components VT BBK/CWH. Chart LNG Vehicle Tank and Fuel System Installation Guidelines

Effect of Compressor Inlet Temperature on Cycle Performance for a Supercritical Carbon Dioxide Brayton Cycle

Camera Electronics Systems

Owned and operated as a joint venture by a consortium of Canadian universities via a contribution through the National Research Council Canada

Created: 4/23/2003 Page: 1 of 12. Abstract

Experience with Small Turbomachinery in a 400 Watt Refrigerator

NLCTA Accelerator Safety Envelope

Integration issues in the tunnel and Impact on general LHC systems

STATUS OF THE LARGE HADRON COLLIDER (LHC)

CO 2 Bulk Delivery System. Team Members: Courtney Barkey, Chris Jones, DJ Lee, Dennis McBrearty, Merrill Myers

CRYO FTIR.

Review of the Magnetic Shielding Design of Low-Beta Cryomodules Bob Laxdal, TRIUMF

Continuing Research and Development of Linac and Final Doublet Girder Movers

Available online at ScienceDirect. Physics Procedia 67 (2015 )

Technical Service Bulletin IOX/DCX Transmitter Maintenance Schedule

SPLIT-SYSTEM AIR-COOLED CONDENSING UNITS DESCRIPTION FEATURES H2CA300, 360, 480 & THRU 50 NOMINAL TONS

technical catalogue tetris KW Chiller and heat pumps air/water

Vacuum isolated transfer lines for bath cryostats

Progress Towards Doubling the Beam Power at Fermilab s Accelerator Complex

HYLIAL. Range of automatic hydrogen liquefiers

Magnet. Status Report. Pablo Campero Detector Support Group

ARIEL s E-linac and beam transport line vacuum systems

Status of the Nuclotron-M project

EVT A Memo 34. ig^la MONITOR AND CONTROL SYSTEM Monitor and Control Points. George Peck

Pumping Systems for ITER, FIRE and ARIES

Electron Beam Alignment Strategy in the LCLS Undulators

Study of the impact of the remote alignment in the vacuum system

Groove Mitigation and Plans

Liquid Nitrogen Research Dewars

The Upgrade of the Northern Terminal of the Pacific NW-SW HVdc Intertie Celilo Converter Station

XFEL Bunch Compressor BC1 and BC2 Vacuum Issues

The ATLAS Detector at the Large Hadron Collider. Peter Krieger IPP/University of Toronto

Technical Information

Market Drivers for Battery Storage

PETRA III Damping Sections

HYDROVANE ROTARY VANE COMPRESSOR WITH REGULATED SPEED - THE 'RS' RANGE (7kW - 75kW)

Storage + X: Hybrid Energy Storage Systems. Overview Dan Wishnick

Development of the LPT W Concentric Pulse Tube

PACKAGED LIQUID CHILLER 6. HUMIDIFIER SECTIONS. C Member. Liquid Chiller. nowlc And noalc Series

TECHNICAL PAPER 1002 FT. WORTH, TEXAS REPORT X ORDER

NORTHERN ILLINOIS UNIVERSITY PHYSICS DEPARTMENT. Physics 211 E&M and Quantum Physics Spring Lab #6: Magnetic Fields

Reliable Temperature Compensation is Critical to CNG Vehicle Safety

Status of the ESRF RF System Repeated Ceramic Leaks on the Existing Cavities. 12 th ESLS RF meeting Diamond, 1 st -2 nd October, 2008

Carlo J. Bocchetta ESLS XIX Aarhus, Denmark November Status of Solaris

Vacuum pumps for the ESRF EBS project Michael Hahn

POWER RAMPING AND CYCLING TESTING OF VVER FUEL RODS IN THE MIR REACTOR

2015 Grid of the Future Symposium

Lithium-ion battery systems for ABB UPS solutions Reliable, lightweight and compact UPS energy storage for critical applications

Cordova Psychrophiles Bio-Digester. Benefit-Cost and Sensitivity Analysis

High- or Medium-Speed Generator Sets: Which Is Right for Your Application?

