RELIABILITY ASSESSMENT OF POWER EQUIPMENT IN A DISTRIBUTION SUBSTATION USING FAULT TREE ANALYSIS A. J. Adelabu, Y. S. Haruna and U. O.

Similar documents
New York Science Journal 2017;10(3)

Impact Analysis of Fast Charging to Voltage Profile in PEA Distribution System by Monte Carlo Simulation

Computer Aided Transient Stability Analysis

A Comparison of Typical UPS Designs in Today s Markets

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

Research on Failure mode and effect analysis of Diesel Engine

Dual Power. Protection. Protection

Cost Benefit Analysis of Faster Transmission System Protection Systems

SAFETY AND RELIABILITY ANALYSIS OF ELECTRIC POWER STEERING SYSTEM USED IN AUTOMOBILES

Data envelopment analysis with missing values: an approach using neural network

Reliability determination of ignition system of rocket platform using reliability block diagram and FMEA analysis

Comparing the Lateral Behaviour of a Boil off Gas Compressor with Dry and Wet Seals

Design and Implementation of an Automatic Power Supply from Four Different Source Using Microcontroller

Reliability Analysis of Radial Distribution Networks with Cost Considerations

Power System Stability Analysis on System Connected to Wind Power Generation with Solid State Fault Current Limiter

Experience on Realizing Smart Grids. IEEE PES conference, Gothenburg

APPLICATION OF RELIABILITY GROWTH MODELS TO SENSOR SYSTEMS ABSTRACT NOTATIONS

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC

Increasing PV Hosting Capacity in Distribution Networks: Challenges and Opportunities. Dr Andreas T. Procopiou

3.0 Radial Distribution Systems

Assessing Feeder Hosting Capacity for Distributed Generation Integration

International Journal of Advance Research in Engineering, Science & Technology

Substation Maintenance Training

CHAPTER 4 SUBSTATION CONFIGURATION RELIABILITY ESTIMATION BY SUCCESSFUL PATH METHOD

CHAPTER 1 INTRODUCTION

POWER DISTRIBUTION SYSTEM ANALYSIS OF URBAN ELECTRIFIED RAILWAYS

RESILIENT SOLAR CASE STUDY: SUNY New Paltz NYPA Integrated Grid Pilot

Battery Maintenance Solutions for Critical Facilities

Implementation of Steady-State Power System Visualizations Using PowerWorld Simulator. Dr. Jung-Uk Lim, Department of Electrical Engineering

Control System for a Diesel Generator and UPS

Enhancement of Power Quality in Transmission Line Using Flexible Ac Transmission System

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

Utility Distribution Planning 101

MIKLOS Cristina Carmen, MIKLOS Imre Zsolt UNIVERSITY POLITEHNICA TIMISOARA FACULTY OF ENGINEERING HUNEDOARA ABSTRACT:

Development of Electrical Power System Simulator.

Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR)

Presented By: Bob Uluski Electric Power Research Institute. July, 2011

Grounding systems for power supply facilities

Power Quality and Power Interruption Enhancement by Universal Power Quality Conditioning System with Storage Device

American Electric Power s Energy Storage Deployments

Breaking new ground. A circuit breaker with the capacity to switch 15 large power plants

Electric Vehicles Coordinated vs Uncoordinated Charging Impacts on Distribution Systems Performance

INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT

POWER TRANSMISSION OF LOW FREQUENCY WIND FIRMS

Building a 21 st Century Electric Grid. February 23, 2018

An Application of the Fault Tree Analysis for the Power System Reliability Estimation

Available Transfer Capacity with Renewable Energy

RESEARCH OF THE DYNAMIC PRESSURE VARIATION IN HYDRAULIC SYSTEM WITH TWO PARALLEL CONNECTED DIGITAL CONTROL VALVES

Investigating The Effect of Switching and tripping on Flashover and Breakdown in Circuit Breaker

Okelola, M. O. Department of Electronic & Electrical Engineering, Ladoke Akintola University of Technology, P.M.B. 4000, Ogbomoso, Nigeria

