Alternative Delivery as a Form of Risk Mitigation
|
|
- Maud Small
- 5 years ago
- Views:
Transcription
1 Alternative Delivery as a Form of Risk Mitigation Erika P. Moonin, P.E. Lake Mead Intake No. 3 Access Shaft Low feet Lake deep Level Pumping Station November 29, 2017
2 Outline Project Background - Lake Mead Intake No. 3 Risk Mitigation Benefits using Alternative Delivery Highlights on the Challenges during Construction Closing/Questions Lake Mead Intake No. 3 Low Lake Level Pumping Station
3 The Situation Drought in the Colorado River basin Colorado River supplies 90% of Las Vegas water 1983 Now!
4 Drought Impacts Intake No. 1 Out of Service Intake No. 2 Out of Service Spillway Gate - Elevation 1,224 Spillway gates Elevation 1,050 INTAKE NO. 1 INTAKE NO. 2 Elevation 1,000 Hoover Dam Saddle Island INTAKE NO. 3 Dead Pool - Elevation 897 Elevation 860
5 Lake Mead Intake No. 3 Project Project Approved: 2005 Construction: Estimated Cost: $1.4B Primary Project Purpose Preserve existing capacity Multiple Contracts: 01 Tunnel & Shafts Design-Build 07 L3PS UG & AG CMAR The Project Exist. Water Treatment Facility Pump Procurement Test Procurement CMAR Low Lake Level Pumping Station (L3PS) L3PS Discharge Aqueducts Design-Build Intake 3 Tunnel Saddle Island Design-Bid- Build Intake 3 Lake Mead Design-Bid- Build Intake No. 2 Connection Design-Bid- Build Intake No. 2 Connection & Modifications Exist. Intake 1 Exist. Intake 2 Completed Under Construction
6 Variable Geology: The Challenges Hard, fractured Metamorphic rock Weak sedimentary rock Volcanic rock High tunneling pressures 17 bar (250 psi) 15 bar actual Deep Water Intake Structure construction feet of water Intake Structure/TBM - docking within a 1-ft tolerance after 3 miles of tunneling Connection to existing operating intakes Precision drilling for well shafts State of the art submersible pumps
7 Risk Management Benefits Through Alternative Delivery Methods 1) Qualification Based Selection Competent Team Good Fit! 2) Early Contractor Involvement 3) Price and Schedule Advantage Innovative Approach This is why we chose alternative delivery! DBB Limitations
8 Risk Management Benefits 1) Qualification Based Selection 2 Step Short List and Final Proposals DB - RFPP & RFP w/ Presentations CMAR RFP & Presentations Technical Capabilities Risk Management Approach Key Staff - Culture and Team Interaction Build the Partnership during Tender Phase DB Proprietary Meetings GBR, Completion Date, etc
9 Risk Management Benefits Lake Mead Intake No. 3 Project 2) Early Contractor Involvement Underground High Risk! Design - Incorporates the Contractor s Means and Methods CMAR Jointly developed GBR 3) Price and Schedule Advantage Innovative Approach! Alternatives price and schedule comparison In all underground contracts jointly developed Rik Register Examples
10 DB Intake No. 3 Tunnel & Shafts Contract Access Shaft ~ 600 deep 30 finished interior diameter Construction Adit Connector Tunnel Tunnel Launch Chamber ~ 202 long, 47 W x 35 H Starter Tunnel ~ 450 long, 27 W x 25 H TBM tunnel 20 finished internal diameter ~ 15,000 long Intake Structure 96 high 16 diameter
11 Starter Tunnel Incursion of Unstable Ground Starter Tunnel - Flooded over 4 days Beginning of inflow Starter Tunnel June 28, 2010
12 Tunnel Reinstatement Work
13 New Alignment Area of Tunnel Inflows Tunnel Realignment January 2011
14 DB Completed Starter Tunnel Collaborative Approach to Design True Partnership Drill & Blast Starter Tunnel Completed July 2011
15 Tunnel Boring Machine (TBM) Hybrid Design Hard Rock Slurry Handle challenging ground conditions (water pressure of 17 bar, etc) Manufactured in Germany by Herrenknecht 23.5 outside diameter TBM Gantry Support Equipment 585 long, 1500 tons
16 TBM Cutter Head Underground TBM Excavation began December 27, 2011
17 3000+ feet at 13.5 bar Took a Toll on the Machine 2013 Mar 29
18 2013/2014 TBM Repairs 4 foot deep niche excavated in front of cutterhead Collaborative Approach to Design True Partnership
19 Intake Riser - Excavation Spring 2010
20 Intake Riser Construction & Transport DB proposed new location for Intake Structure Better Ground! DB proposed completely different approach to Intake Structure
21 Intake Riser Concrete Transport
22 February and March 2012 Total Tremie Concrete = 11,300 cy
23 10-ft.
