INTERIM CONSTRUCTION RECORD REPORT TAILINGS POND 4 STAGE 3 RAISE

Size: px
Start display at page:

Download "INTERIM CONSTRUCTION RECORD REPORT TAILINGS POND 4 STAGE 3 RAISE"

Transcription

1 # West Georgia St. Vancouver, BC V6E 4A2 Ph: (604) Fax: (604) INTERIM CONSTRUCTION RECORD REPORT TAILINGS POND 4 STAGE 3 RAISE OCTOBER 2009 NORTH AMERICAN TUNGSTEN CORPORATION LTD. CANTUNG MINE, NT P.O. BOX 848 WATSON LAKE, YT YOA 1C0 P: F:

2 Tailings Pond 4 Interim Construction Record Report ii EXECUTIVE SUMMARY The tailings management plan at, NT, calls for tailings deposition in Tailings Pond 4 through the remaining life of the mine, including future production following the current temporary mine shutdown. This requires raising the Tailings Pond 4 containment berm to provide sufficient storage capacity in the pond. The pond will be raised in three stages to a final elevation of ft. Stage 1 of the containment berm raise was undertaken in 2007, Stage 2 was undertaken in 2008, and the partial Stage 3 construction was undertaken in The partial Stage 3 raise construction occurred from July 15, 2009 to August 10, The current berm construction included that required to provide the necessary foundation width to enable future completion of the Stage 3 construction, while accounting for current mine operations. The 2009 construction included upstream construction of a 10 ft wide zone of 75 mm material and a 25 ft wide zone of waste rock encapsulated with geotextile, which was capped with 300 mm material along the length of the dam and to an elevation of approximately 3730 ft, which matched the existing dam. In addition, the upstream face of the new construction slope was covered with a layer of geotextile. Jedway enterprises Ltd. (Jedway) was contracted to complete the partial Stage 3 construction. Survey services were provided by North American Tungsten Corporation Ltd. (NATCL) and EBA Engineering Consultants Ltd. (EBA) provided quality control throughout construction. The partial Stage 3 raise to Tailings Pond 4 was generally constructed in accordance with the design; however, the required deviations in design to accommodate site-specific conditions include: Raising all material in the design by 2.5 ft to accommodate the higher tailings beach elevation. Flattening of the upstream slope from the original design of 1.8:H:1V to 2H:1V to maintain the designed final crest width of 30 ft at an elevation of ft. PO Box 848, Watson Lake, YT, Y0A 1C0 P: , F:

3 Tailings Pond 4 Interim Construction Record Report iii TABLE OF CONTENTS PO Box 848, Watson Lake, YT, Y0A 1C0 P: , F: PAGE 1.0 INTRODUCTION GENERAL SCOPE OF WORK PROJECT DETAILS DEVIATIONS FROM DESIGN TAILINGS BREACH ELEVATION HIGHER THAN DESIGN UPSTREAM SLOPE FLATTENED FROM 1.8H:1V TO 2H:1V CONSTRUCTION MATERIALS MM MATERIAL WASTE ROCK MATERIAL MM MATERIAL GEOTEXTILE CONSTRUCTION ACTIVITIES GENERAL CONSTRUCTION EQUIPMENT SURVEY CONTROL MATERIAL PLACEMENT MM MATERIAL WASTE ROCK MM MATERIAL GEOTEXTILE DAM CREST SURFACE DRAINAGE SETTLEMENT MONUMENTS INSTRUMENTATION MATERIAL QUANTITIES SURVEY DATA QUALITY ASSURANCE PARTICLE SIZE ANALYSIS MOISTURE-DENSITY RELATIONSHIP MONITORING GENERAL PIEZOMETERS 9

4 Tailings Pond 4 Interim Construction Record Report iv 8.3. EMBANKMENT MONITORING PROGRAM SETTLEMENT SURVEY ANNUAL INSPECTIONS CLOSURE REFERENCES 12 FIGURES & PHOTOGRAPHS 13 APPENDIX B TAILS POND 4 AS BUILT DRAWING 22 PO Box 848, Watson Lake, YT, Y0A 1C0 P: , F:

5 Tailings Pond 4 Interim Construction Record Report INTRODUCTION 1.1. GENERAL Construction of Tailings Pond 4 during the summer of 2009 was conducted by North American Tungsten Corporation Ltd. (NATCL) and is based on the design report entitled Design Report for the Stage 2 and 3 Raises of the Containment Berm for Tailings Pond 4 issued March 2008 by EBA Engineering Consultants Ltd. (EBA, 2008). NATCL received approval from the Mackenzie Valley Land and Water Board for dam construction to an elevation of ft as described in the letter dated April 8, 2009 (MVLWB a, 2009). The construction was carried out between July 15 and August 10 as a partial completion of the proposed Stage 3 raise to Tailings Pond 4. The 2009 construction included upstream construction of a 10 ft wide zone of 75 mm material and a 25 ft wide zone of waste rock encapsulated with geotextile, which was capped with 300 mm material along the length of the dam and to an elevation that matched the existing dam. In addition, the upstream face of the new construction slope was covered with a layer of geotextile. On June 29, 2009, NATCL announced the temporary suspension of operations at the site, effective October 15, Consequently, the scheduled Stage 3 raise construction was reduced to include only what was necessary to provide sufficient capacity to operate until October 15, 2009 and to prepare the dam for future completion of the berm to a crest elevation of ft. The length of the mine shutdown is not known; however, NATCL is optimistic that economic and market conditions will improve sufficiently so that operations can resume in The Short Term Closure Plan (NATCL, 2009), submitted to MVLWB in August 2009, includes the shutdown and startup strategies to be followed for tailings pond operations and future construction following the shutdown. This report is an interim construction record report and is limited to an overview of construction that occurred from July 15, 2009 to August 10, 2009 on Tailing Pond 4. The construction supervisor, a representative of NATCL, documented all observations. Select construction photographs are referenced throughout the report where applicable. Imperial units have been used in parts of this report in keeping with standards.

6 Tailings Pond 4 Interim Construction Record Report SCOPE OF WORK A representative from EBA was present on site from July 21, 2009 to August 9, 2009 to observe the completion of the 2009 Tailings Pond 4 construction. Throughout the construction of Tailings Pond 4, EBA s role was as follows: Observe the contractor s material placement techniques. Complete quality control testing of the granular materials, which included particle size analysis and moisture-density relationship testing. Monitor placement and compaction of the waste rock material. Inspect geotextile installation. Throughout the construction of Tailings Pond 4, NATCL s role was as follows: Ensure that proper materials, including granular material and geotextile, were available for construction. Monitor construction to ensure dam is constructed to the design intent. Complete construction surveys and quantity surveys. 2.0 PROJECT DETAILS, operated by North American Tungsten Corporation Ltd., is located approximately 310 km northeast of Watson Lake, YT in western Northwest Territories. The mine site is accessible by road through the Yukon via Highway 4 (Robert Campbell Highway) and Highway 10 (Nahanni Range Road). A general site overview is presented in Figure 1. There are four tailings containment structures and one water management structure at, as shown in Figure 1. Tailings Ponds 1 and 2 are presently decommissioned and Tailings Pond 3 is at design capacity. In accordance with the updated Tailings Management Plan completed by EBA for NATCL (EBA, 2009) and submitted to MVLWB on July 7, 2009, Tailings Pond 4 is currently used for tailings deposition and Tailings Pond 5 is used as a water exfiltration pond. The 2009 partial construction of the Stage 3 raise to Tailings Pond 4 was required to provide the necessary foundation width to enable future completion of the containment berm to the design elevation of ft. Tailings Pond 4 prior to the 2009 construction is presented in Photograph 1.

