POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

Similar documents
POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO KV BUSBAR ON 30 OCTOBER 2011

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011

POWER SYSTEM OPERATING INCIDENT REPORT MULTIPLE CONTINGENCY EVENT IN NORTH WEST TASMANIA ON 6 APRIL 2012

Power System Operating Incident Report Trip of Murray Lower Tumut No kv Transmission Line at Murray End Only on 18 November 2013

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012

POWER SYSTEM OPERATING INCIDENT REPORT LIGHTNING STRIKES IN TASMANIA AND PACIFIC ALUMINIUM POTLINE LOAD REDUCTIONS 21 MARCH 2013

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF B 220 KV BUSBAR AT GEORGE TOWN ON 27 NOVEMBER 2012.

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

Power System Operating Incident Report Trip of Red Cliffs Horsham and Red Cliffs-Wemen Kerang 220 kv transmission lines on 15 January 2014

MULTIPLE LINE OUTAGES IN THE MOUNT ENGLAND TARONG AREA IN QUEENSLAND, 13 FEBRUARY 2017

POWER SYSTEM INCIDENT REPORT NORTHERN POWER STATION STABILISER OUTAGE APRIL AND MAY 2010

TRIP OF HORSHAM-REDCLIFFS 220 KV TRANSMISSION LINE AND MURRAYLINK INTERCONNECTOR ON 12 NOVEMBER 2015

POWER SYSTEM INCIDENT REPORT: OVERLOAD OF WAUBRA- HORSHAM 220 KV TRANSMISSION LINE AND INSECURE OPERATION OF THE SYSTEM ON 13 DECEMBER 2012

Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)*

Guideline for Parallel Grid Exit Point Connection 28/10/2010

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Jemena Electricity Networks (Vic) Ltd

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

TRANSMISSION PLANNING CRITERIA

The Energy Queensland Group Notice of no non-network options

Final Capacity Auction Results 2019/2020 T-1 Capacity Auction. Date 01/02/2019 Document: FCAR1920T-1 Version 1.0

SUBSTATION INTERLOCKING SCHEMES

Final Capacity Auction Results 2018/2019 T-1 Capacity Auction. Date 26/01/2018 Version 1.0

Feasibility Study for the Q MW Solar Project

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

2015 WDC Disturbance and Protection Standards Overview

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Guidelines for connection of generators:

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8

ELECTRICITY TRANSMISSION USE OF SYSTEM PRICES - 1 JULY 2014 TO 30 JUNE 2015

Eyre Peninsula electricity supply options investigation

2017 Interim Area Transmission Review of the New York State Bulk Power Transmission System

Interconnection Feasibility Study Report GIP-222-FEAS-R3

100 MW Wind Generation Project

Western Power s list of exemptions from compliance from Technical Rules granted after 1 July 2007.

15 Nelson-Marlborough Regional Plan

Interconnection System Impact Study Report Request # GI

Specification for 1500V DC Traction Supply WOS 01.E

South Australia Victoria (Heywood) Interconnector Upgrade. RIT-T: Project Specification Consultation Report

Seabrook Substation Reliability Improvement Project

Feasibility Study for the Q MW Solar Project

NATIONAL GRID ELECTRICITY TRANSMISSION plc THE CONNECTION & USE OF SYSTEM CODE TABLE OF CONTENTS

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Exemptions currently in force

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

New 115 kv Disconnect Switches at Bloomsburg MTS

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System

Enquiry Form (Non-Registered Generator With Capacity less than 5 MW)

An advisory circular may also include technical information that is relevant to the rule standards or requirements.

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Arc flash solutions catalogue Australia. Safety solutions - Protecting employees and the enterprise

Draft Agenda. Item Subject Responsible Time. 4. GAS INFORMATION SERVICES PROJECT IMO 10 min. 5. OPTIONS FOR GAS BULLETIN BOARD SYSTEM IMO 15 min

XXXXX. Kokish River Hydroelectric Project. Interconnection Facilities Study and Project Plan

ATTACHMENT Y STUDY REPORT

Proposed New ISO Rules Section Version 2.0 Generating Unit Technical Requirements ( New ISO Rules Section Version 2.

NYISO Tariffs. New York Independent System Operator, Inc. Document Generated On: 2/27/2013

Health and Safety Executive, Technology and Health Sciences Division, Magdalen House, Bootle.