Journal of American Science 2015;11(11) Integration of wind Power Plant on Electrical grid based on PSS/E

Appendix C. Safety Analysis Electrical System. C.1 Electrical System Architecture. C.2 Fault Tree Analysis

The Swedish Government Inquiry on Smart Grids

Using Active Customer Participation in Managing Distribution Systems

Academic Course Description

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems

Design Modeling and Simulation of Supervisor Control for Hybrid Power System

Impact of Distributed Generation on Reliability of Distribution System

Seabrook Substation Reliability Improvement Project

GRID MODERNIZATION INITIATIVE PEER REVIEW GMLC Control Theory

Review paper on Fault analysis and its Limiting Techniques.

PRESENTER PETER NJENGA CHIEF ENGINEER, CUSTOMER SERVICE, KENYA POWER EAST AFRICAN POWER INDUSTRY CONVENTION 2012

Battery Energy Storage System addressing the Power Quality Issue in Grid Connected Wind Energy Conversion System 9/15/2017 1

Automobile Body, Chassis, Occupant and Pedestrian Safety, and Structures Track

A Method for Determining the Generators Share in a Consumer Load

CHAPER 5 POWER FLOW STUDY IN THE INTEGRATED GRID NETWORK

Stress and Design Analysis of Triple Reduction Gearbox Casing

Aswan high dam - Distributed control system AUTOMATION

INTERNATIONAL JOURNAL OF CIVIL AND STRUCTURAL ENGINEERING Volume 5, No 2, 2014

Advanced Protective Relay Training

Fuel Consumption, Exhaust Emission and Vehicle Performance Simulations of a Series-Hybrid Electric Non-Automotive Vehicle

PV inverters in a High PV Penetration scenario Challenges and opportunities for smart technologies

Study on Braking Energy Recovery of Four Wheel Drive Electric Vehicle Based on Driving Intention Recognition

NORDAC 2014 Topic and no NORDAC

International Journal of Scientific & Engineering Research, Volume 6, Issue 7, July ISSN

DATA QUALITY ASSURANCE AND PERFORMANCE MEASUREMENT OF DATA MINING FOR PREVENTIVE MAINTENANCE OF POWER GRID

Design & Development of Regenerative Braking System at Rear Axle

e t Performance of Extended Inlet and Extended Outlet Tube on Single Expansion Chamber for Noise Reduction

Contingency Ranking and Analysis using Power System Analysis. Toolbox (PSAT)

Design, Construction and Testing of an Electric Powered Toggle Jack Mechanism

Excessive Heat In Electric Motors: A Common Root Cause of Insulation Failure

ROAD SAFETY RESEARCH, POLICING AND EDUCATION CONFERENCE, NOV 2001

University Of California, Berkeley Department of Mechanical Engineering. ME 131 Vehicle Dynamics & Control (4 units)

Implementation SVC and TCSC to Improvement the Efficacy of Diyala Electric Network (132 kv).

Umatilla Electric Cooperative Net Metering Rules

Remarkable CO 2 Reduction of the Fixed Point Fishing Plug-in Hybrid Boat

STABILIZATION OF ISLANDING PEA MICRO GRID BY PEVS CHARGING CONTROL

CFD on Cavitation around Marine Propellers with Energy-Saving Devices

Features of PSEC Educational Programs

RC COMPANY PROFILE

Research and Design on Electric Control System of Elevator Tower for Safety Devices Yuan Xiao 1, a, Jianping Ye 2,b, Lijun E 1, Ruomeng Chen 1

VEDECOM. Institute for Energy Transition. Presentation

FAULT ANALYSIS IN GEARBOX USING VIBRATION TECHNIQUE

Analysis of Grid Connected Solar Farm in ETAP Software

FAULT ANALYSIS FOR VOLTAGE SOURCE INVERTER DRIVEN INDUCTION MOTOR DRIVE

Comparison Of Multibody Dynamic Analysis Of Double Wishbone Suspension Using Simmechanics And FEA Approach

Optimal System Solutions Enabled by Digital Pumps

Modular Standardized Electrical and Control Solutions for Fast Track Projects

Project Summary Fuzzy Logic Control of Electric Motors and Motor Drives: Feasibility Study

