Facilities Study for Alberta to US Available Transfer Capability

Similar documents
BC Hydro System 2017 Annual Progress Report

BC Hydro System 2011 Annual Progress Report

BC HYDRO REAL TIME OPERATIONS OPERATIONS SUPPORT SYSTEM OPERATING ORDER 7T-13

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Dynamic Scheduling NI A F S NI S. Where:

Supplemental Report on the NCTPC Collaborative Transmission Plan

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Feasibility Study Report

100 MW Wind Generation Project

New 115 kv Disconnect Switches at Bloomsburg MTS

Use of High-Power Thyristor Technology for Short-Circuit Current Limitation in High Voltage Systems

15 Nelson-Marlborough Regional Plan

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Feasibility Study Report

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

ATTACHMENT - DFO STATEMENT OF NEED

Connection Engineering Study Report for AUC Application: AESO Project # 1674

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

SSF Section Location of Change SSF Issue Change(s) Comments Chapter Part B All Multiple Formatting, spelling and minor Changes applied -

TransWest Express Project

Illinois State Report

Interconnection Feasibility Study Report GIP-226-FEAS-R3

BC Hydro System 2016 Annual Progress Report

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

Interconnection Feasibility Study Report GIP-222-FEAS-R3

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection System Impact Study Report Request # GI

British Columbia Transmission Corporatlon ("BCTC") Transmission System Capital Plan F2006 to F2015 Amllcation

APPENDIX E: Project Need and Description

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

15 Nelson-Marlborough Regional Plan

Gateway South Transmission Project

Sub Regional RTEP Committee Mid-Atlantic

APPENDIX E: Project Need and Description

Transmission Expansion Advisory Committee

DFO STATEMENT OF NEED REPORT

Feasibility Study Report

MILLIGAN SOLAR PROJECT

BC HYDRO T&D SYSTEM OPERATIONS SYSTEM OPERATING ORDER 7T 30. NORTH COAST INTERCONNECTION Supersedes 7T-30 issued 07 June 2018

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

Project #94. Generation Interconnection System Impact Study Report Revision

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Project #148. Generation Interconnection System Impact Study Report

BC HYDRO T&D SYSTEM OPERATIONS SYSTEM OPERATING ORDER 7T-41. VANCOUVER ISLAND SYSTEM OPERATION Supersedes SOO 7T-41 dated 28 August 2018

CUSTOMER/ TWIN ARROWS PROJECT

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project.

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection System Impact Study

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Stability Study for the Mt. Olive Hartburg 500 kv Line

APPENDIX F: Project Need and Description

BC Hydro OATT - Balancing Area Transmission Service Workshop. January 20, 2014

Falcon-Midway 115 kv Line Uprate Project Report

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Manual 3: Transmission Operations Updates Version 52

Interconnection Feasibility Study

Interconnection Feasibility Study Report GIP-369-FEAS-R1

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

Consulting Agreement Study. Completed for Transmission Customer

ATTACHMENT Y STUDY REPORT

Q0044 interconnection at

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

XXXX. Skookum Creek Power Project. Interconnection System Impact Study

Interconnection Feasibility Study Report GIP-046-FEAS-R2

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

XXXX. Kokish River Hydroelectric Project. Interconnection System Impact Study

System Impact Study Report

BC HYDRO REAL TIME OPERATIONS SYSTEM OPERATING ORDER 7T-35. PEACE 138/230 kv NETWORK OPERATION Supersedes 7T-35 issued 15 June 2017

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006

Refurbishment and Life Extension of Existing Facilities in Vermont

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study

Final System Impact Study for. Sierra Pacific Industries 31 MW Generation Project. Mount Vernon, WA. November 16, 2006

Status of PNM s Completed Transmission Construction Projects 11/30/2017

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

CI Number: ACE CI Page 1 of 9. Title: Metro Voltage Support - Add Capacitor Bank

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Pacific Gas and Electric Company s Revised 2016 Annual Progress

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016

The Long-Range Transmission Plan

Benefits of Reducing Electric System Losses

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Appendix D Black Hills Project Summary

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR)

Transcription:

Facilities Study for Alberta to US Available Transfer Capability Report No: NPP2002-05 June 3, 2002 System Planning & Grid Operations, Transmission Line of Business Engineering Services

