Conference Papers. Keith Malmedal P.E., P.K. Sen Ph.D /08/$ IEEE. Paper No. 08 C3

Size: px
Start display at page:

Download "Conference Papers. Keith Malmedal P.E., P.K. Sen Ph.D /08/$ IEEE. Paper No. 08 C3"

Transcription

1 Conference Papers Comparison of Some Randomly Selected Utilities Interconnection Requirements and the Compliance with the IEEE Std Interconnection Guidelines Keith Malmedal P.E., P.K. Sen Ph.D. Paper No. 08 C /08/$ IEEE C3

2 Comparison of Some Randomly Selected Utilities Interconnection Requirements and the Compliance with the IEEE Std Interconnection Guidelines Keith Malmedal P.E. Member, IEEE, P,K. Sen Ph.D. P.E., Senior Member, IEEE Abstract Electric Utilities permitting interconnection of generation (small and/or large) on their power systems have long had standards which any entity wishing to interconnect has to meet. Recently the growing importance of distributed generation (mostly less than 10MVA), especially using renewable sources, has prompted the creation of IEEE Std which sets requirements and guidelines for interconnecting a distributed resource with an electric power system. This paper will examine the requirements of the Std. IEEE 1547 and compare them with the interconnection requirements currently used by a number of randomly selected utilities. Index Terms Distributed Energy Resources, Generators, Interconnection, Renewable Energy. IEEE Std Guideline. An analysis is also added with respect to these data to enhance the understanding and applicability of these requirements. In 1978 the Public Utility Regulatory Policies Act (PURPA) was passed which encouraged the creation of n-utility owned generation and cogeneration. The Energy Policy Act of 2005 modified PURPA and its provisions will further encourage the creation and interconnection of distributed generation on utility facilities. These developments have lead to the creation of IEEE Std and the further creation of utility interconnection standards for power plants and distributed resources which wish to connect with utility facilities. I I. INTRODUCTION EEE Standard titled IEEE Standard for Interconnection Distributed Resources with Electric Power Systems was developed in its own words to provide a uniform standard for interconnection of distributed resources (DR) with electric power systems (EPS). It provides requirements relevant to performance, operation, testing, safety considerations, and maintenance of the interconnection [1]. The standard also states that the requirements contained within it are universally needed for interconnection of DR, including synchrous machines, induction machines, or power inverters/converters and will be sufficient for most installations. Many utilities had developed their own standards some of which have been in use for many years prior to the IEEE Standard Guideline. An examination of a variety of interconnection standards shows that there is a wide variation in the acceptance of the requirements stated in the Std. IEEE This paper will examine, in detail, a number of such randomly selected guidelines and compare them with the Manuscript submitted January 18, 2008 for 2008 IEEE Rural Electric Power Conference, April 28-29, Charleston, SC. This work was partially supported by the NSF IUCRC Power Systems Engineering Research Center ( K. Malmedal is a principal engineer with NEI Electric Power Engineering, Arvada, CO USA. and a doctoral student at Colorado School of Mines, Golden, Colorado 80401, kmalmedal@neiengineering.com P. K. Sen is Professor of Engineering with Colorado School of Mines, Golden Colorado psen@mines.edu II. INTERCONNECTION REQUIRMENTS AND IEEE STD The table shown at the end of this paper in Appendix II is designed to quickly show how a variety of utilities and state requirements for generation interconnection compare with the requirements of IEEE Std Of the standards (available in public domain) examined only two utilities completely the implementation of IEEE Std. 1547, PacifiCorp and the New York State Public Utilities Commission. Several others, such as Otter Tail Power, partially accept the requirements of IEEE Std.1547 while others, independently develop their own requirements. The only meaningful guidelines of IEEE Std which seems to be universally accepted is the provision of requiring a utility to have accessible disconnect switch at the point of common coupling (PCC) with the utility (Fig. 1)[1]. Ather requirement which is well, although t universally, accepted is the requirement that some type of testing (usually field testing) (Appendix 1 Table 4)[1]be done before the distributed energy resource (DER) is released for operation. An area of (wide) common concern is the (voltage) flicker and voltage fluctuations that may be caused by a DR. IEEE Std states a level of acceptable voltage fluctuation which some utilities accept while other simply makes the blanket statement that abrmal voltages will be created by the DR. IEEE Std also states that the DR must be grounded in a way t to produce over voltages without stating how this is to be done. The interconnection standards are generally more specific on grounding and ground fault protection issues, sometimes requiring a transfer trip to the DR to insure over voltages are produced. C3-1

3 IEEE Std contains a number of requirements to limit harmonics created by the DR. Those interconnection standards addressing harmonics commonly include compliance with IEEE Std. 519 rather than referring to IEEE Std (Appendix I Table 3)[1]. There appears to be two areas of considerable disagreement between the IEEE Std and many utility interconnection standards. The first is in the area of frequency protection. IEEE Std has requirements for tripping the DR at certain abrmal frequencies within certain times (Appendix I Table 2) [1]. These requirements disagree with several of the interconnection standards. In some cases, the interconnection standards do t permit tripping in part of the frequency range which IEEE Std requires tripping. In general, where IEEE Std appears to be more concerned with removing the DR from the system during an abrmal frequency event, the utility interconnection standards seem more concerned with keeping generation on to try to prevent an abrmal frequency event from becoming worse due to the removal of generation. The second area of disagreement is the protection that must exist at the point of common coupling (PCC). Fig. 1[1] shows how the DR and EPS may be interconnected and illustrates where the PCC may occur. This is an area t well addressed in the IEEE Std which states: the requirements shall be met at the point of common coupling (PCC), although the devices used to meet these requirements can be located elsewhere. [1] Most utilities, however, require protective devices to be located at the point of common coupling. Fig. 2 shows a typical distribution system including the locations where DER may be connected. This point is commonly protected with fuses only. However, many interconnection requirements call for increased protection at the PCC. This is done to prevent disturbances caused by the DR from affecting the utility, and is often also to insure that there is protective relaying which backs up the relaying which may exist at the DR. Among the protection often by the utility at the PCC are over and under voltage protection, frequency protection, ground fault protection, and occasionally some type of backup system protection such as a 51V relay. Utility interconnection standards often also require additional relaying for the generator which is t by the IEEE Std [2]. Some utility interconnection standards require utility grade relays a certain generation size, and provisions for periodic relay testing by the utility. The periodic re-testing of interconnection equipment is also a requirement often seen as important by utilities, but t well addressed in the IEEE Std. 1547[2]. III. CONCLUSION The table in the Appendix II shows some of the more important requirements of the IEEE Std and compares them with selected utility interconnection standards. It can be seen that there is considerable variation between the standards and the various utilities examined. Although some utilities do accept all of IEEE Std. 1547, most of those also have other standards which must be met. It also appears that from the standpoint of many utilities allowing generation interconnection the provisions of IEEE Std are t, as stated in the standard universally needed and sufficient for most installations [1] and many utilities have other stringent requirements than those stated in IEEE Std Fig. 1 Relationship of Interconnection Terms. 30/40/50 MVA T1 115KV KV 7%Z G 51G 79 C S ST 115KV 50 50G 51 51G 51 51N 50G 51G 79 T3 750KVA 3Ø 12.47KV-480V INDUSTRIAL LOAD 40E WITH DER 87T Voltage Regulator G 51G SECTIONALIZER T2 30KVA 1Ø 7.2KV-120/240V 5E D1 LATERAL RES. LOADS WITH DER Fig. 2 Typical Power Distribution System with Protection Shown. The Energy Policy Act of 2005 (EPACT) specifically states that interconnection services be based upon the IEEE Standard It also states that agreements and procedures shall be established whereby the services offered shall promote current best practices of interconnection for distributed generation, including but t limited to practices stipulated in model codes C3-2

