POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF B 220 KV BUSBAR AT GEORGE TOWN ON 27 NOVEMBER 2012.

Similar documents
POWER SYSTEM OPERATING INCIDENT REPORT LIGHTNING STRIKES IN TASMANIA AND PACIFIC ALUMINIUM POTLINE LOAD REDUCTIONS 21 MARCH 2013

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011

POWER SYSTEM OPERATING INCIDENT REPORT MULTIPLE CONTINGENCY EVENT IN NORTH WEST TASMANIA ON 6 APRIL 2012

POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO KV BUSBAR ON 30 OCTOBER 2011

Power System Operating Incident Report Trip of Murray Lower Tumut No kv Transmission Line at Murray End Only on 18 November 2013

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

Power System Operating Incident Report Trip of Red Cliffs Horsham and Red Cliffs-Wemen Kerang 220 kv transmission lines on 15 January 2014

POWER SYSTEM INCIDENT REPORT NORTHERN POWER STATION STABILISER OUTAGE APRIL AND MAY 2010

TRIP OF HORSHAM-REDCLIFFS 220 KV TRANSMISSION LINE AND MURRAYLINK INTERCONNECTOR ON 12 NOVEMBER 2015

POWER SYSTEM INCIDENT REPORT: OVERLOAD OF WAUBRA- HORSHAM 220 KV TRANSMISSION LINE AND INSECURE OPERATION OF THE SYSTEM ON 13 DECEMBER 2012

MULTIPLE LINE OUTAGES IN THE MOUNT ENGLAND TARONG AREA IN QUEENSLAND, 13 FEBRUARY 2017

XXXXX. Kokish River Hydroelectric Project. Interconnection Facilities Study and Project Plan

SUBSTATION INTERLOCKING SCHEMES

ELECTRICITY TRANSMISSION USE OF SYSTEM PRICES - 1 JULY 2014 TO 30 JUNE 2015

The Energy Queensland Group Notice of no non-network options

South Australia Victoria (Heywood) Interconnector Upgrade. RIT-T: Project Specification Consultation Report

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Jemena Electricity Networks (Vic) Ltd

Final Capacity Auction Results 2018/2019 T-1 Capacity Auction. Date 26/01/2018 Version 1.0

AN RPM to TACH Counts Conversion. 1 Preface. 2 Audience. 3 Overview. 4 References

Final Capacity Auction Results 2019/2020 T-1 Capacity Auction. Date 01/02/2019 Document: FCAR1920T-1 Version 1.0

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Feasibility Study for the Q MW Solar Project

Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)*

MINIMUM OIL BURN/AUTOMATIC FUEL SWAPPING CAPABILITY

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

Enquiry Form for Micro and Small Generators 5MW and Less

Guidelines for connection of generators:

Transend Networks. Annual Planning Report

Emerald Reactive Support Alternative Solution Expressions of interest

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8

Enquiry Form (Non-Registered Generator With Capacity less than 5 MW)

Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR)

Basic Connection Services Application and Price Guide

The Ultimate Smart Grid Solution INSTRUCTION MANUAL

15 Nelson-Marlborough Regional Plan

Procedure PR D Electrical Permits. Engineering Procedure Electrical Distribution Unit. Version 1.0. Date in Force: 4 November 2015

Managing Electrical Safety on Boats

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Guideline for Parallel Grid Exit Point Connection 28/10/2010

NYISO Tariffs. New York Independent System Operator, Inc. Document Generated On: 2/27/2013

2016 Load & Capacity Data Report

Interconnection System Impact Study Report Request # GI

The Ultimate Smart Grid Solution INSTRUCTION MANUAL

TRANSMISSION PLANNING CRITERIA

SOUTH AUSTRALIAN HISTORICAL MARKET INFORMATION REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS

DESCRIPTION OF REQUIREMENTS FOR GENERATION SYSTEMS SEEKING TO PROVIDE SYSTEM RESTART SERVICES

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Back Up Power for Sochi

Engineering Instruction

Summary of Revision, IEEE C , Guide for Breaker Failure Protection of Power Circuit Breakers

100 MW Wind Generation Project

Scania Used Vehicle Extended Driveline Warranty

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Standard Battery Energy Storage System (BESS) Connection Arrangements

ISLANDING SCHEME FOR STATION DURING GRID BLACK-OUT

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study

BSCP31 Trading Unit Application for West Burton A&B Power Stations

Feasibility Study for the Q MW Solar Project

The Grid Link Project. Summary of the Report for the Independent Expert Panel

Energy Regulation : Australian Experience. Engr.Khondkar Abdus Saleque

Comparison of price incentive models for locally matched electricity networks. Appendix C: Private Wires - Legal Definitions

