Black StartDrill in Eastern Regional Power System-Case studies

Similar documents
Report. the feasibility of

Infrastructure Revitalization in India Power System Operation Corporation (POSOCO) New Delhi, India

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

HVDC Systems in India

15 Nelson-Marlborough Regional Plan

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

TRANSMISSION PLANNING CRITERIA

100 MW Wind Generation Project

Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008

The Electric Power System

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Dynamic Study of Bonaire Island Power System: Model Validation and Project Experience

4,1 '~ ~ ~ 1I1f lc/)~ul I Central Electricity Authority

Guide to Restoration. Marketplace Training

Agenda for Connectivity and Long Term (Open) Access of IPP Generation Projects in Odisha of Eastern Region

(i) Establishment of 400kV Pooling Station at Fatehgarh (with a provision to upgrade at 765kV level)

TRANSMISSION CAPACITY ADDITION PROGRAMME DURING No. 1 Introduction 1

National Research Council

Computer Aided Transient Stability Analysis

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Derrick Boltt Southern Region Hydro Generation Eskom South Africa

Use of High-Power Thyristor Technology for Short-Circuit Current Limitation in High Voltage Systems

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden

Seabrook Substation Reliability Improvement Project

2013 Grid of the Future Symposium. Utilizing Single Phase Operation Scheme on Untransposed 765kV lines for a Stability-Limited Plant

ABB POWER SYSTEMS CONSULTING

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC

STABILIZATION OF ISLANDING PEA MICRO GRID BY PEVS CHARGING CONTROL

Western Power s list of exemptions from compliance from Technical Rules granted after 1 July 2007.

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Exemptions currently in force

EPRI Intelligrid / Smart Grid Demonstration Joint Advisory Meeting March 3, 2010

Operational Objectives

Cigre SC B4 Activities Towards HVDC Grids. HVDC Grid Workshop Belgium

Western Alberta Transmission Line (WATL) HVDC Project

Maharashtra State Load Despatch Centre. Partial Grid Disturbance in Mumbai system on 18 th Nov-2010 at 17:45 hrs and 21 st Nov-2010 at 17:10 hrs

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1

Mikael Dahlgren, ABB Corporate Research, 02 December 2011 ABB Technology providers perspective Energidagen Chalmers Energyinitiative

Small Electrical Systems (Microgrids)

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

Agenda of 11 th System Studies Meeting in NER

15 Nelson-Marlborough Regional Plan

American Electric Power s Energy Storage Deployments

A. Operational Issues relating to recent Disturbances in Gajuwaka Simhadri - Kalpaka corridor

Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study

Guidelines for connection of generators:

STATE LOAD DISPATCH CENTRES (SLDC)

CHAPER 5 POWER FLOW STUDY IN THE INTEGRATED GRID NETWORK

DYNAMIC BEHAVIOUR OF SINGLE-PHASE INDUCTION GENERATORS DURING DISCONNECTION AND RECONNECTION TO THE GRID

Climate change drivers for a single and smart EU grid

Northeast Wisconsin/Upper Peninsula Separation 11/14/01. Incident Investigation Report

Smart Grid Automation and Centralized FISR

DESCRIPTION OF REQUIREMENTS FOR GENERATION SYSTEMS SEEKING TO PROVIDE SYSTEM RESTART SERVICES

Review paper on Fault analysis and its Limiting Techniques.

Island operation. tel

SUBSTATION DESIGN TRAINING

SSF Section Location of Change SSF Issue Change(s) Comments Chapter Part B All Multiple Formatting, spelling and minor Changes applied -

The Evolution of System Protection Schemes for the Sarawak Power System By Victor Wong Sarawak Energy Berhad Presented at PQSynergy 2012, Sarawak

Indian Power System Framework

Power System Restoration with Black-Start Pump Storage Power Plants

Wide area monitoring and control activities in Norway and the Nordic power system

MINUTES OF THE 47 th SLCF MEETING HELD ON

Power Conditioning of Microgrids and Co-Generation Systems

Variable speed control of compressors. ABB drives control the compressors of the world s longest gas export pipeline

Georgia Transmission Corporation Georgia Systems Operations Corporation

Performance Analysis of Transient Stability on a Power System Network

Micro Grids, Renewable Generation, Electric Power Resiliency

Hardware Testing of Photovoltaic Inverter Loss of Mains Protection Performance

PES Cook Islands KEMA Grid Study Final Report

SYSTEM INTEGRATION. Railway and urban transport electrification Energy-efficient and reliable solutions

