XXXX. Skookum Creek Power Project. Interconnection System Impact Study

Size: px
Start display at page:

Download "XXXX. Skookum Creek Power Project. Interconnection System Impact Study"

Transcription

1 XXXX Skookum Creek Power Project Report No. August 2010 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority All rights reserved..

2 DISCLAIMER OF WARRANTY, LIMITATION OF LIABILITY This report was prepared by the British Columbia Hydro And Power Authority ( BCH ) or, as the case may be, on behalf of BCH by persons or entities including, without limitation, persons or entities who are or were employees, agents, consultants, contractors, subcontractors, professional advisers or representatives of, or to, BCH (individually and collectively, BCH Personnel ). This report is to be read in the context of the methodology, procedures and techniques used, BCH s or BCH s Personnel s assumptions, and the circumstances and constraints under which BCH s mandate to prepare this report was performed. This report is written solely for the purpose expressly stated in this report, and for the sole and exclusive benefit of the person or entity who directly engaged BCH to prepare this report. Accordingly, this report is suitable only for such purpose, and is subject to any changes arising after the date of this report. This report is meant to be read as a whole, and accordingly no section or part of it should be read or relied upon out of context. Unless otherwise expressly agreed by BCH: 1. any assumption, data or information (whether embodied in tangible or electronic form) supplied by, or gathered from, any source (including, without limitation, any consultant, contractor or subcontractor, testing laboratory and equipment suppliers, etc.) upon which BCH s opinion or conclusion as set out in this report is based (individually and collectively, Information ) has not been verified by BCH or BCH s Personnel; BCH makes no representation as to its accuracy or completeness and disclaims all liability with respect to the Information; 2. except as expressly set out in this report, all terms, conditions, warranties, representations and statements (whether express, implied, written, oral, collateral, statutory or otherwise) are excluded to the maximum extent permitted by law and, to the extent they cannot be excluded, BCH disclaims all liability in relation to them to the maximum extent permitted by law; 3. BCH does not represent or warrant the accuracy, completeness, merchantability, fitness for purpose or usefulness of this report, or any information contained in this report, for use or consideration by any person or entity. In addition BCH does not accept any liability arising out of reliance by a person or entity on this report, or any information contained in this report, or for any errors or omissions in this report. Any use, reliance or publication by any person or entity of this report or any part of it is at their own risk; and 4. In no event will BCH or BCH s Personnel be liable to any recipient of this report for any damage, loss, cost, expense, injury or other liability that arises out of or in connection with this report including, without limitation, any indirect, special, incidental, punitive or consequential loss, liability or damage of any kind. British Columbia Hydro and Power Authority, All rights reserved ii

3 COPYRIGHT NOTICE Copyright and all other intellectual property rights in, and to, this report are the property of, and are expressly reserved to, BCH. Without the prior written approval of BCH, no part of this report may be reproduced, used or distributed in any manner or form whatsoever. British Columbia Hydro and Power Authority, All rights reserved. iii

4 Executive Summary The XXXX, the Interconnection Customer (IC), proposes to develop the Skookum Creek Power Project to deliver electric energy to BC Hydro (BCH) through the BCH 2008 Clean Power Call (CPC). This report identifies the required system modifications for interconnecting the proposed Skookum Power Project. The maximum power injection to the system is 27.5 MW at the Point of Interconnection (POI) located at the 132 kv bus of Cheekye (CKY) Substation. The proposed Commercial Operation Date (COD) is August 1, To interconnect the Skookum project and its facilities to the BCH Transmission System at the POI at CKY Substation, this System Impact Study (SIS) has identified the following issues and requirements: The customer-owned 132 kv transmission interconnection line will be terminated at CKY 132 kv bus by creating a three-breaker ring bus configuration. A HV circuit breaker with independent pole operation and point-on-wave controller may be required at the IC site for step-up transformer energization from the system. A generation run-back or tripping scheme is required to resolve the post-contingency overloads on 2L9 and 2L13. If overload is detected on 2L9 or 2L13 at Cheekye substation (CKY), then a signal is sent to Skookum Power plant to run back or trip the Skookum generation. A direct transfer tripping scheme to trip the Skookum Power plant or the IC line is required to resolve transient instability issues and overload on 1L35 caused by the loss of CKY T4. A direct transfer tripping scheme to trip the Skookum Power plant or the IC line is required to resolve transient instability issues caused by the loss of 1L31. Out of step protection function is required at the Skookum Power plant. Minor revision of the existing system protection, control and/or telecom is required to accommodate the interconnection of the project. The non-binding good faith cost estimate for interconnection Network Upgrades required to interconnect the proposed project to the BCH Transmission System is $4.7 million. The estimated time to construct the Network Upgrades required to interconnect the project to the BCH Transmission System is estimated at 18 months. The Interconnection Facilities Study report will provide greater details of the interconnection Network Upgrade requirements and associated cost estimates and estimated construction timeline for this project. Upgrades that are common to the other IPP projects in this area are not included in this report. British Columbia Hydro and Power Authority, All rights reserved. iv

5 Table of Contents DISCLAIMER OF WARRANTY, LIMITATION OF LIABILITY...ii COPYRIGHT NOTICE... iii Executive Summary...iv 1.0 Introduction Purpose of Study Terms of Reference Assumptions System Studies Steady State Pre-outage Power Flows Power Flow Based First Contingency Study Transient Stability Study Islanding Fault Analysis Analytical Studies Protection and Control & Telecommunications BCH System Black Start Capability Transmission Line Upgrade Requirements Additional BCH Station Upgrades/Additions Other Issues Cost Estimate and Schedule Conclusion & Discussion...14 Appendix A Skookum Creek Model and Data...15 British Columbia Hydro and Power Authority, All rights reserved. v

