Successful Strategies. for Managing the Complex ebart Extension
|
|
- Clifton Malone
- 5 years ago
- Views:
Transcription
1 Successful Strategies for Managing the Complex ebart Extension
2 1 Maurice Ric Rattray, PE Group Manager, Capital Program BART
3 1 Andy Kleiber, PE Principal Construction Manager MNS Engineers, Inc.
4 0 1 Introduction 2 Project Background 3 Management of Complex Project AGENDA 4 Planning 5 Project 6 Questions and Implementation Success and Answers
5 1 Team
6 2 PROJECT BACKGROUND
7 2 Project Background Adopted by BART Board in April 2009 Diesel Multiple Unit (DMU) technology State Route 4 median alignment Ten-mile extension to City of Antioch Facilities Transfer Platform at Pittsburg/Bay Point Pittsburg Center Station Antioch Station Maintenance Facility
8 2 Project Background Pittsburg Center Station Transfer Platform BART/eBART Antioch Station Existing Alignment ebart Extension Transfer Platform Pittsburg Center Station Antioch Station
9 2 Technologies Evaluated Conventional BART Conventional BART Light Rail Vehicle DMU Trains DMU Bus Rapid Transit
10 2 Diesel Multiple Unit (DMU) Technology Service proven EPA Tier 4 compliant Self propelled Reliable redundancy Light weight Low floor Capable of operating at 75 mph
11 2 Diesel Multiple Unit (DMU) Technology Capacity Bio Diesel 3 car consists Crash Energy Management
12 2 Vehicle Layout Description Dimension Fixed Seats 88 Flip Up Seats 16 Total Seats 104 Standing Area 26 m² Standees (4 Pers/m²) 96 Total Passenger Capacity, max 200
13 3 MANAGEMENT OF COMPLEX PROJECT
14 3 Construction Complexity 15 overlapping construction contracts 12 agencies 10 utility companies 6 years of environmental, design, and Caltrans coordination 7 years of construction
15 3 Multiple Contracts BART Construction Contracts Transfer Platform Maintenance Facility Shell and Parking Lot Trackwork, Systems, and Station Finishes Sanitary Sewer Final Paving Landscaping CCTA/Caltrans/ Highway Contracts Caltrans Segment 0 Caltrans Segment 1 Caltrans Segment 2 Caltrans Segment 3A Caltrans Segment 3B BART Procurement Contracts Vehicles Rail Procurement Station Equipment Parking Lot Solar Panels
16 3 Multiple Agencies Funding Agencies The Metropolitan Transportation Commission (MTC) Contra Costa Transportation Authority (CCTA) East Contra Costa Regional Fee and Finance Authority (ECCRFFA) The State of California Support Agencies City of Pittsburg City of Antioch City of Oakley City of Brentwood Contra Costa County Tri Delta Transit Caltrans
17 3 Packaging Strategies to Minimize Risk Scopes Structures and underground early BART interface isolated Early procurement for long lead items
18 3 Packaging Strategies to Minimize Risk Contract Milestone 9 included in main BART contract Access and availability dates 19 included in main BART contract Area 1 and Area 2 for vehicle testing
19 3 Pittsburg Center Station Increased ebart ridership by 20% Complies with BART s system expansion policy and MTC s TOD policy Low incremental operating costs for additional riders
20 4 PLANNING AND IMPLEMENTATION
21 4 Schedule First Vehicle On Site Pre-Revenue and Simulated Testing MAY 2018
22 4 Project Budget Description Budget Conventional BART Conceptual/Environmental $11.2 $11.2 Preliminary Engineering $14.9 $20 Final Design $38.5 $45 Construction and Procurement $384.1 $1015 Construction Management (CM) & Design Service During Construction (DSDC) $49.0 $55 Right-of-Way $13.0 $31 Program Reserve $14.2 $45 TOTAL $524.9 $1,222.2
23 4 BART/CCTA/Caltrans Cooperation Median Guideway Utility Duct Banks Bridges Pedestrian Overcrossing Bridges
24 4 Antioch Station
25 4 Antioch Station and Pedestrian Bridge
26 4 ebart Maintenance Facility
27 4 ebart Maintenance Facility
28 4 Management Strategies CM software MS access PDFs with hyperlinks Inspector workbooks weekly check-in meetings with ALL involved
29 4 Vehicle Fabrication 2 9
30 4 Vehicle Journey 3 0
31 4 Vehicle Journey
32 4 Vehicle Unloading Maintenance Facility 3 2
33 5 PROJECT SUCCESS
