Functional Specification Revision History

Similar documents
ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Proposed New ISO Rules Section Version 2.0 Generating Unit Technical Requirements ( New ISO Rules Section Version 2.

Generation Interconnection Facilities Study For

Guideline for Parallel Grid Exit Point Connection 28/10/2010

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Generator Interconnection System Impact Study For

INTERCONNECTION FACILITIES STUDY REPORT

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Interconnection System Impact Study Report Request # GI

Jemena Electricity Networks (Vic) Ltd

Bohn to Kettle River Transmission Project

Kettle River Transmission Project

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

Interconnection Feasibility Study Report GIP-226-FEAS-R3

RE: Application for Alteration of Vermilion Substation 710S 144 kv Equipment Addition, 72 kv Equipment Removal, and Fence Expansion

ATTACHMENT - DFO STATEMENT OF NEED

REQUEST FOR PROPOSALS FOR THE ESTABLISHMENT OF SOLAR PV POWER PLANT ON BUILD, OWN AND OPERATE BASIS. International Competitive Bidding (ICB)

Guidelines for connection of generators:

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

XXXXX. Kokish River Hydroelectric Project. Interconnection Facilities Study and Project Plan

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study

KERALA STATE ELECTRICITY REGULATORY COMMISSION. NOTIFICATION Dated, Thiruvananthapuram 6 th August,2007

Small Generator Interconnection Program Interconnection Technical Requirements

Decision on Merced Irrigation District Transition Agreement

Merger of the generator interconnection processes of Valley Electric and the ISO;

Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna

Willingdon Substation Decommission

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Large General Service Time-of-Use Storage Program

EXTRA ORDINARY 16 AASHAADHA, 1937(S) BIHAR ELECTRICITY REGULATORY COMMISSION

Included in this Stakeholder Information Package:

Decision Blaze Energy Ltd. Application for an Exemption under Section 24 of the Hydro and Electric Energy Act.

Reactive Power Requirements and Financial Compensation. Addendum to Draft Final Proposal

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016

Net +Plus Connection Code

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.

MICHIGAN ELECTRIC UTILITY

APPENDIX C - AESO PIP SUMMARY

City of Palo Alto (ID # 6416) City Council Staff Report

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION

Application for Commission Approval to Construct a Generating Station Pursuant to Public Utilities Article Section and

Annex to technical regulation for thermal plants above 11 kw

Currant Lake Transmission Project

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Impact of Distributed Energy Resources on Transmission System Reliability

Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)*

Net Metering Interconnection Requirements

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

CUSTOMER/ TWIN ARROWS PROJECT

Rate Schedules. Effective 1/1/2019

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM

The cost estimation methodology used to update the charges and credits is the same methodology the Company utilized in the prior year s filing.

PHILIPPINE DISTRIBUTION CODE 2017 EDITION

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

Schedules 1 to 4, Lot B: Extension of the Lessos Substation

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents

Chapter 6 Generator-Voltage System

MMP Investigation of Arthur Kill 2 and 3

D. Operation and Maintenance Data. In addition to items specified in Division 1 Section "Operation and Maintenance Data," include the following:

ISO Rules Part 300 System Reliability and Operations Division 304 Routine Operations Section Electric Motor Start Requirements

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013

Western Power s list of exemptions from compliance from Technical Rules granted after 1 July 2007.

Title Electrical Technical Maintenance Coding System. Reference Number PMP 01 (RIC Standard: EP SP)

MISSOURI SERVICE AREA

North Oregon Coast Area Study. Adam Lint

MICHIGAN ELECTRIC UTILITY

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Generating unit functional document submission form

Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study

Enquiry Form (Non-Registered Generator With Capacity less than 5 MW)

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

INTERCONNECTION REQUIREMENTS POLICY

PUD ELECTRIC SYSTEM INTERCONNECTION

Requirements for Secondary Voltage Revenue Metering (750 V and less)

MICHIGAN ELECTRIC UTILITY

Customer Name : Account Number: Customer Service Address (Street, City, State, ZIP Code): Customer Mailing Address: Customer Telephone Number:

INTERCONNECTION RULES AND REGULATIONS FOR NET ENERGY METERING SYTEMS

Load Side PV Connections

2015 WDC Disturbance and Protection Standards Overview

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

Transcription:

Functional Specification Revision History Revision Description of Revision Author Date B0 For comments Yale Zhou January 26, 2016 B1 Updated as per comments Yale Zhou February 1, 2016 Final issuance Yale Zhou February 12, 2016 File No. 1692 AESO Functional Specification Page 2 of 13

