Generation Interconnection Facilities Study For

Similar documents
Generator Interconnection System Impact Study For

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

100 MW Wind Generation Project

Interconnection System Impact Study Report Request # GI

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

Schneider Electric PV Skid. Optimized solar power conversion system tailored to enhance any North American PV power plant

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

MILLIGAN SOLAR PROJECT

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Feasibility Study Report

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

Sub Regional RTEP Committee Western Region ATSI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

ELECTRIC SERVICE RULES DISTRIBUTED GENERATION Issued Jan 2016

PJM Generation Interconnection Request Queue #A55 Lakewood 230kV Facilities Study Report

ABB POWER SYSTEMS CONSULTING

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Functional Specification Revision History

New 115 kv Disconnect Switches at Bloomsburg MTS

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Sunmine Solar Project. Interconnection System Impact Study

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Feasibility Study Report

Schedules 1 to 4, Lot B: Extension of the Lessos Substation

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

INTERCONNECTION FACILITIES STUDY REPORT

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

Targeted Application of STATCOM Technology in the Distribution Zone

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

Solar Power Switchgear & Energy Storage Renewable Energy Systems

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis

El Paso Electric Company

Solar Farms: design & construction

15 Nelson-Marlborough Regional Plan

Modular integrated transportable substation (MITS)

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Essential Reliability Services From PV Plants

Imperial Irrigation District Energy Consumers Advisory Committee Agenda Report

Power Purchase and Grid Connection Procedures

15 Nelson-Marlborough Regional Plan

The Power Potential Project A guide to participating

Small Generator Interconnection Program Interconnection Technical Requirements

Interconnection Process for Generation Systems

Q0044 interconnection at

Feasibility Study Report

The North Carolina solar experience: high penetration of utility-scale DER on the distribution system

Greater reliability and flexibility for large solar installations. Conext Core XC-NA series central inverters

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

PREPARED DIRECT TESTIMONY

Transmission Switching

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Implementing a Microgrid Using Standard Utility Control Equipment

LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST

DFO STATEMENT OF NEED REPORT

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

North Oregon Coast Area Study. Adam Lint

CHAPER 5 POWER FLOW STUDY IN THE INTEGRATED GRID NETWORK

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

DEMONSTRATION OF ESSENTIAL RELIABILITY SERVICES BY A 300-MW SOLAR PV POWER PLANT

CUSTOMER/ TWIN ARROWS PROJECT

PV Grid Integration Research in the U.S.

PUD ELECTRIC SYSTEM INTERCONNECTION

Training Course on Design, Installation of MW Scale Solar PV Systems & Commissioning concepts

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Review of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST

ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS. June 18, 2015 E2Tech Presentation

System Impact Study Report

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Customer Substation Manual

Wind Interconnection and Net-Metering in MA. Tim Roughan - National Grid Joe Feraci - NStar

Chapter 6 Generator-Voltage System

Sub-Regional RTEP Committee PJM South

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Feasibility Study for the Q MW Solar Project

The Role of Electricity Storage on the Grid each location requires different requirements

Merger of the generator interconnection processes of Valley Electric and the ISO;

MILESTONE SUMMARY REPORT Project funding provided by customers of Xcel Energy through a grant from the Renewable Development Fund

American Electric Power s Energy Storage Deployments

SECTION 1 DESCRIPTION OF THE PROPOSED PROJECT

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

EPRI Intelligrid / Smart Grid Demonstration Joint Advisory Meeting March 3, 2010

June Substation Refurbishment and Modernization. Prepared by: Substatiort Refu14bislrment and Modernization NP 2012 CBA

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PES Cook Islands KEMA Grid Study Final Report

Guideline on Energy Storage

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

Supply-Side PV Connections

Umatilla Electric Cooperative Net Metering Rules

3.0 Radial Distribution Systems

New Jersey State Report

Building a 21 st Century Electric Grid. February 23, 2018

Transcription:

Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015

TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications... Page 3 Scope of Work, Cost Estimates and Time to Complete... Page 4 Summary... Page 5 Figure 1 Engineer Single Line Layout... Page 6 Figure 2 Site Location... Page 7 Figure 3 SCE&G owned 46kV Switching Station General Arrangement... Page 8 Figure 4 SCE&G owned 46kV Switching Station Switching Configuration... Page 9 2