6 1.0 Introduction The project reviewed in this System Impact Study (SIS) report is as described in Table 1 below. Table 1: Summary Project Information Project Name Skookum Power Project Interconnection Customer (IC) XXXX Point of Interconnection (POI) 132 kv bus at CKY Substation IC Proposed COD August 1, 2013 Type of Interconnection Service NRIS ERIS Maximum Power Injection (MW) 27.5 (Summer) 27.5 (Winter) Number of Generator Units 2 Plant Fuel Hydro The XXXX, the Interconnection Customer (IC), proposes to develop the Skookum Power Project which involves construction of a powerhouse with two hydro power generators each rated at 14.8 MVA on Skookum Creek to deliver electric energy to BC Hydro (BCH) through the BCH 2008 Clean Power Call (CPC). The generating station will be connected to the 132 kv bus of Cheekye (CKY) Substation through a step-up transformer and a 20.4 km customer-owned 132 kv transmission line. The proposed maximum power to be injected to the BCH system from the generating station is 27.5 MW. The Point of Interconnection (POI) is the 132 kv bus of CKY Substation. The proposed Commercial Operation Date (COD) is August 1, Figure 1 shows the transmission system in the Cheekye Area. British Columbia Hydro and Power Authority, All rights reserved. Page 1 of 17

7 Skookum Power km 22 km Figure 1 Transmission System with the interconnection of Skookum Power in the CKY Area The following diagram in Figure 2 shows the more detailed connection of the Skookum Power (SKO) to the Transmission System. Skookum Power Figure 2 - The Skookum Power Project Interconnection One Line Diagram British Columbia Hydro and Power Authority, All rights reserved. Page 2 of 17

8 2.0 Purpose of Study The purpose of this SIS is to assess the impact of the IC interconnection on the BCH Transmission System. This study will identify constraints and Network Upgrades required for the reliable operation of the Transmission System. 3.0 Terms of Reference The study investigates and addresses the voltage and overloading issues of the transmission networks in the vicinity of the Skookum Power generating station as a result of the proposed interconnection. Topics studied include equipment thermal loading and rating requirements, system transient stability and voltage stability, transient over-voltages, protection coordination, operation flexibility, telecom requirements and high level remedial action scheme requirements. BCH planning methodology and criteria are used in the studies. The SIS does not investigate the operating restrictions and other factors for the possible second contingency outages. Subsequent internal network studies will determine the requirements for reinforcements or operating restrictions/instructions for those kinds of events. Impact to the bulk transmission system is not included in the SIS and will be covered in a separate study. The work necessary to implement the network improvements identified in this SIS report will be described in greater detail in the Interconnection Facilities Study report for this project. 4.0 Assumptions The power flow conditions studied are base cases that include generation, transmission facilities, and load forecast representing the queue position applicable to this project. Applicable seasonal conditions and the appropriate study years for the study horizon are also incorporated. The 2013 heavy winter, 2013 heavy summer and light summer load flow base cases were selected for this study. The study is based on the model and data information provided by the proponent in the Generator Interconnection Data Form for this project. Reasonable assumptions are made to complete the study and the report, whenever such information is unavailable. Prior to addition of the proposed Box Canyon Project, the 230/60 kv transformers at Cheekye Substation (CKY) would already be overloaded for the loss of CKY (T6&7) or CKY T5. A generation run-back scheme is required to reduce Mamquam (MAM) generation output within minutes. 5.0 System Studies Power flow, short circuit and transient stability studies were carried out to evaluate the impact of the proposed interconnection. Studies were also performed to determine the protection, control and communication requirements and to evaluate possible over-voltage issues. British Columbia Hydro and Power Authority, All rights reserved. Page 3 of 17

9 5.1 Steady State Pre-Outage Power Flows Pre-outage power flows are prepared to assess the impact of the proposed interconnection using three basic system load conditions: 2013 winter peak load, 2013 summer light load and 2013 summer peak load, and defined generation conditions. The steady-state power flow studies have indicated: No voltage violations are observed. No circuits overload before and after the proposed interconnection Table 2 provides the power flow study results for the proposed interconnection Table 2: Steady-state Pre-outage Power Flow Study Results System Condition IPP Injection Bus Voltage (PU) Circuit Flow (MW) (MW) SKO 13G CKY 132 CKY T4 230/ HW LS HS Note: LS: light summer load; HW: heavy winter load; HS: heavy summer load CKY T4 summer rating: 90 MVA 5.2 Power Flow Based First Contingency Study Power flow based single contingency (N-1) studies have been conducted to check if the post-disturbance performance including bus voltage deviation and facility loading meets the planning criteria under different system load conditions including heavy winter, heavy summer and light summer. The single contingency studies have indicated that there are severe overload problems on 2L9 or 2L13 due to high Bridge River generation and the addition of the Skookum Creek Project. Therefore, a generation run-back scheme is required to reduce the generation output at Skookum Creek. This scheme should be expandable to include generation runback or tripping at Box Canyon and Culliton Creek as they are connected to the BC Hydro system. 2L9 (CKY-LYN), 2L13 (CKY-CYP) and 2L17 (LYN-WLT) will be overloaded in both 2013 LS and HS cases for the following contingencies: 2L13(CKY-CYP) + CYP T2 2L78 (ROS-ALZ) + ROS T1 2L77 ALZ-CBN + ALZ T2 British Columbia Hydro and Power Authority, All rights reserved. Page 4 of 17

10 2L9 (CKY-LYN) + LYN T1 2L17(LYN-WLT) + LYN T2 2L14 CYP-WLT 3L2 BRT-UHT 3L5 UHT-ROS Existing Bridge River gen-shedding RAS is relied on to address this issue first. If the overloads still exist, generation runback or generation tripping will be applied at the three CPC IPPs: Box Canyon, Culliton Creek and Skookum Creek. The single contingency studies also indicated that there is a minor overloading problem on 1L35 for loss of CKY T4. A direct transfer tripping scheme is required to trip the Skookum Creek IPP or the IPP line. The contingency study results based on 2013 summer light load and 2013 summer heavy load are listed in Tables 3 to 6. British Columbia Hydro and Power Authority, All rights reserved. Page 5 of 17

