1 FERRY TERMINAL IMPROVEMENTS PROJECT City of Sausalito Planning Commission/Historic i i Landmarks Board 1 st Joint Hearing April 1, 2015
2 Golden Gate Ferry Provides Public Transportation Service Between Larkspur/Sausalito and San Francisco Larkspur Terminal 2 Sausalito Terminal San Francisco Terminal
3 3 Reason for Project Replace Aged Ferry Landing Structures to Keep them Structurally Sound Bring Passenger Access to Vessels Into Compliance with Current ADA Requirements
4 4 Secondary Benefits of Project Improve Operational Efficiencies Standardize Main Deck Loading of Vessels Better Management of Passenger and Bicycle Loading and Unloading Upgrade Emergency Preparedness
5 Local Vicinity Map 5
6 Existing 6
7 Existing Facilities 7 Aging g Boarding Ramps and Float Gangway and Aging g Pier
8 Existing Float 8
9 Sausalito Ferry Service Existing Boarding 9 Heavy Bicycle Use Limited Access due to Narrow Pier & Gangway Narrow Pier and dgangway Single Door Boarding and Disembarking
10 Improvements Designed to Meet ADA Requirements and Operational Needs 10 Gangway Boarding Apron Boarding Platform Fixed Landing Hydraulic Gangplank Concrete Float
11 ADA Ramp Requirements 11
12 Existing Gangway exceeds 1:12 Slope at Tides of -1.1 feet or Lower 12
13 New Gangway Meets ADA Guidelines 13 Gangway slope at low water 1 : 9.5 EXISTING Gangway slope at low water 1 : 12 PROPOSED
14 Operational Needs Current boarding and disembarking from vessels is through one door. Current ramp width from float to vessel is 4 feet. Ridership for fiscal year ending June 2014 was 793,192 passengers. Weekday average was 1,944 and weekend average was 2,758. Narrow facilities impact boarding and disembarking. 14 Vessels are being retrofitted for two 8 foot wide doors. Project will provide two 8 foot wide ramps from float to vessels. The two 8 foot ramps will connect to 16 foot wide boarding platform. New wider facilities will improve boarding and disembarking.
15 Vessel Door Locations 15
16 Golden Gate Ferry Fleet Golden Gate Ferry fleet consists of 3 Spaulding class vessels and 4 high speed catamaran vessels TypicallySpaulding class vessels are used between San Francisco and Sausalito Vessel Name Class Passenger Capacity Bicycle Capacity* M.S. Marin Spaulding , but up to 250 M.S. Sonoma Spaulding , but up to 250 M.S. San Francisco Spaulding 630** , but up to 250** M.V. Del Norte High Speed Catamaran , but up to 150 M.V. Mendocino High Speed Catamaran , but up to 60 MV M.V. Napa High Speed dct Catamaran , but up to 45 M.V. Golden Gate High Speed Catamaran , but up to 45 * The total number of bicycles allowed to board is at the discretion of the vessel Captain and the Terminal Supervisor and depends on: the scheduled turnaround time the number of passengers with and without bikes designated dbicycle stowage area **M.S. San Francisco is currently being retrofitted. New numbers TBD 16
17 Float Length Requirement 17
18 Level of Services Considerations Level of service for passengers walking taken as D/E. Taken as approximately 10 square feet per person. Average A flow of 20 passengers per foot per minute. Normal walking speed is restricted. This is consistent with observed conditions at facility. 18
19 Level of Service Considerations Level of service for passengers waiting to board taken as C/D. Represents 3 7 square feet per person. Space is provided so there is no contact with others. This is consistent with observed conditions at facility. 19
20 Disembarking with Existing Facilities at Projected Growth 20
21 Boarding with Existing Facilities at Projected Growth 21
22 Boarding with Existing Facilities at Projected Growth 22
23 Current Ferry Operations 23
24 Current Ferry Operations 24
25 Current Ferry Operations 25
26 Disembarking with 21-ft Wide Pier 26
27 Boarding with 21-ft Wide Pier 27
28 Project Background June 24, 2008 District provides introduction to project March 10, 2009 District presents update on project. June 1, 2010 District presents conceptual designs of project, including float, gangway and pier sizes. September 28, 2010 District presents update on project. May 3, 2011 District i t presents update dt on project and receives consensus from City Council to proceed with the improvements. September 17, 2012 District files a notice of intent to adopt a mitigated negative declaration (MND) for project. September 25, 2012 District presents update on project. October2, 2012 District holds public meeting on project in City Hall Chamber. October 18, 2012 District receives City s comments on the IS/MND environmental document. December 18, 2012 District files notice of determination. 28
29 Project Background 29 September 23, 2014 District presents update on project. December 2, 2014 District presents update on project. February 10, 2015 District attends City Council meeting where City approves a public review process of the project. March 11, 2014 District presents project to joint Planning Commission and Historic Landmarks Board meeting.