34 5 Project Success $525M vs $1B traditional BART Cost-effective, timely solution More than double the ridership Predicted 3,995 trips/day More than 8,000 trips/day currently New parking lot being planned already
35 QUESTION AND ANSWER
BART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010
BART Silicon Valley Berryessa Extension Project Community Update October 27, 2010 1 Agenda Welcome and Introductions Program and Project Background Project Status Project and Station Details Current and
More informationDraft Results and Recommendations
Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Recommendations Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System
More informationRapid Transit and Land-Use Integration a Reality
City of Charlotte Rapid Transit and Land-Use Integration a Reality Transportation Oversight Committee Carolyn Flowers CEO Charlotte Area Transit System April 29, 2010 Charlotte Region Statistics Mecklenburg
More informationREPORT CARD FOR CALIFORNIA S INFRASTRUCTURE WHAT YOU SHOULD KNOW ABOUT CALIFORNIA S TRANSIT FACILITIES
TRANSIT GRADE: C- WHAT YOU SHOULD KNOW ABOUT TRANSIT FACILITIES California needs robust, flexible and reliable transit systems to reduce peak congestion on our highways, provide options for citizens who
More informationVAN NESS AVENUE BUS RAPID TRANSIT
VAN NESS AVENUE BUS RAPID TRANSIT Commission of the Environment Policy Committee May 22, 2014 Peter Gabancho Project Manager III Capital Programs & Construction SFMTA 1 Conceptual Visual Simulation Center-Running
More informationBROWARD BOULEVARD CORRIDOR TRANSIT STUDY
BROWARD BOULEVARD CORRIDOR TRANSIT STUDY FM # 42802411201 EXECUTIVE SUMMARY July 2012 GOBROWARD Broward Boulevard Corridor Transit Study FM # 42802411201 Executive Summary Prepared For: Ms. Khalilah Ffrench,
More informationProposed FY Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1
Proposed FY 2019-2023 Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1 The Capital Improvement Program is: A fiscally constrained, 5-year program of capital projects An implementation
More informationPacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis
Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis Transit Coalition September 26, 2012 2 Study Area Pacific Electric Rightof-Way/West Santa Ana Branch (PEROW/ WSAB) extends
More informationDraft Results and Open House
Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi
More informationCharlotte-Mecklenburg Region Rapid Transit and Land-Use Integration
Charlotte-Mecklenburg Region Rapid Transit and Land-Use Integration Legislative Committee on Urban Growth and Infrastructure Carolyn Flowers CEO Charlotte Area Transit System March 23, 2010 Charlotte Region
More informationHigh Speed Rail Conference
High Speed Rail Conference Denver, October 23, 2012 FAST START PROJECT FOR PENINSULA HIGH-SPEED RAIL Kern Jacobson InfraConsult LLC Objective Evaluate incremental approach to expedite high-speed rail to
More informationFREQUENTLY ASKED QUESTIONS
FREQUENTLY ASKED QUESTIONS 2018 What is the More MARTA Atlanta program? The More MARTA Atlanta program is a collaborative partnership between MARTA and the City of Atlanta to develop and implement a program
More informationBalancing the Transportation Needs of a Growing City
Balancing the Transportation Needs of a Growing City FY 2019 and FY 2020 Capital Budget SFMTA Board Meeting Ed Reiskin, Director of Transportation April 3, 2018 1 FY 2019-23 Capital Improvement Program
More informationRedefining Mobility Ready or not: Autonomous and connected vehicle planning and policy, now and in the future
Redefining Mobility Ready or not: Autonomous and connected vehicle planning and policy, now and in the future Randy Iwasaki November 30, 2017 WHO WE ARE The Contra Costa Transportation Authority (CCTA)
More informationOakland County Board of Commissioners General Government Committee April 23, SMART Services in Oakland County