11 Table 3: The Power Flow Study Results after Single Element Contingency in 2013 LS case (Bus voltage) Cont. Name Bus Voltages (pu) CKY 132 MSA 132 SEC 132 WFR 132 SCG 132 PHR 132 COM 132 GIB 132 CKY 230 CKY 60 SQH 60 WFR 31P Pre Contingency (system normal) CKY T MSA T1&T5 trip 1L CKY T5 + T CKYT5+T9 shed CTN CKY T6 + T CKY T6+T7 shed CTN L13(CKY-CYP) + CYP T L3 ROS-WAH + WAH T L78 (ROS-ALZ) + ROS T L77 ALZ-CBN + ALZ T L1(BRT-FCN) + FCN T L5 (CKY-FCN) + FCN T L2 BRT-CKY + RBW T L9 (CKY-LYN) + LYN T L17 (LYN-WLT) + LYN T L14 CYP-WLT L12 (CKY to CMS) + CMS L31 (GIB-CKY) L32(SEC-GIB) L35(MSA-SEC) + PHR T L70 CKY-SQH L68 CKY-SQH L69 SQH-PTO L72 MAM-MAM 72P L2 BRT-UHT L5 UHT-ROS British Columbia Hydro and Power Authority, All rights reserved. Page 6 of 17

12 Table 4: The Power Flow Study Results after Single Element Contingency in 2013 HS case (Bus voltage) Cont. Name Bus Voltages (pu) CKY 132 MSA 132 SEC 132 WFR 132 SCG 132 PHR 132 COM 132 GIB 132 CKY 230 CKY 60 SQH 60 WFR 31P Pre Contingency(System normal) CKY T CKY T5 + T CKY T6 + T L13(CKY-CYP) + CYP T L3 ROS-WAH + WAH T L78 (ROS-ALZ) + ROS T L77 ALZ-CBN + ALZ T L1(BRT-FCN) + FCN T L5 (CKY-FCN) + FCN T L2 BRT-CKY + RBW T L2 BRT-CKY+ RBW T L9 (CKY-LYN) + LYN T L17 (LYN-WLT) + LYN T L14 CYP-WLT L12 (CKY to CMS) + CMS L31 (GIB to CKY) L32(SEC-GIB) L35(MSA-SEC) + PHR T L70 CKY-SQH L68 CKY-SQH L69 SQH-PTO L72 MAM-MAM 72P L2 BRT-UHT L5 UHT-ROS British Columbia Hydro and Power Authority, All rights reserved. Page 7 of 17

13 Table 5: The Power Flow Study Results after Single Element Contingency in 2013LS case (Branch flow) Cont. Name From Bus To Bus No. Name No. Name ID O/L facility Area Zone Current (A) Rating (A) Load (%) CKY T4 102 MSA PHR L SEC PHR L SEC GIB L MSA T1&T5 trip1l GIB BOX 31P 1 1L WFR 31P 9723 BOX 31P 1 1L CKY and CKY T CKY T5 + T9 601 CKY and CKY T CKY and CKY T CKY and CKY T CKY and CKY T CKYT5+T9 shed CTN 601 CKY and CKY T CKY and CKY T CKY and CKY T CKY T6 + T7 201 CKY and CKY T CKY and CKY T CKY T6+T7 shed CTN 201 CKY and CKY T CKY and CKY T L13(CKY-CYP) + CYP T2 201 CKY LYN 2T1 1 2L WLT LYN 2T2 1 2L CKY LYN 2T1 1 2L L78 (ROS-ALZ) + ROS T1 201 CKY CYP 2T2 1 2L WLT LYN 2T2 1 2L L77 ALZ-CBN + ALZ T2 201 CKY LYN 2T1 1 2L L9 (CKY-LYN) + LYN T1 201 CKY CYP 2T2 1 2L L17 (LYN-WLT) + LYN T2 201 CKY CYP 2T2 1 2L L14 CYP-WLT 201 CKY LYN 2T1 1 2L WLT LYN 2T2 1 2L SEC GIB L L35(MSA-SEC) + PHR T3 173 GIB BOX 31P 1 1L WFR 31P 9723 BOX 31P 1 1L L5 UHT-ROS 201 CKY LYN 2T1 1 2L British Columbia Hydro and Power Authority, All rights reserved. Page 8 of 17

14 Table 6: The Power Flow Study Results after Single Element Contingency in 2013 HS case (Branch flow) Cont. Name From Bus To Bus Num Name Num Name ID O/L facility Area Zone Current (A) Rating (A) Load (%) 106 SEC GIB L MSA T1&T5 trip1l GIB BOX 31P 1 1L WFR 31P 9723 BOX 31P 1 1L CKY and CKY T CKY T5 + T9 601 CKY and CKY T CKY and CKY T CKY and CKY T CKY and CKY T CKYT5+T9 shed CTN 601 CKY and CKY T CKY and CKY T CKY and CKY T CKY T6 + T7 201 CKY and CKY T CKY and CKY T CKY T6+T7 shed CTN 201 CKY and CKY T CKY and CKY T L13(CKY-CYP) + CYP T2 201 CKY LYN 2T1 1 2L WLT LYN 2T2 1 2L CKY LYN 2T1 1 2L L78 (ROS-ALZ) + ROS T1 201 CKY CYP 2T2 1 2L WLT LYN 2T2 1 2L L77 ALZ-CBN + ALZ T2 201 CKY LYN 2T1 1 2L L9 (CKY-LYN) + LYN T1 201 CKY CYP 2T2 1 2L L17 (LYN-WLT) + LYN T2 201 CKY CYP 2T2 1 2L L14 CYP-WLT 201 CKY LYN 2T1 1 2L WLT LYN 2T2 1 2L SEC GIB L L35(MSA-SEC) + PHR T3 173 GIB BOX 31P 1 1L WFR 31P 9723 BOX 31P 1 1L L2 BRT-UHT 201 CKY LYN 2T1 1 2L CKY LYN 2T1 1 2L L5 UHT-ROS 201 CKY CYP 2T2 1 2L WLT LYN 2T2 1 2L British Columbia Hydro and Power Authority, All rights reserved. Page 9 of 17

