STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD

Similar documents
The Narragansett Electric Company. d/b/a National Grid (Interstate Reliability Project) RIPUC Dkt. No Testimony of. David M. Campilii, P.E.

JCP&L Verbatim Response to Middletown Township s Questions

Mystic to Woburn Line Project. Town of Winchester Board of Selectmen Lincoln School Auditorium February 11, 2016

City of Palo Alto (ID # 6416) City Council Staff Report

SECTION 1 DESCRIPTION OF THE PROPOSED PROJECT

APPENDIX E: ELECTRIC AND MAGNETIC FIELDS MANAGEMENT PLAN

BEFORE THE NEW JERSEY BOARD OF PUBLIC UTILITIES

Challenges With Underground High Voltage Transmission SCE Tehachapi Renewable Transmission Project First 500 kv Underground T/L in North America

THORNTON SUBSTATION. Why is the substation needed? How were the three potential sites identified?

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO.

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

SECTION 14 TRANSMISSION LINE ROUTE / CONFIGURATION ALTERNATIVES

EXAMINERS' REPORT AND PROPOSAL FOR DECISION STATEMENT OF THE CASE

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

3.0 Radial Distribution Systems

SURREBUTTAL TESTIMONY & ATTACHMENTS

Q. Are you familiar with the matter which is the subject of this petition? A. Yes, I am.

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS PUBLIC UTILITIES COMMISSION IN RE: NEW ENGLAND GAS COMPANY DOCKET NO ANNUAL GAS CHARGE FILING

STATE OF NEW HAMPSHIRE Inter-Department Communication

Appendix D Black Hills Project Summary

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

Energize Eastside. Underground transmission lines and EMF webinar. Leann Kostek. Senior Project Manager, Puget Sound Energy

West Station-West Cañon 115 kv Transmission Project

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO.

When power interruptions happen.

National Grid 2017 ELECTRIC RETAIL RATE FILING. Consisting of the Direct Testimony and Schedules of Adam S. Crary and Tiffany M.

STATE OF MINNESOTA ENVIRONMENTAL QUALITY BOARD MEQB DOCKET NO. MP-HVTL-EA-1-99

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Thank you for your time and attention to this matter. Please feel free to contact me if you have any questions regarding the filing.

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

Public Opinion of Waterloo Region Rapid Transit Proposal May 2011

Application of Primary Fuses

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD

Rocky Mountain Power Docket No Witness: Gregory N. Duvall BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE

STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION DOCKET NO. ET6675/CN OAH DOCKET NO REBUTTAL TESTIMONY

3 Reliability Issues and Solutions

Tom Parece, Reggie Donoghue and Mike Domenica P. R. Ammann

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Proposed New ISO Rules Section Version 2.0 Generating Unit Technical Requirements ( New ISO Rules Section Version 2.

PUBLIC SERVICE COMMISSION OF WEST VIRGINIA %% CHARLESTON

MILLIGAN SOLAR PROJECT

Idaho Power s Proposed Second Transmission Line Warrants Additional Analysis

Unitil Energy Demand Response Demonstration Project Proposal October 12, 2016

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS PUBLIC UTILITIES COMMISSION

ROCKY MOUNTAIN POWER A DIVISION OF PACIFICORP

Seabrook Substation Reliability Improvement Project

Code Calculations. for an Off-Grid PV System

The Capital Grid Project:

Public Information Centre

ACTION TRANSMITTAL No

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan

OIL AND GAS DOCKET NO

SPEED CUSHION POLICY AND INSTALLATION PROCEDURES FOR RESIDENTIAL STREETS

What exactly are next-generation meters?