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Large Embedded Generation User Guide A

HYDRONIC LIFT SOLUTION FOR A3 AMENDMENT

2016 Load & Capacity Data Report

Enquiry Form for Micro and Small Generators 5MW and Less

Vertabelo Academy. Terms of Service PLEASE READ ALL OF THE FOLLOWING TERMS OF SERVICE BEFORE USING THIS WEBSITE A. General Terms

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Managing Electrical Safety on Boats

DFO STATEMENT OF NEED REPORT

XXXX. Skookum Creek Power Project. Interconnection System Impact Study

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

MINIMUM OIL BURN/AUTOMATIC FUEL SWAPPING CAPABILITY

REDUNDANT PROPULSION SHIPS RULES FOR CLASSIFICATION OF NEWBUILDINGS DET NORSKE VERITAS SPECIAL EQUIPMENT AND SYSTEMS ADDITIONAL CLASS PART 6 CHAPTER 2

1000mA - 650mA Phase Dimmable LED Driver

2018 Load & Capacity Data Report

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

The Long-Range Transmission Plan

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

IEEE Guide for the Design of Low Voltage AC and DC Auxiliary Systems for Substations

Facilities Study for Alberta to US Available Transfer Capability

Engineering Instruction

Functional Specification Revision History

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION

15 Nelson-Marlborough Regional Plan

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Bald Hill on track to start lithium concentrate production this quarter

Title Electrical Technical Maintenance Coding System. Reference Number PMP 01 (RIC Standard: EP SP)

Case Study on On EHV Circuit Breaker Flashover NTPC-SINGRAULI

Emerald Reactive Support Alternative Solution Expressions of interest

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Energy Regulation : Australian Experience. Engr.Khondkar Abdus Saleque

Deploying Smart Wires at the Georgia Power Company (GPC)

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

Company Directive STANDARD TECHNIQUE: SD4O/1. Standard HV Connection Arrangements

Breaker-failure protection RAICA

For personal use only

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map

Washington, DC Area Low Voltage Disturbance

NZQA unit standard version 8 Page 1 of 5. Apply and remove earths from conductors on electricity supply networks

Breaker failure relay REB 010

Transcription:

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 PREPARED BY: Electricity System Operations Planning and Performance DATE: 5 June 2012 FINAL

Disclaimer Purpose This report has been prepared by the Australian Energy Market Operator Limited (AEMO) for the sole purpose of meeting obligations in accordance with clause 4.8.15 (c) of the National Electricity Rules (NER). No reliance or warranty This report contains data provided by third parties and might contain conclusions or forecasts and the like that rely on that data. This data might not be free from errors or omissions. While AEMO has used due care and skill, AEMO does not warrant or represent that the data, conclusions, forecasts or other information in this report are accurate, reliable, complete or current or that they are suitable for particular purposes. You should verify and check the accuracy, completeness, reliability and suitability of this report for any use to which you intend to put it, and seek independent expert advice before using it, or any information contained in it. Limitation of liability To the extent permitted by law, AEMO and its advisers, consultants and other contributors to this report (or their respective associated companies, businesses, partners, directors, officers or employees) shall not be liable for any errors, omissions, defects or misrepresentations in the information contained in this report, or for any loss or damage suffered by persons who use or rely on such information (including by reason of negligence, negligent misstatement or otherwise). If any law prohibits the exclusion of such liability, AEMO's liability is limited, at AEMO's option, to the re-supply of the information, provided that this limitation is permitted by law and is fair and reasonable. Abbreviations and Symbols Abbreviation CB kv MW ms NER Term Kilovolt Megawatt Millisecond National Electricity Rules 2012 Australian Energy Market Operator Ltd. All rights reserved 5 June 2012 Page 2 of 8

