June 30, Re: British Columbia Transmission Corporation ( BCTC ) Transmission System Capital Plan F2006 to F2015

Size: px
Start display at page:

Download "June 30, Re: British Columbia Transmission Corporation ( BCTC ) Transmission System Capital Plan F2006 to F2015"

Transcription

1 B-9 Marcel Reghelini Director, Regulatory Affairs Phone: Fax: June 30, 2005 Mr. Robert J. Pellatt Commission Secretary British Columbia Utilities Commission Sixth Floor, 900 Howe Street Box 250 Vancouver, BC V6Z 2N3 Dear Mr. Pellatt: Re: British Columbia Transmission Corporation ( BCTC ) Transmission System Capital Plan F2006 to F2015 Further to BCTC s June 24, 2005 filing with the British Columbia Utilities Commission of the responses to the Commission s Information Request No. 2, Sea Breeze Pacific Regional Transmission System, Inc. s Information Request and the Island Residents Against High Voltage Overhead Lines (IRAHVOL) Information Request No. 2, BCTC files its response to BCUC IR Also, BCTC files the missing attachment to the response to BCUC IR (The covering letter to the June 24, 2005 filing incorrectly referred to this attachment as part of the response to BCUC IR ) The attachment is the referenced in BC Hydro s letter of March 22, This completes BCTC s responses to Information Request No. 2. Sincerely, Original signed by: Marcel Reghelini Director, Regulatory Affairs British Columbia Transmission Corporation, Suite 1100 Four Bentall Centre, 1055 Dunsmuir Street, Vancouver, BC V7X 1V5

2 British Columbia Utilities Commission Information Request Dated 3 June 2005 British Columbia Transmission Corporation Response Issued 30 June 2005 British Columbia Transmission Corporation Capital Plan F2006 Page Reference: ICBS, various pages RESPONSE: Several assets classes have ongoing Sustaining Capital programs or related OMA initiatives For each asset class that has one or more ongoing Sustaining Capital programs, please provide a brief update on the status of the programs that includes program descriptions, start and end dates, initial approved costs, expenditures to date, completion percentages, expected times to completion, and expected total costs at completion. Please see two attached tables: Transmission Projects; and Stations Projects. As discussed in BCUC IR , expenditures exceeding the approved amount by 5% are subject to approval by the appropriate level of BCTC management. Approvals for these additional expenditures are generally justified by approved scope changes or may relate to unanticipated circumstances such as difficult construction conditions.

3 Transmission Projects 1 Project Start Finish Initial Approved Costs Expenditures to Date Percent Complete Estimated Cost at Completion Class No Conductor Systems Overhead Life Extension Programs Vancouver Island 500 kv Supply Hazard Protection (VIHAZARD) $ 2,550,000 $ 2,087,019 74% $ 2,668, * OH Line Life extension - F2006 Program $ 8,150,000 $ - 0% $ 8,150, * Transmission Recurring Capital - F2006 Program $ 4,000,000 $ - 0% $ 4,000,000 Very Old Copper Conductor Replacement * OH Line Reliability Improvements - F2006 Program $ 1,350 $ - 0% $ 1,350 TX Rating Restoration kv Transmission Line Rating Restoration (60KVUPG) $ 336,000 $ 278,172 65% $ 385, Upgrade 5L51 & 5L52 to Present Ratings $ 95,000 $ 68,000 44% $ 163,501 A L71/72/75/76/77/79/91 - Line Clearance Upgrades $ 2,149,000 $ 1,116,000 64% $ 1,843,246 A L301 - Rating Study & Upgrade $ 630,000 $ 286,000 45% $ 564, * 5L87 Line Clearance Upgrade $ 480,000 $ 25,000 15% $ 471, Circuit 1L210 Rating Study (BKL - BAR only) $ 46,489 $ 7,400 3% $ 45,000 Class No Metal Support Structures Overhead Line Corrosion Protection Program Overhead T/L Structural Corrosion Protection Program (CORPRTTL) $ 2,315,000 $ 10,282 0% $ 2,315,000 Wind & Ice Withstand Program L98 Ice Mitigation (5L98UICE) $ 286,000 $ 22,627 12% $ 266,683 A99825 Transmission System - Ice Hazard Risk Reduction $ 897,000 $ 908,000 83% $ 1,049,700 A L390 - Skeena River Crossing Ice Damage Prevention (60L390X) $ 722,000 $ 709,078 83% $ 824,600 Class No Wood Pole Structures Overhead Life Extension Program * COB Clamp-Top Insulator Replacements $ 8,323,000 $ 6,549,000 $ 10,000, * COB Suspension Insulator Replacements $ 7,487,000 $ 7,507,000 50% $ 15,000,000 Overhead Reliability Improvements Program L364 - Half Way River Crossing Relocation (1L364Y04) $ 286,000 $ 170,454 52% $ 321,366 Class No Access Roads Rights of way acquisition A L271 - Right-of-Way Acquisition(60L271RW) $ 46,000 $ 5,399 13% $ 46,677 A kv - Deficient Right-of-way Acquisition (ROWTEN02) $ 739,000 $ 434,109 47% $ 798,440 A L274 and 1L275 - Right-of-way Acquisition(KANELKRW) $ 298,000 $ 141,639 26% $ 361,433 A00129 Farrell Estates - Lands Rights Renegotiation (FARRELL1) $ 76,000 $ 43,224 80% $ 58,498 A L205 (VNT-WDS) Right-of-way Acquisition (60L205RW) $ 70,000 $ 60,435 43% $ 97, * Lower Mainland Deficient Rights study & acquisition program $ 2,500,000 $ - 0% $ 2,500, * Misc land Rights Acquisition program F2006 to F $ 1,000,000 $ - 0% $ 1,000,000