A comparison of metal-enclosed load interrupter (ME) switchgear and metal-clad (MC) switchgear

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Integrating Embedded Generation into distribution networks. Mobolaji Bello and Dr Clinton Carter-Brown Eskom Holdings Limited South Africa

The Long-Range Transmission Plan

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

ISLANDING SCHEME FOR STATION DURING GRID BLACK-OUT

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

PRAGATI ENGINEERING COLLEGE

Elia Ancillary Services: Black-Start

Understanding the National Power Grid and How it Impacts Timeframes for Power Restoration

Advanced Protective Relay Training

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

POWER SESSION. DP3 Class Power System Solutions for Dynamically Positioned Vessels

List of exemptions from compliance with the Technical Rules granted by Western Power after 1 July 2007

Interconnection Feasibility Study Report GIP-226-FEAS-R3

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011

Karl Elfstadius, ABB Smart Grid Program Mmanager / SMART GRID TAIWAN, Smart Grid Overview. ABB SG_Presentation_V4.

III. Substation Bus Configurations & Substation Design Recommendations

HVDC Multi-Terminal Interconnections a viable and optimal solution for India

Distributed Energy Resources

Final Written Examination.

Dual Power. Protection. Protection

Grid Integration Costs: Impact of The IRP Capacity Mix on System Operations

Transmission Planning for Wind Energy Resources in the Eastern United States. Dale Osborn

Development and Demonstration of Redox Flow Battery System

Transcription:

Black StartDrill in Eastern Regional Power System-Case studies P.Pentayya * U.K Verma ** GopalMitra*** M.Thakur****S.Sahay ***** Abstract:The phenomenal increase in complexity of integrated power system operation demands more reliability in supplying of bulk power. The forced outages of power system elements due to faults in a grid are practically unavoidable. Widespread propagation of such disturbances in a system may affect the healthy part of the grid eventually leading to a partial or a total collapse of a system. As mandated in Indian Electricity Grid code(iegc)[1], the restoration plans for all the regional grids are in place. Such restoration plans are being finalized and reviewed with due discussions with all the state as well as central utilities system. However, once a restoration plan is developed it requires a periodic drill to evaluate the plan that provides a measure for an utilities ability to respond to a real time situation besides validation of its plan[2]. Eastern Regional Load Despatchcentre in coordination with utilities have conducted such drills at different hydro stations of having black start capabilities. This paper discusses the experience gained for such exercises carried out. Keywords: - restoration, Indian Electricity Grid code, black start, HEP, voltage, frequency. I.INTRODUCTION LACK Start is the procedure to recover from a Btotal or partial collapse of the transmission system which has caused an extensive loss of supplies. In the event of a partial or total collapse of the transmission system, the general principle of recovery includes reestablishment of isolated power stations through black start to provide power islands. These are then integrated into larger sub-systems eventually allowing the re instatement of the whole regional or national grid system. By having this capability at a number of strategically located sites, electrical supplies can be rapidly restored. In general, all power stations need an electrical supply to start up. Under normal operation this supply would come from the transmission or distribution system while under emergency conditions Black Start stations (Generally Hydro) through itsself-start facilities provide this electrical supply.normally P.Pentayya*:GM,Western regional Load Despatch Centre(WRLDC) UK.Verma**GM, Eastern Regional Load DespatchCentre(ERLDC) GopalMitra***,DGM, ERLDC Manoj Thakur****, Sr. Engr ERLDC SauravSahay*****, Engr. ERLDC these auxiliary supplies are provided by a small hydro plant, gas turbine or a diesel plant, the minimum size of which is dependent on the size of the main Generating units, which in turn is started from a battery or some other form of energy storage device. II. RESTORATION IN EASTERN REGION The restoration procedures prepared [3] and made available atstate Load Despatch Centre (SLDCs) and Regional LoadDespatch Centre (RLDC) define restoration paths forextending start up power to each power station clearly alongwith alternative paths and priorities of paths. The priorities aregenerally decided based on usage of short line sections andlower voltage lines.geographically the Hydro power stations of Eastern Region having Blackstart facilities are mainly located at the North East corner and at the southern part of the region. This renders a major challenge of extending start up power to the large thermal power stations which are geographically located in the Central zone. The Fig 1 shows the locations of the hydro power stations of Eastern Region having black start facilities and major thermal stations Black start facilities are available in Power station as shown in Table 1. Figure:1 Location of major power plants in eastern region 1

