POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO KV BUSBAR ON 30 OCTOBER 2011

Similar documents
POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011

Power System Operating Incident Report Trip of Murray Lower Tumut No kv Transmission Line at Murray End Only on 18 November 2013

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

POWER SYSTEM OPERATING INCIDENT REPORT MULTIPLE CONTINGENCY EVENT IN NORTH WEST TASMANIA ON 6 APRIL 2012

POWER SYSTEM OPERATING INCIDENT REPORT LIGHTNING STRIKES IN TASMANIA AND PACIFIC ALUMINIUM POTLINE LOAD REDUCTIONS 21 MARCH 2013

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

MULTIPLE LINE OUTAGES IN THE MOUNT ENGLAND TARONG AREA IN QUEENSLAND, 13 FEBRUARY 2017

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF B 220 KV BUSBAR AT GEORGE TOWN ON 27 NOVEMBER 2012.

Power System Operating Incident Report Trip of Red Cliffs Horsham and Red Cliffs-Wemen Kerang 220 kv transmission lines on 15 January 2014

POWER SYSTEM INCIDENT REPORT NORTHERN POWER STATION STABILISER OUTAGE APRIL AND MAY 2010

TRIP OF HORSHAM-REDCLIFFS 220 KV TRANSMISSION LINE AND MURRAYLINK INTERCONNECTOR ON 12 NOVEMBER 2015

POWER SYSTEM INCIDENT REPORT: OVERLOAD OF WAUBRA- HORSHAM 220 KV TRANSMISSION LINE AND INSECURE OPERATION OF THE SYSTEM ON 13 DECEMBER 2012

The Energy Queensland Group Notice of no non-network options

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Jemena Electricity Networks (Vic) Ltd

SUBSTATION INTERLOCKING SCHEMES

XXXXX. Kokish River Hydroelectric Project. Interconnection Facilities Study and Project Plan

Managing Electrical Safety on Boats

Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)*

Final Capacity Auction Results 2019/2020 T-1 Capacity Auction. Date 01/02/2019 Document: FCAR1920T-1 Version 1.0

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

Guidelines for connection of generators:

Final Capacity Auction Results 2018/2019 T-1 Capacity Auction. Date 26/01/2018 Version 1.0

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8

TRANSMISSION PLANNING CRITERIA

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

South Australia Victoria (Heywood) Interconnector Upgrade. RIT-T: Project Specification Consultation Report

Emerald Reactive Support Alternative Solution Expressions of interest

Substation Lightning Protection. Document Number: 1-11-FR-11

ELECTRICITY TRANSMISSION USE OF SYSTEM PRICES - 1 JULY 2014 TO 30 JUNE 2015

Procedure PR D Electrical Permits. Engineering Procedure Electrical Distribution Unit. Version 1.0. Date in Force: 4 November 2015

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Energy Regulation : Australian Experience. Engr.Khondkar Abdus Saleque

Washington, DC Area Low Voltage Disturbance

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System

Electricity Industry Code Minimum Service Standards & Guaranteed Service Levels Quarterly Report July September 2008

Feasibility Study for the Q MW Solar Project

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Grid Tied Limiter User Manual

Engineering Instruction

GHA. Gas-Insulated Switchgear. Gas-Insulated Switchgear. Switchgear extension and replacement of a panel

Bald Hill on track to start lithium concentrate production this quarter

Main Transmission System Planning Guideline

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

2016 Load & Capacity Data Report

2017 Interim Area Transmission Review of the New York State Bulk Power Transmission System

Installation Power Management Unit Battery Cables and Battery Harness

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Remote Monitor for Solar Regulator

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study

www. ElectricalPartManuals. com Instructions for Field Testing of Ground Fault Systems Utilizing Cutler-Hammer Magnum DS Circuit Breakers

MINIMUM OIL BURN/AUTOMATIC FUEL SWAPPING CAPABILITY

SNZ TR 6120:2014. New Zealand Technical Report. Low voltage supply earthing systems SNZ TR 6120:2014

Eyre Peninsula electricity supply options investigation

DFO STATEMENT OF NEED REPORT

Volume CHARGESTORM AB. Charging station model EVA Start and Protected. User Manual Start & Protected

MICROCARE 3 PHASE INVERTER MANUAL

Arc flash solutions catalogue Australia. Safety solutions - Protecting employees and the enterprise

Title Electrical Technical Maintenance Coding System. Reference Number PMP 01 (RIC Standard: EP SP)

Scania Used Vehicle Extended Driveline Warranty

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)

American Electric Power s Energy Storage Deployments

Generation Capacity Guide

15 Nelson-Marlborough Regional Plan

REAL WORLD DRIVING. Fuel Efficiency & Emissions Testing. Prepared for the Australian Automobile Association

Thank you for the detailed information regarding the Refurbishment Project at Marchwood MTS. This project will facilitate equipment maintainability.