4 adopted by associations of state regulatory agencies. All such agreements and procedures shall be just and reasonable, and t unduly discriminatory or preferential. So EPACT recognizes both IEEE Std and utilities interconnection practices and standards. It can be seen that in some cases the a utility s interconnection standards are the same as the requirements of IEEE Std. 1547, however, in most cases there is considerable variability between what the utility requires and what is suggested in IEEE Std Some states are proposing to use IEEE Std as the basic standard to determine if a new DR can automatically be connected to a system without further review or if further study of the system is by the utility before the DR can be allowed to connect (which will be paid for by the customer). The procedure might require a new DR customer to fill out a form which would include a number of questions about the new DR. If the answers provided proved that the provisions of IEEE Std were satisfied, the interconnection of the new DR could proceed without further study. The basic IEEE Std is t sufficient to determine if a certain type of interconnection is safe for the rest of the system. IEEE Std mainly addresses the generator and PCC itself, while t concerning itself with other parts of the system or system operation. For example, the requirement that the DR t cause over voltages may be met at the point of common coupling (PCC), but may t be met in other parts of the distribution system. The customer filling out the forms may have way of kwing that this is true and examination of the system with DR by a distribution engineer might be needed to determine that this problem even existed. This problem may become more prounced when the DR is connected at the residential level and every effort is made by simplifying the procedure. Ather area of concern is reclosing and the effect DR may have on the existing utility reclosing scheme. Nearly every distribution system in the U.S. incorporates multiple-shot reclosing. However, how this scheme may be impacted by the addition of DR is certainly t clear to the customer who is designing only the equipment in the new power plant at the PCC. IEEE Std doesn t address the impacts of DR on reclosing and line sectionalizing schemes. As long as the penetration level of DR is small (say less than 5% of the feeder capacity) the addition of an additional unit, especially small inverter based DR, may cause minimum impact to the system and can be connected without further review by the utility s engineers. However, when DR penetration level on a distribution system becomes sufficiently high (presently estimated at 20% or higher) this may cause problems with the system [3]. Will the latest DR to connect be to pay for all the system upgrades to make it possible to safely connect this generator? Or will all the DR s on the system, old and new, be to contribute to this cost? This question has to be addressed. As DR penetration levels become high the impacts become more widespread and the IEEE Std concentrates on impacts at the PCC and does t address what may become widespread future effects on both distribution and transmission systems and their operation. These are valid questions currently imposed and must be addressed in the future revision of the Standard. Utilities need to be more careful in allowing interconnections base only on the IEEE Std It is evident that utilities have seen the necessity of providing their own standards, which may or may t include provisions of IEEE Std in the foreseeable future, to insure their systems can continue to operate safely and reliably as DER becomes a more important part of the generation mix. The attempt to make a more general Standard by the IEEE was good, but future revisions must address a number of additional issues. Additional Std. of the 1547 series may also include some of the questions raised by this paper. REFERENCES [1] IEEE Standard for Interconnecting Distributed Resources with Electric Power Systems, IEEE Standard , IEEE Piscataway, NJ. [2] K. Malmedal, P.K. Sen, and J. P. Nelson, Application of Out-of-Step Relaying for Small Generators in Distributed Generation, IEEE Transactions on Industry Applications, Vol. 41, No. 6, Nov./ Dec. 2005, pp [3] K. Malmedal, B. Kroposki, and P.K. Sen, Distributed Energy Resources and Renewable Energy in Distribution Systems: Protection Considerations and Penetration Levels, (In Review), 2008 IEEE Industry Applications Society 43 rd Annual Meeting, Edmonton, Alberta, October 5-9, [4] IEEE Standard Conformance Test Procedures for Equipment Interconnecting Distributed Resources with Electric Power Systems, IEEE , IEEE, Piscataway, NJ. [5] XCEL Energy Interconnection Guidelines for Transmission Interconnected Producer-Owned Generation 20MW and less. Version 1, Xcel Energy, June 15, [6] PacifiCorp Cogeneration and Parallel Generation Interconnection Guide, ificorp/pplengin.pdf [7] AESO Generation and Load Interconnection Standard, [8] Otter Tail Power Company, Guidelines for Generation, Tie-Line, and Substation Interconnection, [9] Rules for Interconnecting Distributed Generation Systems, Wisconsin Public Service Commission PSC 119, [10] Distributed Generation Interconnection Manual, Public Utility Commission of Texas May 1, [11] Guidelines for Interconnection of Customer Generators, City of Anaheim Public Utilities Department, Electrical Engineering, s2-1.pdf, December [12] New York State Standardized Interconnection Requirements and Application Process for New Distributed Generators 2 MW or Less Connected in Parallel with Utility Distribution Systems, New York State, Public Service Commission, September [13] SRP Interconnection Guidelines for Distributed Generators, December [14] Application Guide for Distributed Generation Interconnection: 2006 Update, The NRECA Guide to IEEE 1547, Resource Dynamics Corporation, Final.pdf, March [15] K. Malmedal, B. Kroposki, and P. K. Sen, The Energy Policy Act of 2005 and its Impact on Distributed Generation, IEEE IAS Magazine, January 2007, pp [16] K. Malmedal, B. Kroposki, and P.K. Sen, The Energy Policy Act of 2005 and it s Impact on Renewable Energy Applications in the USA, 2007 IEEE Power Engineering Society General Meeting Conference Record, Annual Summer Meeting, Tampa Bay, Florida, June [17] Energy Policy Act of 2005, Washington, DC, C3-3