TABLE:1 GENERATING STATIONS IN EASTERN REGION HAVING BLACK- START FACILITY Power Capacity Unit Start up stations Subarnrekha ( Stage I) Jharkhand SEB Maithon (Damodar Valley Corporation) Rengali (OHPC) Indravati (OHPC) Jaldhaka Rammam TCF Purulia Rangit (NHPC) Teesta V NHPC) MW type 2X65 Hydro Diesel sets 2x250KW 3x20 Hydro Battery 5x50 Hydro Diesel sets 400KW & 500KW 4x150MW Hydro Diesel sets 2x500kVA 3x9+4x2 Hydro Diesel sets 200KVA & 230kVA 4x12.5 Hydro Diesel sets 2x310kW 9x7.5 Hydro Diesel sets 4x225 Pumped storage hydro 750kVA Diesel sets 3x20 Hydro Diesel 312.5 kva 3x170 Hydro Diesel sets 2x500kVA III DRILL STRATEGIES Strategic choice for SystemRestoration in the event of a major failure could be build up strategy or a build down strategy [6]. In the Build up strategy the black start facilities are used to extend supply to the rest of the system whereas Build down strategy suggeststo avail supply from the healthy neighboring system for restoration. While planning the various mock drill exercises of the Eastern Regional Grid both such strategies were attempted. The various drills defined their respective content and objectives. While the primary objective was to evaluate theexisting emergency restoration plan the drills to start with aimed at building confidence amongst power plant operators. The other objective was to assess there readiness and response of the operators involved during the exercises. The mock Black Start drillsconducted in Eastern Region during the year 2010, 2011& 2012 is shown in Table 2.While all the exercises was to build an island using black start facility, operate it stably and finally synchronizing with rest of the grid using build up strategies, the start up exercise carried out for Indravati HEP on 24.3.11 used the build down strategy when power was extended from Southern Regional grid using HVDC AC bypass at Gazuwaka.In this paper three such mock drill exercises at Tessta V, Indravatiwithstart up using black start facility and AC bypass at HVDC Gazuwaka have been discussed TABLE: 2 MOCK BLACKSTART DRILLS Sl Generating station Date of drill No 1 Teesta V 22.04. 2010 2 Maithon HEP 02.07.2010 & 14.10.2011 3 Rengali HEP 09.03.2011 4 Indravati HEP 10.2.2012 5 Subarnrekha HEP 19.11.2011 6 Indravati HEP through Gazuwaka HVDC by pass 24.3.2011 IV. CASE STUDIES ON MOCK BLACK START DRILL A) Black Start of Teesta-V on 24th April 2010. Teesta V is a run of river type hydro generating stationbuilt on snow fed river Teesta. The power station is connected to the grid through 400 kv twin moose D/C line of115km length at Binaguri substation of Powergrid.The 400kV and adjoining 220kV network around Teesta V and Binaguri S/S is shown at Fig: 2 Figure 2: Network around Binaguri s/s Teesta V is having an installed capacity of 3 X 170 MW with a GIS based switchyard with one and half breaker scheme. The station strategically located with its 400kV connectivity at Binaguri S/S of POWERGRID that feeds around 200MW of load of West Bengal. The restoration Mock drill thus envisaged curbing out a portion of the West Bengal system Load to form an island. However, because of certain problems envisaged bywbsetcl,the 2

formation of the island not was considered.the mock drill was thus revised to attempt blackstart of one unit at Teesta V to extend power at Binaguri, Necessary bus splitting arrangement as envisaged is shown at Fig 3 Fig:4Binaguri Bus II and Teesta Bus I Voltage Figure 3: Switching arrangement at Binaguri 400 kv S/S Similarly bus splitting arrangement at Teesta V was also planned with an objective to keep one running machine on bar and to continue feeding power at 400kV Bus II of Binagurithrough the 2 nd feeder of Binaguri. In order to contain the voltage, it was decided to preclose the 63MVAR bus reactor with Teesta I feeder. The system synchronization was planned at Binaguri by way of closing the tie breaker of Teesta I and Bongaigaon II. At 12:01 Hrs the exercise commenced with desynchronisation of Unit 3 ( to be taken into service through black start) and making the Bus 1 of Teesta dead by opening of Binaguri feeder1. However, while attempting to do so an induced EMF of 40-45 kv was observed. While detailed feed back from the station is still awaited it is expected that a 10% induce voltage could be a common phenomenon in a GIS substation. Eventually, the entire drill plan was revised and was decided to make the station completely dead. At 13:27Hrs the unit 3 of Teesta was black started and power was extended to Bus 1 of Binaguri. The excitation was well controlled and the post charging voltage at Bus 1 at Binaguri was observed as 371 kv(vide FIG 4). The voltage was raised gradually to 392kV at 13:52 Hrs and at 13:54 Hrs the tie breaker between Teesta 1 and Bongaigaon 2 at Binaguri was closed for synchronization(vide FIG 5). The MW and MVAR plots for Teesta Generators are shown at Fig: 6 Figure: 5 Island Synchronization of two systems Figure 6: Mw and Mvar plots for Teesta generation B) Extending start-up power to Indravati HEP from SR grid through AC bypass at HVDC Gazuwaka on 24 th March 2011. Indravati hydro Power station in South Orissa has installed capacity of 150X4 MW and it has connectivity with Theruvali by four ckts of 220KV and with 400KV Indravati Power grid sub-station circuit diagram shown in Fig.7 3