1 Introduction At 2216 hrs on 9 February 2012, the 5A6 Bannaby 500 kv line and the No.2 generating unit at power station in New South Wales simultaneously tripped out of service. The unit trip also resulted in the loss of station auxiliary supply to the switchyard. Lightning activity was reported in the vicinity of 5A6 line at the time. Shortly after, the 330 kv circuit breakers (CBs) of the No.2 generator group 1 opened, de-energising the generator s, auxiliary s and excitation. Unit 2 was generating 342 MW prior to the incident. This report has been prepared under clause 4.8.15 (c) of the National Electricity Rules to assess the adequacy of the provision and response of facilities and services and the appropriateness of actions taken to restore or maintain power system security. This report is largely based upon information provided by TRUenergy/Delta Electricity ( power station) and TransGrid. Data from AEMO's Energy Management System and Electricity Market Management System has also been used in analysing the incident. All references to time in this report are to National Electricity Market time (Australian Eastern Standard Time). 2 Pre-Contingent System Conditions The status of the power system prior to the incident is shown in Figure 1. For clarity only equipment relevant to this incident has been included in the diagram. Figure 1 Network topology prior to the incident 5A62A A 5A72A BANNABY 71 70 Wellington 72 MAIN 5A6 5A62B 5A7 5A72B B 712 702 352 722 362 5A62 5A72 5072 5062 5032 5022 5012 TIE1 6412A 6422A 6032 6042 MT PIPER 5212 5222 5432 5422 5412 GEN 2912 6412B 6422B 5A32 5A52 1H 2H 3H TIE2 R1 Bayswater 5A3 Wollar 5A5 2212 2222 4432 94Y 94Y2 2922 R2 Unit 1 Unit 2 94E2 4422 4412 94M2 9472 94E Ilford Tee 94M/2 Wellington/Piper 947 Station Auxiliaries (Backup) Legend Generating Unit 330/23 kv closed 500 kv Bus Load 132/66 kv 330/132 kv 500/330/33 kv 3 winding open Reactor 66 kv line 500 kv line 330 kv Bus 330 kv line 132 kv Bus 132 kv line 1 The No.2 generator group consists of two 330/23 kv generator s, two 23/11 kv auxiliary s and a 23 kv/1 kv/110 V excitation. 5 June 2012 Page 3 of 8

The auxiliary supply to the 500 kv switchyard (including tie s), as per current operating arrangements, is supplied through the No.1/2 unit 11 kv switchboard. TransGrid had not advised this special auxiliary supply arrangement to AEMO prior to this incident. At the time of the incident, the Station 11 kv switchboard was operated such that there was an open point between the Unit 1 and 2 supply to the switchboard. 3 Summary of Events At a time of lightning activity on 9 February 2012, a one phase to ground fault occurred on the red phase of the 5A6 Bannaby 500 kv transmission line resulting in a three phase trip of the line. Zone 1 distance protection at Bannaby 500 kv substation detected the fault and tripped CBs 5A62A and 5A62B at Bannaby. Zone 1 distance protection at 500 kv substation detected the fault and tripped CBs 5A62 and 6032 at. The fault was cleared within 52 ms from the end and 62 ms from the Bannaby end. The fault was cleared within the required fault clearance times specified in the NER. All CBs auto-reclosed within 20 seconds of the trip. The distance to fault measured by the protection relays was approximately 33.19 km from the end. Coincident with the 5A6 line trip, the No. 2 generator CB 2222 and its 11 kv auxiliary supply CBs (not shown in the diagrams) opened, disconnecting the generating unit from the power system and de-energising all its auxiliary supplies including auxiliary supplies to the switchyard and No.2 generator cooling systems. Approximately 1 minute and 43 seconds later, the No.2 generator 330 kv CBs 5062 and 5222 opened, deenergising the No.2 generator group. The key events that took place during the incident are summarised in Table 1 below. Table 1: Summary of events Time Event Comments Bannaby 500 kv CB 5A62A open. Bannaby 500 kv CB 5A62B open. 500 kv CB 5A62 open. 500 kv CB 6032 open. No. 2 generator CB 2222 open. 5A6 Bannaby 500 kv line tripped. No. 2 generating unit, the unit and station auxiliary supplies supplied form the No.2 generating unit disconnected from the power system. 22:16:21 22:16:23 22:16:23 22:16:25 22:17:48 Bannaby 500 kv CB 5A62B auto-reclose. Bannaby 500 kv CB 5A62A auto-reclose. 500 kv CB 5A62 auto-reclose. 500 kv CB 6032 auto-reclose. 330 kv CB 5062 open. 5A6 Bannaby 500 kv line returned to service. No. 2 generator group de-energised. 5 June 2012 Page 4 of 8