4 Transmission Projects 2 Project Start Finish Initial Approved Costs Expenditures to Date Percent Complete Estimated Cost at Completion Class No Civil Works Civil Protective Works L79/2L240 Erosion Protection Structure 7/2 (SHUSWAPR) $ 450,000 $ 47,827 5% $ 473, L9 Erosion Control - Structures 576 and 587 (2L9Y04) $ 399,000 $ 82,944 28% $ 368, L20 Slide Protection - Structures 9-07 and 9-08(60L20Y04) $ 240,000 $ 97,280 95% $ 97, L101 - Riprap Erosion Protection Strs 77/3, 77/4(2L101Y04) $ 1,489,000 $ 1,419,899 93% $ 2,263, L15 Erosion Protection - 15 poles Hayward Lake Reservoir (60L15HLE) $ 136,000 $ 16,874 0% $ 156, L63 Str Anchor C Stabilization (5L63Y05) $ 403,500 $ 29,546 0% $ 458, Deflector Berms - Circuits 5L42 & 5L45 (5L42EW05) $ 122,000 $ 2,457 0% $ 139, L45 Noon's Creek Crossing Erosion Protection - Str (5L45NCXE) $ 143,500 $ 963 0% $ 164, Replumb 5L79 guyed Strs and (5L79SS05) $ 41,000 $ 1,144 0% $ 46, L101 (SKA-RUP) Riprap Erosion Protection (2L101M83) $ 298,500 $ 7,104 0% $ 338, L1 Bent Steel Members Strs ,10-04 and (2L1BS05) $ 140,000 $ 1,905 0% $ 161, Rutherford Creek Erosion Control - 5L42, 2L1, 2L2 (RUTHERCK) $ 527,139 $ 574, % $ 636,974 A L10 (WAH-BBR) - Riprap Erosion Protection, Peter's Island(60L10Y02) $ 1,205,595 $ 1,153,257 88% $ 1,330,186 Class No Underground and submarine cables and oil systems Replacement of defective cables L55/2L56 (Ingledow to Camosun) - Cable Upgrading $ 7,100,000 $ 5,267,000 45% $ 8,856, Cable life Extention prog & Sheath Bonding Switch(CABDEF) $ 50,000 $ 5,132 10% $ 49,963 A L29/31 Thermal Assessment and Optimization $ 2,418,000 $ 1,974,000 91% $ 2,176,250 A Metro Vancouver kv Reinforcement Development(MV230DEF) $ 789,000 $ 785,952 83% $ 916,456 A HVDC Pole 2 - Cable #9 Replacement(P2C9REPL) $ 3,513,000 $ 2,212,098 76% $ 3,037,744 A L50 (Burrard to Murrin) - Cable Upgrading $ 806,000 $ 674,000 77% $ 852,287 A L39/40 - Cable Replacement $ 31,613,000 $ 28,691,000 92% $ 31,028,791 Replacement of problem stop joints A Oil Stop Joint Replacement Program $ 2,345,000 $ 2,229,000 95% $ 2,345,971 A L53 - Stop Joint Replacement (2L53SJ) $ 1,916,462 $ 1,913, % $ 1,996,270 Upgrade of oil alarm and control systems to improve circuit restoration time Metro Supply kv Oil Alarm System Upgrade $ 1,798,000 $ 428,000 16% $ 1,804,766 A L53 (MAN-MUR) - Cable Oil Pressure Alarm Upgrade(2L53ALUP) $ 190,000 $ 185, % $ 201,654 Upgrade of pumping plants and oil reservoir systems A kv Oil fill cable Circuits-Oil Reservoir Capacity Upgrade-Defini $ 686,000 $ 220,000 14% $ 682, L50 Oil Pump Alarm System Upgrade (2L50PUMP) $ 311,000 $ 173,244 50% $ 325,633 A GVWD Capilano Pumping PLant 69 kv Connection Project (GVWDY05) $ 1,375,000 $ 1,380,982 94% $ 1,477, kV SCOF Cables Reservoir Capacitor Upgrade - Station $ 188,000 $ - 0% $ 188,000 Installation of protection barriers for 500 kv potheads vulnerable to vandalism A kv Cable Pothead Barrier Additions (CIP02CPB) $ 298,000 $ 304,350 24% $ 450,912

5 Stations Projects 1 Project Start Finish Initial Approved Costs Expenditures to Date Percent Complete Estimated Cost at Completion Class No Circuit Breakers 230 KV Walters 230kV CB Replacement (WLT05CB) $ 399,586 $ 6,410 0% $ 399, kv Circuit Breaker Replacement (230CBR05 & NEL05CB) $ 1,975,000 $ 135,708 6% $ 1,964, KV Williston 5CB2 Replacement (CB04WSN5) $ 758,000 $ 615, % $ 615, Malaspina 5CB3 Replacement (MSA5CB3) $ 994,000 $ 515,251 38% $ 2,071, Circuit Breaker Replacements /05 (CB04KI22, CB04MLN2, CB04WHY2) $ 2,717,000 $ 1,969, % $ 1,968, Circuit Breaker Replacements / $ 9,543,000 $ 2,715,000 45% $ 8,586, Williston - Circuit Breaker (PK8) Replacement Program $ 4,319,000 $ 47,000 33% $ 2,886, Williston 5CB5 Replacement (WSN5CB5) $ 750,000 $ 597, % $ 760,457 Class No Disconnect Switches GMS - Disconnect Switch Replacement (GMS04DS & GMS05DS) $ 465,000 $ 334,000 78% $ 408,719 Class No Circuit Switchers A /230 kv Circuit Switcher Replacement Program (CB03NIC,CB04KLY,CB04WSN) $ 4,839,000 $ 4,525, % $ 4,525, Circuit Switcher Replacements - Williston and Dunsmuir (CB04DMRS,CB04WSNS) $ 2,789,000 $ 2,353,000 90% $ 2,385,925 Class No Transformers/Tap Changers Station Animal Outage Reduction - F2006 (PG05SAO) $ 365,000 $ 82,153 37% $ 229, Station Animal Outage Reduction (PG03SAO) $ 1,895,000 $ 2,175, % $ 2,175,000 Class No Shunt Capacitors PCB Filled Capacitor Can Replacements /05 (PCB04REP) $ 1,715,000 $ 340,670 33% $ 1,993,883 Class No Station Insulators A Pin & Cap Type Insulator Replacements (PG03PIN & PG04PIN) $ 3,472,000 $ 3,411,000 98% $ 3,720, Pin & Cap Type Insulator Replacements (PG05PIN) $ 1,440,000 $ 51,073 10% $ 1,598,069 Class No High Pressure Air Systems Air Compressor Replacements /06 (ACREP05) $ 489,000 $ 35,657 4% $ 474,297 Class No Protection and Control Systems Line Protection Systems Replacements - over 500 kv kv Line Protection Replacement - Stage 4 (500PNS4) $ 3,826,000 $ 379,766 22% $ 3,298,597 Line Protection Systems Replacements - under 500 kv U-500 kv Line PN Replacements Stage 6 & Transformer PN Replacement (U5PNS6) $ 5,727,000 $ 1,026,643 28% $ 5,111,520 A72041 Line Protection Replacements - Under 500 kv, Stage $ 5,232,000 $ 4,742,000 88% $ 5,288,960 Station Equipment P&C Systems Replacements Transformer PN Replacements (Gas Relay) - F2006 (TXPROT06) $ 25,000 $ 17,550 5% $ 23, Transformer Protection Replacements /05 (TXPROTO3) $ 1,876,000 $ 1,374,786 76% $ 1,657, Port Kell - Auto Reclose (PKL05AR) $ 114,000 $ 76,386 92% $ 84,079 Circuit Breaker Failure Protective Relay Replacements

