Sub Regional RTEP Committee Mid-Atlantic

Reliability Analysis Update

New Jersey State Report

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board

Transmission Expansion Advisory Committee

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee - Southern. August 19, 2011

Reliability Analysis Update

Subregional RTEP Committee Mid-Atlantic Area. September 9, 2008

Sub Regional RTEP Committee South

Transmission Expansion Advisory Committee. Reliability Analysis Update

Reliability Analysis Update

Sub-Regional RTEP Committee PJM South

Sub Regional RTEP Committee Mid-Atlantic

PJM Regional Transmission Expansion Planning (RTEP) Process

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

Sub Regional RTEP Committee South

System Impact Study Report

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

Illinois State Report

Feasibility Study Report

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study

Generation Deactivation Notification Update

4.7: New Jersey RTEP Overview

Market Efficiency RTEP Proposal Window

Reliability Analysis Update

Sub Regional RTEP Committee Western Region ATSI

Reliability Analysis Update

Sub Regional RTEP Committee - Southern

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

Reliability Analysis Update

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

Sub Regional RTEP Committee Mid-Atlantic First Energy MAAC Solution Meeting

Transmission Expansion Advisory Committee Meeting. April 23, 2008

Market Efficiency RTEP Proposal Window

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

North Oregon Coast Area Study. Adam Lint

Transmission Expansion Advisory Committee

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Falcon-Midway 115 kv Line Uprate Project Report

PJM SRTEP Meeting Questions Pertaining to Proposed Projects & Scopes AEP: Ambler Ridge:

Market Efficiency Update

ATTACHMENT - DFO STATEMENT OF NEED

DFO STATEMENT OF NEED REPORT

TRANSMISSION PLANNING CRITERIA

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

New Services Queue Network Upgrades

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Entergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects

Transmission Expansion Advisory Committee

Case Study- DG Uses at Conectiv Future Challenges & Opportunities

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016

Proposed New Construction for

MTEP13 SPM #2- Central Region. March 25, 2013

First Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012

STATE OF NEW JERSEY Board of Public Utilities 44 South Clinton Avenue, 9 th Floor P.O. Box 350 Trenton, New Jersey

Feasibility Study Report

100 MW Wind Generation Project

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN

Feasibility Study Report

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

Sub Regional RTEP Committee PJM West

The Energy Queensland Group Notice of no non-network options

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Market Efficiency Update

Transmission Expansion Advisory Committee Meeting 2014 Market Efficiency Analysis

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

ATC Year Asessment Network Project List. Zone 2 switching initiative ASAP*** Operating flexibility Proposed -- --

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Surry Skiffes Creek Whealton Modeling and Alternatives Analysis Review

Appendix D Black Hills Project Summary

Chapter 7 - Appendix A

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

MILLIGAN SOLAR PROJECT

Market Efficiency Update

Maddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016

Stability Study for the Mt. Olive Hartburg 500 kv Line

2017 Indiana State Infrastructure Report (January 1, 2017 December 31, 2017)

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

The Capital Grid Project:

National Grid s 2017 Local Transmission Plan

National Grid s 2018 Local Transmission Plan

Sub Regional RTEP Committee - Western. October 21, 2009

EXCEPTIONS TO RELIABILITY RULES Revision 11 February 9, 2018

Black Hills Project Summary

Pacific Gas and Electric Company s Revised 2015 Annual Progress

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project.

Transcription:

Sub Regional RTEP Committee Mid-Atlantic September 24, 2014 1

Reliability Analysis Update 2

AE Transmission Zone Generation Deliverability Violation: The Middle 230/69 kv is overloaded for line fault stuck breaker contingency loss of the BL England Middle - Carson and Carson - Dennis 138 kv circuits. Recommended Solution: Replace Middle T3 138/69 kv transformer with 225 MVA nameplate. (B2553) Project ID: P2014_1-12J-U from 2014 RTEP Proposal Window #1 $ 7.5 M Required IS Date: 6/1/2019 3

PECO Transmission Zone N-1-1 Violation. The Eddystone to Llanerch 138 kv circuit 130-45 is overloaded for N-1-1 contingency loss of Plymouth Brynmawr 230 kv and Eddystone to Llanerch 138 kv 130-42 circuits. Recommended Solution: Replace terminal equipment inside Llanerch substation on the 130-45 (Eddystone to Llanerch) 138 kv line (B2551). Project ID: P2014_1-5E-U from 2014 RTEP Proposal Window #1 $ 0.1 M Required IS Date: 6/1/2019 4

