LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST

Similar documents
Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

CUSTOMER/ TWIN ARROWS PROJECT

Rate Schedules. Effective 1/1/2019

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

TELL CITY ELECTRIC DEPARTMENT RATES AND CHARGES

M.P.S.C. No. 2 Electric Third Revised Sheet No. 65 (Rate Case) Cancels Second Revised Sheet No. 65

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

JEA Distributed Generation Policy Effective April 1, 2018

Umatilla Electric Cooperative Net Metering Rules

AUSTIN UTILITIES. CHARACTER OF SERVICE: AC, 60 cycles, 120/240 Volt, three wire, single-phase; or 120 Volt, two wire.

MILLIGAN SOLAR PROJECT

D. Operation and Maintenance Data. In addition to items specified in Division 1 Section "Operation and Maintenance Data," include the following:

100 MW Wind Generation Project

Feasibility Study Report

Generation Interconnection Facilities Study For

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Small Generator Interconnection Program Interconnection Technical Requirements

Southwest Power Pool Network Integration Transmission Service Application

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

INTERCONNECTION FACILITIES STUDY REPORT

SANTA CLARA CITY RENEWABLE NET METERING & INTERCONNECTION AGREEMENT

PUD ELECTRIC SYSTEM INTERCONNECTION

FACILITIES STUDY CONSTELLATION ENERGY TRANSMISSION SERVICE REQUEST OASIS

Project #148. Generation Interconnection System Impact Study Report

Interconnection System Impact Study Report Request # GI

RATE DS-2 SMALL GENERAL DELIVERY SERVICE

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

Feasibility Study Report

Imperial Irrigation District Energy Consumers Advisory Committee Agenda Report

KAUAI ISLAND UTILITY COOPERATIVE KIUC Tariff No. 1 RULE NO. 17 NET ENERGY METERING

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

GENERATOR INTERCONNECTION FACILITIES STUDY FOR DAN RIVER STEAM PLANT COMBINED CYCLE PROJECT With BIOMASS CONVERSION IN PLACE ROCKINGHAM COUNTY, NC

FACILITIES STUDY TRANSMISSION SERVICE REQUEST OASIS

PEAK LOAD CAPACITY AGREEMENT XXXX/2017. Customer Oy. and. Finextra Oy

Southern California Edison Original Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Cal. PUC Sheet No.

NORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service. Effective: For bills rendered on and after February 1, 2019.

FACILITIES STUDY TRANSMISSION SERVICE REQUESTS OASIS

Sub Regional RTEP Committee - Southern. August 19, 2011

Public Access Electric Vehicle Charging Station Rebate Program Agreement

INDUSTRIAL HAUL AGREEMENT

ROLLOVER RIGHTS OF LONG TERM FIRM TRANSMISSION SERVICE

White River Electric Association, Inc. Net Metering Information & Service Requirements

TERMS AND CONDITIONS

Considerations for Municipal Solar Projects. Ben Frevert Larsen Engineers November 16, 2016

Q0044 interconnection at

Heber Light & Power Electric Service Rule No. 14 NET METERING SERVICE

Feasibility Study for the Q MW Solar Project

Feasibility Study Report

M.P.S.C. No. 2 Electric Ninth Revised Sheet No. 50 (Rate Case) Cancels Eighth Revised Sheet No. 50

RATE 765 RENEWABLE FEED-IN TARIFF

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

The Rollover Request customer accepts a reservation term for the rollover at least as long as that offered by any competing customer.

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

Northeastern Rural Electric Membership Corporation Columbia City, Indiana

INSTRUCTIONS FOR SECONDARY EMPLOYMENT APPROVAL APPLICATION FOR PRIVATE BUSINESSES AND PUBLIC AGENCIES AND FOR SPECIAL EVENTS

ATTACHMENT - DFO STATEMENT OF NEED

A. Basic Customer Charge: $ B. Energy Charge: $.09316/kWh

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

DFO STATEMENT OF NEED REPORT

City of Palo Alto (ID # 6416) City Council Staff Report

NORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service. Effective: For bills rendered on and after January 1, 2014.