30 30 Sausalito Historic Ferry Uses Sausa o s o c e y Uses & Sausalito Historical District
31 Historic Ferry Use in Sausalito 31
32 Historic Ferry Use in Sausalito 32
33 GGBHTD Begins Ferry Service in
34 Ferry Facility between 1970 and
35 View from Yacht Club 35
36 City of Sausalito Historical District 36 Existing ferry facility is not a historic structure Existing landside pier and access pier are inside the Sausalito Historical District Existing gangway and float are outside the Sausalito Historical District Existing Landside Pier (approximate) Existing Float (approximate)
37 City of Sausalito Historical District - Arches 37
38 City of Sausalito Historical District - Arches 38
39 City of Sausalito Historical District - Arches Original proposed gate and gangway truss utilized arches 39 To reduce height, arches are no longer proposed
40 City of Sausalito Historical District - Colors 40 White and blue areobserved White and blue areconsidered nautical
41 City of Sausalito Historical District - Colors 41
42 City of Sausalito Historical District - Colors Original proposed facility utilized white on steel structure and blue accents 42 To blend into background, white is no longer proposed
43 43 Discussion of Proposed Design Elements
44 Summary of March 11, 2015 City of Sausalito Joint PC/HLB Study Session 44 PC s, HLB s, and Sausalito Residents comments of discretionary items were taken into consideration Reduce width of access pier Rd Reduce hiht height of gangway Grey or darker color is preferred by most Keep railing similar to existing Use simple gate Provide story pole equivalent demonstration
45 Access Pier Width feet wide This is a 16% reduction from the original 25 feet proposed
46 Gangway Height Gangway height was reduced 8 feet total height 5 feet 1 inch height from walking surface 46
47 Gangway Height 47 9 foot Gangway Truss Previous flat truss height 8 foot Gangway Truss Proposed flat truss height
48 Gangway Height 48 9 foot Gangway Truss Previous flat truss height 8 foot Gangway Truss Proposed flat truss height
49 Gangway Height 49 9 foot Gangway Truss Previous flat truss height 8 foot Gangway Truss Proposed flat truss height
50 Colors 50 A grey color or combination of grey and dark blue
51 Pier Railing 51 Vertical steel pickets Design matches existing i
52 Access Control Gate 52 Simple swing gate
53 Access Control Gate 53 Simple swing gate
54 Control Access Gate Location 54 New gate will be located at end of access pier to provide public access on pier Gate width is smallest with orientation as shown Gangway Existing Landside Pier Location of gate
55 55 Story Pole Equivalent Demonstration
56 Story Pole Equivalent Demonstration 56 Pole with caution tape flag SW edge of proposed float Poles with caution tape Width of proposed gangway truss Buoy SE edge of proposed float 21 feet wide N 53 feet wide Buoy NE edge of proposed float Buoy NW edge of proposed float 19 feet wide 150 feet long Green rope Width of proposed access pier Ariel View Photo by: Anthony Scopazzi Saturday, March 21, :00am 10:00am
57 Story Pole Equivalent Demonstration 57 Proposed railing height same as existing Green rope 21 foot wide access pier top of railing Buoy NW edge of proposed float Landside Pier to remain View from Existing Landside Pier Looking East Sunday, March 22, :00am 10:00am
58 Story Pole Equivalent Demonstration Pole with caution tape flag SW edge of proposed float Pole with caution tape Height and width of proposed gangway truss 58 Proposed railing height same as existing Buoy NE edge of proposed float Buoy NW edge of proposed float Green rope 21 foot wide access pier top of railing View from Existing Landside Pier Looking East Note: Top of poles to show gangway truss height are at 6-1 from top of walkway. Since demonstration, height has been lowered to 5-1 Saturday, March 21, :00am 10:00am
59 Story Pole Equivalent Demonstration 59 Proposed railing height same as existing Pole with caution tape Height and width of proposed gangway truss Pole with caution tape flag SW edge of proposed float View from South Looking North Note: Top of poles to show gangway truss height are at 6-1 from top of walkway. Since demonstration, height has been lowered to 5-1 Saturday, March 21, :00am 10:00am Buoy SE edge of proposed float
60 Story Pole Equivalent Demonstration 60 Flag NW edge of proposed float Flag NE edge of proposed float Pole with caution tape flag SW edge of proposed float Poles with caution tape and rope Width of proposed gangway truss Story Pole 6 1 Proposed 5 1 View from Existing Gangway Looking East Sunday, March 22, :00am 10:00am
61 61 Proposed Ferry Terminal Improvements
62 Elevations 62
63 Simple Swing Gate on 21 Foot Access Pier 63