Electricity Safety (Electrical Installations) Regulation 2005

Vertabelo Academy. Terms of Service PLEASE READ ALL OF THE FOLLOWING TERMS OF SERVICE BEFORE USING THIS WEBSITE A. General Terms

Heber Light & Power Electric Service Rule No. 14 NET METERING SERVICE

2018 Load & Capacity Data Report

Eyre Peninsula Electricity Supply Options

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

18/10/2018. Mr Peter Adams General Manager, Wholesale Markets Australian Energy Regulator. By

2015 WDC Disturbance and Protection Standards Overview

XXXX. Kokish River Hydroelectric Project. Interconnection System Impact Study

II DISTRIBUTION & SUBSTATION TYPE C

Smart Grid Automation and Centralized FISR

Overview Overvoltage protection

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

New 115 kv Disconnect Switches at Bloomsburg MTS

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

NORDIC AND BALTIC GRID DISTURBANCE STATISTICS 2016

Project #148. Generation Interconnection System Impact Study Report

Generator Interconnection System Impact Study For

Summary of Revision, IEEE C , Guide for Breaker Failure Protection of Power Circuit Breakers

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

KAUAI ISLAND UTILITY COOPERATIVE KIUC Tariff No. 1 Lihue, Kauai, Hawaii Original Sheet 5 RULE NO. 2 CHARACTER OF SERVICE

Maintenance of Signal Sighting and Signals

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

GC-1. Roof and Gutter De-Icing Control Installation and Operating Instructions FOR EXTERIOR INSTALLATION ONLY

Louisville Gas and Electric Company

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

The Ultimate Smart Grid Solution INSTRUCTION MANUAL

Investigation into UK socket-outlets incorporating USB charging points

PowerFLEX Module Limited Warranty Program

Feasibility Study for the Q MW Solar Project

Hurricane Sandy. Preparations, Response & Recovery. Wes Yeomans Vice President Operations Management Committee Meeting November 2, 2012

SERVICES INNOVATION. Montreal Symposium March 29, Jack Simpson Director, Generation & Capacity Planning

Transcription:

POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO.1 275 KV BUSBAR ON 30 OCTOBER 2011 PREPARED BY: Electricity System Operations Planning and Performance DATE: 20 April 2012 FINAL

Disclaimer Purpose This report has been prepared by the Australian Energy Market Operator Limited (AEMO) for the sole purpose of meeting obligations in accordance with clause 4.8.15 (c) of the National Electricity Rules. No reliance or warranty This report contains data provided by third parties and might contain conclusions or forecasts and the like that rely on that data. This data might not be free from errors or omissions. While AEMO has used due care and skill, AEMO does not warrant or represent that the data, conclusions, forecasts or other information in this report are accurate, reliable, complete or current or that they are suitable for particular purposes. You should verify and check the accuracy, completeness, reliability and suitability of this report for any use to which you intend to put it, and seek independent expert advice before using it, or any information contained in it. Limitation of liability To the extent permitted by law, AEMO and its advisers, consultants and other contributors to this report (or their respective associated companies, businesses, partners, directors, officers or employees) shall not be liable for any errors, omissions, defects or misrepresentations in the information contained in this report, or for any loss or damage suffered by persons who use or rely on such information (including by reason of negligence, negligent misstatement or otherwise). If any law prohibits the exclusion of such liability, AEMO s liability is limited, at AEMO s option, to the re-supply of the information, provided that this limitation is permitted by law and is fair and reasonable. Abbreviations and Symbols Abbreviation CB CT kv Term CB Current Transformer Kilovolt 2012 Australian Energy Market Operator Ltd. All rights reserved 19 April 2012 Page 2 of 12