5 Keith Malmedal (Member, IEEE) received his BSEET degree from Metropolitan State College of Denver in 1995, a MSEE degree (Power) and a MSCE degree (Structures) from the University of Colorado at Denver in 1998 and 2002, respectively. Keith is presently a PhD candidate at Colorado School of Mines in Engineering Systems (Electrical Specialty). He has over sixteen years combined experience in electrical power system analyses and system study, teaching and research and is presently the President and a senior project manager at NEI Electric Power Engineering, Arvada, Colorado, specializing in all aspects of power system design. Keith has published over a dozen technical papers in archival journals and conference proceedings and taught (and co-taught) regular university courses, short courses on a variety of subjects related to the interrelated areas of power systems, machines, protections, renewable energy applications, and energy policy issues to hundreds of practicing professionals. Mr. Malmedal is a member of the American Society of Civil Engineers and a registered professional engineer in 14 states. TABLE 1 Interconnection System Response to Abrmal Voltages. TABLE 2 Interconnection System Response to Abrmal Frequencies. Pankaj K. (PK) Sen (Sr. Member, IEEE) received his BSEE degree (with hors) (1966) from Jadavpur University, India, and the M.Eng. (1971) and Ph.D. (1974) degrees in electrical engineering from the Technical University of Nova Scotia (Dalhousie University), Halifax, NS, Canada. He is currently a Professor of Engineering and Site Director of the Power Systems Engineering Research Center ( at Colorado School of Mines in Golden, Colorado. His research interests include application problems in electric machines, power systems, protection, renewable energy and distributed generation and power engineering education. He has published more than 130 articles in various archival journals and conference proceedings and has supervised over 120 students with MS and PhD degrees. Dr. Sen taught a number of regular advanced level graduate and many undergraduate university courses, and conducted workshops and taught short courses on machines, power systems, transmission and distribution, renewable energy, energy policy and energy ecomics to literally thousands of practicing engineers and is a registered professional engineer in the State of Colorado. TABLE 3 Maximum Harmonic Current Distortion in Percent of Current. TABLE 4 Sequence for Conducting Design Test. APPENDIX I Selected Sketches from the IEEE Std. 1547[1] Fig. 3 Schematic of Interconnection. TABLE 5 Synchronization Parameter Limits for Synchrous Interconnection to an EPS or an Energized Local EPS to an Energized Area EPS. TABLE 6 Maximum Harmonic Distortion in Percent of Rated Voltage for Synchrous Machines. C3-4

6 APPENDIX II TABLE 7 Comparison of Utility Requirements with IEEE Std. No Requirement IEEE 1547 XCEL Interconnection Standard for <20MW PacifiCorp Alberta Electric Must Comply with IEEE 1547 (DR) shall t regulate voltage at (PCC) (4.1.1) Voltage Regulation may be allowed Otter Tail Power Flicker requirements only Generation must control line-ground voltage if islanded Wisconsin PUC For paralleling equipment only Texas PUC City of Anaheim New York State PUC Salt River Project Grounding scheme shall t cause over voltages or disrupt ground fault protection. DR shall parallel with EPS without causing voltage fluctuation greater than 5%. Network protectors shall t be used to isolate a network to which DR is connected unless protectors are tested and rated for the purpose. DR shall t prevent the reclosing of any network protectors and shall t require changes in protector clearing times. (4.1.2) (4.1.3) ( ) ( ) Must be effectively grounded Must be effectively grounded Generation must control line-ground voltage if islanded and several schemes may be used to prevent over voltages Isolation Trans. may be DR shall t cause cycling of network protectors. ( ) Network loading and fault interrupting capacity shall t be exceeded with the addition of DR. DR shall t energize the EPS when the EPS is de-energized. DR <250kVA at the PCC shall monitor real and reactive power, and voltage at its PCC ( ) (4.1.5) (4.1.6). C3-5

7 Requirement Interconnection system shall withstand EMI and EMI shall t cause misoperation. Interconnection system shall withstand voltage and current surges per IEEE C or C Paralleling device shall withstand 220% of interconnected system rated voltage. DR shall t energize faults on the EPS circuit to which it is connected. DR shall de-energize the EPS prior to any reclosure on the EPS. DR protection system shall detect voltages at terminals if DR<30kW, interconnection equipment is certified to pass a nislanding test, or DR is less than 50% of local EPS minimum demand and export of power is t permitted. Shall trip in 0.16 sec if V<50%, Shall trip in 2.00 sec if 50%<V<88%, Shall trip in 1 sec if 110%<V<120%, Shall trip in 0.16 sec if V>120% Freq trip settings shall be adjustable for over 30kW Shall trip in 0.16 sec if F>60.5Hz Shall trip in 0.16 sec if F<59.3 Hz IEEE 1547 ( ) ( ) ( ) (4.2.1) (4.2.2) (4.2.4) (4.2.4) (4.2.4) XCEL Interconnection Standard for <20MW PacifiCorp Alberta Electric Otter Tail Power Wisconsin PUC Texas PUC City of Anaheim New York State PUC Salt River Project 1-5 sec Yes 1-5 sec Yes 1-5 sec ; 30 cy at 105% Yes Yes Tripping t permitted below 60.5 Hz Tripping t permitted 10 cycles 61 Hz 6 cycles below 59 Hz Tripping t permitted below 60.6Hz. 3 min. 60.6Hz, 30 secs Hz 3 minutes; 30 secs. below 58.4Hz; 7.5 secs. below 57.8Hz; 45 cycles below 57.3 Hz Tripping t permitted below 60.5 Hz Tripping t permitted 59.5 Hz 0.25 sec Yes 0.25 sec Yes C3-6