Executive Summary The following OASIS requests were submitted to BC Hydro Transmission Line of Business (TLoB) for Long Term Firm Point-to-Point transmission service under the Wholesale Transmission Service (WTS) tariff on the EAL BPAT Path: No. 293825 TransCanada Power for 25 MW (Jan 2001 Dec 2005) No. 299499 Duke Energy for 100 MW (Jan 2001 Dec 2005) No. 343349 BC Hydro Power Supply for 250 MW (Apr 2001 Mar 2006) No. 344670 TransCanada Power for 50 MW (Jan 2002 Dec 2006.) Further to the 28 February 2001 System Impact Study for Increased Interior to Lower Mainland Transfer (without new transmission line) report (http://gridops.bchydro.bc.ca/transmission_system/studies/ilm_sis.pdf), this Facilities Study identifies Network Upgrades that would provide Available Transfer Capability (ATC) on the EAL BPAT Path through the Interior to Lower Mainland transmission system. This Facilities Study identifies the required modifications to TLoB s Transmission System, including a good faith estimate of the cost and scheduled completion date for such modifications to provide increments up to the total 425 MW of the transmission service requests. The Study concluded that 425 MW of ATC is available on the EAL BPAT Path. The following are Network Upgrades required to provide incremental ATC above existing commitments: ATC Incremental Reinforcements 0 MW No reinforcements > 0 MW 170 MW Series capacitor bank on 5L82 upgraded for 3.3 ka operation Series capacitor bank on 5L41 & 5L42 upgraded for 3 ka operation Summer ratings of 5L42 upgraded to 3 ka Summer rating of 2L1 to 0.98 ka Replace 5L44 2.0 ka circuit breakers (5CB11 at Ingledow Station) with 3.0 ka circuit breakers Addition of 1 250 MVAR and 1 250 MVAR mechanically switched shunt capacitors at Ingledow 500 kv Station and Meridian 500 kv Station Facilities Study for Alberta to US ATC 2

ATC > 170 MW 220 MW > 220 MW 290 MW > 290 MW 390 MW > 390 MW at least 425 MW Incremental Reinforcements Series capacitor bank on 5L81 upgraded for 3.3 ka operation Summer ratings of 5L44 upgraded to 3 ka Summer ratings of 2L90 & 2L91 to 0.7 ka Replace 5L40 2.0 ka circuit breakers (5CB7 & 5CB8 at Ingledow Station) with 3.0 ka circuit breakers Addition of 1 250 MVAR mechanically switched shunt capacitor at Nicola 500 kv Station Series capacitor bank on 5L87 upgraded for 3 ka operation Addition of 1 250 MVAR mechanically switched shunt capacitor at Meridian 500 kv Station Summer rating of 5L41 upgraded to 3 ka Replace 5L82 3.0 ka circuit breakers (5CB12 & 5CB22 at Nicola Station, and 5CB7 & 5CB8 at Meridian Station) with 4.0 ka circuit breakers Addition of 200 to +300 MVAR SVC at Ingledow 500 kv Station Addition of 1 250 MVAR and 1 250 MVAR mechanically switched shunt capacitors at Ingledow 500 kv Station and Meridian 500 kv Station Replace 5L81 3.0 ka circuit breakers (5CB18 & 5CB28 at Nicola Station, and 5CB9 & 5CB10 at Ingledow Station) with 4.0 ka circuit breakers Addition of 1 250 MVAR mechanically switched shunt capacitors at Ingledow 500 kv Station In addition, various Remedial Action Schemes are required for Undervoltage-Load- Shedding, Direct Load Shedding, Generation Shedding and Transfer Trip for multicontingency events. Alberta generation shedding must also be available for various multi-contingency events. As there are no interconnection requirements identified, there are no Direct Assignment Facilities included in this Facilities Study. The earliest possible in-service date of Network Upgrades is considered to be 31 December 2004. Appendix A contains the Network Upgrade facilities costs and schedules for providing the transmission service. Facilities Study for Alberta to US ATC 3

