FORTISBC INC. PRUDENCY REVIEW KETTLE VALLEY SUBSTATION EXHIBIT A2 5

Similar documents
FORTISBC INC. RATE DESIGN & RATES FOR ELECTRIC VEHICLE DIRECT CURRENT FAST CHARGING SERVICE EXHIBIT A-2

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

Attention: Mr. Patrick Wruck, Commission Secretary and Manager, Regulatory Support

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

FortisBC Inc. (FBC) Application for Amendment to Electric Tariff Rate Schedule 50 Lighting All Areas

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

Direct Energy Regulated Services

Diane Roy Vice President, Regulatory Affairs

Patrick Wruck Commission Secretary

SUBJECT: CONTRACT C080S, HOIST REPLACEMENT AT BUS MAINTENANCE DIVISIONS 3, 5, 9, 10, AND 18, PETERSON HYDRAULICS AND ROTARY LIFT, A JOINT VENTURE

BC HYDRO SUPPLY CHAIN APPLICATIONS PROJECT EXHIBIT A-8

Western Alberta Transmission Line (WATL) HVDC Project

s m BC hydro REGENERATION December 22, 2011

P.O BOX 429, NUKU ALOFA, Tel: (676) Fax: (676)

Electric Vehicle Program

Engineers Ireland Site Visit 23 rd March 2010

Fund and 2015 revenue bonds Est. State and Local Taxes: $2,810,000

QUARTERLY REVIEW OF BUSINESS CONDITIONS: MOTOR VEHICLE MANUFACTURING INDUSTRY / AUTOMOTIVE SECTOR: 4 TH QUARTER 2016

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

Contract Awards December 22, Composite Report

M A N I T O B A ) Order No. 42/14 ) THE PUBLIC UTILITIES BOARD ACT ) April 23, 2014

SPP Notification to Construct with Conditions

Metropolitan Domestic Water Improvement District Board of Directors Meeting. August 8, July 2011 Report

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

SPP Notification to Construct

Too Good to Throw Away Implementation Strategy

The Director, Purchasing and Materials Management recommends that:

TORONTO TRANSIT COMMISSION REPORT NO.

CITY OF VANCOUVER ADMINISTRATIVE REPORT

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

STAFF REPORT ACTION REQUIRED

Modernising the Great Western railway

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

Public Works and Infrastructure Committee. Director, Purchasing and Materials Management General Manager, Transportation Services

October 17, Please contact the undersigned directly with any questions or concerns regarding the foregoing.

STAFF REPORT ACTION REQUIRED

Attention: Ms. Laurel Ross, Acting Commission Secretary and Director

August 15, Please contact the undersigned directly with any questions or concerns regarding the foregoing.

FOR IMMEDIATE RELEASE

QUARTERLY REVIEW OF BUSINESS CONDITIONS: NEW MOTOR VEHICLE MANUFACTURING INDUSTRY / AUTOMOTIVE SECTOR: 2 nd QUARTER 2018

STAFF REPORT ACTION REQUIRED

Appendix D Black Hills Project Summary

TORONTO TRANSIT COMMISSION REPORT NO.

QUARTERLY REVIEW OF BUSINESS CONDITIONS: NEW MOTOR VEHICLE MANUFACTURING INDUSTRY / AUTOMOTIVE SECTOR: 2 ND QUARTER 2017

City of Palo Alto (ID # 6416) City Council Staff Report

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

Insulator Replacements

System Status Briefing

SPP Notification to Construct

FOR IMMEDIATE RELEASE

BEFORE THE NEW JERSEY BOARD OF PUBLIC UTILITIES

SUBJECT: Russell Hill Subway Train Accident Of August 11, 1995 Due Diligence Checklist Update

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

congestion management program

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution

TOTAL PROPOSED CONTRACT PRICE Ring Power Corporation $4,875,951

GAZIFÈRE INC. Prime Rate Forecasting Process 2017 Rate Case

Glendale Water & Power Smart Grid Project

FOR IMMEDIATE RELEASE

BC Hydro writes in compliance with Exhibit A-4 to provide its Final Submission in respect of the Application (Exhibit B-1).

National Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA )

Comprehensive project bid to grant in concession GTS Project 220 Kv Tintaya - Azangaro Transmission Line. GTS: Guaranteed Transmission System

Quarterly Hogs and Pigs

Peninsula Corridor Electrification Project (PCEP)

SPP Notification to Construct with Conditions

Quarterly Hogs and Pigs

Electricity Industry Code Minimum Service Standards & Guaranteed Service Levels Quarterly Report July September 2008

The cost estimation methodology used to update the charges and credits is the same methodology the Company utilized in the prior year s filing.