6 Stations Projects 2 Project Start Finish Initial Approved Costs Expenditures to Date Percent Complete Estimated Cost at Completion A72073 Circuit Breaker Failure Protection Replacement - Stage 2 (CBFPN04) $ 645,000 $ 285,188 56% $ 519,068 Station SCADA RTU Equipment Replacements Britt Creek - Control Upgrade (BCKCTRUP) $ 105,000 $ 75,000 64% $ 105,000 A00239 SCC - Telemetry Additions for Security Applications (SCC01TM) $ 200,000 $ 157,166 93% $ 152, Long Beach RTU Addition (LBH05RTU) $ 69,932 $ 61, % $ 63,096 A02107 Valemount and Avola - Remote Control of Feeders (VLMCBCR) $ 11,000 $ 16,278 93% $ 16,962 Minor and Emergency Capital P&C Program P&C Additions/Replacements (MInor Capital) /05 (PG04MCP) $ 318,000 $ 114,949 n/a $ 158, Surge Arrestors Surge Arrester Additions/Replacements Program (SA206DEF) $ 2,421,000 $ 258,708 6% $ 2,421, Batteries Station Battery Bank Replacements /06 (PG05BATS) $ 500,000 $ 9,579 10% $ 633, Facilities - General Roof Replacements Roof Replacements /05 (PG04ROOF) $ 436,000 $ 487,000 92% $ 701, Roof Replacements /04 (PG03ROOF) $ 263,000 $ 254, % $ 254,674 Seismic Upgrades Murrin Curtain Wall Seismic Reinforcement (MUR06SEI) $ 125,000 $ 43,656 35% $ 102, Kidd 1 Sheet Pile Wall (KI106SHT) $ 310,000 $ 187,000 17% $ 343,684 Auxiliary Equipment Upgrades As-builts for closed projects $ 700,000 $ 684,000 91% $ 732,642 A00172 Ingledow - Station Service Upgrade (ING02SS) $ 874,000 $ 732,788 74% $ 1,519,939 Spill Containment Improvements Oil Spill Containment - Group $ 2,307,000 $ 186,000 8% $ 2,326, Oil Spill Containment - Group 10 Sites $ 145,000 $ 10,000 2% $ 146,476 Gravel Refresh Substation Gravel Replacement 2004/05 to 2007/ $ 1,250,000 $ 732,000 49% $ 1,371, Fire Protection Systems A72065 Fire Risk CO2 and Halon Replacement (FRCO204) $ 87,000 $ 75,245 96% $ 75, Fire Risk Reduction /2004 Site Assessments (FRRP03) $ 182,000 $ 151,792 91% $ 153, Cathedral Square - CO2 System Replacement (CSQ04REM,CSQ05REM) $ 428,000 $ 289,000 76% $ 370, Microwave Equipment A01180 Microwave System Replacement - Peace/Skeena Northern Region (MWPESC) $ 21,778,000 $ 18,576,199 90% $ 21,907, Power Line Carrier Equipment Power Line Carrier Replacements /06 (PLCREPS3) $ 4,078,000 $ 105,429 44% $ 4,111,394

7 Stations Projects 3 Project Start Finish Initial Approved Costs Expenditures to Date Percent Complete Estimated Cost at Completion HVDC Pole HVDC - Pole I Mercury Cross Contamination and HVAC Upgrade $ 3,482,000 $ 422,000 14% $ 3,755,923

8 1 Circuit Breakers Materiality: HI should be accurate within TRANSMISSION ASSETS 1.Circuit breaker design type (e.g. oil, air blast, SF6). Should penalize obsolete technologies (e.g oil CBs) 2. Doble Test bushing capacitance loss angle (to detect moisture ingress). 3. Dissolved gas analysis of oil-filled bushing oil. 4. Number of operations 5. Age 1. Bushing tests are particularly important because of the risk of explosive failure. 2. The significance of fatal end-of-life criteria is diminished by non-critical criteria in the Health Index (HI) formulation (based on typical weightings). 3. Composite results, that include all different breaker designs, can be misleading Disconnect Switches 3 Circuit Switchers 1. Too few older (>40 years) disconnects. 1. The key condition indicator reported is a thermographic test. That is important but not diagnostic, it will only tell about the ability to carry current if it is carrying current at the instant of the test. Missing is data on a simple operation of the disconect to prove the disconnect is not seized. 1. Should penalize obsolete models no longer supported. 2. Number of operations 3. Age 1. Loss of SF6 gas which accounts for most circuit switcher failures. 1. Results do not agree with actual field problems and failures of disconnect switches. Report states all disconnects are "good or very good". The assessment should factor in past failures and known problems with certain types of disconnects. 1. An HI of 98.3 "good or very good" rating is not consistent with numerous past failures. 2. The reported distribution with almost all good or very good and two very poor but with none fair or poor is inconsistent with known continuous statistical distributions Transformers 1. Largest transformers are not identified. The system has 3 phase autotransformers up to 500MVA and a number of 1200MVA banks made up of 400MVA single phase units. 1

9 5 Instrument Transformers 1. Dry type lower voltage VTs missing (e.g 67kV). 2. Dry type 230kV and 500kV CTs don't exist. Materiality: HI should be accurate within 1. Doble Test bushing capacitance loss angle. 2. Partial discharge for dry type equipment (may lead to explosive failure). 1. Transformation Ratio. 2. Propensity of oil filled CTs to explode violently is omitted in evalution. 1. and repeatability of the results are in doubt since about half of the population was assessed using the 50% Rule 2. of CVT health index data is at odds with recorded failure rates (at least 10 failures within the last 8 years) Shunt Reactors 1. Dry type reactors incorrectly characterized. 2. Age information incorrect (e.g. Peace River 500kV system shunt reactors.) 3. Nonexistent voltage class identified (138kV shunt reactors). 7 Shunt Capacitors 1. Too many 138 kv banks and not enough 230 kv banks. 1. Condition assessment inappropriate in Table 7.3.3, rating D&E are failed units, not poor condition 8 Station Insulators 9 Station Cables 1. Demographic data is not included for this asset class. 1. No 360 kv or 500 kv station cables. 2. New 69 kv cables at McLellan Substation are not shown. 8 cables unidentified as to voltage or station, therefore 55% of population either unidentified or non-existent % of the cables have incomplete age information. 1.The assessment considers primarily aging cap & pin insulators which are not the current standard. Whether all types were considered for the HI, and whether the HI includes composites, is not clear. 1. Age. 1. Report should discuss the fact that 23% of cables are years old and nearing their life expectency Low because of large errors in demographics 10 Synchronous Condensers 1) Readily available demographic information (age) not identified for 40% of units. 2. The condition rating critera are very subjective, mostly based on observation. A different auditor may choose a different rating. 2

10 11 Gas Insulated Switchgear 12 Static VAR 1. Fort St. James STATCOM is missing Compensator (or should appear in SDA section). s Materiality: HI should be accurate within 1. Large portions of the SVC equipment (capacitors, reactors and transformers) were not included in the health assessment. 2. SVC controls. 3. Availability of spares for key power components and controls may be an issue and is missing from the condition criteria. 1. Report's ranking of HSY does not agree with comments by Acres' expert. 2. Results mainly based on expert opinion rather than condition data. No end-of-life measurements. 70 No comment. 13 High Pressure Air Systems 1. Missing high pressure air system for Murrin distribution (SDA issue as the air system only supplies the 12 kv distribution breakers) than the receiver, ratings (e.g air dryer and compressor) are very subjective. 14 Protective Relays 1. Control cables that connect relays to 1. Dust switchyard equipment (breakers and other accumulation is controlled devices). usually benign. 1. Relay condition data and the HI calculation methodology were not used. Instead, the HI is based on the technology used to implement the relaying system (electro-mechanical, static or numerical). The correlation between technology of implementation and the actual health of the P&C system is questionable. 2. The unexplained differences of the HI calculation rules between transmission relaying systems and distribution relaying systems casts doubt on the accuracy of both these HIs. Based on design type 1. The relay technology was used as the basis to determine HI and since it is not subject to any aging or deterioration mechanisms, the HI should be repeatable but for the wrong reason. 15 Surge Arrestors 1. Failure of hermetic seal. 2. Age. 1. A divider was used in HI calculation which results in significantly different HI from that calculated for identical distribution arresters. 2. Exceptionally low rating of gapped type surge arresters is inconsistent with failure to similarly rank explosion prone oil filled CTs. 70 3