15 5.3 Transient Stability Study A series of transient stability studies under various system conditions including the heavy winter case and the most severe light summer case have been performed. The model of the generating project was based on the IC s data submission plus additional assumptions where the IC s data was incomplete/inappropriate. The models and data values of the key components are shown in Appendix A. Skookum Creek generators will be unstable after the loss of CKY T4 or 1L31 in 2013 LS, HS and HW cases. A direct transfer tripping (DTT) scheme is required to trip Skookum Creek IPP or the IPP interconnection line in 9 cycles for loss of CKY T4 or 1L31. An alternative method is for the IPP to replace the AC excitation system with a fast-responding static excitation system. If the second option is adopted by the IPP, further study is required to assess the performance of this option. The IPP must be able to detect and be tripped for out-of-step conditions caused by severe disturbances in the transmission system. Out of step protection is required at Skookum Creek and shall be provided by the IC. The swing center is expected to be inside the power plant. BCH can provide apparent impedance versus time plots of stable and unstable swings if requested. The transient stability study results for 2013 summer light load are summarized in Tab. 7. British Columbia Hydro and Power Authority, All rights reserved. Page 10 of 17

16 Table 7: Transient Stability Study Results (Pre-outage condition: 2013 LS, Skookum Power injection: 27.5 MW) Fault Clearing Time IPP Max Rotor Swing (Deg.) 3 Fault (Cycles) (Delta =max - initial) Stability Case Outage Location BOX SKO COM Performance Close End Far End MCH IPP IPP IPP IPP 1L35 SEC132 MSA132 Unstable SEC acceptable (MSA-SEC) 8 9 (Note 3) 1L31 CKY132 GIB132 2 CKY132 islanding Unstable acceptable (CKY-GIB) 8 8 (Note 2) 1L31 CKY132 GIB132 Unstable 3 GIB132 islanding acceptable (CKY-GIB) 8 8 (Note 1) CKY132 CKY230 Unstable 4 CKY T4 CKY acceptable 8 6 (Note 2) CKY230 CKY132 5 CKY T4 CKY acceptable L32 (SEC-GIB) 1L32 (SEC-GIB) SEC132 GIB132 SEC132 8 GIB132 8 GIB132 9 SEC Unstable (Note 1) Unstable (Note 1) acceptable acceptable Notes: 1. To be tripped by out-of-step relay. 2. Direct transfer tripping SKO IPP or the IPP line is required. 3. The circuit breakers of 1L35 (8 cycles fault clearing time) will be upgraded to new faster ones (fault clearing time no more than 6 cycles). This issue has been identified and resolved in a previous study (Bear Creek Hydro Project SIS study). 4. Stability performance is acceptable after applying the above solutions. 5.4 Islanding Islanded operation is normally not an acceptable practice in BCH. Power quality protection will be required at the generating units to detect abnormal system conditions such as under/over voltage and under/over frequency and subsequently trip the units. The settings of these protective relays must conform to the existing BCH practice for generating plants so that the generator will not trip during normal ranges of voltages and frequencies. 5.5 Fault Analysis The short circuit analysis for the CPC System Impact Studies is based upon the latest BCH system short circuit model, which includes project equipment and impedances provided by the successful CPC Interconnection Customers. The model includes higher queued projects and planned system reinforcements but excludes the Northwest Transmission Line (NTL) and other lower queued projects. At this stage, the report does not provide Thevenin impedances at the Point of Interconnection (POI) due to uncertainties associated with the system reinforcement options identified for the CPC British Columbia Hydro and Power Authority, All rights reserved. Page 11 of 17

17 projects and the statuses of higher queued projects. However, these Thevenin impedances, including the ultimate fault levels at POI, will be made available to Interconnection Customers upon request. BC Hydro will work with the IC to provide accurate data, as required, during the project design phase. 5.6 Analytical Studies Preliminary calculation results indicate that i) when energizing the customer owned stepup transformer under system normal conditions, the voltage sag at the POI will be about 9.7%, which exceeds the limits stated in the Interconnection Requirements; and ii) the voltage sags will be much higher if the CKY transformer T4 is out of service (the worst single contingency). Therefore, the IPP may require a HV breaker with independent pole operation and a Point-on-Wave controller to energize its step-up transformer from CKY. The IC will be responsible for undertaking the appropriate studies required to determine the necessity of an inrush mitigation scheme. A scheme to delay controlled opening of GIB terminal of 1L31 and send a direct transfer tripping (DTT) signal to the IPP is required to avoid over-voltages when CKY T4 is out of service. 5.7 Protection and Control & Telecommunications Protection, control and telecom requirements for the new Skookum Power generator addition have also been reviewed. The main items are summarized below: The IC is responsible to provide protection equipment at its site for the 132 kv interconnection line from the IPP to CKY. The IC is responsible to provide required telemetry and status information to BCH s Fraser Valley Office and Southern Interior Office via broadband satellite communication. Revision of 2L9 and 2L13 protections at CKY substation is required to add a new special protection scheme to signal generation run-back at Skookum Power to mitigate overload on 2L9 or 2L13. Revision of 1L31 protections at CKY and GIB is required to accommodate control scheme to delay GIB controlled opening of 1L31. GIB will send transfer tripping signal to CKY to trip the IPP line. The scheme is armed by the condition of CKY T4 out of service. At CKY substation, protection will be provided to the customer-owned transmission line. Revision of CKY T4 protection is required to add a connection to the new breaker 1CB1. Revision of 1L31 protections is required to add a connection to the new breaker 1CB1. Broadband satellite communication from the IPP to BCH is required Other minor revisions of existing system protection, control and telecom are required British Columbia Hydro and Power Authority, All rights reserved. Page 12 of 17