1 Introduction At 2134 hrs on 30 October 2011, the No. 1 275 kv busbar at Mt. England in Queensland tripped. A sequence of events took place in the transmission network over a two second period when lightning activity was present in the area. The lightning activity caused high voltage faults on the 837 Tarong Mt. England 275 kv line and its 275 kv current transformer (CT) at Mt. England substation, resulting in the trip of the No. 1 275 kv busbar at Mt. England. At 1023 hrs on 31 October 2011, the Mt. England No.1 275 kv busbar and all the affected network elements were returned to service. There was no loss of load as a result of this incident. This report has been prepared under clause 4.8.15 of the National Electricity Rules (NER) to assess the adequacy of the provision and response of facilities and services and the appropriateness of actions taken to restore or maintain power system security. This report is largely based upon information provided by Powerlink. Data from AEMO s Energy Management System have also been used in analysing the incident. All references to time in this report refer National Electricity Market time (Eastern Standard Time). 2 Pre-Contingent System Conditions Prior to the incident, all circuit breakers (CB) and transmission elements connecting to Tarong and Mt. England substations were in service with the exception of capacitors, which were switched off for voltage control. The status of the power system prior to the incident is shown in Figure 1. For clarity, only equipment relevant to this incident has been included in the diagram. 19 April 2012 Page 3 of 12

Figure 1 Status of the power system prior to the incident H018 Tarong Feeder 827 CB8272 CB5012 CB8372 275 kv 1 Busbar Feeder 823 Feeder 824 Feeder 8812 Feeder 825 CB5812 CB8232 CB8372 CB88122 CB8252 CB5042 CB5052 CB5062 CB5822 CB8242 CB88232 CB8022 H012 Mt England Feeder 8823 Feeder 802 275 kv Line 275 kv Bus Line Bus Capacitor Closed Circuit Breaker Open CB 19 April 2012 Page 4 of 12

3 Summary of Events At 21:34:58 on 30 October 2011, a one phase to ground fault occurred on the B phase of the 837 Tarong Mt. England 275 kv line during lightning activity in the area. Protection systems operated to trip the faulted phase at Tarong and Mt. England substations. The detailed information acquired by Powerlink showed evidence that a lightning strike caused the one phase to ground fault. Initially, the following CBs operated and cleared the fault from the power system: H018 Tarong CB 8372 B phase only H018 Tarong CB 5012 H012 Mt. England CB 8372 B phase only H012 Mt. England CB 5042 Figure 2 shows the status of the relevant CBs immediately following the incident. 19 April 2012 Page 5 of 12

Figure 2 - Status of the power system after the one phase to ground trip of 837 Tarong Mt. England 275 kv line H018 Tarong Line 827 CB8272 CB5012 CB8372 275 kv 1 Busbar Line 823 Line 824 Line 8812 Line 825 CB5812 CB8232 CB8372 CB88122 CB8252 CB5042 CB5052 CB5062 CB5822 CB8242 CB88232 CB8022 H012 Mt England Line 8823 Line 802 275 kv Line 275 kv Bus Line Open CB Bus CB Open on One Phase Capacitor Closed Circuit Breaker 19 April 2012 Page 6 of 12

TRIP OF NO. 1 275KV BUSBAR AT MT. ENGLAND Approximately 500 milliseconds after the initial fault on the B phase of 837 line, and during the time 837 line B phase was open, an insulation flashover occurred internal to the B phase of 275 kv CT associated with CB 8372 at Mt. England substation and within the zone protected by the No.1 275 kv busbar protection systems. The insulation flashover was most likely due to lightning activity in the vicinity of the 837 line. The faulted CT triggered the operation of the Mt. England No.1 275 kv busbar protection systems. As a result of the busbar protection system operation, the Mt. England No.1 275 kv busbar was de-enegised with the following CBs at Mt. England opening: 275 kv CB 8372 A and C phases, which off-loaded the 837 Tarong Mt. England 275 kv line (B phase was already open) 275 kv CB 8232, which de-energised the 823 Mt. England Wivenhoe / Wivenhoe Unit 1 275kV line. Wivenhoe Unit 1 was not in service at the time of the event. 275 kv CB 8252. 275 kv CB 88122. Figure 3 shows the status of the CBs after the trip of No. 1 275 KV busbar at Mt. England. 19 April 2012 Page 7 of 12

Figure 3 - Status of the power system after the trip of No. 1 275 kv Busbar at Mt. England H018 Tarong Line 827 CB8272 CB5012 CB8372 275 kv 1 Busbar Line 823 Line 824 Line 8812 Line 825 CB5812 CB8232 CB8372 CB88122 CB8252 CB5042 CB5052 CB5062 CB5822 CB8242 CB88232 CB8022 H012 Mt England Line 8823 Line 802 275 kv Line 275 kv Bus Line Open CB Bus CB Open on One Phase Capacitor Closed Circuit Breaker 19 April 2012 Page 8 of 12