Transcription:

GSJ: VOLUME 6, ISSUE 2, FEBRUARY 2018 249 GSJ: Volume 6, Issue 2, February 2018, Online: ISSN 2320-9186 RELIABILITY ASSESSMENT OF POWER EQUIPMENT IN A DISTRIBUTION SUBSTATION USING FAULT TREE ANALYSIS A. J. Adelabu, Y. S. Haruna and U. O. Aliyu Department of Electrical and Electronics Engineering Abubakar Tafawa Balewa University, Bauchi-Nigeria. Corresponding Author: getademola@yahoo.com ASTRACT: This paper presents the reliability assessment of power equipment in a distribution substation using fault tree analysis (FTA) technique. The 33/11kVAnglo-Jos distribution substation of the Jos Electricity Distribution PLC was used as the case study for this research. The aim of the research is to analyze the reliability of power equipment in a distribution substation by using fault tree analysis. The data recorded in the substation s log book was used as the field data for this research work. The field data includes frequencies of failures of power equipment in the substation and their respective durations of failures. The single line diagram and the fault tree diagram of the power equipment in the distribution substation was constructed. The FTA model showed the logical arrangement of the basic events in hierarchical form leading to the desired top event. The qualitative fault tree analysis was done to determine the minimal cuts of the basic events that could lead to the top event by using Boolean algebra and probability expressions. The quantitative fault tree analysis was carried out to determine the mean time between failures (MTBF), mean time to repair (MTTR) and unavailability of each power equipment by using reliability expressions. The power equipment with the best MTBF and MTTR were also identified and discussed. This paper identified the power equipment that should be upgraded so as to achieve reliable distribution substation and guarantee improved electricity delivery to consumers. Keywords: Power Equipment, Reliability, Fault tree Analysis and Distribution Substation. I.

GSJ: VOLUME 6, ISSUE 2, FEBRUARY 2018 250 I. INTRODUCTION Electricity is the hub of both economic and technological development. More important is the fact that every other sector of the economy depends on adequate supply of electricity. Poor state of electricity supply in Nigeria has imposed significant costs on the manufacturing sector. The bulk of these costs relate to the firms acquisition of very expensive backup capacity to cushion them against the even larger losses arising from frequent and long power fluctuations. Small-scale operators are more heavily affected by the power outage as they are unable to finance the cost of backup power necessary to mitigate the impact of frequent outages [1]. Due to lack of efficiency in the power sector in Nigeria, the Nigerian Electricity Supply Industry (NESI) was unbundled into eighteen companies comprising of 6 generating companies (GENCOs), 1 transmission company (TRANSYSCO) and 11 distribution companies (DISCOs). The intention of this metamorphosis was to ensure improved system reliability, but this is very difficult to achieve because of the poor system maintainability that has been occurring for a very long time. The issue of maintenance of electric power equipment is of paramount national interest [2]. The electric power distribution substations are the most critical part of a power system because the power equipment in the distribution substation connects the consumers to the power grid. A substation reliability assessment evaluates the effect of these aspects on the service continuity of the main power system connected to the substation [3]. With increasing demand for electricity supply, the distribution companies have to achieve an acceptable level of reliability, quality and safety at an economic price in order to guarantee improved electricity delivery and maintain consumer s loyalty [4]. II. LITERATURE REVIEW This paper focuses on the use of fault tree analysis (FTA) method to perform the reliability assessment of power equipment in a distribution substation. A fault tree translates the failure behavior of a physical system into a visual diagram and a logical model [5]. Fault Tree Analysis (FTA) was originally developed in 1962 at Bell Laboratories by H.A Watson, under a U.S Air Force Ballistics Systems Division contract to evaluate the Minuteman I Intercontinental Ballistic Missile (ICBM) Launch Control System [6]. The use of fault trees has since gained widespread support and is often used as a failure analysis tool by reliability experts. Following the first published use of FTA in the 1962 Minuteman I Launch Control Safety Study, Boeing and AVCO expanded use of FTA to the entire Minuteman II system in 1963-1964 [7]. The Boeing Company improved the technique and introduced computer programs for both qualitative and quantitative fault tree analysis. At the 1965 Safety Symposium, sponsored by the University of Washington and the Boeing Company, several papers were presented that expounded the virtues of fault tree analysis. The presentation of these papers marked the beginning of the wide-spread interest in using fault tree analysis as a system safety and reliability tool for complex dynamic system such as nuclear reactors [8]. Since 1960, great efforts have been made in solving fault trees to obtain reliability information about complex systems. Following the lead of the aerospace industry, the nuclear power industry discovered the virtues and benefits of fault tree analysis, and began using the tool in the design and development of nuclear power plants [9]. Many key individuals in nuclear power industry contributed to advancing fault tree theory and fault tree software codes. In fact, the nuclear power industry may have contributed more to the development of fault tree analysis than any other single user group. Many new evaluation algorithms were developed, along with software using these algorithms. Today fault tree analysis is by far the most commonly used technique of risk and reliability studies. Fault tree analysis has particularly been used with success to analyze system in nuclear power station [8].