18 5.8 BCH System Black Start Capability BCH does not require the proposed project to have black start (self-start) capability. However, if the IC desires their facilities to be energized from the BCH system, the IC is required to apply for an Electricity Supply Agreement. Upon receipt of this application, a plant pick-up study would be required to assess the impact of energizing the IC s facilities. A high level plant pick-up screening was performed as part of the SIS and any issues are identified in Section Transmission Line Upgrade Requirements To accommodate the Skookum Power project s interconnection into the Transmission System, the IC will build a 132 kv transmission line from Skookum Power generation station to the POI at its own cost. No transmission line upgrade is required on the BCH Transmission System side Additional BCH Station Upgrades/Additions The customer-owned 132 kv transmission interconnection line will be terminated at the CKY 132 kv bus by creating a three-breaker ring bus configuration, in which two new 132 kv circuit breakers will be installed with associated electric power devices such as disconnects, CVT, surge arrestors, etc Other Issues There are no other issues identified at this stage Cost Estimate and Schedule The non-binding good faith cost estimate for interconnection Network Upgrades required to interconnect the proposed project to the BCH Transmission System is $4.7 million. The Facilities Study Report will provide more accurate information of the cost estimates. The estimated time to construct the Network Upgrades required to interconnect the project to the BCH Transmission System is estimated at 18 months after the Standard Generation Interconnection Agreement is signed and a BCH capital project is approved. A more detailed construction timeline will be provided in the Facilities Study Report. BCH system upgrades triggered by CPC projects are being determined and the IC may be required to post security to cover one or more upgrade. Further information will be provided over the next few months. British Columbia Hydro and Power Authority, All rights reserved. Page 13 of 17

19 6.0 Conclusion & Discussion To interconnect the Skookum Creek Power Project and its facilities to the BCH Transmission System at the 132 kv CKY bus, this System Impact Study has identified the following issues and requirements: The customer-owned 132 kv transmission interconnection line will be terminated at CKY 132 kv bus by creating a three-breaker ring bus configuration. A HV circuit breaker with independent pole operation and point-on-wave controller may be required at the IC side for step-up transformer energization. No unacceptable voltage condition in the Transmission System was observed in the power flow and transient stability analysis due to the Skookum plant interconnection under normal and N-1 contingencies. No voltage instability has been observed in the Transmission System due to Skookum power plant interconnection. A generation run-back or tripping scheme is required to resolve the post-contingency overloads on 2L9 and 2L13. If overload is detected on 2L9 or 2L13 at Cheekye substation (CKY), then a signal is sent to Skookum Power to run back or trip the generation within minutes. This scheme should be expandable to run back or trip the generation at Box Canyon and Culliton generating plants as they connect to the BCH system. A direct transfer tripping scheme to trip the Skookum Power plant or the IC line is required to resolve transient instability issues and overload on 1L35 caused by the loss of CKY T4. A direct transfer tripping scheme to trip the Skookum Power plant or the IC line is required to resolve transient instability issues caused by the loss of 1L31. Out of step protection is required at the Skookum Power plant. Islanded operation of the plant is not allowed. Power quality protection is required to prevent/mitigate possible islanded operation. Revision to system protection, control and telecom in the BCH Transmission System and control center is needed to accommodate the interconnection of the generating project. Upgrades that are common to the other IPP projects in this area are not included in this report. British Columbia Hydro and Power Authority, All rights reserved. Page 14 of 17

20 Appendix A IPP Model and Data Skookum Power Generator Model The contents of this section have been removed due to the proprietary nature of the information. British Columbia Hydro and Power Authority, All rights reserved. Page 15 of 17

21 Skookum Power Excitation Control System Model The contents of this section have been removed due to the proprietary nature of the information. British Columbia Hydro and Power Authority, All rights reserved. Page 16 of 17

22 Skookum Power Governor Control System Model The contents of this section have been removed due to the proprietary nature of the information. British Columbia Hydro and Power Authority, All rights reserved. Page 17 of 17

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study XXXX Knob Hill Wind Farm Project Report No. August 2010 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2010. All rights reserved.. DISCLAIMER OF WARRANTY, LIMITATION

More information

XXXX. Kokish River Hydroelectric Project. Interconnection System Impact Study

XXXX. Kokish River Hydroelectric Project. Interconnection System Impact Study XXXX Kokish River Hydroelectric Project Report No. August 2010 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2010. All rights reserved.. DISCLAIMER OF WARRANTY,

More information

XXXX. Crowsnest Pass Waste Heat Project. Interconnection System Impact Study

XXXX. Crowsnest Pass Waste Heat Project. Interconnection System Impact Study XXXX Crowsnest Pass Waste Heat Project Report No. ASP2010- T062 August 2010 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2010. All rights reserved.. DISCLAIMER

More information

XXXXX. Kokish River Hydroelectric Project. Interconnection Facilities Study and Project Plan

XXXXX. Kokish River Hydroelectric Project. Interconnection Facilities Study and Project Plan XXXXX Kokish River Hydroelectric Project Interconnection Facilities Study and Project Plan March 16, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2010. All

More information

Interconnection Feasibility Study

Interconnection Feasibility Study Interconnection Feasibility Study Mount Mabel Wind Energy Project Report No: T&S Planning 2015-054 December 2015 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2015.

More information

Sunmine Solar Project. Interconnection System Impact Study

Sunmine Solar Project. Interconnection System Impact Study XXXX Sunmine Solar Project Interconnection System Impact Study Report No: T&S Planning 2013-012 May 2013 Revision 0 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority

More information

Conifex Mackenzie Combined Heat and Power Project. Interconnection System Impact Study

Conifex Mackenzie Combined Heat and Power Project. Interconnection System Impact Study Interconnection System Impact Study Report No: T&S Planning 203-064 November 20, 203 Revision 0 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 203. All rights reserved.