FEEDER 837 AUTO-RECLOSE AT TARONG At 21:34:59, the 837 line autoreclose function at Tarong operated to re-energise B phase of the 837 line from Tarong substation. The high voltage fault was still present due to the insulation flashover internal to the 275 kv CT associated with CB 8372 at Mt. England substation. This caused the protection systems of the 837 line at Tarong to operate, resulting in the trip and lockout of CB 8372 at Tarong and, consequently, de-energisation of the 837 line Figure 4 shows the status of the CBs after the de-energisation of the 837 line. 19 April 2012 Page 9 of 12

Figure 4 - Status of the power system after trip of 837 Tarong Mt. England 275 kv line 19 April 2012 Page 10 of 12

4 Immediate Actions Taken Date Time Operation 2140 hrs AEMO invoked the constraint sets associated with the outage of 837 Tarong Mt. England 275 kv line (Q-TRME) 30-Oct-11 AEMO invoked the constraint sets associated with the outage of 823 Mt. England 2145 hrs Wivenhoe 275 kv line (Q-MEWV-823) Market Notice 36471 was issued to inform participants of inter-regional transfer 2158 hrs limitations due to the constraints invoked. The constraints did not bind. 31-Oct-11 0039 hrs 0040 hrs No. 1 275 kv busbar at Mt. England was returned to service; 825 Tarong Mt. England 275 kv line was reconnected to Mt. England No.1 275 kv busbar. 8812 Tarong Mt. England 275 kv line was reconnected to Mt. England 275 kv 1 Busbar. Market Notice 36472 was issued to advise participants of a non-credible contingency 0059 hrs event and that AEMO did not reclassify this event as a credible contingency event. 823 Mt. England Wivenhoe 275 kv line was returned to service. 0110 hrs Constraint set (Q-MEWV-823) was revoked. 10:23-10:26 hrs 837 Tarong Mt. England 275 kv line was returned to service via No. 2 275 kv busbar at Mt. England by closing H012 Mt. England CB 5042 and H018 Tarong CB 5012 and CB 8372. 1030 hrs Constraint set (Q-TRME) was revoked. In accordance with its operating procedure SO_OP 3715 Power System Security Guidelines 1, AEMO determined that it was not appropriate to reclassify the loss of 837 Tarong Mt. England 275 kv line and No.1 275 KV busbar at Mt. England as a credible contingency because the high voltage equipment associated with the failed Mt. England No.1 275 KV busbar remained out of service for repairs. 5 Follow-up Actions Powerlink identified and replaced the faulty 275 kv CT equipment associated with CB 8372 at Mt. England substation. The 837 Tarong Mt. England 275 kv line was reconnected to No.1 275 kv busbar at Mt. England and re-energised at 1632 hrs on 2 November 2011. 6 Power System Security Assessment There was no loss of load or generation as a result of this event. The power system voltages and frequencies remained within the normal operating bands and the power system remained in a secure operating state throughout the incident. AEMO followed its procedures and determined that it was not appropriate to reclassify the loss of 837 Tarong Mt. England 275 kv line and No.1 275 KV busbar at Mt. England as a credible contingency based on the information Powerlink provided to AEMO. 1 Clause 4.2.3B of the NER requires that AEMO establish criteria to use when considering whether a noncredible contingency event is reasonably possible. This is published in AEMO operating procedure SO_OP 3715 Power System Security Guidelines, which is available at: http://www.aemo.com.au/electricityops/3715.html 19 April 2012 Page 11 of 12

7 Conclusions At 2134 hrs on 30 October 2011, a sequence of transmission system network events occurred over a two second period as a result of separate one phase to ground faults occurring on 275 kv Feeder 837 Tarong Mt. England conductors during a storm. Consequently, Mt. England No.1 275 kv busbar tripped due to a flashover, which occurred at a location internal to the CT and within the zone protected by the No.1 275 kv busbar protection systems. The faults were cleared from the power system and Powerlink replaced the affected network elements at Mt. England substation. AEMO is satisfied that Powerlink has carried out the appropriate work to minimise the risk of a similar incident occurring in the future. AEMO correctly applied the criteria published in section 12 of its Power System Security Guidelines in assessing that the circumstances of this incident did not warrant reclassifying similar incidents as a credible contingency event. 8 Recommendations There are no recommendations arising from this incident. 19 April 2012 Page 12 of 12