Re: Kettle Valley CPCN Application - Project #

SPP Notification to Construct

RE: Advice Schedule 45 Public DC Fast Charger Delivery Service Optional Transitional Rate REPLACEMENT PAGES

Re: YEC & YECL Rider F Fuel Adjustment Rider & Deferred Fuel Price Variance Policy

February 26, Ms. Laurel Ross Acting Commission Secretary British Columbia Utilities Commission Sixth Floor 900 Howe Street Vancouver, BC V6Z 2N3

Quarterly Hogs and Pigs

FOR IMMEDIATE RELEASE

MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Recommend to Board. Final Action

Monthly Hog Market Update United States Hog Production

Director of Finance & Administrative Services

Transit Project Delivery Status Report. Significant Issues

congestion management program

March 14, Please contact the undersigned directly with any questions or concerns regarding the foregoing.

SPP Notification to Construct

For further information, please contact Geoff Higgins at or by at

Decision D Finlay Group. Complaint Regarding FortisAlberta Inc. Distribution Line Rebuild Project. February 3, 2016

APPROVE CONTRACT MODIFICATION AWARD

Salalah Liquefied Petroleum Gas (SLPG) - Salalah LPG Extraction. Salalah Liquefied Petroleum Gas (SLPG) CB&I - Chicago Bridge & Iron Company

1SPP Notification to Construct. RE: Notification to Construct Approved Reliability Network Upgrades

Temporary Adjustments to Rates for Low-Income Programs.

Docket No EI Date: May 22, 2014

Horseshoe Bay Terminal Open House

FORTISBC INC. NET METERING PROGRAM TARIFF UPDATE EXHIBIT A 4

QUARTERLY REVIEW OF BUSINESS CONDITIONS: NEW MOTOR VEHICLE MANUFACTURING INDUSTRY / AUTOMOTIVE SECTOR: 4 TH QUARTER 2017

CPG is pleased to report the following accomplishments this quarter:

Decision Blaze Energy Ltd. Application for an Exemption under Section 24 of the Hydro and Electric Energy Act.

M onthly arket. Jan Table of Contents. Monthly Highlights

MILLIGAN SOLAR PROJECT

100 MW Wind Generation Project

April 6, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

NATIONAL ASSOCIATION OF AUTOMOBILE MANUFACTURERS OF SOUTH AFRICA

REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT COMPRESSED NATURAL GAS TRANSIT FLEET UPDATE

Transcription:

ALANNA GILLIS ACTING COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, BC CANADA V6Z 2N3 TELEPHONE: (604) 660 4700 BC TOLL FREE: 1 800 663 1385 FACSIMILE: (604) 660 1102 Log No. 33543 VIA EMAIL electricity.regulatory.affairs@fortisbc.com January 4, 2012 Mr. Dennis Swanson Director, Regulatory Affairs Regulatory Affairs Department FortisBC Inc. Suite 100, 1975 Springfield Road Kelowna, BC V17 7V7 FORTISBC INC. PRUDENCY REVIEW KETTLE VALLEY SUBSTATION EXHIBIT A2 5 Dear Mr. Swanson: Re: FortisBC Inc. Expenditure Review regarding the Kettle Valley Distribution Source Project Commission staff submits the following document for the record in this proceeding: FortisBC Progress Report No. 6 to September 30, 2008 for the Kettle Valley Distribution Source Project. elm Enclosure cc: Registered Interveners 2012 13RR (FBC 2012 13RR RI) Registered Interveners Kettle Valley Project (Fortis KettleValley RI) Yours truly, Alanna Gillis PF/FBC Kettle Valley Prudency Review/A2 5_Progress Report No. 6

Joyce Martin Manager, Regulatory Affairs FortisBC Inc. 1290 Esplanade PO Box 130 Trail, BC V1R 4L4 Tel 250 368 0319 Fax 866 605 9431 Joyce.Martin@fortisbc.com www.fortisbc.com October 31, 2008 Via Email Ms. Erica Hamilton Commission Secretary BC Utilities Commission Sixth Floor, 900 Howe Street, Box 250 Vancouver, BC V6Z 2N3 Dear Ms. Hamilton: Re: FortisBC Inc. ( FortisBC ) Kettle Valley Distribution Source Project Pursuant to Commission Order C-5-06, please find attached FortisBC s Progress Report No. 6 to September 30, 2008 for the Kettle Valley Distribution Source Project. Yours truly, Joyce Martin Manager, Regulatory Affairs Enclosed