7 Tailings Pond 4 Interim Construction Record Report DEVIATION FROM DESIGN The full Stage 3 raise to Tailings Pond 4 was not completed during the 2009 construction season. The construction was limited to necessary material placement on Tailings Pond 4 to allow for future construction to a final elevation of ft. Deviations from the design are detailed below TAILINGS BEACH ELEVATION HIGHER THAN DESIGN In the Tailings Pond 4 design report (EBA, 2008) it was estimated that the upstream tailings elevation would be at 3721 ft, however, immediately prior to construction the tailings beach elevation ranged between 3723 ft and ft. To accommodate the higher tailings beach elevation, the design was adjusted by raising all materials in the design by 2.5 ft. Consequently, the overlying 300 mm crest material, to be constructed in the future, required a 2.5 ft decrease in layer thickness to maintain a final design elevation of ft for the Stage 3 raise UPSTREAM SLOPE FLATTENED FROM 1.8H:1V TO 2H:1V At the request of EBA, the upstream slope of the containment berm was flattened from 1.8H:1V to 2H:1V. This was achieved by offsetting the toe of the berm raise further into the tailings pond in order to maintain the designed final crest width of 30 ft at the elevation of ft. 4.0 CONSTRUCTION MATERIALS MM MATERIAL The 75 mm minus material used in construction was mainly sourced from a stockpile located on the east side of the airstrip. The airstrip stockpile had been screened in 2008 to remove material larger than 75 mm. The balance of the 75 mm material was sourced from a stockpile at the Ski Hill burrow that had also been screened in The 75 mm material is well-graded sand and gravel with a maximum particle size of 75 mm. In total, approximately 92,272 ft 3 (2,613 m 3 ) of the 75 mm material was used for the Tailings Pond 4 Stage 3 partial raise.

8 Tailings Pond 4 Interim Construction Record Report WASTE ROCK MATERIAL The waste rock material used in construction was sourced from the non-acid generating waste rock pile across from and east of the mine portal (see Photograph 2). The waste rock used in construction has a maximum particle size of 700 mm and a nominal size of 300 mm to 500 mm. A sample of the material was tested for carbon, sulphur, and tungsten every 500 tons during placement to assess the acid generating potential. Approximately 121,509 ft 3 (3441 m 3 ) of waste rock was sourced from the non-acid generating stockpile for the Tailings Pond 4 Stage 3 partial raise MM MATERIAL The 300 mm minus material used in construction was sourced from the stockpile just north of Tailings Pond 4 (see Photograph 3). The 300 mm material stockpile was originally sourced from the Ski Hill burrow area but relocated to its present location in The material is well-graded granular material with a maximum particle size of 300 mm. Particles in the stockpile larger than 300 mm were removed with the excavator. Approximately 23,501 ft 3 (665 m 3 ) of the 300 mm material was used for the Tailings Pond 4 Stage 3 partial raise GEOTEXTILE Two types of geotextile were used during construction on Tailings Pond 4, LP8 nonwoven geotextile and LP16 nonwoven geotextile. Layfield Environmental Services Ltd supplied all geotextile used in construction. 5.0 CONSTRUCTION ACTIVITIES 5.1. GENERAL Jedway Enterprises Ltd. (Jedway) of Watson Lake, YT was contracted by NATCL to construct the partial Stage 3 Tailings Pond 4 raise. Construction commenced on July 15, 2009 and was completed on August 10, The partial raise comprised placement of the upstream berm raise to ± 1.0 ft. The construction extended throughout the length of the dam, from Sta ft to Sta ft. Prior to construction, the tailings beach elevation ranged between 3723 ft and ft.

9 Tailings Pond 4 Interim Construction Record Report 5 The 2009 partial construction of the Stage 3 raise included: A 10 ft wide zone of 75 mm material against the existing upstream slope to an elevation of ± 0.4 ft at crest and ± 1 ft at the centre. A 25 ft wide zone of waste rock material to an elevation of ± 0.6 ft at the crest and ± 0.6 ft at the centre, which was encapsulated with LP16 geotextile and placed upstream of the 75 mm material. A 0.5 ft to 1 ft thick layer of 300 mm material placed across the 25 ft wide zone of encapsulated waste rock from an elevation of ± 0.5 ft at the crest and ± 0.4 ft at the centre, which tied into the adjacent 75 mm material crest. A 2H:1V upstream slope. A shallow inward slope of 4% along the dam crest for inward surface drainage CONSTRUCTION EQUIPMENT Jedway Enterprises Ltd. mobilized the following equipment to site by July 15, 2009 to complete construction on Tailings Pond 4: 1 Caterpillar 345 Excavator 1 D400D 40 Ton Rock Truck 1 A35 Volvo Rock Truck 1 Caterpillar 972G Loader 1 Caterpillar D6H 1 Caterpillar Packer In addition, Jedway Enterprises Ltd. utilized the following equipment which was already present at the mine site: 1 Link Belt 3400 Excavator 1 Caterpillar 330 Excavator 1 D400D 40 Ton Rock Trucks 1 Caterpillar D8R 1 Caterpillar 966G Loader 5.3. SURVEY CONTROL NATCL provided Jedway with surveying control during construction. Surveyors were onsite to complete construction surveys, quantity surveys, and to provide other assistance as required. The quantity survey was recorded for the production of a final quantity report supplied to Jedway. NATCL was responsible for completing the surveys and compiling the survey data used to produce the final as-built drawings.

10 Tailings Pond 4 Interim Construction Record Report MATERIAL PLACEMENT To gain access to Tailings Pond 4, a road was constructed in the bank northwest of the pond. The access road was constructed using waste rock material sourced from the nonacid generating mine waste rock stockpile MM MATERIAL Tailings Pond 4 Stage 3 construction commenced with a key-in to Tailings Pond 3 in preparation for placing 75 mm minus material (see Photograph 4). Waste rock was pushed into the tailings beach across the length of the dam and subsequently covered with a thin layer of 75 mm material and a layer of LP8 geotextile to create a solid foundation (see Photograph 5). The placement of the 75 mm material followed in 1 ft lifts from a base elevation of ± 0.3 ft to tie in with the existing upstream crest of the dam, at an elevation of ± 1.0 ft, from Sta ft to Sta ft. Each lift was compacted with multiple passes of the vibratory drum roller (see Photograph 6) and an upstream slope of 2H:1V was maintained. The width of the filter zone is 9.3 to 13.8 ft. EBA completed quality control testing of the 75 mm filter zone. Refer to Photograph 7 for complete placement of the 75 mm filter zone WASTE ROCK As detailed in the design report (EBA, 2008), waste rock placement followed placement of the 75 mm filter zone. LP16 geotextile was rolled out perpendicular to the dam from Sta ft to Sta ft, followed by placement of the waste rock in 1.5 to 2 ft lifts (see Photograph 8). The waste rock was placed against the upstream slope and inwards towards the centre of the tailings pond. In areas where softer tailings were encountered, a layer of waste rock was compacted into the tailings beach until a firm foundation was achieved. Thereafter, construction continued as per the design. Each 1.5 ft to 2 ft lift was compacted with multiple passes of the D6H Cat until no deflection was observed (see Photograph 9). The upstream waste rock slope was sloped to 2H:1V (see Photograph 10). The final elevation of the waste rock is ± 0.6 ft at the crest and ± 0.6 ft at the centre. Following waste rock placement, the geotextile was wrapped to enclose the waste rock. A 2 ft minimum overlap was maintained along the transverse axis, while a 4 to 5 ft overlap was maintained along the longitudinal axis. At both ends of the dam, the geotextile was rolled up to completely encapsulate the waste rock. The width of the

11 Tailings Pond 4 Interim Construction Record Report 7 waste rock zone is 20.7 ft to 28.7 ft. EBA monitored the material placement and compaction. Photograph 11 shows the encapsulated waste rock MM MATERIAL Following construction of the waste rock zone, a 300 mm material cap was placed to protect the geotextile from damage (see Photograph 12). A 0.5 ft to 1 ft lift was placed across the waste rock zone to a final elevation of ± 0.5 ft at the crest and ± 0.4 ft at the centre. The variance in final elevation is due to a 4% inward slope across the dam crest. The material was compacted with multiple passes of the vibratory drum roller. The 300 mm material crest tied into the crest of the 75 mm filter zone, while the upstream slope of the 300 mm material blended into the 2H:1V slope of the underlying waste rock. The width of the 300 mm cap is 20.7 ft to 28.7 ft GEOTEXTILE After material placement on Tailings Pond 4, LP8 geotextile was placed on the upstream slope, perpendicular to the length of the dam. The geotextile extended 10 ft onto the tailings beach from the toe of the upstream slope and 10 ft onto the 300 mm cap from the surface of the upstream slope. On the surface of the dam, wooden stakes secured the geotextile. Rounded boulders were placed on the seams and at the toe of the geotextile along the upstream slope and on the tailings beach to secure the geotextile, as shown in Photograph DAM CREST SURFACE DRAINAGE The elevation of the dam surface on the upstream slope is ± 0.5 ft. The elevation of the dam surface on the downstream slope is ± 0.9 ft. The difference in elevation of the dam surface at the upstream and downstream slopes is due to the shallow inward slope for surface drainage. An inward slope of 4% was maintained across the crest of Tailings Pond 4 to manage surface drainage into the tailings pond. The shallow slope extends across the entire dam crest, including the recently placed 75 mm filter zone and 300 mm cap material. Low areas detected across Tailings Pond 4 where filled with the appropriate material (see Photograph 14).