Oakland County Board of Commissioners General Government Committee April 23, 2018 SMART Services in Oakland County Today s Presentation SMART in Oakland County Promises Kept Fixed Route Buses Small Buses
More informationO-Train Confederation Line Stage 1
O-Train Confederation Line Stage 1 Presented to: Regional Public Works Commissioners of Ontario June 23, 2017 by Steve Cripps, Director, O-Train Construction The Need Ottawa s population is projected to
More informationSEPULVEDA PASS CORRIDOR
SEPULVEDA PASS CORRIDOR PUBLIC PRIVATE PARTNERSHIP DELIVERY PRE-DEVELOPMENT AGREEMENT PDA Sepulveda Pass Mobility Issues Most congested highway segment in the U.S. 295,000 vehicles per day (2010) 430,000
More informationLeveraging Land Use Changes through Transportation Funding
Leveraging Land Use Changes through Transportation Funding Railvolution 2005 September 10, 2005 James Corless Senior Planner What is the MTC region? 9 7 101 26 San Francisco Bay Area counties Million people;
More informationStrategic Planning for Metro s Transition to Zero Emission Buses. October 2017
Strategic Planning for Metro s Transition to Zero Emission Buses October 2017 Requirements and Guidelines/Guiding Principles Continue to replace Aging Bus Fleet (~200 Buses per Year) Upgrade current CNG
More information3.15 SAFETY AND SECURITY
3.15 SAFETY AND SECURITY Introduction This section describes the environmental setting and potential effects of the alternatives analyzed in this EIR with regard to safety and security in the SantaClara-Alum
More informationConverting BRT to LRT in the Nation s Capital Ottawa, Canada. John Manconi City of Ottawa Ottawa, Canada
Converting BRT to LRT in the Nation s Capital Ottawa, Canada John Manconi City of Ottawa Ottawa, Canada 1 The Challenge *Mackenzie King Bridge Ottawa, AM peak period 2 The Challenge Ottawa s population
More informationCANADA LINE a Canadian P3 Success Story
CANADA LINE a Canadian P3 Success Story Project Context The Canada Line An automated light rail rapid transit system linking downtown Vancouver with both Richmond and Vancouver International Airport Construction
More informationElectric Multiple Unit Procurement Update
Electric Multiple Unit Procurement Update Board of Directors August 7, 2014 Context* * The proposed project is not yet approved pending environmental clearance. 2 1 Status April 2014 - JPB update on EMU
More informationVAN NESS AVENUE BUS RAPID TRANSIT
VAN NESS AVENUE BUS RAPID TRANSIT Peter Gabancho Project Manager III Capital Programs & Construction SFMTA Shari Tavafrashti Principal Engineer SFCTA 1 Project Purpose and Need Improve transit reliability,
More informationACTION TRANSMITTAL No
Transportation Advisory Board of the Metropolitan Council of the Twin Cities DATE: January 4, 2016 TO: ACTION TRANSMITTAL No. 2016-19 TAC Funding and Programming Committee PREPARED BY: Joe Barbeau, Senior
More informationExhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup
Exhibit A Sound Transit Board Resolution R2016-07 Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Access Improvement Project. RESOLUTION NO. R2016-07 Selecting
More informationACEforward. BART Connectivity Alternatives Preliminary Forecasts and Costs Altamont Regional Rail Working Group July 13, 2016
ACEforward ACEforward BART Connectivity Alternatives Preliminary Forecasts and Costs Altamont Regional Rail Working Group July 13, 2016 ACEforward Project Goals Tri-Valley BART Connection Union City BART
More informationRocky Mountain. Corridor Input Team. Alternatives Overview. TEMS, Inc. / Quandel Consultants, LLC TEMS, Inc. / Quandel Consultants, LLC
Rocky Mountain Rail Authority (RMRA) Corridor Input Team Meeting #2 Alternatives Overview December 2008 TEMS, Inc. / Quandel Consultants, LLC 0 Agenda Introductions Study Overview Alternatives Overview
More informationWaco Rapid Transit Corridor (RTC) Feasibility Study
Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM
More informationL. A. Metro s Parking Management Program Principles Applied. October 17, 2011 Rail-Volution, Washington D.C.