Earlier Lecture. For an optimum design of a Stirling cryocooler, a compromise between the operating and the design parameters may be sought.

Snack Foods Manufacturer Fleet EV Charging Station Program Overview. Part of the solution

1012-Electrical Diagrams

Theory Test Bronze (A)_int

Reciprocating Compressor Installation and Validation

Unitil Energy Demand Response Demonstration Project Proposal October 12, 2016

Emerging Oil Free Technologies. Ray Good Global Director of Application Engineering Danfoss Turbocor Compressors, Inc.

LHA LHA A ++ High efficiency air to water heat pumps EVI EVI EVI DC. Versions

DRIVE UNITS CATALOG TABLE OF CONTENTS

PAC 1967 HERNANDEZ: LAMINATION SHAPE FOR ALTERNATING GRADIENT MAGNET CORE 377

Extended requirements on turbogenerators

Collaboration between CELLS in Barcelona and BINP in Novosibirsk in the construction of ALBA Synchrotron

The CU Beam Test at CERN Status Report and highlights from workshop II

2011 Advanced Energy Conference -Buffalo, NY

Ballard Power Systems

Conceptual Design Report on JT-60SA Fuelling System Gas Fuelling System

Driving to Net Zero with full performance. Bob Simpson - founder and CTO of EVDrive Inc

Nuclear L.L. C. 10 CFR 50.55a

IFE Engineering Test Facility (ETF) - Opportunities for Reducing Fusion Development Costs

The Results of the KSTAR Superconducting Coil Test

REFUELING SYSTEMS AND INFRASTRUCTURE DAVID COOKE OSU CENTER FOR AUTOMOTIVE RESEARCH MARK FINNICUM - SARTA

Mobile Air Conditioning (MAC)

Development of a Superconducting High-Speed Flywheel Energy Storage System

Available online at ScienceDirect. Physics Procedia 67 (2015 )

Transcription:

QuickTime and a TIFF (Uncompressed) decompressor are needed to see this picture. QuickTime and a TIFF (Uncompressed) decompressor are needed to see this picture. QuickTime and a TIFF (Uncompressed) decompressor are needed to see this picture. Present and Future Cryogenics at Cornell Richard Ehrlich, Eric Smith, Dan Sabol LEPP, Wilson Synchrotron Lab Cornell University Ithaca NY 14853

Under PRESENT we ll discuss: cryo support only for CESR (3-6 GeV CM e + e - collider) and CLEO (the detector) operations and R&D. there s much more low-temp physics activity at CU QuickTime and a TIFF (Uncompressed) decompressor are needed to see this picture. QuickTime and a TIFF (Uncompressed) decompressor are needed to see this picture. 1

A Brief History First 4.5K operation started ~1979 with 1T, 2m-diam. X 2mlong CLEO solenoid : indirectly cooled via 100m of 1/2 tubing in series flow path. LBL-inspired, not cryogenically stable many quenches. Built by AMI. retired to BNL in ~1987 after good service, 24hrs./day 7days/week, ~52 wks/yr. Many lessons learned! Initial Plant: (2) CTI 1430 fridges with LN2 assist, (2 )93KW screw compressors. (CTI >PSI >Koch >Chart >Linde) Ping-pong OPERATION with 10-12 week cycle per fridge. Closed helium circuit, oil separation, no extra purification. 60,000 gallon (~2000 liters LHe) med. press. GHe storage. 2

A Brief History, continued.. 1988 (CLEO II era). New 1.5T, 3m diameter. 25MJ solenoid ~ 12W + 15l/hr liquefaction load at 3300 A. Built by Oxford Instruments: Thermosyphon cooled, cryo-stable, 700 l dewar, can run through power outages or fridge loss.. Unchanged fridge plant, but added extensive UPSmaintained controls: compressor 480 V breaker contacts, fault relays, engine braking.. 3