More information

Interconnection System Impact Study

Interconnection System Impact Study Interconnection System Impact Study Report #: T&S Planning 2015-052 February 2016 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2015. All rights reserved. Acknowledgements

More information

Interconnection System Impact Study

Interconnection System Impact Study Interconnection System Impact Study Pennask and Shinnish Creek Wind Project Report No: T&S Planning 2014 072 December 2014 DRAFT British Columbia Hydro and Power Authority British Columbia Hydro and Power

More information

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Operational Planning Study Report RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks Report No. T&S Planning 2013-062 British Columbia Hydro and Power Authority British Columbia Hydro and

More information

Kwalsa Phase II Project (Big Silver) System Impact Study Addendum May 20, 2016

Kwalsa Phase II Project (Big Silver) System Impact Study Addendum May 20, 2016 (Big Silver) System Impact Study Addendum May 20, 2016 This is an addendum to the System Impact Study Report (No. T&S Planning2012 004 Kwalsa Phase II Project Interconnection System Impact Study) dated

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q171 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q174 74.5 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood Prepared for: SCE&G Fossil/Hydro June 30, 2008 Prepared by: SCE&G Transmission Planning Table of Contents

More information

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test: Salisbury Substation 11kV Feeders DISCLAIMER The purpose of this document is to inform customers, Interested Parties,

More information

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012 POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 PREPARED BY: Electricity System Operations Planning and Performance DATE: 5 June 2012 FINAL

More information

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Interconnection Feasibility Study Report GIP-369-FEAS-R1 Interconnection Feasibility Study Report GIP-369-FEAS-R1 System Interconnection Request #369 50 MW Wind Generating Facility Cumberland County (L-6513) 2012-02-09 Control Centre Operations Nova Scotia Power

More information

System Impact Study Report

System Impact Study Report Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR)

Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR) Report-BCTC-R009A Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR) December 8, 2005 Prepared by Wenyuan Li

More information

Interconnection Feasibility Study Report GIP-046-FEAS-R2

Interconnection Feasibility Study Report GIP-046-FEAS-R2 Interconnection Feasibility Study Report GIP-046-FEAS-R2 Generator Interconnection Request #46 32 MW Wind Generating Facility Colchester (L-6513), NS August 17, 2007 Control Centre Operations Nova Scotia

More information

Project #148. Generation Interconnection System Impact Study Report

Project #148. Generation Interconnection System Impact Study Report Project #148 Generation Interconnection System Impact Study Report June 05, 2012 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Energy Resource Interconnection

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

TRIP OF HORSHAM-REDCLIFFS 220 KV TRANSMISSION LINE AND MURRAYLINK INTERCONNECTOR ON 12 NOVEMBER 2015

TRIP OF HORSHAM-REDCLIFFS 220 KV TRANSMISSION LINE AND MURRAYLINK INTERCONNECTOR ON 12 NOVEMBER 2015 TRIP OF HORSHAM-REDCLIFFS 220 KV TRANSMISSION LINE AND MURRAYLINK INTERCONNECTOR ON 12 AN AEMO POWER SYSTEM OPERATING INCIDENT REPORT FOR THE NATIONAL ELECTRICITY MARKET Published: August 2016 IMPORTANT

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8 Header Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations RT 007-11 Balhannah and Uraidla - Final Draft Page 1 of 8 DISCLAIMER The purpose of this document is to inform customers,

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015 No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO KV BUSBAR ON 30 OCTOBER 2011

POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO KV BUSBAR ON 30 OCTOBER 2011 POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO.1 275 KV BUSBAR ON 30 OCTOBER 2011 PREPARED BY: Electricity System Operations Planning and Performance

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Customer --- Service Location: Rutherford County Total Output: 79.2 MW Commercial Operation Date: 9/1/2014 In-Service Date (if given): 9/1/2014

More information

Project #94. Generation Interconnection System Impact Study Report Revision

Project #94. Generation Interconnection System Impact Study Report Revision Project #94 Generation Interconnection System Impact Study Report Revision October 2, 2009 Electric Transmission Planning Table of Contents Table of Contents...2 Executive Summary...3 Energy Resource Interconnection

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

Facilities Study for Alberta to US Available Transfer Capability

Facilities Study for Alberta to US Available Transfer Capability Facilities Study for Alberta to US Available Transfer Capability Report No: NPP2002-05 June 3, 2002 System Planning & Grid Operations, Transmission Line of Business Engineering Services Executive Summary

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY January 7, 2002 Prepared by Jorge Chacon (Consultant) Tucson Electric Power Company Ed Beck ii EXECUTIVE SUMMARY

More information

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This

More information

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study ` Dunvegan Hydroelectric Project For Glacier Power Limited Preliminary Interconnection Study Prepared by Pung Toy, P. Eng. and Ata Rehman, P. Eng. September 24, 2004 Table of Contents Table of Contents...

More information

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,

More information

Feasibility Study Report

Feasibility Study Report Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS El Paso Electric Company System Operations Department System Planning Section May 2004

More information

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011 POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011 PREPARED BY: Electricity System Operations Planning and Performance DATE: 22 March 2012 FINAL

More information

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management Southern Company Interconnection Process Dexter Lewis Research Engineer Research and Technology Management Southern Company Outline Southern Company GPC Solar Interconnection Process Application requirements

More information

Power System Operating Incident Report Trip of Murray Lower Tumut No kv Transmission Line at Murray End Only on 18 November 2013

Power System Operating Incident Report Trip of Murray Lower Tumut No kv Transmission Line at Murray End Only on 18 November 2013 Power System Operating Incident Report Trip of Murray Lower Tumut No.66 0 kv Transmission PREPARED BY: AEMO Systems Capability DATE: 1 December 201 FINAL Version Release History VERSION DATE BY CHANGES