Los Angeles County Metropolitan Transportation Authority L. A. Metro s Parking Management Program Principles Applied October 17, 2011 Rail-Volution, Washington D.C. What is Parking Management? Various
More informationExecutive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009.
Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009 Background As the Treasure Valley continues to grow, high-quality transportation connections
More informationAgenda. Preliminary Station Footprint High Speed Train Station in the City of Millbrae
Agenda Preliminary Station Footprint High Speed Train Station in the City of Millbrae Open House 7:00 7:30 Presentation 7:30 8:00 Community Question/Answer 8:00 9:00 Adjourn 2 Preliminary Station Footprint
More informationMOTION NO. M Preferred Alternative for the Puyallup Station Access Improvement Project
MOTION NO. M2014 64 Preferred Alternative for the Puyallup Station Access Improvement Project MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 8/14/14 8/28/14 Recommendation
More informationMetro Green Line to LAX Alternatives Analysis. March 2012
Metro Green Line to LAX Alternatives Analysis 1 2 The Crenshaw/LAX Project Foundation for Metro Green Line to LAX 8.5 mile extension Metro Exposition Line (Crenshaw Exposition) to Metro Green Line (Aviation/LAX
More informationLetter EL652 City of Mercer Island. Page 1. No comments n/a
Letter EL652 City of Mercer Island Page 1 No comments n/a Page 2 Response to comment EL652 1 Section 4.5.3 of the Final EIS presents the range of potential impacts of the project. This project also lists
More informationRolling Road (Route 638) Widening Project
Rolling Road (Route 638) Widening Project From: 0.369 Mile North of Fairfax County Parkway (Route 286) To: Old Keene Mill Road (Route 644) State Project No. 0638-029-156, P104, R204, C504; UPC 5559 Public
More informationDRAFT Subject to modifications
TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M DRAFT To: Council Members AGENDA ITEM 7A From: Date: Subject: Staff September 17, 2010 Council Meeting High Speed Rail Update Introduction The
More informationMarch 2, 2017 Integrating Transportation Planning, Project Development, and Project Programming
COORDINATION WITH VDOT DISTRICTS TO DELIVER IMPLEMENTABLE IMPROVEMENT PROJECTS March 2, 2017 Integrating Transportation Planning, Project Development, and Project Programming PRESENTATION OUTLINE What
More informationI 680 Transit Investment/Congestion Relief Options Study
I 680 Transit Investment/Congestion Relief Options Study Prepared for Contra Costa Transportation Authority By 1970 Broadway, Suite 740 Oakland, CA 94612 (510) 763 2061 In association with Parsons Transportation
More informationRoma McKenzie-Campbell Amtrak, Project Manager. Caroline Ducas VHB, Senior Transit Planner. Boston, Massachusetts
DMU Implementation on Existing Commuter Rail Corridors: Opportunities, Challenges and Lessons Learned Roma McKenzie-Campbell Amtrak, Project Manager Caroline Ducas VHB, Senior Transit Planner Boston, Massachusetts
More informationEUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT
EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT (BRIEF) Table of Contents EUGENE-SPRINGFIELD, OREGON (USA)... 1 COUNTY CONTEXT AND SYSTEM DESCRIPTION... 1 SYSTEM OVERVIEW... 1 PLANNING
More informationBroward County Intermodal Center And People Mover. AASHTO Value Engineering Conference Presentation. September 1, 2009 San Diego, CA
Project Development & Environment Study Broward County Intermodal Center And People Mover AASHTO Value Engineering Conference Presentation September 1, 2009 San Diego, CA Background P D & E Study Regional
More informationTPA Steering Committee for Tri-Rail Extension to Northern Palm Beach County. February 26, 2018