24 Completed Intake Tunnel TBM Hole Thru - December 10, 2014 Operational September 26, 2015
25 Low Lake Level Pumping Station CMAR
26 L3PS Components Aboveground Well shafts - 34 steellined 6 ft diameter, 500 ft deep Access Shaft - 26 ft diameter 527 ft deep Riser Shaft Connector Tunnel - 20 ft long by 20 ft wide by 20 ft high D- shape Riser Shaft - 26 ft diameter 45 ft deep Forebay - 33 ft wide by 36 ft high by 377 ft long horseshoe-shaped Cavern Pumps 32 total, 22 low lift and 10 high lift pumps Underground
27 CMAR Underground Excavation - Well Shafts
28 L3PS Early Contractor Involvement Started 50% design UG co-located Reviewing plans/construction approach Attending weekly progress meetings Blind Bore vs. Raise Bore Workshop June 23, 2015 Risk Comparison Raised vs. Blind Bore Sub-Contractor Advertisement July 7, 2015 Short List Created July 27, 2015 Bids due (Drillers) Aug 20, 2015 Final Design Produced Sept 14, 2015 CMAR UG Package Award Sept 17, 2015 $209 M - $20 M Contingency Raise Bore Blind Bore
29 L3PS Early Contractor Involvement Blind bore was selected Mitigate ground risk better control of the ground Introduce other risk more difficult to comply with already tight drilling tolerance Worked together to develop innovative approach & Weighed the risks! Included coordination with pump manufacturers to determine allowable tolerance
30 CMAR Underground Excavation - Well Shafts
31 Test Pumps - Factory Performance Tests Indar pump Andritz pump Ebara pump
32 Underground Excavation - Shafts
33 Underground Excavation - Forebay
34 Underground Excavation - Forebay
35 SNWA Lake Mead Intake No. 3 Thank you MWH/Stantec & CH2M Barnard of Nevada & North American Drillers Vegas Tunnel Constructors Salini-Impregilo & SA Healy & ARUP Renda Pacific Parsons Questions?
Southern Nevada Water Authority Lake Mead Intake No. 3. The Last Straw?
Southern Nevada Water Authority Lake Mead Intake No. 3 The Last Straw? WESTCAS October 29, 2015 Underlying Intake No. 3 Factors Lake Mead is the primary water source for So. Nevada 90% of supply No guarantees
More informationLake Mead Intake No. 3
Lake Mead Intake No. 3 1 Lake Mead Intake No. 3 Total Project Scope INTAKE STRUCTURE PUMPING STATION ACCESS SHAFTS WATER TREATMENT FACILITY CONNECTOR TUNNEL INTAKE 1 INTAKE 2 C-2 Lake Mead Intake No. 3
More informationMulti Mode TBMs. OCT 4 6, 2015 Queens University Kingston, ON Canada Challenges and Innovations in Tunnelling
OCT 4 6, 2015 Queens University Kingston, ON Canada Challenges and Innovations in Tunnelling Multi Mode TBMs Shawn Hourtovenko Herrenknecht Tunnelling Systems Canada, Inc. October 5 th, 2015 Tunnelling
More informationCrenshaw/LAX Transit Corridor. Transit Coalition Meeting June 26, 2012
Transit Coalition Meeting June 26, 2012 Measure R Projects 8 ½ mile light rail line from Exposition/Crenshaw Blvds. to Metro Green Line s Aviation/LAX station Six stations with two optional stations carried
More informationMcNary Northshore Fishway Hydro Project. History & Lessons Learned
McNary Northshore Fishway Hydro Project History & Lessons Learned May 6, 2017 21 th Annual TECHNICAL SEMINAR Machines, Maintenance, and Management: Keeping Hydro Facilities Up and Running History & Lessons
More informationCity of Peachtree City
City of Peachtree City Lake Peachtree Spillway Replacement City Council Update September 15, 2016 Project Team Integrated Science & Engineering 1 Spillway Alternatives Analysis Spillway Alternatives Evaluated
More informationRolling Road (Route 638) Widening Project
Rolling Road (Route 638) Widening Project From: 0.369 Mile North of Fairfax County Parkway (Route 286) To: Old Keene Mill Road (Route 644) State Project No. 0638-029-156, P104, R204, C504; UPC 5559 Public
More informationHinkley Point C our approach to Health and Safety Iain Graham Head of Health & Safety