Table of Contents Executive Summary... 2 Table of Contents...4 1. Introduction...5 2. Terms of Reference... 5 3. System Study Results... 5 3.1. N-1 Capability... 5 3.2. N-1 during Maintenance Capability... 5 3.3. N-2 and N-2 during Maintenance Capability... 6 3.4. Available Transfer Capability... 6 4. Network Upgrade and Direct Assignment Facilities... 7 5. Project and Transmission Service Risks... 7 6. Conclusions... 8 Appendix A. Network Upgrade Facilities... A-1 A.1 Series Capacitor Stations...A-2 A.1.1 Chapmans Series Capacitor Station on 5L41...A-2 A.1.2 Creekside Series Capacitor Station on 5L42...A-2 A.1.3 American Creek I & II Series Capacitor Stations on 5L81 & 5L82...A-3 A.1.4 Guichon Series Capacitor Station on 5L87...A-3 A.2 Transmission Circuit Upgrades and Additions...A-4 A.2.1 Upgrade 5L40, 5L41, 5L42 and 5L44...A-4 A.2.2 Upgrade 5L81...A-4 A.2.3 Upgrade 5L82...A-4 A.2.4 Upgrade 2L1, 2L90 and 2L91...A-4 A.3 SVC and Shunt Capacitor Additions...A-5 A.3.1 Ingledow SVC...A-5 A.3.2 Ingledow, Meridian, and Nicola 500 kv Shunt Capacitor Banks...A-5 A.4 Remedial Action Scheme Additions and Upgrades...A-5 A.5 Costs and Schedules...A-6 Facilities Study for Alberta to US ATC 4

1. Introduction The 28 February 2002 System Impact Study for Increased Interior to Lower Mainland Transfer (without new transmission line) identified Network Upgrades that would provide approximately 1090 MW of additional ATC. This Facilities Study identifies the required modifications to TLoB s Transmission System, including a good faith estimate of the cost and scheduled completion date for such modifications to provide increments up to the total 425 MW of transmission service requests. 2. Terms of Reference The base conditions for the study are the BC Hydro native load requirements from 2004/05 to 2007/08 and prior firm export and transfer commitments. The Point-of- Receipt (POR) for the transmission service is the EAL BCHA Path, and the Point-of- Delivery (POD) is BCHA BPAT Path. 3. System Study Results Studies were performed as per TLoB s Transmission System Planning Criteria and Study Methodology. These studies were conducted to: Determine the ATC of the EAL BPAT Path. Assess the elements constraining the ATC. Determine Network Upgrades that would relieve the constraints. 3.1. N-1 Capability The Interior to Lower Mainland transmission network has 0 MW available N-1 transfer capability and is thermally limited by the first contingency single outages of 5L81 or 5L82. Upgrading AMC II on 5L82 and AMC I on 5L81 will avoid overloads. Reactive support in the form of shunt capacitors and static var compensators was then determined to match the thermal transfer capabilities. 3.2. N-1 during Maintenance Capability The Interior to Lower Mainland transmission network has 0 MW available N-1 transfer capability during maintenance and is thermally limited by the outages of 5L81 and 5L82, or of 5L81 and 5L41. Upgrading CRK on 5L42 and CHP on 5L41, and 5L44 will avoid overloads on the 500 kv system. At higher transfer levels, GUI on 5L87 will have to be upgraded for outages of 5L81 and 5L82. Corresponding circuit breaker replacements are also required. Facilities Study for Alberta to US ATC 5