11 16 Grounding Systems Materiality: HI should be accurate within 1. No information on the stations that 1. Measurements that confirm 1. Crushed rock. If the comprised the population or discussion of performance (e.g. fall of potential crushed rock is particular stations. measurement). inadequate (depth or 2.The demographics show 35% are Age. quality) safety hazards plus years. may exist in the substation. 1. End of Life criteria to account for system changes should be considered. For example, system changes over the life of a substation may result in fault levels above the design value. 17 Batteries 1. Charging system should have been considered separately from batteries The condition rating critera are very subjective, mostly based on observation. A different auditor may choose a different rating. 18 Standby Generators 19 Facilities General 20 Fire Protection Systems 1. The numbers of facilities appear to vary 1. Seismic vulnerability. with information filed by BCTC with Grid West. See: tieslist_bchydro_july xls.xls This shows a total of 257 stations in July The types of fire extinguishing equipment and fire protection systems noted in the tables are vague and do not cover the numbers and types of systems in place. 1. Corrosion, damage, deterioration or any abnormality are good measures of system health. 2. The repeatability is low because the scoring is very high level, does not identify critical elements and all of the fire protection inventory. The condition ratings are very subjective and therefore, subject to interpretation. 21 Microwave Equipment 22 Power Line Carrier Equipment 1. Coupling capacitors 2. Wave traps 70 4

12 23 Series Capacitors 1. Count of capacitor platforms is incorrect. Materiality: HI should be accurate within 1. 5% to 20% failed capacitors is unreasonable (Table ). Use 0.5% to 2%. 1. Bypass circuit breaker and other switching devices. 1. P&C system Low because of large errors in demographics suggesting lack of appropriate evaluation 24 HVDC Pole 1 1. Considering that approximately 90% of the condition assessment tests for Pole I are simple visual inspections, and that one of the two converter terminals is in the Lower Mainland, sufficient data should be available to meet the Rule. 2. Some of the data and associated health assessment tests are incorrect (e.g. checking fuses in the case of internally fused capacitors and no MG checks for the first grade power supply). All of this suggests the HI is not accurate. 3. HI is lower than expected. 25 HVDC Pole 2 1. Considering that approximately 90% of the condition assessment tests for Pole I are simple visual inspections, and that one of the two converter terminals is in the Lower Mainland, sufficient data should be available to meet the Rule. 2. Some of the data and associated health assessment tests are incorrect (age of one converter transformer incorrect, no PCB capacitors at Arnott, valve electronics failure rate cutoffs seem out by a factor of 10). All of this suggests the HI is not accurate HI is lower than expected. 5

13 26 Conductor Systems 27 Metal Support Structures 28 Wood Pole Structures 1) Composite HI must consider total conductor lengths. The composite HI results for the 500 kv conductor systems (or any voltage class with more than one conductor per span) appears to be skewed. For 500 kv, the conductor span is about 1500 feet with a 4-conductor bundle and for 60 kv the conductor span is about 300 feet with a single conductor. The individual results for 60 kv, 138kV, etc. should be okay but the combined results for the system will be lower due to skewing by the number of the 60 kv spans compared with the 500 kv spans rather than the amount of actual conductor. Materiality: HI should be accurate within 1) It appears that the HI ratings have come more from the age of the lines rather than actual structure condition information in STARR (Page bottom). This is probably why the 138 kv towers are rated lower as most of these are on Vancouver Island, which has an older metal line. This is probably okay but only gives a rough approximation and perhaps this should be stated in the Report. 1) No data was available for assessment largely due to inadequate information regarding the age and condition of the poles The condition assessment is largely based on age rather than actual condition, so the boundaries for the various categories would have to be defined in order to make the results repeatable. Conductors that were 38 years old would be 41 years old in next survey and that might put them in a different category. Should be repeatable but for the wrong reason. 1. The condition assessment is largely based on age rather than actual condition, so the boundaries for the various categories would have to be defined in order to make the results repeatable. Metal Towers that were 38 years old would be 41 years old in next survey and this might put them in a different category. Should be repeatable but for the wrong reason. 29 Vegetation/Ri ghts of Way 1. No data was available for assessment and assessments were made from discussions with Field staff. Assessment was quite subjective so will be difficult to repeat. 30 Access Roads 1) No data was available for assessment. This is largely a subject where input needs to come from Field Services. 70 Not rated. 6

14 Materiality: HI should be accurate within 31 Civil Works 1) No data was available for assessment. Soil erosion is shown as an asset, which seems odd. - Not rated. 32 Underground & Submarine Cables 1. No SCFF cable systems were listed in 'very good' condition, even though > $75M has been spent recently on 2L39, 2L40 and 2L Similarly, no XLPE cable systems were listed as 'very good', even though 60L50 was recently commissioned. We suggest updating the database to reflect true condition. 1. Tables 'Gas-in- Oil Analysis' and 'Sheath Bonding, CP tests, etc.' are benign and should not be used as end-oflife critera 2) Table shows 1 SCGF cable system as 'fair', and three as 'good', however all of the submarine cable circuits (including both of 1L17/18) were installed in 1956/58 and should be in the same condition. Since the circuits have been capacity derated due to advanced armour corrosion, we suggest they both be described as 'poor'. 2. BCH's submarine cable system is a ~$1B asset, yet methods are not provided to accurately gauge its health, uniquely defined by installation conditions different than land cables. 33 Manholes & 1. Only one manhole was classified as Duct Systems being in 'very good' condition (ref. Figs ), even though 11 new manholes were installed for new circuit 2L33 in Circuit Breakers 1. Seismic vulnerability. It is an important 1. Tables indicator of underground transmission through circuit health, which can be compared to are benign and performance expectations. Several Metro should not be Vancouver circuits are quite weak used a end-oflife critera. seismically; in some sections susceptible to liquefaction soil instability. Repairs are easy and overall asset health is not threatened. SDA ASSETS Suggestion: Separate End-of-life Criteria and Condition Rating tables should be created for ducts and manholes. It is expected that the results would considerably modify the HI Results in Table and Figure On the 2L39-40 (NEL-HIL) circuits which were redone a couple of years ago, about 75% of the ducts were redone due to the poor condition of the existing ducts. The reason that no defects were noted for the ducts is they largely have not been inspected whereas the manholes have been. 70 No comment.? See transmission comments. 2 Disconnect Switches 1. Only two 138 kv disconnects noted; there should be none or many more depending on the exact SDA boundary definition (probably none).? 7

15 3 Circuit Switchers 1. Only one 138 kv switcher is listed; there should be none or many more depending on the exact SDA boundary definition (ALL circuit switchers are probably for switching reactive equipment and not SDA). Materiality: HI should be accurate within? 1. Low due to errors in demographics; data for critical condition measures believed unavailable to auditors, data on operability believed unavailable or unknown. 4 Transformers 1. A number of large transformers that are larger than any supplying the distribution system were included. Also a 360 kv transformer is identified but there is no such transformer.? 1. Low due to large errors in demographics. 5 Instrument Transformers 1. Dry type VTs? 1. Low due to errors in demographics. 6 Shunt Capacitors capacitors in 0-9 year age bracket reported; the correct number is more like 13.? 1. Low due to large errors in demographics. 7 Insulators No data 8 Substation Cables and Terminations 1. The number of failures in recent years suggests an aging condition criterion that is missing 1. The only direct measure of actual cable condition is a thermographic scan that is not diagnostic, especially for underground cables.? 1. Low since the condition of the cables was not actually determined. 8