Hinkley Point C our approach to Health and Safety Iain Graham Head of Health & Safety 1 Where are we? Hinkley Point 2 EDF Energy s Nuclear New Build Projects February 2018 EDF Energy plc. All rights Reserved
More informationAppendix E Water Supply Modeling
Supply Modeling Modesto Irrigation District Treatment Plant Expansion Project Modeling I. Introduction The Modesto Irrigation District (MID) is situated adjacent to and north of the Tuolumne River. Over
More informationMobility Corridor Updates. Transit & Active Transportation Projects
Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate
More informationProject Description - 1 -
Project Description The Mother Ann Lee Hydroelectric Station is located at Lock and Dam 7 on the Kentucky River. This dam is part of a system of 14 lock and dams installed on the Kentucky River between
More informationAction Requested From AMWG
Action Requested From AMWG NONE, These Two Presentations Are For Information Transfer Only The information is derived from a multi-year synthesis research effort related to existing data on flow, sediment-transport
More informationExhibit 1. Background. Authorizing Legislation
Background Authorizing Legislation The Boulder Canyon Project Act (43 U.S.C. 617, et seq.), enacted by the U.S. Congress in 1928 (The 1928 Act), authorized the Secretary of the Interior to spend up to
More informationALBENI FALLS DAM AND LAKE PEND OREILLE
ALBENI FALLS DAM AND LAKE PEND OREILLE Fall Public Meeting 237 237 237 217 217 217 200 200 200 0 0 0 163 163 163 131 132 122 Aug. 7, 2017 255 255 255 239 65 53 80 119 27 252 174.59 83 36 118 110 135 120
More informationILLINOIS COMMERCE COMMISSION
ILLINOIS COMMERCE COMMISSION Public Notice of Successful Bidders and Average Prices Ameren Illinois Company and Commonwealth Edison Company Spring 2015 Procurement of Standard Energy Products April 1,
More informationNASHVILLE DISTRICT UPDATE TRVA ANNUAL CONFERENCE
NASHVILLE DISTRICT UPDATE TRVA ANNUAL CONFERENCE 1 LTC Cullen A. Jones, P.E., PMP Nashville District Commander Great Lakes and Ohio River Division US Army Corps of Engineers (USACE) 10 October 2017 The
More informationAll Annual Operating Plan Recipients
To: All Annual Operating Plan Recipients From: Lower Colorado Region Boulder Canyon Operations Office River Operations Group Daniel Bunk P.O. Box 647 Boulder City, NV 896-47 Phone: 72-293-83 The operation
More informationJurong Rock Caverns. 9 November Teo Tiong Yong JTC Corporation
Jurong Rock Caverns 9 November 2017 Teo Tiong Yong JTC Corporation Presentation of Jurong Rock Caverns (JRC) Development of JRC Project Details and mplementation Project Specifics Planning Project Management
More informationPeninsula Corridor Electrification Project (PCEP)
Peninsula Corridor Electrification Project (PCEP) Q2 Quarterly Update #13 October 1 December 31, 2017 JPB Board Meeting February 1, 2018 Agenda Item # 8b Electrification - Infrastructure Progression of
More informationBoston Scientific Energy Storage Project. Final Report (PUBLIC) November 2016
Boston Scientific Energy Storage Project Final Report (PUBLIC) November 2016 Executive Summary Kingspan ESB Limited applied for Energy RD&D funding for the Boston Scientific Solar PV Energy Storage Project
More informationChallenges With Underground High Voltage Transmission SCE Tehachapi Renewable Transmission Project First 500 kv Underground T/L in North America
Challenges With Underground High Voltage Transmission SCE Tehachapi Renewable Transmission Project First 500 kv Underground T/L in North America Noe Bargas, PE Supervising Senior Civil Engineer Southern
More informationDelivering the North West Rail Link. Colin Rudd, Deputy Project Director, NWRL David Polkinghorne, Design Team Leader, TJHD
Delivering the North West Rail Link Colin Rudd, Deputy Project Director, NWRL David Polkinghorne, Design Team Leader, TJHD November 26, 2013 The starting point Project overview $8.3 billion budget Open