BEFORE THE CANTERBURY REGIONAL COUNCIL. Act 1991 AND. of Plan Change 3 to the Waitaki Catchment Water Allocation Regional Plan

Regulatory Treatment Of Recoating Costs

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

D.P.U A Appendix B 220 CMR: DEPARTMENT OF PUBLIC UTILITIES

BOARD OF ZONING ADJUSTMENT STAFF REPORT Date: November 7, 2016

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

100 MW Wind Generation Project

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

AEP Ohio Distribution Reliability and Technology Programs

P&C Flex. Non-Metallic Rigid Conduit, Fittings and Accessories. Corrugated Flexible Conduit. Applications

Appendix M-2 EMF from Underground and Overhead Transmission Lines on Block Island

STATE OF NEW HAMPSHIRE BEFORE THE NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION RE: PENNICHUCK WATERWORKS, INC. DW 13-

Minnesota Public Utilities Commission Staff Briefing Papers

Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications

Frequently Asked Questions October 2012

February 10, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

PREPARED DIRECT TESTIMONY

Title 24: Building Codes for Plug-in Electric Vehicles September 22, 2015 Webinar Questions

Building a 21 st Century Electric Grid. February 23, 2018

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) APPLICATION

PUBLIC REDACTED VERSION

UNDERGROUND SERVICE. Items to consider. There will be charges from ComEd if you convert from overhead to underground service.

FILED. IN THE MATfER OF THE APPLICATION OF 1 AND CONSTRUCT A 161 KV TRANSMISSION LINE )

(2) Scope. 220 CMR applies to all Distribution Companies subject to the jurisdiction of the Department.

Electric Service Conversion Overhead-to-Underground Xcel Energy Electric Connections. Minnesota North Dakota South Dakota

DFO STATEMENT OF NEED REPORT

Kake - Petersburg Intertie Update

March 31, 2014 VIA HAND DELIVERY & ELECTRONIC MAIL

CHAPTER 8 - GAS AND ELECTRICITY TRANSMISSION COMPARATIVE CASE STUDY

Sub Regional RTEP Committee Western Region ATSI

Low Speed Design Criteria for Residential Streets Andrew J. Ballard, P.E. and David M. Haldeman, E.I.T.

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit

Transmission Expansion Advisory Committee

Docket No EI Date: May 22, 2014

ABB POWER SYSTEMS CONSULTING

Frequently Asked Questions Leander-Round to Rock 138-kV Transmission Line Project Williamson County

April 18, Mr. David Schmit, County Manager Arapahoe County 5334 S. Prince Street Littleton, CO Conoco Phillips Section 6 Swan Well

STATE OF MINNESOTA ENVIRONMENTAL QUALITY BOARD

For Conduit Inspections

Included in this Stakeholder Information Package:

application of Robert Mosbacher asking that he be authorized to complete and produce the well hereinafter described in the Smackover

Zero Emission Bus Impact on Infrastructure

CUSTOMER/ TWIN ARROWS PROJECT

Transcription:

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD In re : : Docket No. SB-00-0 () : Testimony of David M. Campilii, P.E. June, 00 PROV--

0 0 TESTIMONY OF DAVID M. CAMPILII, P.E. Q. Please state your full name and business address. A. My name is David M. Campilii. My business address is 0 Sylvan Road, Waltham, MA. Q. Have you previously testified in this matter? A. Yes. I filed prefiled testimony in RIPUC Dkt. No. 0 on February 0, 00. I understand that the prefiled testimony in RIPUC Dkt. No. 0 will be incorporated in this hearing. I also filed rebuttal testimony in SB-00-0 on June, 00 regarding this matter. Scope of Testimony Q. What is the purpose of your testimony? A. The primary purpose of my testimony is to address issues pertaining to underground alternatives that have arisen during the various Zoning and Planning Board hearings for the. Q. Please describe the underground alternative issues that have arisen. A. The primary underground alternative issue pertains to the installation of short underground segments, commonly referred to as dips, along portions of the overhead transmission project route. This has taken the form of statements or requests to the effect of Just put the line underground past my house, neighborhood, town, etc. Q. Mr. Campilii, please describe in general what is required to underground a section of kilovolt (kv) overhead transmission line. A. Although lower voltage distribution lines are frequently installed underground, installing an underground dip in a kv transmission line requires much more significant