KAUAI ISLAND UTILITY COOPERATIVE KIUC Tariff No. 1 RULE NO. 17 NET ENERGY METERING

Elia Ancillary Services: Black-Start

Interconnection Feasibility Study Report GIP-222-FEAS-R3

GHA. Gas-Insulated Switchgear. Gas-Insulated Switchgear. Switchgear extension and replacement of a panel

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

Installation Power Management Unit Battery Cables and Battery Harness

REAL WORLD DRIVING. Fuel Efficiency & Emissions Testing. Prepared for the Australian Automobile Association

Distributed Energy Resources

Basslink HVDC Interconnector. The Journey from Project to Operations

Eyre Peninsula electricity supply options investigation

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

2018 Load & Capacity Data Report

Louisville Gas and Electric Company

Discipline: Engineering (Track & Civil) Category: Code of Practice. Clearances. Section 7. Applicability. ARTC Network wide.

Proposed New ISO Rules Section Version 2.0 Generating Unit Technical Requirements ( New ISO Rules Section Version 2.

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

2017 Interim Area Transmission Review of the New York State Bulk Power Transmission System

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

KAUAI ISLAND UTILITY COOPERATIVE KIUC Tariff No. 1 Lihue, Kauai, Hawaii Original Sheet 5 RULE NO. 2 CHARACTER OF SERVICE

Substation Lightning Protection. Document Number: 1-11-FR-11

Western Power s list of exemptions from compliance from Technical Rules granted after 1 July 2007.

SSR SSR SSR SSR

SERVICES INNOVATION. Montreal Symposium March 29, Jack Simpson Director, Generation & Capacity Planning

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System

Distributed resource participation in the Australian National Electricity Market

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Age-dependent & multi-load reliability analysis in transmission systems

15 Nelson-Marlborough Regional Plan

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS

Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study

Guidelines when working near TasNetworks electrical assets

- Data Brochure D 156. Difference Setpoint Control 156. Item 06/10

American Electric Power s Energy Storage Deployments

Transcription:

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF B 220 KV BUSBAR AT PREPARED BY: System Performance & Commercial DATE: 1 March 2013 FINAL

Disclaimer Purpose This report has been prepared by the Australian Energy Market Operator Limited (AEMO) for the sole purpose of meeting obligations in accordance with clause 4.8.15 (c) of the National Electricity Rules (NER). No reliance or warranty This report contains data provided by third parties and might contain conclusions or forecasts and the like that rely on that data. This data might not be free from errors or omissions. While AEMO has used due care and skill, AEMO does not warrant or represent that the data, conclusions, forecasts or other information in this report are accurate, reliable, complete or current or that they are suitable for particular purposes. You should verify and check the accuracy, completeness, reliability and suitability of this report for any use to which you intend to put it, and seek independent expert advice before using it, or any information contained in it. Limitation of liability To the extent permitted by law, AEMO and its advisers, consultants and other contributors to this report (or their respective associated companies, businesses, partners, directors, officers or employees) shall not be liable for any errors, omissions, defects or misrepresentations in the information contained in this report, or for any loss or damage suffered by persons who use or rely on such information (including by reason of negligence, negligent misstatement or otherwise). If any law prohibits the exclusion of such liability, AEMO's liability is limited, at AEMO's option, to the re-supply of the information, provided that this limitation is permitted by law and is fair and reasonable. 2013 Australian Energy Market Operator Ltd. All rights reserved 1 March 2013 Page 2 of 10

Abbreviations and Symbols Abbreviation BLGC CB CCGT DI EMMS EMS FCAS kv MW MWh NEM NEMDE NOS TVGCS Term Basslink Georgetown Convertor Station Circuit Breaker Combined Cycle Gas Turbine Dispatch Interval Electricity Market Management System Energy Management System Frequency Control Ancillary Service Kilovolt Megawatt Megawatt hour National Electricity Market National Electricity Market Dispatch Engine Network Outage Schedule Tamar Valley Power Station Generator Contingency Scheme 1 March 2013 Page 3 of 10

Contents Disclaimer... 2 Abbreviations and Symbols... 3 Incident summary... 5 1 Introduction... 6 2 Pre-Contingent System Conditions... 6 3 Summary of Events... 7 4 Immediate Actions Taken...10 5 Follow-up Actions...10 6 Power System Security Assessment...10 7 Conclusions...10 8 Recommendations...10 1 March 2013 Page 4 of 10

Incident summary Date and time of incident Region of incident Affected regions Event type Primary cause Impact Associated reports 27 November 2012 at 0732 hrs. Tasmania. Tasmania. BB - Busbar Trip. PTN & CTR - Protection and Control S- Significant NIL 1 March 2013 Page 5 of 10