TABLE OF CONTENTS 1 PURPOSE... 4 2 INTERPRETATION AND VARIANCES... 4 3 PROJECT OVERVIEW... 4 4 FORECAST OF FUTURE DEVELOPMENT IN THE PROJECT AREA... 5 5 SCOPE OF WORK... 5 5.1 General... 5 5.2 Compliance with AESO Authoritative Documents... 5 5.3 Modeling Data Requirements... 6 5.4 Substation Equipment Specifications... 6 5.5 Scope of Work for the Legal Owner of the Transmission Facility... 6 5.6 Scope of Work for the Market Participant... 8 6 TRANSMISSION SYSTEM OPERATING CHARACTERISTICS... 8 6.1 Short Circuit Current Levels... 8 6.2 Voltage Levels... 10 6.3 Insulation Levels... 10 7 APPENDICES... 11 7.1 System Interconnection in the project area... 11 7.2 Single Line Drawing Jenner 275S Substation Existing... 12 7.3 Single Line Drawing Jenner 275S Substation Proposed... 13 File No. 1692 AESO Functional Specification Page 3 of 13

1 PURPOSE (1) The purpose of this document (the Functional Specification ) is to set out the technical specifications and requirements and approved variances issued by the AESO to the legal owner of the transmission facility, AltaLink Management Ltd., and the market participant, FortisAlberta Inc., related to the design, construction, development and commissioning of certain new or modified facilities (the Project ) that have been proposed for or are related to a physical facilities connection with the interconnected electric system (the "Purpose"). (2) This Functional Specification is issued for the Purpose only, and the legal owner of the transmission facility and the market participant must comply with the Functional Specification provisions. (3) The AESO is not responsible for any facilities designed by or for any third party, or installed on a third parties behalf, to accomplish the connection of the Project facilities. (4) This Functional Specification includes: (i) certain specific engineering, technical and functional requirements for the Project; (ii) the requirements to comply with ISO rules, including OPPs, reliability standards, technical standards, and ISO tariff provisions, (the Authoritative Documents ); (iii) the electrical system environment in which the connecting facilities must be designed and operated; and (iv) any approved variances from requirements set out in any applicable AESO Authoritative Documents. 2 INTERPRETATION AND VARIANCES (1) Subject to subsection (2), any revision or variance to any of the Functional Specification provisions by the legal owner of the transmission facility or the market participant is prohibited. (2) The legal owner of the transmission facility or the market participant may make application, jointly or individually, in writing to the AESO requesting a variance to this Functional Specification, and the AESO may in writing approve of the variance after the AESO has completed an analysis of the implications to the interconnected electric system with respect to the requested variance. (3) Words or phrases appearing in bold have the meanings set out in the Consolidated Authoritative Document Glossary. 3 PROJECT OVERVIEW On August 18, 2015, the market participant requested to AESO to install one (1) new 25 kv feeder breaker at the Jenner 275S, located in the Empress Planning Area (Area 48), to address the distribution service deficiencies in the area. Two (2) additional 25 kv breakers are also proposed at Jenner 275S to meet reliability requirement. The Demand Transmission Service (DTS) capacity contract will remain same as before (65.5 MW) The requested in-service date (ISD) for the project is August 1, 2017. File No. 1692 AESO Functional Specification Page 4 of 13

