1 ASP General Information Metering and Connection Policy Alert Number: GI34_16 Subject: NSW Solar Bonus Scheme Net Conversions 23 November 2016 Background The NSW Solar Bonus Scheme (SBS) payments will cease at midnight 31 December NSW SBS customers have been encouraged to look at an option to convert their gross metered generation systems to a net metered system once the NSW SBS closes. So as to maximise payments under the SBS, it is of most benefit to NSW SBS customers that this conversion occurs as close as practicable to the 31 December The customer has the power of choice, to either engage an electricity retailer to provide an advanced metering solution, or engage an ASP2 to arrange for the installation of an Ausgrid net Type 5 meter. The link to Ausgrid s website out lining NSW SBS follows: Submission of Connection Applications for Gross to Net Conversion Not Required. Ausgrid does not require ASPs or MPs to submit an Ausgrid Connection Application form for a NMI where a Gross to Net conversion is proposed to be converted. NOTE: If any service works, addition or removal of load or generation occurs, a relevant Ausgrid Connection Application form MUST be submitted. If a Connection Application for a Gross to Net Changeover is submitted to Ausgrid, it will be returned to the connection applicant stating a Connection Application is not required. A Basic Connection Offer fee will not be levied to the connection applicant in these situations. Use of Job Numbers to Order Meters for Gross to Net Conversion Not Required. Ausgrid has reviewed the requirement mandating that an Ausgrid issued job number must be used to order meters for Gross to Net conversions. All ASP2s can order net metering configurations for Gross to Net conversions directly from local meter store without a job number, this will be added to your normal meter quota. Approval for bulk meter issue of metering equipment as defined in ES4 is not required in this instance. Meter issue maximum level will still be enforced. Meter must be installed within 30 days of issue, otherwise they will become overdue and meter issue will be suspended. Metering equipment picked under this conversion application process, cannot be used on New or Upgrade works. The normal connection application and job number / bulk issue process remains in place. Preferred Option - Net Metering Solution Ausgrid will allow ASP2s to pick up Type 5 net metering equipment and arrange installation of this net meter and the removal of the gross metering equipment as negotiated between the ASP2 and their customer. The ASP2 will be charged for the Type 5 metering equipment as per Ausgrid s Connection Policy Connection Charges document. See the link below: See Appendix 3 for an example of the NOSW Details expected. Issued by: Metering Compliance and Regulation Date Issued: 23/11/2016 Copy to: level 2 How: level2asp@ausgrid.com.au

2 Alternative Conversion Solution Gross Rewire (Limited Application) Ausgrid has developed an alternate solution for NSW SBS customer wishing to convert from gross to net Type 5 metering. It is being referred to as the Gross Rewire metering solution. This solution takes advantage of the fact that the gross meter is programmed to measure energy flows in both directions (to measure any inverter load that may be consumed whilst the inverter is in standby mode). NOTE: This solution is only applicable in the following scenario: Single Phase with Separate Single Phase Gross Metering. This scenario applies to approximately 30% of the 42,000 gross metered installations connected to Ausgrid s network. Process On or near the 1 January 2017 the following process occurs: 1. Onsite works involve, ASP2 leaves gross meter onsite and rewires the installation so that SBS generation and customer load are connected to gross meter in a net manner as detailed in Appendix 1; IMPORTANT: Ensure cabling from SPD/MPD to Str 25 meter and cable from Str 25 meter to Domestic main switch are adequately sized to handle expected load and that switchboard labelling is updated to reflect any new arrangement; 2. ASP2 removes uni directional Type 5 meter (i.e Str 19 ); 3. ASP2 submits NOSW to Ausgrid showing the removal of the Str 19 meter and also identifies that the Str 25 gross meter has now been rewired to a net configuration. 4. The NOSW must be labelled Gross Rewire. See Appendix 2 as an example. REPEATING - This solution will only work where single phase load and single phase gross generation are onsite in the configurations detailed in the scenario above. This solution will not work where the site has 3 phase load or any scenario that does not match the scenario above. Note: ASP2s should only utilise the Alternate conversion solution if they are confident using this process. Any divergences from the above process will result in a defect being raised and additional costs to the ASP2 to rectify. Regards Ausgrid Project Officers

3 Appendix 1 Gross Rewire Diagram. Existing SBS Customer Single Phase with Separate Single Phase Gross (Str19) (Str25) General Supply N Solar Convert Gross Re-Wire (Str19) (Str25) General Supply N Solar Protection

4 Appendix 2 NOSW Details for Gross Rewire Solution.

5 Appendix 3 NOSW Details for Gross to Net Replacement.

Review of General Information Notices and Safety Alerts

Review of General Information Notices and Safety Alerts Review of General Information Notices and Safety Alerts SA04_17 Cable strike incident When working near or around underground cables always follow the requirements of NS156 and where required NS165 (in

More information

JEA Distributed Generation Policy Effective April 1, 2018

JEA Distributed Generation Policy Effective April 1, 2018 Summary This JEA Distributed Generation Policy is intended to facilitate generation from customer-owned renewable and non-renewable energy generation systems interconnecting to the JEA electric grid. The