Supplemental 5

AE Transmission Zone Supplemental Project : Improves reliability due to age and condition of the circuit. Rebuild 1.86 miles of the Corson-Middle-Lake 69 kv circuit '0720', sections P-Z Lake Tap, including Sections S through V. (S0789) $ 7.83 M 5/31/2015 6

AE Transmission Zone Supplemental Project : Improves reliability due to age and condition of the transformer. Replace (9) Single phase 138/69 KV Auto Transformer Units with (3) Three Phase 138/69 KV Auto Transformer at Lewis substation. (S0790) $ 15.01 M 5/31/2015 7

Improves reliability due to age and condition of the circuit. Rebuild 10.96 miles the Deepwater to Salem 69 kv circuit '0724'. (S0791) $ 5.32 M 12/31/2015 AE Transmission Zone 8

Improves reliability due to age and condition of the circuit. Rebuild the Lewis- Ontario #2 69 kv circuit 0742. (S0792) $ 13.78 M 6/1/2016 AE Transmission Zone 9

Improves reliability due to age and condition of the circuit. Rebuild approximately 6.4 miles of the Lewis - Higbee 69 kv #1 circuit. (S0793) $ 12.20 M 6/1/2016 AE Transmission Zone 10

AE Transmission Zone Supplemental Project : Improves reliability due to age and condition of the transformer. Replace the existing Sickler T1-230/69kV, autotransformer with a 230/69kV, 335 MVA Transformer. (S0794) $ 7.5 M 5/1/2017 11

Improves reliability due to age and condition of the circuit. Rebuild 4.14 miles of the Corson-Sea Isle-Swainton 69 kv circuit '0717', sections B & C. (S0795) $ 5.5 M 6/1/2017 AE Transmission Zone 12

Improves reliability due to age and condition of the circuit. Rebuild the Corson- Middle #1 138 kv circuit '1412'. (S0796) $ 13.5 M 12/31/2017 AE Transmission Zone 13

AE Transmission Zone Supplemental Project : Improves reliability due to age and condition of the circuit. Rebuild the Upper Pittsgrove - Landis 138 kv '1406' 138kv circuit. The rebuild will include parts of the 1404 and 1405 circuits. (S0797) $ 10.71 M 12/31/2019 14

Improves reliability due to age and condition of the circuit. Rebuild the Monroe- Lewis 138 kv '1404' Sections B-E. (S0798) $ 88.58 M 3/31/2020 AE Transmission Zone 15

To improves reliability due to the retirement of the of the Deepwater substation. Install 336 MVA 230/138 kv transformer at Churchtown to be connected to the Pittsgrove. (S0799) $ 8.58 M 5/31/2016 AE Transmission Zone 16

To improves reliability due to the retirement of the of the Deepwater substation. Install 69/34 kv transformer at Churchtown to feed Valley substation. (S0800) $ 2.7 M 5/31/2016 AE Transmission Zone 17

AE Transmission Zone Supplemental Project : To improves reliability due to the retirement of the of the Deepwater substation. Re-terminate Deepwater- Beckett 69 kv line at Churchtown Sub as a result of Deepwater retirement. (S0801) $ 2.57 M 12/31/2016 18

AE Transmission Zone Supplemental Project : To improves reliability due to the retirement of the of the Deepwater substation. Re-terminate Deepwater- Salem 69 kv line at Churchtown Sub as a result of Deepwater retirement. (S0802) $ 2.57 M 12/31/2016 19

AE Transmission Zone Supplemental Project : To improves reliability due to the retirement of the of the Deepwater substation. Re-terminate the Deepwater- Woodstown #1 69 kv line at Churchtown Substation as a result of Deepwater retirement. (S0803) $ 1.8 M 5/31/2017 20

AE Transmission Zone Supplemental Project : To improves reliability due to the retirement of the of the Deepwater substation. Build, and/or rebuild 3.2 miles of 69 kv line to connect the Churchtown - Pennsgrove 69 kv line to Carneys Point. (S0804) $ 2.4 M 5/31/2017 21

To improves reliability due to the retirement of the of the Deepwater substation. Install 69 kv double ring bus with normally closed bus tie, with 12 (ultimate) terminal positions. (S0805) $ 10.6 M 5/31/2017 AE Transmission Zone 22