More informationInventory Levels - All Prices. Inventory Levels - By Price Range
Inventory Levels - All Prices Idaho Falls Bonneville Total 3-Mar-17 152 108 260 2-Mar-18 109 78 187-28% Inventory Levels - By Price Range 3-Mar-17 2-Mar-18 0-100,000 41 6 100,001-125,000 19 8 125,001-150,000
More informationInventory Levels - All Prices. Inventory Levels - By Price Range
Inventory Levels - All Prices Idaho Falls Bonneville Total 7-Apr-17 154 111 265 6-Apr-18 113 91 204-23% Inventory Levels - By Price Range 7-Apr-17 6-Apr-18 0-100,000 36 10 100,001-125,000 13 9 125,001-150,000
More informationDallas CBD Second Light Rail Alignment (D2)
Dallas CBD Second Light Rail Alignment (D2) Subway Project Refinement Stakeholder Meeting December 7, 2016 Discussion Items Background Schedule Public/Stakeholder Involvement Comments/Questions from Audience
More informationTransit Project Delivery Status Report. Significant Issues
Item 1 Transit Project Delivery Status Report Significant Issues Presented By K.N. Murthy Executive Director Construction Committee 1 I-405 Sepulveda Pass Closure Construction Committee I-405 Sepulveda
More informationMetropolitan Water District of Salt Lake & Sandy CAPITAL PROJECT REPORT
Last Updated: April 5, 2018 Metropolitan Water District of Salt Lake & Sandy CAPITAL PROJECT REPORT April 2018 Routine Non-Capacity Improvement Projects Terminal Reservoir Replacement Project (TR003) see
More informationRequest for Statements of Qualification Gardnerville Station (Eagle Gas Station Redevelopment Project) 1395 Highway 395 N Gardnerville, NV
Gardnerville Station (Eagle Gas Station Redevelopment Project) 1395 Highway 395 N Gardnerville, NV Issued: Monday, Site Tour: Friday, January 30, 2015 at 10:00 a.m. Submittal Deadline: 5:00 p.m. on Friday,
More informationOTTAWA LIGHT RAIL TRANSIT PROJECT:
November, 2013 OTTAWA LIGHT RAIL TRANSIT PROJECT: TUNNEY S PASTURE TO BLAIR STATION BC CONSTRUCTION ROUNDTABLE / NOVEMBER 21, 2013 Agenda 1. Introduction to RTG 2. Proposal phase 3. Overview of Confederation
More informationA REPORT TO. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution. Telecontrol. System Planning
A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Electrical 4v ^c 0:01'1 S0^O c.. ^ '^ W E. G. PIERCY i^ x zoto/off/zq,.'ftrif4^#ft^^,' r Mechanical Civil Protection & Control Transmission &
More informationMETRO CNG Program Phase I Update. Customer Service Committee April 2014
METRO CNG Program Phase I Update Customer Service Committee April 2014 METRO CNG Program Background Bus purchase Short term solutions Long term plans Bus purchase options 2 METRO CNG Program April 2011
More informationInvitation for Bid Y PD
SWANA Residential Procurement Process Invitation for Bid Y15-144-PD Residential Solid Waste and Recycling Collections Services Term Contract Presentation Overview Background Invitation for Bid Bid Options
More informationAyeyarwady Integrated River basin Management Project (AIRBM)
Public Disclosure Authorized Public Disclosure Authorized I. GENERAL Ayeyarwady Integrated River basin Management Project (AIRBM) Procurement Plan 1. Project information a. Country/Borrower: Myanmar b.
More informationDrought Contingency Planning Process Workshop III
Photo courtesy of Bryan Flores floresfotography.com Drought Contingency Planning Process Workshop III November 14, 2018 Colorado River Drought Monitor and Snowpack Conditions 2018 2017 2 11-6-18 http://droughtmonitor.unl.edu/currentmap/statedroughtmonitor.aspx?west
More informationMOTION NO. M Purchase of Thirty-one Articulated Hybrid Diesel Expansion and Replacement Buses
MOTION NO. M2018-161 Purchase of Thirty-one Articulated Hybrid Diesel Expansion and Replacement Buses MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee PROPOSED ACTION
More informationBoard of Directors authorization is required for all goods and services contracts obligating TriMet to pay in excess of $500,000.