GSJ: VOLUME 6, ISSUE 2, FEBRUARY 2018 251 A. Reliability Expressions in Fault Tree Analysis Reliability expressions are used in fault tree analysis to determine the failure rate probability of the basic and overall top events. The expressions include; ) Where, = Reliability λ = failure rate T = Average down time per failure MTBF= Mean time between failures MTTR = Mean time to repair and 8760 = Total hours for a year

GSJ: VOLUME 6, ISSUE 2, FEBRUARY 2018 252 III. MATERIAL AND METHODS The procedure in carrying out reliability assessment of power equipment in 33/11kV Anglo-Jos distribution substation using fault tree analysis technique is shown in Figure 1. The line diagram of the 33/11kV Anglo-Jos distribution substation shows the single-line schematic principle of breakdown of 33kV coming from Makeri transmission substation to 11kV been distributed to consumers within Anglo-Jos axis and its environs. The single line diagram of the 33/11kV Anglo-Jos distribution substation can be seen in Figure 2. The fault tree diagram of the 33/11kV Anglo-Jos distribution substation shows the logical arrangements of power equipment in the distribution substation. It represents the combination of the power equipment and their contribution to the overall system unavailability. The fault tree diagram is represented in Figure 3. Figure 1: Outlined Procedure of Fault Tree Analysis of the 33/11kV Distribution Substation

GSJ: VOLUME 6, ISSUE 2, FEBRUARY 2018 253 Figure 2: The Single Line Diagram of the 33/11kV Anglo-Jos Distribution Substation. Figure 3: Fault Tree Diagram of the 33/11kV Anglo-Jos Distribution Substation.