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

1065 Woodman Drive Twelfth Revised Sheet No. T8 Dayton, Ohio Page 1 of 5

TEXARKANA, TEXAS SERVICE AREA. First Revised Sheet No /7

SCHEDULE 62 COGENERATION AND SMALL POWER PRODUCTION SCHEDULE - IDAHO

Too Good to Throw Away Implementation Strategy

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis

Delaware Electric Cooperative. Solar: What You Need to Know

Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

MICHIGAN ELECTRIC UTILITY

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Sub Regional RTEP Committee Western Region ATSI

Gateway South Transmission Project

EXTRA ORDINARY 16 AASHAADHA, 1937(S) BIHAR ELECTRICITY REGULATORY COMMISSION

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS

XXXXX. Kokish River Hydroelectric Project. Interconnection Facilities Study and Project Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan

Electric Rates. For Michigan customers

Table of Contents. Purpose. Eldorado Intertie and System (Eldorado- Moenkopi) Scheduling at Willow Beach. Operating Procedure

Contents. Solar Select TM Frequently Asked Questions

Northeastern Rural Electric Membership Corporation Schedule DG-2 Columbia City, Indiana Page 1 of 5

Interconnection and Net Metering Service in Ohio

ELECTRIC SERVICE RULES DISTRIBUTED GENERATION Issued Jan 2016

Consumer Guidelines for Electric Power Generator Installation and Interconnection

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis

Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study

EXHIBIT A ORDINANCE NO. O CITY OF LAURINBURG, NORTH CAROLINA SCHEDULES OPR RESIDENTIAL TIME-OF-USE SERVICE

FACILITIES STUDY TRANSMISSION SERVICE REQUESTS OASIS

Buy All Sell All Rider for Interconnection of Renewable Generation

Transcription:

Cleco Power LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST OASIS 71956063 0 Rev Issue Date Description of Revision

Table of Contents 1. Purpose...3 2. System Impact Study Conclusions...3 2.1 The Pineville to Sherwood 230kV Line 2.2 The Hunter to Pineville 138kV Line 3. Facility Study Results...3 3.1 The Pineville to Sherwood 230kV Line 3.2 The Hunter to Pineville 138kV Line 4. Cost...4 4.1 Network Upgrades...4 4.2 Direct Assignment Facilities...4 5. Other Contractual Arrangements...7 Page 6. Schedule...7 Issued on: June 20, 2008 2 of 7

1. Purpose The purpose of this is to estimate the cost and schedule to construct the facilities identified in the System Impact Study which are necessary to accommodate the request for 203 MW of Yearly Firm Network Integration Transmission Service ( NITS ) across Cleco Power s ( Cleco ) Transmission System. The time period for this transfer is from October 1, 2008 through October 1, 2020. This Facility Study is being issued to satisfy the Facility Study Agreement between Cleco Power LLC and Transmission Customer. Cleco will pursue, at the Transmission Customers request, a joint facility study with RW Beck to determine the best solution for service to the City of Alexandria ( City or Alexandria ) under NITS service. Cleco will continue to capture the cost of such a joint facility study pursuant to the current Facility Study Agreement that is in place. Cleco will also begin working on a Network Integration Transmission Service Agreement ( NITSA ) to send to the Transmission Customer. All terms capitalized herein are defined in the Cleco Power s Open Access Transmission Tariff. 2. System Impact Study Conclusions Based on the results of the System Impact Study dated April 2008, two limiting elements were identified. They are: 2.1 The Pineville to Sherwood 230kV Line In 2018, the 9 mile long bundled 336 ACSR 26/7 Linnett conductor overloads for the loss of the Rapides to Twin Bridges 230kV line or the Twin Bridges 230/138kV autotransformer. 2.2 The Hunter to Pineville 138kV Line In 2018, the one mile long 1272 ACSR 45/7 Bittern conductor overloads for the loss of the Rapides to Twin Bridges 230kV line or the Twin Bridges 230/138kV autotransformer. 3. Facility Study Results The following Network Upgrades are required solutions to the limiting elements: 3.1 The Pineville to Sherwood 230kV Line Replace the existing conductors with a single 1780 ACSR 84/19 Chukar conductor. The existing wooden H-frame structures are not capable of supporting the larger conductor. The structures must be replaced with steel H-frame structures. The 138kV circuit breaker and disconnect switch on the low side of the autotransformer at Pineville Substation must also be replaced. Issued on: June 20, 2008 3 of 7