TPA Steering Committee for Tri-Rail Extension to Northern Palm Beach County February 26, 2018 Agenda Review Committee Purpose Review Project Map Discuss Service Alternatives Capital Costs (Stations, Track,
More informationCommuter Rail Vehicle Technology Analysis
Commuter Rail Vehicle Technology Analysis May, 2007 Commuter Rail Vehicle Technology Analysis 1 Purpose: To present the results of the EMU, DMU and DMU double deck (DMU dd) analysis Including: Description
More informationThe Denton County Transportation Authority Thomas M. LeBeau Vice President Rail Development
The Denton County Transportation Authority Thomas M. LeBeau Vice President Rail Development Historical Timeline 2001-2004: Governance and Organization House Bill 3323/Chapter 460 Initial Service Plan Developed
More information4 COSTS AND OPERATIONS
4 COSTS AND OPERATIONS 4.1 INTRODUCTION This chapter summarizes the estimated capital and operations and maintenance (O&M) costs for the Modal and High-Speed Train (HST) Alternatives evaluated in this
More informationBus Rapid Transit: Basic Design for Non-Transit Planners
Bus Rapid Transit: Basic Design for Non-Transit Planners Paul Bignardi, AICP - Principal Planner San Francisco Municipal Transportation Agency Graham Carey, PE Principal careybrt Consulting Peter Gabancho,
More informationTransit Implementation Strategy. Presentation for the Atlanta City Council
Transit Implementation Strategy Presentation for the Atlanta City Council March 7, 2011 This Legislation authorizes the IGA and New Vehicle Purchase There are two parts to this legislation: 1. IGA between
More informationMOTION NO. M Purchase of Thirty-two Double Deck Buses for Increased Passenger Capacity, Bus Replacement and Service Expansion
MOTION NO. M2016-66 Purchase of Thirty-two Double Deck Buses for Increased Passenger Capacity, Bus Replacement and Service Expansion MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations Committee 07/07/16
More informationCity of Pacific Grove
Regional Study Utilizing Caltrans Intersection Evaluation Section 7: City of Pacific Grove s: FIRST STREET AT CENTRAL AVENUE Transportation Agency for Monterey County Prepared by Transportation Agency
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 27, 2012 SUBJECT: NOTICE OF AWARD PROCUREMENT AUTHORIZATION - ARTICULATED BUSES INFORMATION ITEM RECOMMENDATION
More informationRegional Transportation Commission, Washoe County Lee Gibson, Executive Director Roger Hanson, Senior Planner
Regional Transportation Commission, Washoe County Lee Gibson, Executive Director Roger Hanson, Senior Planner Presentation Outline Transit System Facts Economic Challenges in the Truckee Meadows RTC Transit
More informationParking & TOD around BART Stations. Jessica ter Schure November 1, 2009 Rail~Volution 2009 Boston, Massachusetts
Parking & TOD around BART Stations Jessica ter Schure November 1, 2009 Rail~Volution 2009 Boston, Massachusetts Outline Background Replacement Parking Policy South Hayward BART MacArthur BART Parking Privatization
More informationPeninsula Corridor Electrification Project Cost / Schedule Update
Peninsula Corridor Electrification Project Cost / Schedule Update LPMG Meeting November 20, 2014 Context Caltrain/high-speed rail blended system - Primarily 2 track system - Minimize impacts - Shared system
More informationI-405 and SR 522/NE 145th Bus Rapid Transit. Elected Leadership Groups Meeting November 30, 2018
I-405 and SR 522/NE 145th Bus Rapid Transit Elected Leadership Groups Meeting November 30, 2018 Agenda Welcome and Introductions Public Comment BRT Connection in Bothell Common Elements: Bus base, Station
More informationMARTA s blueprint for the future. COFFEE AND CONVERSATION Kyle Keahey, More MARTA Atlanta Dec. 5, 2018