16 9 Protection and Control Systems Materiality: HI should be accurate within 1. Relay condition data and the HI calculation methodology were not used. Instead, the HI is based on the technology used to implement the relaying system (electro-mechanical, static or numerical). The correlation between technology of implementation and the actual health of the P&C system is questionable. 2. The unexplained differences of the HI calculation rules between transmission relaying systems and distribution relaying systems casts doubt on the accuracy of both these HIs. Based on design type 1. The relay technology was used as the basis to determine HI and since it is not subject to any aging or deterioration mechanisms, the HI should be repeatable but for the wrong reason. 10 Surge Arrestors? 1. Unsubstantiated difference of HI in comparison with identical distribution arresters. 11 Mobile Transformers and Unit Substations 12 Voltage Regulators 1. Four units were assessed; there are six. 1. Tap changers. These units get a lot of use and are a major cause of deterioration Low due to the failure to evaluate the tap changers and account for significant average age. 13 Series Reactors 1. There is a large population of CLRs serving the distribution feeders. It was overlooked entirely. - No results. 14 Static Var Fort St. James unit - No results. Compensator s 9

British Columbia Transmission Corporatlon ("BCTC") Transmission System Capital Plan F2006 to F2015 Amllcation

British Columbia Transmission Corporatlon (BCTC) Transmission System Capital Plan F2006 to F2015 Amllcation B-2 Marcel Reghelini Director, Regulatory Affairs Phone: 604 699-7331 Fax: 604 699-7537 E-mail: marcei.reghelini@bctc.com May 5,2005 Mr. Robert J. Pellatt Commission Secretary British Columbia Utilities

More information

BC Hydro System 2017 Annual Progress Report

BC Hydro System 2017 Annual Progress Report March 14, 2017 Philip Augustin, P.E. Chair, Technical Studies Subcommittee 503-464-7783 philip.augustin@pgn.com Mr. Enoch Davies WECC Technical Staff 155 North 400 West, Suite 200 Salt Lake City, UT 84103-1114

More information

V. Design, Application, Maintenance & Operation Technical Requirements

V. Design, Application, Maintenance & Operation Technical Requirements V. Design, Application, Maintenance & Operation Technical Requirements V.L Line & Substation Operation and Maintenance 1.0 General Requirements 1.1 Each facility owner shall have an established and documented

More information

BC Hydro System 2016 Annual Progress Report

BC Hydro System 2016 Annual Progress Report March 11, 2016 Philip Augustin, P.E. Chair, Technical Studies Subcommittee 503-464-7783 philip.augustin@pgn.com Mr. Enoch Davies WECC Technical Staff 155 North 400 West, Suite 200 Salt Lake City, UT 84103-1114

More information

BC HYDRO SUPPLY CHAIN APPLICATIONS PROJECT EXHIBIT A-8

BC HYDRO SUPPLY CHAIN APPLICATIONS PROJECT EXHIBIT A-8 Patrick Wruck Commission Secretary Commission.Secretary@bcuc.com Website: www.bcuc.com Sixth Floor, 900 Howe Street Vancouver, BC Canada V6Z 2N3 TEL: (604) 660-4700 BC Toll Free: 1-800-663-1385 FAX: (604)

More information

BC Hydro System 2011 Annual Progress Report

BC Hydro System 2011 Annual Progress Report March 1, 2011 Mr. Kyle R. Kohne, Chairman WECC Technical Studies Subcommittee Bonneville Power Administration P.O. Box 491 MS, TPP-OPP-3 Vancouver, WA 98666 Mr. Kent Bolton WECC Technical Staff 155 North

More information

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map EH2741 Communication and Control in Electric Power Systems Lecture 3 Lars Nordström larsn@ics.kth.se 1 Course map 2 1 Outline 1. Repeating Power System Control 2. Power System Topologies Transmission Grids

More information

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic Sub Regional RTEP Committee Mid-Atlantic July 26, 2016 Reliability Analysis Update MetEd Transmission Zone N-1 First Energy Planning Criteria (FERC Form 715): The North Boyertown West Boyertown 69 kv is

More information

ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES Revision 0

ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES Revision 0 ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES 2018-04-24 - Revision 0 EUB Decision 2007-071 Board Direction 52 For questions or comments regarding

More information

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. System Planning

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. System Planning A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Electrical vo1e.5s 0j 44, AMY., CK NI r. SIGNATURE Mechanical Civil Protection & Control t^ /DATE 1 o Transmission & Distribution AND Telecontrol

More information

A 500kV AIS Switchyard Rejuvenation in British Columbia using Hybrids

A 500kV AIS Switchyard Rejuvenation in British Columbia using Hybrids A 500kV AIS Switchyard Rejuvenation in British Columbia using Hybrids Author Company Email Presenter T.A. Messinger BC Hydro toly.messinger@bchydro.com E. Burt BC Hydro ed.burt@bchydro.com P.Glaubitz Siemens

More information

Title Electrical Technical Maintenance Coding System. Reference Number PMP 01 (RIC Standard: EP SP)

Title Electrical Technical Maintenance Coding System. Reference Number PMP 01 (RIC Standard: EP SP) Discipline Engineering Standard NSW Category General Title Reference Number PMP 01 (RIC Standard: EP 00 00 00 02 SP) Document Control Status Date Prepared Reviewed Endorsed Approved Mar 05 Standards and

More information

SYLLABUS FOR ELECTRICAL SUPERVISOR CERTIFICATE OF COMPETENCY (SCC MV) Electrical Engineering Paper (Written Test)

SYLLABUS FOR ELECTRICAL SUPERVISOR CERTIFICATE OF COMPETENCY (SCC MV) Electrical Engineering Paper (Written Test) ANNEXURE I SYLLABUS FOR ELECTRICAL SUPERVISOR CERTIFICATE OF COMPETENCY (SCC MV) Electrical Engineering Paper (Written Test) Paper I & Paper II for General Category of S.C.C. Examination Paper I & Paper

More information

Surabaya Seminar Ferdinand Sibarani, Surabaya, 30 th October Power Quality

Surabaya Seminar Ferdinand Sibarani, Surabaya, 30 th October Power Quality Surabaya Seminar 2014 Ferdinand Sibarani, Surabaya, 30 th October 2014 Power Quality Content 1. Power quality problems 2. ABB s low voltage (LV) solution PCS100 AVC (Active Voltage Conditioner) PCS100

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2018 RELIABILITY SCORECARD

OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2018 RELIABILITY SCORECARD OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2018 RELIABILITY SCORECARD June 1, 2018 Table of Contents 1.0 Introduction...3 2.0 Summary...3 3.0 Purpose...3 4.0 Definitions...4 5.0 Analysis...5

More information

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Electrical.1_ UFSS#p A:_. DAVID/ IC, L re Mechanical Civil Protection & Control an LAND& 4^ Transmission & Distribution Telecontrol System Planning

More information

ADVISE DESIGN IMPLEMENT FOR ELECTROTECHNICAL EXCELLENCE

ADVISE DESIGN IMPLEMENT FOR ELECTROTECHNICAL EXCELLENCE ADVISE DESIGN FOR ELECTROTECHNICAL EXCELLENCE IMPLEMENT ADVISE DESIGN FOR ELECTROTECHNICAL EXCELLENCE Gemitech was founded in 1990 and, in just a few short years, grew to be recognized as medium and IMPLEMENT