GSJ: VOLUME 6, ISSUE 2, FEBRUARY 2018 254 IV. RESULTS AND DISCUSSIONS The results of this paper showed the qualitative fault tree analysis and the quantitative fault tree analysis of the 33/11kV Anglo-Jos distribution substation. The log books were used as data received. The qualitative fault tree analysis was done using Boolean algebra and probability expressions. The quantitative fault tree analysis was done by using reliability expressions as shown in the literature review. A. Qualitative Fault Tree Analysis Results The purpose of performing the qualitative fault tree analysis is to determine the minimal cut sets that could easily lead to the overall system unavailability of power in the 33/11kV distribution substation. Let: F a = 33kV wiring failure, F b = Battery bank failure, F c = Auxiliary transformer failure F d = 33kV circuit breaker failure, F e = Current transformer failure, F f = Disc insulator failure F g = Power Transformer T1 failure, F h =Power Transformer T2 failure, F i =11kV Liberty Dam feeder failure F j = 11kVHwolshefeeder failure, F k = 11kVTudunwada feeder failure, F l = 11kVIbrahim Taiwo feeder failure The following failures can be calculated as; Station service failure = (F b F c ) (11) System protection failure = (F d F e F f ) (12) Power transformer failure = (F g F h )... (13) 11kV distribution feeder failure = (F i F j F k F l ) (14) Overall system unavailability = F a (F b F c ) (F d F e F f ) (F g F h ) (F i F j F k F l ) = F a + (F b F c ) + (F d +F e + F f ) + (F g F h ) + (F i F j F k F l ) (15) The minimal cut sets are F a, (F b F c ), F d, F e, F f, (F g F h ) and (F i F j F k F l ). The list of the minimal cut sets can be seen in Table 1. Table 1: List of minimal cut sets and their corresponding power equipment S/No. Cut Sets Power Equipment 1 F a 33kV wiring failure 2 F b F c Battery bank failure and Auxilliary transformer failure 3 F d 33kV circuit breaker failure 4 F e Current transformer failure 5 F f Disc insulator failure 6 F g F h Power transformer T1 failure and Power transformer T2 failure 7 F i F j F k F l 11kV distribution feeders B. Quantitative Fault Tree Analysis of the 33/11kV Anglo-Jos Distribution Substation The data received were analyzed based on the power equipment used in the Anglo-Jos distribution substation. Durations of failure of each power equipment were extracted. Similarly, frequency of failure of each power equipment were extracted. These data were extracted for a period of one year (January 2016 to December2016). The tabulated results are analyzed in Table 2.The comparison of the failure frequencies (F), duration of failures (T), mean time between failures (MTBF), mean time to repair (MTTR) and unavailability of power equipment were done as listed in Figures 4 to 8.

GSJ: VOLUME 6, ISSUE 2, FEBRUARY 2018 255 Table 2: Analysis of the Power Equipment in Anglo-Jos Distribution Substation in 2016 S/No. Power Equipment Frequency (F) Duration (Hrs) MTBF (Hrs) MTTR (Hrs) Unavailability 10-4 1 33 kv Line 29 70 299.6551 2.4137 7990 2 Auxiliary Transformer 22 45 396.1363 2.0454 5136 3 110 V DC Battery Bank 5 36 1744.8000 7.2000 4109 4 33 kv Circuit Breaker 2 2 4379.0000 1.0000 228 5 Current Transformer 1 1 8759.0000 1.0000 114 6 Disc Insulators 10 12 874.8000 1.2000 1369 7 Power Transformer T1 11 40 792.7272 3.6363 4566 8 Power Transformer T2 3 11 2916.3333 3.6666 1255 9 11 kv Liberty Dam Feeder 86 264 98.7906 3.0697 30136 10 11 kv Hwolshe Feeder 40 84 216.9000 2.1000 9589 11 11 kv Tudun Wada Feeder 48 117 180.0625 2.4375 13356 12 11 kv Ibrahim Taiwo Feeder 53 94 163.5094 1.7735 10730 failure frequencies 100 90 80 70 60 50 40 30 20 10 0 29 22 5 2 1 10 11 3 86 40 48 53 Figure 4: Comparison of Frequencies of Failures of Power Equipment in 33/11kV Anglo-Jos Distribution Substation in Year 2016

GSJ: VOLUME 6, ISSUE 2, FEBRUARY 2018 256 Duration of failures (HRS) 300 250 200 150 100 50 0 70 45 36 2 1 12 40 11 264 84 117 94 Figure 5: Comparison of Duration of Failures of Power Equipment in 33/11kV Anglo-Jos Distribution Substation in Year 2016 MTBF (HRS) 10000 9000 8000 7000 6000 5000 4000 3000 2000 1000 0 299.7 396.1 1744.8 4379 8759 874.8 792.7 2916.3 98.8 216.9 180.1 163.5 Figure 6: Comparison of Mean Time Between Failures (MTBF) of Power Equipment in 33/11kV Anglo-Jos Distribution Substation in Year 2016

GSJ: VOLUME 6, ISSUE 2, FEBRUARY 2018 257 MTTR (HRS) 8 7 6 5 4 3 2 1 0 2.4 2 7.2 1 1 1.2 3.6 3.7 3.1 2.1 2.4 1.8 Figure 7: Comparison of Mean Time to Repair (MTTR) of Power Equipment in 33/11kV Anglo-Jos Distribution Substation in Year 2016 35000 30000 30136 UNAVAILABILITY 10-4 25000 20000 15000 10000 5000 0 7990 5136 4109 228 114 1369 4566 1255 9589 13356 10730 Figure 8: Comparison of Unavailability of Power Equipment in 33/11kV Anglo-Jos Distribution Substation in Year 2016