FortisBC Inc. Kettle Valley Distribution Source Project Order C-5-06 Project Status Report No. 6 to September 30, 2008 1. Project Status: This report is the sixth quarterly report to be completed on the Kettle Valley Distribution Source Project ( Kettle Valley Project ), approved by Commission Order C-5-06 on August 9, 2006 1.1 General Project Status: Construction at the Kettle Valley Substation is complete; the apparatus and protection commissioning was completed in the first quarter of 2008. The substation transformers were energized on April 9, 2008. Construction on the main double circuit line between the Ingram Bridge and Midway is complete. The main line to Midway and the Midway step-down station are complete and energized. Engineering on the Greenwood step-down station is complete. Engineering on the main line from Midway to Greenwood is being adjusted due to routing issues. In December 2007, crews completed the installation of the communications cable between Oliver and Grand Forks. The new multiplexers at the Oliver and Grand Forks Terminal stations and the Kettle Valley Substation are in service and transporting network and telephony signals. Total Project Cost is forecast to be $28.44 million. 1.2 Project Accomplishments and Challenges: Distribution Source: The station construction schedule is complete. The substation transformers were energized on April 9, 2008. Voltage Conversion: Line stringing in the section from Ingram Bridge to Midway is complete. The Midway step-down station is complete and was energized September 9, 2008. Construction on Kettle Valley South Road is complete. FortisBC crews completed customer extensions on the Kettle Valley East Road enabling the line to be energized from the new distribution source. The conversion of main line customer taps up to Midway is proceeding with FortisBC crews and is scheduled for completion in November 2008. Kettle Valley Progress Report No. 6 Page 1

Engineering for the Greenwood step-down station is complete and construction is proceeding and scheduled to be complete late fourth quarter of 2008. Detailed engineering for the line construction (Phase 3) between Midway and Greenwood identified permitting and land issues. Routing of this portion is being adjusted to deal with these issues. This portion is now scheduled to have engineering completed and ready for construction within the first quarter of 2009 with construction to start shortly after. Construction is scheduled to be completed in the second quarter of 2009. A salvage plan has been established for the removal of 9 Line and 10 Line. High Capacity Communication Upgrade: The environmental deficiencies that were identified by KRM and Associates have been corrected. There are three instances on 11 Line where the new communications cable resides above the existing marker balls on a marked crossing. A solution is under review with regard to scope and costing. 1.3 Activities for Next Quarter: Project activities scheduled to the end of December 2008 include: Distribution Source: Energizing the distribution circuits as the work is completed. Load will be transferred to the station as the sections of the voltage conversions circuits are brought online. Continuation of project close out phase. Voltage Conversion: Complete the conversion of main line customer services by late November 2008. Engineer an alternative solution to supply Greenwood step-down station with 25 kv by the first quarter 2009. Continue construction of Greenwood step-down station. Develop a tender package for the salvage work. High Capacity Communication Upgrade: Transport Canada marker ball relocation. Project close out. 2. Project Cost: The current financial forecast to complete the project is $28.44 million. The variance is mainly driven by world-wide material markets (metal commodities) and Western Canada labour pressures on trades and engineers. Comprehensive explanations were provided in FortisBC s letter to the Commission dated August 22, 2008. A summary of project costs to September 30, 2008 is shown below. FortisBC continues to actively manage the project in an effort to reduce costs. Kettle Valley Progress Report No. 6 Page 2