3.2 The Hunter to Pineville 138kV Line Replace the existing conductor with a single 795 ACCR Hi-Temp Drake conductor. The existing structures have adequate strength to support the new conductor. The circuit breaker and two disconnect switches on the Pineville end of the line must also be replaced. The Hunter line terminal and 0.698 miles of the line on the Alexandria side of the river are not owned by Cleco. The Alexandria owned section of the line and possible upgrades to the Hunter line terminal equipment are not included in this, but an evaluation will be required between Cleco and the Transmission Customer to define any upgrades that may be needed. The evaluation of the Alexandria owned facilities will have to be completed, upgrades agreed to by Cleco and the Transmission Customer, and defined in the Service Agreement as a condition to grant service. 4. Cost 4.1 Network Upgrades For the purpose of this, and subsequently the NITSA, the Transmission Customer shall acknowledge and agree that the cost listed hereafter is only an estimate using Good Utility Practices. Cleco stipulates that the estimates quoted herein are as accurate as possible considering the information available. The Transmission Customer shall protect, indemnify and hold harmless Cleco from the cost consequences of any current tax liability imposed against Cleco as the result of payments made by the Transmission Customer to Cleco. Cleco s tax gross up rate is 61.52%, which will be applied if applicable. Estimated costs including overheads and interest for Network upgrades are: Pineville to Sherwood 230kV Line... $ 9,271,000 The Hunter to Pineville 138kV Line... $ 637,000 Subtotal $9,908,000 4.2 Direct Assignment Facilities Data Acquisition Equipment (see note 1) Remote terminal units (RTUs) are necessary to obtain information from the City facilities. All telephone equipment, leased telephone circuits, fiber optic circuits, and other communications equipment necessary to collect and transmit data to/from remote locations, and any other equipment or service necessary to provide for the telemetry requirements shall be paid for and owned by the Transmission Customer. One GE-Harris D20 RTU shall be installed at the City s Hunter Generating Plant. Transmission Customer to provide 19 rack for mounting RTU with access to both front and rear of rack in climate controlled room. RTU CPU at Twin Bridges substation shall be replaced with D20ME processor module for DNP communication to meters. A 4-wire data circuit will be required to communicate with the RTU at Hunter Generating Plant to Cleco. Dial-up connections will be required to all six Maxsys 2510 meters at Hunter Generation Plant. Dial-up connections will be required to the two Maxsys 2510 meters at Twin Bridges Substation. Dial-up connections will be required to the two Maxsys 2510 meters at Pineville Substation. Also need two wire RS-485 shielded data link between RTU and all Maxsys 2510 meters at all locations where the meters will be installed. Issued on: June 20, 2008 4 of 7

Metering Equipment (see note 1) Metering Equipment consists of high accuracy (0.2% accuracy or better) solid state four quadrant meters, metering cabinets, metering panels, conduits, cabling, metering accuracy (ANSI 0.3% accuracy class or better) current transformers, and metering accuracy (ANSI 0.3% accuracy class or better) potential transformers which, directly or indirectly, provide input to meters or transducers, meter recording devices (e.g., solid state data receivers), telephone circuits, signal or pulse dividers, transducers, pulse accumulators, and any other equipment necessary to implement the provisions of the Network Operating Agreement ( NOA ). All the Metering Equipment installed by Transmission Customer in accordance with the NOA shall conform to the Cleco's standards for similar installations as detailed below: Items currently in place that meet or exceed requirements Metering CT s on Generator #3 at Hunter Generating Plant Metering CT s on Generator #4 at Hunter Generating Plant Metering CT s at Twin Bridges to Rapides tie point Metering PT s at Twin Bridges to Rapides tie point Metering CT s at Pineville to Hunter tie point Metering PT s at Pineville to Hunter tie point Items that need to be replaced or added to meet requirements Units 3&4 generator meters at Hunter to be replaced with Maxsys 2510 meters with firmware version 5759, DNP card, and internal modem. Units 3&4 MAT meters at Hunter to be replaced with Maxsys 2510 meters with firmware version 5759, DNP card, and internal modem. Tie transformers #1&2 meters at Hunter to be replaced with Maxsys 2510 meters with firmware version 5759, DNP card, and internal modem. Tie point meters (4) at Twin Bridges sub. and Pineville sub. to be replaced with Maxsys 2510 meters with firmware version 5759, DNP card, and internal modem. PT s on Units 3&4 at Hunter Generating Plant to be replaced with 0.3% accuracy class (14400/120 V) PT s on Units 3&4 MAT bus to be replaced with 0.3% accuracy class (4200/120 V). PT s on Tie transformers 1&2 buses to be replaced with 0.3% accuracy class (7200/120 V). CT s on Units 3&4 MAT bus to be replaced with 0.3% accuracy class. CT s on Tie transformers 1&2 bus to be replaced with 0.3% accuracy class. Note 1: This study includes only units 3 & 4 at D.G. Hunter generating facility, since these are the only units defined in the NITS Application. If in the future, D. G Hunter Units 1 & 2 were designated as network resources, all metering associated with units 1 & 2 would have to be updated accordingly before bringing units on-line. Issued on: June 20, 2008 5 of 7