MARTA s blueprint for the future COFFEE AND CONVERSATION Kyle Keahey, More MARTA Atlanta Dec. 5, 2018 TODAY S AGENDA About MARTA Economic development/local impact More MARTA Atlanta program Program summary/timeline
More informationLink LRT: Maintenance Bases, Vehicles and Operations for ST2 Expansion
Project Number SYS-LRT Subareas All Primary Mode Impacted Link Facility Type Link Service Version Number 4.0 Date Last Modified 7/24/2008 Project Locator Map Short Project Description Construct new light
More informationFeasibility Study. Community Meeting March, North-South Commuter Rail Feasibility Study
Feasibility Study Community Meeting March, 2017 1 Agenda 1. Welcome / Introductions 2. Background / Meeting Purpose 3. Progress to Date Options Evaluated Capital/Operating Costs Ridership 4. Financial
More informationTempe Streetcar. March 2, 2016
Tempe Streetcar March 2, 2016 Tempe Profile 40 sq. miles, highest density in state University Town, center of region Imposed growth boundaries (density increase) Mixed use growth/intensifying land use
More informationConnected Vehicle and Autonomous Vehicle (CV/AV) Mobility and Technology
Connected Vehicle and Autonomous Vehicle (CV/AV) Mobility and Technology Randy Iwasaki Executive Director Contra Costa Transportation Authority May13, 2016 WHO WE ARE The Contra Costa Transportation Authority
More informationTransit in Bay Area Blueprint
Rail~Volution 2010 Click to edit Master title style Transit in Bay Area Blueprint October 21, 2010 0 Bottom Line State-of-Good Repair essential for reliable transit service large funding shortfalls BART
More informationKANSAS CITY STREETCAR
KANSAS CITY STREETCAR KAREN CLAWSON MID-AMERICA REGIONAL COUNCIL KANSAS CITY STREETCAR Regional Context Alternatives Analysis Kansas City Streetcar Project KANSAS CITY REGION KANSAS CITY REGION KANSAS
More informationPersonal Rapid Transit as an Alternative to Bus Service in Two Communities
Personal Rapid Transit as an Alternative to Bus Service in Two Communities Peter Muller, PE President, Advanced Transit Association President, PRT Consulting, Inc. Ingmar Andreasson, Ph. D. Vice President,
More informationChapter 9 Recommended Locally Preferred Alternative and Alternatives for Evaluation in Draft SEIS/SEIR
Chapter 9 Recommended Locally Preferred Alternative and Alternatives for Evaluation in Draft SEIS/SEIR 9.0 RECOMMENDED LOCALLY PREFERRED ALTERNATIVE AND ALTERNATIVES FOR EVALUATION IN DRAFT SEIS/SEIR
More informationRedefining Mobility. Randy Iwasaki. Executive Director Contra Costa Transportation Authority January 18, 2018
Redefining Mobility Randy Iwasaki Executive Director Contra Costa Transportation Authority January 18, 2018 Who We Are CCTA is a public agency formed by voters in 1988 to manage the county s transportation
More informationProgram. presented by: September 22, 2010
Minnesota s s High Speed Passenger Rail Program presented by: Minnesota Department of Transportation September 22, 2010 Presentation Overview State Rail Plan National High Speed Rail Initiatives Passenger
More informationBusiness Advisory Committee. July 7, 2015
Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS
More informationU.S. System Summary: ARIZONA/SOUTHWEST
U.S. System Summary: ARIZONA/SOUTHWEST Arizona/Southwest High-Speed Rail System (Source: Texas A&M Transportation Institute) The Arizona/Southwest high-speed rail system described in this summary groups
More informationChapter 7. Transportation Capital Improvement Projects. Chapter 7
Chapter 7 Transportation Capital Improvement Projects Chapter 7 81 Chapter 7 Transportation Capital Improvement Projects Local Transportation Sales Tax Programs For over three decades, Santa Clara County
More informationValley Metro: Past, Present and Future. September 11, 2014