Still More, (1997-1999) SRF era, NEW plant: installed four Nb cryomodules: 1-cell, 500 MHz, 6-10 MV/m, up to 100 W each at 4.5K + 5 l/h For HEX flow. Refrigerate with 2 CCI Machines: 600W/150 l/h with LN2 reciprocating. 450-500 HP Sullair screw comp. Buy one new, one used machine. Transport 4.5K LHe as 2-phase from 2000 l storage dewar to loads ~80m away. 4

3 CCI Fridges 5

A compressor,with gas mgmnt. 6

Valve box, xfer lines, 1400 s.. 7

And then there followed Two SC final focus packages (1999-present): Each with HF, VF, and skew quads + steering~ 200W equivalent with leads and xfer lines. 12 SC wigglers( superferric) in CESR tunnel to provide Damping for CESR-c, CLEO-c era. HTSC leads, ~3W heat load, up 100m further away from plant, but still use 2-phase flow LHe. Tee into SRF supply/return. Two compensating anti-solenoids (2006) to improve CESR-c luminosity. Follow wiggler cryo design. Third (used) CCI fridge: total capacity now ~ 2kW at 4.5K 8

CESR-c West IR CLEO solenoid pole (red),sc quad cryostat (chrome) antisolenoid (blue) 9

Three SC wiggler cryostats Cryogenic Operations Worksho SLAC, May 9-11, 2006 10

and, by the way ILC Damping Ring Baseline Wiggler Recommendation: Is based on the CESR-c wiggler design. Cornell Plans: Optimize the CESR-c design for ILCDR use, adapt to Likely ILC cryoplant Prototype a realistic ILCDR wiggler 11

Present Plant Characteristics 2 kw at 4.5K, ~800W margin max. Typically, use two CCI fridges in parallel, common discharge press. for screw compressors. Siemens- Moore controls, with heater in 2000l dewar; 5% overcapacity. 6 PSIG supply pressure, ~3 PSIG return, simple 2-phase flow in 250 m-long transfer line. All cryostats, transfer lines have static vacuum. 96,000 gallon medium pressure storage. About 5000 l (equivalent). 0.6 MW + LN2 in typical mode. No cryo crew after 1630 or on weekends. 1 year interval for major maintenance on CCI machines, 12 week cycle for 1400 s. Completely UNACCEPTABLE efficiency for future Cornell plans. COP inv =562 at 4.5K vs. 200 achievable. 12

Proposed Upgrade of CESR to ERL In 2008, the particle physics experimentation at CESR will shut down. Synchrotron radiation experimentation at CHESS will continue. It is desired to make a major upgrade of the accelerator to provide a light source with capabilities 10-100 times greater than current 3 rd generation light sources. This project will involve a major extension of the existing accelerator and expansion of the infrastructure. One major feature of the new operation would be a cryogenics plant which will be roughly 20 times larger than the present system! 13

ERL Upgrade for CESR (5GeV) 6 5 8 7 1 4 2 3 14

Nature of the cryogenic loads 390 7-cell Nb 1.3GHz SRF cavities, similar to TESLA 100 ma, 5 GeV beam (cw operation) Operation at 16MV/m gradient in cavities, with average Q=2x10 10 while running at 1.8K. Higher order mode (HOM) power absorbed at 80K rather than room temperature. Expected operation 5000 hours per year for experimenters, additional 1000 hours per year for machine studies. Possible periods of operation at lower beam currents, resulting in greatly reduced HOM power. 15

Anticipated Refrigeration Requirements for the ERL at Cornell Cooling Stream Design Load (kw) Load with 50% margin (kw) Achievable COP (inv.) (W 300 /W T ) Wall Power Demand (MW) 1.8K He at 16 mbar 5 7.5 950 590 7.1 4.4 4.5K He at 3 bar 9 13.5 200 2.7 40-80K He At 10 bar 70 105 20 2.1 16

Comments on Preceding Table Design heat loads are challenging but probably achievable goals. We nonetheless need to allow a safety margin in the design of the cryogenic plant. Efficiency is highly important. With our projected cryogenics power demands drawing on the order of 10MW from the grid for 75% of the year, over the lifetime of the project the power bill is anticipated to be larger than the capital cost of the plant. The most optimistic literature estimates for the attainable efficiency of 1.8K operations are considerably more optimistic than what is currently achieved. Is there any chance for making improvements here? 17