Upgrades of 2L1, 2L90 & 2L91 will prevent overloads on the underlying voltage systems for a contingency with a 230 kv or 500 kv circuit out-of-service. A Transfer Trip of 2L27 to protect 2L22 and 2L27 from thermal overload is required for a contingency with 5L81, 5L41 or 5L44 out-of-service. In the South Interior, a Remedial Action Scheme is required for Alberta generation shedding for 2L293 contingency with 5L92 out-of-service. 3.3. N-2 and N-2 during Maintenance Capability For equitable service, Alberta generation shedding is required for double outages of 5L51 & 5L52, 5L81 & 5L82, or 5L91 & 5L98. Remedial Action Schemes are also required for Selkirk area and Alberta generation shedding for a 5L76 & 5L79 double contingency with 5L98 out-of-service. 3.4. Available Transfer Capability The following table provides the Contingencies and Incremental Reinforcements for the corresponding ATCs for both sequences: ATC Contingency Incremental Reinforcements 0 MW No reinforcements > 0 MW 170 MW 5L81ko/5L82ol 5L81mo/5L82ko/5L41ol 5L82mo/5L81ko/5L41ol 5L81mo/5L82ko/5L42ol 5L82mo/5L81ko/5L42ol 5L42mo/2L2ko/2L1ol 5L41mo/5L81ko/5L44ol 5L81mo/5L41ko/5L44ol 5L42ko or 5L82ko > 170 MW 220 MW > 220 MW 290 MW 5L82ko/5L81ol 5L41mo/5L81ko/5L44ol 5L81mo/5L41ko/5L44ol 5L42mo/2L90ko/2L91ol 5L42mo/2L91ko/2L92ol 5L81mo/5L82ko/5L40ol 5L82mo/5L81ko/5L40ol 5L42ko or 5L82ko 5L81mo/5L82ko/5L87ol 5L82mo/5L81ko/5L87ol 5L42ko or 5L82ko Series capacitor bank on 5L82 upgraded for 3 ka operation Series capacitor bank on 5L41 upgraded for 3 ka operation Series capacitor bank on 5L42 upgraded for 3 ka operation Summer rating of 5L42 upgraded to 3 ka Summer rating of 2L1 to 0.98 ka Replace 5L44 2.0 ka circuit breakers (5CB11 at Ingledow Station) with 3.0 ka circuit breakers Addition of 1 250 MVAR and 1 250 MVAR mechanically switched shunt capacitors at Ingledow 500 kv Station and Meridian 500 kv Station Series capacitor bank on 5L81 upgraded for 3 ka operation Summer ratings 5L44 upgraded to 3 ka Summer ratings of 2L90 & 2L91 upgraded to 0.7 ka Replace 5L40 2.0 ka circuit breakers (5CB7, 5CB8 at Ingledow Station) with 3.0 ka circuit breakers Addition of 1 250 MVAR mechanically switched shunt capacitor at Nicola 500 kv Station Series capacitor bank on 5L87 upgraded for 3 ka operation Addition of 1 250 MVAR mechanically switched shunt capacitor at Meridian 500 kv Station Facilities Study for Alberta to US ATC 6

ATC Contingency Incremental Reinforcements 5L81ko/5L82ol > 290 MW 390 MW > 390 MW at least 425 MW Notes: 5L81mo/5L82ko/5L41ol 5L82mo/5L81ko/5L41ol 5L42ko or 5L82ko 5L82ko/5L81ol 5L42ko or 5L82ko Series capacitor bank on 5L82 upgraded for 3.3 ka operation Replace 5L82 3.0 ka circuit breakers (5CB12 & 5CB22 at Nicola Station, and 5CB7 & 5CB8 at Meridian Station) with 4.0 ka circuit breakers Summer ratings of 5L41 upgraded to 3 ka Addition of 200 to +300 MVAR SVC at Ingledow 500 kv Station Addition of 1 250 MVAR and 1 250 MVAR mechanically switched shunt capacitors at Ingledow 500 kv Station and Meridian 500 kv Station Series capacitor bank on 5L81 upgraded for 3.3 ka operation Replace 5L81 3.0 ka circuit breakers (5CB 18 & 5CB28 at Nicola Station, and 5CB9 & 5CB10 at Ingledow Station) with 4.0 ka circuit breakers Addition of 1 250 MVAR mechanically switched shunt capacitors at Ingledow 500 kv Station For cost efficiency, Series capacitor banks on 5L81 and 5L82 will be upgraded for 3.3 ka operation when upgrade for 3 ka operation is required. Various Remedial Action Schemes are required for Undervoltage-Load-Shedding, Direct Load Shedding, Generation Shedding (including Alberta generators) and Transfer Trip for multi-contingency events. At 425 MW of transfer on the EAL BPAT Path and during system peak load, the BC Hydro system will have approximately 90 MW of additional losses. 4. Network Upgrade and Direct Assignment Facilities The required Network Upgrade facilities costs and schedules for providing transmission service are shown in Appendix A. As there are no interconnection requirements identified, there are no Direct Assignment Facilities included in this Facilities Study. 5. Project and Transmission Service Risks This Facilities Study contains some uncertainty in the plan, reinforcement, costs and in-service dates. Facilities Study for Alberta to US ATC 7