0 0 construction. Putting a segment of kv transmission line underground also creates operational issues for the overall transmission system. In many cases, it is not possible to match the power ratings of an overhead transmission line with a single underground cable, so it is often necessary to install two or more cables to match the overhead line. Underground cables have substantially longer repair times than overhead lines (typically to hours for overhead lines, a month or more for underground lines at kv). Because of this, and because transmission lines serve much larger geographic areas than distribution lines, more than one underground cable may be required per overhead line to provide for a faster restoration in the event of a transmission cable failure. Underground cables also have different electrical characteristics than overhead lines, which may require the installation of additional substation and line equipment. These effects become more significant as the length of the underground line increases. At both ends of an underground kv dip, it is necessary to construct a transition station. Each transition station provides a means to connect the overhead line to the underground cables. The transition station also provides space for additional equipment (switches, circuit breakers, protective relaying equipment, etc.) required to operate the overall hybrid overhead/underground system. These transition stations have the appearance of an electrical substation. Installing an underground transmission cable dip requires trenching the entire segment length between the transition stations to install the conduit and manhole system. The trenching could occur either along the ROW (if suitable), or along established roadways (if available). Areas with wetlands or water bodies would require special construction

0 0 techniques, as further described in Section of the ER. Underground construction in such resource areas has the potential to cause much more significant impacts to the resource than would overhead construction, which can often span resource areas or only cause marginal impacts at structure sites. Once the conduit system was in place, transmission cables would then be pulled into the conduits, spliced in manholes, and terminated in the transition stations. Q. Mr. Campilii, please describe the form that an underground kv transmission dip would take for the. A. If an underground dip were to be installed as a segment in the proposed Project, the existing overhead kv line (the line) and the two existing overhead kv lines (the S and T lines) on that segment of ROW would remain in place. For the new kv line, National Grid would require two kv cables to underground the single overhead line. We have preliminarily sized the cable as,000 kcmil copper, and have preliminarily selected a solid dielectric (cross linked polyethylene, or XLPE) cable system. The conduit system would consist of six inch polyvinyl chloride (PVC) conduits, with several smaller auxiliary conduits, installed in a trench approximately feet wide and feet deep. Manholes, 0 feet wide and 0 feet long, would be required at approximately,00 foot intervals for splicing the cables. Transition stations would be required at both ends of the dip. For the Rhode Island Reliability Project, each transition station would require a fenced area of approximately one acre, with additional space required for setbacks, access roads, etc. The fenced area would contain the overhead line dead end structure, the underground transmission cable

0 0 risers, kv switching equipment, and a control building. There is not enough room on the ROW to fit the transition stations, so a suitable site, approximately. to acres in size, and located adjacent to the ROW, would be required at both ends of a dip. Each transition station site would have to have access to the overhead transmission line and to a suitable underground transmission route. Access to a public road would also be required for operation and maintenance of the transition station equipment. Suitable sites meeting all of these criteria would have to be identified and purchased by the Company. Q. Mr. Campilii, please discuss the costs of an underground kv dip for the Rhode Island Reliability Project. A. The Company developed a study grade cost for underground dips for the Rhode Island Reliability Project. For illustration purposes, National Grid examined a half mile long and a one mile long generic dip. By generic, we mean that the dips are not tied to a particular location along the ROW, but are intended to give a representative idea of the cost of a dip. National Grid has estimated that each kv overhead to underground transition station will cost approximately $. million each, not including the cost of the land for the transition stations. Each dip requires two transition stations. The underground transmission cables and duct line system is estimated to cost approximately $ million for a half mile dip, and $ million for a mile dip. In total, a half mile dip with the two associated transition stations would cost approximately $0 million. A one mile dip with the two associated transition stations would cost approximately $ million. These costs would not include the cost of the transition station land, or any additional land or land

0 0 rights required for the dip. Unusual construction (wetlands, water crossings, heavy underground utility density, significant rock, etc.) would increase these costs. The equivalent overhead line cost for rebuilding the two kv lines and constructing the new kv overhead line (the Project) is approximately $. million per mile, or $. million per half mile. The underground dip alternative, therefore, represents a substantial cost increase as compared to an equivalent length of overhead installation. For a mile segment, the underground dip is nearly four times the cost of the overhead line as proposed in the Project. Q. Does putting a transmission line underground eliminate magnetic fields? A. No. Magnetic fields are present for both overhead and underground transmission cables. Magnetic fields over an underground dip are expected to be comparable to or perhaps higher than the edge of ROW fields associated with the proposed Project. Q. In its unfavorable advisory opinions pertaining to the Project, the West Warwick Zoning Board has made a number of statements regarding installing underground transmission dips in West Warwick. Please respond to the West Warwick s Zoning Board assertion that the relief to be granted [i.e. the height variance] is not the least necessary in that portions of the area of the transmission lines could be underground, eliminating the concerns stated, for a nominal increase in cost. A. We disagree with these assertions. The West Warwick Zoning Board was under a mistaken impression that a short segment of the project in West Warwick could be placed underground for a cost of $ million, a number that apparently was first mentioned by a member of the public during public comments at the Town Planning Board meeting. As