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

POWER SYSTEM OPERATING INCIDENT REPORT MULTIPLE CONTINGENCY EVENT IN NORTH WEST TASMANIA ON 6 APRIL 2012

POWER SYSTEM OPERATING INCIDENT REPORT MULTIPLE CONTINGENCY EVENT IN NORTH WEST TASMANIA ON 6 APRIL 2012 POWER SYSTEM OPERATING INCIDENT REPORT MULTIPLE CONTINGENCY EVENT IN NORT WEST TASMANIA ON 6 APRIL 2012 PREPARED BY: Systems Capability DATE: 28 September 2012 FINAL IN NORT WEST TASMANIA ON 6 APRIL 2012

More information

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012 POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012 PREPARED BY: System Performance and Commercial DATE: 7 March 2013 FINAL Disclaimer Purpose This

More information

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER 1 Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER Lisa Dangelmaier Hawaii Electric Light lisa.dangelmaier@hawaiielectriclight.com Hawai'i Electric Light System Overview

More information

Gateway South Transmission Project

Gateway South Transmission Project Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive

More information

Midway/Monument Area TTC Study

Midway/Monument Area TTC Study Midway/Monument Area TTC Study (includes the following lines: Midway Geesen 115 kv, Geesen Falcon 115 kv, Falcon Fuller 115 kv, Fuller Black Squirrel 115 kv, and Black Squirrel Monument 115 kv) Johnny

More information

ATTACHMENT - DFO STATEMENT OF NEED

ATTACHMENT - DFO STATEMENT OF NEED ATTACHMENT - DFO STATEMENT OF NEED Table of Contents Executive Summary... 3 1. Description of the Area... 5 1.1 Geographic Study Area... 5 1.2 Current System Configuration... 7 1.3 Distributed Generation...

More information

Net Metering Interconnection Requirements. Customer Generation Capacity Not Exceeding 100 kw. Date: Version: 1

Net Metering Interconnection Requirements. Customer Generation Capacity Not Exceeding 100 kw. Date: Version: 1 Net Metering Interconnection Requirements Customer Generation Capacity Not Exceeding 100 kw Date: 2017-07-01 Version: 1 Revision History Date Rev. Description July 01, 2017 1 Initial release Newfoundland

More information

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010 POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010 PREPARED BY: Electricity System Operations Planning and Performance FINAL Disclaimer (a) Purpose - This report

More information

Power System Operating Incident Report Trip of Red Cliffs Horsham and Red Cliffs-Wemen Kerang 220 kv transmission lines on 15 January 2014

Power System Operating Incident Report Trip of Red Cliffs Horsham and Red Cliffs-Wemen Kerang 220 kv transmission lines on 15 January 2014 Power System Operating Incident Report Trip of Red Cliffs Horsham and Red Cliffs-Wemen Kerang PREPARED BY: AEMO Systems Capability DATE: 19 May 2014 STATUS: FINAL CONTENTS 1 Introduction... 3 2 The Incident...

More information

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-157-FEAS-R2 Interconnection Feasibility Study Report GIP-157-FEAS-R2 System Interconnection Request #157 100.5 MW Wind Generating Facility Guysborough County (L-6515) 2009 09 14 Control Centre Operations Nova Scotia

More information

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016 New Transmission Line April 1, 2016 The enclosed information is proprietary to PSE&G and is provided solely for your use. It should not be copied, reproduced, or shared with others without PSE&G s prior

More information

ATTACHMENT Y STUDY REPORT

ATTACHMENT Y STUDY REPORT Attachment Y Study Edwards Unit 1: 90 MW Coal Retirement December 31, 2012 ATTACHMENT Y STUDY REPORT 7/5/2013 PUBLIC / EXECUTIVE SUMMARY MISO received an Attachment Y Notification of Potential Generation

More information

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company SYSTEM IMPACT RESTUDY H252W ERIS REPORT Prepared for: El Paso Electric Company Prepared by: Engineers, LLC 1526 Cole Boulevard Building 3, Suite 150 Lakewood, CO 80401 (303) 395-4018 FOREWORD This report

More information

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Connection Engineering Study Report for AUC Application: AESO Project # 1674 APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF B 220 KV BUSBAR AT GEORGE TOWN ON 27 NOVEMBER 2012.

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF B 220 KV BUSBAR AT GEORGE TOWN ON 27 NOVEMBER 2012. POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF B 220 KV BUSBAR AT PREPARED BY: System Performance & Commercial DATE: 1 March 2013 FINAL Disclaimer Purpose This report has been prepared by the Australian

More information

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION Presentation by Engr. O. C. Akamnnonu Chief Executive Officer, Ikeja Electricity Distribution Company AGENDA WORK THROUGH

More information

Net Metering Interconnection Requirements

Net Metering Interconnection Requirements Net Metering Interconnection Requirements Customer Generation Capacity Not Exceeding 100 kw Date: 2017-07-01 Version: 1 Revision History Date Rev. Description July 1, 2017 1 Initial Release Newfoundland

More information

MULTIPLE LINE OUTAGES IN THE MOUNT ENGLAND TARONG AREA IN QUEENSLAND, 13 FEBRUARY 2017

MULTIPLE LINE OUTAGES IN THE MOUNT ENGLAND TARONG AREA IN QUEENSLAND, 13 FEBRUARY 2017 MULTIPLE LINE OUTAGES IN THE MOUNT ENGLAND TARONG AREA IN QUEENSLAND, 13 FEBRUARY 2017 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES Published: 3 August 2017 INCIDENT CLASSIFICATIONS

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION PJM RTEP - Artificial Island Area FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION Part 1 Report REDACTED VERSION FirstEnergy Corp. Energy Delivery, Transmission Planning and Protection

More information

Small Generator Interconnection Program Interconnection Technical Requirements

Small Generator Interconnection Program Interconnection Technical Requirements General Program Information What is the purpose of the PGE Small Generator Interconnection Program? How do I initiate a distribution interconnection request for my project? The purpose of our Small Generator