8 Requirement If DR>30kW shall have adjustable trip set point for F<59.8 to 57 Hz and adjust between 0.16 and 300 sec No DR reconnection shall occur if voltage and frequency are out of range. DR shall have adjustable time delay or a delay of 5 minutes before reconnection. DR shall t inject more DC current than 0.5% of its rated output. DR shall t produce objectionable flicker Shall t produce more than 4% harmonic below the 11th. Shall t produce more than 2% harmonics between 11th and 17th. Shall t produce more than 1.5% harmonics between 17th and 23rd. Shall t produce more than 0.6% harmonics between 23rd and 35th. Shall t produce more than 0.3% harmonics greater than the 35th. Total harmonic distortion shall t exceed 5% DR shall detect and de-enrgize an island. DR shall undergo testing at factory or in field. IEEE 1547 (4.2.4) XCEL Interconnection Standard for <20MW Tripping permitted below 58.5 Hz. PacifiCorp Alberta Electric Tripping t permitted 59.4 Hz Otter Tail Power Wisconsin PUC Texas PUC City of Anaheim New York State PUC Salt River Project Yes (4.2.6) (4.2.6) (4.3.1) (4.3.2) <1% below the 7th IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 IEEE 519 (4.4.1.) If islanding is possible SCADA is (5.1) C3-7

9 Requirement Goverr must operate between 59.5 and 60.5 HZ and be adjustable 0-10% droop. IEEE 1547 XCEL Interconnection Standard for <20MW PacifiCorp Alberta Electric Otter Tail Power Wisconsin PUC Texas PUC City of Anaheim New York State PUC Must have Circuit breaker at PCC For synch. mach. 25 relay Salt River Project 59 relay 27 relay 1MW 50kW Yes 81 relay 51N relay 51V or 21 relay 32 relay may be may be 1MW 1MW 50kW May be 47 relay 15 relay for induction machines System Study Required Must t increase voltage unbalance by more than 1% Information must be available for units 5MW may be Utility grade relays 100kW System must be UL listed Must provide test switches for protection testing interrupting device UL kW Disconnect Switch and interrupting devices C3-8

Copyright 2003 Advanced Power Technologies, Inc.

Copyright 2003 Advanced Power Technologies, Inc. Overview of the Standard for Interconnecting Distributed Resources with Electric Power Systems, IEEE 1547 and it s potential impact on operation of the Distributed Generation (DG) systems and on the design

More information

GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS

GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS Prof. Suryanarayana Doolla Department of Energy Science and Engineering Indian Institute of Technology Bombay OUTLINE Intoduction Grid

More information

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems Ben Huckaba, P.E. President & Principal Engineer 317-273-9841 benh@alphaeng.us Indiana University Bloomington,

More information

Small Electrical Systems (Microgrids)

Small Electrical Systems (Microgrids) ELG4126: Microgrids Small Electrical Systems (Microgrids) A microgrid is a localized, scalable, and sustainable power grid consisting of an aggregation of electrical and thermal loads and corresponding

More information

Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1

Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1 Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1 A Guide for Iowa s Municipal Electric Utilities On the How the IEEE 1547 Distributed Generation Interconnection Standard Affects Solar

More information

Net Metering Interconnection Requirements

Net Metering Interconnection Requirements Net Metering Interconnection Requirements Customer Generation Capacity Not Exceeding 100 kw Date: 2017-07-01 Version: 1 Revision History Date Rev. Description July 1, 2017 1 Initial Release Newfoundland

More information

Distributed Energy Resources and Renewable Energy in Distribution Systems: Protection Considerations and Penetration Levels

Distributed Energy Resources and Renewable Energy in Distribution Systems: Protection Considerations and Penetration Levels Distributed Energy Resources and Renewable Energy in Distribution Systems: rotection Considerations and enetration Levels Keith Malmedal,.E. Member IEEE rincipal Engineer/roject Manager NEI Electric ower

More information

Net Metering Interconnection Requirements. Customer Generation Capacity Not Exceeding 100 kw. Date: Version: 1

Net Metering Interconnection Requirements. Customer Generation Capacity Not Exceeding 100 kw. Date: Version: 1 Net Metering Interconnection Requirements Customer Generation Capacity Not Exceeding 100 kw Date: 2017-07-01 Version: 1 Revision History Date Rev. Description July 01, 2017 1 Initial release Newfoundland

More information

3.0 Radial Distribution Systems

3.0 Radial Distribution Systems 3.0 Radial Distribution Systems Radial distribution systems (RDS) are the most common design used by electric utilities, and are the least expensive to plan, construct, and maintain. They generally consist

More information

Impact of Distributed Energy Resources on Transmission System Reliability

Impact of Distributed Energy Resources on Transmission System Reliability S E P T E M B E R 1 3, 2 0 1 8 W E B I N A R Impact of Distributed Energy Resources on Transmission System Reliability National Council on Electricity Policy (NCEP) Alan McBride D I R E C T O R, T R A

More information

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655) - (SMUD FORM 2655) A. Applicability: This Generating Facility Interconnection Application (Application) shall be used to request the interconnection of a Generating Facility to Sacramento Municipal Utility

More information

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System This document is intended to be a general overview of PG&E s current technical

More information

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES 10-100 KILOWATTS IN THE STATE OF NEW JERSEY January 1, 2005 Rockland Electric Company 390 West Route 59 Spring Valley,

More information

GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM

GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM Page 1 of 19 Table of Contents 1.0 SCOPE...4 2.0 PURPOSE...4 3.0 LIMITATIONS...5 4.0 GENERAL INTERCONNECTION

More information

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Adopted Based on State and Tariff Interconnection Rules Applicable to Northern States Power,

More information

IEEE SCC21 Overview/Status IEEE Standards Coordinating Committee 21 on Fuel cells, Photovoltaics. Dispersed Generation, and Energy Storage

IEEE SCC21 Overview/Status IEEE Standards Coordinating Committee 21 on Fuel cells, Photovoltaics. Dispersed Generation, and Energy Storage IEEE SCC21 Overview/Status IEEE Standards Coordinating Committee 21 on Fuel cells, Photovoltaics. Dispersed Generation, and Energy Storage Richard DeBlasio SCC21 Chair/IEEE Standards Board Member/U.S.

