Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications

Similar documents
Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

APPENDIX F: Project Need and Description

Merger of the generator interconnection processes of Valley Electric and the ISO;

Decision on Merced Irrigation District Transition Agreement

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Interconnection Feasibility Study Report GIP-084-FEAS-R2

TransWest Express Project

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

Updates. Pat Reiten President and CEO, PacifiCorp Transmission

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report

Interconnection Feasibility Study Report GIP-222-FEAS-R3

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

ABB POWER SYSTEMS CONSULTING

Black Hills Project Summary

TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016

Supplemental Report on the NCTPC Collaborative Transmission Plan

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

West Station-West Cañon 115 kv Transmission Project

100 MW Wind Generation Project

Interconnection Feasibility Study Report GIP-226-FEAS-R3

CUSTOMER/ TWIN ARROWS PROJECT

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

Interconnection System Impact Study Report Request # GI

Sub Regional RTEP Committee Western Region ATSI

Updates and Modifications to Report

Sub Regional RTEP Committee South

Guideline on Energy Storage

EIPC HIGH LEVEL TRANSMISSION COST ESTIMATION TASK #5: DOE PROJECT NO. DE-OE

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013

Project #148. Generation Interconnection System Impact Study Report

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

Gateway South Transmission Project

Table of Contents. Purpose. Eldorado Intertie and System (Eldorado- Moenkopi) Scheduling at Willow Beach. Operating Procedure

Appendix D Black Hills Project Summary

2015 Grid of the Future Symposium

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Generator Interconnection System Impact Study For

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

Feasibility Study Report

SDG&E Valley-Rainbow Project

MILLIGAN SOLAR PROJECT

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

SPS Planning Criteria and Study Methodology

Sub Regional RTEP Committee South

(2) Scope. 220 CMR applies to all Distribution Companies subject to the jurisdiction of the Department.

The Narragansett Electric Company. d/b/a National Grid (Interstate Reliability Project) RIPUC Dkt. No Testimony of. David M. Campilii, P.E.

Decision on the ISO Transmission Plan

City of Palo Alto (ID # 6416) City Council Staff Report

III. Substation Bus Configurations & Substation Design Recommendations

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis

FERC 101 for Environmental Lawyers. Linda L. Walsh Hunton & Williams LLP February 11, 2015

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis

Interconnection Feasibility Study Report GIP-157-FEAS-R2

SHORE POWER RATE BC HYDRO 333 DUNSMUIR STREET VANCOUVER, BC

D.P.U A Appendix B 220 CMR: DEPARTMENT OF PUBLIC UTILITIES

Appendix 6.7 January 23, 2015 SURPLUS ENERGY PROGRAM PROPOSED TERMS AND CONDITIONS

for DRECP Alternatives

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO.

Feasibility Study Report

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS

NERC-led Review Panel Decision on the Request of City of Pasadena Water and Power

Southeastern Regional Transmission Planning (SERTP)

SERTP rd Quarter Meeting

Falcon-Midway 115 kv Line Uprate Project Report

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study

Electrical Transmission System Analysis EE 456 project. Team Members Abdulaziz Almarzouqi Hamzah Abeer

Impact of Distributed Energy Resources on Transmission System Reliability

New Mexico Transmission Expansion Concepts For Wind Resources

APPENDIX E: ELECTRIC AND MAGNETIC FIELDS MANAGEMENT PLAN

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

SPP Notification to Construct

welcome to the BC Hydro community open house

WestConnect Regional Planning Update

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Q0044 interconnection at

Sub Regional RTEP Committee Mid-Atlantic

Maddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016

Reliability Analysis Update

PREPARED DIRECT TESTIMONY

MILESTONE SUMMARY REPORT Project funding provided by customers of Xcel Energy through a grant from the Renewable Development Fund

Transcription:

Supplement to 2013-2014 ISO Transmission Plan Harry Allen-Eldorado Project Description and Functional Specifications

Description and Functional Specifications of Proposed Economically Driven Harry Allen Eldorado 500 kv Line Project 1 Description In the 2013-2014 Transmission Plan, the ISO has identified an economically-driven need for a 500 kv transmission line between SCE majority owned Eldorado 500 kv substation and NV Energy owned Harry Allen 500 kv substation, as depicted below: Harry Allen Harry Allen-Eldorado line McCullough Crystal Mead Arizona Moenkopi Navajo Eldorado Mojave Victorville Lugo Existing ISO Controlled Existing Non-ISO Controlled Planned The estimated cost of the proposed 500 kv line is $144 million in 2015 dollars. This estimated cost excludes facilities necessary at the Eldorado and Harry Allen substations that will be installed by the owners of those substations. The economic justification for the project is dependent on its estimated cost, and as a result cost estimates and cost management information provided by project sponsors will be carefully considered with respect to the estimated cost assumed in the ISO s economic analysis. 1 The Harry Allen-Eldorado 500kV line was approved by the ISO Board of Governors at the December 18, 2014 Board meeting.