More information

Connecting to the network information pack Version 5

Connecting to the network information pack Version 5 Connecting to the network information pack Version 5 Updated: Contents 1.0 What is a new connection or connection alteration?... 3 2.0 Connection enquiry... 3 3.0 Connection application... 3 3.1 Processing

More information

Customers with solar PV units in NSW producing and consuming electricity

Customers with solar PV units in NSW producing and consuming electricity Independent Pricing and Regulatory Tribunal FACT SHEET Customers with solar PV units in NSW producing and consuming electricity Based on Solar feed-in tariffs - Setting a fair and reasonable value for

More information

Customers with solar PV units in NSW producing and consuming electricity

Customers with solar PV units in NSW producing and consuming electricity Independent Pricing and Regulatory Tribunal FACT SHEET Customers with solar PV units in NSW producing and consuming electricity Based on Solar feed-in tariffs - Setting a fair and reasonable value for

More information

Renewable Net Metering Program Appendix ESD APX 001 1

Renewable Net Metering Program Appendix ESD APX 001 1 CITY OF ST.GEORGE Energy Services Department (SGESD) Renewable Net Metering Program Appendix Document No. Effective Date 10/15/2005 Revision No. 1.0 Review Date 02/18/2016 Review Cycle Annually Creation

More information

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Adopted Based on State and Tariff Interconnection Rules Applicable to Northern States Power,

More information

Final report. Solar feed-in tariff report

Final report. Solar feed-in tariff report Final report Solar feed-in tariff report 2016 17 October 2017 We wish to acknowledge the contribution of the following staff to this report: Thomas Gardiner, Adam Liddy Queensland Competition Authority

More information

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Adopted Based on State and Tariff Interconnection Rules Applicable to Northern States Power,

More information

SCHEDULE 6 RESIDENTIAL SERVICE ON-SITE GENERATION

SCHEDULE 6 RESIDENTIAL SERVICE ON-SITE GENERATION I.P.U.C. No. 29, Tariff No. 101 Original Sheet No. 6-1 PUBLIC UTILITIES COMMISSION AVAILABILITY Service under this schedule is available at points on the Company's interconnected system within the State

More information

Purpose. Background. Exclusions

Purpose. Background. Exclusions Guidance No. 1 for the Interconnection of Electric Storage as Stand-Alone Sources, Parallel Operation for Customers without Generation, and in Parallel with Self-Generation 1 Purpose This document provides

More information

Major Customer Connections. Preliminary Enquiry Form Embedded Generation > 30 kw

Major Customer Connections. Preliminary Enquiry Form Embedded Generation > 30 kw Major Customer Connections Preliminary Enquiry Form Embedded Generation > 30 kw MARCH 2018 Privacy Notice Ergon Energy is collecting information (including personal information) on this form for the purposes

More information

MENARD ELECTRIC COOPERATIVE POLICY MANUAL. SECTION IV Operating Rules for Cooperative Members

MENARD ELECTRIC COOPERATIVE POLICY MANUAL. SECTION IV Operating Rules for Cooperative Members 49.1 INTERCONNECTION OF AND SERVICE TO QUALIFYING FACILITIES UNDER Objective To provide for the interconnection of and service to a Qualifying Facility in keeping with the provisions of the Public Utility

More information

ENERGY STRATEGY FOR YUKON. Net Metering Policy DRAFT FOR CONSULTATION

ENERGY STRATEGY FOR YUKON. Net Metering Policy DRAFT FOR CONSULTATION ENERGY STRATEGY FOR YUKON Net Metering Policy DRAFT FOR CONSULTATION February 2011 Page 1 of 4 BACKGROUND The Yukon government released the Energy Strategy for Yukon in January 2009. The Energy Strategy

More information

MINIMUM REQUIREMENTS FOR PLACEMENT ON ROTATION

MINIMUM REQUIREMENTS FOR PLACEMENT ON ROTATION MANAGEMENT DIRECTIVE TOWING ROTATION LIST RULES Promulgated Pursuant to the Administrative Procedures Act Authority - Ark. Code Ann. 12-8-106(a)(2) Effective date - June 6, 2005 RULE 1: OWNER S PREFERENCE

More information

Umatilla Electric Cooperative Net Metering Rules

Umatilla Electric Cooperative Net Metering Rules Umatilla Electric Cooperative Net Metering Rules Version: July 2017 Umatilla Electric Cooperative NET METERING RULES Rule 0005 Scope and Applicability of Net Metering Facility Rules (1) Rule 0010 through

More information

Solar*Rewards Community Engineering Frequently Asked Questions For Garden Operators Minnesota

Solar*Rewards Community Engineering Frequently Asked Questions For Garden Operators Minnesota P a g e 1 Solar*Rewards Community Engineering Frequently Asked Questions For Garden Operators Minnesota The purpose of this document is to provide Garden Operators further documentation of engineering

More information

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Adopted Based on State and Tariff Interconnection Rules Applicable to Northern States Power,