64 Simple Swing Gate on 21 Foot Access Pier 64
65 Flat Truss 65
66 Flat Truss 66
67 View from Plaza Looking East 67
68 View from Plaza Looking East 68
69 View from Yacht Club Looking South 69
70 View from Yacht Club Looking South 70
71 View from South of Plaza Looking North 71
72 View from South of Plaza Looking North 72
73 Transformer Location 73 Approximate dimensions
74 Option 1 Relocate Ticket Vending Machines 74
75 Option 1 Relocate Ticket Vending Machines 75 Location Alternative 1
76 Option 1 Relocate Ticket Vending Machines 76 Location Alternative 2
77 Option 2 Relocate City of Sausalito Newsrack 77
78 Proposed Ferry Facility Improvements 78
79 FERRY TERMINAL IMPROVEMENTS PROJECT City of Sausalito Planning Commission/Historic i i Landmarks Board 1 st Joint Hearing April 1, 2015
80 Proposed Facility Lighting g 80 Existing Proposed Top of Guardrail LED Lighting Overhead LED Lighting
81 Lease between City and District 81
82 Lease between City and District 82
83 District Lease Area 83
QUESTIONS AND RESPONSES FROM THE MARCH 11, 2015 PLANNING COMMISSION AND HISTORIC LANDMARKS BOARD JOINT MEETING
QUESTIONS AND RESPONSES FROM THE MARCH 11, 2015 PLANNING COMMISSION AND HISTORIC LANDMARKS QUESTIONS FROM THE PUBLIC (NOS. 1-41) PGS 2-9 QUESTIONS FROM THE PLANNING COMMISSION AND HISTORIC LANDMARKS BOARD
More informationSAUSALITO FERRY TERMINAL REPLACEMENT PROJECT. Item 5A- PPT Presentation Page 1 of 23
SAUSALITO FERRY TERMINAL REPLACEMENT PROJECT OCTOBER 10, 2017 CITY OF SAUSALITO CITY COUNCIL MEETING Page 1 of 23 PROPOSED PROJECT SUMMARY EXISTING PROPOSED (ACCESS PIER WITHOUT BELVEDERES) Gate Location
More informationLilly Whalen. Sausalito City Council, If we are headed for a similar monster terminal, I urge you to oppose it.
Lilly Whalen From: Sent: To: Subject: Attachments: Vernel Larner Friday, September 22, 2017 4:56 PM City Council Fwd: South San Francisco's WETA Passenger Ferry Terminal Site Visit
More informationSTAFF REPORT SAUSALITO CITY COUNCIL
STAFF REPORT SAUSALITO CITY COUNCIL MEETING DATE: AGENDA TITLE: LEAD DEPARTMENT: March 27, 2018 Report on the National Park Service's Proposal for New Ferry Service from Pier 31 ½ in San Francisco to Fort
More informationTable Station Elements
The overall layout of the station in the Preferred Alternative (Modified Alternative 2) is described in Table 7.5-1. Table 7.5-1 Station Elements Ground Level Mezzanine Level Platform Level Existing/Upgraded
More informationTerminal Alternatives
Chapter 5 Terminal Alternatives Missoula International Airport Master Plan Update Prepared for Missoula County Airport Authority OCTOBER 2008 Contents Section Page 5 Terminal Alternatives...5-1 5.1 Terminal
More informationSTAFF REPORT. To: Planning Commission Meeting date: April 12, 2017 Item: UN Prepared by: Robert Eastman
# 5 ) UN-15-17 LA SIERRA AUTO SALES SPECIAL USE PERMIT VEHICLE SALES PUBLIC HEARING STAFF REPORT To: Planning Commission Meeting date: April 12, 2017 Item: UN-15-17 Prepared by: Robert Eastman GENERAL
More informationMobility Management: Caltrain
Mobility Management: Caltrain Community Relations Committee October 4, 2017 Agenda Item 7 Presentation Outline Operating Statistics Ridership On-time Performance Fleet Reliability Capital Program Review
More informationDecision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82
Decision 21447-D01-2016 August 23, 2016 Decision 21447-D01-2016 Proceeding 21447 Application 21447-A001 August 23, 2016 Published by the: Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary,
More informationCity of San Juan Capistrano Agenda Report
12/16/214 82 City of San Juan Capistrano Agenda Report TO: FROM: DATE: SUBJECT: Karen P. Brust, City Manag4(?1-- Keith Van Der Maaten, P.E., Public Works and Utilities Directo Prepared by: George Alvarez,
More informationANDERSON PROPERTY SITE ANALYSIS
ANDERSON PROPERTY SITE ANALYSIS Introduction The Montgomery County Department of Transportation (MCDOT) initiated a feasibility study in the fall of 2012 to evaluate the need for transit service expansion
More informationSAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY
THIS PRINT COVERS CALENDAR ITEM NO.: 10.3 DIVISION: Transit Services BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Approving traffic and parking modifications to implement a new bus
More informationSAN RAFAEL CITY COUNCIL AGENDA REPORT
Agenda Item No: 8.b Meeting Date: December 19, 2016 Department: PUBLIC WORKS SAN RAFAEL CITY COUNCIL AGENDA REPORT Prepared by: Bill Guerin, Public Works Director City Manager Approval: File No.: 18.01.79
More informationARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of November 18, 2017
ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of November 18, 2017 DATE: November 7, 2017 SUBJECT: Six-Month Extension of car2go Demonstration Study Agreement C. M. RECOMMENDATIONS: 1. Authorize
More informationRight-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001
Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001 Revised April 5, 2005 Revised January 27, 2006 Prepared by: Steve Collin, Engineer 2.5 Revised by Douglas
More informationMOTION NO. M Preferred Alternative for the Puyallup Station Access Improvement Project
MOTION NO. M2014 64 Preferred Alternative for the Puyallup Station Access Improvement Project MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 8/14/14 8/28/14 Recommendation
More informationRavenswood Avenue Railroad Crossing Project City Council Meeting Study Session April 4, Ravenswood Avenue Railroad Crossing Project
Ravenswood Avenue Railroad Crossing Project City Council Meeting Study Session April 4, 2017 1 Presentation Outline Project Background Review Current Alternatives City Council Requests Council Direction
More informationCITY COUNCIL STUDY SESSION UPDATE ON SMART. January 19, 2017 CITY OF SAN RAFAEL
CITY COUNCIL STUDY SESSION UPDATE ON SMART January 19, 2017 CITY OF SAN RAFAEL SONOMA MARIN AREA RAIL TRANSIT UPDATE OUTLINE BACKGROUND INITIAL OPERATION SYSTEM (IOS1) CIVIC CENTER AREA LARKSPUR EXTENSION
More informationWelcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date,
Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, is now called the Valley Line. We are here to present
More information2019 New Transit Service Plan
Agenda Item 7.2 2019 New Transit Service Plan Draft Proposal VTA Board of Directors January 2019 Background: Next Network Plan and Today s Plan Early 2016 Transit Choices report and the ridership-coverage
More informationSAN FRANCISCO TO SAN JOSE PROJECT SECTION
SAN FRANCISCO TO SAN JOSE PROJECT SECTION Local Policy Maker Group Thursday, February 23, 2017 San Carlos, California INTRODUCTIONS 1 CALIFORNIA HIGH-SPEED RAIL PROGRAM UPDATE Jeff Morales, CEO HIGH-SPEED
More informationCITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan
Date: Wednesday, June 24, 2014 Location: Ann Arbor District Library Attendees: 40 citizen attendees Ann Arbor Station Environmental Review Public Meeting Meeting Notes Meeting #2 The second public meeting
More informationSAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY
THIS PRINT COVERS CALENDAR ITEM NO. : 10.3 DIVISION: Sustainable Streets BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Authorizing the Department of Public Works (DPW) to award DPW Contract
More informationElectric Multiple Unit Procurement Update
Electric Multiple Unit Procurement Update Public Meetings September 2014 Caltrain Today 2 1 Key Facts Diesel commuter rail system SF to SJ area 77 mile corridor, 32 stations 92 trains / weekday Ridership:
More informationMiddle Harbor Project: Draft EIS/EIR LA Chamber of Commerce June 26, 2008, APM Maersk HQ Pier 400
Middle Harbor Project: Draft EIS/EIR LA Chamber of Commerce June 26, 2008, APM Maersk HQ Pier 400 Richard D. Cameron Director of Environmental Planning, Port of Long Beach CEQA/NEPA Process Summary The
More informationTransportation Sustainability Program
Transportation Sustainability Program Photo: Sergio Ruiz San Francisco is a popular place to work, live and visit, straining the existing transportation network Roads and transit vehicles nearing capacity
More informationRevised Strategy for Downtown Parking
Revised Strategy for Downtown Parking December 4, 2017 Council Workshop Presented by Jennifer McCoy, P.E., City Traffic Engineer City-Owned Parking Today 3,500 metered parking spaces Parking meters charge
More informationKendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study
Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What
More informationAuthorize Public Hearing To Discontinue Non- Regional Metrobus Routes 2W, 12A-S and 20F-Y in Fairfax County
Customer Services, Operations, and Safety Committee Board Action Item IV-A October 2, 2008 Authorize Public Hearing To Discontinue Non- Regional Metrobus Routes 2W, 12A-S and 20F-Y in Fairfax County Washington
More informationCommunity Open Houses November 29 December 7, 2017
Community Open Houses November 29 December 7, 2017 1 Community Open House Agenda 6:00 PM Open House 6:30-7:30 PM Presentation and Q&A 7:30-8:00 PM Open House Resumes after the presentation and Q&A Thank
More informationTechnical Question and Answer No November 2017 Rachel Rowe, Skagit County Public Works FROM: Will Moon, Glosten JOB/FILE NO
GUEMES ISLAND FERRY REPLACEMENT TO: Rachel Rowe, Skagit County Public Works FROM: Will Moon, Glosten JOB/FILE NO. 17097.01 Specific questions raised by the Ferry Committee Question 1 Will reliability of