4 FORECAST OF FUTURE DEVELOPMENT IN THE PROJECT AREA Refer to AESO s website (www.aeso.ca) for the details of future development in the project area. 5 SCOPE OF WORK 5.1 General (1) The legal owner of the transmission facility and the market participant must complete all engineering, design, land or land-use acquisition, siting, public consultation, applicable regulatory approvals and permits, material procurement, construction, commissioning, and associated permitting requirements for the Project facilities. (2) The legal owner of the transmission facility and the market participant must coordinate with each other as required on all project facility design details, including protection and control, grounding, insulation, point of connection, and site layout with proper consideration of maintenance coordination. (3) The legal owner of the transmission facility and the market participant must develop joint operating procedures and any connection agreements as required such that all connecting transmission facilities will operate safely and reliably. (4) The legal owner of the transmission facility and the market participant must deliver to the AESO all final design and as-built Project facility information and records in the format and content required by the AESO, to enable the AESO to update and maintain its transmission technical records and system models. (5) The legal owner of the transmission facility and the market participant must submit the Project information and records referred to in subsection (4) above, under the professional stamp and signature of a registered professional engineer in Alberta who assumes responsibility for the preparation and accuracy of the content of the information and records. (6) The legal owner of the transmission facility and the market participant must mutually agree on each party s roles and responsibilities regarding inspection of all facilities of the Project prior to energization of the facilities. (7) The legal owner of the transmission facility and the market participant must ensure, prior to energization of any or all Project facilities, that the facilities to be energized have been inspected by qualified personnel in accordance with industry standards and practices, so that the facilities are declared to be: (a) (b) Safe for operation; and In compliance with this Functional Specification, Alberta Reliability Standard and any Authoritative Documents for which the Project must comply (8) No Project facilities are to be energized until an energization authorization has been issued by the AESO in accordance with the ISO rules. 5.2 Compliance with AESO Authoritative Documents The legal owner of the transmission facility and the market participant must comply with the Authoritative Documents provisions which are applicable to the Project and which must be incorporated in to the design, construction, commissioning and operation of the connecting facilities and other connection Project work, including but not limited to, these provisions contained herein: AESO Operating Policies and Procedures File No. 1692 AESO Functional Specification Page 5 of 13

AESO Alberta Reliability Standards 1 AESO Measurement System Standard Rev. 1 (dated September 18, 2007)0F AESO Generation and Load Interconnection Standard (dated September 19, 2006) 1F1 ; ISO Rules, including but not limited to: Section 502.3, Interconnected Electric System Protection Requirements (effective March 27, 2015) Section 502.4, Automated Dispatch and Messaging System and Voice Communication Systems Requirements (effective March 27, 2015) Section 502.8, SCADA Technical and Operating Requirements (effective March 27, 2015) Section 9.1, Transmission Facility Projects (effective September 24, 2013) 5.3 Modeling Data Requirements All modeling data shall be provided per the Information Transmission Modeling Data Requirements (dated February 6, 2014). 5.4 Substation Equipment Specifications All new substation equipment must meet the following minimum specifications: Temperature rating of -50ºC for all outdoor equipment. Equipment maximum and minimum continuous voltage ratings as indicated in Table 4. Minimum continuous equipment current ratings as indicated in Table 1. Equipment maximum fault level: 31.5 ka for 138 kv and 40kA for 240kV. Table 1 Minimum Continuous Equipment Current Ratings (A) Component 25 kv 138 kv 240 kv Main Bus 1) 1200 1200 2000 Cross Bus 2) 600 600 2000 Feeder 3) or line terminal 4) 600 600 2000 1) Main bus includes all sections of ring bus scheme and single bus of simple bus scheme. 2) Cross bus includes diameter sections of breaker and a half or breaker and third schemes. 3) Feeder includes all equipment from the connection at the low voltage bus to the riser pole. 4) Line terminal includes all equipment and conductor from the transmission line to the line breakers. 5.5 Scope of Work for the Legal Owner of the Transmission Facility (1) General Requirements 1 The AESO considers this standard to remain in effect notwithstanding the statement in clause 1.5 in the standard. Efforts to revise the standard are currently underway through an industry work group. File No. 1692 AESO Functional Specification Page 6 of 13

Coordinate with the market participant to develop necessary connection agreements and joint operating procedures. Ensure project safety is appropriately managed through all stages of the project. Undertake all required grounding studies, testing and mitigation as required for electrical safety and any mitigation for electrical effects on communication systems. Complete insulation coordination studies and coordinate with market participant as required to establish appropriate insulation levels. Complete all site preparation, foundations, grounding, bus-work, support structures, termination structures, duct work and cabling as required for the proposed additions. Coordinate all alignments with the market participant for the 25 kv feeder connections. (2) Substation Jenner 275S Appendices 7.2-7.3 Substation Equipment and major construction Install one (1) new 25 kv feeder with associated breaker and switches. Install two (2) 25 kv isolating circuit breakers with associated switch. Protection and Control Complete system protection coordination studies and coordinate with adjacent substations and the market participant as required to establish settings appropriate for the facility additions and ATS operations. Install appropriate protection for the 25 kv facility additions. Install UFLS relays to meet load shedding requirement as per AESO OPP804. Install all other required protection equipment for the safe and reliable operation at Jenner 275S substation. Any frequency relays installed to protect equipment for off-nominal frequency operation must not be disabled for transmission system voltages that are below eighty percent (80%) of the rated voltage. Telecommunication Review or upgrade if required the communication system and interfaces for teleprotection, SCADA, operational voice and data to ensure ISO Rule 502.4 requirements are met at Jenner 275S. SCADA Update communication interface points if required such that SCADA data can be transmitted back to the AESO s System Coordination Centre (SCC) and Backup Coordination Centre (BUCC). Revenue metering Install demand/energy meters as detailed in the AESO Measurement System Standard to measure power flow through the Measurement Point. File No. 1692 AESO Functional Specification Page 7 of 13