Valley Metro: Past, Present and Future September 11, 2014 Valley Metro Who are We? Two Boards of Directors Regional Public Transportation Authority Fund and operate regional transit services Valley Metro
More informationCITY COUNCIL STUDY SESSION UPDATE ON SMART. January 19, 2017 CITY OF SAN RAFAEL
CITY COUNCIL STUDY SESSION UPDATE ON SMART January 19, 2017 CITY OF SAN RAFAEL SONOMA MARIN AREA RAIL TRANSIT UPDATE OUTLINE BACKGROUND INITIAL OPERATION SYSTEM (IOS1) CIVIC CENTER AREA LARKSPUR EXTENSION
More informationSFMTA Energy Use by Vehicle Type: Transit Investments vs Life Cycle Costs
SFMTA Energy Use by Vehicle Type: Transit Investments vs Life Cycle Costs Peter Brown Project Manager, Long Range Planning Sustainable Streets Division 10 17 2011 Lake Arrowhead, California Outline of
More informationDevelop ground transportation improvements to make the Airport a multi-modal regional
Project Overview TRANSPORTATION IMPROVEMENTS WHAT ARE THE PROJECT GOALS? Transportation transportation hub. Develop ground transportation improvements to make the Airport a multi-modal regional Land Use
More informationSERVICE DESIGN GUIDELINES
VTA TRANSIT SUSTAINABILITY POLICY: APPENDIX A SERVICE DESIGN GUIDELINES Adopted February 2007 COMMUNITYBUS LOCALBUS EXPRESSBUS BUSRAPIDTRANSIT LIGHTRAILTRANSIT STATIONAREAS S A N T A C L A R A Valley Transportation
More information6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION
June 7, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments
More informationUpdate on Transportation Activities in Fairfax County
Update on Transportation Activities in Fairfax County Transportation Roundtable Dulles Area Transportation Association June 13, 2018 Tom Biesiadny, Director Fairfax County Continuing Project Implementation
More information5. OPPORTUNITIES AND NEXT STEPS
5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours
More informationTransit on the New NY Bridge
Transit on the New NY Bridge TZB Cross Section North bridge incorporating 12ft shared use path and space for future bus lane South bridge with space for a future bus lane Gap between the two decks for
More information2030 Multimodal Transportation Study
2030 Multimodal Transportation Study City of Jacksonville Planning and Development Department Prepared by Ghyabi & Associates April 29,2010 Introduction Presentation Components 1. Study Basis 2. Study
More informationCorridor Management Committee. March 7, 2012
Corridor Management Committee March 7, 2012 2 Today s Topics SWLRT Project Office Update Engineering Services Procurement Update Legislative Leadership Tour Annual New Starts Report Update on Proposed
More informationARLINGTON COUNTY, VIRGINIA
ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of April 24, 2004 DATE: April 14, 2004 SUBJECT: Arlington Boulevard (U.S. 50) Bridge Deck Replacement at Washington Boulevard - Overhead Utility
More informationUpdate on Bus Stop Enhancements
Customer Service and Operations Committee Board Information Item III-A February 2, 2012 Update on Bus Stop Enhancements Page 3 of 15 Washington Metropolitan Area Transit Authority Board Action/Information
More informationMetro Transit Update. Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office. John Dillery, Senior Transit Planner
Metro Transit Update Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office John Dillery, Senior Transit Planner Metro Transit Service Development May 16, 2013 1 Transit Planning
More informationAgenda. Utility Undergrounding Strategies & Laguna Canyon Road Master Plan
Utility Undergrounding Strategies & Laguna Canyon Road Master Plan January 17, 2017 City Council Meeting 2 Agenda Progress since March 2016 Status of undergrounding and road widening between El Toro Rd.