More information

BACS APPROVED BUREAU SCHEME SUPPORT GUIDELINES

BACS APPROVED BUREAU SCHEME SUPPORT GUIDELINES BACS APPROVED BUREAU SCHEME SUPPORT GUIDELINES VERSION 2.03 10 NOVEMBER 2017 CONTENTS 1 DOCUMENT INFORMATION... 3 1.1 VERSION HISTORY... 3 1.2 COPYRIGHT STATEMENT... 3 2 INTRODUCTION... 4 2.1 BACS PAYMENT

More information

Heber Light & Power Electric Service Rule No. 14 NET METERING SERVICE

Heber Light & Power Electric Service Rule No. 14 NET METERING SERVICE Heber Light & Power Electric Service Rule No. 14 NET METERING SERVICE 1. Overview The Company offers Residential and Small General Service Customers net metering service that allows the Customer to use

More information

M.P.S.C. No. 2 Electric Third Revised Sheet No. 65 (Rate Case) Cancels Second Revised Sheet No. 65

M.P.S.C. No. 2 Electric Third Revised Sheet No. 65 (Rate Case) Cancels Second Revised Sheet No. 65 M.P.S.C. No. 2 Electric Third Revised Sheet No. 65 (Rate Case) Cancels Second Revised Sheet No. 65 CLASS OF SERVICE: CUSTOMER GENERATING SYSTEMS OVER 20 KW RATE CGS 1 AVAILABILITY To customers owning generating

More information

For personal use only

For personal use only AER ISSUES NETWORK REVENUES DRAFT DECISIONS FOR ACT AND NSW ENERGY CUSTOMERS The Australian Energy Regulator (AER) has issued draft decisions on the revenue proposals submitted by ACT and NSW distribution

More information

SCHEDULE 84 CUSTOMER ENERGY PRODUCTION NET METERING SERVICE

SCHEDULE 84 CUSTOMER ENERGY PRODUCTION NET METERING SERVICE Idaho Power Company Fourth Revised Sheet No. 84-1 I.P.U.C. No. 29, Tariff No. 101 Third Revised Sheet No. 84-1 AVAILABILITY Issued per Order No. 34046 June 1, 2018 Service under this schedule is available

More information

d. Note: LPG conversions are acceptable providing the relevant Vehicle Declaration is completed by the HSVOC Registrar.

d. Note: LPG conversions are acceptable providing the relevant Vehicle Declaration is completed by the HSVOC Registrar. Title: Historic & Classic Vehicles Registration Rules Number of Pages: 5 Reviewed By: Michael Benton Issue Date: 9 th November 2018 UNCONTROLLED IF PRINTED Replaces Issue: 12th February 2017 1. BACKGROUND

More information

SOUTH HADLEY ELECTRIC LIGHT DEPARTMENT Net Metering Policy As Amended 03/23/16 By the South Hadley Municipal Light Board

SOUTH HADLEY ELECTRIC LIGHT DEPARTMENT Net Metering Policy As Amended 03/23/16 By the South Hadley Municipal Light Board SOUTH HADLEY ELECTRIC LIGHT DEPARTMENT Net Metering Policy As Amended 03/23/16 By the South Hadley Municipal Light Board Policy Description: In an effort to ensure fair treatment of all of its customers,

More information

Direct Energy Regulated Services

Direct Energy Regulated Services Decision 23986-D01-2018 Application for True-Up of the 2017 and 2018 Interim Rates for the Default Rate Tariff and the Regulated Rate Tariff December 4, 2018 Alberta Utilities Commission Decision 23986-D01-2018

More information

Licensing Committee 20 January 2016

Licensing Committee 20 January 2016 Licensing Committee 20 January 2016 Agenda Item No: 6 Report Title Accountable Strategic Director Originating service Review of Fees and Charges for Hackney Carriage and Private Hire Licensing functions

More information

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program. Electric Tariff _2nd Revised Sheet No. 72 Filed with Iowa Utilities Board Cancels _1st Sheet No. _72 Cooperative is a member of Central Iowa Power Cooperative (CIPCO), a generation and transmission cooperative

More information

Duke Energy Carolinas North Carolina Interconnection Request Checklist

Duke Energy Carolinas North Carolina Interconnection Request Checklist Duke Energy Carolinas North Carolina Interconnection Request Checklist The North Carolina Utilities Commission issued North Carolina Interconnection Procedures, Forms, And Agreements For State-Jurisdictional

More information

Solar and Smart Meter Update. 1 April 2014 to 30 June 2014 Released July 2014

Solar and Smart Meter Update. 1 April 2014 to 30 June 2014 Released July 2014 Solar and Smart Meter Update 1 April 2014 to 30 June 2014 Released July 2014 2 CONTENTS 1. Solar and Smart Meter Cases... 3 2. SMART METER UPDATE... 4 2.1. EWOV Smart Meter Cases Increase by 36%... 4 2.2.