F5.1 Functional Specifications Transmission Line Functional Specifications Overhead Line Construction Line Terminus 1: Eldorado Substation 500 kv Bus Line Terminus 2: Harry Allen Substation 500 kv Bus Nominal Phase to Phase Voltage: 500 kv Minimum Line Continuous Ampacity - Summer: 3,800 Amps Minimum Line Continuous Ampacity Winter: 3,800 Amps Minimum Line 4 Hour Emergency Ampacity Summer: 5,200 Amps Minimum Line 4 Hour Emergency Ampacity Winter: 5,200 Amps Minimum Line 30 Minute Emergency Ampacity Summer: 5,600 Amps Minimum Line 30 Minute Emergency Ampacity Winter: 5,600 Amps Approximate Line Impedance: (0.0005 to 0.0006) + j(0.011 to 0.015) pu (100 MVA base). Approximate Line Length: 60 miles Approximate Series Compensation Level: 70%. Project Sponsor must include provisions to automatically bypass the series capacitor due to faults in the series capacitor. Project sponsor shall also include a means to isolate the series capacitor, such as a bypass switch to facilitate maintenance. The ampacity of this bypass switch should be no more limiting than the series capacitors. Location of Series Compensation: Anywhere in the line, including within the termination stations. The cost of the series compensation is within the scope of this project and will be the responsibility of the approved project sponsor.

Minimum Series Capacitor Continuous Ampacity - Summer: 2,700 Amps Minimum Series Capacitor Continuous Ampacity Winter: 2,700 Amps Minimum Series Capacitor 4 Hour Emergency Ampacity Summer: 2,700 Amps Minimum Series Capacitor 4 Hour Emergency Ampacity Winter: 2,700 Amps Minimum Series Capacitor 30 Minute Emergency Ampacity Summer: 3,645 Amps Minimum Series Capacitor 30 Minute Emergency Ampacity Winter: 3,645 Amps Latest In Service Date: May 1, 2020 Support Structures: Single circuit structures Transposition: The cost of transposing the line at two towers to create three approximately equidistant segments should be provided as a separate line item. Shield Wire Required: Optical ground wire (minimum 6 pairs of fibers) Failure Containment Loading Mitigation (anti-cascade structures, etc.): Per applicable codes Shield Wire Ground Fault Withstand Ampacity: Coordinate with interconnecting entities Aeolian Vibration Control (Conductor and Shield Wire): Vibration dampers must be installed on all conductors and overhead shield wires, with the exception of slack spans. Transmission Line Minimum BIL: 1,800 kv with solidly grounded systems Minimum ROW Width: Per applicable codes

Route Requirement: The transmission solution was developed on the basis that route would meet the applicable NERC/WECC standard so that Part 1.1.1 of Section E. Regional Differences of Standard FAC 010-2.1 related to the common mode contingency does not apply to the Harry Allen-Eldorado 500 kv line and any other 500 kv line. Alternatives that include multiple circuit structures will be considered only if the project sponsor provides mitigation for meeting system performance requirements as required by NERC/WECC reliability standards with no reduction in overall reliability. Further, the ISO will assess if this configuration reduces the net financial benefits of this economically-driven project. The ISO prefers a transmission solution that proposes sufficient spatial diversity that eliminates a common mode contingency. Governing Design and Construction Standards: (GO 95, NESC Code, applicable municipal codes) Additional Information The economic justification for this project is dependent on its cost, and as a result the CAISO will carefully consider binding cost caps and other cost containment measures, as well as cost management information. The approved project sponsor will be responsible for the interconnection costs to terminate the new transmission line inside Harry Allen substation. These costs will be eligible for cost recovery in accordance with ISO tariff Section 26.1. Key Selection Factors The ISO has identified an economically driven need for a 500 kv transmission line between Eldorado 500 kv substation, primarily owned by SCE, and Harry Allen 500 kv substation, which is owned by NV Energy. The key qualification criteria and selection factors as denoted in the ISO tariff are: 24.5.4 (a) the current and expected capabilities of the Project Sponsor and its team to finance, license, and construct the facility and operate and maintain it for the life of the solution. (This key selection factor is important because this 500 kv transmission line will be a major component in the ISO s bulk transmission system). 24.5.4 (d) the proposed schedule for development and completion of the transmission solution and demonstrated ability to meet that schedule of the Project Sponsor and its team; (This key selection factor is important because the economic benefits to ratepayers may decrease if the project goes into service later than May 2020). 24.5.4 (j) demonstrated cost containment capability of the Project Sponsor and its team, specifically, binding cost control measures the Project Sponsor agrees to accept, including any binding agreement by the Project Sponsor and its team to accept a cost cap that would preclude costs for the transmission solution above the cap from being recovered through the CAISO s Transmission Access Charge, and, if none of the competing Project Sponsors proposes a binding cost cap, the authority of the selected siting authority to impose binding cost caps or cost containment measures on the Project Sponsor, and its history of imposing such measures. (This key selection factor is important because the justification for this project is based on economic benefits to ratepayers).