Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Similar documents
Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

100 MW Wind Generation Project

New Mexico Transmission Expansion Concepts For Wind Resources

Sub Regional RTEP Committee Western Region ATSI

Interconnection System Impact Study Report Request # GI

The Green Line Project

Feasibility Study Report

MILLIGAN SOLAR PROJECT

CUSTOMER/ TWIN ARROWS PROJECT

Supplemental Report on the NCTPC Collaborative Transmission Plan

PSE Attachment K Puget Sound Area Transmission Meeting

SPS Planning Criteria and Study Methodology

TRANSMISSION PLANNING CRITERIA

Feasibility Study Report

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

Feasibility Study Report

System Impact Study Report

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

New Jersey State Report

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Illinois State Report

Project #148. Generation Interconnection System Impact Study Report

15 Nelson-Marlborough Regional Plan

DFO STATEMENT OF NEED REPORT

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

SERTP rd Quarter Meeting

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

West Station-West Cañon 115 kv Transmission Project

SPP Notification to Construct

SERTP rd Quarter Meeting

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

15 Nelson-Marlborough Regional Plan

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Project #94. Generation Interconnection System Impact Study Report Revision

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project.

Transmission Planning for Wind Energy Resources in the Eastern United States. Dale Osborn

Interconnection Feasibility Study Report GIP-084-FEAS-R2

ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS. June 18, 2015 E2Tech Presentation

Appendix D Black Hills Project Summary

ATTACHMENT Y STUDY REPORT

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Sheffield-Highgate Export Interface SHEI. VSPC Quarterly Meeting October 18, 2017

Sub Regional RTEP Committee Mid-Atlantic

North Oregon Coast Area Study. Adam Lint

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Reliability Analysis Update

Western Area Power Administration Sierra Nevada Region

NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources

The Long-Range Transmission Plan

Falcon-Midway 115 kv Line Uprate Project Report

LOCAL TRANSMISSION PLAN

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Consulting Agreement Study. Completed for Transmission Customer

PG&E s 2012 Request Window Proposals

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Generation Deactivation Notification Update

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

3 Existing National Grid

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Seabrook Substation Reliability Improvement Project

Sub Regional RTEP Committee - Southern. August 19, 2011

Energy Storage Interconnection Initiative

Impact of Distributed Energy Resources on Transmission System Reliability

EIPC HIGH LEVEL TRANSMISSION COST ESTIMATION TASK #5: DOE PROJECT NO. DE-OE

REDACTED. Eastside Needs Assessment Report Transmission System King County. Redacted Draft. October 2013 Puget Sound Energy

Maddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016

ATTACHMENT - DFO STATEMENT OF NEED

Electric Power Transmission: Research Needs to Sustain a Critical National Infrastructure

Overview of ISO New England and the New England Wholesale Power Markets

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Western Area Power Administration Sierra Nevada Region

New 115 kv Disconnect Switches at Bloomsburg MTS

Generator Interconnection System Impact Study For

Sub Regional RTEP Committee South

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Sub-Regional RTEP Committee PJM South

Surry Skiffes Creek Whealton Modeling and Alternatives Analysis Review

Reliability Analysis Update

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Interconnection Feasibility Study Report GIP-369-FEAS-R1

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

SPP Notification to Construct

3 Reliability Issues and Solutions

May 11, Ms. Kavita Kale Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway Post Office Box Lansing, MI 48909

March 7, Subject: Southern California Edison 2011 Annual Progress Report

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Guideline for Parallel Grid Exit Point Connection 28/10/2010

SMUD 2014 Ten-Year Transmission Assessment Plan. Final. December 18, 2014

Key to Status Fields in the Project List

2018 & 22 Final LCR Study Results Greater Bay Area

Transcription:

OCTOBER 22, 2014 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting E M i R t ti Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Purpose of Local System Plan (LSP) Per Attachment K of the ISO-New England OATT The LSP is an annual report that: t Describes non PTF transmission system reliability needs Reflects Local System planning studies Proposed solutions Identifies Local planning process Criteria, Data and Assumptions 2