More informationGlengowrie Depot Upgrade. Nick Marciano, Manager Tram Maintenance, PTS
Glengowrie Depot Upgrade Nick Marciano, Manager Tram Maintenance, PTS Introduction Nick Marciano Took up role of Tram Maintenance Manager in June 2009. Prior to that: 35 years in manufacturing starting
More informationTransportation Sustainability Program
Transportation Sustainability Program Photo: Sergio Ruiz San Francisco 2016 Roads and public transit nearing capacity Increase in cycling and walking despite less than ideal conditions 2 San Francisco
More informationDecision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016
Decision 21481-D01-2016 October 18, 2016 Alberta Utilities Commission Decision 21481-D01-2016 Proceeding 21481 Application 21481-A001 October 18, 2016 Published by the: Alberta Utilities Commission Fifth
More information4 COSTS AND OPERATIONS
4 COSTS AND OPERATIONS 4.1 INTRODUCTION This chapter summarizes the estimated capital and operations and maintenance (O&M) costs for the Modal and High-Speed Train (HST) Alternatives evaluated in this
More informationElectric Multiple Unit Procurement Update
Electric Multiple Unit Procurement Update Board of Directors August 7, 2014 Context* * The proposed project is not yet approved pending environmental clearance. 2 1 Status April 2014 - JPB update on EMU
More informationHonorable Mayor and Members of the City Council. Disabled Placard Parking Policy for City-Owned Garages
Office of the City Manager CONSENT CALENDAR April 2, 2013 To: From: Honorable Mayor and Members of the City Council Christine Daniel, City Manager Submitted by: Andrew Clough, Director, Public Works Subject:
More informationDowntown Parking/Wayfinding Study. Review of Recommendations to City Council: January 16, 2018
Downtown Parking/Wayfinding Study Review of Recommendations to City Council: January 16, 2018 Tonight s Focus Objectives & Timeline Recap Study Findings Present Staff Recommendations 2018 Action items
More information41 One Gateway Plaza Los Angeles, CA
41 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.20C metro. net SYSTEM SAFETY AND OPERATIONS COMMITTEE FEBRUARY 21, 2013 EXECUTIVE MANAGEMENT COMMITTEE FEBRUARY 21, 2013 SUBJECT: ACTION: ADMINISTRATIVE
More informationUS 50/SOUTH SHORE COMMUNITY REVITALIZATION PROJECT
US 50/SOUTH SHORE COMMUNITY REVITALIZATION PROJECT April 25, 2012 Tahoe Transportation District (TTD) Tahoe Transportation District (TTD) established 1980 as Bi-State Agency TTD Goals Implement Transportation
More informationTransportation Sustainability Program
Transportation Sustainability Program Photo: Sergio Ruiz A Comprehensive Approach to Growing Sustainably Public Investment and Strategies for Existing and Future Population Underway Transit capital and
More informationTransit Glossary and Terms Glosario de Términos de Tránsito
On the Go? Go Mobile! Visit the Golden Gate mobile friendly Web site. Fares, Schedules & Maps Trip Planner Bus Schedules Ferry Schedules Fares Bridge Tolls & Information Maps Transit Route Locator FasTrak
More informationCITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM
CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM Date: April 11, 2018 To: The Honorable City Council c/o City Clerk, Room 395, City Hall Attention: Honorable Mike Bonin, Chair, Transportation Committee
More informationPeninsula Corridor Electrification Project Cost / Schedule Update
Peninsula Corridor Electrification Project Cost / Schedule Update LPMG Meeting November 20, 2014 Context Caltrain/high-speed rail blended system - Primarily 2 track system - Minimize impacts - Shared system
More informationExhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup
Exhibit A Sound Transit Board Resolution R2016-07 Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Access Improvement Project. RESOLUTION NO. R2016-07 Selecting
More informationWelcome to Open House #5 Scarborough Rapid Transit
Welcome to Open House #5 Scarborough Rapid Transit Welcome to the Scarborough Rapid Transit (SRT) Conversion and Extension Study, including Kennedy Station improvements. Tonight s event provides details
More informationDecember Individual Quality Review Calendar FY 18 FY 19. Mon Tues Wed Thu Fri Sat. Sun METRO1 SAMPLE TO REGION
December 2017 Sun Mon Tues Wed Thu Fri Sat 1 2 3 4 5 6 7 8 9 METRO1 SAMPLE TO REGION 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Christmas METRO1 Schedules issued to IQR Updated 1/5/18
More informationCTA Capital Construction Update May 17, 2007
Block 37 Signals Project Brown Line Howard CTA Capital Construction Update May 17, 2007 1 Capital Construction Update Agenda Howard Station Reconstruction Brown Line Capacity Expansion Project Block 37