1 Introduction At 0732 hrs on 27 November 2012, the B 220 kv Busbar at George Town Substation tripped due to an incorrect protection operation (operator involved) that occurred during work on the protection scheme at George Town Substation. The George Town Tamar Valley No 3 220 kv transmission line and the George Town Comalco No 4 220 kv transmission line also tripped. Prior to the event, the Tamar Valley Combined Cycle Power Station was generating 202 MW, and the George Town Comalco No 4 220kV transmission line was loaded to 106 MW (Rio Tinto Aluminium Smelter load). The event led to a total generation reduction of 202 MW and an interruption to load of 337 MW. Tripping of the George Town Tamar Valley No 3 220 kv transmission line resulted in a reduction of generation of 202 MW which is greater than the Tamar Valley Power Station Generator Contingency Scheme 1 (TVGCS) threshold of 144MW. As a result, the TVGCS operated to trip the selected Temco and Nyrstar load blocks. However, load blocks at Rio Tinto Aluminium Smelter (101 MW) connected to the George Town Comalco No 5 220 kv transmission line, and further load blocks at Nyrstar (28 MW) also tripped unexpectedly. The George Town Comalco No 4 220kV transmission line supplies the auxiliaries of the load connected to George Town Comalco No 5 220 kv transmission line. Therefore, when the George Town Comalco No 4 220kV transmission line tripped and interrupted auxiliary supplies to Rio Tinto load blocks, the load blocks at Rio Tinto also tripped. Further load blocks at Nyrstar tripped due to oversensitive control/protection settings within their plant. This report has been prepared under clause 4.8.15 (c) of the National Electricity Rules (NER) to assess the adequacy of the provision and response of facilities and services and the appropriateness of actions taken to restore or maintain power system security. This report is largely based upon information provided by Transend and AETV Power. Data from AEMO's Energy Management System (EMS) and Electricity Market Management System (EMMS) has also been used in analysing the incident. All references to time in this report are to National Electricity Market time (Australian Eastern Standard Time). 2 Pre-Contingent System Conditions Prior to 0732 hrs, there was a planned outage of a protection scheme at George Town Substation to upgrade the George Town Substation bus zone A protection. No primary equipment was out of service at that time. The status of the power system prior to the incident is shown in Figure 1. For clarity only equipment relevant to this incident has been included in the diagram. 1 The Tamar Valley Power Station Generator Contingency Scheme (TVGCS) is designed to interrupt load (selected load blocks at Temco and Nyrstar) in the event of a trip of the Tamar Valley Power Station CCGT with a generated output exceeding 144MW. 1 March 2013 Page 6 of 10

Figure 1 Status of the power system prior to the incident TAMAR VALLEY CCGT ST1 GT1 ST52 GT52 ST GT A429 B429 GEORGE TOWN Basslink Comalco 5 Comalco 4 3 Hadspen 2 Hadspen 1 Sheffield 2 Sheffield 1 F G152 F152 X152 D129C C129C B129C A129C Z152 Y129F X129F B629F D152 C152 B152 A152 G729F F729F B629FB D729F C729F B729F A729F H752 D752 C752 B752 A752 G129A F729B B629BF D729B C729B B729B XA129B C452 B452 A452 B H729B G129B F129B B629B D429B B429B A429B V129B XB629B B652 T3 T2 T1 C2 220 kv Busbar, line 220 / 132 kv Transformer Closed CB Closed Isolator 132 kv Busbar, line 220 / 13 kv Transformer Open CB Generator Open Isolator 3 Summary of Events Table 1 shows the summary and sequence of events. 1 March 2013 Page 7 of 10

