The Upgrade of the Northern Terminal of the Pacific NW-SW HVdc Intertie Celilo Converter Station

Similar documents
2013 Grid of the Future Symposium

Refurbishment & Upgrade of the Celilo HVdc Converter Station

B4-114 CIGRE Celilo Pacific DC Intertie Upgrade presentation. K ERIKSSON*, O SAKSVIK, T HOLMGREN Bonneville Power Administration

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS

This page is intentionally left blank.

HVDC Systems in India

Refurbishment and Life Extension of Existing Facilities in Vermont

HVDC / FACTS Highlights

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

The Role of Offshore Wind

HVDC Transmission: Part of the Energy Solution? Peter Hartley Economics Department & James A. Baker III Institute for Public Policy, Rice University

street LIGHtING Display of Street Light Equipment at the Civic Auditorium Exhibition Hall, 1932

HVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector

Transmission Planning. WECC 2014 Progress Report. March 14, 2014

3 Existing National Grid

Longevity of Power Electronic Solutions in the Macro Grid historical perspective of AC (FACTS) and DC (HVDC) installations

A 500kV AIS Switchyard Rejuvenation in British Columbia using Hybrids

ABB POWER SYSTEMS CONSULTING

2013 ANNUAL PROGRESS REPORT

OBJECTIVES LCC HVDC SYSTEMS VSC HVDC SYSTEMS COMMON EQUIPMENT DIFFERENT OPTIONS ECONOMIC IMPACTS CONCLUSIONS

NorthernLights HVDC Project

Power Engineering - Egill Benedikt Hreinsson. Lecture 15a. HVDC Transmission. 2 November 2011

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden

HVDC Solutions. for Integration of the Renewable Energy Resources. Marcus Haeusler HVDC Lead Engineer. siemens.com/energy/power-transmission

High-performance power transmission siemens.com/hvdc

STREET LIGHTING ADOPTED CAPITAL IMPROVEMENT PROGRAM FISCAL YEAR

Gateway South Transmission Project

Load Modeling for Power System Studies

Dynamic Control of Grid Assets

ABB Roger Rosenqvist: August 30, 2012

HVDC. TMT&D provides the best and most economical HVDC system.

Western Alberta Transmission Line (WATL) HVDC Project

Benefits of HVDC and FACTS Devices Applied in Power Systems

The Application of Power Electronics to the Alberta Grid

INFRASTRUCTURE RENEWAL FOR THE NEXT GENERATION PATCO High Speed Line Power Infrastructure Renewal

Chapter 1. Overview of HVDC applications

The Green Line Project

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

15 Nelson-Marlborough Regional Plan

TransWest Express AC and DC Project Comprehensive Progress Report (CPR) 3,000 MW DC and 1,500 MW AC WECC Phase 1 Analysis

Status and Trends of HVDC

The Challenges facing HVDC in the Early 21 st Century. Dr Norman MacLeod Technical Director, HVDC Visiting Professor, Leeds University

PUD ELECTRIC SYSTEM INTERCONNECTION

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

The Northeast Corridor Master Plan Amtrak s Next Generation High-Speed Rail and Northeastern Maryland

ABB UPS 3. November 2014

APPENDIX F: Project Need and Description

Use of High-Power Thyristor Technology for Short-Circuit Current Limitation in High Voltage Systems

EMERGING REQUIREMENTS

FY Capital Improvement Program Street Lighting

The Capital Grid Project:

APPENDIX E: ELECTRIC AND MAGNETIC FIELDS MANAGEMENT PLAN

2011 Special Reliability Assessment: Power Interdependency in the United States

Dynamic Control of Grid Assets

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. System Planning

Latest development in transmission in 800kVDC

Substation Equipment (Bushings)

ABB Power Cables Service Turnkey Cable Repairs Three Reference Cases

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

Merger of the generator interconnection processes of Valley Electric and the ISO;

Green Line LRT: Beltline Segment Update April 19, 2017

Docket No EI Date: May 22, 2014

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

ABB s capabilities in advanced power transmission

What can HVDC Light do for you it s time to connect Applications Key Components

Printed on elementary chlorine-free bleached paper.