12 Tailings Pond 4 Interim Construction Record Report SETTLEMENT MONUMENTS After the partial Stage 3 raise was completed on Tailings Pond 4, two settlement monuments were installed to monitor future vertical movement of the containment berm. The monuments were installed at Sta ft and Sta The settlement monuments are anchored into the 75 mm filter material and their locations were surveyed INSTRUMENTATION Vibrating wire piezometers were installed in Boreholes TP4-07-BH01, TP4-07-BH2, TP4-07-BH03, TP4-07-BH04, TP4-07-BH05, and TP4-07-BH06 in the existing Tailings Pond 4 berm during the April 2007 geotechnical investigation. On June 17, 2008, an additional vibrating wire piezometer was installed 6 ft (1.8 m) beneath the waste rock foundation at Sta and at an approximate elevation of ft. The wiring for the piezometers was extended during the berm raise in 2008 to allow for continued pore pressure measurement during and after construction. No additional piezometers were installed in MATERIAL QUANTITIES 6.1. SURVEY DATA A Leica TCR 705 Total Station was used by NATCL personnel to complete the required surveys on Tailings Pond 4. Further, the CAD program Promine was used to calculate material quantities and complete final as-built drawings. The completed partial Stage 3 construction is shown in Photograph 15. The total volume of material placed on Tailings Pond 4 was 237,281 ft 3 (6,719 m 3 ) during 2009 construction. This volume includes the 75 mm material, waste rock, and 300 mm material and includes the estimated amount of material pushed into the tailings to create a solid foundation in the tailings. A breakdown of the calculated quantities for each material type is shown in Table 1. TABLE 1: Construction Quantities for Tailings Pond 4 Material Imperial Volume (ft 3 ) Metric Volume (m 3 ) 75 mm 92,272 2, mm 121,509 3,441 Waste Rock 23, Total Volume Placed in ,281 6,719

13 Tailings Pond 4 Interim Construction Record Report QUALITY ASSURANCE Quality control testing of the 75mm and 300mm material was provided by EBA during construction. The information relating to the quality control testing will be presented by EBA in a separate report PARTICLE SIZE ANALYSIS Particle size analysis completed by EBA was conducted on 75 mm and 300 mm material samples during construction MOISURE-DENSITY RELATIONSHIP Moisture-density relationship testing by EBA was conducted on both 75 mm and 300 mm materials during construction. 8.0 MONITORING 8.1. GENERAL Performance monitoring is an integral part of the design, construction, and operation of any water or tailings containment structure. Monitoring of the berm serves the following functions: Monitor groundwater level within the new embankment. Monitor movements of the berm. Monitor groundwater quality downstream. Satisfy regulatory requirements for berm performance. A monitoring program is currently in effect at. Measurements and observations are recorded on a regular basis by NATCL and reviewed by EBA to assess berm performance and to identify maintenance requirements PIEZOMETERS The vibrating wire piezometers installed during the geotechnical investigation in April 2007 shall be sufficient to monitor variations of the local physical groundwater conditions.

14 Tailings Pond 4 Interim Construction Record Report EMBANKMENT MONITORING PROGRAM Observations during the geophysical investigation in April 2007 and Stage 1 construction in the fall of 2007 indicate that buried waste exists under Tailings Pond 4 berm. There is a risk that some berm movement may be experienced as a result of the underlying industrial waste shifting or consolidating. In November 2007, six inclinometers and six additional piezometers were installed along the berm length on the downstream slope to monitor and evaluate future berm movement. The inclinometers, in combination with the piezometers, shall provide a means of monitoring berm performance SETTLEMENT SURVEY Permanent settlement survey monitoring points shall be established once the berm reaches the final design elevation of ft, to monitor long term vertical movement in the structure. Temporary settlement monitoring points were established at 2 locations on the upstream crest of the berm in the 75 mm material following the partial Stage 3 raise construction. The settlement monuments are located at Sta ft and Sta ft and shall be used to monitor short term vertical movement. The temporary settlement monuments shall be removed prior to the completion of the Stage 3 berm raise ANNUAL INSPECTIONS In compliance with the water license, License No. MV2002L2-0019, issued to NATCL by the Mackenzie Valley Land and Water Board on January 30, 2009, an inspection of the tailings containment area shall be carried out annually during the summer season by a Geotechnical Engineer (MVLWB b, 2009, Section E.3.e). It will be necessary for the Geotechnical Engineer to conduct visual inspections for signs of instability, such as deformations, slumping, or transversal cracks. Specific tasks conducted during the inspection will include the following: Inspection of the upstream and downstream slopes for signs of distress. Inspection of the berm crest for signs of transverse cracking. Inspection of the abutments and downstream toe for any evidence of seepage. Review of deformation and piezometer data to verify conformance with design assumptions. In addition, the water license requires that an independent dam safety review be completed prior to September 30, 2010 and shall be carried out every five years until expiry of the license (MVLWB b, 2009, Section E.3.d).

15 Tailings Pond 4 Interim Construction Record Report CLOSURE This report is an account of the construction activities completed in 2009 for the Tailings Pond 4 partial Stage 3 construction and has been prepared by Tessa Brinkman, Junior Mine Engineer of NATCL for. Please do not hesitate to contact the Environmental Department at with any questions or concerns pertaining to the report. Tessa Brinkman Junior Mine Engineer site, North American Tungsten Corp.

16 Tailings Pond 4 Interim Construction Record Report REFERENCES North American Tungsten Corporation Ltd. (NATCL). (2009, August). Care and Maintenance Plan for Short Term Closure Commencing October Tungsten, NT. EBA Engineering Consultants Ltd. (EBA). (2009, July) Tailings Monitoring Plan, NT. Edmonton, AB. Mackenzie Valley Land and Water Board (MVLWB a). (2009, April 8). Request to raise Tailings Pond 4: Mining and Milling. Yellowknife, NT. Mackenzie Valley Land and Water Board (MVLWB b). (2009, January 30). Mackenzie Valley Land and Water Board Water License (License No. MV2002L2-0019). Yellowknife, NT: Section E.3. EBA Engineering Consultants Ltd. (EBA). (2008, March). Design Report for the Stage 2 and 3 Raises of the Containment Berm for Tailings Pond 4 Cantung Mine, Tungsten, NT. Whitehorse, YT.