AE Transmission Zone Supplemental Project : To improves reliability due to the retirement of the of the Deepwater substation. Re-terminate #2 Deepwater- Woodstown 69 kv line at Churchtown Sub as a result of Deepwater retirement. (S0806) $ 2.57 M 5/31/2017 23

AE Transmission Zone Supplemental Project : To improves reliability due to the retirement of the of the Deepwater substation. Re-terminate Deepwater- Pennsgrove 69 kv line at Churchtown Sub as a result of Deepwater retirement. (S0807) $ 2.57 M 5/31/2017 24

To improves reliability due to the retirement of the of the Deepwater substation. Retire the Deepwater 138 kv and 69 kv substation. (S0808) $ 1.7 M 12/31/2018 AE Transmission Zone 25

Improves reliability due to age and condition of the circuit. Rebuild the Mill - Marven 69 kv circuit '0749'. (S0809) $ 14.72 M 12/31/2018 AE Transmission Zone 26

Improves reliability due to age and condition of the circuit. Rebuild the Corson - Merion 138 kv circuit '1411'. (S0810) $ 10.04 M 12/31/2018 AE Transmission Zone 27

Improves reliability due to age and condition of the circuit. Rebuild the BL England - Scull - Mill - Lewis 138 kv #1 circuit '1407'. (S0811) $ 11.46 M 12/31/2020 AE Transmission Zone 28

Improves reliability due to age and condition of the circuit. Rebuild the BL England - Scull - Mill - Lewis 138 kv #2 circuit '1408'. (S0812) $ 9.55 M 12/31/2020 AE Transmission Zone 29

Improves reliability due to age and condition of the circuit. Rebuild 20.96 miles of Circuit the Lewis - Motts Farm 69 kv circuit '0702'. (S0813) $ 24.6 M 5/31/2015 AE Transmission Zone 30

Improves reliability due to age and condition of the circuit. Rebuild 10.8 miles of the Salem to Woodstown 69 kv circuit '0745'. (S0814) $ 24.6 M 12/31/2015 AE Transmission Zone 31

Improves reliability due to age and condition of the circuit. Rebuild 5.15 miles of the Lincoln - Union 138kV circuit '1419' to 2000A with 1590 ACSR. (S0815) $ 7 M 12/31/2016 AE Transmission Zone 32

Improves reliability due to age and condition of the circuit. Rebuild 0.23 mile section of the Cumberland - Sherman 138kV circuit to 2000A with 1590 ACSR. (S0816) $ 0.34 M 12/31/2015 AE Transmission Zone 33

Improves reliability due to age and condition of the circuit. Rebuild the Wells- Harrington 69 kv circuit '6784'. (S0817) $ 8.79 M 12/31/2015 DPL Transmission Zone 34

Improves reliability due to age and condition of the circuit. Rebuild the Salisbury - Worcester 69 kv circuit '6741 '. (S0818) $ 20.34 M 5/31/2016 DPL Transmission Zone 35

Improves reliability due to age and condition of the circuit. Rebuild the North Salisbury - Pemberton 69 kv circuit ' 6701'. (S0820) $ 1.36 M 12/31/2016 DPL Transmission Zone 36

Improves reliability due to age and condition of the circuit. Rebuild the Church - Steele 138 kv circuit ' 13701'. (S0821) $ 29.5 M 5/31/2017 DPL Transmission Zone 37

Improves reliability due to age and condition of the circuit. Rebuild the Hares Corner - Red Lion 138 kv circuit ' 13812 '. (S0822) $ 4.22 M 12/31/2017 DPL Transmission Zone 38

Improves reliability due to age and condition of the circuit. Rebuild the Mt. Hermon - Chesapeake 69 kv circuit '6726'. (S0824) $ 1.36 M 12/31/2017 DPL Transmission Zone 39

Improves reliability due to age and condition of the circuit. Rebuild 4.58 miles of the Basin Rd - Bear 138 kv circuit '13816'. (S0825) $ 8.48 M 12/31/2018 DPL Transmission Zone 40

Improves reliability due to age and condition of the circuit. Rebuild the Hillsboro - Wye Mills 138 kv circuit '13788'. (S0826) $ 9.15 M 12/31/2018 DPL Transmission Zone 41

Improves reliability due to age and condition of the circuit. Replace the Kings Creek AT1 138/69 kv autotransformer. (S0827) $ 1.75 M 12/31/2018 DPL Transmission Zone 42