More information

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Adopted Based on State and Tariff Interconnection Rules Applicable to Northern States Power,

More information

Appendix A2: Technical Requirements for Distributed Generators > 10 kw to be Connected to Kitchener-Wilmot Hydro Inc. s Distribution System

Appendix A2: Technical Requirements for Distributed Generators > 10 kw to be Connected to Kitchener-Wilmot Hydro Inc. s Distribution System Appendix A2: Technical Requirements for Distributed Generators > 10 kw to be Connected to Kitchener-Wilmot Hydro Inc. s Distribution System A. INTRODUCTION This document outlines the technical requirements

More information

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS. 25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context indicates otherwise, this section and 25.212 of this title (relating to Technical Requirements

More information

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1. Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.3, 5/16/18 1.0 Scope This document is currently limited in scope to inverter interfaced PV installations

More information

STATE OF NORTH DAKOTA DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS TABLE OF CONTENTS

STATE OF NORTH DAKOTA DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS TABLE OF CONTENTS STATE OF NORTH DAKOTA DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS TABLE OF CONTENTS Foreword 2 1. Introduction 3 2. References 6 3. Types of Interconnections 7 4. Interconnection Issues and Technical

More information

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION Work Order No: File Reference: 16/2/1 This application form for the connection of small scale embedded generation is for small

More information

DISTRIBUTED RESOURCE GENERATION Feed-In-Tariff Single Phase

DISTRIBUTED RESOURCE GENERATION Feed-In-Tariff Single Phase PAGE 1 OF 7 USE: Requirements and guidelines for interconnection of single phase customer owned, (DR) Distributed Resource generation source, to NIPSCO s electric system, configured for. LATEST REVISION:

More information

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008 NB Power Customer Service and Distribution June 2008 Prepared by: Steven Wilcox Revised by: Steven Wilcox TABLE OF CONTENTS 1.0 Introduction 4 2.0 NB Power Policy on Independent Power Production 4 3.0

More information

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS 1. PURPOSE AND SCOPE OF THIS DOCUMENT... 3 2. DEFINITIONS...

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Adopted: September 24, 2015 Version: Version 1.0

Adopted: September 24, 2015 Version: Version 1.0 Interconnection Standards for Parallel Installation and Operation of Customer Owned Renewable Electric Generating Facilities for Coon Rapids Municipal Utilities Adopted: September 24, 2015 Version: Version

More information

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew. Guide Department: Interconnection Services Document No: GD-1401 v1.0 Title: WIND ISLANDING Issue Date: 11-24-2014 Previous Date: N/A Contents 1 PURPOSE... 2 2 SCOPE AND APPLICABILITY... 2 3 ROLES AND RESPONSIBILITIES...

More information

TERMS AND CONDITIONS

TERMS AND CONDITIONS XXV. NET METERING A. Applicability and Availability 1. The terms Net Metering Service, Demand Charge-based Time-of- Use Tariff, Net Metering Customer, Customer, Time-of-Use Customer, Time-of-Use Tier,

More information

GUIDELINES FOR OPERATING, METERING AND PROTECTIVE RELAYING FOR. NET METERED SYSTEMS UP TO 50 kw AND BELOW 750 VOLTS

GUIDELINES FOR OPERATING, METERING AND PROTECTIVE RELAYING FOR. NET METERED SYSTEMS UP TO 50 kw AND BELOW 750 VOLTS GUIDELINES FOR OPERATING, METERING AND PROTECTIVE RELAYING FOR NET METERED SYSTEMS UP TO 50 kw AND BELOW 750 VOLTS 1. INTRODUCTION... 3 1.1 POLICY ON CUSTOMER GENERATION.... 3 1.2 GENERATION SOURCES AND

More information

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE Yunqi WANG, B.T. PHUNG, Jayashri RAVISHANKAR School of Electrical Engineering and Telecommunications The

More information

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Adopted Based on State and Tariff Interconnection Rules Applicable to Northern States Power,

More information

Net +Plus Connection Code

Net +Plus Connection Code Net +Plus Connection Code LANKA ELECTRICITY COMPANY (PRIVATE) LIMITED 1.0 BACKGROUND The existing Net Metering Concept launched in the year 2010 noticed an exponential growth in the recent year and at

More information

DAKOTA ELECTRIC ASSOCIATION DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS

DAKOTA ELECTRIC ASSOCIATION DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS DAKOTA ELECTRIC ASSOCIATION DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS TABLE OF CONTENTS Foreword 2 1. Introduction 3 2. References 6 3. Types of Interconnections 7 4. Interconnection Issues and

More information

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program As part of our commitment to support renewable energy, Kissimmee Utility Authority

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

New Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities

New Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities New Ulm Public Utilities Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities INDEX Document Review and History... 2 Definitions... 3 Overview... 3 Application

More information

RECOMMENDATION: It is recommended that the City Council, following a public hearing, adopt the attached resolution which:

RECOMMENDATION: It is recommended that the City Council, following a public hearing, adopt the attached resolution which: DATE: July 16,2007 TO: FROM: SUBJECT: CITY COUNCIL CITY MANAGER CONSIDERATION OF ADOPTION OF NEW FEDERAL STANDARDS RELATING TO ELECTRIC UTILITIES UNDER THE PUBLIC UTILITIES REGULATORY POLICIES ACT AND

More information

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY Table of Contents Chapter 1. Purpose and scope. Pg 3 Chapter 2. Application

More information

Enabling Smart Grid Interoperability: A System of Systems Approach via IEEE P2030 TM and IEEE 1547 TM

Enabling Smart Grid Interoperability: A System of Systems Approach via IEEE P2030 TM and IEEE 1547 TM Enabling Smart Grid Interoperability: A System of Systems Approach via IEEE P2030 TM and IEEE 1547 TM Standards presented May 2010 by Tom Basso Electricity, Resources and Building Systems Integration Center

More information

Application for Operation of & Net Metering for Member-Owned Generation Name: Mailing Address: City: County: State: Zip Code: _