RENGALI(PG) MERAMUNDALI switching off the bus coupler and connecting 400 kv Jeypore Meramandali, 2x 315 MVA ICT to bus I. The bus reactor was kept pre-closed to dead bus to control charging over voltage. 50 INDRAVATI(PG) 2x315 IND(O) 71 4x150 63 JAYPORE(PG) 90 80 458 2X315 136 130 7 220 THERUVALI 190 6 JAINAGAR 2x80 171 BHANJNAGAR NARENDRAPUR U.KOLAB 4X80 MW GAZUWAKA 93 24 BALIMELA Figure:7 Schematic SLD for Indravati HEP & adjoining Substations 6X60+2x75 MW U. SILERU One of the major challenges for extending start up power to Indravati through AC bypass link involved huge number of switching operations. The mock drill commenced from 09:45 Hrs The basic plan for the drill was envisaged in consultation with Indravati HEP, Jeypore S/S,OPTCL SLDC. Jeypore-Gajuwaka-I was to be charged from Gajuwakaend, after obtaining final clearance from Jeypore(PG). As estimated by SRLDC, the shortcircuit capacity of Gajuwaka(South) bus being of the order of 10,000 MVA, thus the voltage rise at Gajuwaka was expected to be around 2 kv, while the rise along the line of the order of 5kV. As an alternate measure it was also planned that the line CB of 400kV Jeypore-Gajuwaka-II at Jeypore and main CB of the 63 MVAR bus reactor at Jeypore to be kept pre-closed, thereby ensuring that the reactor acts as a line reactor for the line, thus help controlling overvoltage issue. The study further suggested that Jeypore voltage after charging from Gazuwaka shall have to be maintained within 415kV. The voltage of Jeypore bus was expected to rise further by around 9 kv, while the rise along the line will be of the order of 1.5 kv with charging of 400kV Jeypore- Indravati(PG) section. a) Bus Switching operation at Jeypore sub-station. 400 kv Jeypore is having one and half breaker bus scheme. First both the 400 kv JeyporeGazuwaka lines were switched off after making the power orderof HVDC Gazuwaka B/B to zero. Subsequently 400 kv Jeypore-Indravati(PG), Indravati(PG)- Rengali and Indravati HEP was switched off. This results in a complete blackout of 400 kv Indravati (PG) substation. Bus-II at Jeypore was made off by b) Switiching operation at UIHEP switchyard 400 kv side of Indravati HEP has one and half breaker bus scheme while 220 kv side is having two main and one transfer bus scheme. Unit 2 was identified as the machine to be black started. By around 10:56 Hrs, 400kV IndravatiHEP Indravati (PG) S/C line, 400/220kV ICT-II ( ICT I was already under shutdown) were switched out and 220 kv transfer bus was disconnected from main 1 and main 2with desynchonisation of Indravati Unit 2. 220 kv Theruvali circuits and other units at UIHEP (1, 3 & 4) remain connected to 220kV mainbus I & II. With the aforesaid switching operations, the system was ready for availing start up power through AC Bypass at Gazuwaka to be extended up to Indravati HEP 220kV Transfer bus. Figure 8: Start up route of Indravatihep via HVDCgazuwaka bypass c) Extension of Startup power. Gazuwaka East Bus was charged by bypassing B/B HVDC at Gazuwaka at 11:02 Hrs. Power was extendeduptojeypore by charging 400 kv Gazuwaka- Jeypore II from Gazuwaka end. This energized Bus- II at Jeyporealongwith the bus reactor when voltage at Jeypore could be contained at 404kV. The 400 kv Bus II was thus got connected with Southern Grid while Bus I remained synchronized with NEWGrid.Power was then extended upto 400 kv IndravatiHEP via 400 kv Jeypore(from Bus-II)- Indravati-Indravati(OHPC) section. Post charging voltage after charging of the entire section was observed at 427kV at Indravati. 315MVA ICT-2 at 4