Date: April 11, 2012 To: From: Board of Directors Neil McFarlane Subject: RESOLUTION 12-04-30 OF THE TRI-COUNTY METROPOLITAN TRANSPORTATION DISTRICT OF OREGON (TRIMET) AUTHORIZING A CONTRACT WITH SIEMENS
More informationThis are the pictures from the Stockholders Report
Utah Securities Corporation Utah Light and Traction Company Financial and Physical Data As of March 31, 1915 This are the pictures from the Stockholders Report Page 32 Electrically Operated Hydraulic Dredge
More informationOverview of hydro electric dams and how they work Provide background on basic principles of hydropower and its history. Explain features that all
Overview of hydro electric dams and how they work Provide background on basic principles of hydropower and its history. Explain features that all hydro power dams have and compare the design of Revelstoke
More informationFasTracks News. RTD s Eagle P3 Transit Project Nears Halfway Mark to Opening Day EP3 will add three commuter rail lines to metro area in 2016
July 29, 2013 Welcome to Inside RTD FasTracks a monthly e- update to keep you informed about the progress of the Regional Transportation District's FasTracks program. FasTracks News RTD s Eagle P3 Transit
More informationJURONG ROCK CAVERNS. Workshop on the Optimisation of Shaft Design 4 June 2013
JURONG ROCK CAVERNS Development of Underground Rock Caverns for Hydrocarbon Storage on Jurong sland Workshop on the Optimisation of Shaft Design 4 June 2013 The Flow Journey of Jurong Rock Caverns Access
More informationWillamette River Transit Bridge. Portland - Milwaukie Light Rail Willamette River Bridge Willamette River Bridge Advisory Committee
Portland - Milwaukie Light Rail Willamette River Bridge Willamette River Bridge Advisory Committee 05.28.09 09 Bridge Type - Cost Vertical Clearance Bicycle Pedestrian Path Width Bridge Type - Cost WRBAC
More informationMaking Electricity since December Melody Collis Facilities Engineering Assistant Manager Toyota Motor Manufacturing Canada
Making Electricity since December 2015 Melody Collis Facilities Engineering Assistant Manager Toyota Motor Manufacturing Canada Cambridge 1 Company Culture Vision Woodstock TMMC's goal is to maintain a
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 27, 2012 SUBJECT: NOTICE OF AWARD PROCUREMENT AUTHORIZATION - ARTICULATED BUSES INFORMATION ITEM RECOMMENDATION
More informationEngineers Ireland Site Visit 23 rd March 2010
Whitegate Independent Power Plant CER Site Visit 24 th October 2008 CER Site Visit 24 th October 2008nt Engineers Ireland Site Visit 23 rd March 2010 Agenda Presentation of project and progress to date.
More informationRFP No. P3010 New l.i ght Rail Vehicles
rr Los Angeles County Metropolitan Transportation Authority RFP No. P3010 New l.i ght Rail Vehicles Source Selection Committee Award Recommendation Light Rail Transit Project Requirements end P30i 0 Delivery
More informationSTAFF REPORT ACTION REQUIRED
STAFF REPORT ACTION REQUIRED Procurement Authorization Amendment Purchase of 18 Forty Foot Low Floor Clean Diesel City Buses Date: July 29, 215 To: From: TTC Board Chief Executive Officer Summary This
More informationPeninsula Corridor Electrification Project (PCEP)
Peninsula Corridor Electrification Project (PCEP) Q4 Quarterly Update #11 April 1 June 30, 2017 JPB Board Meeting August 3, 2017 Agenda Item # 8a Electrification - Infrastructure Design Build Contract
More informationTodd Carlson Program Coordinator Engineering MMSD PP I/I Summit 2.0 October 15,
Todd Carlson Program Coordinator Engineering MMSD PP I/I Summit 2.0 October 15, 2015 1 North Shore of Lake Superior 883 feet of Elevation Aging Sanitary/Storm Sewer System dating back to 1880 s Second
More informationTargeted Group Business and Veteran- Owned Small Business Programs
This document is made available electronically by the Minnesota Legislative Reference Library as part of an ongoing digital archiving project. http://www.leg.state.mn.us/lrl/lrl.asp Targeted Group Business
More informationAGENDA ITEM C3. RECOMMENDATION: Approve Contract No with Lavandera Electrical
AGENDA ITEM C3 DATE: June 1, 2014 TO: FROM: SUBJECT: Matt Jordan, General Manager Charles H. Carden, Chief Operating Officer Section 21 Wellfield Electrical Components - Project No. 07530 Award Construction
More informationMetropolitan Domestic Water Improvement District Board of Directors Meeting. August 8, July 2011 Report
Metropolitan Domestic Water Improvement District Synopsis The purpose of this agenda item is to provide the Board with an update of the District s activities for the past month. This is not an action item,
More informationFINAL LICENSE APPLICATION Exhibit A Description of Project
FINAL LICENSE APPLICATION Exhibit A Description of Project PacifiCorp Portland, Oregon April 2004 Copyright 2004 by PacifiCorp Reproduction in whole or in part without the written consent of PacifiCorp
More informationSano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)
Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : June,
More informationMetro Highway Program
Metro Highway Program ACEC November 2018 I-5 North HOV and Truck Lanes 14 miles of HOV lanes in both directions 2 miles of truck climbing lanes at the south end 7 bridge modifications at: Gavin Canyon