Major question on approximate pricing A figure (originating from CERN) circulating in the recent literature suggests a refrigeration cost may be estimated as: Price (MCHF 1998 )=2.2 x (kw@4.5k) 0.6 We have heard rumors that this price is currently an underestimate. Is there a better estimation formula? Is the 0.6 power law a reasonable scaling? To determine the equivalent cost for 1.8K or 40K refrigeration, do we scale from 4.5K values by the ratio of COP at the two temperatures? 18

Several Questions for Discussion 1) Modularity. Our system demands are probably too large for a single cold box. How many subunits are likely to be optimal for construction? The load is likely to be constant (at maximum level) for the 1.8K cooling whenever the machine is in use. The 4.5K and 40-80K systems may have extended operation periods at as little as 25% of full load if operating in a low-beam-current configuration. Should the 1.8K system be operated as a completely separate system from the 4.5K/40-80K system? 19

Questions for Discussion (continued) 2) Efficiency. If we achieve design goals on heat loads, refrigerator will run at 2/3 of its design capacity. How will this affect the efficiency and stability of operation? 3) Nitrogen precooling? Total plant capacity is likely too large to truck in LN 2 for precooling (frequency and reliability of delivery, especially in winter). Is nitrogen liquefaction more efficient than helium refrigeration near 80K would on-site nitrogen re-liquefaction make a sensible component of the plant? 20

Questions for Discussion (continued) 4) Cold vs. warm compression. For the 1.8K portion of the refrigeration, at least part of the compression will be in the form of cold compression. Some large refrigeration plants use exclusively cold compression for the sub-atmospheric gas, others use a mix of cold and warm compression. What are the impacts of using exclusively cold compression on the ease of control, the adaptability to moderate variation in average heat load (both in terms of efficiency and control), and the rather different operations of cooldown and warmup? 21

Questions for Discussion (continued) 5) Helium inventory for the system will be in the range of 10,000-15,000 liquid liters. Our initial thoughts are to use primarily a single 20,000 liter dewar for storage, with an additional medium pressure storage vessel for 4,000 liters additional capacity in gas form. This arrangement would presumably require an additional small re-liquefaction refrigerator for any periods of extended shutdown. Our main reasons for thinking of using dominantly cold storage is questions of smaller footprint on the somewhat crowded campus, but capital cost also looks probably advantageous. What are the reasons that warm medium-pressure storage seems more usual? 22

Questions for Discussion (continued) 6) There will be an extended distribution system to the actual refrigeration loads, which will be 15-20 meters below the plant level, and in some cases 150-200 meters distant from the plant. We anticipate a number of remote JT valves as part of the distribution system for the 1.8K coolant. What are the efficiency implications of such a configuration? 7) In specifying system loads, somewhat arbitrary choices were made for pressures of the 4.5K and 40K gas streams. What are the efficiency implications for circulating at different pressures (densities). 23

Questions for Discussion (continued) 8) What maintenance intervals are needed for a system of this size? How many months of continuous operation can be anticipated, and what is the minimum length of time that would be expected for a warmup/cooldown cycle? 24

Ongoing Smaller Project to Test ERL Injector (Phase 1a) There is already work in progress to test the proposed injector for the ERL. By comparison with the overall project, this is a rather small perturbation on the existing cryogenic setup. It does give us experience in working with cryomodules operating at 1.8K, and will test various aspects of cooling the large heat loads on the HOM loads and input couplers with gaseous helium stream (in particular, we have demands for very low vibration levels in the final ERL). 25

ERL injector overview Max current Energy range Installed RF power Emittance goal Typical bunch length 100 ma 5 15 MeV 0.5 MW + 75 kw HV PS 0.1 1 mm-mrad 2-3 ps rms (shortest 0.2 ps) CHESS / LEPP 26

2K cooling for tests 27