More information

THE COUNCIL OF STATE GOVERNMENTS RESOLUTION SUPPORTING ELECTRIC POWER GRID MODERNIZATION TO ACHIEVE ENERGY EFFICIENCY AND DEMAND REDUCTION BENEFITS

THE COUNCIL OF STATE GOVERNMENTS RESOLUTION SUPPORTING ELECTRIC POWER GRID MODERNIZATION TO ACHIEVE ENERGY EFFICIENCY AND DEMAND REDUCTION BENEFITS THE COUNCIL OF STATE GOVERNMENTS RESOLUTION SUPPORTING ELECTRIC POWER GRID MODERNIZATION TO ACHIEVE ENERGY EFFICIENCY AND DEMAND REDUCTION BENEFITS Resolution Summary The resolution offers numerous findings,

More information

Basic Connection Services Application and Price Guide

Basic Connection Services Application and Price Guide Basic Connection Services Application and Price Guide 2016-17 Disclaimer TasNetworks (which, for the purposes of this disclaimer, includes all of its related bodies corporate, its officers, employees,

More information

Queensland Electricity Connection and Metering Manual

Queensland Electricity Connection and Metering Manual Queensland Electricity Connection and Service and Installation Rules Issued Date: 01/12/2017, Effective Date: 01/12/2017 THIS PAGE HAS BEEN DELIBERATELY LEFT BLANK Check this is the latest version before

More information

Monitoring report. Solar feed-in tariff report

Monitoring report. Solar feed-in tariff report Monitoring report Solar feed-in tariff report 2017 18 October 2018 We wish to acknowledge the contribution of the following staff to this report: Karan Bhogale, Shannon Murphy and Thomas Gardiner Queensland

More information

Powering Sydney s Future

Powering Sydney s Future Powering Sydney s Future Frequently Asked Questions December 2017 Project background Q: Why is this project needed? A: Inner Sydney is one of the most critical parts of the NSW electricity network. However,

More information

Dominion Energy Instructional Guide for Completing Virginia Form NMIN

Dominion Energy Instructional Guide for Completing Virginia Form NMIN Complete Sections 1 through 4, sign the form at the bottom, and submit to Dominion Energy either by scanning and e-mailing to net.metering@dominionenergy.com, or send by US Mail to Dominion Energy, Net

More information

International Road Haulage Permits Guidance on Determining Permit Allocations. Moving Britain Ahead

International Road Haulage Permits Guidance on Determining Permit Allocations. Moving Britain Ahead International Road Haulage Permits Guidance on Determining Permit Allocations Moving Britain Ahead November 2018 The Department for Transport has actively considered the needs of blind and partially sighted

More information

Connecting your home or small business generation

Connecting your home or small business generation Connecting your home or small business generation For connections 10kW or less March 2018 2 Contents Introduction to small distributed generation systems 3 Congestion management and safety 6 Application

More information

CITY OF SASKATOON ADMINISTRATIVE POLICY

CITY OF SASKATOON ADMINISTRATIVE POLICY ORIGIN/AUTHORITY Administration and Finance Committee Report No. 13-2007; and Item 8.4.2 of Standing Policy Committee on Environment, Utilities and Corporate Services Report June 22, 2015; and Leadership

More information

City of Washington, Kansas Electric Department. Net Metering Policy & Procedure For Customer-Owned Renewable Energy Resources

City of Washington, Kansas Electric Department. Net Metering Policy & Procedure For Customer-Owned Renewable Energy Resources Ordinance No. 743 Exhibit A City of Washington, Kansas Electric Department Net Metering Policy & Procedure For Customer-Owned Renewable Energy Resources Page 1 of 7 1. INTRODUCTION The provisions of this

More information

Final Report. Solar feed in tariff for regional Queensland for

Final Report. Solar feed in tariff for regional Queensland for Final Report Solar feed in tariff for regional Queensland for 2014 15 May 2014 Table of Contents Table of Contents 1 INTRODUCTION 1 1.1 Terms of reference 1 1.2 Background 1 1.3 About this review 2 1.4

More information

REGFORM s Missouri Air Seminar The Clean Air Act Section 112(r)(1) General Duty Clause March 2, 2017 Bob Lambrechts Lathrop & Gage LLP

REGFORM s Missouri Air Seminar The Clean Air Act Section 112(r)(1) General Duty Clause March 2, 2017 Bob Lambrechts Lathrop & Gage LLP REGFORM s Missouri Air Seminar The Clean Air Act Section 112(r)(1) General Duty Clause March 2, 2017 Bob Lambrechts GENERAL DUTY CLAUSE APPLICABILITY Under the Clean Air Act Section 112(r)(1), the General

More information

BACS APPROVED BUREAU SCHEME SUPPORT GUIDELINES

BACS APPROVED BUREAU SCHEME SUPPORT GUIDELINES BACS APPROVED BUREAU SCHEME SUPPORT GUIDELINES VERSION 8.2 May 2017 CONTENTS 1 DOCUMENT INFORMATION 4 1.1 VERSION HISTORY 4 1.2 DOCUMENT REVIEWERS 4 1.3 COPYRIGHT STATEMENT 4 2 CONFIDENTIALITY 4 3 INTRODUCTION

More information

Fuel Mix Disclosure 2016

Fuel Mix Disclosure 2016 An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Fuel Mix Disclosure 2016 Information Paper Reference: CRU/17288 Date Published: 06/10/2017 Closing Date: N/A 0 www.cru.ie Executive