Application for Operation of & Net Metering for Member-Owned Generation Name: Mailing Address: City: County: State: Zip Code: _ Application for Operation of & Net Metering for Member-Owned Generation -------------- OWNER/APPLICANT INFORMATION Name: Mailing Address: City: County: State: Zip Code: _ Phone Number: Email Address:.Representative:

More information

Interconnection and Net Metering Service in Ohio

Interconnection and Net Metering Service in Ohio Interconnection and Net Metering Service in Ohio Partnership between National Association of Regulatory Utility Commissioners and The National Commission for Energy State Regulation of Ukraine June 20,

More information

INTERCONNECTION for GENERATING FACILITIES Up to 20 MW

INTERCONNECTION for GENERATING FACILITIES Up to 20 MW PROGRAM REQUIREMENTS Important Information from Your Local Non-Profit Utility INTERCONNECTION for GENERATING FACILITIES Up to 20 MW Interconnecting to the Electrical Distribution System of Public Utility

More information

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program. Electric Tariff _2nd Revised Sheet No. 72 Filed with Iowa Utilities Board Cancels _1st Sheet No. _72 Cooperative is a member of Central Iowa Power Cooperative (CIPCO), a generation and transmission cooperative

More information

Umatilla Electric Cooperative Net Metering Rules

Umatilla Electric Cooperative Net Metering Rules Umatilla Electric Cooperative Net Metering Rules Version: July 2017 Umatilla Electric Cooperative NET METERING RULES Rule 0005 Scope and Applicability of Net Metering Facility Rules (1) Rule 0010 through

More information

Technical Requirements for Renewable Energy Power System

Technical Requirements for Renewable Energy Power System Hotline: 2843 3228 Email address: RE@hkelectric.com Issued on 20 Nov 2018 1. Introduction 1.1. This document aims to provide the technical requirements for renewable energy power system (the REPS) connected

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT

More information

Louisville Gas and Electric Company

Louisville Gas and Electric Company P.S.C. Electric No. 11, Original Sheet No. 57 APPLICABLE In all territory served. AVAILABILITY OF SERVICE Available to any customer-generator who owns and operates a generating facility located on Customer

More information

Accidental Islanding of Distribution Systems with Multiple Distributed Generation Units of Various Technologies

Accidental Islanding of Distribution Systems with Multiple Distributed Generation Units of Various Technologies CIGRÉ-EPRI Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS Boston, MA, October 20-22, 2013 http : //www.cigre.org Accidental Islanding of Distribution Systems with Multiple Distributed Generation

More information

Renewable Grid Integration Research in the U.S.

Renewable Grid Integration Research in the U.S. Renewable Grid Integration Research in the U.S. Barry Mather Ph.D. NREL- Distributed Energy Systems Integration Group UNSW IEA PVPS Task 14 Workshop Sydney, AU November 26 th, 2013 NREL is a national laboratory

More information

PSNH INTERCONNECTION REQUEST

PSNH INTERCONNECTION REQUEST PSNH INTERCONNECTION REQUEST Send the completed Interconnection Request and required attachments to: Public Service of New Hampshire Attn: Michael Motta, Senior Engineer Supplemental Energy Sources P.

More information

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management Southern Company Interconnection Process Dexter Lewis Research Engineer Research and Technology Management Southern Company Outline Southern Company GPC Solar Interconnection Process Application requirements

More information

APPLICATION ELECTRICITY SERVICES. APPLICATION FOR THE CONNECTION OF SMALL SCALE EMBEDDED GENERATION Page 1

APPLICATION ELECTRICITY SERVICES. APPLICATION FOR THE CONNECTION OF SMALL SCALE EMBEDDED GENERATION Page 1 APPENDIX 2B APPLICATION ELECTRICITY SERVICES APPLICATION FOR THE CONNECTION OF SMALL SCALE EMBEDDED GENERATION Page 1 This application form for the connection of small scale embedded generation is for

More information

INTERCONNECTION REQUIREMENTS POLICY

INTERCONNECTION REQUIREMENTS POLICY Issue Date: January 8, 2018 Resolution No. 2097-18 INTERCONNECTION REQUIREMENTS POLICY 1. Purpose and Scope A. The purpose of these Interconnection Requirements is to establish rules for determining the

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner

More information

RULES FOR CUSTOMER INTERCONNECTION OF ELECTRIC GENERATING FACILITIES

RULES FOR CUSTOMER INTERCONNECTION OF ELECTRIC GENERATING FACILITIES RULES FOR CUSTOMER INTERCONNECTION OF ELECTRIC GENERATING FACILITIES Last Revised Date: October 15, 2015 Contents Chapter 1 - Purpose and Scope 2 Chapter 2 - Application of Rules 2 Chapter 3 - Definitions

More information

Planning for a Power Engineering Institute

Planning for a Power Engineering Institute Session Number 2233 Planning for a Power Engineering Institute Frank W. Pietryga, Gregory M. Dick, Jerry W. Samples University of Pittsburgh at Johnstown Abstract Anecdotal evidence suggests that emphasis

More information

INTERCONNECTION STANDARDS FOR COGENERATORS AND SMALL POWER PRODUCERS LA PLATA ELECTRIC ASSOCIATION, INC. DURANGO, COLORADO

INTERCONNECTION STANDARDS FOR COGENERATORS AND SMALL POWER PRODUCERS LA PLATA ELECTRIC ASSOCIATION, INC. DURANGO, COLORADO INTERCONNECTION STANDARDS FOR COGENERATORS AND SMALL POWER PRODUCERS LA PLATA ELECTRIC ASSOCIATION, INC. DURANGO, COLORADO SEPTEMBER 2006 Introduction The purpose of this document is to set forth the requirements

More information

Standards, Procedures and Policies for Grid Connection

Standards, Procedures and Policies for Grid Connection Standards, Procedures and Policies for Grid Connection CONTENTS 1 INTRODUCTION 1 2 EMBEDDED GENERATION 1 2.1.1 OUTLINE OF EMBEDDED GENERATION 1 2.1.2 CHANGES IN EMBEDDED GENERATION 1 2.1.3 ASPECTS OF EMBEDDED