Generator Interconnection Facilities Study For Project in SC A Generator Interconnection Facilities Study follows the previous Generation Interconnection System Impact Study, and specifies and estimates the cost of the equipment, engineering, procurement and construction work needed to implement the conclusions of the Generator Interconnection System Impact Study in accordance with Good Utility Practice to physically and electrically connect the Interconnection Facility to the Transmission System. A Generator Interconnection Facilities Study also identifies the electrical switching configuration of the connection equipment, including, without limitation: the transformer, switchgear, meters, and other station equipment; the nature and estimated cost of any Transmission Provider's Interconnection Facilities and Network Upgrades, if necessary, to accomplish the interconnection; and an estimate of the time required to complete the construction and installation of such facilities. General Discussion has requested a Solar Photovoltaic (PV) plant in Hampton County. This solar facility has a total generation capacity of 8.16 MVA, consisting of (12) Schneider Electric Conext Core XC680-NA 680 kva solar inverters. group has requested an in service date of 10/1/2016 and that this generation be interconnected to the existing SCE&G 46 kv transmission system at a site near the. A previous Generator Interconnection System Impact Study was conducted to determine the ability of the SCE&G transmission system to interconnect the Generator to the Transmission System and to address any identified power flow, short circuit and instability issues. In that System Impact Study, facilities were identified that would require modifications in order to provide the requested Generator Interconnection. This Facilities Study identifies the cost and scheduled completion date of those modifications needed to provide the requested Generator Interconnection. Generator Interconnection Specifications The solar generation facility design consists of the following information: MVA: 8.16 MW: 8.16 PF: 80% lead/lag GSU: 46/26.56 kv (Wye-Wye) Speed: N/A 3

Scope of Work, Cost Estimates and Time to Complete The Table below includes the scope of work, cost estimate and time to complete for the transmission improvements required to provide the requested Generator Interconnection. Time to Complete includes design, drafting, ordering equipment, issuing drawings for construction, issuing drawings, lead time for equipment and construction. (Note that the installation of some equipment may require planned outages of transmission facilities. The ability to schedule an outage and perform the installation is subject to review and is based on transmission system conditions at the time of installation.) Scope of Work Estimated Cost 1 Complete 2 Time to Make modifications to the SCE&G transmission system to provide a radial Generator Interconnection off of the adjacent to project. (See Figure 1, 2, 3 and 4) - Construct an SCE&G-owned 46 kv switching station including, but not limited to, a 46 kv Circuit Breaker, structures, foundation, switches, PT s, CT s, batteries, revenue quality metering, SCADA, station service, lightning arresters, gravel, fencing and ground grid. - Install a Triple Suspended Pull Off (TSPO) wood pole in the center line of the line adjacent to project. Install two spans of transmission conductor from the TSPO to a structure in the SCE&G-owned 46 kv switching station. This cost assumes the SCE&G-owned 46 kv switching station is adjacent to or within 150 ft of the R/W. The cost does not include R/W procurement due to the unknown location of the station. - Make modifications at the Transmission Substation to accommodate reverse power flow through the transformers. $712,300 10 months $65,000 8 months $8,000 3 9 months TOTAL Required for Generator Interconnection $785,300 10 months 1. Estimated Costs based on future required In-service date. Costs do not include site cost, site preparation, road access or Right of Way procurement if needed. 2. Time to complete based on normal lead times for structures and major equipment and timing to allow an off-peak outage of the Estill-Estill 46 kv line. Time to Complete does not include time to acquire site, prepare the site and/or acquire Right of Way if needed. 3. The need for this modification exists in higher priority generator interconnection requests and may be completed as part of a generator interconnection that has a higher position in the generator interconnection queue. If the higher position generator interconnection request continues, then this modification may not be required as part of this generator interconnection. 4

Summary This Generator Interconnection Facilities Study has identified the cost and scheduled completion dates of the modifications needed to provide the requested Generator Interconnection. The 10 month Time to Complete, as shown above, will commence after all appropriate agreements have been signed. 5

6

7

8

9