More information

EASTERN ILLINI ELECTRIC COOPERATIVE REGULATION NO. 26A

EASTERN ILLINI ELECTRIC COOPERATIVE REGULATION NO. 26A EASTERN ILLINI ELECTRIC COOPERATIVE REGULATION NO. 26A SUBJECT: Interconnection of and Service to Qualifying Facilities under Public Utility Regulatory Policies Act (PURPA) OBJECTIVE: To provide, through

More information

GUIDELINES FOR PERMITTING PRIVATELY OWNED CIRCUITS COACHING / PRACTICE & OTHER NON-COMPETITION EVENTS

GUIDELINES FOR PERMITTING PRIVATELY OWNED CIRCUITS COACHING / PRACTICE & OTHER NON-COMPETITION EVENTS GUIDELINES FOR PERMITTING PRIVATELY OWNED CIRCUITS for COACHING / PRACTICE & OTHER NON-COMPETITION EVENTS Table of Contents Item 1.0 Background 2.0 Key Steps Step 1: Application For A Track Licence Step

More information

Marina Bay Sands Guidelines for Electrical and Wiring Service

Marina Bay Sands Guidelines for Electrical and Wiring Service Marina Bay Sands Guidelines for Electrical and Wiring Service 1) The supply of electrical mains in the licensed area of the event is an exclusive service offered by Marina Bay Sands (MBS). In the event

More information

registered with TRA as a carbon levy direct remitter for transportation fuels; or

registered with TRA as a carbon levy direct remitter for transportation fuels; or Tax and Revenue Administration (TRA) Transportation Fuels Carbon Levy Remitter Return Instruction Guide Date released / updated: January 2018 Transportation Fuels Carbon Levy Remitter Return Instruction

More information

Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna

Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna 800 021 ------------------------------------------------------------------------------------------------------------- ROOFTOP

More information

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY Table of Contents Chapter 1. Purpose and scope. Pg 3 Chapter 2. Application

More information

A detailed copy of the proposed tariff application can be downloaded from Kenya Power and the ERC websites /

A detailed copy of the proposed tariff application can be downloaded from Kenya Power and the ERC websites   / PRESS STATEMENT The Kenya Power & Lighting Company Limited (KPLC) has submitted an Application to the Energy Regulatory Commission (ERC) for approval of the proposed Electricity Tariffs and Tariff Structures

More information

BC Hydro Rate Schedule 1289 Revision 1 Effective: April 20, 2018 Page 6-1

BC Hydro Rate Schedule 1289 Revision 1 Effective: April 20, 2018 Page 6-1 Page 6-1 6. OTHER RATE SCHEDULE 1289 NET METERING SERVICE Availability For any Residential Service Customer and for any General Service Customer who: 1. installs a Generating Facility to generate electricity

More information

Criteria. As background, the US Environmental Protection Agency s Green Vehicle Guide states that:

Criteria. As background, the US Environmental Protection Agency s Green Vehicle Guide states that: GREEN COMMUNITIES Fuel efficient 4 Vehicles GRANT PROGRAM GUIDANCE Criteria INTRODUCTION Criteria Four of the Green Communities Program states that communities must purchase only fuel-efficient vehicles

More information

Price schedule for metering services 1 July 2017

Price schedule for metering services 1 July 2017 Price schedule for metering services 1 July 2017 1. Price schedule for metering services effective 1 July 2017 Metering services will be charged for at the AER determined rates as provided in the tables

More information

The Waste Electrical and Electronic Equipment Regulations 2013 (as amended) Notification of grant of approval of an authorised treatment facility

The Waste Electrical and Electronic Equipment Regulations 2013 (as amended) Notification of grant of approval of an authorised treatment facility Mr Simon Gilchrist BCMY LTD Unit 1 Fort Road Wick Littlehampton West Sussex Bn17 7QU Our ref: WEE/FX0002ZS/ATF Date: 09 November 2017 Dear Mr Simon Gilchrist, The Waste Electrical and Electronic Equipment

More information

New Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities

New Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities New Ulm Public Utilities Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities INDEX Document Review and History... 2 Definitions... 3 Overview... 3 Application

More information

Addressing ambiguity in how electricity industry legislation applies to secondary networks

Addressing ambiguity in how electricity industry legislation applies to secondary networks In Confidence Office of the Minister of Energy and Resources Chair, Cabinet Business Committee Addressing ambiguity in how electricity industry legislation applies to secondary networks Proposal 1 This

More information

THE CONNECTICUT LIGHT AND POWER COMPANY dba EVERSOURCE ENERGY AND THE UNITED ILLUMINATING COMPANY

THE CONNECTICUT LIGHT AND POWER COMPANY dba EVERSOURCE ENERGY AND THE UNITED ILLUMINATING COMPANY THE CONNECTICUT LIGHT AND POWER COMPANY dba EVERSOURCE ENERGY AND THE UNITED ILLUMINATING COMPANY Virtual Net Metering Application Effective November 18, 2016 This application form addresses virtual net

More information

July 16, Dear Mr. Randolph:

July 16, Dear Mr. Randolph: July 16, 2012 Edward F. Randolph Director of Energy Division California Public Utilities Commission 505 Van Ness Ave., Room 4004 San Francisco, CA 94102 Re: Southern California Edison Company Report on

More information

The relative site locations are detailed below with the main headquarters circled in blue and the new Fiji Airways Aviation Academy in green.