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

Adaptive Power Flow Method for Distribution Systems With Dispersed Generation

Adaptive Power Flow Method for Distribution Systems With Dispersed Generation 822 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 17, NO. 3, JULY 2002 Adaptive Power Flow Method for Distribution Systems With Dispersed Generation Y. Zhu and K. Tomsovic Abstract Recently, there has been

More information

Comments on the Solar Alliance Proposal for Changes to New Jersey Interconnection Rules

Comments on the Solar Alliance Proposal for Changes to New Jersey Interconnection Rules Comments on the Solar Alliance Proposal for Changes to New Jersey Interconnection Rules Submitted to New Jersey Board of Public Utilities By Qado Energy Power Engineering Team August 12, 2011 1 Table of

More information

Large Electric Motor Reliability: What Did the Studies Really Say? Howard W Penrose, Ph.D., CMRP President, MotorDoc LLC

Large Electric Motor Reliability: What Did the Studies Really Say? Howard W Penrose, Ph.D., CMRP President, MotorDoc LLC Large Electric Motor Reliability: What Did the Studies Really Say? Howard W Penrose, Ph.D., CMRP President, MotorDoc LLC One of the most frequently quoted studies related to electric motor reliability

More information

Guidelines for connection of generators:

Guidelines for connection of generators: Guidelines for connection of generators: Greater than 30 kva, and not greater than 10 MW, to the Western Power distribution network January, 2017. EDM 32419002 / DM 13529244 Page 1 of 14 Contents 1 INTRODUCTION...

More information

TODAY S electric system is expected to bring high-quality

TODAY S electric system is expected to bring high-quality IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 49, NO. 6, NOVEMBER/DECEMBER 2013 2741 Optimum Sizing and Placement of Distributed and Renewable Energy Sources in Electric Power Distribution Systems Benjamin

More information

Generating Unit Model Validation Policy

Generating Unit Model Validation Policy Generating Unit Model Validation Policy approved by WECC BOT WECC Generator Testing Task Force History August 10, 1996 WSCC Outage 4600 Observed COI Power (Dittmer Control Center) Real event 4400 4200

More information

City of Washington, Kansas Electric Department. Net Metering Policy & Procedure For Customer-Owned Renewable Energy Resources

City of Washington, Kansas Electric Department. Net Metering Policy & Procedure For Customer-Owned Renewable Energy Resources Ordinance No. 743 Exhibit A City of Washington, Kansas Electric Department Net Metering Policy & Procedure For Customer-Owned Renewable Energy Resources Page 1 of 7 1. INTRODUCTION The provisions of this

More information

Some of the main objectives of the Smart Grid initiatives in the State of California are:

Some of the main objectives of the Smart Grid initiatives in the State of California are: Standards, Rules, and Issues for Integration of Renewable Resources M.Y. Vaziri-Senior Member IEEE, S. Vadhva-Member, S. Ghadiri-Member C. J. Hoffman-Student Member, K. K. Yagnik-Student Member Abstract-

More information

DG Standard Updates. IEEE 1547, UL 1741 SA, and Rule 21 CHASE SUN GII/PG&E 3/28/18

DG Standard Updates. IEEE 1547, UL 1741 SA, and Rule 21 CHASE SUN GII/PG&E 3/28/18 DG Standard Updates IEEE 1547, UL 1741 SA, and Rule 21 CHASE SUN GII/PG&E 3/28/18 DER Interconnection Standards Chronology Arab Oil Embargo 1973 Gas Rationing. Oil went from $3/barrel (gas at $ 0.35/gal)

More information

Solar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011

Solar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011 Solar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011 Jim Calore Public Service Electric & Gas Co. Overview This

More information

Presentation to the PJM NEMSTF Interconnection Issues. Interconnecting Solar Projects on the PSE&G Distribution System

Presentation to the PJM NEMSTF Interconnection Issues. Interconnecting Solar Projects on the PSE&G Distribution System Interconnecting Solar Projects on the PSE&G Distribution System This presentation is intended to be a brief discussion of the effects of interconnecting of large amounts of solar generation on the distribution

More information

MISSOURI SERVICE AREA

MISSOURI SERVICE AREA MO.P.S.C. SCHEDULE NO. 6 2nd Revised 170 6 1st Revised 170 FROM QUALIFYING FACILITIES 1. *STANDARD RATES FOR PURCHASE The standard rates for purchase from a customer with a design capacity of 100 kw or

More information

Proposed New ISO Rules Section Version 2.0 Generating Unit Technical Requirements ( New ISO Rules Section Version 2.

Proposed New ISO Rules Section Version 2.0 Generating Unit Technical Requirements ( New ISO Rules Section Version 2. Stakeholder Comment and Rationale Form AESO AUTHORITATIVE DOCUMENT PROCESS Stakeholder Consultation Draft 2012-11-29 Proposed New ISO Rules Section 502.5 Version 2.0 Generating Unit Technical Requirements

More information

Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018

Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018 Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018 Outlined below are the engineering documents and their associated minimum detail requirements for a Distributed Energy Resource (DER)

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Designing and Maintaining a Pollution-Resilient Electric Power System. Managing Pollution Issues

Designing and Maintaining a Pollution-Resilient Electric Power System. Managing Pollution Issues Designing and Maintaining a Pollution-Resilient Electric Power System Tom McDermott IEEE/PES T&D Conference April 21-24, 2008 Chicago, IL Managing Pollution Issues Define the metrics, and measure them

More information

Purpose. Background. Exclusions

Purpose. Background. Exclusions Guidance No. 1 for the Interconnection of Electric Storage as Stand-Alone Sources, Parallel Operation for Customers without Generation, and in Parallel with Self-Generation 1 Purpose This document provides

More information

Large Scale Solar Integration

Large Scale Solar Integration Large Scale Solar Integration Experiences and Coming Changes in Distributed Energy Resource Interconnections October 26 th, 2017 Overview Background on Xcel Energy Expansion of Solar in Minnesota Changes

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd Embedded Generation - Technical Access Standards Embedded Generation - 5 MW or Greater ELE SP 0003 Public 1 October 2014 TABLE OF CONTENTS TABLE OF CONTENTS Abbreviations...