More informationVernon G. Hartsock, PMP Deputy Chief / Chief Engineer Maryland Transit Administration. Tedd L. Snyder, P.E. Senior System Engineer CH2M Hill
Baltimore Metro Retrofit A Combined Train Control and Railcar Procurement Vernon G. Hartsock, PMP Deputy Chief / Chief Engineer Maryland Transit Administration Tedd L. Snyder, P.E. Senior System Engineer
More informationMobility Corridor Updates. Transit & Active Transportation Projects
Mobility Corridor Updates Transit & Active Transportation Projects Laura Cornejo, DEO Regional Planner Regional Operator Metro is LA County s Regional Builder/Funder Rail Bus Service (Metro/Muni/Local)
More informationACTION: ESTABLISH LIFE-OF-PROJECT BUDGET FOR UP TO 100 NEW COMPO BUSES
QD Metro Los Angeles County Metropolitan Transportation Authority One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro.net oplo OPERATIONS COMMITTEE June 16, 2011 SUBJECT: PURCHASE REPLACEMENT
More informationApril 10, Dear Customer:
Dear Customer: April 10, Attached is the monthly water supply outlook and projected operations for Yellowtail Dam and Powerplant. If you have any questions or concerns, please feel free to call me at 406-247-7334
More informationMobility Management: Caltrain
Mobility Management: Caltrain Community Relations Committee October 4, 2017 Agenda Item 7 Presentation Outline Operating Statistics Ridership On-time Performance Fleet Reliability Capital Program Review
More informationInventory Levels - All Prices. Inventory Levels - By Price Range
Inventory Levels - All Prices Idaho Falls Bonneville Total 3-Nov-17 198 128 326 2-Nov-18 155 134 289-11% Inventory Levels - By Price Range 3-Nov-17 2-Nov-18 0-100,000 17 11 100,001-125,000 15 9 125,001-150,000
More informationWentzville Parkway South Phase 2 & 2A
Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total
More informationSimson Haulofu Divisional Manager. NamPower Namibia
Simson Haulofu Divisional Manager NamPower Namibia Agenda Overview of Ruacana Some interesting facts about Ruacana Ruacana s contribution to Namibia Ruacana operating regime Unit 4: Business case & feasibility
More informationCONFEDERATION LINE EAST SEGMENT
The O-Train Confederation Line project is the first stage in Ottawa s future light rail network. The 12.5 kilometre electric rail system will replace existing diesel powered buses, providing rapid transit
More informationup the formulas. You can copy/paste the formulas for the days within the same October 2017 Jan 1, 2 & 5 Student Christmas Break April 2018
School Year Calendar Template 2013-2014 Vertex42 LLC INSTRUCTIONS Year: 2017 Beginning Month: 8 Start day: 1 1:Sunday, 2:Monday «Choose the year and beginning month Note: If you choose Monday as the start
More informationConfederation Line West Queensway Terrace North. May 27, 2017
Confederation Line West Queensway Terrace North May 27, 2017 Agenda Background Lincoln Fields Station Concept LRT alignment, southwest of Lincoln Fields to Queensway, including: Pedestrian bridge replacement
More informationLIST OF OPEN TRAINING TRAINING PLANNER 2016/2017 Course location: Lagos, Abuja, Port Harcourt.
JANUARY 2016 Credit Management and Collection of 4-6 11-15 14-27 Abuja/Lagos/PH 150,000 220,000 320,000 Receivables Developing Executive Management 4-6 11-15 14-27 Abuja/Lagos/PH 150,000 220,000 320,000
More informationHYDRAULIC CUTTING ATTACHMENTS
The Leader in Rock & Concrete Cutting HYDRAULIC CUTTING ATTACHMENTS A Q ANTRAQUIPCORP HYDRAULIC CUTTING ATTACHMENTS FACTORS FOR EQUIPMENT SELECTION Rock Type & Hardness Applications Excavator Size & Power
More informationPATH Integrated Railcar and Signal System Replacement Program
PATH Integrated Railcar and Signal System Replacement Program Overview and Status American Public Transportation Association Rail Conference, Boston, MA June 14, 2011 Douglas Dreisbach Program Manager,
More informationPCDO. Jan Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project
PCDO Jan-2018 Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project Northern Railway vuqjkx dqekj lpku vkbzvkj,lb Anurag Kumar Sachan
More informationDecember 2018 RenewableGenerations Monthly Report
2018 RenewableGenerations Monthly Report Ecosystem of Clean Energy Programs Contractor Training Webinar Table of Contents Solar Electric... 3 Solar Thermal Heating (Northern Nevada Gas Customers)... 5
More informationOut of Sight Out of Mind Revisited. EEI Transmission, Distribution, & Metering Conference October 14, 2009 Ken Hall Hall Energy Consulting
Out of Sight Out of Mind Revisited EEI Transmission, Distribution, & Metering Conference October 14, 2009 Ken Hall Hall Energy Consulting 1 Presentation Outline Customer Expectations Storms and Outages:
More informationGeorge Carter III Dept. of Enterprise Services Olympia Washington
George Carter III Dept. of Enterprise Services Olympia Washington george.carter@des.wa.gov 360-664-9213 Agency Background 4,300 vehicles Electric vehicles in fleet since 2014 Central service provider to
More informationNORTHERN INDIANA PUBLIC SERVICE COMPANY NORWAY AND OAKDALE HYDRO ELECTRIC PLANTS MONTICELLO, INDIANA
NORTHERN INDIANA PUBLIC SERVICE COMPANY NORWAY AND OAKDALE HYDRO ELECTRIC PLANTS MONTICELLO, INDIANA INTRODUCTION: NIPSCO is the proud owner of two Hydro Electric Plants located near Monticello, Indiana.
