EIPC HIGH LEVEL TRANSMISSION COST ESTIMATION TASK #5: DOE PROJECT NO. DE-OE

Similar documents
New Mexico Transmission Expansion Concepts For Wind Resources

Transmission Planning for Wind Energy Resources in the Eastern United States. Dale Osborn

Feasibility Study Report

Alternatives Analysis Findings Report

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal

Jay Caspary Director Research, Development & Tariff Services

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Supplemental Report on the NCTPC Collaborative Transmission Plan

Sub Regional RTEP Committee Western Region ATSI

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

100 MW Wind Generation Project

Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications

The Development of Competitive Renewable Energy Zones in Texas

PREPARED DIRECT TESTIMONY

The Green Line Project

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

15 Nelson-Marlborough Regional Plan

for DRECP Alternatives

4.0 TIER 2 ALTERNATIVES

MILLIGAN SOLAR PROJECT

West Station-West Cañon 115 kv Transmission Project

15 Nelson-Marlborough Regional Plan

Interconnection System Impact Study Report Request # GI

The Long-Range Transmission Plan

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

DIgSILENT Pacific PowerFactory Technical Seminar

High Plains Regional Transmission Summit. Timelines for Planning Processes / Policy

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

2011 Special Reliability Assessment: Power Interdependency in the United States

Civil Engineer. Tasks

SERTP rd Quarter Meeting

The Grid Link Project. Summary of the Report for the Independent Expert Panel

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

CUSTOMER/ TWIN ARROWS PROJECT

Fueling Savings: Higher Fuel Economy Standards Result In Big Savings for Consumers

FERC Order 1000 Upgrade Definition

City of Palo Alto (ID # 6416) City Council Staff Report

Transmission Planning using Production Cost Simulation & Power Flow Analysis

Appendix D Black Hills Project Summary

Net Metering Policy Framework. July 2015

The Boston South Station HSIPR Expansion Project Cost-Benefit Analysis. High Speed Intercity Passenger Rail Technical Appendix

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO.

Accommodating High Levels of Variable Generation. EPRI Managing Complexity for Safety and Reliability September 14-15, 15, 2009

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

SDG&E Valley-Rainbow Project

Aaren Healy, 20 September 2017 / 1

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

SERTP rd Quarter Meeting

Electric Vehicle Cost-Benefit Analyses

Merger of the generator interconnection processes of Valley Electric and the ISO;

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

APPENDIX F: Project Need and Description

2015 Grid of the Future Symposium

Utilizing GIS Models in Prioritizing and Selecting Transportation Projects

Interconnection and Net Metering Service in Ohio

Distributed Energy Resources: How Do Utilities Accommodate Customer Owned Generation?

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study

3.17 Energy Resources

DFO STATEMENT OF NEED REPORT

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013

Michigan Thumb Loop Transmission Line Project

Western NY Public Policy Transmission Planning Report

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

Southeastern Regional Transmission Planning (SERTP)

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO DIRECT TESTIMONY AND EXHIBITS OF CHRISTOPHER E. PINK TABLE OF CONTENTS

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

Feasibility Study for the Q MW Solar Project

Contact person: Pablo Taboada Mobile:

Analysis of options for the future allocation of PV farms in South Africa

System Impact Study Report

HVDC Back-to-Back Interconnections Enabling reliable integration of power system

Looking Towards the Future: Advantages of 765-kV Transmission Technology

Scope of Services January 26, Project Development and Conceptual Engineering for City of Lake Forest Amtrak Station

Tri-State December 2013 Board Meeting

Introduction to transmission network characteristics - technical features. Slobodan Markovic EKC Athens,

Financing Public Transportation Operations

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

ERCOT Independent Review of Houston Import RPG Project

Guideline for Parallel Grid Exit Point Connection 28/10/2010

ABB POWER SYSTEMS CONSULTING

Feasibility Study Report

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

RIIO-T2 Energy Scenarios

NRECA Cooperative Research Network. Modern Grid Initiative Southeast Summit August 10, 2006 Nashville, TN

METRO CNG Program Phase I Update. Customer Service Committee April 2014

MOTION NO. M Purchase of Thirty-two Double Deck Buses for Increased Passenger Capacity, Bus Replacement and Service Expansion

MAKING USE OF MOBILE6 S CAPABILITIES FOR MODELING START EMISSIONS

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

The Transmission Lay of the Land

Falcon-Midway 115 kv Line Uprate Project Report

3 Reliability Issues and Solutions

ARLINGTON COUNTY, VIRGINIA

Decision on Merced Irrigation District Transition Agreement

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT

4 COSTS AND OPERATIONS

Transcription:

EIPC HIGH LEVEL TRANSMISSION COST ESTIMATION TASK #5: DOE PROJECT NO. DE-OE0000343 Background: To support the SSC in assessing the results of the macroeconomic analysis and reaching consensus on the three (3) future scenarios of interest, the EIPC has developed an approach which employs generic, high-level transmission expansion cost estimates for use in comparisons among the macroeconomic scenarios. Because generic cost estimates are needed to develop and select scenarios of interest prior to specific modeling and detailed power flow analysis to be performed in Phase 2 of the Project, they are intended only for use by the SSC in quantifying levels of transmission impacts among the many uncertain future expansion scenarios being considered relative to each other. The approach applied in developing the high-level cost estimates is to utilize generic transmission line building blocks in a consistent manner by each of the PAs to approximate the SSC requested increases in transfer capability between regions represented in the macroeconomic scenarios. These generic building blocks and cost estimates do not represent likely project solutions and are not intended to reflect specific facility costs. The absolute dollar values of these generic estimates are intended only to assist the SSC in selecting scenarios of interest, and are not applicable for other purposes or in any way indicative of actual transmission expansion costs, which must be developed through detailed local and regional assessments of specific expansion requirements. Examples of costs not considered include substation costs, upgrades to existing transmission systems, financing costs, specific ROW routing requirements, etc. The EIPC will provide a single cost estimate for each macroeconomic Future for which the SSC selects specific increased transfer capabilities. These high-level cost estimates are to provide the SSC with guidance of the relative transmission cost differences between the multiple Futures in order to assist the SSC in the determination of the three (3) future scenarios for which detailed transmission expansion information will be developed in Phase 2 of the Project. Approach: 1) Existing system capacity between regions is fully utilized and cannot be relied upon; and therefore, only new transmission enhancements will be utilized to obtain the requested increase in transfer capability. 2) To represent increases in transmission capacity between regions, the EIPC will use green field, generic transmission line building blocks. 3) To represent contingency capability, include redundant circuits (e.g. for a 1000 MW increase, two 1000 MW circuits are needed; the second circuit to account for reinforcements to support the contingency loss of the first). 4) Planning Authorities should approximate termination points for the transmission line building blocks based upon knowledge of their local system(s).

5) No power flow analyses will be performed. 6) Local impacts to the sending and receiving ends of the proposed circuits will not be addressed. 7) The integration of remote resources and large blocks of resource additions will be assessed on a case by case basis. 8) HVDC solutions will not be utilized as part of the high-level analyses and cost estimates; however, Planning Authorities will provide the stakeholders guidance where HVDC could potentially be utilized. The EIPC has compiled a cost matrix of planning level, cost per mile estimates for common HVAC voltage levels among the PAs. The EIPC has determined that the regions have enough geographic diversity to warrant for differences in regional costs. Therefore, this cost matrix will provide the cost per mile ranges for typical transmission line voltage types by applying a range of regional multipliers to the base cost for each Bubble. A simplified example of the cost matrix is shown below:

Table 1: Example of Transmission Line Costs per Mile 1 Base Cost for Different Types Voltage (kv) Capacity (MW) $M/mile Region X Regional Multipliers Region Y Region Z 230 600 $A 0.93 1.02 0.99 230 1200 $B 0.93 1.02 0.99 345 1200 $C -- 1.04 1.01 345 2400 $D -- 1.04 1.01 500 2600 $E 0.97 1.10 1.03 765 4000 $F -- 1.07 1.04 Step 1: The SSC provides the EIPC with the requested increase in transfer capability for each corresponding Pipe. Step 2: The Planning Authorities ( PA ) that were responsible for developing the initial transfer limits for the corresponding Pipe are to approximate the combination of building blocks using the above matrix that will achieve the requested increase in transfer capability. In general, the PAs should utilize existing voltage types found within the specific Bubble as part of the solution. Step 3: The PAs should use the knowledge of their local system(s) to approximate the termination points and mileages of the transmission building blocks that could potentially accommodate the increase in transfer capability. Step 4: Once the new transmission building blocks, as well as, the corresponding mileages of the proposed circuits have been approximated, the PAs shall apply the base costs per mile for the amount of facilities located within each Bubble and the multipliers applicable to the Bubbles involved. Step 5: If applicable, the PAs will provide the SSC with guidance on the potential utilization of HVDC. 1 This table is a simplified example of the developed matrix and does not represent specific cost of any region.