LSP Communication LSP is communicated via Transmission Owners Planning Advisory Committee (TOPAC) meeting following an ISO-New England PAC meeting The material is posted prior to the TOPAC meeting (via the ISO-New England PAC posting system) Transmission Customers and Stakeholders have 30 days after TOPAC presentation ti to provide written comments for consideration by Emera Maine 3

LSP Communication (continued) Emera Maine Contact: Kendra Overlock PO Box 932 970 Illinois Avenue Bangor, Maine, 04402-0932 (207) 973-2895 Kendra.Overlock@EmeraMaine.com EM LSP is located at: http://www.emeramaine.com/about-us/transmissiondevelopment/local-system-plan plan.aspxaspx 4

Local System Planning Process The process is Needs Assessment followed by Solutions Proposals Local System needs can result from: Load Growth Sub-area reliability assessments Point of delivery request from customers Generation interconnection requests (in accordance with appropriate generator interconnection procedures) Local System Plan consists of: Summary of needs assessment results Listing of criteria, data and study assumptions Identification of proposed alternatives Solution study results and selection of preferred alternative 5

Criteria, Data, and Assumptions Loads are based on the New England specific area as provided d in the ISO-New England MOD case, EM specific forecasts and local customer needs are used to refine this Studies use relevant assumptions regarding transmission, generation and demand resources found in the latest ISO-New England Regional System Plan Criteria follows ISO-New England as well as TPL criteria or local planning criteria as appropriate Local criteria listed at the end of this presentation 6

LSP Project List The LSP project list is a cumulative listing of proposed transmission solutions intended to meet local needs Similar to the ISO-New England PTF RSP, the LSP contains the status of each project Concept Project is under consideration as a solution to a partial needs assessment Proposed Needs assessment completed and project proposed as a solution, but not formally budgeted d Planned Formally budgeted and if necessary, approved by ISO-New England Under Construction Significant engineering and internal approvals in process and project is being implemented In-Service Project used and useful 7

LSP - Needs Need Needs Assessment Service Area Potential Solutions Year of Need QP478 Interconnection study Transmission upgrades to support proposed generation Washington County Under study 6/2015 8

LSP Concept Status Need Reliability Reliability Reliability Needs Assessment Line 74 Condition L50 condition and support of area load growth Service Area Project Name Status Solutions Bangor Line 74 Study Bangor Corinth Village support Study L70 condition and Thermal Bangor Line 73 Study and Voltage L74 Rebuild/Recon ductor L50 Rebuild/Recon ductor Project In- Service Month/Year 12/2016 12/2016 L73 Rebuild/Recon 12/2016 ductor 9

LSP Proposed Status Need Reliability Needs Assessment Service Area Project Name Status Solutions Eastern Bangor 46kV line load Waterworks extension and Bangor Proposed requirements substation load serving including hospital substation Project In- Service 12/2016 10

LSP Planned Status Need Needs Assessment Service Area Reliability Line 13 Condition Downeast Project Name Line 13 Rebuild E Franklin east Status Reliability Line 5 Overload Bangor T9L/501 line Planned Reliability Reliability eab Improve area reliability, support MDI loads, defer L32 loading issue and improve ability to maintain transmission circuits Line 8 Condition and dloading Downeast MDI reliability Planned Bangor Line 8 Reconductor Solutions Project In- Service Planned Rebuild 12/2015 Rebuild 0.25 mi Additional 34.5kV circuit with diverse route. Part of area looping Line 8 Planned reconductor o sections 12/2014 12/2016 06/2015 11

LSP Under Construction Status Need Project In-Service Service Area Project Name Status Reliability 12/2014 Northern Chester T3 Addition Under Construction Reliability 12/2014 Northern Line 87 Rebuild Under Construction Reliability 12/2015 Bangor Reliability 12/2014 Downeast Line 75 Rebuild/reconductor L13 from E Franklin west rebuild Under Construction Under Construction 12

LSP In-Service Need Project In-Service Month/Year Service Area Project Name Status Nothing to report 13