More information

OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2017 RELIABILITY SCORECARD

OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2017 RELIABILITY SCORECARD OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2017 RELIABILITY SCORECARD May 1, 2017 Table of Contents 1.0 Introduction...3 2.0 Summary...3 3.0 Purpose...3 4.0 Definitions...4 5.0 Analysis...5

More information

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat Galapagos San Cristobal Wind Project VOLT/VAR Optimization Report Prepared by the General Secretariat May 2015 Foreword The GSEP 2.4 MW Wind Park and its Hybrid control system was commissioned in October

More information

SUBSTATION DESIGN TRAINING

SUBSTATION DESIGN TRAINING 2017 SUBSTATION DESIGN TRAINING ADVANCE ELECTRICAL DESIGN & ENGINEERING INSITUTE (Registered under MSME& An ISO 9001:2008 CERTIFIED) Training Centre: Advance Group of Institutions C-1, Second Floor Near

More information

Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR)

Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR) Report-BCTC-R009A Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR) December 8, 2005 Prepared by Wenyuan Li

More information

Hydro Plant Risk Assessment Guide

Hydro Plant Risk Assessment Guide September 2006 Hydro Plant Risk Assessment Guide Appendix E2: Circuit Breaker Condition Assessment E2.1 GENERAL Circuit breakers are key components in the power train at hydroelectric powerplants and are

More information

TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID.

TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID. A GUIDE TO TRANSPOWER 2009 TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID. Contents 01 Introduction 02 System Operator 24/7

More information

XXXXX. Kokish River Hydroelectric Project. Interconnection Facilities Study and Project Plan

XXXXX. Kokish River Hydroelectric Project. Interconnection Facilities Study and Project Plan XXXXX Kokish River Hydroelectric Project Interconnection Facilities Study and Project Plan March 16, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2010. All

More information

S C ELECTRIC EUROPE LTD. Excellence Through Innovation. Harnessing the Wind. November 2011 Descriptive Bulletin E

S C ELECTRIC EUROPE LTD. Excellence Through Innovation. Harnessing the Wind. November 2011 Descriptive Bulletin E S C ELECTRIC EUROPE LTD. Excellence Through Innovation Harnessing the Wind November 2011 Descriptive Bulletin 2000-42E Introduction Founded in 1911, S&C Electric Company is a global provider of equipment

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

Facilities Study for Alberta to US Available Transfer Capability

Facilities Study for Alberta to US Available Transfer Capability Facilities Study for Alberta to US Available Transfer Capability Report No: NPP2002-05 June 3, 2002 System Planning & Grid Operations, Transmission Line of Business Engineering Services Executive Summary

More information

ABB Wind Power Solution

ABB Wind Power Solution Feng Li, Wind ISI, CNABB, November, 2016 ABB Wind Power Solution November 13, 2016 Slide 1 ABB deliveries from A to Z into the wind industry Wind power generation, transmission and integration, control

More information

PUB NLH 174 Island Interconnected System Supply Issues and Power Outages Page 1 of 4

PUB NLH 174 Island Interconnected System Supply Issues and Power Outages Page 1 of 4 PUB NLH 174 Island Interconnected System Supply Issues and Power Outages Page 1 of 4 1 2 3 4 5 6 7 8 9 Q. Please describe Hydro s terminal station and substation inspections policies and practices. In

More information

SECTION 9: ELECTRICAL POWER DISTRIBUTION. ESE 470 Energy Distribution Systems

SECTION 9: ELECTRICAL POWER DISTRIBUTION. ESE 470 Energy Distribution Systems SECTION 9: ELECTRICAL POWER DISTRIBUTION ESE 470 Energy Distribution Systems 2 Introduction The Electrical Grid 3 Three main components to the electrical grid Generation ESE 450 Transmission Transmission

More information

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202 Transmission and Distribution Substation Projects Operating Company: Entergy Gulf States - Texas Customer: PID # 202 Funding Project Number: F4PPGS0386 Facility Study for PID # 202: Study for 146 MW Revision

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner

More information

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PJM Sub Regional RTEP Committee Mid-Atlantic January 22, 2016 Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PSE&G System Characteristics New Jersey utility characterized by densely populated

More information

Schedules 1 to 4, Lot B: Extension of the Lessos Substation

Schedules 1 to 4, Lot B: Extension of the Lessos Substation 1.0 LIGHTNING ARRESTORS 1.1 ZNO lightning arrester, 192 kv rated voltage, 10 ka nominal discharge current 2.0 CAPACITIVE VOLTAGE TRANSFORMER ea. 45 2.1 220 kv capacitive voltage transformer 220/ 3 / 0.11/

More information

Small wonder. Station service voltage transformers for small power requirements

Small wonder. Station service voltage transformers for small power requirements Small wonder Station service voltage transformers for small power requirements MATHEW PAUL An estimated 1.3 billion people worldwide have no access to electricity. In small communities, this is often due

More information

Figures obtained from schedules by line of business - see highlighted numbers on each schedule

Figures obtained from schedules by line of business - see highlighted numbers on each schedule Summary of Forecast Dismantling Costs by LOB Dismantling Projections ($ million) F2004 F2005 F2006 Distribution $9 $10 $12 Generation 3 3 3 Transmission 5 5 5 $17 $18 $19 Figures obtained from schedules

More information

ELECTRIC SYSTEM RELIABILITY ANNUAL REPORT

ELECTRIC SYSTEM RELIABILITY ANNUAL REPORT ELECTRIC SYSTEM RELIABILITY ANNUAL REPORT 2016 LIBERTY UTILITIES (CALPECO ELECTRIC) LLC (U 933 E) Prepared for California Public Utilities Commission July 15, 2017 EXECUTIVE SUMMARY The Electric System

More information

The Narragansett Electric Company. d/b/a National Grid (Interstate Reliability Project) RIPUC Dkt. No Testimony of. David M. Campilii, P.E.

The Narragansett Electric Company. d/b/a National Grid (Interstate Reliability Project) RIPUC Dkt. No Testimony of. David M. Campilii, P.E. (Interstate Reliability Project) RIPUC Dkt. No. 0 Testimony of David M. Campilii, P.E. November, 0 -v RIPUC Dkt. No. 0 PREFILED TESTIMONY OF DAVID M. CAMPILII 0 0 INTRODUCTION Q. Please state your name

More information

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) February 2013 Contents I. Introduction 1 II. Status of Electricity Supply and Demand 2 1. Electricity Demand 2 2. Electricity

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

The cost estimation methodology used to update the charges and credits is the same methodology the Company utilized in the prior year s filing.