The relative site locations are detailed below with the main headquarters circled in blue and the new Fiji Airways Aviation Academy in green. Page 1 of 8 This is NOT the Expression of Interest Application Form. The Expression of Interest Application Form is a separate document. This information document is provided such that interested firms

More information

City of, Kansas Electric Department. Net Metering Policy & Procedures for Customer-Owned Renewable Energy Resources

City of, Kansas Electric Department. Net Metering Policy & Procedures for Customer-Owned Renewable Energy Resources Ordinance No. Exhibit A ----------------------------------------- City of, Kansas Electric Department Net Metering Policy & Procedures for Customer-Owned Renewable Energy Resources -------------------------------------

More information

AIR POLLUTION AND ENERGY EFFICIENCY. Guidelines for onboard sampling and the verification of the sulphur content of the fuel oil used on board ships

AIR POLLUTION AND ENERGY EFFICIENCY. Guidelines for onboard sampling and the verification of the sulphur content of the fuel oil used on board ships E MARINE ENVIRONMENT PROTECTION COMMITTEE 68th session Agenda item 3 MEPC 68/3/18 6 March 2015 Original: ENGLISH AIR POLLUTION AND ENERGY EFFICIENCY Guidelines for onboard sampling and the verification

More information

TECHNICAL ALERT No Rev.01

TECHNICAL ALERT No Rev.01 Technical Alert No. 16-12 Rev.01 Issue Date 20 September 2016 TECHNICAL ALERT No. 16-12 Rev.01 Sulphur Oxides Emission Regulations in China 1. Introduction 1.1. The People s Republic of China s Ministry

More information

Developments in Retail Electricity Markets

Developments in Retail Electricity Markets Developments in Retail Electricity Markets 2017 Australian Conference of Economists Sofitel Sydney, 21 July 2017 DR KRIS FUNSTON, kris.funston@aemc.gov.au SENIOR DIRECTOR, RETAIL AND WHOLESALE MARKETS

More information

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655) - (SMUD FORM 2655) A. Applicability: This Generating Facility Interconnection Application (Application) shall be used to request the interconnection of a Generating Facility to Sacramento Municipal Utility

More information

THE EU AND PALM OIL: WHAT S GOING ON?

THE EU AND PALM OIL: WHAT S GOING ON? THE EU AND PALM OIL: WHAT S GOING ON? RSPO Roundtable 9 Kota Kinabalu, 24 November 2011 Nina Činkole Delegation of the European Union to Malaysia 1 PRESENTATION OUTLINE EU Context & Policy background Biofuels:

More information

APPLICATION ELECTRICITY SERVICES. APPLICATION FOR THE CONNECTION OF SMALL SCALE EMBEDDED GENERATION Page 1

APPLICATION ELECTRICITY SERVICES. APPLICATION FOR THE CONNECTION OF SMALL SCALE EMBEDDED GENERATION Page 1 APPENDIX 2B APPLICATION ELECTRICITY SERVICES APPLICATION FOR THE CONNECTION OF SMALL SCALE EMBEDDED GENERATION Page 1 This application form for the connection of small scale embedded generation is for

More information

European Regulation MRV. Luis Guerrero 2 nd November 2015

European Regulation MRV. Luis Guerrero 2 nd November 2015 European Regulation MRV Luis Guerrero 2 nd November 2015 CONTENTS THE EU MRV REGULATION GENERAL OBJECTIVE OF THE MRV REGULATION SCOPE OF THE MRV REGULATION METHOD FOR MONITORING CO2 EMISSIONS CALCULATION

More information

2017 PETROLIAM NASIONAL BERHAD (PETRONAS)

2017 PETROLIAM NASIONAL BERHAD (PETRONAS) 2017 PETROLIAM NASIONAL BERHAD (PETRONAS) All rights reserved. No part of this document may be reproduced in any form possible, stored in a retrieval system, transmitted and/or disseminated in any form

More information

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION Work Order No: File Reference: 16/2/1 This application form for the connection of small scale embedded generation is for small

More information

energy price fact sheet - electricity

energy price fact sheet - electricity energy price fact sheet - electricity - New South Wales - Ausgrid Distribution Zone Domestic Single Rate Usage of first 10.9589 kwh/day cents per kwh 29.34 32.274 20.54 22.594 Usage of next 10.9589 kwh/day

More information

CUSC Modification Proposal Form CMP270

CUSC Modification Proposal Form CMP270 CUSC Modification Proposal Form CMP270 Connection and Use of System Code (CUSC) Title of the CUSC Modification Proposal Potential consequential changes to the CUSC as a result of CMP265 Submission Date

More information

BC Hydro writes in compliance with Exhibit A-4 to provide its Final Submission in respect of the Application (Exhibit B-1).