5.6 Scope of Work for the Market Participant (1) General Requirements Coordinate with the legal owner of the transmission facility as required to perform insulation coordination, grounding studies, protection coordination, supervisory control and data acquisition The market participant is required to participate in the ATS under-frequency load shedding program as per AESO OPP-804. The market participant shall ensure that sufficient load is equipped with under-frequency load shedding relays that are capable of being armed in each frequency band to meet the program specifications, and have the scheme installed, tested, and commissioned appropriately as required Co-ordinate all alignments with the legal owner of the transmission facility as required to connect the market participant s facility to the ATS Ensure connection project safety is appropriately managed throughout the project. (2) Jenner 275S Substation Appendices 7.2-7.3 Protection and control Complete protection coordination studies and coordinate with the legal owner of the transmission facility as required to establish settings appropriate for the market participant facility additions and ATS operations. Revenue metering Provide the description of the measurement point location for the point of delivery/point of supply, and the acceptable installation options for revenue metering in order to report on the measurement point. 6 TRANSMISSION SYSTEM OPERATING CHARACTERISTICS The legal owner of the transmission facility and the market participant must ensure all facilities are capable of operating in the following electrical environment. 6.1 Short Circuit Current Levels (1) The short circuit current levels set out in Table 2 and 3 have been developed by the AESO based on information provided by the legal owners of the transmission facility, any connecting generating units, and adjacent operating areas. Available fault current levels will continue to increase as generation, transmission, and system inter-ties are added to the interconnected electric system. The legal owner of the transmission facility and market participant must continue to review the fault levels and their equipment ratings for adequacy. (2) Any future equipment upgrades or protection system setting changes required due to increasing fault levels are the responsibility of the legal owner of the transmission facility or the market participant, as applicable. (3) The following assumptions were incorporated into the AESO short circuit current models: (i) All expected Alberta generation is dispatched. (ii) All transmission elements are in service. File No. 1692 AESO Functional Specification Page 8 of 13

(iii) The proposed project facility is connected as per this document. (iv) V base = V bus, MVA base = 100 Table 2: Summary of Short-Circuit Current Levels Post-Connection (2017 WP) Substation Cypress 562S Amoco Empress 163S Jenner 275S Ware Junction 132S Wardlow 230S Base Voltage (kv) Pre Fault Voltage (kv) 3 Φ Fault (ka) Positive Sequence Impedance (R1 + j X1) (p.u.) 1 Φ Fault (ka) Zero Sequence Impedance ( + j X0) (p.u.) 240 263.27 6.0 0.007553+j0.04345 6.4 0.003927+j0.036218 138 141.37 8.9 0.008168+j0.047249 8.8 0.0044+j0.051652 240 263.24 6.0 0.007398+j0.043168 6.0 0.006079+j0.044548 138 141.33 8.8 0.008305+j0.047551 8.4 0.006882+j0.058304 240 262.14 7.7 0.006024+j0.033488 4.8 0.02267+j0.09299 138 140.68 0.5 0.075281+j0.823503 0.4 0.045912+j1.392546 240 260.71 14.4 0.002908+j0.017823 12.7 0.004067+j0.024325 138 140.59 0.5 0.107315+j0.886222 0.4 0.110819+j1.622477 Table 3: Summary of Short-Circuit Current Levels Post-Connection (2025WP) Substation Cypress 562S Amoco Empress 163S Jenner 275S Ware Junction 132S Wardlow 230S Base Voltage (kv) Pre Fault Voltage (kv) 3 Φ Fault (ka) Positive Sequence Impedanc e (R1 + j X1) (p.u.) 1 Φ Fault (ka) Zero Sequence Impedance ( + j X0) (p.u.) 240 253.07 6.3 0.006957+j0.039351 6.6 0.003901+j0.035658 138 143.06 9.0 0.008539+j0.046835 8.7 0.004825+j0.054663 240 253.07 6.3 0.006805+j0.039105 6.2 0.005993+j0.043786 138 142.89 9.0 0.008634+j0.047006 8.3 0.007285+j0.061026 240 255.05 8.3 0.005481+j0.030271 4.9 0.022427+j0.091233 138 137.82 0.5 0.075998+j0.78135 0.4 0.044956+j1.330603 240 257.02 17.1 0.002268+j0.014778 15.3 0.003295+j0.019642 138 137.73 0.5 0.108034+j0.844127 0.4 0.109824+j1.560402 File No. 1692 AESO Functional Specification Page 9 of 13