17 Tailings Pond 4 Interim Construction Record Report 13 FIGURE 1:, NT Site Plan

18 Tailings Pond 4 Interim Construction Record Report 14 PHOTOGRAPH 1: Tailings Pond 4 Prior to 2009 Construction PHOTOGRAPH 2: Waste Rock Stockpile Located East of the Mine Portal

19 Tailings Pond 4 Interim Construction Record Report 15 PHOTOGRAPH 3: 300 mm Material Stockpile Located Adjacent to Tailings Pond 4 PHOTOGRAPH 4: Key-in to Tailings Pond 3

20 Tailings Pond 4 Interim Construction Record Report 16 PHOTOGRAPH 5: Foundation Preparation for the 75 mm Filter Zone PHOTOGRAPH 6: 75mm Filter Zone being Compacted with the Vibratory Drum Roller

21 Tailings Pond 4 Interim Construction Record Report 17 PHOTOGRAPH 7: Completed Placement of the 75 mm Filter Zone PHOTOGRAPH 8: Initial Waste Rock Placement

22 Tailings Pond 4 Interim Construction Record Report 18 PHOTOGRAPH 9: Waste Rock Lifts are Graded and Compacted with the Cat PHOTOGRAPH 10: Upstream Slope of Waste Rock is Sloped 2H:1V

23 Tailings Pond 4 Interim Construction Record Report 19 PHOTOGRAPH 11: Waste Rock Zone Encapsulated with Geotextile PHOTOGRAPH 12: Placement of the 300 mm Material Cap to Protect the Underlying Geotextile

24 Tailings Pond 4 Interim Construction Record Report 20 PHOTOGRAPH 13: Geotextile Wrapped Around Wood and Boulders to Secure the Geotextile PHOTOGRAPH 14: Filling and Compacting Low Spots on Tailings Pond 4

25 Tailings Pond 4 Interim Construction Record Report 21 PHOTOGRAPH 15: End of 2009 Construction for Tailings Pond 4

26 Tailings Pond 4 Interim Construction Record Report 22 INTERIM CONSTRUCTION RECORD REPORT TAILINGS POND 4 STAGE 3 RAISE OCTOBER 2009 APPENDIX A TAILS POND 4 AS BUILT DRAWING

27

Revision Tailings Management Plan Minto Mine, YT

Revision Tailings Management Plan Minto Mine, YT Revision 2017-1 Minto Mine, YT Prepared by: Minto Explorations Ltd. Minto Mine February, 2017 Minto Explorations Ltd. Minto Mine 2017-01 Minto Mine First Issue: January 2007 REVISION INFORMATION Rev. Number

More information

AIRCRAFT HANGAR PINCHGUT LAKE

AIRCRAFT HANGAR PINCHGUT LAKE AIRCRAFT HANGAR PINCHGUT LAKE ABSTRACT Please find enclosed Environmental Assessment submission relating to a proposed Aircraft Hangar at Pinchgut Lake, File 200.20.2707. Calv Swift [Course title] File

More information

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document Decision 2013-127 Alberta Electric System Operator Saleski Transmission Project Needs Identification Document ATCO Electric Ltd. Saleski 901S Substation and 144-kV Transmission Line 7L142 Facility Application

More information

ONONDAGA LAKE PRE-DESIGN INVESTIGATION: WASTEBED 13 SETTLEMENT PILOT STUDY MONITORING DATA YEAR 2 Onondaga County, New York

ONONDAGA LAKE PRE-DESIGN INVESTIGATION: WASTEBED 13 SETTLEMENT PILOT STUDY MONITORING DATA YEAR 2 Onondaga County, New York ONONDAGA LAKE PRE-DESIGN INVESTIGATION: WASTEBED 13 SETTLEMENT PILOT STUDY MONITORING DATA YEAR 2 Onondaga County, New York Prepared For: 5000 Brittonfield Parkway Suite 700 East Syracuse, NY 13057 Prepared

More information

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017 TODAY WE LL TALK ABOUT Our challenges and how we re meeting them Why we re building this project Our planning process and considerations

More information

GT-MHR COMMERCIALIZATION STUDY

GT-MHR COMMERCIALIZATION STUDY GT-MHR COMMERCIALIZATION STUDY Technical Progress and Cost Management Report for the Period July 1 through July 31, 2003 by GT-MHR Staff Contact: A. S. Shenoy Prepared under Oakland Operations Office Program

More information

Air Quality Permit File SOOP # Lindy Paving, Inc. I Homer City Plant

Air Quality Permit File SOOP # Lindy Paving, Inc. I Homer City Plant OffiCIAL FILE COPY SOUTHWEST REGIONAL OFFICE MEMO TO FROM THROUGH DATE Air Quality Permit File SOOP # 32-00311 Lindy Paving, Inc. I Homer City Plant Sheila A. Shaffer~ Air Quality Engineering S~ecialist

More information

BUREAU OF Statistics Yukon Energy Facts

BUREAU OF Statistics Yukon Energy Facts BUREAU OF Statistics Yukon Energy Facts Electricity Generation YUKON ELECTRICAL COMPANY YUKON ENERGY CORPORATION YUKON TOTAL HYDRO THERMAL HYDRO THERMAL WIND HYDRO THERMAL WIND (MW.h) (MW.h) (MW.h) 26

More information

Minto North Access Design

Minto North Access Design Minto North Access Design September 3, 2014 Minto North Access Design September 2, 2014 1 Introduction This document presents an updated plan for creating an access road to the Minto North pit. It shows

More information

RURAL ROAD MAINTENANCE PROGRAM GUIDELINES

RURAL ROAD MAINTENANCE PROGRAM GUIDELINES RURAL ROAD MAINTENANCE PROGRAM GUIDELINES April 2015 Contents: Overview:.. 1 Policy Goals and Objectives:... 1 Definitions:.. 1 Program Requirements:. 2 Road Standards and Specifications: 3 Right-of-Way:....

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016 Decision 21481-D01-2016 October 18, 2016 Alberta Utilities Commission Decision 21481-D01-2016 Proceeding 21481 Application 21481-A001 October 18, 2016 Published by the: Alberta Utilities Commission Fifth

More information

Hutchinson WWTF Solar PV EP4-41

Hutchinson WWTF Solar PV EP4-41 Hutchinson WWTF Solar PV EP4-41 John Paulson Project/Environmental/Regulatory Manager April 12, 2016 Site Preparation Panoramic 2 Site Preparation Aerial 3 Ballast Piers 18 H x 30 D - 410 total 4 5 6 7

More information

Worcester Public Schools Student Transportation Contract Proposed Bid Specification Change Summary Sheet

Worcester Public Schools Student Transportation Contract Proposed Bid Specification Change Summary Sheet Worcester Public Schools 2020-2022 Student Transportation Contract Proposed Bid Specification Change Summary Sheet 1 for a five-year period beginning the First Day of Summer School 2015 and ending on the

More information

Appendix E Water Supply Modeling

Appendix E Water Supply Modeling Supply Modeling Modesto Irrigation District Treatment Plant Expansion Project Modeling I. Introduction The Modesto Irrigation District (MID) is situated adjacent to and north of the Tuolumne River. Over

More information

SULPHUR IN DIESEL FUEL REGULATIONS [FEDERAL]

SULPHUR IN DIESEL FUEL REGULATIONS [FEDERAL] PDF Version [Printer-friendly - ideal for printing entire document] SULPHUR IN DIESEL FUEL REGULATIONS [FEDERAL] Published by Quickscribe Services Ltd. Updated To: [includes SOR/2006-163 amendments] Important:

More information

Night Work Specification

Night Work Specification Night Work Specification 1.0 Hours of Work The contractor is advised that most work for this contract will be carried out during night time hours. For the purposes of this contract night is defined as

More information

Magnetic Extensometer Systems GXM Range

Magnetic Extensometer Systems GXM Range DATASHEET Magnetic Extensometer Systems GXM Range The Geosense GEO-XM settlement system is used typically to monitor settlement and heave in foundations, excavations and embankments Overview Access Casing

More information

(2111) Digital Test Rolling REVISED 07/22/14 DO NOT REMOVE THIS. IT NEEDS TO STAY IN FOR THE CONTRACTORS. SP

(2111) Digital Test Rolling REVISED 07/22/14 DO NOT REMOVE THIS. IT NEEDS TO STAY IN FOR THE CONTRACTORS. SP S-xx (2111) Digital Test Rolling REVISED 07/22/14 DO NOT REMOVE THIS. IT NEEDS TO STAY IN FOR THE CONTRACTORS. SP2014-54.2 The Veda Software and Digital Test Rolling forms are available on the MnDOT Advanced