BC Hydro writes in compliance with Exhibit A-4 to provide its Final Submission in respect of the Application (Exhibit B-1). Ken Duke Solicitor & Counsel Phone: 604-623-3623 Fax: 604-623-3606 bchydroregulatorygroup@bchydro.com April 30, 2014 Sixth Floor 900 Howe Street Vancouver, BC V6Z 2N3 Dear Ms. Hamilton: RE: (BCUC) British

More information

Energy Regulation : Australian Experience. Engr.Khondkar Abdus Saleque

Energy Regulation : Australian Experience. Engr.Khondkar Abdus Saleque Energy Regulation : Australian Experience Engr.Khondkar Abdus Saleque 14/11/2014 Australian Energy Regulator Australia is a federal Country with Six Sates and two territories Victoria, NSW, Queensland,

More information

Application to Amend Net Metering Service under RS Appendix B. Revised RS 1289 Clean and Black-lined

Application to Amend Net Metering Service under RS Appendix B. Revised RS 1289 Clean and Black-lined Application to Amend Net Metering Service under RS 1289 Revised RS 1289 Clean and Black-lined Rate Schedule 1289 Revision 1 Effective: April 20, 2018 Page 6-1 Clean 6. OTHER RATE SCHEDULE 1289 NET METERING

More information

Interface Requirements for Grid Connection of Renewable Energy Power System

Interface Requirements for Grid Connection of Renewable Energy Power System Hotline: 2843 3228 Email address: RE@hkelectric.com Issued on 20 Nov 2018 1. Introduction 1.1. This document aims to provide the general requirements for meter position, metering arrangement, meter cubicles

More information

Net Metering in Illinois. Eric P. Schlaf Senior Economic Analyst Illinois Commerce Commission January 31, 2014

Net Metering in Illinois. Eric P. Schlaf Senior Economic Analyst Illinois Commerce Commission January 31, 2014 Net Metering in Illinois Eric P. Schlaf Senior Economic Analyst Illinois Commerce Commission January 31, 2014 Topics What is Net Metering Benefits of Net Metering Net Metering in US Net Metering in Illinois

More information

GOVERNMENT OF NCT OF DELHI

GOVERNMENT OF NCT OF DELHI 104 Compendium of State Government Policies on Renewable Energy Sector in India SI. No. GOVERNMENT OF NCT OF DELHI Draft Delhi Solar Energy Policy, 2015 Dated 10 th September, 2015 Description Summary

More information

Application for Net Export Rebate

Application for Net Export Rebate 1. Customer Information Premise Address: Application for Net Export Rebate Existing Utility Account number (load): Application Number : Date Received : 2. Contestability Status: Non-contestable Contestable

More information

Feed in tariffs in Australia - at a glance

Feed in tariffs in Australia - at a glance LB-Windservice Pty Ltd Renewable Energy PO Box 621 Byron Bay NSW 2481 mobile: 0401 373787 info@lb-windservice.com lb-windservice.com Feed in tariffs in Australia - at a glance Australia currently has no

More information

Garden waste charging: implementation and impact mitigation measures

Garden waste charging: implementation and impact mitigation measures Midlothian Council Tuesday 2 October 2018 Item No 8.9 Garden waste charging: implementation and impact mitigation measures Report by Head of Commercial Operations 1 Purpose of Report This paper outlines

More information

(KL) Jeep Cherokee

(KL) Jeep Cherokee Dealer Service Instructions for: Safety Recall S41 Wheel Flare Protection Spats Revised November 2016 NOTE: Inspection LOP changed to 0.1 hours and $5 inspection fee eliminated. Models 2014-2016 (KL) Jeep

More information

Municipality of Strathroy- Caradoc

Municipality of Strathroy- Caradoc Directed to: Prepared by: Department: Subject: Municipality of Strathroy- Caradoc Mayor Vanderheyden and Members of Council Mark Harris Environmental Services Strathroy WPCP Blower Replacement Update Page

More information

Large Embedded Generation User Guide A

Large Embedded Generation User Guide A Large Embedded Generation User Guide A For Generating Systems AS4777 compliant and up to 200kW January 2013 SA Power Networks www.sapowernetworks.com.au Table of Contents 1. Introduction... 3 1.1 Embedded

More information

PV SELF CONSUMPTION SCHEMES. Marie Latour. IEA-PVPS task 1 meeting, Aarhus, DK. 22 September OVERVIEW in EUROPE.

PV SELF CONSUMPTION SCHEMES. Marie Latour. IEA-PVPS task 1 meeting, Aarhus, DK. 22 September OVERVIEW in EUROPE. Marie Latour Senior National Policy Advisor Marie Latour PV SELF CONSUMPTION IEA-PVPS task 1 meeting, SCHEMES Aarhus, DK OVERVIEW in EUROPE 22 September 2012 Introduction PV self-consumption The possibility

More information

DEVELOPMENT OF DRAFT GUIDELINES FOR CONSISTENT IMPLEMENTATION OF REGULATION OF MARPOL ANNEX VI

DEVELOPMENT OF DRAFT GUIDELINES FOR CONSISTENT IMPLEMENTATION OF REGULATION OF MARPOL ANNEX VI E INTERSESSIONAL MEETING ON CONSISTENT IMPLEMENTATION OF REGULATION 14.1.3 OF MARPOL ANNEX VI Agenda item 2 25 May 2018 ENGLISH ONLY DEVELOPMENT OF DRAFT GUIDELINES FOR CONSISTENT IMPLEMENTATION OF REGULATION

More information

Newfoundland & Labrador USED TIRE MANAGEMENT PROGRAM TIRE SUPPLIER GUIDE

Newfoundland & Labrador USED TIRE MANAGEMENT PROGRAM TIRE SUPPLIER GUIDE Newfoundland & Labrador USED TIRE MANAGEMENT PROGRAM TIRE SUPPLIER GUIDE TABLE OF CONTENTS The following handbook is presented for general information. The contents in this document are subject to change

More information

Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group

Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group Table of Contents 1. Introduction... 1 2. Purpose... 1 3. Customer Eligibility...