FortisBC Kettle Valley Substation Project BCUC Order No. C-5-06 Report No. 6 BCUC Actuals to Budget Sep 30/08 EAC Variance WBS $ millions $ millions $ millions % Comments / Explanation KV SUBSTATION 2005 Dollars +/- 10% LINE WORK 0.19 0.37 0.37 96.91% CIVIL & SITE & BUILDINGS 1.4 1.50 1.50 7.47% STATION EQUIPMENT & APPARATUS & STRUCTURES & BUS WORK 4.51 5.89 5.89 30.70% STATION COMMUNICATION & SCADA EQUIPMENT 0.18 0.25 0.25 40.62% PROTECTION & CONTROL AND METERING 0.47 0.54 0.54 14.76% ENGINEERING 1.13 1.96 1.96 73.69% COMMISSIONING 0.25 0.28 0.28 12.99% PROJECT MANAGEMENT & SUPERVISION 0.61 0.70 0.70 14.47% OVERALL KETTLE VALLEY SUBSTATION DEVELOPMENT COST 8.74 11.51 11.51 31.68% Unforeseen additonal grounding requirements coupled with commodity market increases. Variance due to cost increase on transformers. Commodity market increases and unforeseen equipment requirements. Market pressures on fees for professional engineering consultants and startup delays. Equipment commissioning contract competively tendered and awarded to the lowest bidder. KV DISTRIBUTION UPGRADE 2005 dollars +/- 25% MATERIALS 3.46 4.19 4.07 17.62% CONSTRUCTION 3.62 4.03 4.92 35.84% OTHER CONTRACT (Telus) 0.49 0.28 0.35-29.34% LAND / ROW 0.13 0.17 0.18 38.86% ENGINEERING 0.4 0.80 0.81 101.68% PROJECT MANAGEMENT & SUPERVISION 0.46 0.43 0.46-0.63% OVERALL KETTLE VALLEY DISTRIBUTION UPGRADE COST 8.56 9.91 10.78 25.90% Commodity market increases. Forecast to receive material credits to project. Variance due to increased rubber glove work required to minimize outages in addition to labour market increases. Variance due to market pressures. EAC costs are consistent with overall Distribution Upgrade costs. Project Management costs are consistent with overall Distribution Upgrade costs. KV HIGH CAPACITY COMMUNICATIONS 2005 dollars +/- 25% MATERIALS 0.89 1.02 1.02 15.10% $0.4 million savings on fibre offset by market increases. CONSTRUCTION 1.5 2.11 2.12 41.05% Variance due to Western Canada labour pressures. Work competitively bid and awarded to the lowest bidder. ENGINEERING 0.2 0.87 0.87 337.27% Design package produced as part of earlier project could not be used as expected. Reengineering required. PROJECT MANAGEMENT & SUPERVISION 0.07 0.16 0.16 129.00% OVERALL KETTLE VALLEY HIGH CAPACITY COMMUNICATION COST 2.66 4.17 4.17 56.95% Line and Substation Salvage 1.26 0.70 1.76 39.30% Substation Land / ROW / Easement Issues 0.26 0.22 0.22-13.65% Total 21.48 26.52 28.44 32.41% Project Management costs are consistent with overall High Capacity Communication cost. Kettle Valley Progress Report No. 6 Page 3

2.1 Project S Curve: Thousands 30,000 25,000 20,000 15,000 10,000 5,000 0 May-05 Jul-05 Cumulative Monthly Costs Sep-05 Nov-05 Jan-06 Mar-06 May-06 Jul-06 Sep-06 Nov-06 Jan-07 Mar-07 May-07 Jul-07 Sep-07 Nov-07 Jan-08 Mar-08 May-08 Jul-08 Sep-08 Nov-08 Jan-09 Mar-09 May-09 Jul-09 Sep-09 Kettle Valley Progress Report No. 6 Page 4 Actual Forecast 3. Project Schedule: The Gantt chart below provides a status of milestones and activities as of September 30, 2008. Highlights of the schedule are: Engineering: Engineering is nearing completion on this project. The distribution station and communications upgrade are in the project closeout stage. Major milestones remaining for engineering include construction support for the Midway taps, the distribution line to Greenwood and the step-down station in Greenwood. Major Procurement: All major procurement is complete. Budget Construction: Construction is complete at the distribution source. Efforts have shifted to the conversion of main line taps as well as the Greenwood step-down station. Construction of the revised feed to Greenwood from Midway is scheduled to proceed in the first quarter of 2009. In Service: The in-service milestones are expected to remain consistent with the schedule based on the April 2008 energization of the distribution source. Salvage: Planning for the line and station salvage work has begun with the work to be completed over the next 12 months.

Kettle Valley Progress Report No. 6 Page 5

Scope Control: With the intent to mitigate cost variances as well as various land issues, the third phase of distribution line construction (Midway to Greenwood) has been adjusted. Land issues have forced FortisBC to build on the existing 9/10 Line right-of-way, therefore, the decision was made to utilize 9 Line as a distribution feed to Greenwood. Estimates for the salvage are higher than was originally budgeted. FortisBC is in the process of reviewing various options to mitigate the increase. 4. Project Risks: Distribution Source: No further risks Voltage Conversion: Right-of-way issues have created issues with the Midway to Greenwood (Phase 3) main line route. This portion is now being modified to utilize the existing 9 Line to supply Greenwood. As no engineering has been completed for this solution, potential rebuilds and upgrades to 9 Line may exist. Copper credits for the salvage of 9 Line and 10 Lines have been ascertained at August values and used in the salvage estimates. As commodity pricing changes, the net cost to complete the salvage will be affected. A salvage plan is attached at Appendix A, in confidence. High Capacity Upgrade: The application for aeronautical clearance from Transport Canada s requirement for maker balls on wires is a cost risk for the project. The scope and cost of this work is not fully defined. Kettle Valley Progress Report No. 6 Page 6