6. Conclusions The Study concluded that 425 MW of ATC is available on the EAL BPAT Path. The following are Network Upgrades required to provide the ATC: Series capacitor banks on 5L81 and 5L82 upgraded for 3.3 ka operation Series capacitor banks on 5L41, 5L42 and 5L87 upgraded for 3.0 ka operation Summer ratings of 5L41, 5L42 and 5L44 upgraded to 3.0 ka Summer ratings of 2L1, 2L90 and 2L91 upgraded up to 1 ka Addition of 200 to +300 MVAR SVC at Ingledow 500 kv Station Addition of 3 250 MVAR, 3 250 MVAR and 1 250 MVAR mechanically switched shunt capacitors at Ingledow 500 kv Station, Meridian 500 kv Station and Nicola 500 kv Station Replace 5L81 and 5L82 3.0 ka circuit breakers (5CB12, 5CB18, 5CB22 & 5CB28 at Nicola Station; 5CB9 & 5CB10 at Ingledow Station; and 5CB7 & 5CB8 at Meridian Station) with 4.0 ka circuit breakers Replace 5L40 and 5L44 2.0 ka circuit breakers (5CB7, 5CB8 & 5CB11 at Ingledow Station) with 3.0 ka circuit breakers salvaged from the item above Add/Upgrade/Modify various Remedial Action Schemes which are required for Undervoltage-Load-Shedding, Direct Load Shedding, Generation Shedding (including Alberta generators) and Transfer Trip for multi-contingency events. As there are no interconnection requirements identified, there are no Direct Assignment Facilities included in this Facilities Study. The earliest possible in-service date of Network Upgrades is considered to be 31 December 2004. Appendix A contains the Network Upgrade facilities costs and schedules for providing the transmission service. Facilities Study for Alberta to US ATC 8

Appendix A. Network Upgrade Facilities Facilities Study for Alberta to US ATC A-1

A.1 Series Capacitor Stations A.1.1 Chapmans Series Capacitor Station on 5L41 Upgrade Chapmans Series Capacitor Stations by reconnecting existing capacitors on one set of platforms and provide additional capacitors on separate platforms to increase the rating with no change to compensation level. The station characteristics are: Compensation 57% Series reactance 51.4 ohms Nameplate current rating 2730 A Continuous overload rating 3000 A (8 hrs in 12 hrs) Reactive Rating 1147 MVAR (550 & 600 MVAR per segment) Bank Configuration MOV gapless (approx 100 MJ per platform) Nom. operating voltage 500 kv Max. continuous voltage 550 kv Provide new protection and control for equipment on new platforms, and using existing protection and control on the existing platforms is acceptable. Provide transfer trip facilities for the new bypass breakers associated with the second platform, and breaker failure signals to Clayburn and Kelly Lake Stations. Reconfigure transfer trip facilities related to generation shedding associated with the new bypass CBs equivalent to what exists today. A.1.2 Creekside Series Capacitor Station on 5L42 Upgrade Creekside Series Capacitor Stations by reconnecting existing capacitors on one set of platforms and provide additional capacitors on separate platforms to increase the rating with no change to compensation level. The station characteristics are: Compensation 55% Series reactance 36.8 ohms Nameplate current rating 2730 A Continuous overload rating 3000 A (8 hrs in 12 hrs) Reactive Rating 803 MVAR (~520 & 280 MVAR per segment) Bank Configuration MOV gapless (~100 MJ per platform) Nom. operating voltage 500 kv Max. continuous voltage 550 kv Provide new protection and control for equipment on new platforms, and assume existing protection and control on the existing platforms is acceptable. Provide transfer trip facilities for the new bypass breakers associated with the second Facilities Study for Alberta to US ATC A-2