Table 1: Summary and sequence of events Time (hrs) Event 0732 The B 220 kv busbar at George Town Substation, the George Town Comalco No 4 220 kv transmission line (106 MW), and the George Town Tamar Valley No 3 220 kv transmission line (202 MW) all tripped. The Tamar Valley Power Station CCGT was disconnected with output of 202 MW. The Tamar Valley Power Station Steam Turbine (ST1) immediately tripped. An electrical island was established with the Tamar Valley Power Station Gas Turbine (GT1) supplying the Tamar Valley Power Station s auxiliary equipment, a load of approximately 4 MW. At the time of islanding, the power system frequencies met the frequency operating standards for this type of event. Voltages remained within limits. Temco load block (74 MW) tripped by operation of the TVGCS. Nyrstar RZ6 (Nyrstar s sixth load block; 28 MW) tripped by operation of the TVGCS. Nyrstar RZ5 (Nyrstar s fifth load block; 28 MW) tripped due to oversensitive control/protection settings within their plant. A potline tripped at Rio Tinto Aluminium Smelter following trip of the George Town Comalco No 5 220 kv transmission line (101 MW). 0739 Permission to proceed with restoration of the B 220 kv busbar at George Town. 0749 The B 220 kv Busbar at George Town Substation was restored. 0751 The George Town Comalco No 4 220 kv transmission line restored. 0804 The George Town Tamar Valley No 3 220 kv transmission line returned to service. (Note that Tamar Valley Power Station GT1 was shutdown prior to the George Town Tamar Valley Power Station No 3 220 kv transmission line being restored). 0844 Market Notice No 40416 issued to advise that the cause of this non credible contingency event has been identified. AEMO decided not to reclassify this event as a credible contingency event. 1115 Tamar Valley Power Station CCGT returned to service. The Basslink frequency controller maintained Tasmanian region frequency within the normal frequency operating band. 1 March 2013 Page 8 of 10

The status of the power system immediately after the incident is shown in Figure 2. For clarity, only the equipment relevant to the incident has been included in the diagram. Figure 2 - Status of the power system immediately after the incident TAMAR VALLEY CCGT ST1 GT1 ST52 GT52 ST GT A429 B429 GEORGE TOWN Basslink Comalco 5 Comalco 4 3 Hadspen 2 Hadspen 1 Sheffield 2 Sheffield 1 F G152 F152 X152 D129C C129C B129C A129C Z152 Y129F X129F B629F D152 C152 B152 A152 G729F F729F B629FB D729F C729F B729F A729F H752 D752 C752 B752 A752 G129A F729B B629BF D729B C729B B729B XA129B C452 B452 A452 B H729B G129B F129B B629B D429B B429B A429B V129B XB629B B652 T3 T2 T1 C2 220 kv Busbar, line 220 / 132 kv Transformer Closed CB Closed Isolator 132 kv Busbar, line 220 / 13 kv Transformer Out of service Busbar, line Open CB Generator Open Isolator Out of service Generator The Tamar Valley Power Station Gas Turbine (GT1) remained in-service supplying the Tamar Valley Power Station s house load and energising the following :- the Tamar Valley Power Station Gas Turbine 220/14.5 kv Generator Transformer (GT) the Tamar Valley Power Station Steam Turbine 220/13.2 kv Generator Transformer (ST) to the open CB ST52, and the off-loaded George Town Tamar Valley No 3 220 kv transmission line to the open 220 kv CB X152 at George Town Substation. 1 March 2013 Page 9 of 10

4 Immediate Actions Taken At 0749 hrs, the B 220 kv busbar at George Town Substation was returned to service. At 0804 hrs, AEMO gave permission to restore load in steps of 30 MW. Load restoration was completed by 0830 hrs. Tamar Valley Power Station combined cycle gas turbine came on load at 1115 hrs (total cleared for 71 MW). Transend believes that this event is unlikely to reoccur because it was initiated by incorrect operation (operator involved). After considering Transend s information, AEMO determined that the event would not be reclassified as a credible contingency event. 5 Follow-up Actions Transend subsequently investigated the reasons for protection operation that occurred during the work on the protection scheme at George Town Substation. There was an incorrect labelling of a cable within the bus zone protection wiring which the test procedures had not identified. The cable labelling is now corrected and the test procedures are modified. Contractors are currently reviewing the control and protection settings of the Nyrstar equipment. The TVGCS has been reconfigured, and excludes Nyrstar load blocks since 1 January 2013. 6 Power System Security Assessment The power system frequencies in the Tasmania mainland and the electrical island 2 with Tamar Valley Power Station GT1 remained within the relevant Frequency Operating Standards and voltages remained within limits. The power system remained in a secure operating state throughout the incident. 7 Conclusions After receiving advice from Transend, AEMO correctly applied the criteria published in section 12 of its Power System Security Guidelines in assessing the incident. Given the circumstances, reclassification of similar incidents as a credible contingency event was not required. The power system remained in a secure operating state during the incident. The provision and response of facilities and services was adequate in relation to power system security. The actions taken were adequate to maintain power system security. Transend has investigated the event and advised AEMO of the outcomes and corrective actions taken within the requested timeframe. 8 Recommendations There are no recommendations. 2 The maximum frequency in the electrical island was 53.85 Hz and achieved 4.85 seconds after separation. The relevant frequency operating standard for a separation event applying to an island in the Tasmania region is a containment band of 47.0 to 55.0 Hz. The island frequency returned to the normal operating frequency band in approximately 35 seconds following the incident and remained within the band until restoration. 1 March 2013 Page 10 of 10