More information

U.S. Census Bureau News Joint Release U.S. Department of Housing and Urban Development

U.S. Census Bureau News Joint Release U.S. Department of Housing and Urban Development Raemeka Mayo or Stephen Cooper Economic Indicators Division (01) 76-5160 FOR IMMEDIATE RELEASE TUESDAY, MARCH 17, 015 AT 8:0 A.M. EDT NEW RESIDENTIAL CONSTRUCTION IN FEBRUARY 015 The U.S. Census Bureau

More information

Revision 4, Maine Yankee s License Termination Plan

Revision 4, Maine Yankee s License Termination Plan October 15, 2004 MN-04-051 RA-04-095 UNITED STATES NUCLEAR REGULATORY COMMISSION Attention: Document Control Desk Washington, DC 20555 References: 1. License No. DPR-36 (Docket No. 50-309) 2. MYAPC Letter

More information

APPENDIX 4-F. Construction Equipment Peak Analysis

APPENDIX 4-F. Construction Equipment Peak Analysis APPENDIX 4-F Construction Equipment Peak Analysis PORT METRO VANCOUVER Roberts Bank Terminal 2 This page is intentionally left blank Container Capacity Improvement Program - Roberts Bank Terminal 2 Construction

More information

DR SE WAY SOMERSIDE. C-N Neighborhood Commercial Site. R-LD - Development in accordance. Fully Landscaped Park/ Playground.

DR SE WAY SOMERSIDE. C-N Neighborhood Commercial Site. R-LD - Development in accordance. Fully Landscaped Park/ Playground. LAND & BUSINESS SUPPORT DEPT Southlands Phase 6A Plan 01231 City of Medicine Hat Land & Business Support Ph (03) 52-1 Fax (03) 502-055 land_properties@medicinehat.ca updated August 20, 201 SOMERSET BAY

More information

Transatlantic Mining Corporation Kearsarge Drilling Update.

Transatlantic Mining Corporation Kearsarge Drilling Update. Transatlantic Mining Corporation Kearsarge Drilling Update. TCO NEWS RELEASE-VANCOUVER, B.C., March 2, 2018 Transatlantic Mining Corp. (the Company ) (TCO:TSX.V) is pleased to announce that further due

More information

U.S. Census Bureau News Joint Release U.S. Department of Housing and Urban Development

U.S. Census Bureau News Joint Release U.S. Department of Housing and Urban Development Raemeka Mayo or Stephen Cooper Economic Indicators Division (01) 76-5160 FOR IMMEDIATE RELEASE FRIDAY, JUNE 17, 016 AT 8:0 A.M. EDT NEW RESIDENTIAL CONSTRUCTION IN MAY 016 The U.S. Census Bureau and the

More information

U.S. Census Bureau News Joint Release U.S. Department of Housing and Urban Development

U.S. Census Bureau News Joint Release U.S. Department of Housing and Urban Development Raemeka Mayo or Stephen Cooper Economic Indicators Division (01) 76-5160 FOR IMMEDIATE RELEASE WEDNESDAY, MARCH 16, 016 AT 8:0 A.M. EDT NEW RESIDENTIAL CONSTRUCTION IN FEBRUARY 016 The U.S. Census Bureau

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT RIDE QUALITY (MEAN ROUGHNESS INDEX ACCEPTANCE CRITERIA)

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT RIDE QUALITY (MEAN ROUGHNESS INDEX ACCEPTANCE CRITERIA) MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT RIDE QUALITY (MEAN ROUGHNESS INDEX ACCEPTANCE CRITERIA) CFS:TEH 1 of 10 APPR:KPK:JFS:07-07-16 FHWA:APPR:07-15-16 a. Description. This

More information

Northwest Territories Highway Traffic, 2007

Northwest Territories Highway Traffic, 2007 Northwest Territories Highway Traffic, 2007 Northwest Territories Highway Traffic, 2007 Department of Transportation Government of the Northwest Territories August 2008 Acknowledgements This report was

More information

Information Meeting Transfer Station Options. September 30, 2014

Information Meeting Transfer Station Options. September 30, 2014 Information Meeting Transfer Station Options September 30, 2014 Outline of Presentation Why we are looking at changes Background on current Transfer Station Options that were considered need, function

More information

THE USE OF PERFORMANCE METRICS ON THE PENNSYLVANIA TURNPIKE

THE USE OF PERFORMANCE METRICS ON THE PENNSYLVANIA TURNPIKE Wilke, P.W.; Hatalowich, P.A. 1 THE USE OF PERFORMANCE METRICS ON THE PENNSYLVANIA TURNPIKE Paul Wilke, P.E. Principal Engineer Corresponding Author Applied Research Associates Inc. 3605 Hartzdale Drive

More information

Penn West Petroleum Ltd. Well Blowout W5M August 17, 2010

Penn West Petroleum Ltd. Well Blowout W5M August 17, 2010 Penn West Petroleum Ltd. Well Blowout 14-20-065-10W5M August 17, 2010 ERCB Investigation Report August 24, 2011 ENERGY RESOURCES CONSERVATION BOARD ERCB Investigation Report: Penn West Petroleum Ltd.,

More information

Major/Area Source. Speaker: Eric Swisher. 23rd Virginia Environmental Symposium April 11, Your environmental compliance is clearly our business.

Major/Area Source. Speaker: Eric Swisher. 23rd Virginia Environmental Symposium April 11, Your environmental compliance is clearly our business. Major/Area Source Boiler MACT Rule Speaker: Eric Swisher 23rd Virginia Environmental Symposium April 11, 2012 Your environmental compliance is clearly our business. Overview Ground Rules Regulatory Framework

More information

Appendix G Aquilla Lake Pool Rise Recreational Resources

Appendix G Aquilla Lake Pool Rise Recreational Resources Appendix G Aquilla Lake Pool Rise Recreational Resources 1. INTRODUCTION The purpose of this appendix is to document the impacts of a 2.5 ft (Alternative A), 4.5 ft (Alternative B), and 6.5 ft. (Alternative

More information

Request for Statements of Qualification Gardnerville Station (Eagle Gas Station Redevelopment Project) 1395 Highway 395 N Gardnerville, NV

Request for Statements of Qualification Gardnerville Station (Eagle Gas Station Redevelopment Project) 1395 Highway 395 N Gardnerville, NV Gardnerville Station (Eagle Gas Station Redevelopment Project) 1395 Highway 395 N Gardnerville, NV Issued: Monday, Site Tour: Friday, January 30, 2015 at 10:00 a.m. Submittal Deadline: 5:00 p.m. on Friday,

More information

ALL AMERICAN CANAL LINING PROJECT. CM Status as of July 31, 2008

ALL AMERICAN CANAL LINING PROJECT. CM Status as of July 31, 2008 ALL AMERICAN CANAL LINING PROJECT CM Status as of 1 AACLP STATIONS 2 Reach 1A Reach 1B Reach 2 Reach 3 Reach 2 2 SAFETY 3 Monthly Injury/Illness Data KPC 0 Recordable accidents for the month of 1 Recordable

More information

NEW GOLD RAINY RIVER MINE APPENDIX I EXCEEDANCE TABLE

NEW GOLD RAINY RIVER MINE APPENDIX I EXCEEDANCE TABLE NEW GOLD RAINY RIVER MINE APPENDIX I EXCEEDANCE TABLE Incident Spill New Gold or Contractor New Gold Spill Origin Mill Operations Date and Time Reported 2018-01-03 Product Spilled Reclaim Water Impact

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82 Decision 21447-D01-2016 August 23, 2016 Decision 21447-D01-2016 Proceeding 21447 Application 21447-A001 August 23, 2016 Published by the: Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary,

More information

DESIGN STANDARDS SECTION DS 3 STREETS

DESIGN STANDARDS SECTION DS 3 STREETS DESIGN STANDARDS SECTION DS 3 STREETS DS 3-01 GENERAL: A. INTENT: The intent of these Design Standards is to provide minimum standards for the design of public streets. These standards are intended to