6.2 Voltage Levels Table 4 provides the normal planned operating voltage range in the area of the proposed facility. Table 4: Planned Operating Range Substation Name and Number Nominal (kv) Minimum Limit (kv) Normal Operating Minimum (kv) Normal Operating Maximum (kv) Maximum Limit (kv) Jenner 275S 138 124 135 145 150 Jenner 275S 240 216 234 252 264 Notes: 1. The Normal Operating Minimum and Normal Operating Maximum are generally associated with Category A events and system normal. 2. The Minimum Limit and Maximum Limit are generally associated with Category B, C, and D events and system abnormal. 3. The new facilities must be capable of continuous operation at voltages up to and including the Maximum Limit. 6.3 Insulation Levels (1) Table 5 provides the minimum required basic insulation levels for the transmission system. Station equipment with lower insulation levels may be used provided that protection and coordination can be maintained with judicious insulation design and use of appropriate surge arresting equipment. (2) For 25 kv circuit breakers where there is a grounded wye transformer and surge arrestors are installed a basic insulation level of 125 kv is acceptable. Table 5: Basic Insulation Levels (kv) Nominal Voltage Classification (kv rms) 240 138 25 Station Post Insulators and Airbreaks 900 550 150 Circuit Breakers 1050 650 150 Current and Potential Transformers 1050 650 150 Transformer Windings (Protected by Surge Arresters) 850 550 125 File No. 1692 AESO Functional Specification Page 10 of 13

7 APPENDICES 7.1 System Interconnection in the project area File No. 1692 Functional Specification Page 11 of 13

7.2 Single Line Drawing Jenner 275S Substation Existing 240 kv Bus 1 240 kv Bus 2 T1 240/25kV 83 MVA T2 240/25kV 83 MVA T3 138/25kV 25 MVA 25 kv Bus 1 25 kv Bus 4 25 kv Bus 2 25 kv Bus 3 N.O. N.O. AltaLink Fortis AltaLink Fortis L11 310L L14 2269L L12 2175L 138 kv 601L To Wardlow 230S L10 2174L L9 2036L L8 167L L7 312L Legend Note Circuit Breaker Motorized Disconnect Switch Manual Ganged Disconnect Switch LTC Transformer This single line diagram provides an illustration of a functional arrangement that would meet the need of the proposed project. The exact routing and configuration of the project may vary slightly from this configuration based on more detailed engineering, routing and siting information obtained from the legal owner of transmission facility and the market participant. Wenner 275S Substation 9xisting SL5 (tartial) 1692-275S-SLD-01 File No. 1692 AESO Functional Specification Page 12 of 13

Fortis Jenner 27S Upgrade 7.3 Single Line Drawing Jenner 275S Substation Proposed 240 kv Bus 1 240 kv Bus 2 T1 240/2DkV 83 MVA T2 240/2DkV 83 MVA T3 138/2DkV 2D MVA 2D kv Bus 1 2D kv Bus 4 2D kv Bus 2 2D kv Bus 3 N.O. N.O. AlPaLink ForPis AlPaLink ForPis L11 310L L14 2269L L12 217DL 138 kv 601L To Jardlow 230S L10 2174L L9 2036L L8 167L L7 312L 2323L Legend NoPe CircuiP Breaker MoPorized DisconnecP SwiPch Manual Ganged DisconnecP SwiPch Transformer Proposed addipions This single line diagram provides an illusprapion of a funcpional arrangemenp PhaP would meep Phe need of Phe proposed projecp. The exacp rouping and configurapion of Phe projecp may vary slighply from Phis configurapion based on more depailed engineering, rouping and siping informapion obpained from Phe legal owner of Pransmission facilipy and Phe markep parpicipanp. Jenner 275S Substation (Partial) Proposed SLD 1692-27DS-SLD-02 File No. 1692 AESO Functional Specification Page 13 of 13