More information

AGRALITE ELECTRIC COOPERATIVE 320 EAST HIGHWAY 12 P.O. BOX 228 BENSON, MN PHONE: (320) FAX: (320)

AGRALITE ELECTRIC COOPERATIVE 320 EAST HIGHWAY 12 P.O. BOX 228 BENSON, MN PHONE: (320) FAX: (320) AGRALITE ELECTRIC COOPERATIVE 320 EAST HIGHWAY 12 P.O. BOX 228 BENSON, MN 56215-0228 PHONE: (320) 843-4150 FAX: (320) 843-3738 www.agralite.coop Thank you for your interest to interconnect Distributed

More information

Update on State Solar Net Metering Activities Lori Bird, NREL RPS Collaborative Summit Washington, DC September 23, 2014

Update on State Solar Net Metering Activities Lori Bird, NREL RPS Collaborative Summit Washington, DC September 23, 2014 Update on State Solar Net Metering Activities Lori Bird, NREL RPS Collaborative Summit Washington, DC September 23, 2014 NREL is a national laboratory of the U.S. Department of Energy, Office of Energy

More information

PV Grid Integration Research in the U.S.

PV Grid Integration Research in the U.S. PV Grid Integration Research in the U.S. Barry Mather Ph.D. NREL- Power Systems Engineering Center HEPIA IEA PVPS Task 14 Utility Workshop Geneva, Switzerland March 31 st, 2014 NREL is a national laboratory

More information

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER 1 Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER Lisa Dangelmaier Hawaii Electric Light lisa.dangelmaier@hawaiielectriclight.com Hawai'i Electric Light System Overview

More information

What, Why, and Where? Brian Lips Senior Project Manager for Policy NC Clean Energy Technology Center

What, Why, and Where? Brian Lips Senior Project Manager for Policy NC Clean Energy Technology Center What, Why, and Where? Brian Lips Senior Project Manager for Policy NC Clean Energy Technology Center bclips@ncsu.edu About the 50 States of Solar Quarterly publication detailing state and utility distributed

More information

Small Generator Interconnection Program Interconnection Technical Requirements

Small Generator Interconnection Program Interconnection Technical Requirements General Program Information What is the purpose of the PGE Small Generator Interconnection Program? How do I initiate a distribution interconnection request for my project? The purpose of our Small Generator

More information

JEA Distributed Generation Policy Effective April 1, 2018

JEA Distributed Generation Policy Effective April 1, 2018 Summary This JEA Distributed Generation Policy is intended to facilitate generation from customer-owned renewable and non-renewable energy generation systems interconnecting to the JEA electric grid. The

More information

GENERATING FACILITY INTERCONNECTION APPLICATION. Part 1 Introduction and Overview

GENERATING FACILITY INTERCONNECTION APPLICATION. Part 1 Introduction and Overview Part 1 Introduction and Overview A. Applicability: This Generating Facility Interconnection Application (Application) is used to request the interconnection of a Generating Facility to Southern California

More information

NRS 097-series / Grid Code Discussion:

NRS 097-series / Grid Code Discussion: SASGI Meeting: NRS 097-series / Grid Code Discussion: Gerhard Botha Research, Testing and Development 2014/04/16 Overview Introduction What is NRS 097? What do we have? What do we want? Comparison of international

More information

Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group

Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group Table of Contents 1. Introduction... 1 2. Purpose... 1 3. Customer Eligibility...

More information

Distributed Generation Interconnection Policy

Distributed Generation Interconnection Policy Distributed Generation Interconnection Policy 1 Introduction Carroll Electric Membership Corporation Distributed Generation Interconnection Policy Carroll Electric Membership Corporation (herein after

More information

RULES ENABLING THE NET- METERING PROGRAM FOR RENEWABLE ENERGY

RULES ENABLING THE NET- METERING PROGRAM FOR RENEWABLE ENERGY RULES ENABLING THE NET- METERING PROGRAM FOR RENEWABLE ENERGY Outline 1. Introduction 2. Legal Basis 3. Scope, Applicability & Qualification 4. Interconnection Set-Up 5. Pricing Methodology 6. Net-Metering

More information

American Electric Power s Energy Storage Deployments

American Electric Power s Energy Storage Deployments American Electric Power s Energy Storage Deployments 1 2 American Electric Power : Company Profile The Evolution of the Electric Utility System Before Smart Grid: One-way power flow, simple interactions,

More information

Consumer Guidelines for Electric Power Generator Installation and Interconnection

Consumer Guidelines for Electric Power Generator Installation and Interconnection Consumer Guidelines for Electric Power Generator Installation and Interconnection Habersham EMC seeks to provide its members and patrons with the best electric service possible, and at the lowest cost

More information

City of, Kansas Electric Department. Net Metering Policy & Procedures for Customer-Owned Renewable Energy Resources

City of, Kansas Electric Department. Net Metering Policy & Procedures for Customer-Owned Renewable Energy Resources Ordinance No. Exhibit A ----------------------------------------- City of, Kansas Electric Department Net Metering Policy & Procedures for Customer-Owned Renewable Energy Resources -------------------------------------

More information

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND

More information

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th Alex Bettencourt Managing Director National Association Made Up of Entire Industry Utilities Industry Academia / R&D

More information

Exelon Energy Delivery Interconnection Guidelines for Generators 2 MVA or less

Exelon Energy Delivery Interconnection Guidelines for Generators 2 MVA or less Exelon Energy Delivery Interconnection Guidelines for Generators 2 MVA or less Original: October 31, 2006 Table of Contents: INTRODUCTION and SCOPE... 3 DEFINITIONS... 3 QUALIFICATIONS FOR AN EXPEDITED

More information

TECHNICAL REQUIREMENTS FOR PARALLEL OPERATION OF MEMBER-OWNED GENERATION

TECHNICAL REQUIREMENTS FOR PARALLEL OPERATION OF MEMBER-OWNED GENERATION TECHNICAL REQUIREMENTS FOR PARALLEL OPERATION OF MEMBER-OWNED GENERATION EFFECTIVE JANUARY 27, 2014 TECHNICAL CONSIDERATIONS COVERING PARALLEL OPERATIONS OF CUSTOMER OWNED GENERATION INTERCONNECTED WITH

More information

Connecting your business diesel generation

Connecting your business diesel generation Connecting your business diesel generation March 2018 For connections more than 10kW 2 Contents Introduction to large distributed generation systems 3 Congestion management and safety 6 Application form

More information