More information

WHITE POINT LANDSLIDE

WHITE POINT LANDSLIDE Gary Lee Moore, PE, ENV SP Alfred L. Mata, P.E., Deputy City Engineer WHITE POINT LANDSLIDE Status Report Recommended Immediate Measures (Estimate $12.96 Million) FUNDING APPROVED BY CITY COUNCIL ON: AUGUST

More information

Ambient PM 10 Monitoring Sechelt, B.C Update

Ambient PM 10 Monitoring Sechelt, B.C Update Ministry of Environment LOWER MAINLAND REGION Ambient PM 10 Monitoring Sechelt, B.C. 2004-2005 Update E N V I R O N M E N T A L Q U A L I T Y Library and Archives Canada Cataloguing in Publication Data

More information

A9 Data Monitoring and Analysis Report. January Content. 1. Executive Summary. 2. Overview. 3. Purpose. 4. Baseline Data Sources

A9 Data Monitoring and Analysis Report. January Content. 1. Executive Summary. 2. Overview. 3. Purpose. 4. Baseline Data Sources A9 Data Monitoring and Analysis Report January 2018 Content 1. Executive Summary 2. Overview 3. Purpose 4. Baseline Data Sources 5. Casualty Analysis 6. Vehicle Speed Data 7. Incident Frequency & Impact

More information

MONTHLY NEW RESIDENTIAL CONSTRUCTION, AUGUST 2017

MONTHLY NEW RESIDENTIAL CONSTRUCTION, AUGUST 2017 FOR RELEASE AT 8:30 AM EDT, TUESDAY, SEPTEMBER 19, MONTHLY NEW RESIDENTIAL CONSTRUCTION, AUGUST Release Number: CB17-158 Notice: For information on the impact of Hurricanes Harvey and Irma on the compilation

More information

U.S. Census Bureau News Joint Release U.S. Department of Housing and Urban Development

U.S. Census Bureau News Joint Release U.S. Department of Housing and Urban Development Raemeka Mayo or Stephen Cooper Economic Indicators Division (301) 763-5160 FOR IMMEDIATE RELEASE TUESDAY, MAY 17, 2016 AT 8:30 A.M. EDT NEW RESIDENTIAL CONSTRUCTION IN APRIL 2016 The U.S. Census Bureau

More information

Copyright Statement FPC International, Inc

Copyright Statement FPC International, Inc Copyright Statement All rights reserved. All material in this document is, unless otherwise stated, the property of FPC International, Inc. Copyright and other intellectual property laws protect these

More information

Road Condition Assessment and Road Contributions Study. 270 Grants Road, Somersby. June 2015 Our Ref: SY140135

Road Condition Assessment and Road Contributions Study. 270 Grants Road, Somersby. June 2015 Our Ref: SY140135 Condition Assessment and Contributions Study 270 June 2015 Our Ref: SY140135 Copyright Barker Ryan Stewart Pty Ltd 2015 All Rights Reserved Project No. SY140135 Author DH Checked PM Approved GB Rev No.

More information

LONG RANGE PERFORMANCE REPORT. Study Objectives: 1. To determine annually an index of statewide turkey populations and production success in Georgia.

LONG RANGE PERFORMANCE REPORT. Study Objectives: 1. To determine annually an index of statewide turkey populations and production success in Georgia. State: Georgia Grant Number: 08-953 Study Number: 6 LONG RANGE PERFORMANCE REPORT Grant Title: State Funded Wildlife Survey Period Covered: July 1, 2010 - June 30, 2011 Study Title: Wild Turkey Production

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

MONTHLY NEW RESIDENTIAL CONSTRUCTION, FEBRUARY 2017

MONTHLY NEW RESIDENTIAL CONSTRUCTION, FEBRUARY 2017 FOR RELEASE AT 8:30 AM EDT, THURSDAY, MARCH 16, MONTHLY NEW RESIDENTIAL CONSTRUCTION, FEBRUARY Release Number: CB17-38 March 16, - The U.S. Census Bureau and the U.S. Department of Housing and Urban Development

More information

MONTHLY NEW RESIDENTIAL CONSTRUCTION, JULY 2017

MONTHLY NEW RESIDENTIAL CONSTRUCTION, JULY 2017 FOR RELEASE AT 8:30 AM EDT, WEDNESDAY, AUGUST 16, MONTHLY NEW RESIDENTIAL CONSTRUCTION, JULY Release Number: CB17-133 August 16, - The U.S. Census Bureau and the U.S. Department of Housing and Urban Development

More information

Industrial, Commercial and Institutional Boilers at Area Source Facilities (Boiler GACT) Final Reconsidered Rule Requirements Summary

Industrial, Commercial and Institutional Boilers at Area Source Facilities (Boiler GACT) Final Reconsidered Rule Requirements Summary Industrial, Commercial and Institutional Boilers at Area Facilities (Boiler GACT) Final Reconsidered Rule Requirements Summary Federal Regulation NESHAP, 40 CFR 63, Subpart JJJJJJ Proposed rule published

More information

MONTHLY NEW RESIDENTIAL CONSTRUCTION, APRIL 2017

MONTHLY NEW RESIDENTIAL CONSTRUCTION, APRIL 2017 FOR RELEASE AT 8:30 AM EDT, TUESDAY, MAY 16, MONTHLY NEW RESIDENTIAL CONSTRUCTION, APRIL Release Number: CB17-75 May 16, - The U.S. Census Bureau and the U.S. Department of Housing and Urban Development

More information

Installation and Maintenance Manual CORRUGATED RIVETED GALVANIZED STEEL WATER STORAGE TANKS

Installation and Maintenance Manual CORRUGATED RIVETED GALVANIZED STEEL WATER STORAGE TANKS BH TANK A Division Of American Tank Co., Inc. Installation and Maintenance Manual CORRUGATED RIVETED GALVANIZED STEEL WATER STORAGE TANKS American Tank Co., Inc. P.O. Box 340 Windsor CA 95492 www.bhtank.com

More information

3. Application Fees, Certificate Of Insurance & Performance Bond

3. Application Fees, Certificate Of Insurance & Performance Bond SUBSECTION 13.10 CONSTRUCTION OF DRIVEWAYS 13.10A PERMIT REQUIREMENTS 1. General A driveway or access road serving private property and intersecting with a town road shall be constructed in such a manner

More information

MONTHLY NEW RESIDENTIAL SALES, APRIL 2017

MONTHLY NEW RESIDENTIAL SALES, APRIL 2017 FOR RELEASE AT 10:00 AM EDT, TUESDAY, MAY 23, MONTHLY NEW RESIDENTIAL SALES, APRIL Release Number: CB17-80 May 23, - The U.S. Census Bureau and the U.S. Department of Housing and Urban Development jointly

More information

A REPORT TO. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution. Telecontrol. System Planning

A REPORT TO. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution. Telecontrol. System Planning A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Electrical 4v ^c 0:01'1 S0^O c.. ^ '^ W E. G. PIERCY i^ x zoto/off/zq,.'ftrif4^#ft^^,' r Mechanical Civil Protection & Control Transmission &

More information

APPENDIX G. Towing Survey for Concrete Floats

APPENDIX G. Towing Survey for Concrete Floats APPENDIX G Towing Survey for Concrete Floats June 3, 2016 Our File # V 16/039 Trip in Tow Survey Of Concrete Floats For Vancouver Pile Driving Ltd. Report of survey undertaken March 8, 2010 review for

More information

PROPOSED HELICOPTER LANDING PAD 85 MILL ROAD LARA

PROPOSED HELICOPTER LANDING PAD 85 MILL ROAD LARA PROPOSED HELICOPTER LANDING PAD 85 MILL ROAD LARA Assessment of Helicopter Noise A report Prepared on behalf of: JamCo Constructions Pty Ltd PO Box 631 Yarraville Victoria 3013 Ref: 11573-3jg March 2015

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 27, 2012 SUBJECT: NOTICE OF AWARD PROCUREMENT AUTHORIZATION - ARTICULATED BUSES INFORMATION ITEM RECOMMENDATION