GSJ: VOLUME 6, ISSUE 2, FEBRUARY 2018 258 C. Discussions of Results Figure 4 showed that 11kV liberty dam feeder had the highest number of failure in the year 2016. Figure 5 showed that 11kv liberty dam feeder had the highest duration of failures in the year 2016. In general, 11kV liberty dam feeder had the highest number of failures and duration of failures within the period. It is therefore necessary to work on the causes of failures of the 11kV liberty dam feeder in order to improve the reliability of the distribution substation. Figure 6 showed that the current transformers had the highest mean time between failures (i.e above 8759 hours) within the period reviewed. This means that the current transformers can work for an average of 8759 hours before it fails. The 11kV liberty dam feeder had the least mean time between failures (i.e below 99 hours) within the period reviewed. This means that 11kV liberty dam feeder cannot efficiently work for 99 hours without developing a fault. Figure 7 showed that the 110V DC battery bank had the highest mean time to repair within the period reviewed. This means that the 110V DC battery bank is not been repaired or fixed for a long period of hours (i.e 7.2 hours) whenever it fails. Figure 8 showed that 11kV liberty dam feeder had the highest probability of unavailability among the power equipment used in the distribution substation. The results also showed that 33kV circuit breaker and the current transformer had the least probability of system unavailability. V. CONCLUSION The aim of this paper is to perform a reliability assessment of power equipment in a 33/11kVdistribution substation using fault tree analysis technique. The single line diagram of the distribution substation showed the power equipment in the substation and their arrangement in breaking down the 33kV to 11kV for the purpose of delivering power to consumers. The fault tree diagram showed the logical arrangement of the power equipment and their contribution towards overall system unavailability. The qualitative fault tree analysis showed the minimal cut sets that could easily lead to the overall system unavailability and the quantitative fault tree analysis has helped to identify the power equipment that are contributing majorly to system unavailability and these power equipment should be upgraded to obtain a better reliability of the system.

GSJ: VOLUME 6, ISSUE 2, FEBRUARY 2018 259 REFERENCES [1] Nnanna, I. &Uzorh, A. (2016). The impact of power outages on Nigeria manufacturing sector, Nigerian Institute of Industrial Engineers, vol. 1, no 2. [2] Awosope, C.A. (2014). Nigeria electricity industry: issues, challenges and solutions, public lecture at Covenant University, series, vol. 3, no. 2. [3] Zapata, C. Alzate, A. & Rios, M. (2010). Reliability assessment of substations using stochastic point processes and Monte Carlo simulation, IEEE international conference on power system technology, September, 2010. [4] Adegboyega, G. &Onime, F. (2014). Reliability analysis of power distribution system in Nigeria: A case study of Ekpoma network, Edo state, International journal of electronics and electrical engineering vol. 2, No. 3, September 2014. [5] Johan, K. (2014). Analyzing substation automation system reliability using probabilistic relational models and enterprise architecture, KTH, dissertation, Royal institute of technology, Stockholm, Sweden, March, 2014. [6] Isaac, A. Awelewa, A. Katende, J. &Odigwe, I. (2013). Fault tree-based reliability assessment of a 132-kV transmission line protection scheme, American journal of engineering research, vol. 2, pp100-106. [7] Mohammad, J, Nobakht, A. & Meskarbashee, A. (2011). Fault Tree Analysis Approach in Reliability Assessment of Power System, International Journal of Multidisciplinary Sciences and Engineering, 2(6). [8] Josep, S. (2014). Failure Analysis of Power Transformer Based on Fault Tree Analysis, Ph D. Dissertation, Kyoto University Research Repository. [9] Ahmed, A. Ruzli, R. & Buang, A. (2013). Reliability analysis using fault tree analysis: A review, International Journal of Chemical Engineering and Applications, 4(3).