More information

METRO NORTH TRANSMISSION STUDY ELECTRIC AND MAGNETIC FIELD PROFILES (VILLAGE OF ANMORE)

METRO NORTH TRANSMISSION STUDY ELECTRIC AND MAGNETIC FIELD PROFILES (VILLAGE OF ANMORE) METRO NORTH TRANSMISSION STUDY ELECTRIC AND MAGNETIC FIELD PROFILES (VILLAGE OF ANMORE) File: T2016-6004 METRO NORTH TRANSMISSION STUDY ELECTRIC AND MAGNETIC FIELD PROFILES METRO NORTH TRANSMISSION STUDY

More information

Reliability Analysis Update

Reliability Analysis Update Reliability Analysis Update Transmission Expansion Advisory Committee October 11, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects

More information

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning. A subsidiary of Pinnacle West Capital Corporation Q95 Vicksburg 69kV System Impact Study APS Contract No. 52246 By Arizona Public Service Company Transmission Planning December 1, 2010 Version 2.6 Final

More information

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028. Merchant Transmission Interconnection PJM Impact Study Report For PJM Merchant Transmission Request Queue Position X3-028 Breed 345 kv October/2014 System Impact Study Breed 345 kv Merchant Transmission

More information

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX 131-250 MW generator at new Western Refinary Substation System Planning Section April, 2005 TABLE OF CONTENT 1 EXECUTIVE SUMMARY

More information

POWER SYSTEM OPERATING INCIDENT REPORT LIGHTNING STRIKES IN TASMANIA AND PACIFIC ALUMINIUM POTLINE LOAD REDUCTIONS 21 MARCH 2013

POWER SYSTEM OPERATING INCIDENT REPORT LIGHTNING STRIKES IN TASMANIA AND PACIFIC ALUMINIUM POTLINE LOAD REDUCTIONS 21 MARCH 2013 POWER SYSTEM OPERATING INCIDENT REPORT LIGHTNING STRIKES IN TASMANIA AND PACIFIC ALUMINIUM POTLINE LOAD REDUCTIONS MARCH 03 PREPARED Y: Systems Capability DATE: 7 June 03 FINAL Disclaimer Purpose This

More information

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018 March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM-2017-11 May 2018 Prepared by: Public Service Company of New Mexico Foreword This report is prepared

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT INTERCONNECTION FACILITIES STUDY REPORT Interconnection Request No. TI-12-0217 8 MW Hydropower Generating Facility POI on the Dallas Creek to South Canal 115kV Line in SW Colorado FINAL REPORT February

More information

PUD ELECTRIC SYSTEM INTERCONNECTION

PUD ELECTRIC SYSTEM INTERCONNECTION APPENDIX A PROCEDURES & REQUIREMENTS for OKANOGAN PUD ELECTRIC SYSTEM INTERCONNECTION Version 4.0 December 2011 Version 4.0 12/28/2011 Page 1 of 15 TABLE OF CONTENTS DEFINITIONS 1.0 Introduction 2.0 Procedures

More information

The Energy Queensland Group Notice of no non-network options

The Energy Queensland Group Notice of no non-network options The Energy Queensland Group Notice of no non-network options 24 September 2018 MCE Mount Crosby East Establish new substation to replace Mount Crosby Substation (SSMTC) Page 1 of 1 DISCLAIMER While care

More information

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY Transmission Department Transmission Planning Duke Energy Progress TABLE OF CONTENTS I. SCOPE 3 II. TRANSMISSION PLANNING OBJECTIVES 3 III. TRANSMISSION

More information

The Long-Range Transmission Plan

The Long-Range Transmission Plan The Long-Range Transmission Plan 2015 2025 Matt Koenig Presentation to ESPWG / TPAS October 29 th, 2015 Long-Range Transmission Plan Driver of the Plan is to maintain local reliability 10-year planning

More information

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT Report No.: RP-160388-02-141-0001 CAA ID No. 2010-380 Rev. 01 Prepared by: AMEC Americas Limited Energy and Mining Division Power

More information

Vertabelo Academy. Terms of Service PLEASE READ ALL OF THE FOLLOWING TERMS OF SERVICE BEFORE USING THIS WEBSITE A. General Terms

Vertabelo Academy. Terms of Service PLEASE READ ALL OF THE FOLLOWING TERMS OF SERVICE BEFORE USING THIS WEBSITE A. General Terms Vertabelo Academy Terms of Service PLEASE READ ALL OF THE FOLLOWING TERMS OF SERVICE BEFORE USING THIS WEBSITE A. General Terms 1. These Terms of Service ("ToS") govern users access to and use of the Vertabelo

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

Craigieburn Employment Precinct North and English Street

Craigieburn Employment Precinct North and English Street Craigieburn Employment Precinct North and English Street METROPOLITAN PLANNING AUTHORITY Intersection Analyses 7 February 2014 Intersection Analyses Craigieburn Employment Precinct North and English Street

More information

Appendix A2: Technical Requirements for Distributed Generators > 10 kw to be Connected to Kitchener-Wilmot Hydro Inc. s Distribution System

Appendix A2: Technical Requirements for Distributed Generators > 10 kw to be Connected to Kitchener-Wilmot Hydro Inc. s Distribution System Appendix A2: Technical Requirements for Distributed Generators > 10 kw to be Connected to Kitchener-Wilmot Hydro Inc. s Distribution System A. INTRODUCTION This document outlines the technical requirements

More information

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV LINE El Paso Electric Company System Planning Department

More information

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008 NB Power Customer Service and Distribution June 2008 Prepared by: Steven Wilcox Revised by: Steven Wilcox TABLE OF CONTENTS 1.0 Introduction 4 2.0 NB Power Policy on Independent Power Production 4 3.0

More information

END USER TERMS OF USE

END USER TERMS OF USE END USER TERMS OF USE The following is the End Users Terms of Use as it currently appears in the Mobileye User Manual and Warranty information. This is here for your review and information; it is subject

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information