More informationPAPER FOR AREMA 2006 ANNUAL CONFERENCE LOS ANGELES UNION STATION RUN-THROUGH TRACKS UNION STATION TERMINAL IMPROVEMENTS. Paul Mak, PE, SE HDR Inc
PAPER FOR AREMA 2006 ANNUAL CONFERENCE LOS ANGELES UNION STATION RUN-THROUGH TRACKS UNION STATION TERMINAL IMPROVEMENTS Paul Mak, PE, SE HDR Inc 801 S. Grand Ave. Suite 500, Los Angeles, CA 90017. Tel
More informationStaff Contact: Carlos de Melo, Community Development Director, (650)
Meeting Date: April 10, 2018 STAFF REPORT Agency: City of Belmont Staff Contact: Carlos de Melo, Community Development Director, (650) 595-7440 cdemelo@belmont.gov Agenda Title: Agenda Action(s): Caltrain
More informationWest Santa Ana Branch Transit Corridor. Informational Briefing Gateway Cities Service Council April 13, 2017
West Santa Ana Branch Transit Corridor Informational Briefing Gateway Cities Service Council April 13, 2017 Project Study Area 98 square miles 20 individual cities plus unincorporated LA County 1.2 million
More informationProject Location. Purpose and Need for Action. File Code: 1950 Date: September 14, Dear Interested Party,
United States Department of Agriculture Forest Service Idaho Panhandle National Forests Sandpoint Ranger District 1602 Ontario Street Sandpoint, ID 83864 File Code: 1950 Date: September 14, 2016 Dear Interested
More informationSPECIAL LEGISLATIVE COMMISSION TO STUDY POTENTIAL ECONOMIC OPPORTUNITIES IN THE DEVELOPMENT OF PORT FACILITIES IN THE STATE OF RHODE ISLAND
Quonset Update April 7, 2011 SPECIAL LEGISLATIVE COMMISSION TO STUDY POTENTIAL ECONOMIC OPPORTUNITIES IN THE DEVELOPMENT OF PORT FACILITIES IN THE STATE OF RHODE ISLAND QUONSET BUSINESS PARK 8,800 Jobs
More informationCITY OF SASKATOON ADMINISTRATIVE POLICY
ORIGIN/AUTHORITY Administration and Finance Committee Report No. 13-2007; and Item 8.4.2 of Standing Policy Committee on Environment, Utilities and Corporate Services Report June 22, 2015; and Leadership
More informationAlberta Electric System Operator Saleski Transmission Project Needs Identification Document
Decision 2013-127 Alberta Electric System Operator Saleski Transmission Project Needs Identification Document ATCO Electric Ltd. Saleski 901S Substation and 144-kV Transmission Line 7L142 Facility Application
More informationNew York City Department of Transportation. Notice of Adoption
New York City Department of Transportation Notice of Adoption NOTICE OF ADOPTION relating to horse drawn cab boarding areas in Chapter 4 of Title 34 of the Rules of the City of New York. NOTICE IS HEREBY
More informationEXCEPTION TO STANDARDS REPORT
EXCEPTION TO STANDARDS REPORT PROJECT DESCRIPTION AND NEED The project is located in Section 6, Township 23 North, Range 9 East and Section 31 Township 24 North, Range 9 East, in the Town of Stockton,
More informationCLACKAMAS RIVER WATER FEES AND CHARGES
FEES AND CHARGES : July 1, 2014 FEES AND CHARGES This Fees and Charges document consolidates all District fees and charges, adopted by Commission resolutions, for the various services provided by the district.
More informationAgenda Cover Memorandum
Agenda Cover Memorandum Meeting Date: August 21, 2017 Meeting Type: COW (Committee of the Whole) City Council Budget Workshop Item Title: Final approval of an Ordinance amending various sections of Article
More informationClearlake Road (State Road 501) Project Development & Environment (PD&E) Study
Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study FROM MICHIGAN AVENUE TO INDUSTRY ROAD BREVARD COUNTY, FLORIDA Financial Project ID No: 433605-1-22-01 Federal Aid Project
More informationCapital Metro Downtown Multimodal Station
Capital Metro Downtown Multimodal Station Stakeholder Briefing December 11, 2015 Agenda 1 2 3 4 5 Project Summary Downtown Station Concept Evaluation 4 th Street Traffic Analysis 5 th Street Traffic Analysis
More informationClick to edit Master title style
Nelson/Nygaard Consulting Associates SERVICE IMPROVEMENT STRATEGIES September 22, 2015 1 PROJECT OVERVIEW & WORK TO DATE 1. Extensive stakeholder involvement Throughout 2. System and market assessment
More informationJune 9, The County Board of Arlington, Virginia. Ron Carlee, County Manager
June 9, 2003 TO: FROM: SUBJECT: The County Board of Arlington, Virginia Ron Carlee, County Manager Amendments to the Arlington County Code 14.2-34 to limit parking of commercial vehicles, motor homes,
More informationSTAFF REPORT # CHANGE OF ZONING
STAFF REPORT #17-2000-0007 CHANGE OF ZONING PLANNING COMMISSION MEETING DATE: November 16, 2017 (Applicant Provided Materials / Traffic Study = Blue) 1. APPLICATION: A public hearing for an application
More informationDockless Micromobility Regulatory Framework