Indravati HEP was then charged to extend power at 220 kv transfer bus. And finally to Unit 2 for its start up. The entire exercise could be completed successfully within 1 Hr and 50 minutes that involved over 25 numbers of switching operations. The generation of Unit # 2 of UIHEP was raised to 50 MW and it was operated for about 9 minutes in synchronization with SR grid. No major voltage problems were encountered during charging of lines while extending start up power to Indravati ( vide FIG 8). C. Black start of Indravati HEP and its operation in islanded mode on 10 th Feb 2012 The mock drill for Black start for Indravati station was attempted again on 10 th Februray 2012. The exercise aimed at black start of one of its unit(unit 3) at Indravati, extending power at Therubali 220kV station and forming an island of around 70MW of load at 132kv by way of having bus section arrangement at 132kv Therubali. The schematic arrangement is shown at Figure 9. Figure 9: The schematic black start arrangement for Indravati HEP alongwith island formed The Indravati Therubali 220kv line being of around 90km no major voltage problems could be observed. However, the island formed with around 60-70MW of load of Kesinja could be operated stabily and the sub-system was synchronized with rest of the grid at Therubali 220kv through main bus breaker of Indravati-Therubali 220kV ckt 2. The entire drill time took around 1 Hr and 32 minutes Figure: 10 Island synchronisation of two systems V. FUTURE PLANS The mock black start drill for othersmaller power stations such asmaithon(dvc), Rengali(OHPC), Subrnrekha(JSEB) could also be successfully carried out in Eastern Region. Besides the experience, the drills have brought in awareness and their importance amongst the operators. It has also revealed many a weakness and deficiencies in various stations. These are being attended to for a detailed drill to be carried out as a part of routine practice to fulfill the objective of disaster management such as quick restoration of the grid in the event of a major blackout. As has been stated, most of the hydro power stations in Eastern Region being located at the farthest corners of the region, it is of utmost importance to attempt the black start of units at Purulia Pumped storage plant of West Bengal. The plant is centrally located in the region with its proximity of major thermal plants such DPL, Bakreswar, Waria, Mejia and Chandrapura besides the major load centre at Bidhnnagar. V. CONCLUSION Since blackouts occur rarely, it would be difficult totrain the system operators on system restoration in real time. With significant loss to economy and great inconvenience to consumers, faster and efficient restoration is of utmost importance. This would require well documented detailed restoration plans tested through system studies, dispatcher training simulator, mock drills and creation of awareness, confidence and familiarity not onlyto grid operators but also to operating personnel at generating stations and sub-stations. 5

ACKNOWLEDGMENT The authors acknowledge with thanks the guidance and support given by management of POSOCO and for permitting the publication of this paper. The views expressed in this paper are of the authors in their individual capacity and not necessarily that of Power System Operation Corporation Ltd. References [1] Indian Electricity Grid Code (IEGC) May 2010. [2]: System Restoration Guidelines: How to Set up, Conduct, and evaluate a Drill : A report by the Operator training group Joseph D.Willson, PJM Interconnection Associastion [3] The restoration procedures of Eastern regional Grid Jan 2012. [4] V. K Agrawal, R. K. Porwal, Rajesh Kumar, VivekPandey, Mock Blackstart Drills An Excellent Learning Experience for Power System Operators, CBIP 5th International conference on Power System Protection and Automation, 6-9 Dec 2010. [5] Black Start in Power System- A case study in Western Region, India. By U K Verma, Member, IEEE, S R Narasimhan Member, IEEE, A Gartia, Member, IEEE, P A R Bende, Aditya P Das and A K Gupta [6] Adibi, M.M. Power System Restoration Methodologies and Implementation Strategies, Wiley IEEE Press, 2010. [7] UCTE Operation Handbook: Policy 5, Emergency Procedures, Chapter B: System restoration after collapse, v1.0 (03.05.2006), http://www.entsoe.eu [8] Y. Hou, C-C.Liu, P. Zhang, K. Sun, Constructing Power System Restoration Strategies, ELECO 2009 (6th International Conference on Electrical and Electronics Eng.), Bursa, Turkey, Nov. 5-8, 2009. 6