More information

Environment Restoration Operations Solid Waste Management Unit (SWMU) 52: Filling Tanks 2 and 4 with a Permanent Insoluble Material - September 2013

Environment Restoration Operations Solid Waste Management Unit (SWMU) 52: Filling Tanks 2 and 4 with a Permanent Insoluble Material - September 2013 University of New Mexico UNM Digital Repository Environmental Restoration Sandia National Labs/NM Technical Reports 10-9-2013 Environment Restoration Operations Solid Waste Management Unit (SWMU) 52: Filling

More information

RESIDENTIAL WASTE HAULING ASSESSMENT SERVICES. January 10, 2011 Presentation to Arvada City Council

RESIDENTIAL WASTE HAULING ASSESSMENT SERVICES. January 10, 2011 Presentation to Arvada City Council RESIDENTIAL WASTE HAULING ASSESSMENT SERVICES January 10, 2011 Presentation to Arvada City Council CONSULTANT TEAM LBA Associates MSW Consultants Denver based recycling and waste management consultant

More information

The Earthworks and Heavy Haulage Specialists

The Earthworks and Heavy Haulage Specialists The Earthworks and Heavy Haulage Specialists JEFFSANN EXCAVATIONS PTY LIMITED Jeffsann Excavations is a family owned business servicing the greater Sydney Metropolitan area for over 25 years! Established

More information

MONTHLY NEW RESIDENTIAL CONSTRUCTION, NOVEMBER 2017

MONTHLY NEW RESIDENTIAL CONSTRUCTION, NOVEMBER 2017 FOR RELEASE AT 8:30 AM EST, TUESDAY, DECEMBER 19, MONTHLY NEW RESIDENTIAL CONSTRUCTION, NOVEMBER Release Number: CB17-206 December 19, - The U.S. Census Bureau and the U.S. Department of Housing and Urban

More information

The Director, Purchasing and Materials Management recommends that:

The Director, Purchasing and Materials Management recommends that: STAFF REPORT ACTION REQUIRED Request for Quotation 6902-07-3168 For the supply, delivery and off-loading of Pre-blended Ethanol Unleaded Gasoline, and Pre-blended Bio-diesel and Low Sulphur Diesel Fuels

More information

2010 Motorcycle Risk Study Update

2010 Motorcycle Risk Study Update 2010 Motorcycle Risk Study Update Introduction This report provides an update to the Motorcycle Risk Study from AI.16 of the 2005 Rate Application. The original study was in response to Public Utilities

More information

Memorandum October 5, 2017

Memorandum October 5, 2017 614 Magnolia Avenue Ocean Springs, Mississippi 39564 228.818.9626 Memorandum October 5, 2017 To: Gary Miller, U.S. Environmental Protection Agency From: David Keith, John Laplante, Matt Henderson, and

More information

For further information, please contact Geoff Higgins at or by at

For further information, please contact Geoff Higgins at or by  at B-1-3 Tom A. Loski Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 bchydroregulatorygroup@bchydro.com November 30, 2015 Ms. Erica Hamilton Commission Secretary British Columbia Utilities

More information

FINAL LICENSE APPLICATION Exhibit A Description of Project

FINAL LICENSE APPLICATION Exhibit A Description of Project FINAL LICENSE APPLICATION Exhibit A Description of Project PacifiCorp Portland, Oregon April 2004 Copyright 2004 by PacifiCorp Reproduction in whole or in part without the written consent of PacifiCorp

More information

Contract No: OASRTRS-14-H-MST (Missouri University of Science and Technology)

Contract No: OASRTRS-14-H-MST (Missouri University of Science and Technology) Smart Rock Technology for Real-time Monitoring of Bridge Scour and Riprap Effectiveness Design Guidelines and Visualization Tools (Progress Report No. 7) Contract No: OASRTRS-14-H-MST (Missouri University

More information

Ronnie van Eeden. Senior Mining Engineer. Overview

Ronnie van Eeden. Senior Mining Engineer. Overview Senior Mining Engineer Overview is a qualified Mining Engineer with other commercial qualifications. He has 46 years of experience in the coal industry working for mining houses, the smaller coal industry,

More information

Quarterly Activities Report

Quarterly Activities Report Quarterly Activities Report Three months ended 31 December 2017 31 January 2018 Frontier Diamonds Limited (ASX: FDX) (Frontier or the Company) is pleased to provide an overview of its key activities for

More information

WELLINGTON, NEW ZEALAND. PURSUANT to sections 152, 155(a) and (e) and 158(a)(i) of the Land Transport Act 1998

WELLINGTON, NEW ZEALAND. PURSUANT to sections 152, 155(a) and (e) and 158(a)(i) of the Land Transport Act 1998 WELLINGTON, NEW ZEALAND PURSUANT to sections 152, 155(a) and (e) and 158(a)(i) of the Land Transport Act 1998 I, Gerry Brownlee, Minister of Transport, HEREBY make the following ordinary Rule: Land Transport

More information

Appendix 4-2-C Project Air Emissions Inventory

Appendix 4-2-C Project Air Emissions Inventory Appendix A CALPUFF and CALMET Methods and Assumptions Appendix 4-2-C Project Air Emissions Inventory C.1 Introduction For the purposes of estimating effects on air quality associated with the Project,

More information

SNOHOMISH COUNTY PUBLIC UTILITY DISTRICT NO.1. Your Northwest renewables utility

SNOHOMISH COUNTY PUBLIC UTILITY DISTRICT NO.1. Your Northwest renewables utility SNOHOMISH COUNTY PUBLIC UTILITY DISTRICT NO.1 Your Northwest renewables utility May 17, 2013 VIA ELECTRONIC FILING Kimberly D. Bose, Secretary Federal Energy Regulatory Commission (FERC) 888 First Street

More information

GOPALAN COLLEGE OF ENGINEERING AND MANAGEMENT Department of Civil Engineering COURSE PLAN

GOPALAN COLLEGE OF ENGINEERING AND MANAGEMENT Department of Civil Engineering COURSE PLAN Appendix - C GOPALAN COLLEGE OF ENGINEERING AND MANAGEMENT Department of Civil Engineering Academic Year: 2016-17 Semester: EVEN COURSE PLAN Semester: VI Subject Code& Name: 10CV64 & Geotechnical Engineering-II

More information

Garden Well Gold Deposit Diamond Drilling Confirms Gold at Depth Highlights

Garden Well Gold Deposit Diamond Drilling Confirms Gold at Depth Highlights 7 December 2010 ABN 28 009 174 761 www.regisresources.com Manager Announcements Company Announcements Office Australian Securities Exchange Limited Level 4, 20 Bridge Street Sydney NSW 2000 Level 1, 1

More information

WVDP Project Update. Scott Anderson. Deputy General Manager. Citizen Task Force Meeting July 25, 2018

WVDP Project Update. Scott Anderson. Deputy General Manager. Citizen Task Force Meeting July 25, 2018 WVDP Project Update Scott Anderson Deputy General Manager Citizen Task Force Meeting July 25, 2018 www.energy.gov/em 1 Safety Metric June 2018 12-Month Rolling Average TRC (12-Month Rolling Average) DART

More information

Rehabilitation Techniques to Improve Long-term Performance of Highway-Railway At-Grade Crossings

Rehabilitation Techniques to Improve Long-term Performance of Highway-Railway At-Grade Crossings Rehabilitation Techniques to Improve Long-term Performance of Highway-Railway At-Grade Crossings Dr. Jerry G. Rose, P.E. Professor of Civil Engineering 261 Raymond Building University of Kentucky 859-257-4278

More information

TYPICAL DRIVEWAY CONSTRUCTION PER DOUGLAS COUNTY REGULATIONS AND POLICIES

TYPICAL DRIVEWAY CONSTRUCTION PER DOUGLAS COUNTY REGULATIONS AND POLICIES TYPICAL DRIVEWAY CONSTRUCTION PER DOUGLAS COUNTY REGULATIONS AND POLICIES This document is a summary of the Douglas County regulations and policies for constructing residential driveways. It is intended