Dockless Micromobility Regulatory Framework Transportation and Municipal Infrastructure Committee March 19, 2019 Dockless Micromobility was last discussed at the February 5 th committee meeting TMI committee
More informationLacey Gateway Residential Phase 1
Lacey Gateway Residential Phase Transportation Impact Study April 23, 203 Prepared for: Gateway 850 LLC 5 Lake Bellevue Drive Suite 02 Bellevue, WA 98005 Prepared by: TENW Transportation Engineering West
More informationKettle River Transmission Project
April 2012 Why are you receiving this project information package? New transmission facilities are needed in the Fort McMurray area. ATCO Electric has been directed by the Alberta Electric System Operator
More informationBus Stop Optimization Study
Bus Stop Optimization Study Executive Summary February 2015 Prepared by: Passero Associates 242 West Main Street, Suite 100 Rochester, NY 14614 Office: 585 325 1000 Fax: 585 325 1691 In association with:
More informationBORAL CONCRETE GLENORIE
BORAL CONCRETE GLENORIE > Glenorie Progress Association meeting 14 March 2018 Glenorie RSL Club Glenorie A recap of our last discussion (Oct 2017)... Who are we? Boral Concrete (NSW/ACT) is part of the
More informationBohn to Kettle River Transmission Project
April 2012 Why are you receiving this project information package? New transmission facilities are needed in the Fort McMurray area. ATCO Electric has been directed by the Alberta Electric System Operator
More informationOverview of Transit Funding and Planning in the PACTS Region
Overview of Transit Funding and Planning in the PACTS Region Presentation to PACTS Transit Committee and Federal Transit Administration Representatives February 8, 2018 Transit Agencies Agency Communities
More informationADA CHANGES TO METRO'S BUS SERVICE
Los Angeles County Metropolitan Transportation Authority ADA CHANGES TO METRO'S BUS SERVICE PRESENTED TO: TECHNICAL ADVISORY COMMITTEE March 2, 2011 1 Daily Metro: Operates over 2,600 buses 191 different
More informationREPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT
REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT ON April 3, 2014 ZONING BYLAW AMENDMENT APPLICATION NO. ZBA00079 CHANGES TO THE ZONING AND BUSINESS LICENCE
More informationPublic Works and Infrastructure Committee. p:/2015/clusterb/tra/northyork/pw15086
PW9.10 STAFF REPORT ACTION REQUIRED Car-Share Parking in Permit Parking Areas Date: October 22, 2015 To: From: Wards: Reference Number: Public Works and Infrastructure Committee General Manager, Transportation
More informationIncrease Rail Service to the Mid City Green Line Stations
Washington Metropolitan Area Transit Authority Increase Rail Service to the Mid City Green Line Stations P D E C Presented to the Board of Directors: Planning and Development Committee by Planning, Development,
More informationCTA Blue Line Study Area
CTA Blue Line Study Area HISTORY OF THE CTA BLUE LINE / I-290 SYSTEM Blue Line / I-290 infrastructure is 55 years old First integrated transit / highway facility in the U.S. PROJECT STUDY AREA EXISTING
More informationResponse to Surabaya incident
Response to Surabaya incident 13 th April 2010 Flight CX 780 from Surabaya to Hong Kong with 320 crew and pax Experienced engine thrust control problems in flight Made a high speed landing in HKG, but
More informationNote: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars.
Sound Transit Phase 2 South Corridor LRT Design Report: SR 99 and I-5 Alignment Scenarios (S 200 th Street to Tacoma Dome Station) Tacoma Link Extension to West Tacoma Prepared for: Sound Transit Prepared
More informationI-820 (East) Project Description. Fort Worth District. Reconstruct Southern I-820/SH 121 Interchange
I-820 (East) Project Description Fort Worth District Reconstruct Southern I-820/SH 121 Interchange I-820 from approximately 2,000 feet north of Pipeline Road/Glenview Drive to approximately 3,200 feet
More informationW&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237)
W&OD TRAIL BRIDGE OVER LEE HIGHWAY A COMPONENT OF THE I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) October 11, 2018 Bill Cuttler, PE
More informationStudy Purpose 2 Densely populated neighborhoods and increased rates of car ownership over the years have led to serious parking issues in the Canal, S
July 12, 2017 Study Purpose 2 Densely populated neighborhoods and increased rates of car ownership over the years have led to serious parking issues in the Canal, Spinnaker, and Baypoint neighborhoods.
More informationMississauga Bus Rapid Transit Preliminary Design Project
Mississauga Bus Rapid Transit Preliminary Design Project PUBLIC INFORMATION CENTRE OCTOBER 2008 WELCOME The Mississauga Bus Rapid Transit (BRT) Project Thank you for attending this Public Information Centre.