0 0 discussed above, we have estimated the cost to underground a half mile segment of kv line at approximately $0 million, and a mile length at approximately $ million and I testified about the magnitude of these costs to the Zoning Board. We further disagree with the assertion that this will have minimal effect on the ratepayer, as stated in the Planning Board s advisory opinions. The as proposed is expected to qualify for regionalization of costs under ISO New England rules, meaning that the project costs will be spread among all electric customers in New England. If a local requirement for undergrounding were to be imposed on the Project in an area where the project could be constructed overhead, it would be very unlikely that ISO-NE would allow for regionalization of the additional underground costs. ISO-NE would more likely allow regionalization of the equivalent overhead line costs, and the balance of the costs would be borne locally. As an example, if West Warwick required a half mile segment to be placed underground in an area where National Grid had ROW for an overhead line, (underground cost $0 Million), ISO-NE would likely only allow regionalization for the equivalent overhead cost ($. Million). West Warwick or Rhode Island ratepayers could potentially be exposed to the additional $. million cost. We don t feel that this is a minimal effect on the rate to the consumer, as asserted by the Planning Board. Q. Please comment on the West Warwick s Zoning Board assertions that (i) National Grid s primary objection to placing portions of the transmission lines underground is based on the increased time required to repair breakdowns and that National Grid testified that breakdowns were so infrequent that it could not present evidence of the number of times

0 0 or places where such breakdowns occur indicating that the concern for breakdowns is negligible and (ii) because the purpose of the new kv line is to have a redundant transmission line, a breakdown in the underground portion would not be a problem because the existing overhead line will constitute the redundant line to provide service during the time of breakdown. A. Breakdowns (outages) are relatively infrequent on both overhead and underground transmission lines. Even though transmission outages are infrequent, they do occur. National Grid must evaluate the effect of transmission outages on the overall electric supply system. The reliability standards to which National Grid is held include evaluation of the loss of a single transmission component, and after an adjustment of generator output and transmission switching, the subsequent loss of a second transmission component (called N-- criteria). One significant difference between overhead and underground transmission lines is the length of time it takes to repair an outage. At kv, a typical overhead transmission outage can be repaired in hours or less. Underground kv transmission cable repair time is measured in the month or more timeframe. This increases the exposure of the transmission system to the second contingency for a much longer period of time. Transmission lines serve large blocks of load (entire cities, or in the case of the, a significant part of the state of Rhode Island). During the extended time period that an underground transmission line is out of service, the remainder of the transmission system would be operating at higher than normal loads, and possibly at emergency loading. This increased strain on the transmission system may increase the likelihood of a second contingency

0 0 (outage) occurring, which could result in voltage collapse and blackouts across a significant portion of the state. This exposure would exist for a much shorter time period under the proposed overhead line project. Q. Please discuss the West Warwick Zoning Board s assertion that National Grid has the option of placing the new transmission lines underground for the entire West Warwick route or only in areas where transmission lines will be located next to residential properties, thereby rendering a beneficial use that is not more than a mere inconvenience and the assertion that The hardship that will be suffered by the applicant if the dimensional variance is not granted as opposed to the burying of the transmission lines for which the variance will not be required will not amount to more than a mere inconvenience. A. Placing portions of the kv transmission line underground through West Warwick would significantly increase the cost of the Project, and the majority of these increased costs would likely have to be borne by the West Warwick or all Rhode Island electric ratepayers. Further, installing underground segments would expose portions of the transmission system to more extended outages than they otherwise might experience, which potentially affects the reliability of the electric supply to a significant portion of the state of Rhode Island. Finally, our underground dip would likely increase the environmental impacts associated with the Project. We believe that this constitutes more than a mere inconvenience to National Grid, to the ratepayers of West Warwick, and to the electric customers in the larger (statewide) region. Q. Does this conclude your testimony?

A. Yes.