PSE Attachment K Puget Sound Area Transmission Meeting

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

CAPITAL FUND 9510 STREET & SIDEWALK IMPROVEMENTS FIVE-YEAR CAPITAL IMPROVEMENT PROGRAM FISCAL YEARS

The Bulk Way. UHV DC the new dimension of efficiency in HVDC transmission. Answers for energy.

B Influence of HVDC Operation on Deregulated Markets. Transpower New Zealand Limited. New Zealand

HVDC Multi-Terminal Interconnections a viable and optimal solution for India

IEEE T&D FACTS Panel Session Part II (08TD0140) Wednesday, April 23, 2008

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

City of Palo Alto (ID # 6416) City Council Staff Report

ORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement to Purchase Compressed Natural Gas Articulated Buses. Staff Report

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

Long distance bulk transmission

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

Peru-Chile Interconnector: Technical Analysis Study

WECC Regional Planning Review. Canada/Pacific Northwest Northern California Transmission Line Project. Technical Analysis Committee Report

Towards Realization of a Highly Controllable Transmission System HVDC Light

Gas-Insulated Switchgear. Type 8VN1 blue GIS up to 145 kv, 40 ka, 3150 A

Pacific Northwest/Canada To Northern California Transmission Feasibility Study

Maritime Link. MITC Canada Day March 2015

CITIZEN TASK FORCE PRESENTATION

Peter Lundberg, ABB HVDC, Nov 2016 HVDC Light - Power from shore. ABB Group November 16, 2016 Slide 1 1JNL A

S&C Circuit-Switcher Mark VI Outdoor Transmission (69 kv through 138 kv)

Alternatives for meeting the need for transmission improvement described

Climate Change and the Electric Grid

ELECTRIC GENERATION AND TRANSMISSION IN THE RAILBELT

ABB FACTS Customer Service. FACTS Care Upgrades

SDG&E High Voltage DC WECC Path 46 Rating Increase Comprehensive Progress Report

The Xiangjiaba-Shanghai 800kV UHVDC project Status and special aspects. V. F. Lescale, U. Åström W. Ma, Z. Liu State Grid Corporation of China

NORTH SLOPE BOROUGH Department of Public Works P.O. Box 350 Barrow, Alaska 99723

best to you all Gail Carbiener Page 1 of 5

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

Comparison of the Performance of HVDC and HVAC Overhead Transmission Lines for the Itaipu System

Transcription:

The Upgrade of the Northern Terminal of the Pacific NW-SW HVdc Intertie Celilo Converter Station Dan Kell Karl Mitsch Mark Reynolds TransGrid Solution US-DOE BPA Power Engineers Canada USA USA

Introduction Bonneville Power Administration (BPA) is in the process of upgrading their portion of the Pacific DC Intertie (PDCI). This project consists of two major components: Upgrade of the Celilo terminal Re-insulation and upgrade of the dc transmission line. The upgrade of the converter will include; The complete furnishing of a new ± 560 kv bi-polar (12-pulse per pole) converter station rated at 3800 MW. All ac and dc filters shall be replaced with new filters. The transmission line upgrades include new insulation for operation at +/- 560 kv dc for North to South transfers, shunting of splice fittings, replacement of dampers and installation of failure containment deadends.