More informationWestern Alberta Transmission Line (WATL) HVDC Project
Submission for the ACEC Canada Canadian Consulting Engineering Awards 2016 Western Alberta Transmission Line (WATL) HVDC Project Submitted by Teshmont Consultants LP as a Consultant to AltaLink Attachment
More informationPART PROGRESSION LIST AND PART PRICE LIST S As of October 12, 2006
PART PROGRESSION LIST AND PART PRICE LIST S As of October 2, 2006 The following part progression list was taken from the various Ford Part Price List s which were available. One can follow Fords change
More informationUse of Two Novel Hybrid-Type Crossover TBMs for Hard Rock Conditions with Water Inflows
Use of Two Novel Hybrid-Type Crossover TBMs for Hard Rock Conditions with Water Inflows Missy Isaman The Robbins Company ABSTRACT Mixed ground tunnels come in all kinds. In rock tunnels with possible faults
More informationcongestion management program
congestion management program 2550 Rail Vehicle Program March 2012 11-0319tr 2010 lacmta Q U A R T E R LY P R O J E C T S TAT U S R E P O R T 255O RAIL VEHICLE PROGRAM QUARTERLY PROJECT STATUS REPORT THE
More informationResidential and Municipal Solid Waste Collections Contract. January 15, 2019
Residential and Municipal Solid Waste Collections Contract January 15, 2019 1 Overview Background and history RFP Process and Results Automated and Manual Collections CalRecycle Compliance Recommendation
More information2013 PUGET SOUND TIDE TABLES
2013 PUGET SOUND TIDE TABLES Inspiring Conservation of Our Marine Environment Thank you to the many donors whose contributions help us draw citizens to our local beaches, and foster a love of marine life
More informationSacramento Municipal Utility District s EV Innovators Pilot
Sacramento Municipal Utility District s EV Innovators Pilot Lupe Jimenez November 20, 2013 Powering forward. Together. Agenda SMUD Snapshot Pilot Plan v Background v At-a-Glance v Pilot Schedule Treatment
More informationUpdate on Transportation Activities in Fairfax County
Update on Transportation Activities in Fairfax County Transportation Roundtable Dulles Area Transportation Association June 13, 2018 Tom Biesiadny, Director Fairfax County Continuing Project Implementation
More informationINFRASTRUCTURE AND TRANSPORTATION ADVERTISING SCHEDULE 2015/2016 CONSTRUCTION AND MATERIAL SUPPLY TENDERS
INFRASTRUCTURE AND TRANSPORTATION ADVERTISING SCHEDULE 2015/2016 CONSTRUCTION AND MATERIAL SUPPLY TENDERS Manitoba Infrastructure and Transportation Contract Services Branch 1630-215 Garry Street Winnipeg,
More informationPilot Study for Plug-In Hybrids
Pilot Study for Plug-In Hybrids Sustainability/Energy Committee January 26, 2016 Overview Plug-in Electric Vehicle (EV) Pilot Project Employee Access to Charging Stations Next steps Purpose of Pilot Study
More informationRed and Bonita Mine. Removal Action Bulkhead Plan Summary May 2015
Red and Bonita Mine Removal Action Bulkhead Plan Summary May 2015 Mine Discharge and Underground Workings Flow is approximately 200 to 300 gpm Zinc concentration is consistently near 16,000 ug/l Cadmium
More informationBOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY. Consent Workshop [ ]
- _j POSTPONED FROM THE JANUARY 14 BCC MEETING Agenda Item #5,::.. I BOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY Meeting Date: February 4, 2014 [ ] [ ] Department: Submitted By: Engineering & Public
More informationElectric Vehicle Charging Station Installation and Eco-Pass Updates. Report Prepared by: A. Rolston, Parking Operations Coordinator
Report to Council Date: File: 1862-01 To: From: Subject: City Manager D. Duncan, Manager, Parking Services Electric Vehicle Charging Station Installation and Eco-Pass Updates Report Prepared by: A. Rolston,
More informationImpacts of Hurricane Sandy to NYCDEP WWTPs and Pump Stations. December 12, 2012