More information

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date,

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, is now called the Valley Line. We are here to present

More information

MMP Investigation of Arthur Kill 2 and 3

MMP Investigation of Arthur Kill 2 and 3 MMP Investigation of Arthur Kill 2 and 3 Requestor Consolidated Edison Company of New York, Inc. Facility Name Arthur Kill 2 and 3 Date of Request January 27, 2003 Type of Facility NG Generator Topic of

More information

Yukon s Independent Power Production Policy

Yukon s Independent Power Production Policy Yukon s Independent Power Production Policy Updated October 2018 BACKGROUND The Government of Yukon (YG) released the Energy Strategy for Yukon in January 2009. The strategy sets out YG s energy priorities,

More information

Alignment Comparison Report (May 9, 2002) PARK BRIDGE TO BRAKE CHECK (10 Mile Bridge) TRANS CANADA HIGHWAY (CCR)

Alignment Comparison Report (May 9, 2002) PARK BRIDGE TO BRAKE CHECK (10 Mile Bridge) TRANS CANADA HIGHWAY (CCR) Alignment Comparison Report (May 9, 2002) PARK BRIDGE TO BRAKE CHECK (10 Mile Bridge) TRANS CANADA HIGHWAY (CCR) INTRODUCTION The Ministry of Transportation (MoT), Region 2, Highway Engineering staff were

More information

welcome to the BC Hydro community open house

welcome to the BC Hydro community open house welcome to the BC Hydro community open house Dawson Creek/ Chetwynd Area Transmission ProjecT Open House welcome Dawson Creek/Chetwynd Area Transmission Project (DCAT) The purpose of this open house is

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

LAKE CHELAN ANNUAL FLOW AND WATER TEMPERATURE REPORT Final

LAKE CHELAN ANNUAL FLOW AND WATER TEMPERATURE REPORT Final LAKE CHELAN ANNUAL FLOW AND WATER TEMPERATURE REPORT 2013 LICENSE ARTICLES 405 & 408 Final LAKE CHELAN HYDROELECTRIC PROJECT FERC Project No. 637 April 30, 2014 Public Utility District No. 1 of Chelan

More information

Arizona Tank Closure, Assessment and Response

Arizona Tank Closure, Assessment and Response Arizona Tank Closure, Assessment and Response By: Phillip A. Schneider, P.E. August 1, 2013 Agenda > Closure > Assessment > Response Exceptions to the UST State and Federal Regulations > USTs storing heating

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : June,

More information

SFI SPECIFICATION 35.2 EFFECTIVE: DECEMBER 29, 2014 *

SFI SPECIFICATION 35.2 EFFECTIVE: DECEMBER 29, 2014 * SFI SPECIFICATION 35.2 EFFECTIVE: DECEMBER 29, 2014 * PRODUCT: Heavy Duty Stock Car Steel Wheels 1.0 GENERAL INFORMATION 1.1 This SFI Specification establishes uniform test procedures and minimum standards

More information

SOLAR FEASIBILITY STUDY

SOLAR FEASIBILITY STUDY SOLAR FEASIBILITY STUDY KAKE SENIOR CENTER KAKE ALASKA June 24, 2015 Submitted By: BacGen Technologies, Inc, Maud de Bel Maud@bacgen.com 206-459-9418 Executive Summary BacGen investigated the feasibility

More information

PART 665 BUS TESTING. Subpart A General. 49 CFR Ch. VI ( Edition)

PART 665 BUS TESTING. Subpart A General. 49 CFR Ch. VI ( Edition) Pt. 665 PART 665 BUS TESTING Subpart A General Sec. 665.1 Purpose. 665.3 Scope. 665.5 Definitions. 665.7 Grantee certification of compliance. Subpart B Bus Testing Procedures 665.11 Testing requirements.

More information

YUKON DEVELOPMENT CORPORATION

YUKON DEVELOPMENT CORPORATION YUKON DEVELOPMENT CORPORATION 2 http://www.ydc.yk.ca YUKON DEVELOPMENT CORPORATION ANNUAL REPORT 2016 TABLE OF CONTENTS Message from the Chair...4 Message from the President and Chief Executive Office...

More information

Santa Fe Calvada Mine. Final Closure of a Heap Leach Facility Case Study in Design and Construction of E-cells

Santa Fe Calvada Mine. Final Closure of a Heap Leach Facility Case Study in Design and Construction of E-cells Santa Fe Calvada Mine Final Closure of a Heap Leach Facility Case Study in Design and Construction of E-cells Site Location Location with Surrounding Topography Overall Site Layout Google Earth View History

More information

Maddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016

Maddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016 New Transmission Line November 15, 2016 The enclosed information is proprietary to PSE&G and is provided solely for your use. It should not be copied, reproduced, or shared with others without PSE&G s

More information

VALUE ENGINEERING STUDIES FINAL REPORT. Portsmouth Bypass, Phase 1 SCI PID 19415

VALUE ENGINEERING STUDIES FINAL REPORT. Portsmouth Bypass, Phase 1 SCI PID 19415 VALUE ENGINEERING STUDIES FINAL REPORT Portsmouth Bypass, Phase 1 SCI-823-6.81 PID 19415 PREPARED FOR: Ohio Department of Transportation District 9 650 Eastern Avenue Chillicothe, Ohio 45601 PREPARED BY:

More information

A9 Data Monitoring and Analysis Report. March Content. 1. Executive Summary and Key Findings. 2. Overview. 3. Purpose

A9 Data Monitoring and Analysis Report. March Content. 1. Executive Summary and Key Findings. 2. Overview. 3. Purpose A9 Data Monitoring and Analysis Report March 2018 Content 1. Executive Summary and Key Findings 2. Overview 3. Purpose 4. Baseline Data Sources and Methodology 5. Casualty Analysis 6. Vehicle Speed Data

More information

Dalchully, Laggan PH20 1BU, UK T: +44 (0) E: W:

Dalchully, Laggan PH20 1BU, UK T: +44 (0) E: W: Dalchully, Laggan PH20 1BU, UK T: +44 (0) 1528 544 201 E: angus@adac-structures.co.uk W: www.adac-structures.co.uk Location map for various sites Job name: Condition report into foundations of various

More information

SFI SPECIFICATION 39.2 EFFECTIVE: August 25, 2017 *

SFI SPECIFICATION 39.2 EFFECTIVE: August 25, 2017 * SFI SPECIFICATION 39.2 EFFECTIVE: August 25, 2017 * PRODUCT: Racing Seats (Standard) 1.0 GENERAL INFORMATION 1.1 This SFI Specification establishes uniform test procedures and minimum standards for evaluating

More information

Downtown Lee s Summit Parking Study

Downtown Lee s Summit Parking Study Downtown Lee s Summit Parking Study As part of the Downtown Lee s Summit Master Plan, a downtown parking and traffic study was completed by TranSystems Corporation in November 2003. The parking analysis

More information

52.1 SNOW REMOVAL AND ICE CONTROL (TRUCK)

52.1 SNOW REMOVAL AND ICE CONTROL (TRUCK) 52.1 SNOW REMOVAL AND ICE CONTROL (TRUCK) 52.1.1 GENERAL The Work consists of loading trucks, snowplowing and the application of sand, salt or a sand and salt mixture to roadway surfaces. 52.1.2 MATERIALS

More information

Build-A-Box Modular Trench Shielding System

Build-A-Box Modular Trench Shielding System AMERICA S TRENCH BOX BUILDER Build-A-Box Modular Trench Shielding System EFFICIENCY PRODUCTION Build-A-Box Tabulated Data Tabulated Data Effective January 4, 2010 Revised: January 4, 2018 - with CHANGE

More information

Appendix A - Technical Specifications RFQ Emergency WasteWater Cleanup Services

Appendix A - Technical Specifications RFQ Emergency WasteWater Cleanup Services Appendix A - Technical Specifications RFQ 91795 - Emergency WasteWater Cleanup Services SCOPE The biosolids, sand, sewage, debris, grit and /or grease may be malodorous. When required, biosolids, sand,

More information