History In 1977, Current upgrade based on studies of design margin in the equipment raised the current to 2.0kA using inherent capacity of the valves and bringing the rating to 1600MW In 1984, the system was upgraded to +/-500kV by adding 1 x 100kV, thyristor valve group rated for 2kA, which increased the Bipole rating to 2000MW. In 1989, 12-pulse parallel thyristor valve groups where added (Converter 1 and 2), rated for +/- 500kV, 1.1kA, which increased the PDCI capacity to 3100MW. In 2003, the mercury arc valves of Celilo Converters 3 and 4 were replaced with thyristor valves of the same rating, maintaining the current rating of converters 3 and 4 at 2kA, and the station rating of 3100MW. In 2004, at Sylmar, the parallel +/-500kV 1100MW converters were replaced with a new +/-500kV 3100MW converters and the original mercury arc converters 3 and 4 were retired. The replacement was required as a result of extensive damage sustained at the Southern terminal during the 1994 Northridge earthquake. 1 st Thyristor Project: Gotland Extension Original Sylmar Earthquake Intertie Construction Voltage Upgrade Pacific Intertie Thyristor Valves Terminal Expansion Project Sylmar Fire Northridge Earthquake Sylmar Replacement Project Mercury Arc Replacement at Celilo 1970 1980 1990 2000

PACIFIC DC INTERTIE REPLACEMENT & UPGRADE Conv 3 Conv 1 Conv 1 Conv 1 & 2 Conv 4 Conv 2 Conv 3 & 4 Conv 2 Celilo Sylmar 2004 Replace 1100MW converters 1 & 2 at Sylmar with new 3100 MW converters

Upgrade Project Justification Sustain For the Celilo terminal, retain the existing four converter architecture and replace systems and components as they reach their end of life. The dc line would also require substantial improvements to bring the line performance up to current NESC/CAL-GO95 standards. Addition of Insulator Bells, selective use of NCI Insulators, change-outs of Shunt-Fittings, and minor conductor hardware replacements kv ka 8 6 1984 ASEA Converters Thyristor blocking voltage 2004 ABB Converters Sylmar 2001 Siemens Converters Celilo 1995 Siemens Converter Sylmar 1989 BBC Converters 4 2 Rated thyristor current for long distance transmission 1970 1980 1990 2000

Upgrade Project Justification Upgrade Replacement of the existing Converter equipment with new dc converter equipment capable of the entire station rating. The dc line would require re-insulation to allow operation at a higher dc voltage. The Upgrade alternative also allows the opportunity to increase power transmission capability in the N to S direction by taking advantage of some latent capability in the Sylmar Converters. The dc line would also require substantial improvements to bring the line performance up to current standards.

Upgrade Project Justification PDCI Total Capital Cost - Nominal $ 1/ Upgrade compared to Sustain Alternative 160.0 140.0 Capital in Millions $ 120.0 100.0 80.0 60.0 40.0 20.0 0.0 FY 2012 FY 2014 FY 2016 FY 2018 FY 2020 FY 2022 FY 2024 FY 2026 FY 2028 FY 2030 Fiscal Year Preferred Alternative (Upgrade) Alternative Next Best Alternative (Sustain)

Upgrade Project Justification The Upgrade option also has several other benefits such as: Utilizing one vintage of technology, reducing maintenance and spare part inventory for a simplified station configuration and the possibility of dynamic scheduling for the link. When compared to the Sustain option it is one large project instead of a stream of a several projects over 25 years. Ultimately BPA chose the Upgrade alternative as the best approach to maintaining reliable and economic operation into the future

Proposed Stages of Development Existing:3100MW, Stage 1:3220MW, Stage 2:3450MW, Stage 3:3800MW

Unique Challenges Testing (with minimum outage times) Maintaining capacity during construction (design to minimize unscheduled outage potentials Utilizing existing valve hall (minor seismic improvements) Maintaining the Footprint Electrode and Electrode line

A LOOK INTO THE FUTURE AT CELILO

Conclusions Early in 2013, stage 1 of the upgrade project was awarded to ABB. The terminal will be completed by December 2015 and the line work is scheduled to be complete by November 2017. By careful up-front planning and specifying what is required, the PDCI upgrade project is off to an excellent start Design Review and planning activities are in progress, with release of apparatus design specifications expected this Fall (2013) Beginning of apparatus manufacturing in early 2014 Outage coordination and planning for control replacement at bith terminal stations (Celilo & Sylmar)

Questions Dan Kell dkell@transgridsolutions.com Mark A Reynolds mark.reynolds@powereng.com Karl Mitsch kamitsch@bpa.gov