The cost estimation methodology used to update the charges and credits is the same methodology the Company utilized in the prior year s filing. LISA D. NORDSTROM Lead Counsel lnordstrom@idahopower.com December 28, 2018 Public Utility Commission of Oregon Filing Center 201 High Street SE, Suite 100 P.O. Box 1088 Salem, Oregon 97301 Re: Tariff Advice

More information

3 Existing National Grid

3 Existing National Grid 3 Existing National Grid 3.1 Introduction 3.2 Load and generation 3.1 Introduction This chapter provides an overview of New Zealand s existing National Grid as at 28 February 2012 with respect to load

More information

Hydro Plant Risk Assessment Guide

Hydro Plant Risk Assessment Guide September 2006 Hydro Plant Risk Assessment Guide Appendix E8: Battery Condition Assessment E8.1 GENERAL Plant or station batteries are key components in hydroelectric powerplants and are appropriate for

More information

welcome to the BC Hydro community open house

welcome to the BC Hydro community open house welcome to the BC Hydro community open house Dawson Creek/ Chetwynd Area Transmission ProjecT Open House welcome Dawson Creek/Chetwynd Area Transmission Project (DCAT) The purpose of this open house is

More information

Pretest Module 29 High Voltage Unit 1

Pretest Module 29 High Voltage Unit 1 Pretest Module 29 High Voltage Unit 1 1. Is a person qualified to work on high-voltage installations when this module is completed? 2. What is the code definition of high-voltage? 3. What is the IEEE definition

More information

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES 1 PRESENTATION OUTLINE Generation System Demand Outlook Existing Generation Resources Transmission System National Interconnected

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Enabling the power of wind. Competence and expertise for wind power customers

Enabling the power of wind. Competence and expertise for wind power customers Enabling the power of wind Competence and expertise for wind power customers This is Rising demand for energy and its impact on the environment are the defining challenges of this century. is tackling

More information

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta

More information

Insulator Replacements

Insulator Replacements A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Insulator Replacements Electrical Mechanical. Civil Protection & Control Transmission & Distribution Telecontrol System Planning HYDRO THE POWER

More information

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011 POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011 PREPARED BY: Electricity System Operations Planning and Performance DATE: 22 March 2012 FINAL

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA AEP Texas (comprised of its Central and North Divisions

More information

2012 Water Consumption Statistics Report. Water Services Department

2012 Water Consumption Statistics Report. Water Services Department 212 Water Consumption Statistics Report Water Services Department Issued: December 213 TABLE OF CONTENTS 212 Water Consumption Statistics Report December 213 212 GVWD Statistics Book - Notes...3 Annual

More information

Cost Benefit Analysis of Faster Transmission System Protection Systems

Cost Benefit Analysis of Faster Transmission System Protection Systems Cost Benefit Analysis of Faster Transmission System Protection Systems Presented at the 71st Annual Conference for Protective Engineers Brian Ehsani, Black & Veatch Jason Hulme, Black & Veatch Abstract

More information

UBC Technical Guidelines Section Edition Commissioning of Electrical Systems Page 1 of 5

UBC Technical Guidelines Section Edition Commissioning of Electrical Systems Page 1 of 5 Page 1 of 5 1.0 GENERAL 1.1 Coordination Requirements.1 UBC Building Operations Electrical Technical Support.2 UBC Energy & Water Services 2.0 REQUIREMENTS FOR COMMISSIONING AND TESTING 2.1 Testing.1 Unit

More information

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD In re : : Docket No. SB-00-0 () : Testimony of David M. Campilii, P.E. June, 00 PROV-- 0 0 TESTIMONY OF DAVID M. CAMPILII,

More information

Generation Interconnection Facilities Study For

Generation Interconnection Facilities Study For Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015 TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications...

More information

Motor Protection. Voltage Unbalance & Single-Phasing

Motor Protection. Voltage Unbalance & Single-Phasing For Summary of Suggestions to Protect Three-Phase Motors Against Single-Phasing see the end of this section, page 137. Historically, the causes of motor failure can be attributed to: Overloads 30% Contaminants

More information

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design Presented at the 2018 Transmission and Substation Design and Operation Symposium Revision presented at the

More information

SSF Section Location of Change SSF Issue Change(s) Comments Chapter Part B All Multiple Formatting, spelling and minor Changes applied -

SSF Section Location of Change SSF Issue Change(s) Comments Chapter Part B All Multiple Formatting, spelling and minor Changes applied - SSF Update December 2017 Summary of Changes This table only mentions SSF chapters that were updated. All other SSF chapters were checked and confirmed as still being uptodate. SSF Section Location of Change

More information

2016 ELECTRIC SYSTEM RELIABILITY REPORT CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT

2016 ELECTRIC SYSTEM RELIABILITY REPORT CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT 2016 ELECTRIC SYSTEM RELIABILITY REPORT CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT Contents Overview... 3 1.0 Electric System Reliability... 4 1.1 Annual Reliability Data with Utility Comparisons... 4

More information

Building a 21 st Century Electric Grid. February 23, 2018

Building a 21 st Century Electric Grid. February 23, 2018 Building a 21 st Century Electric Grid February 23, 2018 1 DTE strives to provide customers with a 21 st century electric grid that is safe, highly reliable, affordable and accessible 2 Our investment

More information

British Gas Comments and Questions on Kelton Engineering Draft SMER

British Gas Comments and Questions on Kelton Engineering Draft SMER British Gas Comments and Questions on Kelton Engineering Draft SMER 13 th September 2013 These comments and questions are associated with the draft SMER produced by Keith Vugler of Kelton Engineering,

More information

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT

More information

For further information, please contact Geoff Higgins at or by at

For further information, please contact Geoff Higgins at or by  at B-1-3 Tom A. Loski Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 bchydroregulatorygroup@bchydro.com November 30, 2015 Ms. Erica Hamilton Commission Secretary British Columbia Utilities

More information

Guidelines for connection of generators:

Guidelines for connection of generators: Guidelines for connection of generators: Greater than 30 kva, and not greater than 10 MW, to the Western Power distribution network January, 2017. EDM 32419002 / DM 13529244 Page 1 of 14 Contents 1 INTRODUCTION...

More information

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS 1. PURPOSE AND SCOPE OF THIS DOCUMENT... 3 2. DEFINITIONS...

More information

Annex A-4 DIESEL UNITS INDEX TO SYSTEM/COMPONENT CAUSE CODES BALANCE OF PLANT GENERATOR DIESEL ENGINE

Annex A-4 DIESEL UNITS INDEX TO SYSTEM/COMPONENT CAUSE CODES BALANCE OF PLANT GENERATOR DIESEL ENGINE Annex A-4 DIESEL UNITS INDEX TO SYSTEM/COMPONENT CAUSE CODES Electrical 3600-3690 Power Station Switchyard 3700-3730 Generator 4500-4580 Exciter 4600-4609 Cooling System 4610-4650 Controls 4700-4750 Miscellaneous

More information

The University of New South Wales. School of Electrical Engineering and Telecommunications. Industrial and Commercial Power Systems Topic 2

The University of New South Wales. School of Electrical Engineering and Telecommunications. Industrial and Commercial Power Systems Topic 2 The University of New South Wales School of Electrical Engineering and Telecommunications Industrial and Commercial Power Systems Topic 2 SWITCHBOARDS Overview Also called Switchgear and Controlgear Assembly

More information

Substation inspection guidelines Mark B. Goff, P.E.

Substation inspection guidelines Mark B. Goff, P.E. Substation inspection guidelines Mark B. Goff, P.E. Tennessee Valley Authority, Chattanooga, Tennessee ABSTRACT We need to better understand what our infrared camera is really showing us. Without guidelines,

More information

Unified requirements for systems with voltages above 1 kv up to 15 kv

Unified requirements for systems with voltages above 1 kv up to 15 kv (1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) (Corr.1 June 2018) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements

More information

Modular integrated transportable substation (MITS)

Modular integrated transportable substation (MITS) Technical Data TD027002EN transportable substation (MITS) Contents Description Page Voltage regulation with bypassing........................................................ 2 Mobile MITS application...............................................................