Maine and Emera Maine Bangor Hydro District - Major Transmission System 14

Emera Maine Bangor Hydro District Detailed System 15

Project Descriptions - Needs Queue 478 Interconnection 10MW wind interconnection ti to the EM subtransmission i in Washington County 16

17 Project Descriptions - Needs

Project Descriptions - Concept Line 74 Rebuild/Reconductor condition of existing facilities and thermal and voltage issues on 46kV system Line 50 Rebuild/Reconductor Condition based need for rebuild as well as thermal and voltage issues Line 73 Rebuild/Reconductor Condition based need for rebuild as well as thermal and voltage issues 18

19 Project Descriptions - Concept

Project Descriptions Proposed Waterworks Substation new 46/12.5kV substation as well as short 46kV line extension to serve the local l Eastern Bangor load as well as hospital expansion 20

21 Project Descriptions - Proposed

22 Waterworks Substation

Project Descriptions - Planned Line 13 Rebuild E. Franklin east Line 5 T9L/501 Rebuild 0.25 miles MDI Reliability additional 34.5kV circuit with diverse route. Line 8 Reconductor segment and related switching 23

24 Project Descriptions - Planned

25 Line 13 Rebuild E. Franklin east

26 Line 5 Rebuild T9L/501

27 MDI Reliability

28 Line 8 Reconductor

Project Descriptions Under Construction Chester T3 Line 87 Rebuild Line 75 Rebuild/Reconductor Line 13 from E. Franklin west Rebuild 29

Project Descriptions Under Construction 30

31 Chester T3

32 Line 87 Overload

33 Line 75

34 Line 13 E. Franklin west

Local System Planning Criteria The transmission system for purposes of this study is defined as those system facilities that are operated at 34.5kV and above and are not considered to be under ISO-NE planning (in general non PTF). The standard of service to be provided dictates the need for changes to the existing system. It is necessary to consider the capability of transmission system elements, possible equipment failures, and the impact of failures on the ability to serve area loads. Transmission equipment is designed to operate within certain capabilities. The power that may be transferred over transmission lines depends upon the current carrying capacity of the wire and/or the required clearances of lines above ground. Transformers are limited by their heat dissipation capability. Circuit breakers or switches are designed to sustain a certain continuous amount of current. Also, the operation of customer electrical equipment requires that voltage be maintained within a certain acceptable range. Transmission system facilities are capable of regulating voltage within a limited range by varying reactive power and changing transformer tap settings. 35

Local System Planning Criteria Since all equipment is subject to breakdown, it is necessary to consider the consequence of such failures. One possible outcome could be the overload of other equipment that remains in service. For example, if one of two parallel lines trips, the remaining line may become overloaded. Overload beyond emergency ratings must be avoided due to possible permanent damage to the equipment or for public safety. Another consequence of equipment failure is the loss of power supply to customer load. This could occur with the loss of a radial transmission line or as the result of the cascaded outage of a looped transmission system. The loss of supply is critical to loads such as industrial processing, home heating, and hospitals, and must be considered in the design of the transmission system. 36

Local System Planning Criteria CAPACITY CRITERION No facility is to be loaded in excess of its normal rating for any expected dispatch of system generation at any load level. For any single contingency, no facility is to be loaded in excess of its normal rating for the following load cycle or in excess of its emergency rating immediately following the contingency,. Uneconomic generation dispatch may be utilized to maintain power flows within ratings following a contingency. VOLTAGE CRITERION Transmission system voltages are to be maintained between 95% and 105% of operating base voltage under normal system conditions and for any single contingency. Further, voltages on the regulated side of load serving buses are to be maintained between 100% and 105% of operating base voltage under normal system conditions. 37

Local System Planning Criteria LOSS OF LOAD CRITERION No loss of load in excess of 25 MW is to occur for any single contingency. Loss of load less than 25 MW should be resupplied within 24 hours, except under very adverse conditions. MAINTENANCE CRITERION Transmission system planned maintenance is to be possible without exceeding normal voltage and capacity limits and without loss of load. 38

39 Questions?