Time Event Comments 22:17:48 23:41:10 23:41:10 10/02/2012 02:17:00 330 kv CB 5222 open. 330 kv CB 5062 manual close. 330 kv CB 5222 manual close. No.2 generator CB 2222 closed. No. 2 generator group returned to service. No.2 generating unit returned to service. The status of the power system immediately following the trip of the 5A6 line and No.2 generating unit is shown in Figure 2. Figure 3 shows the status of the power system after the subsequent auto-reclose of 5A6 line and de-energisation of the No.2 generator group. Figure 2 Network topology immediately following 5A6 line trip and generating unit trip A 5A62A 5A72A BANNABY 71 70 Wellington 72 MAIN Fault 5A6 5A62B 5A7 5A72B B 712 702 352 722 362 5A62 5A72 5072 5062 5032 5022 5012 TIE1 6412A 6422A 6032 6042 MT PIPER 5212 5222 5432 5422 5412 GEN 2912 6412B 6422B 5A32 5A52 1H 2H 3H TIE2 R1 Bayswater 5A3 Wollar 5A5 2212 2222 4432 94Y 94Y2 2922 R2 Unit 1 Unit 2 94E2 4422 4412 94M2 9472 94E Ilford Tee 94M/2 Wellington/Piper 947 Legend Station Auxiliaries (Backup) Generating Unit 330/23 kv closed 500 kv Bus Load 132/66 kv 330/132 kv 500/330/33 kv 3 winding open Reactor 66 kv line 500 kv line 330 kv Bus 330 kv line 132 kv Bus 132 kv line 5 June 2012 Page 5 of 8

Figure 3 Network topology after 5A6 line auto-reclosed and generator group deenergised A 5A62A 5A72A BANNABY 71 70 Wellington 72 MAIN 5A6 5A62B 5A7 5A72B B 712 702 352 722 362 5A62 5A72 5072 5062 5032 5022 5012 TIE1 6412A 6422A 6032 6042 MT PIPER 5212 5222 5432 5422 5412 GEN 2912 6412B 6422B 5A32 5A52 1H 2H 3H R1 TIE2 Bayswater 5A3 Wollar 5A5 4432 2212 2222 94Y 94Y2 2922 R2 Unit 1 Unit 2 94E2 4422 4412 94M2 9472 94E Ilford Tee 94M/2 Wellington/Piper 947 Station Auxiliaries (Backup) Legend Generating Unit 330/23 kv closed 500 kv Bus Load 132/66 kv 330/132 kv 500/330/33 kv 3 winding open Reactor 500 kv line 330 kv Bus 330 kv line 132 kv Bus 66 kv line 132 kv line 4 Immediate Actions Taken At the time of the incident, since the No.2 unit 11 kv supply was the only source out of the three installed sources available to the auxiliaries of the switchyard, the trip of the Mt Piper No.2 generating unit interrupted those supplies. Following the incident,transgrid personnel were sent to the switchyard to investigate. TransGrid advised AEMO that power supplies to the cooling systems of the TIE1 and TIE2 500/330/33 kv s were lost when the No.2 unit tripped and the s would need to operate at reduced ratings to avoid postcontingent thermal overload. Based on the revised thermal ratings received from TransGrid, AEMO derated both TIE1 and TIE2 s to 750 MVA each in its Energy Management System. At 0028 hrs on 10 February 2012, TransGrid informed AEMO that the power supplies to the cooling systems of the TIE1 and TIE2 s had been restored. Based on this advice AEMO restored the thermal ratings of both s to their normal ratings of 1500 MVA each. The cause of the simultaneous trip of the No.2 generating unit with the 5A6 line is still being investigated. Pending further advice from TransGrid and Delta Electricity, AEMO determined, 5 June 2012 Page 6 of 8