Estimated costs including overheads and interest for Direct Assignment Facilities are as follows: It is the Transmission Customer s responsibility to pay for all equipment at the City s facilities and any facilities on the Cleco system that is for the sole use of the Transmission Customer. It is also the Transmission Customer s responsibility to install all required equipment at the City s facilities. Cleco has provided the estimated cost information below. Cleco does not have estimates for all of the equipment because detailed drawings and specifications on some of the City s equipment were not available to Cleco in time to incorporate into this report. Once the detailed information is received from the City, Cleco will get an estimate from the manufacturer. Item Cost Unit 3 Generator 2510 Meter $5000 Unit 4 Generator 2510 Meter $5000 Unit 3 MAT 2510 Meter $5000 Unit 4 MAT 2510 Meter $5000 Tie XFM #1 2510 Meter $5000 Tie XFM #2 2510 Meter $5000 Tie Point 2510 Meters @ Twin Bridges $10000 Sub (2) Tie Point 2510 Meters @ Pineville Sub (2) $10000 Unit 3 14.4kV Metering Accuracy PT s Unit 4 14.4kV Metering Accuracy PT s Unit 3 4.2kV Metering Accuracy PT s (2) Unit 4 4.2kV Metering Accuracy PT s (2) Tie XFM 1 7.2kV Metering Accuracy PT s Tie XFM 2 7.2kV Metering Accuracy PT s Unit 3 MAT bus Metering Accuracy CT s Unit 4 MAT bus Metering Accuracy CT s Tie XFM 1 bus Metering Accuracy CT s Tie XFM 2 bus Metering Accuracy CT s Twin Bridges Sub RTU D20ME Processor $4000 Board D.G. Hunter Plant RTU $15000* Dial-Up Connectivity to Each 2510 Meter Location NOTE: All price estimates include material and installation. Issued on: June 20, 2008 6 of 7 $200 connection fee + $60/month per location

*Price estimate includes $5000 communication data circuit between RTU and Cleco. This price will vary depending on mode of communication. Price range for communication only could range between $5000 and $25000. See the drawing (E-1) (sent separately) showing the metering and data acquisition equipment to be replaced or added. 5. Other Contractual Arrangements Prior to execution of the NITSA, the Transmission Customer and Cleco shall enter into goodfaith negotiations for the establishment of necessary contract terms within the NOA that clearly allocate responsibilities regarding compliance with reliability related criteria and any charges that may be appropriate for integration of Transmission Customer into the Cleco Balancing Authority Area. 6. Schedule A detailed schedule will be prepared subsequent to the Transmission Customer approval. The following are approximate durations: Pineville to Sherwood 230kV Line... 2 years The Hunter to Pineville 138kV Line... 1 year Notes to Duration Schedules: All construction work requiring outages will be performed during off-peak load seasons. Line outages will be requested from Cleco s Coughlin Transmission Operations Center (CTOC) and they will coordinate the request with other regional transmission operations centers. The assumption is being made that line outages will be executed as planned. However, denial of outages by CTOC along with resulting schedule delay is possible. Schedule durations are high level estimates at this time. Upon project approval, a detailed schedule will be produced. Issued on: June 20, 2008 7 of 7