An Example of the methodology follows: Step 1: The SSC requested the EIPC to develop high level cost estimates for increasing the Pipe from Region X to Region Y by 1300 MWs.

Step 2: The Planning Authorities ( PA ) that were responsible for developing the initial transfer limits from Bubble X to Bubble Y are to approximate the combination of building blocks using the below matrix that will achieve the minimum combination of building blocks to achieve the requested 1300 MWs increase in transfer capability. In general, the PAs should utilize existing voltage types found within the specific Bubble as part of the solution. Base Cost for Different Types Voltage (kv) Capacity (MW) $M/mile Region X Regional Multipliers Region Y Region Z 230 600 $A 0.93 1.02 0.99 230 1200 $B 0.93 1.02 0.99 345 1200 $C -- 1.04 1.01 345 2400 $D -- 1.04 1.01 500 2600 $E 0.97 1.10 1.03 765 4000 $F -- 1.07 1.04 Given that Region X does not currently have any 345 kv or 765 kv facilities, the solution should be comprised of a combination of 230 kv and/or 500 kv. Total Increase in Capacity Requested: 1300 MWs Solution mix: 2 1200 MW, double circuit 230 kv transmission lines and 1 600 MW, single circuit 230 kv transmission line

Step 3: The PAs shall use the knowledge of their local system(s) to approximate the termination points and mileages of the building blocks that could potentially accommodate the increase in transfer capability. The PAs approximated: 1) The new 1200 MW, double circuit 230 kv transmission line between Substation A and Substation B to be approximately 130 miles, of which 80 miles are within Bubble X while the remaining 50 miles are within Bubble Y. 2) The new 1200 MW, double circuit 230 kv transmission line between Substation C and Substation D to be approximately 25 miles, of which 20 miles were within Bubble X and the remaining 5 miles within Bubble Y. 3) The new 600 MW, single circuit 230 kv transmission line between Substation E and Substation F to be approximately 60 miles, of which 20 miles are within Bubble X and the remaining 40 miles are within Bubble Y.

Step 4: Once the type and quantity of new transmission building blocks, as well as, the corresponding mileages of the proposed circuits have been approximated, the PAs shall apply the base costs per mile for the amount of facilities located within each Bubble and the multipliers applicable to the Bubbles involved. Base Cost for Different Types Voltage (kv) Capacity (MW) $M/mile Region X Regional Multipliers Region Y Region Z 230 600 $A 0.93 1.02 0.99 230 1200 $B 0.93 1.02 0.99 345 1200 $C -- 1.04 1.01 345 2400 $D -- 1.04 1.01 500 2600 $E 0.97 1.10 1.03 765 4000 $F -- 1.07 1.04 1) The new 1200 MW, double circuit 230 kv transmission line between Substation A and Substation B to be approximately 130 miles, of which 80 miles are within Bubble X while the remaining 50 miles are within Bubble Y. (Mileage within Bubble X) * (Base Cost for Type) * ( Bubble Multiplier) + (Mileage within Bubble Y) * (Base Cost for Type) * ( Bubble Multiplier) = [(80 miles) * ($B / mile) * (0.93)] + [(50 miles) * ($B / mile) * (1.02)] = Costs 2) The new 1200 MW, double circuit 230 kv transmission line between Substation C and Substation D to be approximately 25 miles, of which 20 miles were within Bubble X and the remaining 5 miles within Bubble Y. (Mileage within Bubble X) * (Base Cost for Type) * ( Bubble Multiplier) + (Mileage within Bubble Y) * (Base Cost for Type) * ( Bubble Multiplier) = [(20 miles) * ($B / mile) * (0.93)] + [(5 miles) * ($B / mile) * (1.02)] = Costs 3) The new 600 MW, single circuit 230 kv transmission line between Substation E and Substation F to be approximately 60 miles, of which 20 miles are within Bubble X and the remaining 40 miles are within Bubble Y. (Mileage within Bubble X) * (Base Cost for Type) * ( Bubble Multiplier) + (Mileage within Bubble Y) * (Base Cost for Type) * ( Bubble Multiplier) = [(20 miles) * ($A / mile) * (0.93)] + [(40 miles) * ($A / mile) * (1.02)] = Costs Step 5: Given the relative short distances of the proposed circuits, the use of HVDC does not appear to be practical.