DPL Transmission Zone Supplemental Project : During peak loading the Crisfield generation cannot support the load along 6725 when Kings Creek AT1 is taken out of service. All planned outages are limited to a short window during the fall or spring. Emergency outages during peak and moderate load conditions could result in the loss of load for potentially significant durations. Relocate Line 13713 going into Kings Creek substation during the construction of the new Kings Creek 69kV bus. (S0828) $ 0.25 M 12/31/2015 43

DPL Transmission Zone Supplemental Project : During peak loading the Crisfield generation cannot support the load along 6725 when Kings Creek AT1 is taken out of service. All planned outages are limited to a short window during the fall or spring. Emergency outages during peak and moderate load conditions could result in the loss of load for potentially significant durations. A new terminal at Crisfield 69 kv substation for the new Kings Creek - Crisfield 69kV circuit. (S0829) $ 4.14 M 12/31/2016 44

DPL Transmission Zone Supplemental Project : During peak loading the Crisfield generation cannot support the load along 6725 when Kings Creek AT1 is taken out of service. All planned outages are limited to a short window during the fall or spring. Emergency outages during peak and moderate load conditions could result in the loss of load for potentially significant durations. A new terminal at Kings Creek 69 kv substation for the new Kings Creek - Crisfield 69kV circuit. (S0830) $ 4.69 M 12/31/2016 45

DPL Transmission Zone Supplemental Project : During peak loading the Crisfield generation cannot support the load along 6725 when Kings Creek AT1 is taken out of service. All planned outages are limited to a short window during the fall or spring. Emergency outages during peak and moderate load conditions could result in the loss of load for potentially significant durations. Rebuild the existing Kings Creek - Crisfield 69kV circuit '6725' and construct a 2nd Kings Creek - Crisfield 69 kv circuit. (S0831) $ 25.58 M 12/31/2017 46

Improves reliability due to age and condition of the circuit. Rebuild 7 miles of the Fruitland - N Salisbury 69 kv circuit '6701'. (S0832) $ 8.33 M 12/31/2016 DPL Transmission Zone 47

Improves reliability due to age and condition of the circuit. Rebuild 6.16 miles of the Vienna - Nelson 138 kv circuit '13707' (Delaware). (S0833) $ 7.21 M 12/31/2018 DPL Transmission Zone 48

Improves reliability due to age and condition of the circuit. Rebuild 7.57 miles of the Vienna - Nelson 138 kv circuit '13707' (Maryland). (S0834) $ 8.9 M 12/31/2018 DPL Transmission Zone 49

Improves reliability due to age and condition of the circuit. Rebuild 14.7 miles of the Vienna - N. Salisbury 69 kv circuit '6708'. (S0835) $ 13.8 M 12/31/2018 DPL Transmission Zone 50

DPL Transmission Zone Supplemental Project : Improves reliability due to age and condition of the circuit. Resolves N-1-1 condition on non BES facility. Rebuild the Worcester - Ocean City 69kV circuit '6724'. (S0836) $ 12.19 M 5/31/2015 51

DPL Transmission Zone Supplemental Project : Improves reliability due to age and condition of the circuit. Resolves N-1-1 condition on non BES facility. Upgrade terminal equipment at Worcester Substation on the Worcester - Ocean City 69 kv. (S0837) $ 0.37 M 5/31/2015 52

Thermal overload on the underground egress into Hoper Ave substation. Construct 34.5 kv bypass line at Hooper Ave. substation (S0787). $ 0.2 M 6/1/2015 JCPL Transmission Zone 53

Load connection. Tap the Tiffany Lennox 115 kv line and provide meter. (S0788) $ 0.7 M 9/19/2014 PenElec Transmission Zone 54

Improves reliability due to load growth. Install a new Waterfront 138/13kV Sub. 223 and build four new 138kV circuits from Buzzard Point to supply the station. (S0838) $ 76 M 12/31/2016 PEPCO Transmission Zone 55

Improves reliability due to load growth. Install Mt. Vernon 230/13kV Sub and 230kV High-Side- Bus at Takoma Sub. 27. Extend four new 230kV U.G. circuits from the new Takoma HSB to the Mt. Vernon substation on two separate rights-of-way. (S0839) $ 345 M 12/31/2021 PEPCO Transmission Zone 56

Improves reliability due to load growth. Install New Harvard 230/13kV Sub and supply the station by tapping two of the extend circuits to serve Mt. Vernon. (S0840) $ 110 M 12/31/2020 PEPCO Transmission Zone 57