More informationTransit Maintenance Equipment. Maintenance Facilities FY
Transit Maintenance Equipment TIP ID: 5861 Fed/St/Loc Title: Maintenance Equipment 2015-2020 Local 0/0/100 4,300 e 42,635 e 58,414 e 41,428 e 35,820 e 15,805 e 198,401 PRIIA 50/0/50 24,290 e 27,144 e 20,409
More informationCity Council Report. Mayor and City Council
City Council Report To: From: Mayor and City Council City Council Meeting: February 23, 2016 Agenda Item: 3.J Edward King, Director, Big Blue Bus, Transit Services Department Subject: Custodial and Maintenance
More informationDevelopment of 220 mph High Speed Rail Service for Illinois. Mark C. Walbrun, PE TranSystems Corporation
Development of 220 mph High Speed Rail Service for Illinois Mark C. Walbrun, PE TranSystems Corporation 1 Study Purpose Worldwide Use of High Speed Rail Technology Japan, France, Italy, Germany, Spain,
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 30, 2010 SUBJECT: PROCUREMENT AUTHORIZATION AMENDMENT - LOW FLOOR LIGHT RAIL VEHICLE OPTIONS: SURFACE VEHICLE SAFETY
More informationTRANSIT IDEA STRATEGIC INITIATIVE On BUS RAPID TRANSIT (BRT)
TRANSIT IDEA STRATEGIC INITIATIVE On BUS RAPID TRANSIT (BRT) The panel for the Transit IDEA program has endorsed a Bus Rapid Transit (BRT) strategic initiative and focus area as part of the Transit IDEA
More informationI-10 West AA/EIS Pre-Screening and Tier 1 Analysis Results. Public Meeting. Wulf Grote, Director Project Development Rick Pilgrim, Project Manager
I-10 West AA/EIS Pre-Screening and Tier 1 Analysis Results Public Meeting Wulf Grote, Director Project Development Rick Pilgrim, Project Manager March 4 & 5, 2008 Today s Agenda Overview of Alternatives
More information5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE
5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE The Rapid Transit Public/Private Partnership Steering Committee recommends the
More informationMichigan/Grand River Avenue Transportation Study TECHNICAL MEMORANDUM #18 PROJECTED CARBON DIOXIDE (CO 2 ) EMISSIONS
TECHNICAL MEMORANDUM #18 PROJECTED CARBON DIOXIDE (CO 2 ) EMISSIONS Michigan / Grand River Avenue TECHNICAL MEMORANDUM #18 From: URS Consultant Team To: CATA Project Staff and Technical Committee Topic:
More informationCOMPRESSED NATURAL GAS (CNG) BUS ENGINES
Metro Los Angeles County Metropolitan Transportation Authority One Gateway Plaza Los Angeles, CA gooi2-zg5z 213.g22.2000 Tel OPERATIONS COMMITTEE JULY 15,2010 SUBJECT: ACTION: COMPRESSED NATURAL GAS (CNG)
More informationSolano County Transit
AGENDA ITEM: 9 BOARD MEETING DATE: FEBRUARY 18, 2016 Solano County Transit TO: PRESENTER: SUBJECT: ACTION: BOARD OF DIRECTORS ALAN PRICE, PROGRAM ANALYST II REVIEW AND APPROVE IMPLEMENTATION OF THE FUELING
More information2019 New Transit Service Plan
Agenda Item 7.2 2019 New Transit Service Plan Draft Proposal VTA Board of Directors January 2019 Background: Next Network Plan and Today s Plan Early 2016 Transit Choices report and the ridership-coverage
More informationEmerging Technologies & Autonomous Vehicle Readiness Planning. Georgia Planning Association Conference Jekyll Island, GA September 5, 2018
Emerging Technologies & Autonomous Vehicle Readiness Planning Georgia Planning Association Conference Jekyll Island, GA September 5, 2018 Agenda 1 U.S. Context 2 U.S. Survey on Emerging Technologies &
More informationCOMMUNITY REPORT FISCAL YEAR We are making progress, are you on board? GOLD COAST TRANSIT DISTRICT
FISCAL YEAR 178 GOLD COAST TRANSIT DISTRICT COMMUNITY REPORT We are making progress, are you on board? OJAI OXNARD PORT HUENEME VENTURA COUNTY OF VENTURA GENERAL MANAGER S MESSAGE STEVEN P. BROWN DEAR
More informationHerding Cats; Strategies used for KC Downtown Streetcar Utility Coordination ASCE Transportation Conference
Herding Cats; Strategies used for KC Downtown Streetcar Utility Coordination ASCE Transportation Conference November 9, 2016 Kansas City Streetcar Project overview Current status Scope of water and sewer
More informationCommuter Rail Vehicle Technology Analysis
Commuter Rail Vehicle Technology Analysis May, 2007 Commuter Rail Vehicle Technology Analysis 1 Purpose: To present the results of the, and double deck ( dd) analysis Including: Description of the Vehicles
More informationChallenges With Underground High Voltage Transmission SCE Tehachapi Renewable Transmission Project First 500 kv Underground T/L in North America
Challenges With Underground High Voltage Transmission SCE Tehachapi Renewable Transmission Project First 500 kv Underground T/L in North America Noe Bargas, PE Supervising Senior Civil Engineer Southern
More information