More information

Norris Public Power District

Norris Public Power District Norris Public Power District Rate Schedules Board Approved: February 12, 2019 Effective: Bill Rendered After January 20, 2019 SCHEDULE 10, 12, 13, and 14 IRRIGATION SERVICE SINGLE or MULTIPHASE General

More information

Summary How UK haulage companies, drivers and freight services would be affected if the UK leaves the EU with no deal.

Summary How UK haulage companies, drivers and freight services would be affected if the UK leaves the EU with no deal. Commercial road haulage in the EU if there s no Brexit deal Summary How UK haulage companies, drivers and freight services would be affected if the UK leaves the EU with no deal. Detail If the UK leaves

More information

Draft Agenda. Item Subject Responsible Time. 4. GAS INFORMATION SERVICES PROJECT IMO 10 min. 5. OPTIONS FOR GAS BULLETIN BOARD SYSTEM IMO 15 min

Draft Agenda. Item Subject Responsible Time. 4. GAS INFORMATION SERVICES PROJECT IMO 10 min. 5. OPTIONS FOR GAS BULLETIN BOARD SYSTEM IMO 15 min Gas Advisory Board Draft Agenda Meeting No. 1 Location: Parmelia Hilton, Swan B Room 14 Mill Street, Perth WA 6000 Date: 20 December 2011 Time: 11:15am 12:15pm Item Subject Responsible Time 1. WELCOME

More information

Solar-Wind Specific Request for Proposals

Solar-Wind Specific Request for Proposals Program Description Solar-Wind Specific Request for Proposals Power Production from Green Resources in North Carolina 04/19/2006 NC GreenPower (NCGP) is a statewide program designed to improve the quality

More information

Export limits for Embedded Generators up to 200 kva connected at Low Voltage

Export limits for Embedded Generators up to 200 kva connected at Low Voltage Export limits for Embedded Generators up to 200 kva connected at Low Voltage Standard Operating Procedure Document number: SOP 33-06 Issue number: 5 Status: FINAL Approver: J Bridge Date of approval: 3

More information

Technical Support for Electric Vehicle Charging Requirements in the Building Code that are in effect January 1, 2018

Technical Support for Electric Vehicle Charging Requirements in the Building Code that are in effect January 1, 2018 Technical Support for Electric Vehicle Charging Requirements in the Building Code that are in effect January 1, 2018 Non-residential Buildings Questions and Answers Provided on December 19, 2017 This document

More information

ST. VINCENT AND THE GRENADINES

ST. VINCENT AND THE GRENADINES ST. VINCENT AND THE GRENADINES MARITIME ADMINISTRATION CIRCULAR N POL 022 FUEL OIL CONSUMPTION DATA COLLECTION SYSTEM Amendments to MARPOL Annex VI, MEPC.278(70) TO: APPLICABLE TO: EFFECTIVE AS FROM: SHIPOWNERS,

More information

Overview of Electricity Trade Agreement between Québec and Ontario. May 10, 2017 For Information Purposes Only

Overview of Electricity Trade Agreement between Québec and Ontario. May 10, 2017 For Information Purposes Only Overview of Electricity Trade Agreement between Québec and Ontario May 10, 2017 For Information Purposes Only Purpose To provide an overview of the electricity trade agreement between the Independent Electricity

More information

CITY OF HAMILTON BY-LAW NO

CITY OF HAMILTON BY-LAW NO Authority: Item 8, General Issues Committee Report 17-001 (PED16099(a)) CM: January 25, 2017 Bill No. 013 CITY OF HAMILTON BY-LAW NO. 17-013 To Amend By-law No. 07-170, a By-law to License and Regulate

More information

Basic tariff guiding principles

Basic tariff guiding principles Basic tariff guiding principles Small-scale Embedded Generation (SSEG) tariffs This brief outlines the basic guiding principles in tariff design for municipalities, to support and adapt to a changing electricity

More information

Interconnection Process Simplification Webinar

Interconnection Process Simplification Webinar Please stay tuned for the 1 Interconnection Process Simplification Webinar We will be starting momentarily last updated 3.4.13 2 Agenda Overview of PG&E s NEM Program What you need to know about NEM interconnections

More information

Certification Scheme

Certification Scheme Certification Scheme Water-based surface-embedded heating and cooling systems in accordance with DIN EN 1264 (Version: November 2009) DIN CERTCO Alboinstraße 56 12103 Berlin Tel: +49 30 7562-1131 Fax:

More information