platform, and breaker failure signals to Cheekye and Kelly Lake Stations. Reconfigure transfer trip facilities related to generation shedding associated with the new bypass CBs equivalent to what exists today. Add local and remote Control and Indication for the new bypass CBs, and revise SCADA. Add local and remote Control and Indication for the new bypass CBs, and revise SCADA. A.1.3 American Creek I & II Series Capacitor Stations on 5L81 & 5L82 Upgrade American Creek I & II Series Capacitor Stations by installing a second set of platforms and distributing the capacitors equally between them. The characteristics of each station are: Compensation 47/49% Series reactance 40 ohms Nameplate current rating 3000 A Continuous overload rating 3300 A (8 hrs in 12 hrs) Reactive Rating 1080 MVAR (2 segments of 540 MVAR) Bank Configuration MOV gapless (approx 100 MJ per platform) Nom. operating voltage 500 kv Max. continuous voltage 550 kv Provide new protection and control for equipment on new platforms, and replace existing protection and control on the existing platforms. Provide transfer trip facilities for the new bypass breakers associated with the second platform, and breaker failure signals to Ingledow and Nicola Stations for AMC I and to Meridian and Nicola Stations for AMC II. Reconfigure transfer trip facilities related to generation shedding associated with the new bypass CBs equivalent to what exists today. Add local and remote Control and Indication for the new bypass CBs, and revise SCADA. A.1.4 Guichon Series Capacitor Station on 5L87 Upgrade Guichon Series Capacitor Stations from 2400 A nameplate to 2730 A. The initial 2400 A project is underway. Facilities Study for Alberta to US ATC A-3

A.2 Transmission Circuit Upgrades and Additions A.2.1 Upgrade 5L40, 5L41, 5L42 and 5L44 Upgrade the contingency summer rating of 5L41, 5L42 and 5L44 to 3.0 ka. The three lines can be upgraded by raising existing towers, adding new towers and where practical recountouring the right-of-way. Also, upgrade 5L40 CBs to 3 ka. 5L41: 12 months project duration & 1 week outage duration. 5L42: 8 months project duration & 1 weeks outage duration. 5L44: 10 months project duration & 1.5 weeks outage duration. Replace ING 5CB7 (5L40), 5CB8 (5L40) and 5CB11 (5L44) with 3 ka CBs. Replace 5L44 protection with new protection capable of single pole trip and reclose. A.2.2 Upgrade 5L81 Upgrade 5L81 line positions at ING and NIC to 4 ka continuous. Upgrade ING 5CB9 and 10 and associated equipment (between 5MB1 and 2) to 4 ka continuous. Upgrade NIC 5CB18 and 28 and associated equipment (between 5MB2 and 4) to 4 ka continuous. Revise 5L81 protection to suit. A.2.3 Upgrade 5L82 Upgrade 5L82 line positions at MDN and NIC to 4 ka continuous. Upgrade MDN 5CB7 and 8 and associated equipment (between 5MB1 and 2) to 4 ka continuous. Upgrade NIC 5CB12 and 22 and associated equipment (between 5MB1 and 3) to 4 ka continuous. Revise 5L82 protection to suit. A.2.4 Upgrade 2L1, 2L90 and 2L91 Upgrade the summer rating of 2L1 to 0.98 ka, and 2L90 & 2L91 to 0.7 ka. 2L1: upgrade the clearances at 12 locations; there may be difficulties in obtaining approval for upgrading the circuit. 2L90 and 2L91: initial assessments required although no major work is anticipated. Facilities Study for Alberta to US ATC A-4