Improves reliability due to load growth. Install New Harrison 138/13kV Sub, to replace the existing Harrison Sub. 38. Supply the station by cutting in and out of two 138kV circuits between Bethesda Sub. 6 and Van Ness Sub. 129. (S0841) $ 73.5 M 12/31/2027 PEPCO Transmission Zone 58

The shunt reactors are being added at Alabama Ave Sub. 136 on Feeders 23088 and 23089 to avoid overvoltage issues on the 230kV and 13.8kV buses at the station. Operating procedures are currently in place to address this problem, but result in the station Firm Capacity being based on the loss of two transformers. With the shunt reactors in place the Firm Capacity will be based on a single transformer outage with a resultant increase in capacity. Install two 100 MVAR Shunt Reactors at Alabama Avenue Sub. 136. (S0842) $ 12 M 12/31/2016 PEPCO Transmission Zone 59

Improves reliability due to age and condition of the transformer. Replace Palmers Corner Sub. 84 TR #3 with a new 230/69kV 224 MVA transformer. (S0843) $ 2.2 M 1/12/2015 PEPCO Transmission Zone 60

Improves reliability due to age and condition of the transformer. Replace Bells Mill Sub. 121 TR #14 with a new 230/69kV 280 MVA transformer. (S0844) $ 3.3 M 1/31/2015 PEPCO Transmission Zone 61

Improves reliability by having Hot Standby to add operational flexibility. Install Palmers Corner Sub. 84 230/69kV 224 MVA TR #1. (S0845) $ 3 M 3/4/2015 PEPCO Transmission Zone 62

Improves reliability due to age and condition of the transformer. Replace Norbeck Sub. 158 TR #3 with a new 230/69kV 224 MVA transformer. (S0846) $ 2.7 M 5/1/2015 PEPCO Transmission Zone 63

Improves reliability due to age and condition of the transformer. Replace Norbeck Sub. 158 TR #4 with a new 230/69kV 224 MVA transformer. (S0847) $ 2.6 M 6/2/2015 PEPCO Transmission Zone 64

Improves reliability due to age and condition of the transformer. Replace Quince Orchard Sub. 118 TR #3 with a new 230/69kV 224 MVA transformer. (S0848) $ 2.7 M 6/15/2015 PEPCO Transmission Zone 65

Improves reliability due to age and condition of the transformer. Replace Norbeck Sub. 158 TR #2 with a new 230/69kV 224 MVA transformer. (S0849) $ 2.5 M 11/1/2015 PEPCO Transmission Zone 66

Improves reliability due to age and condition of the transformer. Replace Quince Orchard Sub. 118 TR #1 with a new 230/69kV 224 MVA transformer. (S0850) $ 2.7 M 12/15/2015 PEPCO Transmission Zone 67

Supplemental Project: Improve reliability due to age and condition of the transformer. Replace Brunswick 230/69 kv transformer 220-5 (S0758). $ 15 M 12/31/2015 PSE&G Transmission Zone 68

PSE&G Transmission Zone Supplemental Project: To improve reliability due to load increase in the Kearny vicinity. In addition it improves reliability and transformer condition at several Class H substations. Install two 230/13 kv transformers at Kearny Substation (S0759). $ 14 M 12/31/2015 69

PSE&G Transmission Zone Supplemental Project: To improve reliability due to station overload. In addition it improves reliability and transformer condition at several Class H substations. Install two 230/13 kv transformers at Waldwick Substation (S0760). $ 14 M 12/31/2015 70

Supplemental Project: Improve reliability due to age and condition of the transformer. Replace Brunswick 230/69 kv transformer 220-1 (S0761). $ 15 M 12/31/2017 PSE&G Transmission Zone 71

Supplemental Project: To improve reliability and transformer availability during contingency/failure Purchase one spare 230/138-27-11 kv dual ratio high side transformer (S0762). $ 7.8 M 12/31/2015 PSE&G Transmission Zone 72

Supplemental Project: To improve reliability and transformer availability during failure. Purchase eight 69/4 kv Transformers for future use (S0763). $ 3.6 M 12/31/2017 PSE&G Transmission Zone 73

Supplemental Project: To improves reliability by remotely monitoring major assets Install microprocessor relays, transformer equipments, SCADA systems and alarm panels at Lake Nelson T-1, Harts Lane T-1, T-2, T-3, Sand Hills T-1, T-2 and Federal Square T-1, T-2, T-3 (S0851). $ 13.5 M 12/31/2015 PSE&G Transmission Zone 74

Questions? Email: RTEP@pjm.com 75