in accordance with its Power System Security Guidelines 2, to reclassify the simultaneous trip of the 5A6 Bannaby 500 kv line and the No.2 generating unit as a credible contingency event from 1800 hours on 10 February 2012 until further notice. At 1834 hrs that day AEMO issued the Market Notice No.37740 to advise this to market participants. 5 Follow-up Actions Since the incident, Delta Electricity, TransGrid and AEMO have been working closely to investigate the cause of the simultaneous trip of the No.2 generating unit and its auxiliary supplies with the 5A6 line. The current status of the investigation is: TransGrid TransGrid has informed AEMO that no interzone protection 3 operated at the 330 kv switchyard and no intertrip signal was sent to disconnect the No.2 generating unit from the power system. Delta Electricity TRUenergy No.2 generating unit trip: Delta Electricity has informed AEMO that the unit electrical protection system logs recorded the receipt of a signal indicating that TransGrid s interzone protection operated. The source of this signal, however, is still being investigated. No.2 generator trip: Delta Electricity has informed AEMO that the subsequent trip of the generator 330 kv CBs is reasoned to have been initiated by the protection systems. The trip of the generating unit and its auxiliary CBs caused the loss of all auxiliary supplies to the unit, including the 415 V main and standby power supplies to the cooling oil pumps of the generator s. The flow of oil for cooling is an essential requirement for the generator s to remain in service. The loss of oil flow was detected by the protection and, after the set time-out, sent a trip signal to the No.2 generating unit protection system. This protection in turn relayed the signal to the TransGrid interzone protection systems which tripped the No.2 generator 330 kv CBs 5062 and 5222. On 30 April 2012, in accordance with clause 4.15 of the National Electricity Rules, TRUenergy submitted a notice of non-compliance with the registered performance standards for No.2 generating unit. This non-compliance is in relation to the capability of the unit to ride-through power system disturbances, particularly for transmission line faults outside their intended protection zone. AEMO has requested TRUenergy to return the unit to compliance by 1 December 2012. 6 Power System Security Assessment The power system voltages and frequencies remained within the normal operating bands and the power system remained in a secure operating state throughout the incident. The provision and response of facilities and services by Delta Electricity, TransGrid and AEMO were adequate to maintain power system security. 2 Clause 4.2.3B of the National Electricity Rules requires that AEMO establish criteria to use when considering whether a non-credible contingency event is reasonably possible. This is published in AEMO operating procedure SO_OP3715 Power System Security Guidelines, which is available at: http://www.aemo.com.au/electricityops/3715.html 3 Interzone protection operates from TransGrid s 330 kv switchyard. A correct operation of interzone protection involves the simultaneous trip of 330 kv CBs 5222 and 5062 and an intertrip signal being sent to No.2 generating unit protection to trip generator CB 2222 and its auxiliary breakers, to disconnect the generating unit from the power system. 5 June 2012 Page 7 of 8

7 Conclusions At 2216 hrs on 9 February 2012, the 5A6 Bannaby 500 kv line tripped and autoreclosed to successfully clear a one phase to ground fault caused by lightning strikes. Coincident with the 5A6 line trip, the No.2 generating unit and its auxiliary supplies tripped out of service, resulting in the loss of 342 MW of generation. All affected equipment was returned to service by 0217 hrs on 10 February 2012. The trip of the unit auxiliary supplies caused the loss of power to the No.2 generator cooling systems, correctly resulting in the tripping of the generator by intertrip signal from the No.2 generating unit protection. TransGrid and Delta Electricity are currently investigating the cause of the trip of the No.2 generating unit and its auxiliary supplies. The facilities and services provided to manage the simultaneous trip of the 5A6 line and the Mt Piper No.2 generating unit, and the subsequent trip of the No.2 generator group, were adequate for the conditions experienced at the time. AEMO correctly applied the criteria published in Section 12 of its Power System Security Guidelines in reclassifying the loss of the 5A6 Bannaby 500 kv line and the No.2 generating unit as a credible contingency event. Note that, at 0618 hrs on 6 April 2012, the simultaneous trip incident reoccurred when the No.2 generating unit tripped out of service during a trip and auto-reclose of the 5A6 Bannaby 500 kv line. Similar to the earlier incident on 9 February 2012, the generator 330 kv circuit breakers opened one minute and 43 seconds later, de-energising the generator s. TransGrid informed AEMO that the 5A6 line tripped due to a one phase to ground fault occurring on the red phase of the line. However, this reoccurrence of the incident is not reviewable under clause 4.8.15 of the National Electricity Rules as the simultaneous trip of the 5A6 line and the No.2 generating unit had already been reclassified as a credible contingency event. 8 Recommendations 1. Delta Electricity and TransGrid will inform AEMO of progress with their investigations into the cause of the trip of the No. 2 generating unit, by the end of July 2012. 2. TransGrid to confirm the date that the auxiliary supply to the switchyard will be reconfigured to provide the normal supply to the 500 kv switchyard from the 330/132 kv 3H by the end of July 2012. 3. TransGrid must, to the extent that TransGrid is aware or ought reasonably to have been aware, keep AEMO fully and timely informed as to the state of the security of the power system. AEMO will reinforce this requirement at the next Power System Security working group and at the regular operational meeting with the TNSPs. This recommendation to be completed by the end of October 2012. 5 June 2012 Page 8 of 8