More informationMEMO VIA . Ms. Amy Roth DPS Director, City of Three Rivers. To:
MEMO To: Ms. Amy Roth DPS Director, City of Three Rivers VIA EMAIL From: Michael J. Labadie, PE Julie M. Kroll, PE, PTOE Brandon Hayes, PE, P.Eng. Fleis & VandenBrink Date: January 5, 2017 Re: Proposed
More informationCity of South St. Paul Planning Commission Agenda
Chair: Stephanie Yendell Vice-Chair: Ruth Krueger Commissioners: Isaac Contreras Angela DesMarais Tim Felton Justin Humenik Jason Pachl City of South St. Paul Planning Commission Agenda Wednesday, July
More informationRIDERSHIP TRENDS. March 2017
RIDERSHIP TRENDS March 2017 Prepared by the Division of Strategic Capital Planning May 2017 Table of Contents Executive Summary...1 Ridership...3 Estimated Passenger Trips by Line...3 Estimated Passenger
More informationBalancing the Transportation Needs of a Growing City
Balancing the Transportation Needs of a Growing City FY 2019 and FY 2020 Capital Budget SFMTA Board Meeting Ed Reiskin, Director of Transportation April 3, 2018 1 FY 2019-23 Capital Improvement Program
More informationSAN RAFAEL CITY COUNCIL AGENDA REPORT
Agenda Item No: 5.a Meeting Date: November 20, 2017 Department: Public Works SAN RAFAEL CITY COUNCIL AGENDA REPORT Prepared by: Bill Guerin, Director of Public Works TOPIC: IMPLEMENTATION OF PARKING TIME
More informationCity-wide LED Street Light Conversion Program
City-wide LED Street Light Conversion Program Arts & Innovation Board of Public Utilities July 25, 2016 Project Description Utility 2.0 Multi-phase implementation of city-wide street light conversion program
More informationSAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY
THIS PRINT COVERS CALENDAR ITEM NO. : 10.5 SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY DIVISION: Capital Programs & Construction BRIEF DESCRIPTION: Awarding San Francisco Municipal Transportation Agency
More informationSCAN Land Use and Transportation Committee Report June 10, 2015
DRAFT DRAFT DRAFT Exhibit A to SCAN Minutes - June 10, 2015 SCAN Land Use and Transportation Committee Report June 10, 2015 Gaiety Hollow In April the Committee provided testimony in support of the Lord
More informationEXECUTIVE SUMMARY. Introduction
EXECUTIVE SUMMARY Introduction The purpose of this study is to ensure that the Village, in cooperation and coordination with the Downtown Management Corporation (DMC), is using best practices as they plan
More informationTaxis and Accessible Services Division Medallion Reform Background May 1, 2018
Introduction: Taxis and Accessible Services Division Medallion Reform Background May 1, 2018 SFMTA s Taxis and Accessible Services Division is responsible for the regulation of the private businesses that
More information1 Downtown LRT Connector: Draft Concept
Downtown LRT Connector: Draft Concept Plan November 2010 We re moving forward. Get involved. On June 21, 2010, City Council approved a street-level downtown LRT route, including a connector for the future
More informationCITY OF OAKLAND INTRODUCTION
CITY OF OAKLAND CITY HALL ONE FRANK OGAWA PLAZA 3RD FLOOR OAKLAND CA 94612 City Administrator s ADA Programs Division (510) 238-4754 TDD: (510) 238-2007 : January 4, To: Mayor s Commission on Persons with
More informationSWLRT Business Advisory Committee. October 10, 2012
SWLRT Business Advisory Committee October 10, 2012 2 Today s Topics Approval of Meeting Minutes SWLRT 101 LRT 101 Guides to Commenting on the DEIS Future Topics of Interest Member/Committee Reports Public
More informationCLACKAMAS RIVER WATER FEES AND CHARGES
FEES AND CHARGES : July 1, 2015 FEES AND CHARGES This Fees and Charges document consolidates all District fees and charges, adopted by Commission resolutions, for the various services provided by the district.
More informationMr. Leif Dormsjo Director, District Department of Transportation 55 M Street, SE Washington, DC July 10, Dear Director Dormsjo,
Adams Morgan BID Capitol Hill BID Capitol Riverfront BID Coalition for Smarter Growth Destination DC Downtown BID Events DC Federal City Council Georgetown BID Golden Triangle BID Greater Greater Washington
More informationPAG Environmental Planning Advisory Committee Sun Link Streetcar Update May 1, 2015
PAG Environmental Planning Advisory Committee Sun Link Streetcar Update May 1, 2015 Project Facts 4-mile route, 23 stops 8 made in USA modern streetcars All electric and green Voter-approved project Connects
More informationHonorable Mayor and Members of the City Council. Parking Policies and Fee Schedule Adjustments for City-Owned Garages
Office of the City Manager To: From: Honorable Mayor and Members of the City Council Christine Daniel, Interim City Manager Submitted by: Andrew Clough, Director, Public Works Subject: Parking Policies
More informationPublic Information Workshop
Public Information Workshop Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 29, 2018 Welcome to the Public Information Workshop for Harborview Road Project Development and Environment (PD&E)
More information