Impacts of Hurricane Sandy to NYCDEP WWTPs and Pump Stations December 12, 2012 Presentation Agenda Overview of NYC Sewer System and Treatment Plants Preparations Made in Anticipation of Sandy Status of
More informationENVIRONMENTAL & ENGINEERING SERVICES DEPARTMENT
CITY OF LONDON ENVIRONMENTAL & ENGINEERING SERVICES DEPARTMENT WASTEWATER TREATMENT OPERATIONS VAUXHALL WASTEWATER TREATMENT PLANT 2013 ANNUAL REPORT FEBRUARY 2014 Vauxhall Wastewater Treatment Plant 2013
More informationDetroit District LOWER FOX RIVER DAMS. Tina Kowitz, P.E. Dam Safety Program Manager 17 June 2009
LOWER FOX RIVER DAMS Tina Kowitz, P.E. Dam Safety Program Manager 17 June 2009 Outline National Dam Safety Program Risk Assessments Interim Risk Reduction Measures Schedule for Remedial Action History
More informationPeninsula Corridor Electrification Project Cost / Schedule Update
Peninsula Corridor Electrification Project Cost / Schedule Update LPMG Meeting November 20, 2014 Context Caltrain/high-speed rail blended system - Primarily 2 track system - Minimize impacts - Shared system
More informationEconomics of Driven Pile Foundations
Economics of Driven Pile Foundations 2013 PDCA Professors Driven Pile Institute ( PDPI ) June 24-28, 2013 Van E. Komurka, P.E., D.GE, F.ASCE Wagner Komurka Geotechnical Group, Inc. 1 Talk Outline Define
More informationINDIANA DEPARTMENT OF TRANSPORTATION PAGE 1 NOTICE TO HIGHWAY CONTRACTORS
INDIANA DEPARTMENT OF TRANSPORTATION PAGE 1 NOTICE TO HIGHWAY CONTRACTORS DATE OF LETTING: March 04, 2015 TIME OF LETTING: 10:00 AM EASTERN STD DESIGN BUILD CONTRACTS Sealed proposals for certain highway
More informationCity-wide LED Street Light Conversion Program
City-wide LED Street Light Conversion Program Arts & Innovation Board of Public Utilities July 25, 2016 Project Description Utility 2.0 Multi-phase implementation of city-wide street light conversion program
More informationNew Generation of Red Power for 2011: Introducing the New Magnum Tractors March, 2011
Tractors TA-1258-11 New Generation of Red Power for 2011: Introducing the New Steiger 350-600 Tractors March, 2011 TA-1259-11 Introducing the Puma Tractors for 2011 March, 2011 TA-1260-11 New Generation
More informationGenerator Rebuild and Unit Refurbishment for the Wells Hydroelectric Project. NWHA Spokane October 30, 2014
Generator Rebuild and Unit Refurbishment for the Wells Hydroelectric Project NWHA Spokane October 30, 2014 0 The Wells Project WELLS Chief Joseph Rocky Reach East Wenatchee Wells Dam Location Columbia
More informationReview of Operations in FY2012
Sales Segment Profit and Ratio Sales by Region for the Fiscal Year ended March 31, 2013 (To Outside Customers) 41 With respect to construction equipment, while demand increased in North America and Japan
More informationVillage Green in Philadelphia
Village Green in Philadelphia Dennis Sosna Hallie Weiss City of Philadelphia Department of Public Health Air Management Services 2015 MARAMA Monitoring Committee Meeting December 17, 2015 Towson, MD ABSTRACT
More informationMetropolitan Water District of Salt Lake & Sandy CAPITAL PROJECT REPORT
Last Updated: April 23, 2018 Metropolitan Water District of Salt Lake & Sandy CAPITAL PROJECT REPORT May 2018 Routine Non-Capacity Improvement Projects Terminal Reservoir Replacement Project (TR003) see
More informationModernising the Great Western railway
Report by the Comptroller and Auditor General Department for Transport and Network Rail Modernising the Great Western railway HC 781 SESSION 2016-17 9 NOVEMBER 2016 4 Key facts Modernising the Great Western
More informationSAUSALITO FERRY TERMINAL REPLACEMENT PROJECT. Item 5A- PPT Presentation Page 1 of 23
SAUSALITO FERRY TERMINAL REPLACEMENT PROJECT OCTOBER 10, 2017 CITY OF SAUSALITO CITY COUNCIL MEETING Page 1 of 23 PROPOSED PROJECT SUMMARY EXISTING PROPOSED (ACCESS PIER WITHOUT BELVEDERES) Gate Location
More information