A.3 SVC and Shunt Capacitor Additions A.3.1 Ingledow SVC Add SVC rated -200 to +300 MVARS connected to the Ingledow Station 500 kv bus. Protection of the SVC and associated transformer will be provided as part of the SVC itself. Provide local and remote control additions, from both SCC and relevant ACC, for new MODS and CBs for the SVC including control, indication, and alarms. At SCC revise SCADA/EMS power system models to include the new equipment. Also revise network application functions including DTS, VSA, TSA and RAS setup scheme. Revise RAS systems at the stations to add more initiating signals. At Mica and Revelstoke Generating Stations, provide redundant Generation Shedding Setup Panels. A.3.2 Ingledow, Meridian, and Nicola 500 kv Shunt Capacitor Banks These reinforcements replace the Ingledow and Ashton Creek shunt capacitors identified in the initial study. Add 500 kv, 250 MVAR switchable shunt capacitor banks at Ingledow (3), Meridian (3), and Nicola (1) Stations. Make 500 kv bus reconnections and add 500 kv main bus CVTs. Provide associated protection (including unbalance and breaker failure protection), control and telecom facilities. Provide local and remote control additions, from both SCC and relevant ACC, for new MODS and CBs for the shunt capacitor banks including control, indication, and alarms. One capacitor bank at Ingledow Station will be reserved for switching by the new SVC. One capacitor bank at Meridian Station will be reserved for switching by the Burrard Station SCs. At SCC revise SCADA/EMS power system models to include the new equipment. Also revise network application functions including DTS, VSA, TSA and RAS setup scheme. Revise RAS systems at the stations to add more initiating signals. A.4 Remedial Action Scheme Additions and Upgrades Upgrade/Modify Remedial Action Schemes (RAS) for Undervoltage-Load-Shedding, Direct Load Shedding for Interior to Lower Mainland N-2 events, and Transfer Trip of 2L27 to protect 2L22 and 2L27 from thermal overload. Add RAS for Alberta generation shedding for 2L293 contingency with 5L92 out-ofservice, and double outages of 5L51 & 5L52, 5L81 & 5L82, or 5L91 & 5L98. Add a RAS for Selkirk area and Alberta generation shedding for a 5L76 & 5L79 double contingency with 5L98 out-of-service. Facilities Study for Alberta to US ATC A-5

The RAS facilities for Alberta generation shedding will be provided as signal(s) to the BC-AB border. The Transmission Customer is responsible for procuring Alberta generators, equivalent to the amount of transmission service, for generation shedding. For double outages of 5L51 & 5L52, 5L81 & 5L82, or 5L91 & 5L98, BC generators may be substituted for Alberta generators. A.5 Costs and Schedules The $k costs below are Capital Direct with TLoB External Loadings and no IDC. The estimates have an accuracy of 15% & +30%. Where possible, TLoB will expedite the reinforcements for an earliest in-service date. Description Total 02/03 03/04 04/05 05/06 AMC (5L82) upgraded to 3.0 ka nominal 10617 550 1657 8411 CHP (5L41) upgraded to 2.73 ka nominal 8061 374 1264 6424 CRK (5L42) upgraded to 2.73 ka nominal 6405 415 1236 4754 5L42 upgraded to 3.0 ka Summer 1002 359 642 2L1 upgraded to 0.98 ka Summer 350 350 ING 1 x 3 ka CB (5L44) 1226 136 395 694 ING 1 x 250 MVAR 500 kv CX 3058 251 696 2111 MDN 1 x 250 MVAR 500 kv CX 2847 395 1282 1169 Add/Upgrade/Modify RAS 3000 1200 1800 Totals for 170 MW ATC 36565 4030 8972 23563 AMC (5L81) upgraded to 3.0 ka nominal 11216 664 1995 8558 5L44 upgraded to 3.0 ka Summer 1973 703 1269 2L90 upgraded to 0.7 ka Summer 246 121 126 2L91 upgraded to 0.7 ka Summer 197 97 100 ING 2 x 3 ka CB (5L40) 2452 272 791 1388 NIC 1 x 250 MVAR 500 kv CX 3083 208 692 2184 Totals for 220 MW ATC 55733 6094 13945 35693 GUI (5L87) upgraded to 2.73 ka nominal 1837 735 1102 MDN 1 x 250 MVAR 500 kv CX 2847 395 1282 1169 Totals for 290 MW ATC 60416 6094 14340 37710 2272 5L41 upgraded to 3.0 ka Summer 3106 1115 1991 MDN 2 x 4 ka CB (5L82) 3401 449 1474 1478 NIC 2 x 4 ka CB (5L82) 4133 183 619 3331 ING -200/+300 MVAR 500 kv SVC 29619 1051 3412 25155 ING 1 x 250 MVAR 500 kv CX 3058 251 696 2111 MDN 1 x 250 MVAR 500 kv CX 2847 395 1282 1169 Totals for 390 MW ATC 106580 6094 16669 46309 37507 ING 2 x 4 ka CB (5L81) 4406 481 1401 NIC 2 x 4 ka CB (5L81) 4133 183 619 ING 1 x 250 MVAR 500 kv CX 3058 251 696 Totals for 425 MW ATC 118177 6094 17584 49026 45472 Facilities Study for Alberta to US ATC A-6