More information

Diagnostic Experience on HV Bushings Retired from Service MANUEL GUZMÁN-V

Diagnostic Experience on HV Bushings Retired from Service MANUEL GUZMÁN-V Diagnostic Experience on HV Bushings Retired from Service MANUEL GUZMÁN-V Diagnostic experience on HV bushing retired from service. Manuel Guzmán; Fernando Elizarraraz; Ricardo Montes Comisión Federal

More information

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012 POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012 PREPARED BY: System Performance and Commercial DATE: 7 March 2013 FINAL Disclaimer Purpose This

More information

What can HVDC Light do for you it s time to connect Applications Key Components

What can HVDC Light do for you it s time to connect Applications Key Components Power from shore inauguration event Bo Normark Marketing and Sales, Grid Systems What can HVDC Light do for you it s time to connect Applications Key Components ABB-Toll Inauguration -1 - HVDC Light :

More information

CA-NP-003. Newfoundland Power 2013/2014 General Rate Application Page 1 of 1

CA-NP-003. Newfoundland Power 2013/2014 General Rate Application Page 1 of 1 Requests for Information CA-NP-003 NP 2013/2014 GRA 1 2 3 4 5 6 Q. [ELG] Please provide the Company s depreciation request based on an ALG calculation procedure rather than the proposed ELG calculation

More information

Experience on Technical Solutions for Grid Integration of Offshore Windfarms

Experience on Technical Solutions for Grid Integration of Offshore Windfarms Experience on Technical Solutions for Grid Integration of Offshore Windfarms Liangzhong Yao Programme Manager AREVA T&D Technology Centre 18 June 2007, DTI Conference Centre, London Agenda The 90MW Barrow

More information

Review of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST

Review of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION In re: Staff's Second Data Request on OUC' s Review of Electric Utility Hurricane Preparedness and Restoration Actions Docket No. 20170215-EU Filed: January

More information

Pacific Gas and Electric Company s Revised 2016 Annual Progress

Pacific Gas and Electric Company s Revised 2016 Annual Progress March 06, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Report Pacific Gas and Electric

More information

MOBILE SUBSTATION DESIGN Brad Bozich & Vitor Vieira 2755 Northwoods Parkway Norcross, Georgia

MOBILE SUBSTATION DESIGN Brad Bozich & Vitor Vieira 2755 Northwoods Parkway Norcross, Georgia MOBILE SUBSTATION DESIGN Brad Bozich & Vitor Vieira 2755 Northwoods Parkway Norcross, Georgia 30071 678.982.8928 brad.bozich@efacec.com SCOPE This document is intended to help define the main parameters

More information

Shunt Capacitor Bank Protection in UHV Pilot Project. Qing Tian

Shunt Capacitor Bank Protection in UHV Pilot Project. Qing Tian Shunt Capacitor Bank Protection in UHV Pilot Project Qing Tian 2012-5 INTRODUCTION State Grid Corp. of China, the largest electric power provider in the country, has first build a 1000 kv transmission

More information

Product Specification Guide. Title: Southern States 362 kv RLSwitcher Vertical Interrupter Style Reactor Switcher

Product Specification Guide. Title: Southern States 362 kv RLSwitcher Vertical Interrupter Style Reactor Switcher TABLE OF CONTENTS PAGE 1.0 SCOPE... 2 2.0 STANDARDS... 2 3.0 DESIGN REQUIREMENTS... 2 3.01 Service Conditions... 2 3.02 Ratings... 2 3.03 Interrupter... 3 3.04 SF6 Gas System... 4 3.05 Terminal Pads...

More information

First Applications on AltaLink s Network. Roggero Ciofani, P. Eng. Colin Clark, P. Eng.

First Applications on AltaLink s Network. Roggero Ciofani, P. Eng. Colin Clark, P. Eng. First Applications on AltaLink s Network Roggero Ciofani, P. Eng. Colin Clark, P. Eng. Overview Technology Overview Applications and Alternatives Advantages Alberta Special Considerations Operational Implications

More information

Attention: Mr. Patrick Wruck, Commission Secretary and Manager, Regulatory Support

Attention: Mr. Patrick Wruck, Commission Secretary and Manager, Regulatory Support Diane Roy Vice President, Regulatory Affairs Gas Regulatory Affairs Correspondence Email: gas.regulatory.affairs@fortisbc.com Electric Regulatory Affairs Correspondence Email: electricity.regulatory.affairs@fortisbc.com

More information

Requirements for Secondary Voltage Revenue Metering (750 V and less)

Requirements for Secondary Voltage Revenue Metering (750 V and less) Requirements for Secondary Voltage Revenue Metering (750 V and less) To view the latest revision of this document go to: http://www.bchydro.com/ext/metering/ January 28, 2010 Copyright 2008 by BC Hydro.

More information

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION Presentation by Engr. O. C. Akamnnonu Chief Executive Officer, Ikeja Electricity Distribution Company AGENDA WORK THROUGH

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Chapter 6 Generator-Voltage System

Chapter 6 Generator-Voltage System Chapter 6 Generator-Voltage System 6-1. General The generator-voltage system described in this chapter includes the leads and associated equipment between the generator terminals and the low-voltage terminals

More information

Modifiable TITAN Horizontal Motors Accessories and Modifications

Modifiable TITAN Horizontal Motors Accessories and Modifications 36. Rotor, Standard And Optional Construction Standard rotor construction of 449, 5000 and 5800 frame TITAN products is typically die-cast aluminum. 720 RPM and slower is typically fabricated aluminum.

More information

Evaluating Losses in Electrical Equipment Focus on Transmission Utilities. CNY Engineering Expo 2016 Syracuse, New York Arthur C. Depoian P.E.

Evaluating Losses in Electrical Equipment Focus on Transmission Utilities. CNY Engineering Expo 2016 Syracuse, New York Arthur C. Depoian P.E. Evaluating Losses in Electrical Equipment Focus on Transmission Utilities CNY Engineering Expo 2016 Syracuse, New York Arthur C. Depoian P.E. Contents Introduction Present Value of ongoing energy costs

More information

High Voltage Surge Arresters Buyer s Guide Section Transmission Line Arrester PEXLINK

High Voltage Surge Arresters Buyer s Guide Section Transmission Line Arrester PEXLINK High Voltage Surge Arresters Buyer s Guide Section Transmission Line Arrester PEXLINK Definitions Transmission Line Arresters Backflashover Occurs when lightning strikes the tower structure or overhead

More information

Welcome to Breckenridge. T&D Research Stem Meeting Tuesday August 11, :00 5:00 pm

Welcome to Breckenridge. T&D Research Stem Meeting Tuesday August 11, :00 5:00 pm Welcome to Breckenridge T&D Research Stem Meeting Tuesday August 11, 2009 1:00 5:00 pm 1 The plan 1:00 A road map for the meeting today Simon and Jerry Speakers: Simon Chiang, Doug McLaughlin, Janos Toth

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

Power Voltage Transformers for Air Insulated Substations

Power Voltage Transformers for Air Insulated Substations Power Voltage Transformers for Air Insulated Substations Introduction Trench Power Voltage Transformers (Power VTs) combine the attributes of an inductive voltage transformer with the application of a

More information

Low and medium voltage service. Power Care Customer Support Agreements

Low and medium voltage service. Power Care Customer Support Agreements Low and medium voltage service Power Care Customer Support Agreements Power Care Power Care is the best, most convenient and guaranteed way of ensuring electrification system availability and reliability.

More information

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Operational Planning Study Report RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Report No. T&S Planning 2013-062 British Columbia Hydro and Power Authority British Columbia Hydro and

More information